Agenda 06/09/2020 Item #16C3 (Change Order #14 to #16-6638 w/Mitchell & Stark Const.)06/09/2020
EXECUTIVE SUMMARY
Recommendation to approve Change Order No. 14 for Agreement No. 16-6638 with Mitchell &
Stark Construction Co., Inc., to balance contract quantities in the Vanderbilt Drive Cul-de-sacs
Public Utility Renewal Project (Projects 70122 and 60122), authorize the necessary budget
amendment and authorize the Chairman to sign the attached Change Order.
OBJECTIVE: To provide reliable, sustainable, and regulatory compliant services to the customers along
Vanderbilt Drive and the 14 adjacent Conners Subdivision neighborhood cul-de-sacs by replacing and
refurbishing the water, wastewater and stormwater infrastructure in coordination with the Wastewater
Basin 101 Program and the Vanderbilt Beach aerial to underground utility conversion.
CONSIDERATIONS: On July 12, 2016 (as Agenda Item 11D), the Board approved Agreement No. 16-
6638 to Mitchell & Stark Construction Co., Inc., for the Vanderbilt Drive Cul-de-sacs Project, which
included the replacement of water, wastewater and stormwater infrastructure. (See Attachment 1 - project
map.)
The project reached final completion on March 23, 2020. Change Order No 14 includes a reconciliation
of pay items from the schedule of values for water, wastewater and stormwater. The allowances do not
have the necessary funds to cover all of the exceeded quantities, therefore, the difference will be covered
by the remaining quantity balances in bid line items.
An additional $160,000 is required to fully cover the costs of the additional stormwater quantities under
Change Order No. 14 and an upcoming final change order to process the final stormwater work directives.
FISCAL IMPACT: A budget amendment is required to transfer funds, in the amount of $ 160,000,
within the Stormwater Capital Fund (325) from Project 60139 to Project 60122.
GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan
standards to ensure the adequacy and availability of viable public facilities.
LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote
for Board approval. -SRT
RECOMMENDATION: To approve attached Change Order No. 14 for Contract 16-6638 with Mitchell
& Stark Construction Co., Inc., to balance quantities in the Vanderbilt Drive Cul-de-sacs Public Utility
Renewal Project (Projects 70122 and 60122), authorize the necessary budget amendment and authorize
the Chairman to sign the attached Change Order.
Prepared by: Diana C. Dueri, PMP, Public Utilities Department, Senior Project Manager
ATTACHMENT(S)
1. Change Order 14 (PDF)
2. Attachment 1 Project Map (PDF)
16.C.3
Packet Pg. 961
06/09/2020
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.3
Doc ID: 12474
Item Summary: Recommendation to approve Change Order No. 14 for Agreement No. 16-6638
with Mitchell & Stark Construction Co., Inc., to balance contract quantities in the Vanderbilt Drive Cul-
de-sacs Public Utility Renewal Project (Projects 70122 and 60122), authorize the necessary budget
amendment and authorize the Chairman to sign the attached Change Order.
