Agenda 11/10/2020 Item #16E 6 (Procurement Services Change Orders and other contract modifications requiring Board approval)11/10/2020
16.E.6
EXECUTIVE SUMMARY
Recommendation to approve the administrative reports prepared by the Procurement Services
Division for change orders and other contractual modifications requiring Board approval.
OBJECTIVE: To promote accountability and provide transparency to the public and gain the
Board's approval/ratification for various procurement -related transactions.
CONSIDERATIONS: In accordance with the Board's Procurement Ordinance 2017-08 and the
Procurement Manual, the Procurement Services Division produces a regular administrative report which
provides for Board approval of the following transactions:
• Change Orders that do not exceed ten (10%) of the current Board approved aggregate amount,
and/or require change in schedule (number of days);
• Amendments to contracts;
• After the fact memos from various County Divisions, as requested by the Clerk's Finance staff
for the timely process of invoices.
• Other items as determined by the County Manager or designee that require Board approval.
This administrative report includes the following:
• Four (4) change orders that in aggregate modify contracts by $219,580.89. and add 115 calendar
days to completion periods, see attached summary and backup for details; and
• Zero (0) amendments this period with a fiscal impact of $0.00; and
• One (1) after the fact memo with a fiscal impact of $6,961.00 for additional services
FISCAL IMPACT: The net total for the five (5) items is $226,541.89.
LEGAL CONSIDERATIONS: This item is approved for form and legality and requires a majority
vote for Board action.
GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this
action.
RECOMMENDATION: To ratify/approve change orders and/or contract amendments and other items
as determined by the County Manager or designee in accordance with Procurement Ordinance 2017-08.
Prepared By: Sara Schneeberger, Procurement Strategist, Procurement Services
ATTACHMENT(S)
1. 1110 After the Fact Report - FY21 (PDF)
2. 1110 After the Fact Backup - FY21 (PDF)
3. 1110 Revised Change Order Report - FY21 (PDF)
4. 1110 Revised Change Order Backup - FY21 (PDF)
Packet Pg. 1832
16.E.6
11/10/2020
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.E.6
Doe ID: 13992
Item Summary: Recommendation to approve the administrative reports prepared by the
Procurement Services Division for change orders and other contractual modifications requiring Board
approval.
Meeting Date: 11/10/2020
Prepared by:
Title: Business Technology Analyst, Senior — Procurement Services
Name: Sara Schneeberger
10/21/2020 11:14 AM
Submitted by:
Title: Manager - Procurement — Procurement Services
Name: Sandra Herrera
10/21/2020 11:14 AM
Approved By:
Review:
Procurement Services
Procurement Services
Procurement Services
Administrative Services Department
Administrative Services Department
County Attorney's Office
Office of Management and Budget
Office of Management and Budget
County Manager's Office
Board of County Commissioners
Opal Vann
Level 1 Purchasing Gatekeeper
Catherine Bigelow
Additional Reviewer
Sandra Herrera
Additional Reviewer
Paula Brethauer
Level 1 Division Reviewer
Len Price
Level 2 Division Administrator Review
Jeffrey A. Klatzkow
Level 3 County Attorney's Office Review
Debra Windsor
Level 3 OMB Gatekeeper Review
Laura Wells
Additional Reviewer
Nick Casalanguida
Level 4 County Manager Review
MaryJo Brock
Meeting Pending
Completed
10/21/2020 11:18 AM
Completed
10/21/2020 11:22 AM
Completed
10/21/2020 1:18 PM
Completed
10/21/2020 2:16 PM
Completed
10/23/2020 12:56 PM
Completed
10/23/2020 2:42 PM
Completed
10/26/2020 8:22 AM
Completed
10/26/2020 10:17 AM
Completed
11/01/2020 8:14 AM
11/10/2020 9:00 AM
Packet Pg. 1833
W
to
T-
(s;.wdai anilea;siuiwpe saainiaS;uawainaoad : Z66£�) �ZAI -:podab loezlayl jeljv o��� :luewy3e;)d
7
O
O
L
It
CM
co
IL
d
Y
V
IL
C.O e-r C;0""ty Collier County
Administrative Services Department After the Fact Form
Procurement Services Division
Instructions
As per section 21 of the Procurement Manual, all purchases shall be consistent and in compliance with the Procurement
Ordinance (2017-08). Should work be authorized or purchases made that is inconsistent with County policy, procedure, or
contract terms, an After -the -Fact Procurement Form is required. This includes purchases made in advance of a Purchase Order,
when a Purchase Order is required to authorize such activity, and purchases made under an expired contract, or for goods and
services not covered by the current contract or purchase order. All such `After the Fact Procurements" will be reported to the
County Manager.
Requester Name: Ayoub Al-Bahou
Division: Parks and Recreation
Division Director: Barry Williams
vendor Name: Aptim Coastal Planning & Eng.
Amount: $6,961.00
contract #:13-6164/4600003478
Purchase Order: 4500188404 & 4500196137
Why is this deemed a non -compliant purchase? Choose one.
Contract W]
Ordinance
Manual ❑
P-Card ❑
Other ❑
Details of Purchase: Explain the circumstances behind this purchase.
Staff inadvertently requested services from Aptim Coastal without verifying the remaining time on
the contract and processing a change order to extend the work order. Project manager has
confirmed that services were rendered and payment is now due to vendor.
Action Required: What are you asking to be done to remedy the situation, include list of invoices if applicable?
Please process payment for the following 3 invoices totaling $6,961.00
486429 - $3,460.75 - PO 4500188404
487222 - $1,667.75 - PO 4500196137
490682 - $1,832.50 - PO 4500188404
Payment is due to vendor number 123397 - Aptim Coastal Planning & Engineering.
Corrective/Preventive Action: What action is being taken to prevent this violation from re -occurring?
We will reinforce purchasing policies and procedures with staff to avoid this issue in the future.
Facilities Management has also created a contract spreadsheet to keep track of project time
lines.
The requestor affirms that to the best of their knowledge the information provided in this document is true.
Requested by: Ayoub R. AI-Bahou, P.E., P.P.M.
