Agenda 01/29/2008 Item #16D 6 Agenda Item No. 1606 January 29, 2008 Page 1 of 5 EXECUTIVE SUMMARY Approve change order #10 in the amount of $35,945.00 for additional construction administration, SFWMD well permit and modeling study, site visits by e]ectrical engineer, reduced water meter size, pool lighting & night use certification and one year warranty inspection to contract #99-2947, "Implementation of a Master Plan for the North Naples Regional Park." OBJECTIVE: To extend construction administration services for the soccer & ball field completion, SFWMD well permit and modeling study, site visits by electrical engineer, water meter to reduce meter size in pool pump #1, pool lighting certification and a one year warranty inspection. CONSIDERATIONS: On May ]0, 2005 item 16D3 the BCC approved Change Order #8 in the amount of $119,772.00 for additional construction observation, pennit modification and reimbursable. This Change Order set the BCC approved amount to $1,540,4]9.75. Staff approved Change Order #9 in the amount of $122,807.74 (7.97%) for extending lhe length of construction observation services as well as miscellaneous Owner requested services during the construction phase of the project Staff is now requesting Change Order #10 in the amount of $35,945.00 for extended construction administration for the soccer & ball field completion, SFWMD well pennit and modeling study, electrical engineer site visits, reduced size water meter in pool pump # I, pool lighting certification and one year warranty inspection. Parks and Recreation negotiated lhe original change order down to a reasonable amount. The negotiations took additional time, more than was originally anticipated. Additionally, there were several outstanding design/construction issues in which the final processing of Change Order #10 relied on. The issues were resolved over a three (3) month course, further delaying the processing of Change Order #10. The cumulative tolal of Change Order #9 and #10 is $]58,752.74 or (10.31 %). County purchasing policy requires that any change order amount over 10% of the BCC approved contract be approved by the Board of County Commissioners. FISCAL IMPACT: The necessary funds are budgeted in the North Collier Regional Park, Fund (346). GROWTH MANAGEMENT IMPACT: North Collier Regional Park is inventoried in the Growth Management Plan. RECOMMENDATION: That the Board of County Commissioners approve Change Order #10 to Contracl #99-2947, "Implementation of a Master Plan for the North Naples Regional Park." PREPARED BY: Tony Ruberto, Senior Project Manager, Parks and Recreation Department ....'_... CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No. 1606 January 29, 2008 Page 2 of 5 _ PROJECT NAME: North Collier Regional Park PROJECT #: 80602 PROJECT MANAGER: Tony Ruberto BID/RFP #: 99-2947 MOD #: 10 PO#: WORK ORDER #: N/A DEPARTMENT: Parks & Recreation CONTRACTOR/FIRM NAME: Herbert-Bellomo and Company, Inc, Original Contract Amount: $1,195,190.00 (Starting Point) Current BCC Approved Amount: $1,540,419.75 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 1,633,227.49 (Including All Changes Prior To This Modification) Change Amount: $ 35,945.00 Revised ContractIWork Order Amount: $1,699,172.49 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ 503,982.49 Dale of Last BCC Approval 5/1012005 Agenda Item # 16(0) 3 Percentage of the change over/under current contract amount 10.31% Fonnula: (Revised Amount/ Last BCC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 10/19/06 CURRENT: 11/26/07 Describe the change(s): 1) Extended Construction Administration for the soccer & Ball Field Completion. 2) SFWMD Well Permit and Modeling Study. 3) Site Visits by Electrical Engineer. 4) Water Meter to reduce meter size in Pool Pump # 1. 5) Pool Lighting Certification. 6) One Year Warranty Inspection. Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3, Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) Co' 5. Value Added r 6, Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Quality Control In Completing the sport Fields. The installation of a back up Well for Irrigation Purposes. Reduce the Impact fees by reducing the meter size for the Pool water supply. Complete the lighting system for night use. Have a one year inspection with Contractor to identify any required repairs after the 1" year of the 2 year warranty as per County General Conditions. This change was requested by: rlcontractor/Consultant P'I Owner rJ Using Department r CDES . r- rDesign Professional rJRegulatory Agency (Specify) r Other (Specify) Revised ] 1.19.2007 CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: ., Yes This form Is to be signed and cIId8d. No Agenda Item No. 1606 January 29, 2008 Page 3 of 5 REVIEWED BY: Date: /1- 1--7~7- APPROVED BY: Date: JI -21-o} Revised ]0.30.2007 Agenda Item No. 16D6 January 29, 2008 Page 4 of 5 TO: Bellomo-Herbert and Company, Inc. 100 East Pine Street, Suite 204 Orlando, FL. 3280] CHANGE ORDER # 10 FROM: Board of Collier County Commissioners Collier County Parks and Recreation Dept. 3300 Santa Barbara Blvd. Naples, FL. 34] 16 Project Name: Implementation of a Master Plan for the North Naples Regional Park Project No, 80602 Contract Dated: May 23, 2000 Change Order No.: 10 Change Order Description: This Change Order #] 0 is in connection with extended Construction Phase services and miscellaneous County requested services during the Construction Observation phase of the work. Refer to attached Scope prepared by Bellomo-Herbert for additional information. No. 99-2947 Date: November 26, 2007 Original agreement amount........................ ............... ..................,........ .................. $ Total of previous change orders............................................................................. $ This Change Order No.IO Amount ....................................................................... $ Current Agreement Amount ................................................................................. S 1,]95,]90.00 468,037.49 35.945.00 1,699.172.49 Original contract time in calendar days .............................................................................. 730 days Adjusted number of calendar days due to previous change orders................................... 1506 days This change order adjusted time is...................................................................................... 285 days Contract Time in working days ....................................................................................... 252] days ( Original Notice to Proceed date................................................................................August 8, 2000 Completion date based on original contract time .....................................................August 8, 2002 Revised completion date due to change order(s) ...............................................November 26, 2007 Your acceptance of this change order shall constitute a modification to our Agreement and will be performed subject to aI] the same terms and conditions as contained in said Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment to this Agreement shall constitute a full and final settlement of any and all claims arising out of, or related to, the change set forth herein, including claims for impact and delay costs. Prepared by~ ~ Date: 1/- 2. 7 - 0 7- . Ton~ RU~6, Project Manger . Parks Recreation Department I I I I Ie I Date:-/)~ '2.-(J) '07 Approved by: Marla Ramsey, Adminis Public Services Division ~rn ~ rn 0 W ~ ~ 100 NOV 27 2007 ~ \ Parkll and Recreation I Date: jI/t7/o7 . I Page 1 of 1 Agenda Item No. 1606 January 29, 2008 Page 5 of 5 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: Item Summary: 1606 Approve change order #1 0 in the amount of $35,945.00 for additional construction administration, SFWMD well permit and modeling study, site visits by electrical engineer, reduced water meter size, pool lighting & night use certification and one year warranty Inspection to contract #99-2947, Implementation of a Master Plan for the North Naples Regional Park Meeting Date: 1/29/2008 90000 AM Approved By Tony Ruberto Project Manager Date Public Services Parks and Recreation 12/20/20073:38 PM Approved By Linda Best Contracts Agent Date Administrative Services Purchasing 1/2/20083:18 PM Approved By Steve Carnell Purchasing/General Svcs Director Date Administrative Services Purchasing 1/3/2008 1 :52 PM Approved By Marla Ramsey Public Services Administrator Date Public Services Public Services Admin. 1/16/200812:58 PM Approved By Barry Williams Director Date Public Services Parks and Recreation 1/16/20081:51 PM Approved By OMB Coordinator OMB Coordinator Date County Manager's Office Office of Management & Budget 1/17/20088:30 AM Approved By Susan Usher Senior Management/Budget Analyst Date County Manager's Office Office of Management & Budget 1/18/200810:10 AM Approved By James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 1/20/200811:09 AM fi le://C:\Agenda Test\Export\99-January%2029, %202008\ 16. %20CON SENT%20AGENDA \... 1/23/2008