Meeting Date: 06/09/2020
Prepared by:
Title: Project Manager – Public Utilities Planning and Project Management
Name: Diana Dueri
05/21/2020 12:39 PM
Submitted by:
Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management
Name: Tom Chmelik
05/21/2020 12:39 PM
Approved By:
Review:
Public Utilities Planning and Project Management Benjamin Bullert Additional Reviewer Completed 05/21/2020 12:54 PM
Growth Management Department Lisa Taylor Additional Reviewer Completed 05/22/2020 9:59 AM
Growth Management Operations Support Christopher Johnson Additional Reviewer Completed 05/22/2020 1:50 PM
Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 05/27/2020 9:43 AM
Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 05/27/2020 2:03 PM
Procurement Services Sara Schneeberger Additional Reviewer Completed 05/27/2020 2:35 PM
Capital Project Planning, Impact Fees, and Program Management Amy Patterson Additional Reviewer Completed 05/27/2020 5:26 PM
Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 05/28/2020 12:09 PM
Capital Project Planning, Impact Fees, and Program Management Liz Gosselin Additional Reviewer Completed 05/28/2020 3:37 PM
Procurement Services Sandra Herrera Additional Reviewer Completed 05/29/2020 10:52 PM
Procurement Services Catherine Bigelow Additional Reviewer Completed 06/01/2020 8:38 AM
Public Utilities Operations Support Tara Castillo Additional Reviewer Completed 06/01/2020 9:29 AM
Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 06/01/2020 11:02 AM
Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 06/01/2020 11:18 AM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 06/02/2020 9:22 AM
Office of Management and Budget Debra Windsor Level 3 OMB Gatekeeper Review Completed 06/02/2020 9:26 AM
16.C.3
Packet Pg. 962
06/09/2020
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 06/02/2020 11:17 AM
Budget and Management Office Ed Finn Additional Reviewer Completed 06/02/2020 11:28 AM
Office of Management and Budget Susan Usher Additional Reviewer Completed 06/02/2020 12:21 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 06/02/2020 4:13 PM
Board of County Commissioners MaryJo Brock Meeting Pending 06/09/2020 9:00 AM
16.C.3
Packet Pg. 963
X
16.C.3.a
Packet Pg. 964 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
SchneebergerSara Digitally signed by SchneebergerSara
Date: 2020.05.21 09:45:49 -04'00'
16.C.3.a
Packet Pg. 965 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
16.C.3.a
Packet Pg. 966 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
Additional Quantities Item with Remaining $ Additional Quantities Item with Remaining $ Additional Quantities Item with Remaining $ Additional Quantities Item with Remaining $
1.8a -Concrete
Driveways 1.8c - Asphalt Driveways 3.5 - 12” HDPE Force
Main
3.28c - Concrete Manholes 10-
14 feet 1.8a - Concrete Driveways 4.12 - Yard Drains
4.17 - Existing Culvert
Removal
SW Allowance – Additonal
Funds Needed
2.2b - 6” Gate Valve 3.14c - 10” PVC Gravity
Sewer 14+Wastewater Allowance 4.1 - Existing Culvert Removal 4.12 - Yard Drains
4.18 - Existing Storm Structure
Removal
SW Allowance – Additonal
Funds Needed
2.4 - Short Double
Service 3.21 - 4” Plug Valve
Wastewater Allowance and
3.28c - Concrete Manholes 10-
14 feet
4.7 - 24” RCP 4.12 - Yard Drains 4.19 - 12” Perf A2000 W/Sock
SW Allowance – Additonal
Funds Needed
2.5 - Connect Existing
WM
3.28b - Concrete
Manholes 6-10 feet 4.8 - 24” Perf A2000 W/Sock
4.3 - 19” x 30” ERCP, 4.6 - 18”
Perforated A2000 W/Sock, 4.10
- Type “D” Inlet
4.24 - Type “C” Inlet SW Allowance – Additonal
Funds Needed
3.28d - Concrete
Manholes 14+ feet
4.9 - Concrete Mitered End
Sections 4.13 - Embankment Allowance 4.26 - Yard Drains
4.20 - 12" RCP, 4.21 - 12"
PVC, 4.22 - 15" RCP, 4.23 -
Concrete Mitered End
Sections, 4.25 - Inline ADS
Drains, 4.27 - Trench Drain,
and SW Allowance.
3.31 - Connect Existing
GS to New MH 4.28 - Swale Grading SW Allowance
3.28c - Concrete Manholes 10-
14 feet
For example, the funds
remaining in Asphalt
Driveways will be used to
pay for Concrete Driveways,
Gate Valve, Short Double
Serice and Connect Existing
WM.
