Backup Documents 12/10/2019 Item #16A 4 - Presentation VBRVanderbilt Beach Road Extension Project
Recommendation to approve
Change Order #3 –Contract 06-
4000 for Vanderbilt Beach Road
Extension from Collier
Boulevard to 16th Street NE.
(Project No. 60168).
BCC Meeting October 22, 2019 –Item 16.A.4
1
Jay Ahmad, P.E., Director Transportation Engineering
•June 26, 2018:Public Information Meeting
•Sept. 25, 2018:BCC approves shifting VBRX northward and relocating Cypress
Canal to the south.
•Oct. 22, 2019 BCC approves Alternative Alignment plus adding Massey Street
from VBRX to Tree Farm Road
2
Vanderbilt Beach Road Extension Project:
3
Revise 11,500 feet (2.2 mi) of VBRX
Add 11,500 feet (2.2 mi) canal relocation
4
Frontage Road -Additional 2750 feet (0.5 mi)
5
Massey Street -4750 feet (0.9 mi)
60% PLANS: 05/2020
90% PLANS: 09/2020
100% PLANS: 12/2020
TARGET BID START: 05/2021
TARGET CONSTRUCTION START:12/2021
TARGET CONSTRUCTION COMPLETION:05/2024
PROJECT SCHEDULE
6
Recommendation to approve Change Order No. 3 to Agreement No. 06-4000
between Collier County and Jacobs Engineering Group, Inc. (formerly CH2M Hill)
in the amount of $885,345.00, for the design of the revised alignment of
Vanderbilt Beach Road Extension from Collier Boulevard to 16th Street NE, and
the design of Massey Street from Vanderbilt Beach Road to Tree Farm Road.
(Project No. 60168).
ITEM 16.A.4 -RECOMMENDATION:
7