Loading...
Agenda 09/24/2019 Item #16C 6 (Award Contract #19-7540 for the Design Build I-75 & 951 Utility Relocation Project)09/24/2019 EXECUTIVE SUMMARY Recommendation to approve the selection committee’s ranking of Request for Professional Services (“RPS”) No. 19-7540, “Design Build Collier County I-75 and 951 Utility Relocation Project,” and authorize staff to begin contract negotiations with the top-ranked firm of Quality Enterprises USA, Inc., so that staff can bring a contract back to the Board at a later meeting. OBJECTIVE: To approve the selection committee’s rankings and authorize staff to begin contract negotiations with the top-ranked firm to secure a design-build team to provide design and construction services for the I-75 and 951 Utility Relocation Project. CONSIDERATIONS: The Florida Department of Transportation (“FDOT”) informed the Collier County Water-Sewer District (“CCWSD”) of its I-75 & 951 Interchange Improvements project that will be commencing as early as October 2020. The FDOT project will be a design-build project that includes constructing additional ramps at the I-75/951 interchange to allow traffic departing Interstate 75 (“I-75”) to proceed directly south on 951 or traffic traveling north on 951 to I-75 to bypass the Davis Boulevard/951 intersection. The FDOT project limits, shown in “I-75 & Collier Blvd Interchange Improvements” (attached), start slightly north of the northerly I-75 ramps and end at Business Circle South. Within the FDOT project limits, the CCWSD has extensive existing water and wastewater utility lines. The existing water mains include a 48-inch pipe, a 36-inch pipe and two 20-inch pipes. The existing wastewater force main is a 12-inch pipe. These large pipes underneath a major FDOT interchange represent a significant risk to both sets of assets. A worst-case scenario would be a 48-inch water main break causing a long-term shut down of I-75 and 951. In November 2017, two repairs were completed on the 48-inch Prestressed Concrete Cylinder Pipe (“PCCP”) water main: one at the 951/City Gate Drive intersection, and the other on the 951 median (south of the Interstate 75 overpass). PCCP pipe is a proprietary material that can only be installed and repaired by Thompson Pipe Group. Repairs are costly ($418,336 for the two repairs mentioned above) and subject to the availability of Thompson Pipe Group personnel and materials. The existing 48-inch PCCP pipe is: (1) located in a high-risk area, (2) prone to failure, (3) expensive to repair, and is (4) 31 years old. For these reasons, this water main is being abandoned and relocated outside of the FDOT project area proactively, before the start of the FDOT Interchange Improvement project. For similar reasons, the other three water mains are also being abandoned and relocated outside of the FDOT project area, I-75 & Collier Blvd - Project Map (attached). The wastewater force main will be replaced by a new force main under a separate project; however, it will remain in place, inactive, for emergency uses only. The condition of these assets is identified as “Red: Level 3 - Risked Compliance,” as reported to the Board at the October 1, 2013, Asset Assessment and Management Workshop. The proposed scope of work for Project 70229, “I-75 / 951 Utility Relocation Project” includes constructing a large transmission water main in the existing Florida Power and Light (“FPL”) easement from the South County Regional Water Treatment Plant (“SCRWTP”) to the south end of the Forest Glen Golf and Country Club. The FPL easement is located east of 951. The new transmission water main will need to be installed and placed into service prior to the start of the FDOT Interchange Improvement project. The project also includes the installation of a new water main on White Lake Boulevard that will connect to the large transmission water main in the FPL easement, the replacement of the SCRWTP reverse osmosis raw water line located within the FPL easement and within the Forest Glen Golf and Country Club, and a new 20-inch water main from Davis Boulevard to Business Circle South. After the completion of this project, a new 20-inch water main traveling south down 951 from Davis Boulevard 16.C.6 Packet Pg. 1373 09/24/2019 will remain in the 951 right-of-way to provide potable water to the existing developments along 951. The preliminary estimate to complete the utility relocation improvements indicates a cost between fifteen and seventeen million dollars. By comparison, the total Capital Improvement Program budget adopted for Water User Fee Fund (412) in Fiscal Year 2019 was $16,940,400. After the completion of this new transmission water main, the existing 48 -inch PCCP water main, existing 36-inch water main (Davis Boulevard to south side of Forest Glen subdivision), existing 20-inch water main (north of I-75 to Davis Boulevard) and the existing 20-inch water main (Davis Boulevard to Business Circle South) will be abandoned. The abandonment/removal of the existing water main will be completed as part of the FDOT Interchange Improvement Design-Build project. The CCWSD will enter into a Utility Work by Highway Contractor Agreement and Memorandum of Understanding with FDOT to have its design-build contractor complete the water main abandonment/removal. On December 18, 2018, the Procurement Services Division released notices for RPS No. 19-7540, Step 1, Design-Build of I-75 and 951 Utility Relocation Project, sending out 26,786 notifications resulting in interested firms downloading 174 solicitation packages. Seven firms submitted proposals by the February 5, 2019 due date, all of which were deemed responsive and responsible. On March 5, 2019, the Selection Committee met to review, score and short list the top four proposals based on qualifications as described in Step 1 of the solicitation documents. Garney Companies, Inc., Douglas N. Higgins, Inc., Wright Construction Group, Inc. and Quality Enterprises USA, Inc. were shortlisted to move on to Step 2. On May 8, 2019, the Procurement Services Division released Step 2 of RPS No. 19-7540 (Technical Proposals/Presentations/GMP) to the four shortlisted firms. Two of the four firms submitted proposals by the July 25, 2019 due date - Douglas N. Higgins, Inc. and Wright Construction Group, Inc. did not submit during Step 2 of the RPS process. On August 22, 2019, the selection committee met to review and score the technical proposals, observe presentations, and open the firms’ Guarantee Maximum Price. At the end of this meeting the selection committee ranked the firms as follows: Firm Rank Quality Enterprises USA, Inc./Q. Grady Minor and Associates 1 Garney Companies, Inc./Tetra Tech, Inc 2 FISCAL IMPACT: There is no fiscal impact associated with this action; however, the submitted guaranteed maximum price of the number one team is $14,962,500. After negotiation, the funding is available in the Fiscal 2020 capital budget approved by the Board on September 19, 2019. The source of funding is the Water User Fee Capital Fund (412). LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.-SRT GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: To approve the selection committee’s rankings for RPS Number 19-7540, “Design Build I-75 and 951 Utility Relocation Project,” and to authorize staff to begin contract negotiations with the number one ranked team, Quality Enterprises, Inc./Q. Grady Minor and Associates (and, if an agreement cannot be reached, begin contract negotiations with the remaining ranked firm), so that a negotiated contract can be brought to the Board for approval at a future meeting. Prepared By: Shon D. Fandrich, P.E., PMP, Senior Project Manager, Engineering and Project Management Division 16.C.6 Packet Pg. 1374 09/24/2019 ATTACHMENT(S) 1. I-75 & Collier Blvd Interchange Improvements (PDF) 2. I-75 & Collier Blvd - Project Map (PDF) 3. 19-7540 Final Ranking Step 2 Signed (PDF) 4. 19-7540 NORA (PDF) 5. [Linked] 19-7540 QE_GradyMinor_Proposal_Final (PDF) 16.C.6 Packet Pg. 1375 09/24/2019 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.6 Doc ID: 9944 Item Summary: Recommendation to approve the selection committee’s ranking of Request for Professional Services (“RPS”) No. 19-7540, “Design Build Collier County I-75 and 951 Utility Relocation Project,” and authorize staff to begin contract negotiations with the top-ranked firm of Quality Enterprises USA, Inc., so that staff can bring a contract back to the Board at a later meeting. Meeting Date: 09/24/2019 Prepared by: Title: – Public Utilities Planning and Project Management Name: Shon Fandrich 09/04/2019 9:10 AM Submitted by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 09/04/2019 9:10 AM Approved By: Review: Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 09/04/2019 9:30 AM Procurement Services Geoff Thomas Additional Reviewer Completed 09/04/2019 10:27 AM Public Utilities Planning and Project Management Benjamin Bullert Additional Reviewer Completed 09/04/2019 11:48 AM Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 09/04/2019 11:51 AM Wastewater Beth Johnssen Additional Reviewer Completed 09/04/2019 12:13 PM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 09/04/2019 12:34 PM Water Steve Messner Additional Reviewer Completed 09/04/2019 2:42 PM Water Pamela Libby Additional Reviewer Completed 09/05/2019 7:48 AM Procurement Services Evelyn Colon Additional Reviewer Completed 09/05/2019 12:13 PM Procurement Services Ted Coyman Additional Reviewer Completed 09/05/2019 2:38 PM Public Utilities Department Drew Cody Level 1 Division Reviewer Completed 09/05/2019 5:56 PM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 09/09/2019 5:48 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 09/10/2019 11:33 AM Office of Management and Budget Laura Wells Level 3 OMB Gatekeeper Review Completed 09/10/2019 1:58 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 09/12/2019 10:28 AM Office of Management and Budget Susan Usher Additional Reviewer Completed 09/12/2019 5:11 PM 16.C.6 Packet Pg. 1376 09/24/2019 County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 09/14/2019 12:52 PM Board of County Commissioners MaryJo Brock Meeting Pending 09/24/2019 9:00 AM 16.C.6 Packet Pg. 1377 16.C.6.a Packet Pg. 1378 Attachment: I-75 & Collier Blvd Interchange Improvements (9944 : Design Build Collier County I-75 and 951 Utility Relocation Project) 