Backup Documents 12/08/2020 Item #14A2 ORIGINAL DOCUMENTS CHECKLIST & ROUTING SLIP
TO ACCOMPANY ALL ORIGINAL DOCUMENTS SENT TO 1 b A 2
THE BOARD OF COUNTY COMMISSIONERS OFFICE FOR SIGNATURE
Print on pink paper. Attach to original document. The completed routing slip and original documents are to be forwarded to the County Attorney
Office at the time the item is placed on the agenda. All completed routing slips and original documents must be received in the County Attorney
Office no later than Monday preceding the Board meeting.
**NEW** ROUTING SLIP
Complete routing lines#1 through#2 as appropriate for additional signatures,dates,and/or information needed. If the document is already complete with
the exception of the Chairman's signature,draw a line through routing lines#1 through#2,complete the checklist,and forward to the County Attorney Office.
Route to Addressee(s) (List in routing order) Office Initials Date
1. Risk Risk Management N N/Pr
2. County Attorney Office County Attorney Office ll
4. BCC Office Board of County �`�
Commissioners Id 41 • I 1-ao
4. Minutes and Records Clerk of Court's Office 04
Po 11-2Y31,-\
5. Procurement Services Procurement Services
PRIMARY CONTACT INFORMATION
Normally the primary contact is the person who created/prepared the Executive Summary. Primary contact information is needed in the event
one of the addressees above,may need to contact staff for additional or missing information.
Name of Primary Staff Jessica Suarez/PURCHASING Contact Information 239-252-8407
Contact/ Department
Agenda Date Item was December 8'1,2020 Agenda Item Number 14.A.2
Approved by the BCC
Type of Document AMENDMENT Number of Original 1
Attached Documents Attached
PO number or account N/A 19-7558 HOLE MONTES,
number if document is HOLE MONTES, INC
to be recorded INC
INSTRUCTIONS & CHECKLIST
Initial the Yes column or mark"N/A"in the Not Applicable column,whichever is Yes N/A(Not
appropriate. (Initial) Applicable)
1. Does the document require the chairman's original signature STAMP OK N/A
2. Does the document need to be sent to another agency for additional signatures? If yes, N/A
provide the Contact Information(Name;Agency;Address;Phone)on an attached sheet.
3. Original document has been signed/initialed for legal sufficiency. (All documents to be JS
signed by the Chairman,with the exception of most letters,must be reviewed and signed
by the Office of the County Attorney.
4. All handwritten strike-through and revisions have been initialed by the County Attorney's N/A
Office and all other parties except the BCC Chairman and the Clerk to the Board
5. The Chairman's signature line date has been entered as the date of BCC approval of the JS
document or the final negotiated contract date whichever is applicable.
6. "Sign here"tabs are placed on the appropriate pages indicating where the Chairman's JS
signature and initials are required.
7. In most cases(some contracts are an exception),the original document and this routing slip N/A
should be provided to the County Attorney Office at the time the item is input into SIRE.
Some documents are time sensitive and require forwarding to Tallahassee within a certain
time frame or the BCC's actions are nullified. Be aware of your deadlines!
8. The document was approved by the BCC on 12/08/2020 and all changes made during N/A is not
the meeting have been incorporated in the attached document. The County an option for
Attorney's Office has reviewed the changes,if applicable. this line.
9. Initials of attorney verifying that the attached document is the version approve . ' /A is not
BCC,all changes directed by the BCC have been made,and the document is , t r.,1 \L:1•` option for
Chairman's signature. i this line.
DEC , 8 12
Risk Management
MEMORANDUM
Date: December 14, 2020
To: Jessica Suarez, Purchasing Technician
Procurement Services
From: Martha Vergara, Sr. Deputy Clerk
Minutes & Records Department
Re: Contract #19-7558 1st Amendment to Agreement" —
for Design Services for Immokalee Runway Rehabilitation &
Taxiway Extension Projects
Contractor: Hole Montes, Inc.
Attached for your records is an original of the referenced document above,
(Item #14A2) adopted by the Board of County Commissioners on Tuesday,
December 8, 2020.
The Board's Minutes & Records Department has kept an original as part of
the Board's Official Records.
If you have any questions, please feel free to contact me at 252-7240.
Thank you.