C.O. #14 Attachment 1 - Summary of Money from Remaining Line Items to be Used
to Pay for Exceeded Quantities
Water Wastewater Stormwater (Vanderbilt Drive) Stormwater (Finger Streets)
16.C.3.a
Packet Pg. 967 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
ITEM
NO.DESCRIPTION ORIGINAL BID
QUANITY UNIT UNIT PRICE
ORIGINAL
CONTRACT
AMOUNT
REVISED BID
QUANTITY REVISED AMOUNT DEVIATION
FROM BID QTY
BALANCE OF
QUANTITIES REASON FOR QUANTITY INCREASE / DECREASE
1.8 Remove and Replace Driveway
a. Concrete 8334.44** SY $39.00 $325,043.16 8621.93 $336,255.27 287.49 $8,072.72
Note: Water pays 72% and Stormwater pays 28% of the general
restoration items associated to driveway restoration activities.
Additional concrete driveway area quantities are needed to account for
driveway restoration beyond the right-of-way limits due to slope
correction issues and sanitary sewer cleanout locations on private
property. This line item will be paid with remaining amount from Item
1.8c - Remove and Replace Asphalt Driveway.
2.2 Install Gate Valve and Boxes
b. 6‐inch Gate Valve 42 EA $1,270.00 $53,340.00 46 $58,420.00 4 $5,080.00
Modifications to the project Scope of Work included additional water
main installation along 103rd Avenue North and Heron Avenue, which
increased the quantity of gate valves to be installed. This line item will be
paid with remaining amount from Item 3.28 - Furnish and Install
Precast Concrete Manholes (10-14 feet).
2.4 Install Water Services
b. Short Double Service 61** EA $1,130.00 $68,930.00 62 $70,060.00 1 $1,130.00
**The original Bid quantity was 60 EA but with Change Order #9 it was
increased to 61 EA. Modifications to the project Scope of Work included
additional water main installation along 103rd Avenue North and Heron
Avenue, which increased the quantity of water services to be installed.
This line item will be paid with remaining amount from Item 3.28 -
Furnish and Install Precast Concrete Manholes (10-14 feet).
2.5 Connect to Existing Water Main 37** EA $4,290.00 $158,730.00 38 $163,020.00 1 $4,290.00
**The original Bid quantity was 33 EA but with Change Order #9 it was
increased to 37 EA.Modifications to the project Scope of Work included
additional water main installation along 103rd Avenue North and Heron
Avenue, which increased the quantity of connections to existing water
mains. This line item will be paid with remaining amount from Item
3.28 - Furnish and Install Precast Concrete Manholes (10-14 feet).
Total $18,572.72
Remaining Allowance after CO #13 $0.00
1.8 Remove and Replace Driveway
c. Asphalt 888 SY $49.50 $43,956.00 227.8 $11,276.10 -660.2 ($23,529.53)
Note: Water pays 72% and Stormwater pays 28% of the general
restoration items associated to driveway restoration activities. All
asphalt driveways were measured for payment and not all quantities were
needed to complete this restoration. The money remaining from this line
item will be used to pay the additional quantities exceeded from Items
1.8 - Remove and Replace Concrete Driveways ($8,072.72), 2.2b -
Install 6" Gate Valve ($5,080.00), 2.4b - Short Double Service
($1,130), and 2.5 - Connect to Existing Water Main ($11,060).
Remaining amount in Line Item 1.8 ‐ Asphalt Driveways after
CO #14 $4,956.81
Water Allowance Remining after CO #14 $0.00
3.5 Install 12" DR11 HDPE Force Main, Fittings and Appurtenances 770 LF $68.19 $52,506.30 797 $54,347.43 27 $1,841.13
Contractor installed new 12" DR11 HDPE Force Main as shown in the
contract documents, which is more than the original quantity included in
the Schedule of values. This line item will be paid with remaining
amount from Item 3.28 - Furnish and Install Precast Concrete
Manholes (10-14 feet).
