Agenda 05/27/2008 Item #16C 2 '111'",1, Agenda Item No, 16C2 May 27, 2008 Page 1 of 6 ~ EXECUTIVE SUMMARY Recommendation to amend Contract # 07.4138 "Reclamation of Collier County Landfill Cells 1 & 2 by (a) Deleting Section 5.4 "Limits on County Payments" and (b) amending Section 8, "Terms" to facilitate payments for earlier completion and to shorten project term from 24 months to 16 months. Obiective: To obtain the Board of County Comrnissioner's approval to amend Contract # 07-4138 "Reclamation of Collier County Landfill Cells 1 & 2" to expedite the completion of the Cells 1 & 2 Reclamation Project by modifying the contract to allow the County to pay for services rendered and approve a shortened project schedule, ~ Considerations: On October 23, 2007 the Board of approved Agenda item No. 10H; 07-4138 Reclamation of Collier County Land fill Cells 1 & 2 to Waste Management of Florida. The County's Solid Waste Management Departrnent is responsible for ensuring that the Collier County Landfill ("Landfill") has sufficient capacity available for the disposal of the County's solid waste. Accordingly, the Department prepared an Integrated Solid Waste Management Strategy ("Strategy"), which has been reviewed and approved by the Board. The Strategy requires the Department to maximize and optimize its use of the County's existing assets, including the Landfill. As part of the Strategy, the County has begun reclarnation of two old, unlined disposal areas (i.e., Cells 1 and 2), at the Collier County Landfill and will build new, lined disposal areas where Cells 1 and 2 had been located. In this rnanner, the County will provide additional disposal capacity at the Landfill, with better environmental safeguards. The Cells 1 & 2 reclamation project is progressing ahead of schedule. The contractor on site, Waste Management Inc. of Florida, has excavated over 180,000 cubic yards of material more quickly than expected. Under the current agreement, Waste Management Inc. of Florida is paid by the cubic yard reclaimed. They have exceeded staff's estimates due to better than expected environmental conditions, and more advanced decomposition of the materials. County staff is recommending that payments continue based on production by the contractor to meet this new updated completion schedule /""'"' This contract modification represents a "best value" solution by aggressively altering the project schedule and allowing payments for services rendered sooner than originally planned. This shortened project schedule will save time and money by reducing the County's potential risk and liability associated with the reclamation of Cells 1 & 2. Section 5A of the "Reclamation of Collier County Landfill Cells 1 and 2" contract states that "the County shall not under any circumstances be obligated to pay the Contractor more than Four Million Dollars ($4,000,000.00) before October 1, 2008". However, the project is significantly ahead of schedule and is expected to be completed by December 2008 (Initial project completion estimate was November 2009). Approval of this request, to delete section 5A of the contract, will allow the Contractor to continue working rather than demobilize, Section 8 "Terms" of the current contract reflects a 10f2 Agenda Item No, 16C2 May 27, 2008 Page 2 of 6 ~-, twenty four month (24) project schedule. This section of the contract will be amended to sixteen (16) months to reflect the new progressive schedule. By deleting section 5.4 and amending section 8, the project will be completed ahead of schedule, Fiscal Impact: The funds for this project (59006) are allocated in full in the Solid Waste Management Fund (474 Capital