16.C.6.bPacket Pg. 1379Attachment: I-75 & Collier Blvd - Project Map (9944 : Design Build Collier County I-75 and 951 Utility 16.C.6.cPacket Pg. 1380Attachment: 19-7540 Final Ranking Step 2 Signed (9944 : Design Build Collier County I-75 and 951 Utility 16.C.6.d Packet Pg. 1381 Attachment: 19-7540 NORA (9944 : Design Build Collier County I-75 and 951 Utility Relocation Project) 16.C.6.d Packet Pg. 1382 Attachment: 19-7540 NORA (9944 : Design Build Collier County I-75 and 951 Utility Relocation Project) CONTACT Phone 239.435.7200 Fax 239.435.7202 contact@qeusa.com ADDRESS QUALITY ENTERPRISES USA, INC. 3494 Shearwater St. Naples, FL 34117 RPS Number 19-7540 | Step 2 Statement of Qualification Design Build I-75 and Collier Blvd Utility Relocation Project JULY 25, 2019 Collier County, FL Transmittal Letter & Executive Summary Project Team Approach Technical Information 01 02 03 table of contents 01 Transmittal Letter & Executive Summary Dear Mr. Thomas AND COMMITTEE MEMBERS, Enclosed please find our Step 2 response to RPS No: 19-7540 for the Design-Build of I-75 and Collier Boulevard Utility Relocation Project. This response is submitted on behalf of the Quality Enterprises USA, Inc. and Q. Grady Minor & Associates, P.A. design-build team. We have received, reviewed, and understand the requirements of RPS No: 19-7540 and agree to be bound by those requirements, including all addenda. Legal evidence of the authority to execute and sign this proposal is included at the end of Section 3: Technical Information. Our Guaranteed Maximum Price has been delivered to you under separate cover. We acknowledge receipt of Addendum 1, Addendum 2, Addendum 3, Addendum 4, Addendum 5, Addendum 6, Addendum 7, and Addendum 8. The signed addendums are included at the end of Section 3: Technical Information, as well. The principal contact for our team will be myself, Louis J. Gaudio, and my contact information is listed below. On behalf of the Quality Enterprises USA, Inc. and Q. Grady Minor & Associates, P.A. team, I thank you for the opportunity to propose on this project. Sincerely, LOUIS J. GAUDIO Vice President Quality Enterprises USA, Inc. 3494 Shearwater St. Naples, FL 34117 239-435-7200 lgaudio@qeusa.com RE: RPS NO: 19-7540, DESIGN-BUILD OF I-75 AND COLLIER BOULEVARD UTILITY RELOCATION PROJECT Procurement Services Division Attn: Geoff Thomas, Procurement Strategist 3295 Tamiami Trail East, BLDG C-2, Naples, FL 34112 JULY 25, 2019 01 QE + GRADY MINOR | A PROVEN & ESTABLISHED PARTNERSHIP The Quality Enterprises USA, Inc. + Q. Grady Minor & Associates, P.A. design-build team is highly qualified for the I-75 and Collier Boulevard Utility Relocation Project. Having collaborated on over 36 projects, the QE+ Grady Minor team is well established in Collier County and has more than 20 years of experience in the local area. Combined, QE +Grady Minor has successfully completed hundreds of projects with similar components, maintains an outstanding working relationship with each other and with Collier County, and has a vested interest in the success of this project. QE + Grady Minor will work collaboratively to provide the County with the most cost effective and successful design. Together, QE+ Grady Minor will: • Work closely with County staff to identify and meet all goals • Provide industry-proven, technical, construction, and management expertise • Use local resources to meet the County’s desired schedule • Identify and mitigate risks to avoid delays and provide the most cost-effective solutions • Comply with all design package criteria and county standards for utilities, roadway, and ROW • Prioritize public concerns to avoid impacts on surrounding residents, areas, and the environment • Be available to the County at all times QE is a versatile general contractor and will self-perform over 90% of the project. This cost saving practice will allow for flexibility in scheduling, adaptability to rapid project changes, and guarantees that a skilled and dynamic workforce will be available throughout the project. The team has also assembled a group of highly reputable, local companies with proven success to participate in this design-build project: Earth View, LLC, QE’s in-house Trenchless Technology sister company, for Horizontal Directional Drilling (HDD), Fusing, and Utility Location Services, Brierley Associates for Trenchless Design, Forge Engineering Inc. for Geotechnical Engineering, Passarella Associates, Inc. for Environmental Consulting and Cella Molnar & Associates, Inc. for Public Information. **Cella Molnar is a change to QE+ Grady Minor’s key team members from RPS NO: 19-7540, Step 1. PROJECT GOALS AND OBJECTIVES The QE+ Grady Minor team understands the County’s goals to: “Design, construct and place into operation the proposed water mains to allow the existing water mains on Collier Boulevard to be abandoned by the start of the FDOT’s Interstate 75 Interchange Improvements project” and to “Ensure the high service pumps are still running at maximum efficiency after connecting to the proposed transmission water mains” as stated in RPS NO: 19-7540, Step 1. QE+ Grady Minor’s projected workload aligns with the design-build schedule and the team commits to providing the required services, mobilizing resources in response to the established timeline, and to being readily available and accessible during all phases of the project. PROJECT DELIVERY QE has successfully completed hundreds of projects for Collier County. With key players from QE and Collier County involved on many of the same projects, a strong relationship has been formed and the QE + Grady Minor team is aware of the County’s high standards and expectations for local projects. The QE + Grady Minor team has put a significant amount of planning into this project and the team’s understanding of local conditions will expedite movement through all phases. QE’s role as overall project manager includes: overseeing pipe installations, all testing, tie-ins, and restoration work. Grady Minor will be instrumental in the project design and will provide survey, permitting, construction administration, and construction engineering inspection (CEI). TRANSMITTAL LETTER & EXECUTIVE SUMMARY QEAT AGLANCE First job with Collier County 2002 First project in Florida 1997 Total Revenue in 2018 $60M Revenue from Collier County in 2018 $6M Collier County Utility Emergency Contract started in and held every year since 2008 Collier County School Board contract started in 2007 02 and held every year since PROJECT MANAGEMENT The I-75 and Collier Boulevard Utility Relocation Design Build Project will require significant coordination between QE+ Grady Minor and Collier County. In response, the QE+ Grady Minor management team is efficiently structured and is focused on strong communication, coordination, and decision making. Combined, QE+ Grady Minor has over 300 employees living and working in the local area and QE’s corporate office and equipment yard are less than ½ mile from the project site. This will strengthen project management, as key personnel can perform daily job site visits, and will result in the prompt mobilization of equipment. QE will self-perform 90% of this design build project, including utility construction by QE’s ten experienced pipe installation crews. Earth View LLC, QE’s in-house trenchless technology sister company, will provide HDD with its multiple drilling crews and Grady Minor will oversee all design, permitting, and engineering efforts. A step ahead, QE will use the industry leading construction ERP solution, Vista by Viewpoint, to help manage this design-build project. A multi-faceted cloud-based construction suite, this state-of-the-art technology program provides a direct line of communication between the office and field, reducing the need for Superintendents and crews to leave the job site and visit the office. CONSTRUCTION RESOURCES QE is prepared for the I-75 and Collier Boulevard Utility Relocation Project. The company has experienced significant growth over the past few years, increasing in total number of pieces of equipment owned, personnel employed, and number of jobs successfully completed. With over 300 local employees and 250+ pieces of modern heavy construction equipment, The QE + Grady Minor team has the resources of large competitors but an attentive and responsive management structure characteristic of a small firm. Technology plays an integral role in QE’s operations, as many machines are equipped with GPS, site positioning systems for machine grading, and 3D technology. The company has also invested in Trimble Sitework Technology which allows millimeter accuracy with fewer passes and no manual staking. All mid to large excavators are equipped with CAT Pin Grabber Coupler System which increases machine performance, versatility, and jobsite safety. Collectively, these resources reduce project risk from the County’s perspective. 