3.14 Install 10" PVC Gravity Sewer
c. (14+ Feet) 90 LF $126.00 $11,339.91 181 $22,805.82 91 $11,465.91
Additional 10-inch PVC gravity sewer was needed for the new gravity
sewer installed along 103rd Avenue North for new Pump Station 101.07.
This line item will be paid with remaining amount from the
Wastewatere Allowance.
3.21 Install 4" Plug Valve 1 EA $1,400.00 $1,400.00 8 $11,200.00 7 $9,800.00
Only one (1) plug valve was included in the Schedule of Values but the
plans showed that eight (8) 4-inch plug valves\ needed to be installed.
This was also confirmed with the EOR. This line item will be paid
with remaining amount from the Wastewater Allowance and the
difference between the remaining Allowance amount and the amount
to be invoiced ($717.82) will be paid with remaining amount from
Item 3.28 - Furnish and Install Precast Concrete Manholes (10-14
feet).
3.28 Furnish and Install Precast Concrete Manholes
b. (6‐10 Feet) 25 EA $7,700.00 $192,500.00 32 $246,400.00 7 $53,900.00
Contractor installed new Precast Concrete Manholes (0-6 feet deep) as
shown in the contract documents, which is more than the original quantity
included in the Schedule of values. This line item will be paid with
remaining amount from Item 3.28 - Furnish and Install Precast
Concrete Manholes (10-14 feet).
d. (14+ Feet) 10 EA $11,060.00 $110,600.00 11 $121,660.00 1 $11,060.00
Contractor installed new Precast Concrete Manholes (14+ feet deep) as
shown in the contract documents, which is more than the original quantity
included in the Schedule of values. This line item will be paid with
remaining amount from Item 3.28 - Furnish and Install Precast
Concrete Manholes (10-14 feet).
3.31 Connect Existing Gravity Sewer to New Precast Concrete Manhole 20 EA $3,300.00 $66,000.00 22 $72,600.00 2 $6,600.00
Two additional connections of existing gravity sewer to new precast
concrete manholes had to be performed when the project scope was
modified to leave in place the existing gravity sewer between manholes
VD-4 and VD-3. This issue was related to discovering that the existing
drainage was two (2) 3’X7’ box culverts instead of two parallel 36" RCP,
as originally contemplated. Due to the depth, and inability to properly
support the culverts while crossing under them by means of open cut, it
was determined that the existing sewer would be left in place. Refer to
RFI #41 for additional information. This line item will be paid with
remaining amount from Item 3.28 - Furnish and Install Precast
Concrete Manholes (10-14 feet).
Total $94,667.04
Wastewater Allowance Remining after CO #13 $20,548.09
3.28 Furnish and Install Precast Concrete Manholes
c. (10‐14 Feet) 43 EA $9,440.00 $405,920.00 35 $330,400.00 -8 ($75,520.00)
All concrete manholes were measured for payment and not all quantities
were needed to complete this work. The money remaining from this line
item will be used to pay the additional quantities exceeded from the
Wastewater System. The money remaining from this line item will be
used to pay the additional quantities exceeded from Items 3.5 - Install
12" DR11 HDPE Force Main ($1,841.13), 3.21 - Install 4" Plug Valve
($717.82), 3.28b - Install Precast Concrete Manholes 6-10 feet
($53,900), 3.28d - Install Precast Concrete Manholes 14+ feet
($11,060) and 3.31 - Connect Existing Gravity Sewer to new Precast
Concrete Manhole ($6,600).
Remaining amount in Line Item 3.28c ‐ Concrete Manholes (10‐
14 feet)$1,401.05
Wastewater Allowance Remining after CO #14 $0.00
C.O. #14 Attachment 2 - Balance of Quantities
Section 2: Water System
Section 3: Wastewater System
16.C.3.a
Packet Pg. 968 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
1.8 Remove and Replace Driveway
a. Concrete 8334.44** SY 39.00 $325,043.16 8621.93 $336,255.27 287.49 $3,139.39
Note: Water pays 72% and Stormwater pays 28% of the general
restoration items associated to driveway restoration activities.