Signature: AI-bahouAyoubDatea'zo20.10.09Y9';0 32040o
Date:
Division Director:
Barry Williams
g y Date 2 20.10.ally signed by W11 00 _0 rrY
Signature: I IamS arr Dace zoza,a,z,o:,too-oa�oo
Date:
Packet Pg. 1835
2
APTIM
Collier County
Collier County Board of County Commissioners
Clerks Finance Department
3299 Tamiami Tri STE 700
Naples, FL 34112-5749
Consultant's Project # 636236701
Billing Period: 2/3/2020 through 3/29/2020
Professional Engineering Services for:
951 Floating Dock
PO# 45-188404
Contract # 13-6164
Collier County Project #80361
TASK 1: Site Investigation
Contract Amount: $24,393.00
Previously Invoiced: $24,355.00
Payment Received: $24,355.00
TASK 2: Engineering Design
Contract Amount: $13,587.00
Previously Invoiced: $13,569.75
Payment Received: $13,569.75
TASK 3: Permitting
Contract Amount: $9,296.00
Previously Invoiced: $9,266.00
Payment Received: $9,266.00
TASK 4: Final Engineering
Contract Amount: $12,194.00
Previously Invoiced: $4,097.73
Payment Received: $4,097.73
WEEK ENDING:
03/15/20
03/29/20
02/19/20
03/01 /20
DIRECT LABOR:
HOURS
Senior Engineer- D. Mann
8.75
Senior Engineer- D. Mann
11.00
Surveyor & Mapper- M. Lowiec
2.00
Surveyor & Mapper- M. Lowiec
1.00
22.75
TASK 5: Construction Engineering
Contract Amount: $13,922.00
Previously Invoiced: $0.00
Payment Received: $0.00
TASK 6: Reimburseable Expenses
Contract Amount: $1,600.00
Previously Invoiced: $963.83
Payment Received: $963.83
TOTAL TASK 1
TOTAL TASK 2
TOTAL TASK 3:
$157.00
$120.00
$120.00
TOTAL TASK 4:
TOTAL TASK 5:
TOTAL TASK 6:
TOTAL CURRENT AMOUNT DUE THIS INVOICE .................
APTI M
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel: +1-561-391-8102
Fax: +1 561-391-9116
April 8, 2020
Invoice # 486429
$0.00
$0.00
$0.00
TOTAL DUE
$1,373.75
$1,727,00
$240.00
$120.00
$3,460.75
$3,460.75
$0.00
$0.00
N
LL
Y
ca
m
T
U
M
LL
N
t
L
N
Q
0
r
r
C
N
I=
t
v
M
r
Q
$3,460.75
Please remit to:
P.O. Box 847958
Boston, MA 02284-7958
Packet Pg. 1836
3
APTIM
APTI M
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel: +1-561-391-8102
Fax: +1 561-391-9116
Collier County
April 15, 2020
r
Collier County Board of County Commissioners
Invoice # 487222
O
Clerks Finance Department
N
3299 Tamiami Trl STE 700
y
Naples, FL 34112-5749
>_
ra
Consultant's Project # 636009448
N
Billing Period: 2/1/2020 through 3/29/2020
MA
Professional Engineering Services for:
E
951 Floating Dock Design
R
to
PO# 45-196137
N
v
Contract# 13-6164CZ
Collier County Project # 80361
d
Cl)
TASK 1: Waterfront Assessment
Contract Amount: $7,672.00
m
Previously Invoiced: $7,621.75
E
Payment Received: $7,621.75
WEEK ENDING: DIRECT LABOR:
HOURS
RATE
TOTAL DUE
0
03/08/20 Engineer- E. Carr -Betts
0.25
$123.00
$30.75
d
02/23/20 Clerical- T. McCauley
0.25
$62.00
$15.50
N
0.50
$46.25
ce)
M
TOTAL TASK 1:
$46.26
TASK 2: Design, Permitting and Construction Documents for Repair
r
N
Contract Amount: $15,070.00
lei
Previously Invoiced: $13,441.25
'
Payment Received: $13,441.25
Q'
WEEK ENDING: DIRECT LABOR:
HOURS
RATE
TOTAL DUE
.he
03/22/20 Senior Designer- K. Christoff
3.00
$114.00
$342.00
m
03/29/20 Senior Designer- K. Christoff
10.50
$114.00
$1,197.00
03/22/20 Planner- H. Berckenhoff
0.75
$110.00
$82.50
v
ra
LL
14.25
$1,621.50
TOTAL TASK 2:
$1,621.50
y
r
TASK 3: Reimburseable Expenses
Q
Contract Amount: $200.00
Previously Invoiced: $84.92
Payment Received: $84.92
EXPENSES:
N
E
TOTAL TASK 3:
$0.00
t
v
R
r
r
Q
TOTAL CURRENT AMOUNT DUE THIS INVOICE ................. $1,667.75
Please remit to:
P.O. Box 847958
Boston, MA 02284-7958
Packet Pg. 1837
2
APTIM
Collier County
Collier County Board of County Commissioners
Clerks Finance Department
3299 Tamiami Trl STE 700
Naples, FL 34112-5749
Consultant's Project # 636236701
Billing Period: 3/30/2020 through 4/30/2020
Professional Engineering Services for
951 Floating Dock
PO# 45-188404
Contract # 13-6164
Collier County Project #80361
TASK 1: Site Investigation
Contract Amount: $24,393.00
Previously Invoiced: $24,355.00
Payment Received: $24,355.00
TASK 2: Engineering Design
Contract Amount: $13,587.00
Previously Invoiced: $13,569.75
Payment Received: $13,569.75
TASK 3: Permitting
Contract Amount: $9,296.00
Previously Invoiced: $9,266.00
Payment Received: $9,266.00
TASK 4: Final Engineering
Contract Amount: $12,194.00
Previously Invoiced: $7,558.48
Payment Received: $4,097.73
TOTAL TASK 1:
TOTAL TASK 2:
TOTAL TASK 3:
WEEK ENDING:
DIRECT LABOR:
HOURS
RATE
04/05/20
Senior Engineer- D. Mann
1.50
$157.00
04/12/20
Senior Engineer- D. Mann
2.00
$157.00
04/26/20
Senior Engineer- D. Mann
1.75
$157.00
04/30/20
Senior Engineer- D. Mann
0.25
$157.00
04/26/20
Senior Designer- K. Christoff
8.50
$114.00
14.00
TOTAL TASK 4:
TASK 5: Construction Engineering
Contract Amount: $13,922.00
Previously Invoiced: $0.00
Payment Received: $0.00
TOTAL TASK 5:
TASK 6: Reimburseable Expenses
Contract Amount: $1,600.00
Previously Invoiced: $963.83
Payment Received: $963.83
TOTAL TASK 6:
TOTAL CURRENT AMOUNT DUE THIS INVOICE .................
APTI M
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel: +1-561-391-8102
Fax: +1 561-391-9116
May 21, 2020
Invoice # 490682
$0.00
$0.00
$0.00
TOTAL DUE
$235.50
$314.00
$274.75
$39.25
$969.00
$1,832.50
$1,832.50
$0.00
$0.00
$1,832.50
Please remit to:
P.O. Box 847958
Boston, MA 02284-7958
Packet Pg. 1838
2
w
k
a |e! Jnm|Wp s mmeS ewa n o d:Z 6 L �zA]-:podeN,ep 0 eBueLlo pemAO N OL��: ems mlv
\o
J7i!
\
$
f
»�2!
a
§
CO
Lq
)!
a
o
)k
CO
o
kk
)
\
o
)
§»
:
®
«
w
\
\
cL
Lu
EL
L�
�
<
|
o
s
]
)
o
>
/
ƒ
EL
\
{
�
{
*
EE
{oo
)}
co
�EL
})
o
��
co
\}
�!
-
m
$
!