03 TRANSMITTAL LETTER & EXECUTIVE SUMMARY QE + Grady Minor is the trusted choice and will not disappoint. The following graphs demonstrate QE’s growth from 2016 – Present: Number of Employees 190 209 240 New Equipment + Vehicles Purchased $2,579,732 $3,156,383 $15,327,185 Number of Jobs 85 167 194 2016 2017 2018 -Present DESIGN AND CONSTRUCTION PLANS OVERVIEW SEGMENT 1 – South County Regional Water Treatment Plant (SCRWTP) to City Gate Boulevard South Segment No. 1 consists of a proposed 30-inch PVC water main to be installed via open cut installation from the SCRWTP to City Gate Boulevard South. Beginning on the northwest side of the SCRWTP potable water ground storage tanks, the proposed 30-inch water main will connect to the existing 36-inch water main with a new, cut-in 36x30” ductile iron tee, a 36-inch gate valve (GV) and a 30-inch GV. The new 30-inch water main will extend east through the SCRWTP site, crossing existing 8 and 30-inch raw water mains, and ultimately to a 15-foot wide Collier County Utility Easement (CUE) within Lot 11 of City Gate Commerce Park Phase 3. The 30-inch water main will be designed and constructed within the 15-foot CUEs through Lots 11-16 and will favor the east side of the CUE. Near the Lot 16/17 line, an existing 30-inch raw water main leaves the SCRWTP property and enters an existing 15-foot wide CUE. The existing 30-inch raw water main will require that the proposed 30-inch water main be shifted to the east. The proposed 30-inch water main will be installed east of the existing 30-inch raw water main, with a minimum separation of 5-feet (wall-to-wall), and 2-feet minimum (wall-to-wall) setback between the eastern edge of the County’s 5-foot CUE and the proposed water main. The installation of the proposed water main within Lots 11-17 will utilize the County’s 20-foot Temporary Construction Easements (TCE) through these lots. At City Gate Boulevard South, the proposed 30-inch water main will be deflected to avoid an existing 4-inch force main and an existing 60-inch stormwater RCP, which are approximately 15-feet apart at the location where the water main will cross each of these existing utilities. The existing 4-inch force main could be deflected to avoid deflecting the proposed 30-inch water main. However, it appears that the existing 60-inch Reinforced Concrete Pipe (RCP) has approximately 1-2 feet of cover over the RCP and thus the proposed 30-inch water main will need to be deflected under the RCP. 15-feet apart at the location where the water main will cross each of these existing utilities. The existing 4-inch force main could be deflected to avoid deflecting the proposed 30-inch water main. However, it appears that the existing 60-inch Reinforced Concrete Pipe (RCP) has approximately 1-2 feet of cover over the RCP and thus the proposed 30-inch water main will need to be deflected under the RCP. PROJECT MEETINGS QE’s corporate office and equipment yard are less than ½ mile from the project site; therefore, all meetings between QE+ Grady Minor and Collier County can be held at QE’s office and followed by project site visits if desired. This is a great benefit for Collier County. QE +Grady Minor proposes the following meeting approach for this project: • Kickoff meeting prior to project start to review project objectives and initiate coordination with County staff • Design review meetings at 60%, 90%, and 100% plans to field questions and incorporate questions from County staff • Biweekly project progress meetings • Additional meetings as necessary to coordinate with suppliers, regulatory agencies, etc. • Public meetings as necessary to inform residents, area businesses, etc. of upcoming activities THE QE+ GRADY MINOR PLAN OF APPROACH QE + Grady Minor maintains the following Plan of Approach for the I-75 and Collier Boulevard Design Build Project: • Prioritize the needs of residents, businesses, and stakeholders within project limits • Prepare sound engineered designs that minimize environmental impact • Maintain clear, accurate communication through the entire project • Install lasting utilities • Offer exceptional service to Collier County at an economical cost 04 TRANSMITTAL LETTER & EXECUTIVE SUMMARY Segment 1 TRANSMITTAL LETTER & EXECUTIVE SUMMARY DESIGN AND CONSTRUCTION PLANS OVERVIEW (CONT.) SEGMENT 2 – White Lake Boulevard from City Gate Drive to FPL Easement Segment No. 2 consists of new 10 and 24-inch water main piping and associated appurtenances along White Lake Boulevard and City Gate Boulevard South within three separate segments as described below. Segment 2.1: A 24-inch PVC water main installed via open cut along White Lake Boulevard from City Gate Drive to City Gate Boulevard South. The new 24-inch water main will replace an existing 20-inch water main that will be grouted and abandoned in place. The new 24-inch water main will connect to the following: 1) an existing 36-inch on City Gate Drive 2) an existing 8-inch water main at lot corner 3819/3815 White Lake Blvd; 3) an existing 20-inch water main, 16-inch water main, and 8-inch water main at SW corner White Lake Boulevard and City Gate Boulevard South. Segment 2.2: A 24-inch PVC water main installed via open cut along City Gate Boulevard South from White Lake Boulevard to the FPL Easement that will connect to the proposed 24-inch water main at White Boulevard and to the proposed 30-inch water main at the southern terminus of Segment No.1, within the FPL easement. This 24-inch water main will replace an existing 16-inch water main along City Gate Boulevard South that will be grouted and abandoned in place. Segment 2.3: A 10-inch PVC water main installed via open cut along White Lake Boulevard from just south of the southern property line of 3807 White Lake Boulevard to the FPL Easement. The new 10-inch water main will replace an existing 10-inch water main that will be grouted and abandoned in place. The new 10-inch water main will connect to the following: 1) an existing 20-inch water main just south of 3807 White Lake Boulevard 2) an existing 10-inch water main at Shaw Boulevard 3) the proposed 36-inch water main at the southern terminus of Segment No. 3. SEGMENT 3 – Within FPL Easement from City Gate Boulevard South to White Lake Boulevard Segment No. 3 consists of a proposed 36-inch PVC water main to be installed via open cut installation from the City Gate Boulevard South (the southern end of Segment No. 1) to White Lake Boulevard (the southeastern terminus of Segment No. 2.) City Gate Boulevard South cannot be closed to traffic during the day. Therfore, construction requiring City Gate Boulevard South to be closed will either be performed at night or be performed with an alternate installation method, if approved by the County. SEGMENT 4 – Within FPL Easement from White Lake Boulevard to Beck Boulevard Segment No. 4 consists of a proposed 36-inch HDPE water main to be installed via HDD from White Lake Boulevard and the FPL Easement to Beck Boulevard and the FPL Easement, under I-75 and under the east parking lots of Super 8 Motel and iStorage Self Storage. The proposed water main will have ARVs and isolation valves on either side of the HDD. At Beck Boulevard the proposed water main will connect to the existing 10-inch water main and proposed 24-inch water main, the eastern terminus of Segment No.8, within the southern ROW of Beck Boulevard. 05Segment 2Segment 3Segment 4 TRANSMITTAL LETTER & EXECUTIVE SUMMARY DESIGN AND CONSTRUCTION PLANS OVERVIEW (CONT.) SEGMENT 5 – Within FPL Easement from Beck Boulevard to Forest Glen Boulevard Segment No. 5 consists of a proposed 36-inch HDPE water main to be installed via HDD from Beck Boulevard and the FPL Easement to Forest Glen Boulevard and the FPL Easement. The proposed water main will require the crossing of the South Florida Water Management District’s (SFWMD) Henderson Canal and the entrance drive to Golden Gate Fire Station No. 72, ultimately into Forest Glenn Golf & Country Club property. The use of HDD installation is proposed to avoid wetland impacts and will be accomplished with 36-inch HDPE and each HDD will include ARVs and isolation valves on either side of each HDD. At Forest Glen Boulevard the proposed water main will connect to an existing 10-inch water main. SEGMENT 6 – Within FPL Easement from Forest Glen Boulevard to the South End of Forest Glen Golf & Country Club Segment No. 6 consists of a proposed 36-inch HDPE water main to be installed via HDD from Forest Glen Boulevard and the FPL Easement to the south end of Forest Glen Golf & Country Club and the FPL Easement. The use of HDD installation is proposed to avoid wetland impacts and will be accomplished with 36-inch HDPE and each HDD will include ARVs and isolation valves on either side of each HDD. Additionally included in Segment No. 6 is the replacement of the existing 30-inch fusible PVC raw water main from Forest Glen Boulevard to the south end of the Forest Glen Golf & Country Club, which will require the connection to one existing raw water well. The 30-inch raw water main will be replaced with 30-inch PVC water main piping installed via open cut from Forest Glen Boulevard to the raw water well. From the well south, the new raw water main will be replaced with 36-inch HDPE piping installed via HDD to the south end of Forest Glen Golf & Country Club. The existing 30-inch fusible PVC raw water main will be grouted and abandoned in place. SEGMENT 7 – Within Collier County Easement from South End of Forest Glen Golf & Country Club to Collier Boulevard Segment No. 7 consists of a proposed 30-inch HDPE water main to be installed via HDD from the south end of Forest Glen Golf & Country Club and the FPL Easement to the eastern ROW of Collier Boulevard, just east of the SFWMD’s Henderson Canal. The proposed water main will have ARVs and isolation valves on either side of the HDD and will connect to an existing 36-inch water main on the east side of Henderson Canal. SEGMENT 8 – Beck Boulevard/Davis Boulevard from the FPL Easement to just East of Bedzel Dr. Segment No. 8 consists of a proposed 24-inch HDPE water main to be installed along Beck Boulevard/ Davis Boulevard via HDD from the FPL Easement and Beck Boulevard to just east of Bedzel Drive and Davis Boulevard, under Collier Boulevard. The proposed water main will have ARVs and isolation valves on either side of the HDD. The proposed 24-inch water main will connect to the proposed 36-inch water main at the FPL Easement, the southern terminus of Segment No. 4, and the proposed 20-inch PVC water main at the existing 48-inch Pre-stressed Concrete Cylinder Pipe (PCCP) water main. The existing 48-inch PCCP water main will be utilized as a conduit for the proposed 20-inch water main to extend under Davis Boulevard and ultimately connect to the existing 16-inch water main on the north side of Davis Boulevard. 