Additional concrete driveway area quantities are needed to account for
driveway restoration beyond the right-of-way limits due to slope
correction issues and sanitary sewer cleanout locations on private
property. This line item will be paid with remaining amount from Item
4.12 - Yard Drains.
4.1 Existing Storm Culvert Removal ‐ Vanderbilt Drive 4282** LF $7.00 $29,974.00 4,728 $33,096.00 446 $3,122.00
**The original Bid quantity was 1,282 LF but with Change Order #4 it
was increased to 4,282 LF. Many existing stormwater culverts that were
supposed to remain have been found to be completely deteriorated and
needed to be removed and replaced for the stormwater system to work as
intended. Due to this the original bid quantities have been exceeded. This
line item will be paid with remaining amount from Item 4.12 - Yard
Drains.
4.7 24" RCP 837 LF $65.56 $54,873.72 863 $56,578.28 26 $1,704.56
Additional stormwater pipe was installed to replace existing stormwater
culverts that were discovered to be extremely deteriorated. This line item
will be paid with remaining amount from Item 4.12 - Yard Drains.
4.8 24" Perforated A2000 W/Sock 5,370 LF $51.71 $277,682.70 5719 $295,729.49 349 $18,046.79
Additional stormwater pipe was installed to replace existing stormwater
culverts that were discovered to be extremely deteriorated. This line item
will be paid with remaining amounts from Items 4.3 - 19"x30"ERCP,
Item 4.6 - 18" Perforated A2000 W/Sock, and Item 4.10 - Type "D"
Inlet.
4.9 Concrete Mitered End Sections 22 EA $1,380.00 $30,360.00 26 $35,880.00 4 $5,520.00
Additional MESs were installed to replace existing stormwater culverts
that were discovered to be extremely deteriorated and for the additional
stormwater system for residences along 103rd Avenue North. This line
item will be paid with remaining amount from Item 4.13 -
Embankment Allowance.
Total $31,532.74
Stormwater Allowance Remaining after CO #13 $0.00
4.3 19"x30" ERCP 90 LF $91.16 $8,204.40 32 $2,917.12 -58 ($5,287.28)
All 10"x30" ERCP was measured for payment and not all quantities were
needed to complete this work. The money remaining from this line item
will be used to pay the additional quantities exceeded from Item 4.8 -
24" Perforated A2000 W/Sock ($18,046.79).
4.6 18" Perforated A2000 W/Sock 247** LF $48.70 $12,028.90 200 $9,740.00 -47 ($2,288.90)
**The original Bid quantity was 279 LF but with Change Order #4 it was
decreased to 247 LF. All stormwater pipe installation was measured for
payment and not all quantities were needed to complete this work. The
money remaining from this line item will be used to pay the additional
quantities exceeded from Item 4.8 - 24" Perforated A2000 W/Sock
($18,046.79).
4.10 Type "D" Inlet 39 EA $3,690.00 $143,910.00 36 $132,840.00 -3 ($11,070.00)
All storm structures were measured for payment and not all quantities
were needed to complete this work. The money remaining from this line
item will be used to pay the additional quantities exceeded from Item
4.8 - 24" Perforated A2000 W/Sock ($18,046.79).
4.12 Yard Drains 44** EA $2,020.00 $88,880.00 40 $80,800.00 -4 ($8,080.00)
**The original Bid quantity was 45 EA but with Change Order #4 it was
decreased to 44 EA. All yard drains were measured for payment and not
all quantities were needed to complete this work. The money remaining
from this line item will be used to pay the additional quantities
exceeded from Items 1.8a - Concrete Driveways ($3,139.39), 4.1 -
Existing Storm Culvert Removal ($3,122), and 4.7 - 24" RCP
($1,704.56).
