#16-6561 Amendment #5 (Atkins North America, Inc.) FIFTH AMENDMENT TO AGREEMENT#16-6561
FOR
"DESIGN SERVICES FOR MARCO EXECUTIVE AIRPORT TERMINAL"
THIS FIFTH AMENDMENT, made and entered into on this day of
2020, by and between Atkins North America, Inc., authorized to do
business in thre State of Florida, whose business address is 4030 West Boy Scout Boulevard,
Suite 700, Tampa, FL 33607 (the "Consultant"), and Collier County, a political subdivision
of the State of Florida (the "County")(collectively, the "Parties").
WHEREAS, on September 27, 2016 (Agenda Item 14.A.1), the County entered
into an Agreement with Consultant to obtain professional design services concerning the
"Design Services for Marco Executive Airport Terminal," which included the New Terminal
Facility and Associated Landside Improvements — Part 1 and the Apron Expansion and
Airfield Safety Improvements — Part 2, with a contract award in the amount of $1,209,298;
and
WHEREAS, on March 13, 2018 (Agenda Item 16.G.2), the Board approved
Amendment 1 to the Agreement to obtain engineering and inspection services during
construction concerning the"Design Services for Marco Executive Airport Terminal" (for New
Terminal Facility and Associated Landside Improvements — Part 1) in the amount of
$919,673.50; and
WHEREAS, on May 14, 2019 (Agenda Item 16.G.2), the Board approved
Amendment 2 to the Agreement to incorporate, Post Design and Inspection Services, as
originally contemplated in Request for Proposal #16-6561, for the Apron Expansion and
Airfield Safety Improvements — Part 2; and
WHEREAS, on July 9, 2019 (Agenda Item 16.G.2), the Board approved
Amendment 3 to the Agreement to extend the schedule one hundred eighty (180) days to
coincide with construction and increase the fee associated with the extended schedule by
$211,976 for the "Design Services for Marco Executive Airport Terminal" (for New Terminal
Facility and Associated Landside Improvements — Part 1); and
WHEREAS, on November 12, 2019 (Agenda Item 16.G.1), the Board approved
Amendment 4 to the Agreement to add Post Design and Inspection Services for Bid
Alternates 1 and 2 for the Apron Expansion and Airfield Safety Improvements— Part 1; and
WHEREAS, the Parties desire to further amend the Agreement to extend the
schedule an additional one hundred eighty (180) days to coincide with the extended
construction schedule and increase the fee associated with the extended schedule by
$147,162 for the "Design Services for Marco Executive Airport Terminal" (for New Terminal
Facility and Associated Landside Improvements — Part 1).
NOW, THEREFORE, in consideration of the mutual promises and covenants
herein contained, it is agreed by the Parties as follows:
Page 1 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
1. The additional services shall be provided in accordance with the attached
Schedule A1-5- Scope of Services, which is hereby incorporated into the Agreement.
2. The fees for the additional services outlined in Schedule A1-5 - Fee Schedule
shall be in accordance with Schedule B1-5, attached hereto and incorporated into the
Agreement.
3. Schedule C1-5 Project Milestone Schedule is attached hereto and incorporated
into the Agreement.
4. Schedule F1-5 Key Personnel, Subconsultants and Subcontractors is attached
hereto and incorporated into the Agreement.
All other terms and conditions of the agreement shall remain in force.
IN WITNESS WHEREOF, the Parties hereto, have each, respectively, by an authorized
person or agent, have executed this Amendment on the date and year first written above.
Crystal K. Kinzel, Clerk of Courts and BOARD OF COUNTY COMMISSIONERS
Comptroller OF COLLIER COUNTY, FLORIDA
A.,%.,....".„,,,..
BY: Li Q L :: Ana By:
tesf�Xas#1o chairman's , , .ep erk Burt L. Saunders ., Chairman
�
signature only, , `,,,,
Consultant's First ' ess: CONSULTANT:
L-7475. � Atkins No h America c.
ElYW—C-'.-1- 22-Q-
Y
s6CTS-' ,C`, (.. ,,,,,,,,s-Qe)(24ay,_1,
Print Name Darin R. Larson, Vice President —
Consultant's Second Witness: Print Name and Title
By: /'�/ � .d
The. ---
Print Name
proved s to "• nd legality:
Sco R. ach "--
Deputy County Attorney
Page 2 of 12
Fifth Amendment to Agreement#16-6561 i'/
"Design Services for the Marco Island Executive Airport(MKY)New Terminal" 9
e
Amendment 5 to Contract#16-6561
"Design and Related Services for the Marco Island Executive Airport (MKY)"
New Terminal Facility and Associated Landside Improvements
SCHEDULE A1-5
SCOPE OF SERVICES
This scope of services covers an additional six (6) months of construction phase services
required for the New Terminal Facility and Associated Landside Improvements.