Attachment
1 4 A 2
FIRST AMENDMENT TO AGREEMENT# 19-7558
FOR DESIGN SERVICES FOR IMM RUNWAY
REHABILITATION& TAXIWAY EXTENSION PROJECTS
THIS FIRST AMENDMENT, made and entered into on this rday of 020,
by and between Hole Montes, Inc. (the "Consultant" and/or "Contractor") and Collier County, a
political subdivision of the State of Florida, (the "County").
WHEREAS, on November 12, 2019 (Agenda Item No. 16.G.2), the County entered into an
Agreement with Consultant to provide professional design, permitting and bidding services for the
rehabilitation of Runway 18/36 and extension of Taxiway C at the Immokalee Regional Airport
(IMM); and
WHEREAS, the Parties desire to amend the Agreement per Article Two, "Additional
Services of Consultant,"to incorporate Post Design services for the extension of Taxiway C services in
the amount of$35,178.25 and Runway services in the amount of$38,566.25.
NOW, THEREFORE, in consideration of the mutual promises and covenants herein
contained, it is agreed by the Parties as follows:
1. The additional services shall be provided in accordance with the attached Schedule A-2
Scope of Services, which is hereby incorporated into the Agreement.
2. The fees for additional services outlined in Schedule A-2 shall be provided in
accordance with Schedule B-2, attached hereto and incorporated into the Agreement.
3. Schedule C-2, Project Milestone Schedule, is attached hereto and incorporated into the
Agreement.
4. Schedule F-2 Key Personnel, Subconsultants and Subcontractors is attached hereto and
incorporated into the Agreement.
5. All other terms and conditions, as amended, shall remain the same.
SIGNATURE PAGE TO FOLLOW
**Remainder of this page left blank intentionally**
Page 1 of 12
First Amendment to Agreement# 19-7558
4 A2 '
IN WITNESS WHEREOF,the Parties have each executed this First Amendment by an authorized
person or agent on the date and year first written above.
ATTEST:
Crystal K.Kinzel,Cleik of Courts& BOARD OF COUNTY COMMISSIONERS
Comptroller COLLIER COUNTY, FLORIDA
/-.)
By: , r.wotYs�tf�t;ti9i By:
,'t
Burt L. Saunders,Chairman
y. .
Dated ' Ignature ollly , QvA D
(SEAL)
Consultant's Witnesses: CONSULTANT:
Hole Monies,Inc.
ss By:
Signs
e/print witness ameT tai466,124) LAd V.P.
TType/print sig►tature and Wet
nd Wi s
?Al ZoZo
�1jr1A'1 ►^ G P-e Date
TType/prin witness name"I
proved to a Le ality:
Sco R.Teach,Deputy County Attorney
Page 2 of 12
First Amendment to Agreement# 19-7558
SCHEDULE A-2
SCOPE OF SERVICES
(First Amendment)
This scope of services covers post-design services required for:
Rehabilitation of Runway 18/36
Project Description
Under a previous task authorization, Collier County Airport Authority (COUNTY) commissioned
HOLE MONTES (CONSULTANT) to perform design services for the rehabilitation of Runway 18/36
at IMM.
The intent of this scope is to perform post-design phase services necessary to support the various
construction elements associated with this project at IMM.
At the request of the COUNTY, Hole Montes has drafted this scope of services to define the effort
necessary to accomplish the Post-Design (Construction Phase Services) for the Rehabilitation of
Runway 18/36 at IMM, excluding Construction Engineering and Inspection (CEO. This will consist of
support during construction, in coordination with the CCAA and its (CEI), Atkins North America, and
the preparation of closeout documents and record drawings.
Objective
The objective shall be the successful completion by the CONSULTANT of project post design
related services necessary for the various construction elements associated with the construction of
Runway 18/36 rehabilitation at IMM, which excludes any Construction Inspection, as CCAA has
retained the services of a separate consultant, Atkins North America, for this work.
Scope
For the purposes of scope definition and CONSULTANT fee development, the work has been
divided into the following tasks. Any modifications and/or revisions to these tasks will constitute a
change in the project scope and may require a revision to the compensation to be paid to the
CONSULTANT. These tasks will begin once the COUNTY provides the CONSULTANT with a
written Notice to Proceed. These tasks will be complete once the CONSULTANT provides the
COUNTY with the closeout documents.
The CONSULTANT shall provide technical support during construction along with the preparation of
closeout documents and record drawings. The Project Manager (PM) will be readily available to the
project team and the COUNTY to oversee necessary project related elements.