Improvements) in the amount of $7,761,946.87. No additional funding will be required as part of this contract modification. Staff believes that there may be recognized savings as part of this contract modification due to less liabilities and the diminished needs for contingencies on a shortened project schedule, Those savings will be recognized at the end of this project. Growth Manaaement Plan: The reclamation of Cells 1 and 2 is in compliance with the County's Growth Management Plan, The Solid Waste sub-elements of the Plan promote measures that will maximize the airspace (capacity) available at the Landfill. The reclamation project also implements the Integrated Solid Waste Management Strategy that was approved by the Board on December 5, 2006. The reclamation project is essential to the County's goal of developing new disposal areas at the Landfill to meet the County's long term Solid Waste disposal needs, This project also provides concurrency with the Solid Waste Management Department's AUIR Level of Service Standard Leaal Considerations: Contract Amendment 07-4138 has been reviewed and approved by the County Attorney's Office - JAB Recommendation: to amend Contract # 07-4138 "Reclamation of Collier County Landfill Cells 1 & 2 by (a) Deleting Section 5.4 "Lirnits on County Payments" and (b) amending Section 8. "Terms" to facilitate payrnents for earlier completion and to shorten project term from 24 months to 16 months PREPARED BY: Dayne Atkinson, Project Manager, Public Utilities Engineering Department. /"..., 2 of2 ~ 1 Item Number: Item Summary: Meeting Date: Page I of2 Agenda Item No, 16C2 May 27, 2008 Page 3 of6 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 16C2 Recommendation to amend Contract # 07-4138 Reclamation of Collier County Landfill Cells 1 & 2 by (a) Deleting Section 5.4 Limits on County Payments and (b) amending Section 8. Terms to facilitate payments for earlier completion and to shorten project term from 24 months to 16 months. 5/27/2008900:00 AM Prepared By Dayne Atkinson Public Utilities Project Manager Date Public Utilities Engineering 5/2/2008 11 :21 :05 AM Approved By William O. Mullin, PE Public Utilities Principal Project Manager Date Public Utilities Engineering 5/6/20082:50 PM Approved By Phil E. Gramatges, P .E. Public Utilities Sr. Project Manager Date Public Utilities Engineering 5/8/20084:43 PM (' Approved By Thomas Wides Public Utilities Operations Director Date Public Utilities Operations 5/9/200810:16 AM Approved By Daniel R. Rodriguez, M.B.A. Solid Waste Director 5/9/2008 11 :15 AM Date Approved By Public Utilities Solid Waste Dianna Perryman Administrative Services Contract Specialist Date Purchasing 5/9/2008 11 :57 AM Approved By Steve Carnell Administrative Services Purchasing/General Svcs Director Date Purchasing 5/12/200811:08 AM Approved By James W. DeLany Public Utilities Public Utilities Administrator Date Public Utilities Administration 5/13/2008 9:45 AM Approved By f' Jennifer A. Belpedio I ' County Attorney Assistant County Attorney Date County Attorney Office 5/15/20085:04 PM file:IIC:\AgendaTest\Export\ ] 08-May%2027 ,%202008\ 16,%20CONSENT%20AGENDA \ I,,, 5/21/2008 Page 20f2 Agenda Item No, 16C2 May 27, 2008 Page 4 of 6 Approved By OMS Coordinator OMS Coordinator Date County Manager's Office Office of Management & Budget 5/16/20083:17 PM Approved By Susan Usher Senior ManagemenUBudget Analyst Date County Manager's Office Office of Management & Budget 5/19/20089:39 AM Approved By Leo E. Ochs, Jr. Board of County Commissioners Deputy County Manager Date County Manager's Office 5/19/200810:01 AM file://C:\AgendaTest\Export\l 08-May%2027,%202008\ 1 