3
o
._e
— _,
7
/lDejzuo:)
\
�
(
§
,_a
_,
l 16.E.6.d
County
Procurement Services
Change Or
xie-rl�
® Contract Modif ❑ Work Order Modification ❑ Amend
Contract #: 20-7684 Change #: 02 Purchase Order #: 4500202679 Project #: N/A
Contractor/Firm Name: Wright Construction Group 7 Contract/Project: Thomasson Drive Beautification Project
T mi Sc tt --- I
Bayshore Gateway Triangle CRA
Project Manager Name: Division Name: c
Original Contract/Work Order Amount $ 6,022,618.68
Current BCC Approved Amount $ 6,022,618.69'
Current Contract/Work Order Amount $ 6,022,618.68
Dollar Amount of this Change $ 0.00
Revised Contract/Work Order Total $ 6,022,618.68
Cumulative Changes 1 $ 0.00
2/25/2020 ':Original BCC Approval Date; Agenda Item #
2/25/2020 Last BCC Approval Date; Agenda Item #
:SAP Contract Expiration Date (Master)
0.00% ;Total Change from Original Amount
0.00% 'Change from Current BCC Approved Amount
0.00% Chanae from Current Amount
Completion Date, Description of the Task( and Rationale for the Change
Notice to Proceed�5/6/2020 Original f 5/6/2021 Last Approved 5/6/2021 J Revi Date 6/6/2021
Date Completion Date L Date (Includes this change) l
# of Days Added 31 Select Tasks ® Add new task(s) ❑ Delete task(s) ❑ Change task( ❑ Other (see
below)
Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and l or the additional
days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed.
Attach additional information from the Design Professional and/or Contractor if needed.
Change Order No. 02 — Contract 20-7684
1. Detail of change — Add additional storm water drainage pipe and structures and replace failing cross drains under
Thomasson Drive, relocate and increase capacity of roadside ditch, utility adjustments, and sidewalk improvements between
Stations 26+30 and 42+20 as designed and provided by the Engineer of Record. This change will reduce the Contract
Allowance by $257,631.16 and add an additional 31 days to the contract.
2. These changes are due to localized flooding and a failing cross drain under Thomasson Drive that became apparent once
construction was underway and identified during field inspection. The improvements were requested by Collier County
Growth Management Department during onsite inspections with the Engineer of Record.
3. Impact of not processing this change- Improving the stormwater system and replacing the cross drains during the
Thomasson Drive project is cost-effective and will help to improve the stormwater system for the community.
Allowance balance after this change:
Allowance $541,91.9.63 Minus $257,631
Prepared by:
Tam! Scott, Pro
Acceptance of this Change Ol
conditions as contained in the
Contract shell constitute a full
to the change set forth herd
Accepted
Approved by: ,
, Collier County
Remaining.
Date:
rI-institute a modification to contract / work order identified above and will be subject to all the same terms and
f work order indicated above, as fully as If the same were stated in this acceptance. The adjustment, If any, to the
alDettlepent of any and all claims of the Contractor / Vendor / Consultant / Design Professional arising out of or related
elis for impact and delay costs.
Group, Inc,
Keisha Westbrook, P.E., RWA Engineering
Digitally signed by SchneebergerSara
Approved byS. c h n chneeeber gerSara Date: 2020.10.20 1 1:21:42-04'00__
Sara 5chneeberger, Procurement Strategist, Collier County
Approved by:
Collier County
Date:��(J�f�—
Date: ,% D
Date:
Date: AS�
Revised: 10/28/2014
(Divisions who may require additional signatures may include on separate sheet.)
PROCUREMENT USE ONLY
Admin BCC
— Packet Pg. 1840
2
Collier County Engineering & Proiect Management Division
WORK DIRECTIVE CHANGE
CONTRACT # / PROJECT NAME:
20-7684 / Thomasson Dr. Beautification Project
DATE OF ISSUANCE: 0812412020
OWNER: Collier County Board of Commissioners
CONTRACTOR: Wright Construction Group
EFFECTIVE DATE: 10/14/2020
PROJECT#: N/A
ENGINEER/DESIGN PROFESSIONAL: RWA
You are directed to proceed promptly with the following change(s):
Description: Due to localized flooding and failing cross drain pipes under Thomasson Drive, this Work
Directive to add additional storm drainage pipe & structures, replace failing cross drains under Thomasson
Drive, relocate and increase capacity of roadside ditch, utility adjustments, and sidewalk improvements between
Stations 26+30 and 42+20 was designed and provided by RWA Engineering via Plan Revision No. 04, All work
items and costs associated with Work Directive No, 04 are provided below.
There will be 31 days added to the contract for the additional work associated with Work Directive No. 04.
Purpose of Work Directive Change: These changes were not included in the original contract documents and
where requested by Collier County Stormwater Department and Collier County ROW Inspection Department
during on site discussions with the Engineer of Record.
Reason/Justification: This Work Directive is being issued to help minimize flooding and replace existing pipes
that have failed under Thomasson Drive.
If a claim is made that the above change(s) have affected Contract/Allowance Price or Contract Times any
claim for a Change Order based thereon will involve one or more of the following methods of determining the
effect of the changes(s).