Task 1: Post Design Services
1.1) This task will include the CONSULTANT's review of shop drawings submitted by the
Contractor as stipulated in the Contract Documents. The Resident Project Representative
(RPR/ OTHERS) will collect and log shop drawings and transmit them to the Engineer.
The CONSULTANT will review the shop drawings and return them to the RPR with
necessary comments.
The CONSULTANT's review of shop drawings will be limited to general design
Page 3 of 12
First Amendment to Agreement# 19-7558 ,� i
concepts and general compliance with the Contract Documents. Reviews by the
CONSULTANT will not relieve the Contractor of the responsibility of compliance with the
Contract Documents. The CONSULTANT shall act as initial interpreter of the
requirements of the Contract Documents and judge of the acceptability of the work. The
CONSULTANT shall have the authority to make decisions related to the interpretation
of the requirements of the Contract Documents pertaining to the execution and progress
of the work.
The CONSULTANT will review and comment on each shop drawing or technical
submittal a maximum of three (3) times. Additional reviews shall be eligible for
additional compensation.
1.2) Under this task, the CONSULTANT will prepare technical responses to the questions
submitted by the Contractor in the format of a Request for Information (RFI). The RPR
will collect, log, and distribute RFI's to the appropriate technical lead for responses and
return the RFI responses to the CONTRACTOR.
The CONSULTANT shall act as initial interpreter of the requirements of the Contract
Documents and judge of the acceptability of the work. The CONSULTANT shall have the
authority to make decisions related to the interpretation of the requirements of the
Contract Documents pertaining to the execution and progress of the work. The
CONSULTANT shall also provide technical support and clarifications related to the
construction documents and shall provide any required revisions or supplemental
information related to the contract documents that may be required during construction.
1.3) Under this task, the CONSULTANT will review the as-built survey of the top of the runway
base surface after the asphalt has been milled. Based on review of this data the
CONSULTANT shall determine if the final surface can be revised to minimize the
amount of asphalt leveling course required. The CONSULTANT will revise the CAD files
and plans as necessary to limit the amount of asphalt leveling required consistent with
maintaining required slopes and grades.
Task 2: Weekly Meetings and Site Visits
2.1) Under this task, the CONSULTANT's Project Manager and/or appropriate technical leads
will attend weekly meetings (either in-person or by phone) and make periodic visits to the
site during construction.
The CONSULTANT will also conduct a Pre-Construction Conference before the
Contractor is provided with a construction Notice to Proceed. The purpose of this meeting
will be to review general administrative procedures of the contract, review technical
requirements, begin the submittal process, and other items as defined in the Contract
Documents.
In addition, the CONSULTANT's Project Manager and/or technical leads will attend the
Substantial Completion and Final Inspections.
Task 3: Preparation of Closeout and Record Documents
3.1) Under this task, the CONSULTANT will take the Contractor's red lined and surveyed as-
built information and incorporate them into the Construction Drawings for the Airport's
record purposes. Also, under this task the CONSULTANT will assist the RPR in
preparing the technical related project closeout documentation in accordance with
COUNTY and FAA requirements.
Page 4 of 12
First Amendment to Agreement# 19-7558
14A2
This scope of services covers post-design services required for:
Extension of Taxiway C.
Project Description
Under a previous task authorization, Collier County Airport Authority (COUNTY) commissioned
HOLE MONTES (CONSULTANT) to perform design services for the extension of Taxiway C at
IMM.
The intent of this scope is to perform post-design phase services necessary to support the various
construction elements associated with this project at IMM.
At the request of the COUNTY, Hole Montes has drafted this scope of services to define the effort
necessary to accomplish the Post-Design (Construction Phase Services) for the Extension of
Taxiway C at IMM, excluding Construction Engineering and Inspection (CEO. This will consist of
support during construction, in coordination with the CCAA and its (CEO, Atkins North America, and
the preparation of closeout documents and record drawings.
Objective
The objective shall be the successful completion by the CONSULTANT of project post design
related services necessary for the various construction elements associated with the construction of
Taxiway C at IMM, which excludes any Construction Inspection, as CCAA has retained the services
of a separate consultant, Atkins North America, for this work.