06Segment 5Segment 6Segment 7Segment 8 TRANSMITTAL LETTER & EXECUTIVE SUMMARY DESIGN AND CONSTRUCTION PLANS OVERVIEW (CONT.) SEGMENT 9 – Collier Boulevard from Davis Boulevard to Business Circle South Segment No. 9 consists of a proposed 20-inch PVC water main to be installed along Collier Boulevard via open cut from Davis Boulevard to Business Circle South. The proposed 20-inch water main will connect to an existing 30-inch water main just east of Bedzel Drive and Davis Boulevard and to an existing 20-inch water main at Collier Boulevard and Business Circle South. Additionally included in Segment No. 9 is the abandonment of the existing 36-inch water main within the median of Collier Boulevard north of the existing 30x10-inch tee. The 36-inch water main will be grouted and abandoned in place from the existing 36/12-inch tee to Business Circle South. From Business Circle South to Davis Boulevard, the existing 36-inch water main will be removed. COLLIER COUNTY’S INPUT QE+ Grady Minor will work diligently for Collier County during all project phases to provide the most economical design and best construction services. The team encourages input from the individuals that will own, operate, and maintain the system after its completion and value feedback from staff at all levels to ensure long-term project satisfaction. QE + Grady Minor strives to ensure that every project completed has a long-lasting positive effect on the county’s utility infrastructure system. MANAGEMENT OF IMPACTS TO SURROUNDING COMMUNITY QE+ Grady Minor has dramatically minimized impacts to the local community by designing the project to use primarily HDD methods. The proposed water mains associated with the I-75 and Collier Boulevard Utility Relocation Project will affect (go through or under) the following individual property owners or entities with jurisdiction: PUBLIC OUTREACH PLAN Community outreach, involvement, and communication is imperative for this design-build project and will be handled in full by Cella Molnar & Associates, Inc. as follows: • Collier County Public Utilities (SCRWTP and existing utility easements) • Collier County ROW and Road Maintenance (ROW use/ permitting and restoration within County ROW) • FPL (Consent Agreement for use of existing FPL easements) • FDOT (I75 Crossing and Coordination with FDOT project) • SFWMD (Jurisdictional Lands and Henderson Canal) • Forest Glen Golf & Country Club • 850 NWN LLC (owner of Lots 11-18 City Gate Commerce Park Phase 3) • White Lakes Common Association, Inc. • Laximi of Naples LLC (Super 8 by Wyndham) • iStorage Self Storage • FLRPT LLC (Business Circle ROW) • A website will be developed and maintained throughout the project. • A comprehensive mailing list of all property owners and tenants in the project area will be prepared. • An email database will be developed and maintained. • Small group or one-on-one meetings will be held with stakeholders in the project area. • A newsletter about the project will be mailed prior to construction. • A preconstruction information meeting will be held for the public to learn about the project, view plans, and have one- on-one discussions with the Design-Build team and Collier County staff. • Project contact cards containing the website address and 24- hour contact information will be distributed to affected parties. • Media releases and roadwatch reports will be provided. • During construction, public inquiries, requests and concerns will be responded to and recorded. • Notifications will be made to businesses and residents regarding water shut-offs and driveway or access changes. • A technical memorandum will summarize the public information activities. 07 TRANSMITTAL LETTER & EXECUTIVE SUMMARY TRAFFIC CONTROL PLAN QE + Grady Minor will follow all FDOT indexes when preparing traffic control plans for the I-75 Utility Relocation project. Bob’s Barricades will prepare, sign, and seal the plans as necessary and the team will incorporate all requirements from the Collier County ROW Department. The MOT for the proposed improvements will not significantly affect traffic, as a majority of the work is either within an FPL easement, being directionally drilled, or is far enough off the edge of travel where the work zone will not require shutting down travel or turn lanes. Three operations that will likely require a lane closure are: The improvements associated with the proposed tie in along Beck Boulevard and Davis Boulevard. The proposed tie in location along Beck Boulevard is within a transition area of the roadway where the roadway begins to transition into a two-lane, two-way road. FDOT Standard Index 102-601, 102-602 or 102-603 will need to be adhered to depending on how far the offset of the work zone is from the edge of travel. The proposed tie in location along Davis Boulevard, which is a six lane divided roadway, will likely require the utilization of FDOT Standard Index 102-611, 102-612 or 102- 613 depending on how far the offset of the work zone is from the edge of travel. Standard Index 102-615 may apply as well since the work will be near the intersection. The work along Collier Boulevard will need to utilize FDOT Standard Index 102-611, 102-612 or 102-613 depending on how far the offset of the work zone is to the edge of travel. MINIMIZE IMPACTS TO MAINTENANCE OF OPERATIONS QE + Grady Minor will work closely with Collier County to minimize impacts and disturbances to facility operations. Tie- ins to existing facilities are currently scheduled to occur out of season. Actual tie-in days will be limited to Tuesday through Thursday with flexibility to perform these tie-ins during off-shift hours. QE will utilize multiple crews to limit duration of tie-ins. DEMOLITION & RESTORATION QE+ Grady Minor will implement over 11,000 LF of pipe installation by Horizontal Directional Drilling (HDD) to minimize impact to the environment, traveling public, local businesses and residences, and recreational facilities (including Forest Glen Golf Club.) it should also be noted that HDD minimizes demolition & restoration and allows for a more time efficient installation. Areas that are open cut will be scheduled at times to minimize impact to the affected public, local businesses and residents, and testing of open cut pipelines will be prioritized so that those segments can be restored quickly upon completion. All areas will be restored to pre-construction conditions or better. QE will utilize in situ material, recycled material, and its resources to make this project less impactful to the environment. All areas of pavement will be removed using a milling machine; millings can then be recycled and used by local asphalt plants. Removed concrete will be crushed off site and recycled as stone bedding. Rock removed from trenches will also be hauled off site and recycled for stone bedding. NOISE & ODOR ABATEMENT The QE+ Grady Minor team does not anticipate noise or odor exceeding acceptable limits for this project. All noise levels will be maintained at or below the allowable Collier County ordinance limits, and the team does not anticipate unacceptable odors from a water main installation. EXTENDED PROJECT WARRANTY In addition to the standard one-year warranty typically provided on all Collier County projects, QE will extend the warranty on labor and materials for the I-75 and Collier Boulevard Utility Relocation Project by one year for a total of two years total warranty. The HDD pipe manufacturer will also provide an extra three years material warranty for a total of five years complete project coverage. This is beneficial for the County and reinforces QE+ Grady Minor’s dedication and interest in this design-build project. SITE SECURITY The QE+ Grady Minor team prioritizes site security; therefore, permanent site fencing will be installed prior to construction, and storage areas will be secured with temporary barriers as needed. With QE’s equipment yard less than ½ mile from the project site, mobilization, storage, and maintenance costs will be reduced. Site access during construction will be controlled, and only authorized personnel will be allowed onsite. Clearly visible signage for permitted access will be furnished. 08 01 02 03 02 Project Team Approach PROJECT TEAM APPROACH QE+ Grady Minor is the local, trusted, and reputable choice for this design-build project. Having completed hundreds of projects with similar components in Southwest Florida, the QE +Grady Minor team is confident in their ability to successfully complete this project on time, within budget, and at high levels of quality. Why QE + Grady Minor? QE recently completed the Collier Boulevard and Golden Gate Canal 36” Water Main Directional Drill within the same geographical footprint as the I-75 and Collier Boulevard Utility Relocation Project. The 36” project was successful, strengthened the company’s familiarity with drilling and excavating through heavy rock in the area, and helped prepare QE +Grady Minor for any geotechnical and environmental issues that may arise on the jobsite. Collier County can be confident in the QE + Grady Minor partnership based on their proven local performance. The county can trust the team to provide a high-quality solution that exceeds standards and deliver timely, cost-effective results. COMPANY OVERVIEWS Quality Enterprises USA, Inc. is a leading construction firm based in Southwest Florida that focuses on major civil, building, and specialized construction in both the private and public sectors. QE has worked in Collier County since 2002 on a variety of infrastructure projects and has a dynamic knowledge and understanding of local construction and regulatory conditions. With the ability to self-perform over 90% of each project, QE maintains job site control and has never been assessed liquated damages for project delays. Established in 1981, Q. Grady Minor & Associates, P.A. provides expert civil consulting services to a wide array of public and private clients throughout Southwest Florida. Fully licensed and insured, the company maintains a strong technical and business foundation and is a local industry leader in civil engineering and land development. Grady Minor has successfully completed a wide range of projects, is locally owned and managed, and supports a team of 58+ employees. Earth View, LLC. (EV) is pleased to partner with the QE+ Grady Minor team for HDD on this design-build project. Founded in 2004, QE’s in-house trenchless technology sister company is one of four companies in the state of Florida to own and operate the American Auger DD-440T Maxi Rig Directional Drill and has successfully completed 29 directional drills on 8 projects for Collier County. The organizational chart on the following page displays all team members for this Design Build. PROJECT TEAM APPROACH 09 • Local experience • Strong relationship with Collier County • Close proximity to the job site (less than ½ mile) • In-house directional drilling capabilities by Earth View, LLC • Knowledgeable with design-build projects • Dedicated to using local resources and businesses (MBE/ DBE) • Thorough understanding of SWFL environmental conditions • Skilled personnel to see project through completion • Trained staff to ensure proper permitting, compliance & safety • Proven partnership on several projects • Extended Project Warranty for this