Agenda 12/10/2019 Item #11E (I-75/951 Utility Relocation Project)12/10/2019 EXECUTIVE SUMMARY Recommendation to award Agreement No. 19-7540 in the total amount of $14,962,500 to Quality Enterprises USA, Inc., for “Design Build Collier County I-75 and 951 Utility Relocation Project,” and authorize the Chairman to execute the attached contract. OBJECTIVE: To secure a design-build team to provide design and construction services for the I-75 and 951 Utility Relocation Project to meet demand, stay in compliance, and serve customers efficiently by providing a compliant and reliable potable water system to Collier County Water-Sewer District (“CCWSD”) customers. CONSIDERATIONS: The Florida Department of Transportation (“FDOT”) informed the Collier County Water-Sewer District of its I-75 & 951 Interchange Improvements project that will be commencing as early as October 2020. The FDOT project will be a design-build project that includes constructing additional ramps at the I-75/951 interchange to allow traffic departing Interstate 75 (“I-75”) to proceed directly south on Collier Boulevard or traffic traveling north on Collier Boulevard to I-75 to bypass the Davis Boulevard/Collier Boulevard intersection. The FDOT project limits (as shown in Attachment 1) start just north of the northerly I-75 ramps and end at Business Circle South. Within the FDOT project limits, the CCWSD has extensive existing water and wastewater utility lines. The existing water mains include a 48-inch pipe, a 36-inch pipe and two 20-inch pipes. The existing wastewater force main is a 12-inch pipe. These large pipes underneath a major FDOT interchange represent a significant risk to both sets of assets. A worst-case scenario would be a 48-inch water main break causing a long-term shut down of I-75 and 951. In November 2017, two repairs were completed to the 48-inch Prestressed Concrete Cylinder Pipe (“PCCP”) water main: one at the Collier Boulevard/City Gate Drive intersection, and the other on the Collier Boulevard median (just south of the Interstate 75 overpass). PCCP pipe is a proprietary material that can only be installed and repaired by Thompson Pipe Group. Repairs are costly ($418,336 for the two repairs mentioned above) and subject to the availability of Thompson Pipe Group. The existing 48 - inch PCCP pipe is: (1) located in a high-risk area, (2) prone to failure, (3) expensive to repair, and is (4) 31 years old. For those reasons, this water main is being abandoned and replaced outside of the FDOT project area proactively before the start of the FDOT Interchange Improvement project. For sim ilar reasons, the other three water mains are also being abandoned and replaced outside of the FDOT project area (see Attachment 2 for the Project Map). The wastewater force main will be replaced by a new force main under a separate project; however, it will remain in place, inactive, for emergency uses only. The condition of these assets is defined as “Red: Level 3 - Risked Compliance,” as reported to the Board of County Commissioners (Board) at the October 1, 2013, Asset Assessment and Management Workshop. The proposed scope of work for Project 70229, “I-75 and 951 Utility Relocation Project” includes constructing a large transmission water main in the existing Florida Power and Light (“FPL”) easement from the South County Regional Water Treatment Plant (“SCRWTP”) to the south end of the Forest Glen Golf and Country Club. The FPL easement is located just east of 951. The new transmission water main will need to be installed and placed into service prior to the start of the FDOT Interchange Improvement project. The I-75 and 951 utility relocation project map is shown in Attachment 2. The project also includes the installation of a new water main on White Lake Boulevard that will connect to the large transmission water main in the FPL easement; the replacement of the SCRWTP reverse osmosis raw water line located within the FPL easement and within the Forest Glen Golf and Country Club; and a new 20-inch water main from Davis Boulevard to Business Circle South. After the 11.E Packet Pg. 1208 12/10/2019 completion of this project, a new 20-inch water main starting from Davis Boulevard and traveling south down 951 will remain in the 951 right-of-way to provide potable water to the