Scope
For the purposes of scope definition and CONSULTANT fee development, the work has been
divided into the following tasks. Any modifications and/or revisions to these tasks will constitute a
change in the project scope and may require a revision to the compensation to be paid to the
CONSULTANT. These tasks will begin once the COUNTY provides the CONSULTANT with a
written Notice to Proceed. These tasks will be complete once the CONSULTANT provides the
COUNTY with the closeout documents.
The CONSULTANT shall provide technical support during construction along with the preparation of
closeout documents and record drawings. The Project Manager (PM) will be readily available to the
project team and the COUNTY to oversee necessary project related elements.
Task 1: Post Design Services
1.1) This task will include the CONSULTANT's review of shop drawings submitted by the
Contractor as stipulated in the Contract Documents. The Resident Project Representative
(RPR/ OTHERS) will collect and log shop drawings and transmit them to the Engineer.
The CONSULTANT will review the shop drawings and return them to the RPR with
necessary comments.
The CONSULTANT's review of shop drawings will be limited to general design
concepts and general compliance with the Contract Documents. Reviews by the
CONSULTANT will not relieve the Contractor of the responsibility of compliance with the
Contract Documents. The CONSULTANT shall act as initial interpreter of the
requirements of the Contract Documents and judge of the acceptability of the work. The
Page 5 of 12
First Amendment to Agreement# 19-7558
14A7
CONSULTANT shall have the authority to make decisions related to the interpretation
of the requirements of the Contract Documents pertaining to the execution and progress
of the work.
The CONSULTANT will review and comment on each shop drawing or technical
submittal a maximum of three (3) times. Additional reviews shall be eligible for
additional compensation.
1.2) Under this task, the CONSULTANT will prepare technical responses to the questions
submitted by the Contractor in the format of a Request for Information (RFI). The RPR
will collect, log, and distribute RFI's to the appropriate technical lead for responses and
return the RFI responses to the CONTRACTOR.
The CONSULTANT shall act as initial interpreter of the requirements of the Contract
Documents and judge of the acceptability of the work. The CONSULTANT shall have the
authority to make decisions related to the interpretation of the requirements of the
Contract Documents pertaining to the execution and progress of the work. The
CONSULTANT shall also provide technical support and clarifications related to the
construction documents and shall provide any required revisions or supplemental
information related to the contract documents that may be required during construction.
Task 2: Weekly Meetings and Site Visits
2.1) Under this task, the CONSULTANT's Project Manager and/or appropriate technical leads
will attend weekly meetings(either in-person or by phone) and make periodic visits to the
site during construction.
The CONSULTANT will also conduct a Pre-Construction Conference before the
Contractor is provided with a construction Notice to Proceed. The purpose of this meeting
will be to review general administrative procedures of the contract, review technical
requirements, begin the submittal process, and other items as defined in the Contract
Documents.
In addition, the CONSULTANT's Project Manager and/or technical leads will attend the
Substantial Completion and Final Inspections.
Task 3: Preparation of Closeout and Record Documents
3.1) Under this task, the CONSULTANT will take the Contractor's red lined and surveyed as-
built information and incorporate them into the Construction Drawings for the Airport's
record purposes. Also, under this task the CONSULTANT will assist the RPR in
preparing the technical related project closeout documentation in accordance with
COUNTY and FAA requirements.
Page 6 of 12
First Amendment to Agreement# 19-7558
I4A ?
SCHEDULE B-2
BASIS OF COMPENSATION
(First Amendment)
1. MONTHLY STATUS REPORTS
B.1.1. As a condition precedent to payment, CONSULTANT shall submit to the COUNTY as part of its monthly
invoice a progress report reflecting the Project status, in terms of the total work effort estimated to be required
for the completion of the Basic Services and any authorized Additional Services, as of the last day of the subject
monthly billing cycle. Among other things, the report shall show all Service items and the percentage complete
of each item.
2. COMPENSATION TO CONSULTANT
B.2.1. For the Basic Services provided for in this Agreement, the COUNTY agrees to make the payments to
CONSULTANT in accordance with the terms stated below. Payments will be made in accordance with the
following Schedule; however, the payment of any particular line item noted below shall not be due until services
associated with any such line item have been completed or partially completed to the COUNTY's reasonable
satisfaction. Lump sum payments will be made upon the percentage complete. In no event shall such Time
and Materials compensation exceed the amounts set forth in the table below.