Project Description
Under task authorization Amendment 1 to Contract #16-6561, Atkins (CONSULTANT)
drafted a scope of services to define the effort necessary to accomplish the Construction
Phase Services for the New Terminal Facility and Associated Improvements at MKY. This
task consisted of providing professional services for the administration and technical support
during construction, and the preparation of closeout documents and record drawings. In
addition, Atkins provided resident project representative (RPR) services for the majority of
the construction contract duration.
The contract documents allowed 320 calendar days from notice to proceed to substantial
completion of construction plus an additional 45 calendar days for project closeout. At the
end of April 2019, the 365 calendar days included in the contract with West Construction
expired. Under task authorization Amendment 2 to Contract #16-6561, the CONSULTANT
drafted a scope of services to define the additional effort necessary to continue the
Construction Phase Services for the New Terminal Facility and Associated Improvements at
MKY through February 5, 2020. As of November 1, 2019, the project is approximately sixty
(60) percent complete.
At the request of the COUNTY, the CONSULTANT has drafted this scope of services to
define the additional effort necessary to continue the Construction Phase Services for the
New Terminal Facility and Associated Improvements at MKY for an additional six(6) months.
This will consist of providing additional professional services for the administration and
technical support during construction. In addition, Atkins will provide resident project
representative (RPR) services for the majority of the additional six(6) months of construction.
Scope
For the purposes of scope definition and CONSULTANT fee development, the work has
been divided into the following tasks. Any modifications and/or revisions to these tasks will
constitute a change in the project scope and may require a revision to the compensation to
be paid to the CONSULTANT. These tasks will begin once the COUNTY provides the
CONSULTANT with a written Notice to Proceed.
Task 1: Project Administration and Coordination
This task involves the additional internal management of the contract including project
bookkeeping, billing, and coordination with project stakeholders as required due to the time
extension. The Project Manager (PM) will be readily available to the project team and the
COUNTY to oversee necessary project related elements. The PM will keep the COUNTY
Page 3 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
C�n
advised of the work progress, schedule, and anticipated review dates and coordinate
necessary revisions. The PM will be the CONSULTANT's main point of contact and will be
responsible for ensuring that the project's goals and objectives are met within the agreed
upon schedule.
Task 2: Weekly Construction Meetings and Site Visits
Under this task, the CONSULTANT's Project Manager and/or appropriate technical leads
will make additional visits to the site during construction as required due to the time
extension. Such visits are not intended to be exhaustive in examining the Contractor's work
in progress, but rather to provide a general observation of the work based on the Engineer's
professional judgment. The CONSULTANT will review the Contractor's work as observed
for general conformance with the Contract Documents. The CONSULTANT will not visit the
site to direct or supervise the Contractor's work.
Note that site visits may be coordinated to happen concurrently with regular project
meetings, or they may be held at other times. Therefore, the design professional will not
necessarily be represented at each of the weekly project meetings.
For the purpose of scope definition, the following number of additional visits are anticipated
by a technical lead from each discipline as required due to the time extension:
• Project Manager— 26
• Civil/Site Engineer—6
• Architect—40
• Utility/Stormwater Engineer - 3
Task 3: Permit Required Revisions and Conformed Documents
No additional effort associated with this amendment is required under for this Task.
Task 4: Shop Drawing Review
This task will include the CONSULTANT's additional reviews of shop drawings submitted by
the Contractor as stipulated in the Contract Documents. Amendment 1 included a maximum
of three (3) reviews on each shop drawing or technical submittal times. Additional reviews
beyond three (3) have been required on multiple submittals related to the terminal building
and shall be eligible for additional compensation based on the scope of Amendment 1.
Task 5: Responses to Contractor Requests for Information (RFI's)
Under this task, the CONSULTANT will prepare additional technical responses to the
questions submitted by the Contractor in the format of a Request for Information (RFI) as
required due to the time extension.
Task 6: Contractor Applications for Payment and Project Delays
Based on the CONSULTANT's on-site observations as an experienced and qualified design
professional, on information provided by the RPR, and on review of applications for payment
and accompanying data and schedules, the CONSULTANT and/or RPR shall approve the
amounts owed to the Contractor(s) based on the Contractor's additional monthly pay
requests as required due to the time extension.