existing developments along 951. After the completion of this new transmission water main, the existing 48-inch PCCP water main, existing 36-inch water main (Davis Boulevard to south side of Forest Glen subdivision), existing 20-inch water main (just north of I-75 to Davis Boulevard) and the existing 20-inch water main (Davis Boulevard to Business Circle South) will be abandoned. The abandonment/removal of the existing water main will be completed as part of the FDOT Interchange Improvement Design-Build project. The CCWSD will enter into a Utility Work by Highway Contractor Agreement and Memorandum of Understanding with FDOT to have its design-build contractor complete the water main abandonment/removal. On September 24, 2019 (Agenda Item 16C6), the Board accepted the selection committee’s ranking for Request for Proposal No. 19 -7540 and authorized staff to negotiate a contract with the top-ranked design-build team, Quality Enterprises USA, Inc. and its consultant, Q. Grady Minor and Associates, P.A. (“Q. Grady Minor”). The resulting contract, insurance information and project presentation are included as Attachments 4, 5 and 6 respectively. The Guaranteed Maximum Price (GMP) as bid was $14,962,500.00. On October 27, 2019 Staff began contract negotiations with Quality Enterprises and Q. Grady Minor. During negotiations, Staff identified a potential cost savings of $266,000.00 for sales tax savings for a direct material purchase (actual savings amount will be determined when the material is ordered) and a cost savings of $45,589.34 in material and labor for not installing a 36-inch valve (the valve was included in the bid but later determined that it could be omitted). The project scope will be updated to change 1,450 feet of Segment 1 pipe installation from open cut to directional drilling at a net additional cost of $558,250.00. After contract awar d, Staff will execute a change order to deduct the sales tax savings for the direct material purchase, to deduct the 36 - inch valve costs and to increase the contract to directional drill 1,450 feet of Segment 1, as shown in the table below: Description Cost Cost Basis Credit for Sales Tax savings on Direct Material Purchase -$266,000.00 Estimate Credit for 36-inch valve -$45,589.34 Negotiated 1,450 foot directional drill (in lieu of open cut) Segment 1 909,150.00 Negotiated Credit for 1,450 foot open cut Segment 1 -350,900.00 Negotiated Net Estimated Cost Increase $246,660.66 (2%) The design-build team originally requested an additional $593,050.00 for the Segment 1 directional drill, which Staff negotiated down to $558,250.00. Staff recommends that the Board approve attached Agreement No. 19-7540 in the amount of $14,962,500.00. An analysis of the negotiated costs listed above were reviewed by an independent third- party professional engineering consultant (See Attachment 3). FISCAL IMPACT: Funding is available in the Fiscal 2020 capital budget approved by the Board on September 19, 2019 to cover the GMP and the costs reflected in the table above. The source of funding is the Water User Fee Capital Fund (412). LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT 11.E Packet Pg. 1209 12/10/2019 GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: To award Agreement No. 19-7540, “Design Build I-75 and 951 Utility Relocation Project,” to Quality Enterprises, USA, Inc., in the amount of $14,962,500.00 for Project Number 70229, and authorize the Chairman to sign the attached agreement. Prepared By: Shon D. Fandrich, P.E., PMP, Senior Project Manager, Engineering and Project Management Division ATTACHMENT(S) 1. Attachment 1: I-75 & Collier Blvd Interchange Improvements (PDF) 2. Attachment 2: I-75 & Collier Blvd - Project Map (PDF) 3. Attachment 3: 11-06-19 - MSD-BNB QGM-QE Review Ltr (PDF) 4. [Linked] Attachment 4: 19-7540 QualityEnterprisesUSA_Contract_VendorSigned_With_Bonds (PDF) 5. Attachment 5: 19-7540 QualityEnterprise_Insurance_11-20-19 (PDF) 6. Attachment 6: Final DB Powerpoint (PDF) 11.E Packet Pg. 1210 12/10/2019 COLLIER COUNTY Board of County Commissioners Item Number: 11.E Doc ID: 10540 Item Summary: Recommendation to award Agreement No. 19-7540 in the total amount of $14,962,500 to the Quality Enterprises USA, Inc., for “Design Build Collier County I-75 and 951 Utility