Method of determining change in Method of determining change in Contract Times:
Contract/Allowance Price:
❑ Unit Prices ❑ Contractor's Records
❑ Lump Sum ❑ Engineer's Record
❑ Time & Material ❑ Other CEl's Record
❑ Other
Estimated decrease in Allowance: Estimated Change in Contract Time:
$257,631.16 Additional 31 Days
10/14/20 10:03 AM
Packet Pg. 1841
3
16.E.6.d
RECOMMENDED:
t�
By: Keisha Westbrook., P.E. 101' O-zozo
RWA Engineering
Engineer of Record
ACCEPTED:
eg Haas
Wright Construction Group
Construction Contractor
AUTHORIZED:
Digitally signed by Culligan, Floyd
M CN °Culligan, Floyd",
Culligan, Floyd OU=AECOMU es, DC na, AMER,
DC=aecomnet, DC=wm
Date: 2020.10.14 11:18:47-04'00'
By: Floyd Culligan
AECOM
Owner's CEI Contractor
Tami Scott
Collier County PP:
Owner's Representative
to, i1l -lao
10/14/20 10:03 AM
Packet Pg. 1842
4 16.E.6.d
1`
Thomasson Drive Beautification Project
BID SCHEDULE
Collier County Bid #20-7684
Change Estimate for Plan Revision 404
SIDEWALK REPLACEMENT & DRAINAGE - WEST OF BAYSHORE AECOM 10/14/2020
PAYITEM
I DESCRIPTION
UNIT
QUANTITY
I UNITCOSTS
COSTS
GENERAL
101.1-1 1PROVIDEIMAINTAIN SIGNED AND SEALED"AS BUILT" PLAN
!S
1
$2,278.00
$2,278.00
1014-2 PROVIDE CONSTRUCTION SURVEYING AND LAYOUT
LS
1
$2,484,00
$2,484.00
102-1 IMAINTENANCE OF TRAFFIC (ADDITIONAL WORK)
LS
1
$36,991X01
$36,991.00
GENERAL SUI-TOTAL= $41,753.00
DEMOLITION
110-1d
CLEARING AND GRUBBING (ADDITIONAL WORK)
LS
1
$54,902.15
$54,902.15
110.4-10
REMOVAL OF CONCRETE PAVEMENT
SY
735
$13.67
$10,047.45
110-4-102
REMOVAL OF EXISTING DRAINAGE PIPE (DISPOSE OF OFFSITE)
EF
17S
$11.44
$2,002.00
DEMOLITION SUB -TOTAL = $66,951.60
EROSION & SEDIMENT CONTROL
104-10-3
SILT FENCE (ADDITIONAL WORK)
LF
1300.00
$0.75
$975A0
104-18
INLET PROTECTION SYSTEM
EA
8
$95.00
$760,00
EROSION& SEDIMENT CONTROL SUB -TOTAL = $1,735.00
EARTHWORK
120.1
REGULAR EXCAVATION USE IN DITCH - NO HAUL OFF
CY
465
$18.94
$8,807,10
120-6
EMBANKMENT(ADDITIONAL WORK) 1
CY
k
100
$30.72
$3,072,00
570-1.2
PERFORMANCE TURF/SODDING I
SY
1 7501
$2.111
$1,582.50
EARTHWORKSUB-TOTAL= $13,461.60
DRAINAGE
425,1621
FDOT TYPE"C"INLET
EA
5
$2,135.05
$10,675.25
4251541
FDO_TYPE"D"INLET
EA
3
$2,77053
$8,311.59
430-174-124
PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 24" 5D
LF
32
$66.74
$2,135,68
430-175-124
PIPE CULVERT(RCP), OPTIONAL MATERIAL, ROUND, 24" S/CD (CROSSINGS)
LF
114
$71.94
$8,2DL16
430-174.130
PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 30" SO
LF
208
$82.091
$17,074.72
430-174136
JPIPE CULVERT, OPTIONAL MATERIAL, ROUND, 36" SD
LF
37
$88.97
$3,291.89
DRAINAGE SUB -TOTAL= $49,69129
PAVEMENT
121-70.6
FLOWABLE FILL FOR CROSS DRAIN PAVEMENT REPAIRS
CY
125
$185.65
$23,206.25
285-709
BASE GROUP 09 - 2-12.5 BLACK BASE (TRENCH RESTORATION - ADDITIONAL WORK)
LS
TBD
TBD
TBD
522-2
SIDEWALK AND DRIVEWAYS, 6" THICK
SY
88S
$35.75
$31,638.75
527-2
DETECTABLE WARNING (ADDITIONAL WORK)
SF
24
$23.00
$552.00
PAVEMENT SUB -TOTAL = $55,397.00
OTHER
0007001 UTILITY ADIUSTMENTS (RELOCATE 2 HYDRANTS/CUT AND PLUG 24" PIPEIMODIFY ES-49) LS I $16,374.52 $16,374.52
OTHERSUB-TOTAL= $16,374,52
BASE CONSTRUCTION COST
SUBTOTAL
$245,363.01
WRIGHT CONSTRUCTION MARKUP -5.00%
LS
0.05
$245,363.01
$12,268.15
GRAND TOTAL
$257,631.
Packet Pg. 1843
5
16.E.6.d
Cotwr Count/
® Contract Modification
❑ Work Order Modification ❑ Amendment
Procurement Services
Change Order Form
Contract #: 19 7558 ✓ Change M 1=
Purchase Order #: 4500200722/4500200723 Project #: 33650/33605
Contractor/Firm Name: Hole Montes, Inc. Contract/Project: Design Services for IMM Runway Rehabilitation
& Taxiway Extension Projects
Project Manager Name: Justin Lobb Division Name: Airport Authority
Original Contract/Work Order Amount $ ✓ 680,344.00 11/12/19 16G2 Original BCC Approval Date; Agenda Item #
Current BCC Approved Amount $ 680,344.00 11/12/19 16G2 Last BCC Approval Date; Agenda Item #
Current ContractfWork Order Amount $ 680,344.00 ✓ SAP Contract Expiration Date (Master)
Dollar Amount of this Change $ 0.00 0.00% Total Change from Original Amount
Revised Contract(Work Order Total $ 680,344.00 0.00% Change from Current BCC Approved Amount
Cumulative Changes $ 0.00 0.00% Change from Current Amount
Completion Date, Description of the Task(s) Change, and Rationale for the Change
Notice to Proceed 11/27/2019 ✓ Original 11/26/202 Last Approved 11/26/2020 Revised Date 1/25/2021 ✓
Date Completion Date Date (Includes this change)
# of Days Added 60 ✓ Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see
below)
Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(s) to the task(s) and / or
the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the Impact
if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
1. Zero Dollar Change Order to extend contract the sixty (60) days in order to provide transition into construction phase and maintain
engineering for necessary post design services during construction of the Runway 18/36 rehabilitation and Taxiway C extension
projects at the Immokalee Regional Airport. NOTE: This change order extends contract #19-7558 sixty (60) days, which includes
Purchase Orders 4500200722 and 4500200723. Both Purchase Orders will expire on 11/26/2020.
2. These services were contemplated but not included in the design contract because funding was not yet available. It was
anticipated that FDOT grant funding would be awarded in July or August 2020, at the beginning of the FDOT fiscal year. However,
because of COVID-19, FDOT funding has been delayed, and the Amendments to add these services cannot be executed until
FDOT grant agreements are fully executed.
3. If this change is not processed, the Engineer of Record will be unavailable to respond to Requests for Information (RFI's), certify
drawings, or assist with closeout documentation.
Prepared by:
Justi
Manager, Airport Authority
Date: 10/6/2020
Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same
terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The
adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant /
Design Professiona!,ari gs?�°—"tou 'bf�or related to the change set forth herein, including claims for impact and delay costs.
Accepted by: _
R
Approved by: /
Gen
, Vice President, Hole Montes, Inc.
, Growth Management Department
Approved by: f I
RN Thaddeus Cohen, Departmen a d, Growth Management Department
SchneebergerSara Digitally signed by SchneebergerSara
Approved by: Date: 2020.10.20 14:14:16-04'00'
Sara Schneeberger, Procurement Specialist, Procurement Services Division
Revised: 10/28/2014 (Divisions who may require additional signatures may include on separate sheet.)
Date:
Date:
Date:
Date:
PROCUREMENT USE ONLY
Admin
BCC ES
Rp!
Packet Pg. 1844
r 6 16.E.6.d
Procurement Services
c county Change Order Form
® Contract Modification ❑ Work Order Modification ❑ Amendment
Contract #: i 9-7590 Change #: E:—:::] Purchase Order #: 4500197793 1 Project #: ff136.1.3
Contractor/Finn Name: I PWC, LLC Contract/Project: SCRWTP Belt Filter Press Replacement
Project Manager Name:{
Alicia Abbott
Division Name `
Engineering & Project Management
Original Contract/Work Order Amount $ 602,825.00 911Cr19 1£C3
Original BCC Approval Date; Agenda Item #
Current BCC Approved Amount $ 602,825.0d' 9110r19 16C3
Last BCC Approval Date; Agenda Item #
Current Contract/Work Order Amount $ 602,825.00 10/20/2020
SAP Contract Expiration Date (Master)
Dollar Amount of this Change $ 0.00
0.00%
Total Change from Original Amount
Revised Contract/Work Order Total
$ 602,825.00
0.00%
Change from Current BCC Approved Amount
Cumulative Changes
$ 4.