design-build project • All projects completed on time, within budget, and at high levels of quality ORGANIZATIONAL CHART 10 design build team DESIGN-BUILD MANAGEMENT TEAM & STAFFING This design-build project will require significant coordination between QE+ Grady Minor and Collier County. QE+ Grady Minor’s strong and experienced leadership (see following page) will manage the skilled construction workforce and will ensure that the project is completed on time, within budget, and at high levels of quality. The QE+ Grady Minor team is efficiently structured with Louis J. Gaudio serving as the Construction Project Manager and single point of contact for the County. Louis will be available to Collier County at all times and will oversee all construction operations. Louis will be supported by a large and local administrative staff and will work closely with Grady Minor, specifically Justin Frederiksen, throughout this project. The management staff will remain hands on to identify opportunities, address challenges, and mitigate risks. QE ensures that a Superintendent will remain on site with the construction crews at all times, and regular site visits will be performed by other lead staff throughout the process. KEY PERSONNEL COMMITMENT PROJECT TEAM APPROACH 15 NAME FIRM ROLE COMMITMENT TO COUNTY’S PROJECT PRECONSTRUCTION CONSTRUCTION Louis J. Gaudio Harlan Sawyer Paul J. Moriarty Margarita Negron Isa Carreras Justin Frederiksen Daniel Flynn Sally Goldman Alex Dunko Donald Saintenoy Rick Featherstone John Daniel Joseph Townsend Alan Hart Brian Dorwart Nicholas Strater Construction Manager Estimator Superintendent Manager of Health and Safety Project Administrator/ EEO Compliance Officer Design Build Project Manager DOT Coordinator Project Engineer Project Engineer Survey Project Manager Quality Assurance/ Quality Control Directional Drill Project Manager Directional Drill Superintendent/ Operator Chemical Engineer Senior Consultant Senior Geologist QE QE QE QE QE Grady Minor Grady Minor Grady Minor Grady Minor Grady Minor Grady Minor Earth View Earth View Earth View Brierley Brierley 65% 100% 30% 30% 20% 80% 80% 80% 80% 30% 40% 30% 30% 30% 65% 65% 100% 40% 100% 80% 80% 80% 50% 50% 50% 60% 70% 80% 100% 100% 70% 50% 11 NAME/ROLE KEY QUALIFICATIONS 25+ years of Construction industry experience Maintains a long-standing relationship with Collier County and is familiar with local conditions, regulations, personnel, etc. Experience managing projects ranging from $500K to $40 Million for Army Corps of Engineers, Charlotte County, City of Naples and of Marco Island, FDOT, various Collier County divisions, Naples Airport Authority, and the Town of Fort Myers Beach to list a few Oversees all QE utility, roadway and bridge projects in the State of Florida and South Carolina Louis will provide overall project coordination • • • • • Vice President Superintendent Directional Drill Project Manager Design Project Manager Design Project Engineer FDOT Coordinator Construction Project Manager Louis J. Gaudio paul j. moriarty john daniel justin frederiksen Alex Dunko, E.I. dANIEL flynn, p.e. 12 KEY PERSONNEL 30+ years of Construction industry experience Extensive background working with Collier County’s Utility Department Certified by the US Army Corps of Engineers, Quality Management for Contractors, and FDOT Maintenance of Traffic Paul will provide daily onsite coordination • • • • 15+ years of Directional Drilling experience in both the utility and oil/gas industries with drills of pipe up to 42” Highlighted Collier County project: installation of the 36” HDPE Watermain crossing the Golden Gate Canal at Collier Boulevard, which lies within the same footprint as this Design Build project John will provide oversight, management, and guidance to Earth View, LLC personnel • • • 17+ years of Engineering and Construction experience in the State of Florida Engineer of Record on various small and large utility projects in Collier County Managed various Municipal Projects, which required: preparation of master planning documents, engineering designs/ plans/ and specifications, project permitting, bidding assistance, contractor selection, and general construction coordination Served as the Deputy Director for the City of Naples where he performed: rate studies, annual reports of utility operations, grant/loan program administration, and assisted in developing and administering the City of Naples Utility Standards, Utility Department annual budgets, and standard utility policies • • • • 6+ years of industry experience with direct involvement on water, wastewater, and site development projects in South Florida Ability to design and construct large and small diameter transmission water main components, lead and coordinate utility construction projects, plan and evaluate Wastewater Reclamation facilities, and perform site civil engineering processes. Trained as a Civil Engineering Site Inspector (CEI) • • • 13+ years of industry experience Works with the FDOT, Collier County, multiple counties and cities in Florida to produce roadway and sidewalk construction plans Extensive design background in projects ranging from minor resurfacing/ widening, to roadway reconstruction, to multimodal complete streets throughout the state of Florida Engineering experience in Maintenance of Traffic (MOT), signing/ paving marking, and horizontal and vertical geometry designs, super-elevation roadway layouts, and sidewalks/ intersection projects FDOT certified in Advanced MOT • • • • • As one of the largest local utility contractors, QE is prepared for the I-75 and Collier Boulevard Utility Relocation Project. With over 200 employees, including ten pipe installation crews, the company has a large and skilled workforce and is proud to celebrate 50 years of service this year. QE is knowledgeable of local conditions, has the capacity to bond this project, can acquire materials in a timely fashion, and will provide machinery from the company’s 250+ piece heavy equipment fleet. PROJECT TEAM APPROACH 13 CATEGORY QTY. Broom Tractors Crawler Cranes Crushing & Screening Equipment Dozers Dump Trucks Epi Rock Drum Cutter Excavators Excavators with Hammers Fusing Machine Graders Horizontal Directional Drilling Rigs Lowboys 05 02 10 03 08 01 35 03 03 02 02 05 CATEGORY QTY. Loaders Milling Machine Articulated Truck Asphalt Pavers Rollers Rubber Tire Excavator Skid Steer Sheet Pile Vibratory Hammer Trailers Tractors VAC Truck, Tankers, Mud Reclaimer QE Mechanics & Lube Trucks 30 02 01 03 14 01 04 02 38 05 06 06 CORPORATE OFFICE LOCATION Quality Enterprises, USA, Inc. Approximately 0.5 miles from proposed project location 3494 Shearwater Street Naples, FL 34117 239.435.7200 qualityenterprisesusa.com CIVIL ENGINEERING LOCATION Q. Grady Minor & Associates, P.A. Approximately 21 miles from proposed project location 3800 Via Del Rey Bonita Springs, Florida 34134 Phone: 239.947.1144 Fax: 239.947.0375 gradyminor.com location QE’s corporate office and equipment yard are located less than ½ mile from the project site; therefore, key personnel can be on location within minutes should the need arise. The corporate office will serve as the central meeting place between QE+ Grady Minor and Collier County staff, and meetings can be easily followed by visits to the project site if requested. The close location will also allow for prompt equipment mobilization, which result in significant cost savings for Collier County. A map has been provided to show the distance between the project site and QE+ Grady Minor. KEY RESOURCES PROJECT TEAM APPROACH 14 SCHEDULE QE + Grady Minor has developed a master schedule and segment/ task-specific schedules for this design- build project to ensure project success from day one. The proposed schedule is approximately 14 months and includes approximately 7 months for design and permitting and 9 months of construction (a portion of which will occur concurrently with various design and permitting phases). This project includes approximately 20,000 linear feet of new water main piping and associated appurtenances, with approximately 5,740 linear feet of water main piping to be grouted and abandoned, and approximately 5,700 linear feet of water main piping to be removed, broken into nine segments. New landscaping is scheduled to be installed on the outside of the SCRWTP in summer 2020 and thus the proposed water main within Segment No. 1 and No. 2 will be completed by May 31, 2020. SEGMENTS OVERVIEW SEGMENT 1 – SCRWTP to City Gate Boulevard South Segment No. 1 includes approximately 2,238 linear feet of water main from the SCRWTP to City Gate Boulevard South by Open Cut. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. It is not anticipated that this segment will require environmental permitting. Construction of segment 1 is anticipated to take 30 days. SEGMENT 2 – White Lake Boulevard from City Gate Drive to FPL Easement Segment No. 2 includes approximately 2,875 linear feet of water main along White Lake Boulevard and City Gate Boulevard South by Open Cut. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. It is not anticipated that this segment will require environmental permitting. Construction of segment 2 is anticipated to take 41 days. SEGMENT 3 – Within FPL Easement from City Gate Boulevard South to White Lake Boulevard Segment No. 3 includes approximately 1,287 linear feet of water main from the City Gate Boulevard South (the southern end of Segment No. 1) to White Lake Boulevard (the southeastern terminus of Segment No. 2) by Open Cut. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. Segment 3 has a previously identified wetland near White Lake Boulevard. This segment may require environmental permitting, if the wetland will be impacted and thus the permitting of this segment may take 6-8 months and as a result would be the scheduled driver. Once permits are received, construction of segment 3 is anticipated to take 20 days. SEGMENT 4 – Within FPL Easement from White Lake Boulevard to Beck Boulevard Segment No. 4 includes approximately 2,033 linear feet of water main from White Lake Boulevard and the FPL Easement to Beck Boulevard and the FPL Easement by Horizontal Directional Drill. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. It is not anticipated that this segment will require environmental permitting. Once permits are received, construction of segment 4 is anticipated to take 25 days. SEGMENT 5 – Within FPL Easement from Beck Boulevard to Forest Glen Boulevard Segment No. 5 includes approximately 3,368 linear feet of water main from Beck Boulevard and the FPL Easement to Forest Glen Boulevard and the FPL Easement by Horizontal Directional Drill. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. Segment 5 has previously identified wetlands along the proposed project route. The team proposes this segment to be installed via HDD and every attempt will be made to avoid wetlands by drilling under them. However, this segment may require environmental permitting if the wetland will be impacted, and thus the permitting of this segment may take 6-8 months and as a result would be the scheduled driver. Once permits are received, construction of segment 5 is anticipated to take 30 days. PROJECT TEAM APPROACH 15 SEGMENTS OVERVIEW (CONT.) SEGMENT 6 – Within FPL Easement from Forest Glen Boulevard to the South End of Forest Glen Golf & Country Club Segment No. 6 includes approximately 2,089 linear feet of new water main and approximately 2,100 linear feet of replaced raw water main from Forest Glen Boulevard and the FPL Easement to the south end of Forest Glen Golf & Country Club and the FPL Easement both by Horizontal Directional Drill. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. Segment 6 has previously identified wetlands along the proposed project route. The team proposes the majority of this segment to be installed via HDD and every attempt will be made to avoid wetlands and HDD under them. However, this segment may require environmental permitting, if the wetland will be impacted and thus the permitting of this segment may take 6-8 months and as a result would be the scheduled driver. Once permits are received, construction of segment 6 is anticipated to take 50 days. SEGMENT 7 – Within Collier County Easement from South End of Forest Glen Golf & Country Club to Collier Boulevard Segment No. 7 includes approximately 1,131 linear feet of water main from the south end of Forest Glen Golf & Country Club and the FPL Easement to the eastern ROW of Collier Boulevard, just east of the SFWMD’s Henderson Canal by Horizontal Directional Drill. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. It is not anticipated that this segment will require environmental permitting. Once permits are received, construction of segment 7 is anticipated to take 20 days. SEGMENT 8 – Beck Boulevard/Davis Boulevard from the FPL Easement to East of Bedzel Drive Segment No. 8 includes approximately 1,751 linear feet of water main from the FPL Easement and Beck Boulevard to just east of Bedzel Drive and Davis Boulevard, under Collier Boulevard, by Horizontal Directional Drill. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. It is not anticipated that this segment will require environmental permitting. Construction of segment 8 is anticipated to take 20 days. SEGMENT 9 – Collier Boulevard from Davis Boulevard to Business Circle South Segment No. 9 includes approximately 2,909 linear feet of water main by Open Cut and approximately 2,900 linear feet of existing water main to be removed/abandoned along Collier Boulevard via open cut from Davis Boulevard to the south side of Forest Glen Golf & Country Club. Once QE + Grady Minor receives a NTP from the county, the team will prepare 60% design plans within 30 days, 90% design within an additional 14 days, and 100% design plans within an additional 7 days. It is not anticipated that this segment will require environmental permitting. Construction of segment 9 is anticipated to take 40 days. 16 QUALITY ENTERPRISES USA, INC. + GRADY MINOR | COLLIER COUNTY DESIGN BUILD i-75 and collier blvd utility relocation project 17 QUALITY ENTERPRISES USA, INC. + GRADY MINOR | COLLIER COUNTY DESIGN BUILD i-75 and collier blvd utility relocation project PROJECT TEAM APPROACH 18 CRITICAL PATHS QE+ Grady Minor has established the following Critical Path Method (CPM) to ensure successful, economical, and non- disruptive design, permitting, and construction phases for this design-build project. As expected, the 14-month timeframe desired by the county will rely heavily on permitting. QE+ Grady Minor will diligently pursue permitting, noting that additional contract time may be required due to permit delays beyond the team’s control. In an attempt to mitigate permitting time, the team has elected to provide Horizontal Directional Drilling (HDD) installation methods where feasibly possible. The critical path of the schedule flows through permitting and through the HDD segments. The critical path of the schedule flows through permitting and the Open Cut segments. The current schedule is based on sequentially working Open Cut and HDD Segments. With the ability to bring on additional crews and equipment, QE has the ability to work open cut and HDD segments concurrently as allowed by permitting. Additionally, should permitting allow, we also have the flexibility to modify open cuts to HDD. Currently, the schedule has the majority of the construction activities occurring out of season, with in-season work limited to Segments 1 and 4. These segments will not impact any seasonal traffic or local businesses. Connection to existing facilities and water mains will also occur out of season. The QE+ Grady Minor team will coordinate closely with Collier County on the timing of the connections and Cella Molnar will communicate public information with any businesses/residents on system interruptions. QE will be flexible in performing these tie-ins to coincide with low demand on the county’s system. Multiple crews will be utilized to perform multiple tie-in points concurrently if necessary. The project schedule shows the CPM in red, which reflects the proposed tie-in schedule for each segment. Provided below is a more detailed list of tie-in locations. Connection to Existing Water Main Restoration will be prioritized by segment. Implementing HDD will minimize restoration required, except for entry/exit pit locations. Upon completion of pipe installation per segment, pipe will be tested so that restoration can occur immediately thereafter. • City Gate Boulevard (East) 12” Water Main Connection • Beck Boulevard (East) 10” Water Main Connection • Beck Boulevard (West) 10” Water Main Connection • Forest Glen Boulevard (East) 10” Water Main Connection • Forest Glen Boulevard (West) 10” Water Main Connection • Connect to 30” RAW Water Main • Collier Boulevard (East) Connect to 36” Water Main • Collier Boulevard (West) Connect to 36” Water Main • White Lake Boulevard (South) Connect to 8” Water Main • White Lake Boulevard (South) Connect to 20” Water Main • White Lake Boulevard (South) Connect to 6” Fire Main Assembly • White Lake Boulevard (South) Connect to 8” Water Main • City Gate Boulevard Reconnect 8” Fire Assembly • City Gate Boulevard Reconnect 8” Water Main • City Gate Boulevard Reconnect 8” Water Main • City Gate Boulevard (East) Reconnect 36” Water Main • City Gate Boulevard (West) Reconnect 36” Water Main • White Lake Boulevard (Southwest) Connect to 20” Water Main • White Lake Boulevard (Northwest) Connect to 20” Water Main • Shaw Boulevard (North) Connect to 8” Water Main • Davis Boulevard (West) Connect to Water Main • Beck Boulevard (East) 36” Water Main Connection • Beck Boulevard (West) 36” Water Main Connection • Collier Boulevard (North) 20” Water Main Connection • Collier Boulevard (South) 20” Water Main Connection • Business Circle N. (North) 12” Water Main Connection • Business Circle N. (West) 10” Water Main Connection 03 Technical Information TECHNICAL INFORMATION 19 DESIGN AND CONSTRUCTION STANDARDS The improvements associated with the I-75 and Collier Boulevard Utility Relocation Design-Build project will adhere to the following standards: • Collier County Utility Standards, Details, and Specifications • Florida Department of Environmental (FDEP) and the Florida Administrative Code requirements and standards • South Florida Water Management (SFWMD) requirements and standards • 10 State Standards • Florida Department of Transportation (FDOT) requirements and standards However, as the water mains associated with this project are transmission mains in nature, QE+ Grady Minor would like the County to consider the following Utility Deviations from Collier County’s Utility Standards: • Fire hydrant every 500-foot within public Right-of-Ways (ROW), but no fire hydrants within the FPL Easement. • Isolation valves every 1,000 feet within public ROWs and at all connections to existing/proposed water mains, but valves every 2,000 feet within the FPL easement. • Two-foot (wall-to-wall) setback from CUE line within the FPL Easement, south of Lot 16 of City Gate Commerce Park Phase 3, instead of the 5-foot minimum per Collier County’s Utility Design Criteria (Section 1.1). QE + Grady Minor understand that the County prefers no vertical deflections on the large water mains proposed with this project and the team intends to adhere to this preference whenever possible. However, it may be necessary to deflect the proposed mains due to existing utility conflicts that either cannot be deflected (for example gravity mains) or if deflection of the existing mains will negatively affect the existing mains. DEVIATIONS FROM DESIGN CRITERIA PACKAGE Step 2 of the I-75 and Collier Boulevard Utility Relocation Design-Build Project includes a Design Criteria Package, dated March 27, 2019. For the most part, QE + Grady Minor’s proposed design and construction for this project will adhere to the criteria in this document. However, Item No. 2 of Addendum No. 8, dated July 10, 2019, allows for deviations from the methods of construction presented in the Design Criteria Manual to “provide the best value to Collier County for each segment in the Design Criteria Package”. As a result of the flexibility provided in Addendum No. 8, QE+ Grady Minor has chosen to utilize Horizontal Directional Drilling (HDD) in lieu of open cut in Segments 5 and 6. Based upon the January 2011 drawings for the South County Regional Water Treatment Plant (SCRWTP) SRO Wellfield Pipeline Repairs, Phase 1, there are a significant amount of wetlands within Segments 5 and 6. The use of HDD installation with High Density Polyethylene Pipe (HDPE) in these two segments have been proposed to minimize wetland