Tasks/Item Description Lump Sum Time and
Materials
Not-To-Exceed
TAXIWAY C
1 Post Design Services $ 10,462.00 $
2 Weekly Meetings and Site Visits $ 17,398.25 $
3 Preparation of Closeout and Record Documents $7,318.00 $
$ $
$ $
RUNWAY 18/36
1 Post Design Services $13,850.00 $
2 Weekly Meetings and Site Visits $17,398.25 $
3 Preparation of Closeout and Record Documents $ 7,318.00 $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
$ $
Total Lump Sum Fee $73,744.50
Total Time and Materials Fee $
GRAND TOTAL FEE $73,744.50
Page 7 of 12
First Amendment to Agreement# 19-7558
14A2
B.2.2.1. Notwithstanding anything herein to the contrary, in no event may CONSULTANT's monthly
billings, on a cumulative basis, exceed the sum determined by multiplying the applicable not to exceed task(s)
limits by the percentage the COUNTY has determined CONSULTANT has completed such task as of that
particular monthly billing.
B.2.3. ®* Lump Sum Fees: The fees noted in Section 2.1. shall constitute the lump sum amount to be paid to
CONSULTANT for the performance of the Basic Services. There shall be no overtime pay without the
COUNTY's prior written approval.
B.2.3.1 CONSULTANT shall submit, with each of the monthly status reports provided for under Section
B.1.1 of this Schedule B, an invoice for fees earned in the performance of Basic Services and Additional
Services during the subject billing month.
B.2.4. For Additional Services provided pursuant to Article 2 of the Agreement, if any, the COUNTY agrees to
pay CONSULTANT a negotiated total fee and Reimbursable Expenses based on the services to be provided
and as set forth in the Amendment authorizing such Additional Services. The negotiated fee shall be based
upon the rates specified in Attachment 1 to this Schedule B and all Reimbursable Expenses shall comply with
the provision of Section 3.4.1 below. There shall be no overtime pay on Additional Services without the
COUNTY's prior written approval.
B.2.5. The compensation provided for under Section B.2.1 of this Schedule B, shall be the total and complete
amount payable to CONSULTANT for the Basic Services to be performed under the provisions of this
Agreement, and shall include the cost of all materials, equipment, supplies and out-of-pocket expenses incurred
in the performance of all such services.
B.2.6. Notwithstanding anything in the Agreement to the contrary, CONSULTANT acknowledges and agrees
that in the event of a dispute concerning payments for Services performed under this Agreement,
CONSULTANT shall continue to perform the Services required of it under this Agreement, as directed by the
COUNTY, pending resolution of the dispute provided that the COUNTY continues to pay to CONSULTANT all
amounts that the COUNTY does not dispute are due and payable.
3. SCHEDULE OF PAYMENTS
B.3.1. Notwithstanding anything herein to the contrary, the CONSULTANT shall submit no more than one
invoice per month for all fees earned that month for both Basic Services and Additional Services. Invoices shall
be reasonably substantiated, identify the services rendered and must be submitted in triplicate in a form and
manner required by the COUNTY.
B.3.1.1 Payments will be made for services furnished, delivered, and accepted, upon receipt and
approval of invoices submitted on the date of services or within six (6) months after completion of contract. Any
untimely submission of invoices beyond the specified deadline period is subject to non-payment under the legal
doctrine of "laches" as untimely submitted. Time shall be deemed of the essence with respect to the timely
submission of invoices under this Agreement.
B.3.2. Invoices not properly prepared (mathematical errors, billing not reflecting actual work done, no
signature, etc.) shall be returned to CONSULTANT for correction. Invoices shall be submitted on
CONSULTANT's letterhead and must include the Purchase Order Number and Project name and shall not be
submitted more than one time monthly.
Page 8 of 12
First Amendment to Agreement# 19-7558
�, I
1 4 A 2
B.3.3. Payments for Additional Services of CONSULTANT as defined in Article 2 hereinabove and for
reimbursable expenses will be made monthly upon presentation of a detailed invoice with supporting
documentation.
B.3.4. Unless specific rates have been established in Attachment 1, attached to this Schedule B,
CONSULTANT agrees that, with respect to any subconsultant or subcontractor to be utilized by CONSULTANT
for this Agreement or Additional Services, CONSULTANT shall be limited to a maximum markup of five percent
(5%)on the fees and expenses associated with such subconsultants and subcontractors.