0.00%
Change from Current Amount
Completion Date, Description of the Task(s) Change, and Rationale for the Change
Notice to Proceed 10J9l2019 Original 7/5/2020 Last Approved 10/20120 Revised Date 10/30/20
Date Completion Date Date
Includes this change)
10
# of Days Added
Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see
below)
Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and / or
the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact
if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
1. This change is to approve a time extension of ten days, to allow additional time for the suppliers' technicians to be on site for start-
up of the belt fitter press. This time will extend the current substantial completion date to August 31, 2020, and the final completion
date to October 30, 2020.
2. This change was not included in the original contract as it was not known at that time that the supplier of the belt fitter press would
encounter delays in scheduling the initial start-up of the equipment, due to travel restrictions in their state.
3. If the change is not processed, the following impacts would result:
The supplier is required to be on site during startup of their equipment, to ensure that the unit is operating as intended. The supplier
is located in New Jersey and the scheduling of technicians was delayed due to the travel restrictions for the State of NJ. If this
additional time is not granted, the contractor would not have the supplier present to start up the equipment, which may result in the
supplier not providing a warranty for the equipment.
abbott a Dig itaIlysigned by abbott_a
Prepared by: — Date: 2020.10.20 14:58:13 -04'00' Date:
Alicia Abbott, EL, Project Manager, Public Utilities Engineering and Project Management
Acceptance of this Change Order shall constitute a modification to contract J work order identified above and will be subject to all the same
terms and conditions as contained in the contract 1 work order indicated above, as fully as if the same were stated in this acceptance. The
adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant J
Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs.
DeAn e!O Henderson contact Info: 239 470-9130
9 Date: �n2o 10.?�0 12:04:3.04*BE 10 / 2 0/ 2 0 2 0
Accepted by: •*Pwc reserves the right to a suture O_a m far me reaar na t zs matter. Date:
Deangelo Henderson,,Sr. Project Manager, PWC, LLC
Approved by:
Approved by:
Engineer
>hjamin N. Bullert, P.E_, Public Utilities EPMD Principal Project Manager
ChmelikTom Digitally signed by ChmelikTom
Date: 2020.10.20 15:09:43-04'00'
Tom Chmelik, P.E., PMP, Public Utilities EPMD Director
Page 1 of 2
Date: lV to
Date:
Date:
Packet Pg. 1845
7
Approved by:
Steve-M—essner, WateF Director
SchneebergerSara Digitally signed by Schneeberger5ara
Approved by: Date: 2020.10.20 15:24:42-04'00'
Sara Schneeberger, Procurement Strategist, Procurement Services Division
16.E.6.d
Date: D Zv ZCZ to
Date:
Re,-idd: 10i28/2014 (Divisions who may require additional signatu— :rclude ors s,parate sheet.)
PROCUREMENT'.`-E ONl`/
Adman Fpacket Pg. 1846
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745
❑ this exhibit is not applicable
8 16.E.6.d
® Contract Modification
EXHIBIT F
CHANGE ORDER
❑ Work Order Modification
Contract M 17-7198 Change #: 16.3 Purchase Order #: 4500185615 Project #: 50156
Contractor/Firm Name: Manhattan Construction Florida Inc. Project Name: F
Phase 1 B Collier County Sports Complex
Project Manager Name: Margaret Bishop Department: Facilites Management
Original Contract/Work Order Amount
Current BCC Approved Amount
Current Contract/Work Order Amount
Dollar Amount of this Change
Revised Contract/Work Order Total
Cumulative Cha
$
19,665,469.0
12/10/19, 11.D
Original BCC Approval Date; Agenda Item #
$
20,072,296.8
6/23/20,16.E.4
Last BCC Approval Date; Agenda Item #
$
20,072,296.87
1/5/2021
SAP Contract Expiration Date (Master)
$ 219,580.89
3.19%
Total Change from Original Amount
$
20,291,877.76
1.09%
Change from Current BCC Approved Amount
$
626,408.761
1.09%
Change from Current Amount
Completion Date, Description of the Task(s) Change, and Rationale for the Change
Notice to Proceed 1-6 2020 Completion
Last Approved Revised Date )
1-5-2021 1-5-2021 1-19 2021
Date Comom letion Date Date Includes this change)
# of Days Added 14 Select Tasks ® Add new task(s) ❑ Delete task(s) ❑ Change task(s) ❑ Other (see below;
Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(s) to the task(s) and /
the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impac
this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
"The above costs are all related to the Collier County Sports Complex project. All cost break downs, fee break outs, and detailed back up an
included with the AR documents within this change order package. Notwithstanding anything to the contrary above, Construction Manager
does not release and expressly reserves the right to pursue claims for time extensions and additional compensation that arise out of or result
from the COVID-19 outbreak and the responses to this outbreak including implementation of any instructions, restrictions, and/or requiremen
by any federal, state, or local governmental or public health entity resulting from this outbreak and which claims may include, but are
not limited to, additional time and costs due to labor or material shortages, quarantines, and implantation of other safety and health
protocols."
1) This change order is requesting:
a) Authorization Request 7648.03-081 The installation of the Furniture, Fixtures and Equipment (FF&E) Low Voltage, Audio and
Visual System, Fire Alarm, Fiber connections, speakers, TV receptacles in the amount of $71,656.32.
b) Authorization Request 7648.03-072 Installation of the FF&E Landscape Ornamental Package that includes sculptures, stones,
boulders, red stone pillars, polished balls, benches, decorative plaque, and respective foundations/anchoring procured by Collier
County in the amount of $21,167.35.
c) Authorization Request 7648.03-119 Order and obtain varying sizes of rebar for the Great Lawn fire pits in the amount of $5,800.0
that will be taken from the owner contingency.
d) Authorization Request 7648.03-076 Installation of artificial turf on the two berm seating areas east of the stadium, including a
concrete wall on top of the berm, and fencing to secure the area in the amount of $30,605.18.
e) Authorization Request 7648.03-115 Change the rounded light fixture lenses at the Cove area to flat glass lenses to bring the to
voltage lighting into ADA compliance in the amount of $13,942.07.
f) Authorization Request 7648.03-077 Add hardware enhancements for security purposes in the amount of $41,743.72.
g) Authorization Request 7648.03-120 Add artificial turf for a safe fall area at the climbing wall and playing areas at the Cove area it
the amount of $21,086.75.
h) Authorization Request 7648.03-121 Additional sod added to the west of Cove Road for erosion purposes that will be future parkir
in the next phase of the project in the amount of $13,716.97.
i) Authorization Request 7648.03-122 Additional palm trees at the roundabout at the Cove area in the amount of $4,029.31.
j) Authorization Request 7648.03-124 Installation of Silt Fence between the Great Lawn and the north side of the Stadium in the
amount of $1,633.22.
