PBSD Budget Committee Minutes 01/28/2020 BUDGET COMMITTEE
PELICAN BAY SERVICES DIVISION
JANUARY 28,2020
The Budget Committee of the Pelican Bay Services Division met on Tuesday, January 28 at
9:30 a.m. at the SunTrust Bank Building, located at 801 Laurel Oak Drive, Suite 302, Naples,
Florida 34108. In attendance were:
Budget Committee Nick Fabregas
Rick Swider, Chairman Michael Fogg
Joe Chicurel Scott Streckenbein (ex-officio)
Pelican Bay Services Division Staff Lisa Jacob, Project Manager
Neil Dorrill, Administrator Alex Mumm, Sr. Field Supervisor (absent)
Chad Coleman, Operations Manager Barbara Shea, Interim Ops. Analyst
Also Present Susan O'Brien, PBSD Board
Denise McLaughlin, PBSD Board
APPROVED AGENDA (AS AMENDED)
1. Pledge of Allegiance
2. Roll call
3. Agenda approval
4. Approval of 8/22/2019 meeting minutes
5. Summary of FY2021 pending projects and estimated costs
a. Review of Dec. 31 financial statements (add-on)
6. Preliminary budget for FY2021
7. Preliminary discussion of alternative taxation methods.
8. Old Business
9. New Business
10. Audience Comments
11. Adjourn
ROLL CALL
All members were present and a quorum was established
AGENDA APPROVAL
1
Budget Committee of the Pelican Bay Services Division
January 28, 2020 Minutes
Dr. Chicurel motioned, Mr. Fogg seconded to approve the agenda as amended.
The motion carried unanimously.
APPROVAL OF 08/22/2019 MEETING MINUTES
Dr. Chicurel motioned, Mr. Fabregas seconded to approve the 08/22/2019
meeting minutes as presented. The motion carried unanimously.
REVIEW OF DEC. 31 FINANCIAL STATEMENTS (ADD-ON)
Mr. Dorrill reviewed the Dec. 31, 2019 combined funds balance sheet;highlights included
identifying total cash and investments of$12.2 million, and total reserves of$3.5 million. He
noted that over 90% of our revenues have already been collected. Mr. Fogg noted that during our
FY 2020 budgeting process, we understated our forecasted carryforward into FY 2020 by $1.2
million. He also estimated that we currently have approximately $4.5 —5 million in cash that will
not be spent in the current fiscal year. Mr. Fogg requested additional clarification on several
figures on the income statements and balance sheet provided.
The committee discussed each of the six budgeted reserves included on the Dec. 31 balance
sheet. They agreed that targets need to be developed for each of these.
STREET LIGHTING FUND 778
Mr. Swider commented on $1.5 million in our street lighting fund 778. Mr. Dorrill
commented that we had an engineer evaluate our streetlight poles a few years ago, and it was
determined that our poles would likely last another 30 years. He noted that after receiving this
report, the PBSD Board elected not to proceed with a pole replacement project. Mr. Dorrill also
noted that the lighting engineer reviewed the level of illumination on PB streets and tree pruning
was completed in identified areas to improve street lighting. He noted that LED bulbs have now
been installed in all of our fixtures. Ms. Jacob commented that at the time of the study, it was
estimated that replacement of all of our poles would be $1.3 million. Mr. Fogg commented that
lighting on PB tertiary roads is inadequate.
Mr. Dorrill commented that fund 778 is eligible to borrow funds from for short-term cash
needs, if necessary. Mr. Fabregas suggested that we stop our ad valorem taxation for street-light
replacement if we have no active project plans. Mr. Steckenbein agreed, and suggested we look
into using fund 778 funds (or part of it) for beach renourishment funding needs. Dr. Chicurel
commented that he is not in favor of depleting fund 778 for other purposes.
LARGE PROJECT FINANCING PACKAGE
Mr.Dorrill commented that at the last County Finance Committee meeting that he attended,
it was understood that our financing would be a "commercial paper alternative" with a ten-year
term. Sizing and solicitation of the financing was planned to be completed in early summer. He
is hopeful that the loan will close in the 4th quarter of this fiscal year so that the sidewalk
replacement project can be underway before next season begins. Mr. Fogg suggested that a line
of credit would be preferable, so that we could draw down funds as needed.