Relocation Project” and authorize the Chairman to execute the attached contract. (Tom Chmelik, Public Utilities Engineering and Project Management Director) Meeting Date: 12/10/2019 Prepared by: Title: – Public Utilities Planning and Project Management Name: Shon Fandrich 11/19/2019 1:50 PM Submitted by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 11/19/2019 1:50 PM Approved By: Review: Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 11/19/2019 1:52 PM Water Pamela Libby Additional Reviewer Completed 11/19/2019 1:56 PM Wastewater Beth Johnssen Additional Reviewer Completed 11/19/2019 2:10 PM Public Utilities Planning and Project Management Benjamin Bullert Additional Reviewer Completed 11/19/2019 2:19 PM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 11/19/2019 3:22 PM Water Steve Messner Additional Reviewer Completed 11/19/2019 3:38 PM Public Utilities Operations Support Tara Castillo Additional Reviewer Completed 11/20/2019 8:02 AM Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 11/20/2019 4:56 PM Procurement Services Drew Cody Additional Reviewer Skipped 11/20/2019 5:18 PM Procurement Services Geoff Thomas Additional Reviewer Completed 11/21/2019 7:36 AM Procurement Services Ted Coyman Additional Reviewer Completed 11/21/2019 8:55 AM Procurement Services Priscilla Doria Additional Reviewer Completed 11/21/2019 9:05 AM Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 11/21/2019 11:44 AM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 11/22/2019 9:06 AM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 11/22/2019 3:11 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 11/22/2019 3:15 PM 11.E Packet Pg. 1211 12/10/2019 County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 11/25/2019 8:19 AM Office of Management and Budget Susan Usher Additional Reviewer Completed 11/25/2019 11:28 AM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 11/29/2019 10:58 AM Board of County Commissioners MaryJo Brock Meeting Pending 12/10/2019 9:00 AM 11.E Packet Pg. 1212 11.E.1 Packet Pg. 1213 Attachment: Attachment 1: I-75 & Collier Blvd Interchange Improvements (10540 : Design Build Collier County I-75 and 951 Utility Relocation 11.E.2Packet Pg. 1214Attachment: Attachment 2: I-75 & Collier Blvd - Project Map (10540 : Design Build Collier County I-75 and 2122 Johnson Street ■Post Office Box 1550 ■Fort Myers, Florida 33902-1550 (239)334-0046 ■ Fax (239) 334-3661 SINCE 1946 November 6, 2019 Via Email Only: Benjamin.Bullert@colliercountyfl.gov Mr. Benjamin N. Bullert, P.E. Collier County Public Utilities - EPMD 3339 Tamiami Trail East, Suite 303 Naples, FL 34112-5361 RE: Q. Grady Minor and Associates (Designer) - Quality Enterprises (Builder) Segment 1 of I-75 and Collier Boulevard Utility Relocation Project Third-Party Review Dear Ben: Please accept this letter in response to your request to provide a third-party review of Quality Enterprises’ request for cost adjustments for the above-referenced project. The requests include the following: 1.) additional cost to install a water main in Segment 1 via horizontal directional drill (HDD) in lieu of open-cut method; 2.) a request for credit for not installing a 36” gate valve; and 3.) a request for credit for not providing a field trailer during the construction on this project. Based upon details provided, our research and recent similar projects, Johnson Engineering provides the following: 1.) Horizontal Directional Drill in Lieu of Open Cut Collier County provided plan sheets 3 and 4 for review with portions requested to be installed via HDD highlighted in yellow. Also provided were the proposed costs for a 36” HDD and the current cost to open cut the 30” pipe: Segment 1 - I-75 & Collier Blvd Utility Relocation Total Unit Price 36” Pipe Installed via HDD (Proposed Price) $627/LF 30” Pipe Installed via Open Cut (Current Price) $218/LF In comparison, Johnson Engineering recently designed a 36” water main that crossed under Golden Gate Canal via HDD for Collier County which was approximately 700 linear feet. The I-75 drill is approximately 1,450 linear feet in length and should be slightly less than Golden Gate based upon project economy of scale. The costs for Golden Gate were as follows: Johnson Engineering Golden Gate Canal Project Installation Unit Price Materials