4.13 Embankment Allowance 400 CY $15.00 $6,000.00 0 $0.00 -400 ($6,000.00)
This work was not needed. The money remaining from this line item
will be used to pay the additional quantities exceeded from Item 4.9 -
Concrete Mitered End Sections ($5,520.00).
Remaining amount in Line Item 4.3 ‐ 19"x30" ERCP $0.00
Remaining amount in Line Item 4.6 ‐ 18" Perforated A2000
W/Sock $0.00
Remaining amount in Line Item 4.10 ‐ Type "D" Inlet $599.39
Remaining amount in Line Item 4.12 ‐ Yard Drains $114.05
Remaining amount in Line Item 4.13 ‐ Embankment Allowance $480.00
Stormwater Allowance Remaining after CO #14 $0.00
4.17 Existing Storm Culvert Removal ‐ Finger Streets 3,711 LF $7.00 $25,977.00 7,216 $50,512.00 3505 $24,535.00
Many existing stormwater culverts that were supposed to remain have
been found to be completely deteriorated and needed to be removed and
replaced for the stormwater system to work as intended. Due to this the
original bid quantities have been exceeded. This line item will be paid
with Stormwater Allowance. Additional funds needed.
4.18 Existing Storm Structure Removal 46 EA $600.00 $27,600.00 60 $36,000.00 14 $8,400.00
Additional storm structures that were originally supposed to remain as
part of this project have been replaced due to their existing deteriorated
conditions. This line item will be paid with Stormwater Allowance.
Additional funds needed.
4.19 12" Perforated HDPE W/Sock 20062** LF $23.49 $471,256.38 20834 $489,390.66 772 $18,134.28
**The original Bid quantity was 19,362 LF but with Change Order #9 it
was increased to 20,062 LF. Additional stormwater pipe was installed to
replace existing stormwater culverts that were discovered to be extremely
deteriorated. This line item will be paid with Stormwater Allowance.
Additional funds needed.
4.24 Type "C" Inlet 33 EA $2,450.00 $80,850.00 39 $95,550.00 6 $14,700.00
After the County performed a stormwater system pre-construction
walkthrough the stormwater design was updated to be consistent with the
current field conditions. With the revision to the design many existing
stormwater culverts and structures that were supposed to remain were
replaced, which increased the amount of new Type "C" catch basins to be
installed throughout Phases 6 and 7 of the project. This line item will be
paid with Stormwater Allowance. Additional funds needed.
4.26 Yard Drains 219 EA $1,130.00 $247,470.00 245 $276,850.00 26 $29,380.00
The Scope of Work was modified to include additional yard drains due to:
additional stormwater drainage installed to replace deteriorated CMP
culverts, addition of new yard drains in areas that were not draining
properly, and replacement of existing and proposed catch basins with new
yard drains. This line item will be paid with remaining amounts from
Items 4.20 - 12" RCP, Item 4.21 - 12" PVC, Item 4.22 - 15" RCP,
4.23 - Concrete Mitered End Sections, Item 4.25 - Inline ADS Drains,
and Item 4.27 - Trench Drain. The difference between the remaining
amounts and the total to be paid ($29,380.00 - $28,300.52 =
$1,079.48) will be covered by the Stormwater Allowance remaining.
4.28 Swale Grading 3,400 LF $4.00 $13,600.00 3487.5 $13,950.00 87.5 $350.00
Additional linear feet of swale grading was needed to correct stormwater
flow elevations on areas that were not originally contemplated and to
regrade swales that present safety concerns to residents (swales deemed a
trip hazard due to its depth). This line item will be paid with
Stormwater Allowance.
Total $95,499.28
Stormwater Allowance Remaining after CO #13 $2,926.31
4.20 12" RCP 428 LF $38.28 $16,383.84 425 $16,269.00 -3 ($114.84)
All stormwater pipe installation was measured for payment and not all
quantities were needed to complete this work. The money remaining
from this line item will be used to pay the additional quantities
exceeded from Item 4.26 - Yard Drains ($29,380.00).