impacts. QE + Grady Minor believes that this change from open cut to HDD installation methods will save a significant amount of time and effort in permitting these segments. However, impact to wetlands depicted in the northern portion of Segment 6 will likely be unavoidable due to the 30- inch raw water main replacement and the requirement to connect to the existing raw water well approximately 400 feet south of Forest Glen Boulevard. Similarly, impact to wetlands depicted in the southern portion of Segment 6 will likely be unavoidable due to the connection necessary to Segment 7 at the southern end of Forest Glen Golf & Country Club. To account for the inside diameter difference between equally sized PVC and HDPE pipe, in Segment 5 and 6, QE + Grady Minor has depicted an increase in the size of the proposed pipe, 36-inch HDPE instead of 30-inch PVC in these two segments. TECHNICAL INFORMATION 20 Additionally, the January 2011 drawings for the SCRWTP SRO Wellfield Pipeline Repairs, Phase 1, depict a small wetland area in the southern portion of Segment 3. QE + Grady Minor is not proposing to HDD this section, but may request to do so depending on feedback from permitting agencies. PIPE MATERIAL TYPE, THICKNESS, AND CLASS For the I-75 Utility Relocation Design-Build project, QE+ Grady Minor proposes the following pipe material type, thickness, and class for the identified segments: A brief description of the nine segments associated with the I-75 and Collier Boulevard Utility Relocation Design-Build project is provided below. However, a more detailed description of the segments can be found in Section 1: Transmittal Letter & Executive Summary. SEGMENT 1 – SCRWTP to City Gate Boulevard South Segment No. 1 consists of a proposed 30-inch PVC water main to be installed via open cut installation from the SCRWTP to City Gate Boulevard South. Beginning on the northwest side of the SCRWTP potable water ground storage tanks, the proposed 30-inch water main will connect to the existing 36-inch water main and extend east through the SCRWTP site and ultimately to a 15-foot wide Collier County Utility Easement (CUE) within Lot 11 of City Gate Commerce Park Phase 3. The 30-inch water main will extend through the 15-foot CUEs through Lots 11-16 of the CUE. Near the Lot 16/17 line, an existing 30-inch raw water main leaves the SCRWTP property and enters an existing 15-foot wide CUE, therefore, the proposed 30-inch water main be shifted to the east and installed east of the existing 30-inch raw water main. SEGMENT 2 – White Lake Boulevard from City Gate Drive to FPL Easement Segment No. 2 consists of new 10 and 24-inch water main piping and associated appurtenances along White Lake Boulevard and City Gate Boulevard South within three separate segments as described below. Segment No. 2.1: A 24-inch PVC water main installed via open cut along White Lake Boulevard from City Gate Drive to City Gate Boulevard South. The new 24-inch water main will replace an existing 20-inch water main that will be grouted and abandoned in place. Segment 2.2: A 24-inch PVC water main installed via open cut along City Gate Boulevard South from White Lake Boulevard to the FPL Easement that will connect to the proposed 24-inch water main at White Boulevard and to the proposed 30- inch water main at the southern terminus of Segment No.1, within the FPL easement. This 24-inch water main will replace an existing 16-inch water main along City Gate Boulevard South that will be grouted and abandoned in place. Segment No. 2.3: A 10-inch PVC water main installed via open cut along White Lake Boulevard from just south of the southern property line of 3807 White Lake Boulevard to the FPL Easement. The new 10-inch water main will replace an existing 10-inch water main that will be grouted and abandoned in place. PIPE SIZE (IN)MATERIAL DIMENSION RATIO (DR) PRESSURE CLASS (PSI) INSIDE DIAMETER (IN) MINI WALL THICKNESS (IN) SEGMENT(S) NO. 10 20 24 24 30 30 36 36 PVC PVC PVC HDPE PVC HDPE PVC HDPE 18 18 18 11 18 11 21 11 235 235 235 200 235 200 200 200 11.10 19.06 22.76 20.82 28.23 25.83 34.43 30.91 0.617 1.200 1.433 2.345 1.778 2.909 1.824 3.482 02 09 02 08 01 07 03 04, 05, 06 TECHNICAL INFORMATION 21 SEGMENT 3 – Within FPL Easement from City Gate Boulevard South to White Lake Boulevard Segment No. 3 consists of a proposed 36-inch PVC water main to be installed via open cut installation from the City Gate Boulevard South (the southern end of Segment No. 1) to White Lake Boulevard (the southeastern terminus of Segment No. 2). SEGMENT 4 – Within FPL Easement from White Lake Boulevard to Beck Boulevard Segment No. 4 consists of a proposed 36-inch HDPE water main to be installed via HDD from White Lake Boulevard and the FPL Easement to Beck Boulevard and the FPL Easement, under I-75 and under the east parking lots of Super 8 Motel and iStorage Self Storage. SEGMENT 5 – Within FPL Easement from Beck Boulevard to Forest Glen Boulevard Segment No. 5 consists of a proposed 36-inch HDPE water main to be installed via HDD from Beck Boulevard and the FPL Easement to Forest Glen Boulevard and the FPL Easement. The proposed water main will require the crossing of the South Florida Water Management District’s (SFWMD) Henderson Canal and the entrance drive to Golden Gate Fire Station No. 72, ultimately into Forest Glenn Golf & Country Club property. SEGMENT 6 – Within FPL Easement from Forest Glen Boulevard to the South End of Forest Glen Golf & Country Club Segment No. 6 consists of a proposed 36-inch HDPE water main to be installed via HDD from Forest Glen Boulevard and the FPL Easement to the south end of Forest Glen Golf & Country Club and the FPL Easement. The use of HDD installation is proposed to avoid wetland impacts and will be accomplished with 36-inch HDPE and each HDD will include ARVs and isolation valves on either side of each HDD. Additionally included in Segment No. 6 is the replacement of the existing 30-inch fusible PVC raw water main from Forest Glen Boulevard to the south end of the Forest Glen Golf & Country Club, which will require the connection to one existing raw water well. SEGMENT 7 – Within Collier County Easement from South End of Forest Glen Golf & Country Club to Collier Boulevard Segment No. 7 consists of a proposed 30-inch HDPE water main to be installed via HDD from the south end of Forest Glen Golf & Country Club and the FPL Easement to the eastern ROW of Collier Boulevard, just east of the SFWMD’s Henderson Canal. SEGMENT 8 – Beck Boulevard/Davis Boulevard from the FPL Easement to just East of Bedzel Drive Segment No. 8 consists of a proposed 24-inch HDPE water main to be installed along Beck Boulevard/Davis Boulevard via HDD from the FPL Easement and Beck Boulevard to just east of Bedzel Drive and Davis Boulevard, under Collier Boulevard. The existing 48-inch PCCP water main will be utilized as a conduit for the proposed 20- inch water main to extend under Davis Boulevard and ultimately connect to the existing 16-inch water main on the north side of Davis Boulevard. SEGMENT 9 – Collier Boulevard from Davis Boulevard to Business Circle South Segment No. 9 consists of a proposed 20-inch PVC water main to be installed along Collier Boulevard via open cut from Davis Boulevard to Business Circle South. Additionally included in Segment No. 9 is the abandonment of the existing 36-inch water main within the median of Collier Boulevard north of the existing 30x10-inch tee. The 36-inch water main will be grouted and abandoned in place from the existing 36x12-inch tee to Business Circle South. From Business Circle South to Davis Boulevard, the existing 36-inch water main will be removed. TECHNICAL INFORMATION 22 PERMITTING The QE +Grady Minor’s experience and knowledge of county requirements will be beneficial when preparing submittals and responses. At the 60% design stage, Grady Minor will prepare the required permit applications and supporting documentation: An Application for a Specific Permit to Construct PWS Components (form 62-555.900(1)) from the FDEP for all segments associated with this project. To streamline the permitting process, Grady Minor will submit one permit to the FDEP for the entire potable water improvements associated with this project. Collier County ROW permit for Segments No. 2, 3, 4, 5, 8, & 9 will be required. Each segment will be applied for separately as each permit is good for 6 months from issuance with the ability for the contractor to extend the permit as needed 3 months at a time. Recently Grady Minor received a 2-year permit from Collier County ROW for the West Goodlette Frank Road Joint Stormwater Sewer project due to the construction of the project taking over 6 months with one single Contractor. Grady Minor will pursue longer ROW permit durations to reduce the amount of permit extensions required for this project. A Notice of Intent (NOI) to use the Generic Permit for Discharge of Ground Water from Dewatering Operations, per Rule 62-621.300(2), F.A.C. from the FDEP. FDOT Utility Permit (Rule 14-46.001 F.A.C.) Environmental Permitting: The project will require an Environmental Resource Permit (ERP) from the Florida Department of Environmental Protection (FDEP). It is anticipated FDEP will process the ERP (not the South Florida Water Management District) since it is a utility line. As part of the FDEP permitting, the Florida Fish and Wildlife Conservation Commission may provide comments on the ERP application. If there will be wetland impacts (which is likely given the proposed alignment), then a U.S. Army Corps of Engineers (Corps) Section 404 permit will be required. As part of the Corps permit review, consultation for threatened and endangered species with the U. S. Fish and Wildlife Service (USFWS) will be required. It is anticipated that the species that will need to be addressed include Florida Panther, Wood Stork, and Eastern Indigo Snake as long as the work is within the existing cleared FPL easement. If impacts are proposed to forested areas, then additional listed species including the red-cockaded woodpecker and Florida bonneted bat will need to be addressed as well. Note that red-cockaded woodpeckers and bonneted bats have been previously document in the vicinity of this project. The necessary environmental permitting will likely be what keeps this project from being designed, permitted and constructed within the 1-year schedule defined in the project requirements. It is estimated that FDEP permitting for the ERP will take 6 to 8 months. If the proposed wetland impacts are minimal and qualify for a Corps Nationwide permit, then Corps permitting can possibly accomplished within the same 6 to 8 months. If wetland impacts are greater than 0.5 acre, then a Corps individual permit will be required and will take approx. 