Page 4 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
(.dtr
The CONSULTANT shall also review Contractor claims for Contract time extensions
submitted by the Contractor and shall recommend or deny acceptance to the Owner. Such
claims shall be submitted within fourteen (14) days of the date(s) of the requested delay for
consideration by the CONSULTANT or the claim will be considered null and void and will not
be reviewed.
Task 7: Resident Project Representative (RPR) Services
Under this task, the CONSULTANT will continue to provide on-site Resident Project
Representative (RPR) services for the Project as required due to the time extension. The
RPR shall serve as the liaison between the COUNTY, the CONTRACTOR, and the
CONSULTANT team throughout the project. The foremost duty of the RPR is to observe
construction for general conformance with the Contract Documents. The RPR will be
responsible for reporting to the Project Manager, Engineer, Architect, Airport, and/or
COUNTY when observing work that is unsatisfactory, faulty, defective, or does not conform
to the Contract Documents. The RPR will be responsible for rejecting such work as agreed
upon with the COUNTY and the CONSULTANT. The duties of the RPR will include:
• collect and log shop drawings, RFI's, RFC's, pay requests, correspondence, etc.
• inspect and monitor Contractor activities
• maintain a daily construction log
• attend weekly progress meetings
• review and approve Contractor's pay requests
• take project progress photographs
• monitor Contractor's Quality Control Plan
• administrate Change Orders as necessary
• organize, prepare for, and lead the substantial completion and final inspections
• create the Contractor's punch list of unfinished items
• verify the Contractor's completion of the punch list
• collect the Contractor's as-built information
• prepare the final closeout documentation
• certify the completion of the project to general conformance with the Contract
Documents
The Resident Project Representative shall have limited authority on site as follows:
• Shall not authorize any deviation from the construction Contract Documents or
substitution of materials or equipment.
• Shall not exceed limitations of Owner or design professional as set forth in the
construction Contract Documents.
• Shall not undertake any of the responsibilities of the Contractors, subcontractors,
or Contractor's superintendents.
• Shall not advise on, issue directions relative to or assume control over any aspect
of the means, methods, techniques, sequences or procedures of construction
unless such advice or directions are specifically required by the construction
Contract Documents.
• Shall not advise on, issue directions regarding or assume control over safety
precautions and programs in connection with the Contractor's work.
Page 5 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
• Shall not accept shop drawings or sample submittals from anyone other than the
Contractor.
• Shall not authorize the Owner to occupy the Project in whole or in part.
• Shall not participate in specialized field or laboratory tests or inspections
conducted by others except as specifically authorized.
The contract documents allow 320 calendar days from notice to proceed to substantial
completion of construction plus an additional 45 calendar days for project closeout. The
additional RPR efforts required beyond the 365 calendar days for the six (6) month extension
equates to 26 weeks of contract time. To best serve the project, it is assumed that there will
be two (2) RPR's required: one for vertical construction and the other for site work. It is
assumed that there will be one (1) part-time (2.5 days per week) site RPR on site through
the duration of the contract. An additional inspector may be required on-site during peak
construction activities including, but not limited to, extended paving operations and night
work. Typically, only one site RPR will be on-site at a time. It is assumed that there will be
one (1) part-time (1.5 days per week) vertical RPR on site through the duration of the
contract. Actual time on site may vary from week to week based on the Contractor's work
schedule.
Task 8: FDOT/COUNTY Coordination and Grant Management
The CONSULTANT will assist the COUNTY on coordination with the various agencies on
project funding grant terms, conditions, and assurances and other related coordination items
as required due to the time extension.
Task 9: Preparation of Closeout and Record Documents
No additional effort associated with this amendment is required under for this Task.
BASIC ASSUMPTIONS
The following is a list of assumptions forming the basis of the CONSULTANT's cost proposal
for providing the services detailed in the Scope of Services for this project. Any modification
and/or revision to these basic assumptions will constitute a change in the project scope and
may result in a revision to the CONSULTANT's cost proposal.
1. The scope and assumptions as generally defined within Amendment 1 to Contract
#16-6561 shall remain in effect unless specifically modified herein.
2. This scope of services does not include preparation for or testimony during any
mediation or litigation which might arise from disputes between the Owner and
Contractor. Such preparation for or testimony during litigation or mediation, should
it be necessary, shall be considered outside the scope of this contract.