4.21 12" PVC 10 LF $45.20 $452.00 0 $0.00 -10 ($452.00)
This work was not needed. The money remaining from this line item
will be used to pay the additional quantities exceeded from Item 4.26 -
Yard Drains ($29,380.00).
4.22 15" RCP 118 LF $43.28 $5,107.04 112 $4,847.36 -6 ($259.68)
All stormwater pipe installation was measured for payment and not all
quantities were needed to complete this work. The money remaining
from this line item will be used to pay the additional quantities
exceeded from Item 4.26 - Yard Drains ($29,380.00).
4.23 Concrete Mitered End Sections 134 EA $1,330.00 $178,220.00 116 $154,280.00 -18 ($23,940.00)
All concrete mitered end sections installation was measured for payment
and not all quantities were needed to complete this work. The money
remaining from this line item will be used to pay the additional
quantities exceeded from Item 4.26 - Yard Drains ($29,380.00).
Section 4: Stormwater System - Conners Subdivision Unforseen Conditions
Section 4: Stormwater System - Vanderbilt Drive Unforseen Conditions
16.C.3.a
Packet Pg. 969 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
4.25 Inline ADS Drains 4 EA $1,310.00 $5,240.00 3 $3,930.00 -1 ($1,310.00)
All inline ADS drains were measured for payment and not all quantities
were needed to complete this work. The money remaining from this line
item will be used to pay the additional quantities exceeded from Item
4.26 - Yard Drains ($29,380.00).
4.27 Trench Drain 16 LF $139.00 $2,224.00 0 $0.00 -16 ($2,224.00)
This work was not needed. The money remaining from this line item
will be used to pay the additional quantities exceeded from Item 4.26 -
Yard Drains ($29,380.00).
Remaining amount in Line Item 4.20 ‐ 12" RCP $0.00
Remaining amount in Line Item 4.21 ‐ 12" PVC $0.00
Remaining amount in Line Item 4.22 ‐ 15" RCP $0.00
Remaining amount in Line Item 4.23 ‐ Concrete Mitered End
Sections $0.00
Remaining amount in Line Item 4.25 ‐ Inline ADS Drains $0.00
Remaining amount in Line Item 4.27 ‐ Trench Drain $0.00
Total Stormwater Funds needed for CO 14 $64,272.45
Total CO#14 Draw $240,271.78 Total CO#14 draw of water, wastewater and stormwater allowances
Stormwater
Vanderbilt Drive
Landscape
Allowance
Stormwater
Vanderbilt Drive
Unforeseen
Conditions
Allowance
Stormwater Conners
Subdivision
Unforeseen
Conditions Allowance
1. Original Contract Allowances $250,000.00 $175,000.00 $975,693.30 $80,000.00 $50,000.00 $50,000.00 $1,580,693.30
2. Remaining Allowance after CO No. 13 $187,195.00 $0.00 $20,548.09 $30,000.00 $0.00 $2,926.31 $240,669.40
3. CO #14 Draw $0.00 $18,572.72 $94,667.04 $0.00 $31,532.74 $95,499.28 $240,271.78
4. Remaining Amount from Quantities Not Used $0.00 $18,572.72 $74,118.95 $0.00 $31,532.74 $28,300.52 $152,524.93
3. Funds Needed for CO No. 14 $0.00 $0.00 $0.00 $0.00 $0.00 $64,272.45 $64,272.45
4. Remaining Allowance after CO No. 14 $187,195.00 $0.00 $0.00 $30,000.00 $0.00 $0.00 $217,195.00
Total
General
Landscape
Allowance
Water
Unforeseen
Conditions
Allowance
Wastewater
Unforeseen
Conditions
Allowance
Stormwater Allowances
16.C.3.a
Packet Pg. 970 Attachment: Change Order 14 (12474 : Change Order No 14 Vanderbilt Cul-de-sacs project)
Vanderbilt Cul-de-sacs Map
16.C.3.b