B.3.4.1 Reimbursable Expenses must comply with §112.061, Fla. Stat., or as set forth in the
Agreement, be charged without mark-up by the CONSULTANT, and shall consist only of the following items:
B.3.4.1.1. Cost for reproducing documents that exceed the number of documents described in
this Agreement and postage and handling of Drawings and Specifications.
B.3.4.1.2. Travel expenses reasonably and necessarily incurred with respect to Project related
trips, to the extent such trips are approved by the COUNTY. Such expenses, if approved by the COUNTY, may
include coach airfare, standard accommodations and meals, all in accordance with §112.061, Fla. Stat. Further,
such expenses, if approved by the COUNTY, may include mileage for trips that are from/to destinations outside
of Collier or Lee Counties. Such trips within Collier and Lee Counties are expressly excluded.
B.3.4.1.3. Permit Fees required by the Project.
B.3.4.1.4. Expense of overtime work requiring higher than regular rates approved in advance
and in writing by the COUNTY.
B.3.4.1.5. Expense of models for the County's use.
B.3.4.1.6. Other items on request and approved in writing by the COUNTY.
B.3.4.1.7. The CONSULTANT shall bear and pay all overhead and other expenses, except for
authorized reimbursable expenses, incurred by CONSULTANT in the performance of the Services.
B.3.4.1.8. Records of Reimbursable Expenses shall be kept on a generally recognized
accounting basis.
B.3.5. The CONSULTANT shall obtain the prior written approval of the COUNTY before incurring any
reimbursable expenses, and absent such prior approval, no expenses incurred by CONSULTANT will be
deemed to be a reimbursable expense.
Page 9 of 12
First Amendment to Agreement# 19-7558
14A ?_
SCHEDULE B-2—ATTACHMENT 1
(FIRST AMENDMENT)
CONSULTANT'S HOURLY RATE SCHEDULE
Title Hourly Rate
Sr. Engineer $160
Designer $110
Clerical $60
The above hourly rates are applicable to Time and Materials task(s) only. The above list may not be all
inclusive. Additional hourly rates for other personnel may be added via an Amendment upon mutual agreement
in advance and in writing by the parties. For Grant Funded Projects, the above hourly rates are for purposes
of providing estimate(s), as required by the grantor agency.
Page 10 of 12
First Amendment to Agreement# 19-7558
14A2
SCHEDULE C-2
(First Amendment)
PROJECT MILESTONE SCHEDULE
Number
Tasklltem of Calendar Days
Description For Completion of Tasks
from Date of
Notice to Proceed
Taxiway C
1 Post Design Services 225
(165 Construction Days plus 60 days)
2 Weekly Meetings and Site Visits 225
(165 Construction Days plus 60 days)
3 Preparation and Closeout and Record Documents 225
(165 Construction Days plus 60 days)
Runway 18136
1 Post Design Services 215
(185 Construction Days plus 30 days)
2 Weekly Meetings and Site Visits 215
(185 Construction Days plus 30 days)
3 Preparation and Closeout and Record Documents 215
(185 Construction Days plus 30 days)
Page 11 of 12
First Amendment to Agreement# 19-7558
14A2
SCHEDULE F-2
(FIRST AMENDMENT)
KEY PERSONNEL
Name Personnel Category Percentage of
Time
TAXIWAY C
Tim Parker, P.E. Project Manager 5%
Rick Brylanski, P.E. Principal-in-Charge 1%
Austin Brown, E.1 Project Engineer 5%
Jackie Lopez Clerical/Administrative 1%
RUNWAY 18/36
Tim Parker, P.E. Project Manager 10%
Rick Brylanski, P.E. Principal-in-Charge 1%
Austin Brown, E.I Project Engineer 10%
Jackie Lopez Clerical/Administrative 5%
Page 12 of 12
First Amendment to Agreement# 19-7558
Detail by Entity Name Page 1 of 3
14A2
Florida Department of State DIVISION OF CORPORATIONS
r_,
Divi IOi I of
5Yiz9f .org JI POr),=Yrr_rDI IL'
an oJfrrul.;rfNr a/Ilor'irla Ffntre
Department of State / Division of Corporations / Search Records / Search by Entity Name /
Detail by Entity Name
Florida Profit Corporation
HOLE MONTES, INC.