The total amount requested is $219,580.89 and an additional 14 days is requested due to material lead time.
2) These changes were not included in the original contract because:
a,b,c) The finish items were purposely left out of the initial design and construction to allow the Owner and Sports Field Inc., the
contract manager, the ability to finalize the type and placement of finish items prior to the completion of construction. The installation
of some of these FF&E items would typically be done outside of the construction project. During selection, placement, and permittin
of these FF&E items, the contractor notified the owner that installation of these items required coordination with fire codes for
Packet Pg. 1847
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745
9 16.E.6.d
emergency shutoff and third -party vendors entering the site and modifying work in progress would void warranties. It is in the County's
best interest to have the Contractor install these items to meet code requirements and maintain warranty.
d) The berm changes were not included in the original contract because separating the berm seating from the outside of the stadiun
during an event was not anticipated. This change is a safety feature that required a design change to the plans to secure the area
during stadium events to prevent unauthorized persons from entering the area.
e) Due to the rounded floor lights being out of ADA compliance, all FX-FC-RG light fixtures around the walking areas of Phase 1 B
were requested to be changed from the specified rounded dome lenses to flush flat glass lenses in order to prevent tripping hazard;
around the walking path and bring into ADA compliance.
f) Collier county changed security access vendors after the construction contract was approved. The original pricing for security wa:
based upon the previous vendor and the new vendor Lenel, required new encrypted controllers and hardware substitutions to meet
county standards. In order to secure the Stadium, Food Truck and Fitness Pavilion, hardware enhancements that include electrified
strikes with panic devices and access control badge entry are added to the project.
o
g) Drainage changes were also added to the climbing wall and teqball areas that resulted in using artificial turf as a viable fall and
CL
playing area surface.
m
h) Future parking was added to the project after contract approval. Sod is required for erosion control purposes to meet code
>
compliance.
L
i) Additional palm trees at the roundabout at the Cove area were added due to design changes.
N
j) The Great Lawn is opening ahead of schedule and events will take place while the Stadium is still under construction. The
E
separation between the Great Lawn and construction at the Stadium is required for safety reasons to keep patrons from entering the
construction site.
'2
3) If this change is not processed:
The requested FF&E work will not be installed per safety codes prior to opening, the pavilion would be turned over to the County
without the items noted above, and a significant cost would be incurred to have a third -party come back after completion to permit,
install, and retrofit the structures. There is also the risk that structural penetrations, electrical connections, and site modifications
would void Contractor warranties. If this change is not processed the berm seating area will not be secured, leaving this area
vulnerable to unsafe conditions and security changes based upon the new access control system will not meet county standards.
Design changes were also included to improve upon ADA and code requirements for safety.
DocuSigned by:
Prepared by: _ Date: 10/30/2020
AOBOFDOEC647416...
(IViaryareL N. DiSnup, ra, racilities Management Division)
Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same ten
and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustme
if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professioi
arising out of or related to the change set forth herein, including claims for impact and delay costs.
DocuSigned by:
11/2/2020
Accepted by: _
O6CEE661 DOOA42ADate:
ry �iau iiau� aii U��...
�Uuution Florida, Inc.)
DocuSigned by:
Approved by:
�6sU" A& r Date: 11/2/2020
_
C3939948E...
`J I I ULI IVJII UU, L/QVIVaini �Iigineering)
DocuSigned by:
Approved by: _ oAa m 1 V1(A a.1 Date: 11/3/2020
twain i11 U ar i? uivision Director)
DocuSigned by: '
Approved by: SAVA St�uA,t,t,loWft,v Date: 10/30/2020
77336190C3294C6... lal)
Packet Pg. 1848
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81FO745 10
16.E.6.d
Manhattan
.Building excellence.
Authorization Request
....J
Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd, N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
To: Margaret Bishop
Collier County
3295 Tarnlam€ Trail East
Naples, FL 34112-4901
CE1B.068-PR#5R1 Electrical for FT & FP
From: Josh Willard
Manhattan Construction (FL), Inc.
3705-1 Westview DR
Naples, FL 34104
Pricing
$71,656.32
CIE:No Date Reference Alvotant Prapased pays Req , Category Reason
........
-0.: r0 Owner
Description
PhasetB Revision Electrical FT/FP
Notes
Cost Event Breakdown:
001 Add to include all low voltage for Fitness Pavilion and Food Truck Pavilion $66,689.02
ELECTRICAL -- B&i
Cost In include all of the updated design plans in relation to the low voltage
for the Food Truck and Fitness Pavilion. These were Issued to include the
speakers, TV's, Daktron€cs controls.
Level 1 1.5% SDI $1,000.34
Level 2 0.736% Performance & Payment Bond $504,05
Level 3 1.175% General Liability $795,36
Level 4 4% CM Fee $2.667.56
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule timelcost impact. We reserve the right to submit for cost/time impacts related to this change
under separate cover when that information is available.
Contractor does not release impacts that arise out of Acts of Nature (including fire, stood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war is declared or not), civil war, rebellion, revolution, Insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemlcs, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract.
Authorization Request: 7648.03-081
Approved By:
Margaret Bishop — Project Manager, Facilities ManagemerSIGNATURE BATE
Collier County Sports Complex Project # 7648
Prolog Manager
Packet Pg. 1849
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81F0745 11
16.E.6.d
Manhattan
Authorization Request
Rf ildilig, !'.i`f'f'.i1 f'Jl f.'E'. Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd. N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax: rn
To: Margaret Bishop From: Josh Willard
Collier County {Manhattan Construction (FL), Inc.
3295 Tamlaml Trail East 3705-1 Westview DR
Nantes. FL 34112-4901 Naples. FL 34104
GMP03 Ornament Placement
Pricing
$21,167.35
CE'No 'Data Reference Amount Proposed Days t2eq Category Reason
r r r�Owner Change
Description
Phase IB Landscape Ornament Placement
Notes
Cost Event Breakdown:
001 Add to Include additional work, as shown In the Exhibit A & B. $17,460.00
LAWNS & PLANTING -[O'DONNELL)
Placement of items in Exhibit A & B including Sculptures, Stones, Boulders,
Benches, Spikes and respective small concrete baseslachoring.
Large foundations for the benches and Monoliths are now included in this
change to safely secure the larger items and contian this scope with a
single subcontractor.
002 LAWNS & PLANTING - [O'DONNELLj
$2,250,00
Added cost for placement of 15 Cap Rocks around Light Pales, With the new
field lights, stones were designed to be placed in front of the poles for
decoration and buffer for any vehicles coming towards the light poles on the
sidewalks.
003 1.5% SDI
$295.55
004 4.0% CM Fee
$788.00
005 0.736% Performance & Payment Bond
$148.90
006 1.175% General Liability $234.90
Collier County Sports Complex Project # 7648
Prolog Manager
Packet Pg. 1850
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 12
16.E.6.d
Manhattan
l3rlilrlirrl; r�.rrr�Ilr�l�rc�.
