Loading...
Agenda 11/12/2019 Item #16C 9 (Budget Amendment for Vanderbilt Dr Cul-dw-sacs Public Utilities Renewal)11/12/2019 EXECUTIVE SUMMARY Recommendation to authorize budget amendments in the amount of $911,912.93 for the Vanderbilt Drive Cul-de-sacs Public Utilities Renewal, Project Number 70122. OBJECTIVE: To provide reliable, sustainable, and regulatory compliant services to the customers along Vanderbilt Drive and the 14 adjacent Conners Subdivision neighborhood cul-de-sacs by replacing and refurbishing the water, wastewater and stormwater infrastructure in coordination with the Wastewater Basin 101 Program and the Vanderbilt Beach aerial to underground utility conversion. CONSIDERATIONS: On July 12, 2016 (as Agenda Item 11D), the Board approved Contract No. 16- 6638 to Mitchell & Stark Construction Co., Inc., for the Vanderbilt Drive Cul -de-sacs Project; which included the replacement of water, wastewater and stormwater infrastructure. Attachment 1 - Project Map. The Vanderbilt Drive Cul-de-sacs Public Utilities Renewal Project achieved substantial completion on October 25, 2019. All water and wastewater utility work has been complete and operational since October 10, 2019. The project installed over 19 miles of water, wastewater and stormwater pipe, rehabilitated four wastewater pump stations, and relocated two wastewater pump stations. 74% of the project streets have the second, final layer of asphalt applied; one layer has been applied to the remaining streets. To date, approximately 496 driveways have been restored. To complete the project, driveway restoration is required at approximately 13 Vanderbilt Drive residences and 51 cul-de-sac residences, and swales need to be graded and sodded on Connors, Seabee, Germain and Seagull Avenues, as well as on small sections of Vanderbilt Drive. In addition, the final phase of the Municipal Service Taxing Unit (MSTU) underground electrical activation is anticipated to complete by the middle of November and the remaining poles scheduled to be removed prior to year-end. A budget amendment is required for the following reasons: Contractor Fixed Costs: On September 11, 2018 (As Agenda Item 16.C.9) the Board approved Change Order No. 5, which added $481,571.05 in associated contract fixed costs for 310 additional days. The forecasted amount was determined by an average negotiated “burn rate” based on costs to date. Fix ed costs included: maintenance of traffic, rental of lots used for material staging, dumpster rentals, porta pots rental, geo-seismic services, asphalt paving and labor. When the contractor invoiced the County for fixed costs, actual invoices were typically higher than the forecasted burn rate. Therefore, the change order amount was not sufficient to cover fixed costs beyond May 23, 2019 and an additional forecasted amount of $408,000.00 is needed to cover fixed costs after that date to completion. This amount is based on a new burn rate calculated from invoices paid to date. This cost will be included in a future change order. Additional Driveway Quantities: Per Contract 16-6638, line items that exceed more than 25% of the original quantities are subject to unit price negotiation. The quantities for brick pavers exceeded more than 25% due to restoration of driveways extended beyond the right of way line for several unforeseen conditions such as slope correction issues due to modifications to the road design, and installation of sanitary sewer laterals on private property to eliminate existing vitrified clay pipes. Additionally, several new houses were constructed or renovated since the start of this project. In total, 6,240 additional square yards of brick paver driveway restoration has been or will be required. These additional quantities were not included in the original contract and are being added now. The total amount needed over existing project funds for driveways is $503,912.93. This cost will be included in a future change order. Combined, the total amount needed for fixed costs and driveways is $911,912.93. No further funding for 16.C.9 Packet Pg. 1447 11/12/2019 fixed costs or driveways are anticipated for the remainder of the project; however, there will be other additional quantities that exceed 100 percent and outstanding work directives that will be reconciled at the end of the project. FISCAL IMPACT: Funding is available in, and is consistent with, the FY2020 Capital Budget approved by the Board on September 19, 2019. The sources of funding for the budget amendment are the