Filing Information
Document Number 449782
FEI/EIN Number 59-1518838
Date Filed 04/03/1974
State FL
Status ACTIVE
Last Event AMENDMENT
Event Date Filed 08/04/2020
Event Effective Date NONE
Principal Address
950 ENCORE WAY
NAPLES, FL 34110
Changed:02/20/2001
Mailing Address
950 ENCORE WAY
NAPLES, FL 34110
Changed:03/07/2008
Registered Agent Name&Address
Sapp,June T
950 ENCORE WAY
NAPLES, FL 34110
Name Changed:05/03/2019
Address Changed: 02/20/2001
Officer/Director Detail
Name&Address
Title CEO, Director
TAYLOR,THOMAS M
950 ENCORE WAY
NAPLES, FL 34110
http://search.sunbiz.org/Inquiry/CorporationSearch/SearchResultDetail?inquirytype=Entit... 10/23/2020
Detail by Entity Name Page 2 of 3
1 4 A ?
Title Secretary,Treasurer
June T. Sapp
950 ENCORE WAY
NAPLES, FL 34110
Title VP
BRYLANSKI, RICHARD
6200 WHISKEY CREEK DRIVE
FORT MYERS, FL 33919
Title VP, Director
BENSON, RONALD E
950 ENCORE WAY
NAPLES, FL 34110
Title VP, Director
Cole,William Terry
950 ENCORE WAY
NAPLES, FL 34110
Title VP
Murphy,Thomas
950 ENCORE WAY
NAPLES, FL 34110
Title President, Director
Mulhere, Robert
950 ENCORE WAY
NAPLES, FL 34110
Title VP
Schmitt, David
950 ENCORE WAY
NAPLES, FL 34110
Title V
PRYSI,WILLIAM E
6200 WHISKEY CREEK DR
FORT MYERS, FL 33919
Annual Reports
Report Year Filed Date
2019 04/24/2019
2019 05/03/2019
http://search.sunbiz.org/Inquiry/CorporationSearch/SearchResultDetail?inquirytype=Entit... 10/23/2020
Detail by Entity Name Page 3 of 3
I4A2
2020 02/07/2020
Document Images
08/04/2020--Amendment View image in PDF format
02/07/2020--ANNUAL REPORT View image in PDF format
05/03/2019--AMENDED ANNUAL REPORT View image in PDF format
04/24/2019--ANNUAL REPORT View image in PDF format
03/05/2018--ANNUAL REPORT View image in PDF format
03/20/2017--ANNUAL REPORT View image in PDF format
02/18/2016--AMENDED ANNUAL REPORT View image in PDF format
02/11/2016--ANNUAL REPORT View image in PDF format
04/16/2015--AMENDED ANNUAL REPORT View image in PDF format
02/04/2015--ANNUAL REPORT View image in PDF format
03/05/2014--ANNUAL REPORT View image in PDF format
02/28/2013--ANNUAL REPORT View image in PDF format
01/06/2012--ANNUAL REPORT View image in PDF format
02/22/2011--ANNUAL REPORT View image in PDF format
02/18/2010--ANNUAL REPORT View image in PDF format
03/18/2009--ANNUAL REPORT View image in PDF format
03/07/2008--ANNUAL REPORT View image in PDF format
03/12/2007--ANNUAL REPORT View image in PDF format
03/09/2006--ANNUAL REPORT View image in PDF format
03/30/2005--ANNUAL REPORT View image in PDF format
02/10/2004--ANNUAL REPORT View image in PDF format
04/28/2003--ANNUAL REPORT View image in PDF format
02/26/2003--ANNUAL REPORT View image in PDF format
02/03/2002--ANNUAL REPORT View image in PDF format
02/20/2001--ANNUAL REPORT View image in PDF format
11/29/2000--Name Change View image in PDF format
03/24/2000--ANNUAL REPORT View image in PDF format
04/14/1999--ANNUAL REPORT View image in PDF format
01/22/1998--ANNUAL REPORT View image in PDF format
02/19/1997--ANNUAL REPORT View image in PDF format
04/05/1996--ANNUAL REPORT View image in PDF format
03/22/1995--ANNUAL REPORT View image in PDF format
02/03/1995--ANNUAL REPORT View image in PDF format
04/03/1974--Filings Prior to 1995 View image in PDF format
Florida Department of State,Division of Corporations
http://search.sunbiz.org/Inquiry/CorporationSearch/SearchResultDetai 1?inquirytype=Entit... 10/23/2020