Agenda 07/14/2020 Item #16C 5 (Change Order No. 1 to Agreement #19-7615 for Big Corkscrew Island Regional Park)07/14/2020 EXECUTIVE SUMMARY Recommendation to approve a zero-dollar Change Order No. 1 to Agreement No. 19-7615, Big Corkscrew Island Regional Park, adding 123 days to the South Contract portion of the Park Project. OBJECTIVE: To approve a zero-dollar Change Order No. 1 to Agreement No. 19-7615, Big Corkscrew Island Regional Park (the “Park”), adding 123 days to the South Contract portion of the Park Project. CONSIDERATIONS: On October 8, 2019, the Board approved Agreement No. 19-7615 (the “Agreement”) to construct Big Corkscrew Island Regional Park, which will include such amenities as an aquatic center, community center, athletic fields, concession buildings, an event lawn, playground, basketball courts, tennis and pickleball courts, and walking paths. Thereafter, on November 10, 2019, the Facilities Management Division issued a Notice to Proceed (“NTP”) to Astra Construction Services, LLC to begin work under the Agreement. The Agreement provides for an overall project completion period of 608 days with Substantial Completion being reached in 563 days and Final Completion achieved within forty-five days thereafter. The reference to a 608 overall project duration is also referenced in the “Bid Scope of Work Outline,” which is an exhibit attached to the Agreement. The work under the Agreement consists of two (2) separate construction periods that relate to the north portion of the Park’s construction (the “North Contract”) and the south portion of the Park’s construction (the “South Contract”). Those separate construction projects encompassed under the Agreement have a separate and distinct total number of days to complete the respective work on those portions of the Park. The NTP commencement date for the North Contract construction is November 12, 2019, with a substantial completion date of November 27, 2020 (381 calendar days), and a final completion date of January 11, 2021, a total of 426 calendar days. The NTP commencement date for the South Contract construction is November 12, 2019, with a substantial completion date of January 25, 2021 (440 calendar days), and a final completion date of March 11, 2021, a total of 485 calendar days. Both of those NTP’s are consistent with the time periods found in Section 5, the Contract Time and Liquidated Damages provision set forth on page two of the Agreement. This Change Order arises as a result of the need to extend the number of days to complete the South Contract construction, which was necessitated by the need to begin work earlier in the southern portion of the Park to promote and support the work that was ongoing in the North Contract construction portion. The attached Change Order revises the NTP to expressly reflect that the South Contract shall have a Substantial Completion of 563 days from the issuance of the NTP (May 28, 2021) and a Final Completion date forty-five (45) days thereafter concluding 608 days from NTP (July 12, 2021). FISCAL IMPACT: No Fiscal impact. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval. -SRT GROWTH MANAGEMENT PLAN IMPACT: There is no impact to the Growth Management Plan related to this action. RECOMMENDATION: To approve zero-dollar Change Order No. 1, adding 123 days to the NTP for 16.C.5 Packet Pg. 1642 07/14/2020 the South Contract portion of the Park Project under Agreement No. 19-7615, Big Corkscrew Island Regional Park, and authorize the Chairman to sign the attached Change Order. Prepared By: James K. Morton, PE, Senior Project Manager, Public Utilities Department ATTACHMENT(S) 1. 111419 Astra to Jim Morton (PDF) 2. 80039 - Notice To Proceed (NTP) Astra BCIRP 11-12-2019 (PDF) 3. 4500201457_ASTRA Const CO#1A (PDF) 16.C.5 Packet Pg. 1643 07/14/2020 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.5 Doc ID: 12697 Item Summary: Recommendation to approve a zero-dollar Change Order No. 1 to Agreement No. 19-7615, Big Corkscrew Island Regional Park, adding 123 days to the South Contract portion of the Park Project. Meeting Date: 07/14/2020 Prepared by: Title: – Facilities Management Name: James Morton 06/19/2020 10:09 AM Submitted by: Title: Director - Facilities Management – Facilities Management Name: Damon Grant 06/19/2020 10:09 AM Approved By: Review: Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 06/19/2020 12:38 PM Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 06/19/2020 2:10 PM Board of County Commissioners Jim Flanagan Additional Reviewer Completed 06/19/2020 4:24 PM Procurement Services Sara Schneeberger Additional Reviewer Completed 06/22/2020 11:08 AM Procurement Services Sandra Herrera Additional Reviewer Completed 06/22/2020 4:19 PM Parks & Recreation Barry Williams Additional Reviewer Completed 06/22/2020 4:28 PM Public Utilities Department Dan Rodriguez Additional Reviewer Completed 06/23/2020 11:55 AM Procurement Services Catherine Bigelow Additional Reviewer Completed 06/23/2020 1:25 PM Facilities Management Damon Grant Director - Facilities Completed 06/23/2020 4:07 PM Public Services Department Todd Henry Level 1 Division Reviewer Completed 