Unit Price Total Unit Price 36” HDPE DR11 Pipe Installed via HDD $470/LF $220/LF $690/LF 11.E.3 Packet Pg. 1215 Attachment: Attachment 3: 11-06-19 - MSD-BNB QGM-QE Review Ltr (10540 : Design Build Collier County I-75 and 951 Utility Relocation Mr. Benjamin N. Bullert, P.E. Re: Segment 1 – I-75 and Collier Blvd Utility Relocation Project Third Party Review November 6, 2019 Page 2 2.) Johnson Engineering is currently installing 36” water main via open cut for Collier County’s NESA Interim Wastewater Treatment Plant at a cost of approximately $275/LF. No rock is located within this project area. We understand that rock is located within Segment 1 - I-75 & Collier Boulevard Utility Relocation project area and based upon discussions with a local contractor, the additional labor cost of conventional rock removal would add approximately $50/LF making the installation cost approximately $325/LF. We contacted a local supplier and obtained the current difference in cost between 30” and 36” pipe which was determined to be $34/LF. Assuming the labor effort is approximately $5 cheaper to install the 30” pipe then the total installation cost should be approximately $286/LF. If the method of rock removal is utilizing an Epi-Rock cutter instead of the conventional method then the cost can be decreased by $30/LF for rock removal for a total cost of $256/LF. Based upon our review and research, Johnson Engineering finds the proposed cost for the 36” HDD of $627 per linear foot to be reasonable and within industry standards, but the open cut deduct should be closer to $286/LF for conventional rock removal and $256/LF for removal by means of the Epi-Rock cutter. Credit Request for Not Installing a 36” Valve = $37,850.00 Based upon the NESA project recently designed for Collier County and the invoice from Ferguson Waterworks dated March 13, 2019, the cost for a 36” Gate Valve with all and required appurtenances is $37,933.96. Materials Cost: $37,933.96 Collier County Tax: $ 2,655.38 Labor (provided by NESA contractor): $ 5,000.00 Recommended Total Credit: $45,589.34 Based upon our review and research, Johnson Engineering finds their deduct cost for item should be closer to $45,589.34. 3.) Credit for Non-Use/Installation of Construction Field Office/Trailer We have reviewed the costs provided in your October 14, 2019 email (attached hereto) for the credit requested for Non-Use of Office Trailer for $7,250. We requested a quote (attached) for the same size trailer to be located in Collier County for a 9 month period and the costs, including their Utilities and Copy/Scanner supplies are as follows: Monthly Rental $1,000/month x 9 months (actual construction time) = $9,035.88 Monthly Utilities $150/month x 9 months = $1,350.00 Copy & scanner with supplies $250/month x 9months = $2,250.00 Recommended Total Credit:$12,653.88 11.E.3 Packet Pg. 1216 Attachment: Attachment 3: 11-06-19 - MSD-BNB QGM-QE Review Ltr (10540 : Design Build Collier County I-75 and 951 Utility Relocation Mr. Benjamin N. Bullert, P.E. Re: Segment 1 – I-75 and Collier Blvd Utility Relocation Project Third Party Review November 6, 2019 Page 3 Based upon the quote received, we believe a total credit of $12,653.88 is a reasonable deduct. Should you have any questions, or require additional information, please let me know. Very truly yours, Michael S. Dickey, P.E. Director of Utility Services MSD/ljb Enclosures 11.E.3 Packet Pg. 1217 Attachment: Attachment 3: 11-06-19 - MSD-BNB QGM-QE Review Ltr (10540 : Design Build Collier County I-75 and 951 Utility Relocation DESIGN -BUILD AGREEMENT between Board of County Commissioners for Collier County Florida, acting as the governing Board of the Collier County Water Sewer District and Quality Enterprises USA, Inc. dated day of ,20_ "Design Build I-75 and Collier Boulevard Utility Relocations Project" RPS#19-7540 "Design Build 1-75 and Collier Boulevard Utility Relocation Project" RPS #19-7540 x TABLE OF CONTENTS Article Name Page ARTICLE1 CONTRACT DOCUMENTS.................................................................................................. 1 ARTICLE 2 CONTRACTOR'S SERVICES AND RESPONSIBILITIES..................................................2 ARTICLE 3 OWNER'S RESPONSIBILITIES...........................................................................................4 ARTICLE4 CONTRACT AMOUNT.......................................................................................................... 