6,%20CONSENT%20AGENDA \ 1", 5/21/2008 r: /". r. EXHIBIT A -I Contract Amendment 07-4138 Agenda Item No, 16C2 ,May 27, 2008 Page 5 of 6 "Reclamation of Collier County umdfiIl Cells 1 and 2" This amendment, dated ,2008_ to the referenced agreement shall be by and , between the parties to the original agreement, Waste Management Ine. of Florida, (to b~ referred to as "Contractor") and Collier County, Florida, (to be referred to as "County'~. Statement of Understanding The following change to the above referenced Agreement has been mutually ",greed to by:the Contractor and the County: A. The deletion to the existing language in 5 A of the Agreement IS shown herein' by slri1<ctbrollghs. ' Section 5 A Limits on County Payments The C."tFaetor undorstands that fundiFlg liH1i\alloBS elllst Iilld tRe CalH>!y's 1'a)....~nts liRa... tR. ;\greemeRt must 'ae 81',eed a. er time. 'f.eea,di"gly, the ea..ln.ter agrees t~'" it sh"n Rot '''''1",,"t l'a'YmeTlt fOO', aRe the COHTlty shail Bet ae. oaligated te, )lay, mere !hEm Thf'ce Million Two Hlffidreel Thou"sr.d Den.... ($3,Z90,99{H)0) limier. this AgreOFll6flt aefe,e aetaaer 1, Z008, \II1leGs: (al the Callflty re""est the Call1raetar t. rental! ml>fe than ane leachate "(ar-age tank at the Sile; (8) the CeBlraeter is r0'lui,ee ""der this ;\grecfi1en! ta "aal Le.ahate OJ' !ruek 10 an olf Site wastewater !fe.anoRt I'I""t fer !lisflasal; (6) :the CounlY""'1Hests the CaRlI'lleter l<Hiandle and "sflase of hallardaw; '.'",.ite di6ea"ere. in the V!orlc .\r6a; (d) the C81mlJ' is wqHired lIfld"f thiG Agreement la Pi!?' tI1te aanll'lle-terifor HnfareseOll eaHaitians a, a C'flange Ord..; (e) $! CaURIy mll"t reifttBCIf'Je the CaRll'llater fer Hsmg aaditiaRal e"ail''''''''! and )lerSflHael at the LaHdfill, pHrsuant Ie -See!iaB 3, I , ef the LlHldfilJ Of>erating f.greemeat; af (f) the COllflty eORseats ta the payment af additianal IlfllOHfltS. Netwitlwta"diag the pra....sions in the preeadm! s"".eaee, the Cm",l)' sha11 Bat unaer ""y aircum,tEm.es Be ""ligatea ta pay the .anlmator mare tit"" FOllr MilliaR Dellaro ($1,90Q,990.QG) aefore aata!>.". I, 299g fer th6 aet,htio. ielentiliea ill j;"hillit 'T', If tho Contraetar ~'Bllld ae entitleel to 1'a)'ffieat of aeelitiooal ame1mts ~llt fer the I'Ta'.1sians of this flaf.agFQ]lh, the CElRlI'lleter _y re~st 1'aymeat of s.6h adaltioBal_aUft!6-Ba er after a6laber I, 2008 ...d Ibe CBURIy "'all !'f""",t1y flay leBe r6'1Ue,teel _elmt Nalhing in this )laffi6'l'lll'lR shall ae ee,,,!rued Ie '.Vai';e ar negate the Calmly'S oaligation ta flay the Coatraeler far liIe warl, is eeHlj3letes m aeHlj3lianee 'lAth the: requiremeat afthis :\g;r:eelmeftt. ~ B. Amending to Section 8 of the Agreement is shown herein by deletions as StFilC..thrOllgflS and changes as underlines; SectionS: Terms The term of this Agreement shall" be for tW(l (Z) yeam 16 months, The term maybe extended for eae (1) year silt (6) months "ojth the mutual consent of the County and ihe Contractor. All other terms and conditions of the Agreement shall remain in force. IN WITNESS WHEREOF, the Contractor and the COU!lty have each, respectively, by an , , authorized person or agent, hereunder set their hands and seals on the date(s) indiaated below. : :i CONTRACTOR: Waste Management Inc. of Florida By: Authorized Signatory Print Name and Title ATIEST: Dwight E, Brock. Clerk Approved as to form and Legal SUffiCi? ~ ~ ~o ty Attorney .I Accepted: Agenda Item No. 16C2 May 27,2008 Page 6 of 6 ,2008 ! OWNER: BOARD OF COUNTY. COMMISSIONERS . COLLIER COUNTY, fLORIDA By By: Tom Henning, Chairman DEPARTMENT DIRECTOR By: Dan Rodriguez DIVISION ADMINISTRATOR , By: Jim Delany CONTRACT SPECIALIST Dianna Perryman j