Agenda 06/24/2008 Item #16B 2 EXECUTIVE SUMMARY Agenda Item No. 16B2 June 24, 2008 Page 1 of9 Recommendation to approve Change Order #5 to add $357,971.20 for continuing Inspection Services for Aim Engineering & Surveying, Inc. under ITN 04-3583 "CEI Services for Collier County Road Projects" for Project No. 63051 " Vanderbilt Beach Road from Airport Road to Collier Boulevard." OBJECTIVE: To continue professional Construction Engineering and Inspection (CEI) Services from a highly qualified firm for the Vanderbilt Beach Road Project from Airport Road to Collier Boulevard. CONSIDERATIONS: On July 26, 2004, Collier County entered into a contract with AIM Engineering & Surveying, Inc. for CEI Services for the Vanderbilt Beach Road Project. This project has had several change orders that extended AP AC's contract to May 12, 2008. The project will not be completed by the current approved time frame due to delays and lack of productivity by the contractor. The Current CPM schedule submitted by the contractor shows a completion date of Jan, 22, 2009. We are funding the CEI services up to February 2009. The CEI contract will have to be readdressed if the project is not completed at that time, It is our intent to get the contractor to pay for these extended services if it is ultimately shown that the delay is the result of their actions. LEGAL CONSIDERATIONS; The County Attorney's Office has reviewed this item for legal sufficiency and there are no outstanding legal considerations, HF AC FISCAL IMPACT: Funds in the amount of$357,971.20 are available in Gas Taxes, Impact Fees. Source of funds are gas taxes, and impact fees. GROWTH MANAGEMENT IMPACT: This request is consistent with the County's Growth Management Plan. RECOMMENDATION: That the Board of County Commissioners approves any necessary budget amendments; approves the Change Order to Aim Engineering & Surveying, Inc. for the continuation of inspection services for this project, and authorizes its Chairman to execute this Change Order No.5. Approve any necessary budget amendments. Prepared by; Eddie Martin, Project Manager-Road Construction, TECM Attachments: (I) Contract Modification Form; (2) Change Order/Aim Engineering Backup - Estimated Cost (3) Allowance Funds Page I of2 Agenda Item No. 1682 June 24, 2008 Page 2 of 9 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: Item Summary: 16B2 Recommendation to approve Change Order #5 to add $357,971.20 for continuing Inspection Services for Aim Engineering & Surveying, Inc. under ITN 04-3583 eEl Services for Collier County Road Projects for Project No. 63051 Vanderbilt Beach Road from Airport Road to Collier Boulevard Meeting Date: 6/24/2008 900:00 AM Prepared By Eddie Martin Field Engineering Inspector Transportation Engineering and Construction Date Transportation Services 4/30/20089:39:41 AM Approved By Steve Ritter Manager-Road Construction Date Transportation Services Transportation Engineering and Construction 6/10/200811:40 AM Approved By Rhonda Rembert Contract Specialist Date Administrative Services Purchasing 6/10/20081 :40 PM Approved By Najeh Ahmad Director Date Transportation Services Transportation Engineering & Construction Management 6/10/20082:22 PM Approved By Lisa Taylor Management/Budget Analyst Date Transportation Services Transportation Administration 6/10/20084:16 PM Approved By Sharon Newman Accounting Supervisor Date Transportation Services Transportation Services Admin 6/10/20084:39 PM Approved By Steve Carnell Purchasing/General Svcs Director Date Administrative Services Purchasing 6/11/20083:38 PM Approved By Norm E. Feder, AICP Transportation Division Administrator Date Transportation Services Transportation Services Admin. 6/12/2008 8:36 AM Approved By Pat Lehnhard Executive Secretary Date file://C;IAgendaTestIExportl 11 0-June%2024,%2020081 16.%20CONSENT%20AGENDA II... 6118/2008 Page 2 of2 Agenda Item No. 16B2 June 24, 2008 Page 3 of 9 Transportation Services Transportation Services Admin 6/12/20089:17 AM Approved By Heidi F. Ashton Assistant County Attorney Date County Attorney County Attorney Office 6/17/200812:48 PM Approved By OMB Coordinator OMS Coordinator Date County Manager's Office Office of Management & Budget 6/17/20083:33 PM Approved By Susan Usher Senior Management/Budget Analyst Date County Manager's Office Office of Management & Budget 6/17/20089:26 PM Approved By James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 6/17/20089:44 PM file://C:\Agenda Test\Export\ll O-June%2024, %202008\16.