5 ARTICLE 5 PERFORMANCE AND PAYMENT BOND.......................................................................... 5 ARTICLE 6 INSURANCE REQUIREMENTS........................................................................................... 6 ARTICLE 7 CONTRACT TIME AND LIQUIDATED DAMAGES.......................................................... 8 ARTICLE8 INDEMNIFICATION............................................................................................................ I0 ARTICLE 9 CONSEQUENTIAL DAMAGES.......................................................................................... 11 ARTICLE10 LAWS AND REGULATIONS............................................................................................ 11 ARTICLE 1 1 INDEPENDENT CONTRACTOR...................................................................................... 12 ARTICLE12 DISPUTE RESOLUTION................................................................................................... 12 ARTICLE13 ASSIGNMENT.................................................................................................................... 13 ARTICLE 14 PERFORMANCE OF WORK AND REMEDY................................................................. 13 ARTICLE15 FORCE MAJEURE............................................................................................................. I3 ARTICLE16 CHANGE IN LAW..............................................................................................................14 ARTICLE 17 TERMINATION FOR DEFAULT......................................................................................14 ARTICLE 18 TERMINATION FOR CONVENIENCE............................................................................16 ARTICLE19 DOCUMENTS.....................................................................................................................16 ARTICLE20 CONFIDENTIALITY..........................................................................................................17 ARTICLE21 SEVERABILITY.................................................................................................................18 ARTICLE 22 PUBLIC ENTITY CRIMES................................................................................................18 ARTICLE23 EXHIBITS INCORPORATED............................................................................................18 ARTICLE24 NOTICES.......................................................................................................I.....................19 ARTICLE 25 CAPTIONS AND HEADINGS ........................................................................................... I9 ARTICLE 26 TRUTH IN NEGOTIATION CERTIFICATE....................................................................19 ARTICLE27 ENTIRE AGREEMENT......................................................................................................20 ARTICLE 28 SUBJECT TO APPROPRIATION......................................................................................20 ARTICLE29 ORDER OF PRECEDENCE............................................................................................... 20 "Design Build I-75 and Collier Boulevard Utility Relocation Project" RPS #19-7540 N DESIGN -BUILD AGREEMENT This Agreement is made this _ day of , 201 between Quality Enterprises USA, Inc., authorized to do business in the State of Florida (hereinafter called "Contractor") whose business address 3494 Shearwater Street, Naples, Florida 34117 and the Board of County Commissioners for Collier County, Florida, a political subdivision of the State of Florida, acting as the governing Board of the Collier County Water Sewer District (hereinafter called the "OWNER"), (collectively referred to as the "Parties"). WITNESSETH: WHEREAS, the Owner solicited for the provision of design and construction services related to the project as described in Request for Professional Services (RPS) #19-7540, "Design Build I-75 Collier Boulevard Utility Relocation Project," on that property located on 3851 City Gate Drive, Naples, Florida 34117, hereinafter referred to as the "Project;" and WHEREAS, the Owner desires to contract with a single party to develop, design, and construct the Project; and WHEREAS, the Owner desires to engage the Contractor to perform services related to such work as described in Solicitation #19-7540 "Design Build I-75 Collier Boulevard Utility Relocation Project" in accordance with this Agreement; and WHEREAS, the Contractor and its sub -consultants and subcontractors are licensed in the State of Florida to provide all engineering and general contracting services required to develop, design and construct the Project; and WHEREAS, Contractor is willing and able to provide any and all services, labor, materials, and equipment necessary to construct the Project, to perform the Work and to bring the Project into full and complete operational status. NOW, THEREFORE, for and in consideration of the terms and conditions contained herein and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the Parties agree as follows: ARTICLE 1 CONTRACT DOCUMENTS 1.1 The Contract Documents are comprised of the following and are incorporated by reference and made a part of this Agreement (all of said documents including the Agreement sometimes being referred to herein as the "Contract Documents" and sometimes as the "Agreement" and sometimes as the "Contract'): 1.1.1 This Agreement, the Exhibits described in Article 23 hereof, the Legal Advertisement, the Bidding Documents and any duly executed and issued addenda, Change Orders, Work Directive Changes, Field Orders, and amendments relating thereto. Page 1 of 64 "Design Build 1-75 and Collier Boulevard Utility Relocation Project" RPS #19-7540 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. INSURER(S) AFFORDING COVERAGE INSURER F : INSURER E : INSURER D : INSURER C : INSURER B : INSURER A : NAIC # NAME:CONTACT (A/C, No):FAX E-MAILADDRESS: PRODUCER (A/C, No, Ext):PHONE INSURED REVISION NUMBER:CERTIFICATE NUMBER:COVERAGES IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. OTHER: (Per accident) (Ea accident) $ $ N / A SUBR WVD ADDL INSD THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. $ $ $ $PROPERTY DAMAGE BODILY INJURY (Per accident) BODILY INJURY (Per person) COMBINED SINGLE LIMIT AUTOS ONLY AUTOSAUTOS ONLY NON-OWNED SCHEDULEDOWNED ANY AUTO AUTOMOBILE LIABILITY Y / N WORKERS COMPENSATION AND EMPLOYERS' LIABILITY OFFICER/MEMBER EXCLUDED? (Mandatory in NH) DESCRIPTION OF OPERATIONS below If yes, describe under ANY PROPRIETOR/PARTNER/EXECUTIVE $ $ $ E.L. DISEASE - POLICY LIMIT E.L. DISEASE - EA EMPLOYEE E.L. EACH ACCIDENT EROTH-STATUTEPER LIMITS(MM/DD/YYYY)POLICY EXP(MM/DD/YYYY)POLICY EFFPOLICY NUMBERTYPE OF INSURANCELTRINSR DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required) EXCESS LIAB UMBRELLA LIAB $EACH OCCURRENCE $AGGREGATE $ OCCUR CLAIMS-MADE DED RETENTION $ $PRODUCTS - COMP/OP AGG $GENERAL AGGREGATE $PERSONAL & ADV INJURY $MED EXP (Any one person) $EACH OCCURRENCE DAMAGE TO RENTED $PREMISES (Ea occurrence) COMMERCIAL GENERAL LIABILITY CLAIMS-MADE OCCUR GEN'L AGGREGATE LIMIT APPLIES PER: POLICY PRO-JECT LOC CERTIFICATE OF LIABILITY INSURANCE DATE (MM/DD/YYYY) CANCELLATION AUTHORIZED REPRESENTATIVE ACORD 25 (2016/03) © 1988-2015 ACORD CORPORATION. All rights reserved. CERTIFICATE HOLDER The ACORD name and logo are registered marks of ACORD HIRED AUTOS ONLY 11/20/2019 A Marsh &McLennan Agency LLC 222 Central Park Avenue,Suite 1340 Virginia Beach VA 23462 Marsh &McLennan Agency LLC 757-456-0577 certificates@MarshMMA.com Zurich American Insurance Company 16535 Evanston Insurance Company 35378QualityEnterprisesUSA,Inc.& Quality Environment Company,Inc. 3494 Shearwater Street Naples FL 34117 Phoenix Insurance Company 25623 Travelers Prop &Casualty Co of America 25674 XL Specialty Insurance Company 37885 912096100 C X 1,000,000 X 300,000 10,000 1,000,000 2,000,000 X Y CO7N91352A19 7/1/2019 7/1/2020 2,000,000 C 1,000,000 X X Comp X Coll 8107N67219019 7/1/2019 7/1/2020 PIP 10,000 aggregate D X X 15,000,000CUP8N00458A7/1/2019 7/1/2020 15,000,000 X 10,000 A X N WC017931004 7/1/2019 7/1/2020 1,000,000 1,000,000 1,000,000 B E Pollution/Professinal Liability Installation Floater MMAENV0001065 UM00030160MA19A 7/1/2018 7/1/2019 7/1/2020 7/1/2020 $1,000,000 each claim $200,000 $2,000,000 Aggre $2,500 DED RE:For Any and All County projects