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule time/cost impact. We reserve the right to submit for cost/time impacts related to this change
under separate cover when that information Is available,
Contractor does not release impacts that arise out of Acts of Nature (Including fire, flood, earihquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war is declared or not), civil war, rebellion, revolution, Insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation deiays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract.
Authorization Request: 7648.03-072
Approved By:
Margaret Bishop — Project Manager, Facilities ManagernerSIGNATURE
Collier County Sports Complex
Prolog Manager
DATE
Project # 7648
Packet Pg. 1851
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 13
16.E.6.d
Manhattan
Bitildingexcellence.
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd. N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
To, Margaret Bishop
Collier County
From: Josh Willard
Manhattan Construction (FL), Inc,
3295 Tamiami Trail East 3705-1 Westview DR
Naples, FL 34112-4901 Naples, FL 34104
Phase 1 B - Fire Pit Rebar
Pricing
r ! 11
CIS No t3ate +Reference Amount Proposed Days i2eq Category Reason
.....
Description
Phasel B Fire Pit Rebar
Notes
Cost Event Breakdown;
002 Added costs for the new decorative rebar In the fire pit. $5,800.00
This rebar was added In Addendum 5-R to surround the exposed gas pipes
of the fire pit at varying heights. The design brings higher asthetics and acts
as a barrier to the fire.
NAPLES CONCRETE & MASONRY
003
Fund the added rebar.
OWNER CONTINGENCY
($6,232.01)
Level 1
1,5% SDI
$87.00
Level 2
0.736% Performance & Payment Bond
$43.84
Level 3
1,176% General Liability
$69.17
Level 4
4.0% CM Fee
$232.00
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule timelcost Impact. We reserve the right to submit for costltime Impacts related to this change
under separate cover when that Information is available.
Contractor does not release impacts that arise out of Acts of Nature (Including fire, flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war Is declared or not), civil war, rebellion, revolution, insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and impact the Project, there shall be an equitable adjustment to the Contract.
Collier County Sports Complex
Prolog Manager
Project # 7648
Packet Pg. 1852
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 14
16.E.6.d
Manhattan
Building excellence.
Authorization Request: 7648.03-119
Approved By:
Margaret Bishop — Project Manager, Facilities Mari agemetSIGNATORE
Collier County Sports Complex
Prolog Manager
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
DATE
Project # 7648
Packet Pg. 1853
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 15
16.E.6.d
Manhattan
Authorization Request
Bitildi 2g'e cellence, Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd. N Tel: 239.643.6000 Project # 7648
Naples, FL 34117 Fax:
To: Margaret Bishop From: Josh Willard
Collier County Manhattan Construction (FL), Inc.
3295 Tamiaml Trail East 3705-1 Westview DR
Naples, FL 34112-4901 Naples, FL 34104
CE-Stadium Berm Enhancements
Pricing
CE No Date Reference Amount Proposed Days Req Category Reason
113.046 61812020 $14,664,63 Owner
Description
PhaselB Berm Changes
Notes
Cost Event Breakdown:
001 Add to include berm turf. $13,545.60
(SYNTHETIC TURF - SCG)
Additional turf to the original design of the turf on the berms at the Stadium.
Level 1 1.5% SDI $203.18
Level 2 0.736% Performance & Payment Bond $102,38
Level 3 1.175% General Liability $161.55
Level 4 4% CM Fee $641.82
Ct~ Na Date Reference Amount Proposed Days Req Catsgary Reason
.....
11B.049 1 $8,628.11 0 :::Owner Change
Descriition
Phasel B Added Bern Seat Wall
Notes
Cost Event Breakdown:
002 Add to include the additional concrete wall ontop of the berm. $8,030.00
CONCRETE - Naples Concrete
Added Berm Seat Wall from the design team.
Level 1 1.5% SDI $120.46
Level 2 0.736% Performance & Payment Bond $60.69
Love l 3 1.175% General Liability $95.77
Collier County Sports Complex Project # 7648
Prolog Manager
Packet Pg. 1854
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 16
16.E.6.d
Level 4 4%CM Fee
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
$321.20
CE'Nn ;Date Reference Amount Ptaposed, 'gays Fteq Categaty Reason
r i.• F Owner Change
Description
Phasel B Added Berm Fencing
Notes
Cost Event Breakdown;
002 Add to Include the added fence ontop of the berms at the Stadium. $6,008,00
FENCE PERMANENT - [SMITH FENCE]
Suppy and Install 100 2' high black vinyl coayed chain link fence on top of
seat walls at berms
Level 1 1.5% SDI $103.62
Level 2 0.736% Performance & Payment Bond $52.21
Level 3 1.175% General Liability $82,39
Level 4 4% CM Fee $276.32
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule timelcost Impact. We reserve the right to submit for cost/time impacts related to this change
under separate cover when that information is available.
Contractor does not release Impacts that arise out of Acts of Nature (including fire, flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war Is declared or not), civil war, rebellion, revolution, Insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract.
Authorization Request: 7648.03-076
Approved By:
Margaret Blahop-- Project Manager, Faallittes ManagemenslGNATURE DATE
Collier County Sports Complex Project # 7648
Prolog Manager
Packet Pg. 1855
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 17
16.E.6.d
Manhattan
Building excellence�
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd. N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
CE. Nn t]ate Reference Amount Proposed Days Req Category Reasnn
r: 020 e r a
Descrintlon
PhaselB Landscape Lighting Changes
Notes
Cost Event Breakdown:
001 Added costs to change the landscape lighting tops from the specified $12,975.60
rounded tops to the flat glass stop. Work includes replacing 64 tights and
miscellaneous asphalt cutting.
ELECTRICAL - IB&I]
Prevent tripping hazards in the walking path.
Level 1 1.50A SDI $194.63
Level 2 0.705% Performance & Payment Bond $98.07
Level 3 1.175% General Liability $154.75
Level 4 4% CM Fee $519.02
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule timelcost impact. We reserve the right to submit for costltime impacts related to this change
under separate cover when that information is available.
Contractor does not release impacts that arise out of Acts of Nature (including fire, flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities {whether war is declared or not), civil war, rebellion, revolution, insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract,
Authorization Request: 7648.03-116
Approved By:
Margaret Bishop —Project Manager, Facltittes Man agemerBrGNATURE DATE
Collier Coun iy Sports Complex
Prolog Manager
Project # 7648
Packet Pg. 1856
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 18
16.E.li.d
Manhattan
Building excellence.
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown}
Collier County Sports Complex
3851 - 3856 City Gate Blvd. N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
To: Margaret Bishop
Collier County
From: Josh Willard
Manhattan Construction (FL), Inc.
3295 Tamiami Trail East 3705-1 Westview DR
Naples, FL 34112-4901 Naples, FL 34104
CE1 B.044-Hardware Overrun
0113/2020 $41,743.72 0 : Owner Change
Description
PhaselB Hardware Overrun
Notes
Cost Event Breakdown:
001 Added costs to effectively secure the Stadium, Food Truck and Fitness $38,850.00
Pavilion to the wishes of the Operator. The Collier County Security
Specifications changed during the construction of the project to a new
provider that required additional design and hardware changes. This
Hardware package will include electrified strikes with panic devices and be
coded to the Access Control Badges for entry as identified In the
Specification approved in RFI 170 by the Design Team.
