#14-6213 Amend #3 (Kyle Construction, Inc.) THIRD AMENDMENT TO AGREEMENT #14-6213
FOR
UNDERGROUND UTILITY CONTRACTORS
THIS AMENDMENT, made and entered into on this v day of t(9 612( 2020,
by and between Kyle Construction, Inc., (the "Contractor") and Collier County, a political
subdivision of the State of Florida, (the "County" or "Owner"):
WHEREAS, on July 8, 2014 (Agenda Item No. 16.C.10), the County entered into an
Agreement with Contractor to obtain the professional utility contracting services (the "Agreement");
and
WHEREAS, on October 6, 2014, the County administratively approved the First
Amendment to the Agreement amending Section 4, The Contract Sum, to include language allowing
Contractor to be compensated for time and material work, including material and specialty equipment
markup, either for emergency and non-emergency work, include Exhibit Al-A rate sheet and a not to
exceed markup of 10% for subcontractors; and
WHEREAS, on May 3, 2016, the County administratively approved the Second
Amendment to the Agreement to include Section 4.1 Price Methodologies (Lump Sum, Time and
Material and Unit Price) definitions to Section 4. The Contract Sum; and
WHEREAS, the Agreement has exhausted all renewals and extensions and is set to expire
on 01/03/2021; and
WHEREAS, the parties desire to amend the Agreement to request an additional six-month
extension to the existing Agreement to allow staff time to enter a new contract for underground
contractor services.
NOW, THEREFORE, in consideration of the mutual promises and covenants herein
contained, it is agreed by the parties as follows:
1. The Agreement shall now be extended for an additional six months, commencing on
01/04/2021 and terminating on 07/04/2021 or until the County exercises termination for
convenience in accordance with paragraph 9 of the Agreement, whichever is sooner.
2. All other terms and conditions of the Agreement, as amended, shall remain the same.
[Signature page to follow]
[20-PRC-04500/1577589/1] Page 1 of 2
Third Amendment to Agreement 14-6213
Kyle Construction, Inc.
CA()
IN WITNESS WHEREOF,the parties have executed this Third Amendment on the date and year first written
above by an authorized person or agent.
ATTEST: a• 111 i
Crystal K. Kin2 ,•Clerrb►l+ urt& BOARD OF COUNTY COMMISSIONERS
Comptroller COLLIER COUNTY, FLORIDA
By. -t;tl 1 S By: 4044411/..Ae40/4.4--
i nattlre onl • Burt L. Saunders, Chairman
Dated: g 1XX)
(SEAL)
Contractor's Witnesses: CONTRACTOR:
K e Cons tion,Inc.
trst ness B :
re
Ay(e. Arab ow'Y1
TT e/print witness na el' koala R. Moca1-x1 l
TType/print signature and title''
Second Witness
I ► /3 )20Zo
Coo Y)e A-bra.. cxrY1 Date
TType/print witness namet
Approve as to Form and Legality:
s t ounty Attorney
SQL 1An ce\ v9
Print Nan °\
[20-PRC-04500/1577589/1] Page 2 of 2
Third Amendment to Agreement 14-6213
Kyle Construction,Inc.
A C