Page 6 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY) New Terminal"
SCHEDULE B1-5 BASIS OF COMPENSATION
Construction Phase Services for
New Terminal Facility and Associated Landside Improvements
1. MONTHLY STATUS REPORTS
B.1.1. As a condition precedent to payment, CONSULTANT shall submit to the COUNTY as
part of its monthly invoice a progress report reflecting the Project status, in terms of the total
work effort estimated to be required for the completion of the Basic Services and any authorized
Additional Services, as of the last day of the subject monthly billing cycle. Among other things,
the report shall show all Service items and the percentage complete of each item.
2. COMPENSATION TO CONSULTANT
B.2.1. For the Basic Services provided for in this Agreement, the COUNTY agrees to make the
payments to CONSULTANT in accordance with the terms stated below. Payments will be
made in accordance with the following Schedule; however, the payment of any particular line
item noted below shall not be due until services associated with any such line item have been
completed or partially completed to the COUNTY's reasonable satisfaction. Lump sum
payments will be made upon the percentage complete.
Tasks Description Lump Sum
1 Project Administration and Coordination $22,440.00
2 Weekly Construction Meetings and Site Visits $44,060.00
3 Permitting Required Revisions & Conformed Documents -
4 Shop Drawing Review $2,520.00
5 Responses to Contractor RFI's $12,320.00
6 Contractor Applications for Payment and Project Delays $7,020.00
7 RPR Services $50,120.00
8 FAA/DOT/County Coordination and Grant Management $6,340.00
9 Preparation of Closeout and Record Docs -
10 QA Testing -
11 Reimbursable Costs 2,342.00
GRAND TOTAL FEE $147,162
B.2.2 Lump Sum Fees: The fees noted in Section 2.1. shall constitute the lump sum amount to
be paid to CONSULTANT for the performance of the Basic Services.
B.2.2.1 CONSULTANT shall submit, with each of the monthly status reports provided
for under Section B.1.1 of this Schedule B, an invoice for fees earned in the performance of
Basic Services and Additional Services during the subject billing month.
Page 7 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
S
B.2.3. For Additional Services provided pursuant to Article 2 of the Agreement, if any, the
COUNTY agrees to pay CONSULTANT a negotiated total fee and Reimbursable Expenses
based on the services to be provided and as set forth in the Amendment authorizing such
Additional Services. The negotiated fee shall be based upon the rates specified in Attachment
1 to this Schedule B and all Reimbursable Expenses shall comply with the provision of Section
3.4.1 below. There shall be no overtime pay on Additional Services without the COUNTY's prior
written approval.
B.2.4. The compensation provided for under Section B.2.1 of this Schedule B, shall be
the total and complete amount payable to CONSULTANT for the Basic Services to be
performed under the provisions of this Agreement, and shall include the cost of all materials,
equipment, supplies and out-of-pocket expenses incurred in the performance of all such
services.
B.2.5. Notwithstanding anything in the Agreement to the contrary, CONSULTANT
acknowledges and agrees that in the event of a dispute concerning payments for Services
performed under this Agreement, CONSULTANT shall continue to perform the Services
required of it under this Agreement, as directed by the COUNTY, pending resolution of the
dispute provided that the COUNTY continues to pay to CONSULTANT all amounts that the
COUNTY does not dispute are due and payable.
3. SCHEDULE OF PAYMENTS
B.3.1. Notwithstanding anything herein to the contrary, the CONSULTANT shall submit
no more than one invoice per month for all fees earned that month for both Basic Services and
Additional Services. Invoices shall be reasonably substantiated, identify the services rendered
and must be submitted in triplicate in a form and manner required by the COUNTY.
B.3.1.1 Payments will be made for services furnished, delivered, and accepted, upon
receipt and approval of invoices submitted on the date of services or within six (6) months after
completion of contract. Any untimely submission of invoices beyond the specified deadline
period is subject to non-payment under the legal doctrine of "laches" as untimely submitted.
Time shall be deemed of the essence with respect to the timely submission of invoices under
this Agreement.
B.3.2. Invoices not properly prepared (mathematical errors, billing not reflecting actual
work done, no signature, etc.) shall be returned to CONSULTANT for correction. Invoices shall
be submitted on CONSULTANT's letterhead and must include the Purchase Order Number
and Project name and shall not be submitted more than one time monthly.
B.3.3. Payments for Additional Services of CONSULTANT as defined in Article 2
hereinabove and for reimbursable expenses will be made monthly upon presentation of a
detailed invoice with supporting documentation.
B.3.4. Unless specific rates have been established in Attachment 1, attached to this
Schedule B, CONSULTANT agrees that, with respect to any subconsultant or subcontractor to
be utilized by CONSULTANT for this Agreement or Additional Services, CONSULTANT shall
be limited to a maximum markup of five percent (5%) on the fees and expenses associated
with such subconsultants and subcontractors.