Water Capital Fund (412), the Wastewater Capital Fund (414), and the Stormwater Capital Fund (325) as distributed below. Water (412) Wastewater (414) Stormwater (325) Total Fixed Costs $204,000.00 $204,000.00 N/A $408,000.00 Additional Driveway Quantities $358,319.42 N/A $145,593.51 $503.912.93 Total Budget Amendment $562,319.42 $204,000.00 $145,593.51 $911,912.93 Staff analyzed current and future needs to ensure that the budget amendments will not negatively affect current and future financial commitments. LEGAL CONSIDERATIONS: No legal issues are raised by this item which is ready for Board action. This is a regular matter requiring majority vote. - JAB GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: Recommendation to authorize budget amendments in the total amount of $911,912.93 for the Vanderbilt Drive Cul-de-sacs Public Utilities Renewal, Project Number 70122. Prepared By: Diana C. Dueri, PMP, Senior Project Manager, Engineering and Project Management Division ATTACHMENT(S) 1. Attachment 1 - Project Map (PDF) 16.C.9 Packet Pg. 1448 11/12/2019 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.9 Doc ID: 10607 Item Summary: Recommendation to authorize budget amendments in the amount of $911,912.93 for the Vanderbilt Drive Cul-de-sacs Public Utilities Renewal, Project Number 70122. Meeting Date: 11/12/2019 Prepared by: Title: Project Manager – Public Utilities Planning and Project Management Name: Diana Dueri 10/18/2019 2:42 PM Submitted by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 10/18/2019 2:42 PM Approved By: Review: Public Utilities Operations Support Tara Castillo Additional Reviewer Completed 10/18/2019 2:52 PM Capital Project Planning, Impact Fees, and Program Management Liz Gosselin Additional Reviewer Completed 10/18/2019 3:05 PM Public Utilities Planning and Project Management Craig Pajer Additional Reviewer Completed 10/18/2019 3:09 PM Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 10/18/2019 4:18 PM Growth Management Department Lisa Taylor Additional Reviewer Completed 10/21/2019 9:15 AM Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 10/22/2019 9:19 AM Procurement Services Ted Coyman Additional Reviewer Completed 10/22/2019 9:51 AM Growth Management Operations Support Christopher Johnson Additional Reviewer Completed 10/22/2019 10:07 AM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 10/22/2019 10:11 AM Capital Project Planning, Impact Fees, and Program Management Amy Patterson Additional Reviewer Completed 10/22/2019 1:35 PM Capital Project Planning, Impact Fees, and Program Management Gerald Kurtz Additional Reviewer Completed 10/22/2019 1:45 PM Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 10/22/2019 2:54 PM County Attorney's Office Jeffrey A. Klatzkow Level 2 Attorney Review Completed 10/23/2019 11:19 AM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 10/25/2019 3:31 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 10/25/2019 3:52 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 10/28/2019 12:40 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 10/29/2019 4:39 PM 16.C.9 Packet Pg. 1449 11/12/2019 County Attorney's Office Jennifer Belpedio Additional Reviewer Completed 11/01/2019 3:55 PM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 11/03/2019 10:00 PM Board of County Commissioners MaryJo Brock Meeting Pending 11/12/2019 9:00 AM 16.C.9 Packet Pg. 1450 dddddddddddddddddddddddddddddddddddddddddddddddddddddd d d d d d d d d d ddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddPhase 2 Phase 1 Phase 4B Phase 5 Phase 6 Phase 7 Phase 3 Phase 3 Phase 4A 6TH ST NVANDERBILT DRGULF SHORE DRBLUEBILL AVE 91ST AVE N 99TH AVE N 98TH AVE N 97TH AVE N 96TH AVE N 95TH AVE N 94TH AVE N VANDERBILT BEACH RD 111TH AVE N 93RD AVE N 110TH AVE N 109TH AVE N 108TH AVE N 101ST AVE N 107TH AVE N 106TH AVE N 105TH AVE N 104TH AVE N 92ND AVE N 100TH AVE N 103RD AVE N EGRET AVE 102ND AVE N HERON AVE CONNERS AVE OAK AVE FLAMINGO AVE B E A CHWALKCIR LAGOON AVE B A Y V I E W A V E C H A N N E L D R TRADEWINDS AVE SOUTHBAY DR S E A B R E E Z E A V ESEABEE AVE PINE AVE WILLET AVE GERMAIN AVE SEAGULL AVE BAYSIDE AVE CENTER ST N SOLIE L DRSEAGROVELN FLA GSHIP DR LAUN CHCIRPALM C T VAN DER BIL T DR IVE C U L-DE -SA CS PU BL IC UTILITIES RENEWAL PROJECTPHASING PLAN | APRI L 26, 2019 Legend d ddEnerg ized UndergroundElectric Service Line First Lift of AsphaltPavement Placed 0 200 400 Feet ($$¯ 16.C.9.a Packet Pg. 1451 Attachment: Attachment 1 - Project Map (10607 : Budget Amendments funds 325, 412, 414)