Ms. McLaughlin commented that the Water Management Committee has not discussed
which and how many lakes might be included in our financing package. She noted that our
2
Budget Committee of the Pelican Bay Services Division
January 28, 2020 Minutes
engineer,Mr. Jim Can, is updating the estimated cost for lake bank remediation for the top 6 lakes
on our prioritized listing of lakes with critically eroded lake banks.
SUMMARY OF FY 2021 PENDING PROJECTS AND ESTIMATED COSTS
FY 2021 CAPITAL PROJECTS PLANNING ESTIMATES
Mr. Swider reviewed the "FY 2021 Capital Projects Planning Estimates" document
provided by staff and included in the agenda packet. He suggested that some of the new projects
listed would not be funded completely in FY 2021,but instead may be included in our large project
financing package.
SIDEWALK REPLACEMENT PROJECT
Mr. Dorrill commented that he expects the BCC to approve the award of a contract for the
design engineering for our sidewalk replacement project on Feb. 11. Mr. Fabregas suggested that
in the future, we confirm with our construction contractor, that our project can be completed in
three years. Dr. Chicurel suggested that it may be possible to complete sidewalk replacement
construction on tertiary streets in season.
BEACH RENOURISHMENT
Mr. Fogg commented that we have $878,000 in reserves for beach renourishment. Mr.
Streckenbein commented that Dr. Trecker has estimated that we need $2.5 —3.0 million to fund a
PB beach renourishment resiliency project (as is being planned by the County). Ms. McLaughlin
expressed concern that the timing of this resiliency project is unknown. However,we will need to
be financially prepared as our project should be completed at the same time that the County
completes their Vanderbilt Beach resiliency project.
PBSD STAFFING
Mr. Dorrill reported that our PBSD posting for an Operations Analyst was re-advertised,
and the posting closed on Friday. Interviews will be conducted this week. He commented that the
job functions of this position include day-to-day budget coordination, payroll, payables, purchase
orders, budget amendments, and related accounting tasks.
Mr. Dorrill reported that staffs current thinking is that we will ask for our FY 2020
budgeted Environmental Specialist position to be re-advertised as an Associate Project Manager.
Ms. O'Brien commented that the board was told that job descriptions for the Environmental
Specialist and the Associate Project Manager would be routed to the Budget Committee for
discussion,to be followed by a recommendation to the board. Mr. Dorrill commented that he was
not aware of this. After committee discussion, it was agreed that the two job descriptions should
be included in the February 12 board agenda packet for discussion by the board.
FUTURE FOLLOW-UP BY MR. DORRILL AND STAFF
Mr. Dorrill will prepare a sizing and a cash flow analysis for the next 24— 36 months for
our three major projects (sidewalk replacement, operations facility replacement, lake bank
remediation and potentially others such as drainage pipe projects), which will be provided to the
committee at the next committee meeting. He will work with our ABB engineer to produce a
schedule to include the sizing and phasing of these projects.
3
Budget Committee of the Pelican Bay Services Division
January 28, 2020 Minutes
Mr. Dorrill will provide an update to the PBSD Board on total funds received so far from
FEMA and insurance proceeds for reimbursement of Hurricane Irma expenses. He will also
provide an estimate of the total reimbursement expected.
Mr. Dorrill will obtain a legal opinion,from the County Attorney's Office,on whether fund
778 funds could be used for other purposes. He assumes this would be possible if we amended
our PBSD ordinance.
Mr. Dorrill will request a follow-up meeting of the County's Finance Committee to discuss
how our financing will be structured.
Mr. Dorrill will contact the County's Office of Management and Budget (OMB) Dept. to
(1)try to determine what their thoughts are on the County's FY 2021 budget policy, (2)determine
when the County's first installment of$500,000 for sidewalk replacement will be received by the
PBSD, and (3) identify the $500,000 in "reserve for sinking fund" in Fund 322. The committee
suggested that"reserve for future construction"might be a better description for this reserve.
PRELIMINARY BUDGET FOR FY2021
Not discussed.
PRELIMINARY DISCUSSION OF ALTERNATIVE TAXATION METHODS
Mr. Swider commented that this agenda item would be discussed at a future meeting.
TENTATIVE DATE FOR NEXT COMMITTEE MEETING
The committee agreed to tentatively schedule the next Budget Committee for 9:00 on
Tuesday, Feb. 25.
ADJOURNMENT
The meeting was adjourned at 11:06 a.m. 1
Rick Swider, Chairman
Minutes approved [ V J as presented OR F j as amended ON [ .2/075/020,20 ] date