06/24/2020 11:21 AM Public Services Department Steve Carnell Level 2 Division Administrator Review Completed 06/29/2020 10:59 AM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 06/30/2020 3:34 PM Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 06/30/2020 4:48 PM Budget and Management Office Ed Finn Additional Reviewer Completed 06/30/2020 4:58 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 07/01/2020 8:48 AM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 07/05/2020 7:47 PM 16.C.5 Packet Pg. 1644 07/14/2020 Board of County Commissioners MaryJo Brock Meeting Pending 07/14/2020 9:00 AM 16.C.5 Packet Pg. 1645 16.C.5.a Packet Pg. 1646 Attachment: 111419 Astra to Jim Morton (12697 : Recommendation to approve a zero dollar CO for BCIRP) 16.C.5.a Packet Pg. 1647 Attachment: 111419 Astra to Jim Morton (12697 : Recommendation to approve a zero dollar CO for BCIRP) DATE: 11/10/2019 Andrew Lindsay, President Astra Construction Services LLC 300 Churchill Court Woodstock, GA 30188 RE: NOTICE-TO-PROCEED FOR: Big Corkscrew Island Regional Park Contract No. 19-7615 Purchase Order No. 4500200288 Dated 11/06/2019 Collier County Project No. 80039 Dear Mr. Lindsay: This letter serves as Collier County's official NOTICE TO PROCEED (NTP) to your Company to Commence with the above referenced project on Tuesday, November 12, 2019. This NTP is issued pursuant to Contract #19-7615. The purchase order number is shown above, and a copy of the P.O. is enclosed. This NTP is limited to the scope of work for the Big Corkscrew Island Regional Park with a lump sum price of Forty-Five Million, Sixty-Five Thousand, Four Hundred Fifty-Four Dollars ($45,065,454.00). To facilitate the payment process, please include the following information on each invoice: The beginning and ending billing dates; the purchase order/work order n umber written above, as well as the Collier County project number. Also, please describe clearly which items in the agreed invoice line items are being billed to, and do not invoice more than is remaining in a particular line item. Lastly, please mark the final invoice as “FINAL”. The Commencement date for the services associated herewith shall be considered to be Tuesday, November 12, 2019. No work is authorized after the final completion date herein unless the time of the contract/work order is extended on or before the final completion date. Invoices for unauthorized work will not be paid. Page 1 of 2 16.C.5.b Packet Pg. 1648 Attachment: 80039 - Notice To Proceed (NTP) Astra BCIRP 11-12-2019 (12697 : Recommendation to approve a zero dollar CO for BCIRP) Page 2 of 2 NOTICE-TO-PROCEED – Continued Big Corkscrew Island Regional Park Contract No. 19-7615 Purchase Order No. 4500200288 Collier County Project No. 80039 The project is divided into two Contract completion schedules. The Commencement date for the North Contract construction shall be considered to be the NTP date of 11/12/2019. The substantial completion date shall be considered to be 11/27/2020 (381 calenda r days) from and after the North Contract Commencement date with an additional 45 calendar days to final completion. Final completion of all work for the North Contract shall be considered to be 1/11/2021, a total of Four Hundred Twenty-six calendar days. The Commencement date for the South Contract construction shall be considered to be the NTP date of 11/12/2019. The substantial completion date shall be considered to be 1/25/2021 (440 calendar days) from and after the South Contract Commencement date with an additional 45 calendar days to final completion. Final completion of all work for the South Contract shall be considered to be 3/11/2021, a total of Four Hundred Eighty- five calendar days. If you have any questions, please contact me. Sincerely, James K. Morton, P.E. Senior Project Manager Facilities Management Division CC: David Pabor, Sr. Project Manager, Astra Group Nestor Fernandez, Sr. Construction Manager, Wood Jennifer Ziglar, Procurement Sonia Powell, Procurement 16.C.5.b Packet Pg. 1649 Attachment: 80039 - Notice To Proceed (NTP) Astra BCIRP 11-12-2019 (12697 : Recommendation to approve a zero dollar CO for BCIRP) 16.C.5.c Packet Pg. 1650 Attachment: 4500201457_ASTRA Const CO#1A (12697 : Recommendation to approve a zero dollar CO for BCIRP) Al-bahouAyoub Digitally signed by Al-bahouAyoub Date: 2020.06.18 10:36:12 -04'00' WilliamsBarry Digitally signed by WilliamsBarry Date: 2020.06.18 14:15:53 -04'00' This item has been electronically signed and sealed by Michael J. Delate, P.E. on the date adjacent to the seal using a SHA authentication code. Printed copies of this document are not considered signed and sealed and the SHA authentication code must be verified on any electronic copies. Digitally signed by Michael J. Delate, P.E. Date: 2020.06.18 09:52:59 -04'00' SchneebergerSara Digitally signed by SchneebergerSara Date: 2020.06.18 15:58:22 -04'00' 16.C.5.c Packet Pg. 1651 Attachment: 4500201457_ASTRA Const CO#1A (12697 : Recommendation to approve a zero dollar CO for BCIRP) 16.C.5.c Packet Pg. 1652 Attachment: 4500201457_ASTRA Const CO#1A (12697 : Recommendation to approve a zero dollar CO for BCIRP)