(Hardware - Fields Door & Hardware)
Cost is over and above the original budgeted allowance In the GMP because
there was originally a less advanced provider with no Lonel Access Control
System.
002 1.5% SDI $582.75
003 1.175% General Liability $463,33
004 0.736% Performance & Payment Bond $203.64
005 4.0% CM Fee $1,554,00
Pri cl ng
$41,743.72
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule timelcost impact. We reserve the right to submit for cost/time impacts related to this change
under separate cover when that information is available.
Contractor does not release impacts that arise out of Acts of Nature (including fire, flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war is declared or not), civil war, rebellion, revolution, Insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract.
Collier County Sports Complex Project # 7648
Prolog Manager
Packet Pg. 1857
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 19
16.E.6.d
Manhattan
Building excellence.
Authorization Request: 7648.03-077
Approved By:
Margaret Bishop — Project Manager, Facilities ManagemerBlGNATUR,E
Collier County Sports Complex
Prolog Manager
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
DATE
Project # 7648
Packet Pg. 1858
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 20
1ti.E.ti.d
Manhattan
Building excellence.
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd, N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
• • • I I R.
To: Margaret Bishop From: Josh Willard
Collier County Manhattan Construction (FL), Inc.
3285 Tamiami Trail East 3705-1 Westview DR
Description
Phasel B Area "A" Synthetic Turf
Notes
Cost Event Breakdown:
"�Y�
icl t7t riot�t bSa}ptiniTloilat Q7Qr�$ aK�Fl� �-
,,-=... :w-;,. ...a�.....,w�,.�:.,�-�: �.:��„� i...��✓�,..., '�v;.:�. ' ter,. `�.' .,� , .�,;.s�
002 A••-• costs to lay turf at the Teqball
n to
replace
�rubber mulch $1 D,626,00
at the rock climbing wall with turf.
FIELDS SPORTS
Level 1 1.6% SDI $294.37
Level 2 0.736% Performance & Payment Bond $148,33
Level 3 1.175% General Liability $234.05
Level 4 4.0% CM Fee $785.00
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule timelcost Impact. We reserve the right to submit for costltime Impacts related to this change
under separate cover when that information is available.
Contractor does not release impacts that arise out of Acts of Nature (including tire, flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war Is declared or not), civil war, rebellion, revolution, insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or Interruption or failure of power
sources. To the extent these conditions may occur and impact the Project, there shall be an equitable adjustment to the Contract.
Authorizatlon Request: 7648.03-120
Approved By:
Margaret Bishop —Project Manager, Facilities ManagemerSIGNATURE
Collier County Sports Complex
Prolog Manager
Dare
Project # 7648
N
M
M
CO)
N
LL
IZ
3
Y
tv
m
L
m
E
L
0
m
c
tv
t
U
m
a)
0
r
c
m
E
t
ns
.r
a
Packet Pg. 1859
DocuSign Envelope ID: F199002D-OF93-402C-9A2A-6FC3F81 F0745 21
16.E.6.d
Manhattan
Building excellence.
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
Collier County Sports Complex
3851 - 3856 City Gate Blvd. N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
To: Margaret Bishop From: Josh Willard
Collier County Manhattan Construction (FL), Inc.
3295 Tamiam€ Trait East 3705-1 Westview DR
Naples, FL 34112-4901 Naples, FL 34104
Phase 1 B - Added Palm Trees at FT&FP Roundabout
1 B.087 6/28/2020
Description
Phase IB Added Palms at FT&FP Roundabout
Notes
Cost Event Breakdown:
Pricing
0
$4, 029.31
31 0 Owner Change Change Condition `
OOt Added Costs for 3 Palm trees to be put In the center of the roundabout at the $3,750.00
Food Trcuk and Fitness Pavilion per Collier County Direction.
LANDSCAPE AND IRRIGATION - O'DONNELL
Level 1 1.5% SDI $56.25
Level 2 0.705% Performance & Payment Bond $28.34
Level 3 1.175%a General Liability $44.72
Level 4 4%CM Fee $150.00
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule time/cost Impact. We reserve the right to submit for costltime impacts related to this change
under separate cover when that information is available.
Contractor does not release impacts that arise out of Acts of Nature (including fire, flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war Is declared or not), civil war, rebellion, revolution, insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or Interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract.
Authorization Request: 7648.03-122
Approved By:
Margaret Bishop - Project Manager, Faclllttes Managemei&1GNATURE
DATE
Collier County Sports Complex Project # 7648
Prolog Manager
Packet Pg. 1860
DocuSign Envelope ID: F1 99002D-OF93-402C-9A2A-6FC3F81 F0745 22
16.E.6.d
Manhattan
Bid1cling excellence.
Collier County Sports Complex
Authorization Request
Detailed Form, Grouped by Number (with CE Breakdown)
3851 - 3856 City Gate Blvd. N Tel: 239-643-6000 Project # 7648
Naples, FL 34117 Fax:
• • .• i g
To: Margaret Bishop From: Josh Willard
Collier County
3295 Tamiami Trail East
Naples, FL 34112-4901
Manhattan Construction (FL), Inc,
3705-1 Westvlew DR
Naples. FL 34104
„✓ r s,.,->i,.- � , .e-'�M . �� ._.., -?�A, �,"'.�.: ,.,.sue.. �. �'��..w
Phase I B - Slit Fence North of •L. Pricing .
t
C No bate Reference Amounk Proposed ? Days Req Category Reason
Omer Change
Descrjltion
PhaselB Silt Fence North of Stadium
Notes
Cost Event Breakdown:
003 1.175% General Liability $18.13
004 0.736% Performance & Payment Bond $11.49
005 4.0% CM Fee $60.80
In order to mitigate possible delays and expedite the approval for the direct cost of work related to this change, unless specifically noted above, we
are submitting this change request without schedule time/cost impact We reserve the right to submit for costitime Impacts related to this change
under separate cover when that Information is available.
Contractor does not release impacts that arise out of Acts of Nature (including fire, Flood, earthquake, storm, hurricane or other natural disaster),
war, invasion, act of public enemies, hostilities (whether war is declared or not), civil war, rebellion, revolution, insurrection, military or usurped
power or confiscation, terrorist activities, riot, nationalization, government actions, tariffs, blockage, embargo, transportation delays not reasonably
foreseeable, labor dispute, strike, lockout, disease outbreak, epidemics, pandemics, quarantine restrictions, or interruption or failure of power
sources. To the extent these conditions may occur and Impact the Project, there shall be an equitable adjustment to the Contract.
Authorization Request: 7648.03-124
Approved By;
Margaret Bishop Project Manager, Facilities Managernei£1GNATUR.E DATE
Collier County Spoils Complex
Prolog Manager
a
Project 4 7648
Packet Pg. 1861