Contractor's Presentation on CR 951 Water Main, Project 70151 and 70152. Akerman
Construction Company, Inc_ will make a presentation to the Board on the status of the CR
951 Water Main project.
2/12/2008900:00 AM
Prepared By
Ronald F. Dillard, P.E.
Senior Project Manager
Date
Public Utilities
Public Utilities Engineering
1/17/20084:41:41 PM
Approved By
William D. Mullin. PE
Principal Project Manager
Date
Public Utilities
Public Utilities Engineering
1124/2008 11 :30 AM
Approved By
Roy B. Anderson, P .E.
Public Utilities Engineering Director
Date
Public Utilities
Public Utilities Engineering
1/28/20082:59 PM
Approved By
James W. DeLony
Public Utilities Administrator
Date
Public Utilities
Public Utilities Administration
2/6/2008 2:12 PM
Approved By
James V. Mudd
County Manager
Date
Board of County
Commissioners
County Manager's Office
2/6/20084:41 PM
file://C:\AgendaTest\Export\ 1 00-February%20 12,%202008\05.%20PRESENT A TIONS\5B\5... 2/6/2008
Agenda Item No. 58
February 12, 2008
Page 2 of 2
CONTRACTOR PRESENT A nON FORM
Board Presentation Date: February 12, 2008
Contract Number. Proiect Title. Proiect Number: Contract No. 06-3996R, C.R. 951
Water Main, Project No. 70151 and 70152.
Firm Name: Akerman Construction Company, Inc.
Proiect Manal!er: Ronald F. Dillard
Proiect Description: Construct a water transmission main along Collier Blvd. (C.R.
951) from Davis Blvd. to U.S. 41. From Davis Blvd. to Rattlesnake Hammock Road
it is a 36" main. From Rattlesnake Hammock Road to U.S. 41 it is a 30" main.
Oril!inal Start Date: November 20, 2006
Notice to Proceed Issuance Date:
November 20, 2006
Oril!inal Completion Date: November
20,2007
Revised Completion Date: April 15,
2008
Reason(s) for Variance: The alignment
had to be revised due to unforeseen
conditions. Unanticipated underground
conditions delayed construction.
Actions PlannedlTaken to Minimize Actions PlannedlTaken to Minimize
Variance: Negotiated a reduction in the Variance:
contractor's requested time extension.
Oril!inal Budl!et: $21,441,622
Revised Budl!et: $2] ,441 ,622
Reason(s) for Variance:
Current Project Status: Filling and testing the main line is in progress. Construction of
interconnections to existing mains will follow.