Agenda 04/08/2008 Item # 5B
Item Number:
Item Summary:
Meeting Date:
Page lof2
Agenda Item No. 58
April 8, 2008
Page 1 of 3
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
5B
Presentation on the status of the Santa Barbara Road Expansion Project. The project
requirements include the expansion and improvement of Santa Barbara Blvd from four (4)
lanes to six (6) lanes for 4.25 miles and of Radio Road from two (2) lanes to four (4) lanes for
1.22 miles. The scope of the work includes bridge widening over Interstate 1-75 and Golden
Gate Canal, drainage improvements. utility relocations, noise abatement walls, signalization
and lighting enhancements, and landscaping improvements.
4/8/2008 900:00 AM
Prepared By
Tad Pluc
Transportation Services
Engineer
Transportation Engineering and
Construction
Date
3/12/20083:02:20 PM
Approved By
Sharon Newman
Transportation Services
Accounting Supervisor
Date
Transportation Services Admin
3/12/20084:15 PM
Approved By
Usa Taylor
Transportation Services
Management/Budget Analyst
Date
Transportation Administration
3/12/2008 4:42 PM
Approved By
Steve Ritter
Transportation Services
Field Engineering Inspector
Transportation Engineering and
Construction
Date
3/13/2008 8:35 AM
Approved By
Najeh Ahmad
Transportation Services
Director
Date
Transportation Engineering &
Construction Management
3/19/20083:47 PM
Approved By
Norm E. Feder, AICP
Transportation Services
Transportation Division Administrator
Date
Transportation Services Admin.
3125/2008 10:03 AM
A pproved By
Pat Lehnhard
Transportation Services
Executive Secretary
Date
Transportation Services Admin
3125/2008 2:01 PM
Approved By
Mark Isackson
County Manager's Office
Budget Analyst
Date
Office of Management & Budget
3/28/20084:59 PM
tile://C;\AgendaTest\Export\ 1 04-April%208,%202008\05.%20PRESENT A TIONS\5B\5B%2,.. 4/2/2008
Page 2 of 2
Agenda Item No. 58
April 8. 2008
Page 2 013
Approved By
Leo E. Ochs, Jr.
Board of County
Commissioners
Deputy County Manager
Date
County Manager's Office
3/27/200811:29 AM
file:! /C:\AgendaT est\Export\ 1 04-April%208, %202008\05. %20PRESENT A Tl ONS\5B\5B %2... 4/2/2008
Agenda Item No. 58
April 8, 2008
Page 3 of 3
CONTRACTOR PRESENT A nON FORM
Board Presentation Date: April 8th, 2008
Contract Number. Proiect Title. Proiect Number: Contract 06-4042 "Santa Barbara
Boulevard six (6) laning from Davis Blvd (SR-84) To Copper Leaf Lane and Radio Road
four (4) laning from Santa Barbara Blvd to Davis Boulevard" (Project #62081)
Firm Name: Astaldi Construction Corporation
Proiect Mana!!er: Felipe Porro for Astaldi and Tad Pluc for Collier County
Proiect Description: The project requirements include the expansion and improvement
of Santa Barbara Blvd from four (4) lanes to six (6) lanes for 4.25 miles and of Radio
Road from two (2) lanes to four (4) lanes for 1.22 miles. The scope of the work includes
bridge widening over Interstate 1-75 and Golden Gate Canal, drainage improvements,
utility relocations, noise abatement walls, signalization and lighting enhancements, and
landscaping improvements.
Ori!!ina1 Start Date: February 5th, 2007
Notice to Proceed Issuance Date: January 81h, 2007
Ori!!ina1 Bud!!et:
$62,051,879.48
Revised Bud!!et:
$62,051,879.48
Ori!!ina1 Completion Date: August 23'd, 2009
Revised Completion Date: August 23'd, 2009
Reason(s) for Variance: None
Reason(s) for Variance: None
Actions PlannedlTaken to Minimize Variance:
N/A
Actions Planned/Taken to
Minimize Variance: N/A
Current Proiect Status: Project on Schedule with 47.8% percent of the work complete
and 41.8% percent of the contract time elapsed as of February 29th, 2008. Value of work
completed to date (2/28/08) is over $29 Million.