Board of County Commissioners in Collier County are included as additional insureds under the General Liability policy as respects to work performed by the insured as required by written contract Board of County Commissioners in Collier County 3925 Tamiami Trail East Naples FL 34112 11.E.5 Packet Pg. 1218 Attachment: Attachment 5: 19-7540 QualityEnterprise_Insurance_11-20-19 (10540 : Design Build Collier County I-75 and 951 Utility Relocation 19-7540 –Design Build Collier County I-75 and 951 Utility Relocation Project Tom Chmelik, Director Public Utilities Department December 10, 2019 Agenda Item 11 Collier County | Florida 11.E.6 Packet Pg. 1219 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility Objective u To secure a design-build team to provide design and construction services for the I- 75 and 951 Utility Relocation Project to meet demand, stay in compliance, and serve customers efficiently by providing a compliant and reliable potable water system to Collier County Water-Sewer District (CCWSD) customers. Public Utilities Department Engineering and Project Management Division 3 11.E.6 Packet Pg. 1220 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility General Scope u To design and construct the proposed utility improvements to relocate the County’s existing water mains on Collier Boulevard prior to the Florida Department of Transportation (FDOT) starting their Interstate-75 Interchange Improvements project. Public Utilities Department Engineering and Project Management Division 3 11.E.6 Packet Pg. 1221 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility SCOPE OF WORK u Remove 3 high risk water mains located within the FDOT project limits. u Construct a large transmission water main in the existing Florida Power and Light (FPL) easement from South County Region Water Treatment Plant (SCRWRP) to the south end of Forest Glen Golf and Country Club. u Construct a new water main on White Lake Boulevard to connect to the large transmission water main in the FPL easement. u Construct a new water main starting from Davis Boulevard traveling south down Collier Boulevard. u Replacement of an existing raw water main located within the Forest Glen Golf and Country Club. u Public Information Program u Project management and coordination u All required permitting u Other required improvements. 11.E.6 Packet Pg. 1222 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility I-75 FDOT Planned Improvements Public Utilities Department Engineering and Project Management Division 11.E.6 Packet Pg. 1223 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility Planned Improvements Public Utilities Department Engineering and Project Management Division 4 11.E.6 Packet Pg. 1224 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility RPS Process u 26,786 Notices Sent u 174 Vendors Downloaded the RPS Package u 7 Step 1 Proposals Received u 7 Deemed Responsive And Responsible u 4 Teams Shortlisted u 2 Shortlisted Firms Submitted Proposals u Proposals and GMP Evaluated by Selection Committee Public Utilities Department Engineering and Project Management Division 5 11.E.6 Packet Pg. 1225 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility Results u Relocate assets outside the FDOT I-75 and 951 Interchange Improvements project area that are defined as “Red: Level 3 – Risked Compliance”, including: –48 inch water main pipe that is 31 year old, prone to failure, expensive to repair and located in high risk areas (Collier Blvd/ City Gate Drive and Collier Blvd Median and I- 75). –36 inch water main –20 inch water main u Coordinate and complete work prior to FDOT I-75 & 951 Interchange Improvements project. Public Utilities Department Engineering and Project Management Division 6 11.E.6 Packet Pg. 1226 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility Recommendation u Recommendation to award contract No. 19-7540, “Design Build Collier County I-75 and 951 Utility Relocation Project” to Quality Enterprises USA, Inc. in the total amount of $14,962,500.00 for Project Number 70229 and authorize the Chairman to execute the contract. Public Utilities Department Engineering and Project Management Division 7 11.E.6 Packet Pg. 1227 Attachment: Attachment 6: Final DB Powerpoint (10540 : Design Build Collier County I-75 and 951 Utility