Page 8 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
CAO
B.3.4.1 Reimbursable Expenses must comply with §112.061, Fla. Stat., or as
set forth in the Agreement, be charged without mark-up by the CONSULTANT, and shall
consist only of the following items:
B.3.4.1.1. Cost for reproducing documents that exceed the number of documents
described in this Agreement and postage and handling of Drawings and Specifications.
B.3.4.1.2. Travel expenses reasonably and necessarily incurred with respect to
Project related trips, to the extent such trips are approved by the COUNTY. Such expenses, if
approved by the COUNTY, may include coach airfare, standard accommodations and meals,
all in accordance with §112.061, Fla. Stat. Further, such expenses, if approved by the
COUNTY, may include mileage for trips that are from/to destinations outside of Collier or Lee
Counties. Such trips within Collier and Lee Counties are expressly excluded.
B.3.4.1.3. Permit Fees required by the Project.
B.3.4.1.4. Expense of overtime work requiring higher than regular rates approved
in advance and in writing by the COUNTY.
B.3.4.1.5. Expense of models for the County's use.
B.3.4.1.6. Other items on request and approved in writing by the COUNTY.
B.3.4.1.7. The CONSULTANT shall bear and pay all overhead and other
expenses, except for authorized reimbursable expenses, incurred by CONSULTANT in the
performance of the Services.
B.3.4.1.8. Records of Reimbursable Expenses shall be kept on a generally
recognized accounting basis.
B.3.5. The CONSULTANT shall obtain the prior written approval of the COUNTY before
incurring any reimbursable expenses, and absent such prior approval, no expenses incurred
by CONSULTANT will be deemed to be a reimbursable expense.
Page 9 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal" ,.
SCHEDULE B1-5 —ATTACHMENT 1
CONSULTANT'S HOURLY RATE SCHEDULE
Title Hourly Rate
Principal $225
Senior Project Manager $185
Project Manager $165
Senior Engineer $135
Engineer $100
Senior Inspector $110
Inspector $90
Senior Planner $145
Planner $105
Senior Designer $115
Designer $80
Environmental Specialist $115
Senior Environmental Specialist $135
Scientist/Geologist $95
Senior Scientist/Geologist $115
Senior GIS Specialist $135
GIS Specialist $105
Clerical/Administrative $80
Senior Technician $105
Technician $80
Surveyor and Mapper $135
CADD Technician $80
Survey Crew - 2 man $155
Survey Crew - 3 man $172
Survey Crew-4 man $208
Senior Architect $160
Architect $110
Grant Funded: The above hourly rates are for purposes of providing estimate(s), as required
by the grantor agency. The above list may not be all inclusive. Additional hourly rates for other
personnel may be added via an Amendment upon mutual agreement in advance and in writing
by the Parties.
Page 10 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
ICAO
SCHEDULE C1-5
PROJECT MILESTONE SCHEDULE
New Terminal Facility and Associated Landside Improvements— Part 1
Cumulative Number
of Calendar Days
For Completion
Task
Descriptionfrom Date of
Notice to Proceed for
Services under this
Agreement
1 Project Administration and Coordination 180
2 Weekly Construction meetings and Site 180
Visits
3 Permitting Required Revisions and 180
Conformed Documents
4 Shop Drawing Review 180
5 Responses to Contractor RFI's 180
6 Contractor Applications for Payment and 180
Project Delays
7 RPR Services 180
8 FAA/DOT/County Coordination and Grant 180
Management
9 Preparation of Closeout and Record Docs 180
10 QA Testing 180
Page 11 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"
SCHEDULE F1-5
KEY PERSONNEL
New Terminal Facility and Associated Landside Improvements— Part 1
Name Personnel Category Percentage
of Time
Darin Larson Principal 10%
Kevin McCauley Senior Project Manager 40%
Thomas Roda Senior Engineer IV 10%
Fleet Wulf Senior Engineer III 15%
Ivan Urdaneta Senior Engineer II 20%
William Bowdoin Senior Engineer I 20%
Adanna Ryce Engineer II 30%
Ahmed Aslheer CADD Technician 20%
TBD Senior Inspector 60%
TBD Inspector 5%
Scotty Bakowski Clerical/Administrative 10%
Gary Krueger Senior Architect 30%
Somer Spencer Architect 20%
Page 12 of 12
Fifth Amendment to Agreement#16-6561
"Design Services for the Marco Island Executive Airport(MKY)New Terminal"