8 to 12 months. This is assuming all activities are within the existing cleared FPL easement. Note that if construction activities require impacts to forested areas, this is likely to require an additional level of consultation with the USFWS and may take additional 4 months (total 12 to 16 months) for Corps permitting. If QE+ Grady Minor is selected for this design-build project, Passarella & Associates, Inc. (Passarella) will reach out to the FDEP and Corps to schedule a pre-application meeting to discuss the project/ likely impacts to environmentally sensitive lands immediately after receiving a NTP from the County. Passarella has significant environmental permitting experience in South Florida and has worked along the I-75 and Collier Boulevard Utility Relocation Design-Build project route, as the company provided the environmental permitting associated with the SCRWTP Wellfield expansion project. The preliminary plans developed as part of QE + Grady Minor’s response (provided in this section) can be reviewed immediately with permitting agencies, helping to expedite the process. • • • • • TECHNICAL INFORMATION 23 SCADA AND INSTRUMENTATION & CONTROLS Collier County has completed hydraulic modeling using the proposed water line sizes as detailed in the Design Criteria Package. As understood, if the Design-Build team alters the proposed design, the Design-Build team will be responsible for preparing a hydraulic model for County acceptance to ensure the system meets operating requirements, including SCADA and Instrumentation & Controls requirements. While QE+ Grady Minor have proposed pipe size and material changes in Segments 5 and 6, these changes are not anticipated to negatively affect the hydraulic conditions of the water system, as the team has adjusted the pipe sizes to match or exceed the inside diameters proposed in the Design Criteria Package. CONSTRUCTION PLANS QE + Grady Minor’s preliminary Construction Plans for the I-75 and Collier Boulevard Utility Relocation Design-Build project can be found at the end of this section, Section 3: Technical Information. These plans include the team’s proposed pipe size and material within all nine segments and provide the general alignment of the proposed water mains. The plans have been used to generate QE+ Grady Minor’s proposed project schedule and Guaranteed Maximum Price. TECHNICAL INFORMATION 24 Impact to any fence or gates, including Forest Glen Blvd. (removed and replace or other?) Response: All fence and/or gates impacted during the construction of the project will be restored to meet the preconstruction condition of the affected fence and/ or gate. If a fence and/or gate cannot be replaced on the same day it is impacted, a temporary fence and/or gate will be installed at the end of the day to secure the protected area. Impact to Forest Glen Blvd (Traffic control, one lane? Repave? Protective barriers, cones keep carts to avoid the areas, others?) Response: QE + Grady Minor propose Segments 5 & 6 as Horizontal Directional Drills. Each drill will terminate at the connection point to the existing 10” PVC WM. The eastbound entrance lane to Forest Glen at this location is 20 ft. wide, distance from curb line to cart path is approximately 18 ft. QE+ Grady Minor propose to provide an 11 ft. vehicular lane to allow movement of traffic without interruption from construction activity. QE + Grady Minor feel that the distance to the cart path is sufficient enough to allow the team to perform this tie-in with no interference to the cart path. QE will follow applicable FDOT Maintenance of Traffic Standards. Same day restoration Response: It is not anticipated that travel lanes and cart paths will be affected within Forest Glen Golf & Country Club by construction associated with this project; therefore, restoration will be completed at the completion of the tie-in. However, if travel lanes and/or cart paths are affected, they will be restored and secured at the end of each day so that trenches are backfilled or covered. Impact to Cart Paths (shown on the attached aerial photo). Response: See item 2 – Cart paths are not anticipated to be impacted. Address concerns with the southern portion of the easement which runs right along a tee, cart path, and fairway. Plan must address (see diagrams below): a) Please note an open cut can negatively impact members. If proposing to open cut, plan must ensure members are not negatively impacted. Response: As previously indicated, QE+ Grady Minor propose to use HDD for Segment 5 & 6 in order to minimize impacts to Forest Glen Golf & Country Club. Although the team proposes HDD to these segments, close coordination will take place with Forest Glen Golf & Country Club when the pipes are pulled through the drill hole. The pulling of the pipe for these segments can be accomplished in one shift, out of season and/or at night. b) Ensure construction is not during season or planned such that there is no impact or effect on golfers (booked from sunrise to sunset every day during season). Response: As depicted in QE+ Grady Minor’s schedule, work within segments 5 & 6 is anticipated to be accomplished during the off season. c) Limit rerouting cart paths Response: Rerouting of cart paths is not anticipated. d) No disturbance to the tee box and cart path just north of Forest Glen Blvd. Response: Disturbance to tee box and cart path is not anticipated due to the planned utilization of HDD installation. e) Limit disturbance to Hole 10, which is located just south of Forest Glen Blvd and runs along the easement area with portions of the cart path located within the easement. The impacted area runs for about 1,100 feet south of Forest Glen Blvd. Response: HDD will be utilized to limit disturbance to Hole 10. The pipe to be fused and pulled will be placed within the FPL easement to the east of Hole 10. Equipment used to fuse pipe does not create any noise that will impact players. FOREST GLEN GOLF & COUNTRY CLUB IMPACT Addendum No. 8 included specific questions to address concerning impact to the Forest Glen Golf & Country Club, provided below are the questions and our responses: 01 02 03 04 05 RevisionsLocation MapPrepared by:GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380GradyMinor I-75 and Collier Boulevard Utility Relocation Project(Preliminary Design)Located in Collier County, Collier CountySections 34 & 35, Township 49 South, Range 26 East and Sections 2 & 3, Township 50 South, Range 26 East I-75 and Collier Boulevard Utility Relocation Project (Preliminary Design)----Plans Prepared For:Engineering and Project Management DivisionPrincipal Project Manager: Ben Bullert, P.E.3339 Tamiami Trail E.Suite 303Naples, FL 34112Tel: (239) 252-4233Fax: (239) 252-3989INDEX OF SHEETSDwg. No.Sheet Description1COVER SHEET2OVERALL AERIAL MAP3WATER MAIN SEGMENT 1 - STA. 0+00 TO 16+004WATER MAIN SEGMENTS 1, 3, 4, 5 - STA. 16+00 TO 66+005WATER MAIN SEGMENT 5, 6, 7 - STA:66+00 TO 111+006WATER MAIN SEGMENT 7 - STA:111+00 TO ENDWATER MAIN SEGMENT 2.1 - STA:0+00 TO END7WATER MAIN SEGMENT 2.2 - STA. 0+00 TO END8WATERMAIN SEGMENT 8 - STA. 0+00 TO END9WATERMAIN SEGMENT 9 - STA:100+00 TO ENDPROJECTLOCATION GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.43800400'800'200'SCALE: 1" = 400'WAL-MART MATCHLINE STA:16+00 SEE SHEET 4GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380040'80'20'SCALE: 1" = 40'CITY GATE BLVD36"X30" TEE AT INTERSECTION36" GV AND CONNECT TO EX. 36" DIP WM - NORTH30" GV AND 30" PVC WM SEGMENT 1 - EAST36" GV AND CONNECT TO EX. 36" DIP WM - SOUTHKEY MAPPROPOSED 30" GV LOT 17 MATCHLINE STA:28+00 MATCHLINE STA:40+00 MATCHLINE STA:53+00MATCHLINE STA:66+00 MATCHLINE STA:40+00MATCHLINE STA:53+00 GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380040'80'20'SCALE: 1" = 40'040'80'20'SCALE: 1" = 40'040'80'20'SCALE: 1" = 40'W H I T E L A K E B L V D I75 W E S T B O U N D I75 E A S T B O U N DI75 ON-RAMPI7 5 O F F - R A M PHENDERSONCANAL ··············4.24.34.4MATCHLINE STA:16+00 - SEE SHEET 3 MATCHLINE STA:28+00 040'80'20'SCALE: 1" = 40'CITY GATEBLVD S·····4.1BECK BLVDKEY MAP 5.45.35.25.1MATCHLINE STA:78+00 MATCHLINE STA:91+00MATCHLINE STA:104+00MATCHLINE STA:111+00 - SEE SHEET 6MATCHLINE STA:91+00MATCHLINE STA:104+00 GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380040'80'20'SCALE: 1" = 40'040'80'20'SCALE: 1" = 40'040'80'20'SCALE: 1" = 40'FOREST GLEN BLVD··MATCHLINE STA:78+00 MATCHLINE STA:66+00 - SEE SHEET 4 040'80'20'SCALE: 1" = 40'·····KEY MAP·· 6.16.26.3MATCHLINE STA:111+00 GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380040'80'20'SCALE: 1" = 40'····COLLIER BLVDCOLLIER BLVDCEDAR HAMMOCKMAINTENANCEFACILITY040'80'20'SCALE: 1" = 40'····040'80'20'SCALE: 1" = 40'CITY GATE BLVD SWHITE LAKE BLVD····WHITE LAKE BLVD····CITY GATE BLVD S ·····CITY GATE DR····MATCHLINE STA:7+10 - SEE BELOW LEFTMATCHLINE STA:7+10 - SEE ABOVE RIGHT····KEY MAP MATCHLINE STA:6+50 GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380MATCHLINE STA:6+50 040'80'20'SCALE: 1" = 40'040'80'20'SCALE: 1" = 40'INCOME LANEWHITE LAKE BOULEVARDWHITE LAKE BOULEVARDSHAW BLVD·············KEY MAP7.27.1 MATCHLINE STA:12+00 GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380040'80'20'SCALE: 1" = 40'···MATCHLINE STA:12+00BECK BOULEVARDDAVIS BOULEVARDBECK BOULEVARDCOLLIER BOULEVARD040'80'20'SCALE: 1" = 40'·····STA:51+00 - SEE SHEET 4STA:53+50 - SEE SHEET 4·········KEY MAP8.18.2 GradyMinorCivil Engineers●Land Surveyors●Planners●Landscape ArchitectsCert. of Auth. EB 0005151Cert. of Auth. LB 0005151Business LC 26000266Q. Grady Minor and Associates, P.A.3800 Via Del ReyBonita Springs, Florida 34134 Bonita Springs: 239.947.1144www.GradyMinor.com Fort Myers: 239.690.4380040'80'20'SCALE: 1" = 40'BUSINESS CIRCLE SCOLLIER BOULEVARDMATCHLINE STA:106+50MATCHLINE STA:106+50MATCHLINE STA:117+00 MATCHLINE STA:118+00 COLLIER BOULEVARDDAVIS BOULEVARD WAL-MART ENTRANCEBUSINESS CIRCLE NCOLLIERBOULEVARD040'80'20'SCALE: 1" = 40'040'80'20'SCALE: 1" = 40'·····KEY MAP9.19.29.3