%20CONSENT%20AGENDA \ I... 6/18/2008 CHANGE ORDER # 5 Agenda Item No. 1682 June 24, 2008 Page 4 of 9 TO: Aim Engineering & Surveying, Inc. 5300 Lee Bouleyard Post Office Box1235 Lehigh Acres, Florida 33970-1235 Collier County Transportation Engineering & Construction Manegement Department 2885 South Horseshoe Drive Naples, Florida 34104 FROM: Project Name: Vanderbilt Beach Road (CR-862) from Airport-Pulling (CR-31) to Collier Blyd. (CR-951) Contract Agreement Dated: February 3, 2005 P.O. No.: 4500089167 Change Order No.: 05 Project No.: 63051 Bid No.; 04-3583 Date: April 18, 2008 Change Order Description: (See Attached Change Order SummalY and Spreadsheet) Original agreement amount .................................................................................... $ Sums of preYious change order amount ............ ...... ...... ......... ...... ...... ...... ............ ..... $ This Change Order Amount... ......... ............. ............ ............ ........................... ......... $ Revised Agreement Amount... .............. ......... ............ ............ ...... ......... ........ .......... $ Your acceptance of this change order shall constitute a modification to our Agreement and will be performed subject to all of the same terms and conditions as contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to this Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of, or related to, change set forth herein, including claims for impact and delay costs. ~ Date:5f' r~/o~ Engineering & Survey, Inc. c1'~/1~ Date: ~kJo.r/ Eddie Martin, Project Manager, Collier County T.E.C.M. / ' 5~~ Date:r.2Q-o!:- Steye Ritter, Manager - Road nstruction, Collier County, T.E.C.M. Date: 'I/;1a? Original contract time in calendar days ... ............ ...... ............... ............................... Adjusted number of calendar days due to preYious change orders ..................... ............ This change order adjusted time is ... ..................... ............ ......... ......... ...... ...... ...... Revised Contract Time in ca/endardays ............................................................... Original Notice to Proceed date ............ ......... ...... ...... ...... ......... ......... ...... ...... ........ Completion date based on original contract time ...... ......... ...... ........-...... ...... ...... ....... Revised completion date ...... ...... ...... ...-.. ......... ..................... .....-......................... Accepted by: Reviewed by: Approyed by: Approyed by: Authorized by: Norman E. Feder, Administrator, T.E.C.M. N/A Roy B. Anderson, P.U,E.D., Collier County Utilities Diyision Authorized by: 2,074,542.00 933,129.00 357,971.20 3,365,642.20 1080 days 108 days 285 days 1473 days FebrualY 3, 2005 JanualY 23, 2008 FebrualY 21 , 2009 Date: Date: CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Vanderbilt Beach Road CR 862 PROJECT #: ~ PROJECT MANAGER: Eddie Martin BIOIRFP #: 04-3583 MOO #: LPO#: 4500089167 WORK ORDER #: DEPARTMENT: T.E.C.M. CONTRACTOR/FIRM NAME:AIM Enalneerlno $ 2074542.00 (Starting Point) $ 3 007.671.0Ct (Last Total Amount Approved by the Bee) $ 3 007.671.0n. (Including All Changes Prior To This Modification) Change Amount: $ 357.971.2() Origln81 Contract Amount: Current Bee Approved Amount: i ddl Current Contract Amount: Revised ContraetlWork Order Amount $ 3 365 642.20 (Including This Change Order) Cumulative Dollar Value of Changea to thll ContractJWort Order: $ 1.291.100.20 Date of Last BCe Approval 11(13107 Agenda Item # ~ Percentage otthe change over/under current contract amount '1'1.90 Fannula: (Revised Amount! Last Bee approved amount).' ~. CURRENT COMPLETION DATE (S): ORIGINAL: Mav 12 2008 CURRENT: Februarv 21 2009 Describe the change(s): 1. This project will not be completed within It's currently approved time frame due to delays, and lack of production by the Contractor, that could not be anticipated prior to the werle The current eEl contract expires 3D days after the contractors approved time runs out. The CEI portion of the project will not be completed on May 12th, 2008 as the contract currently states. The contractor's current CPM SChedule shows 8 completion date of January 22, 2009. This change order will extend the CEI contract by 285 days, or 30 days past the scheduled project completion date. 2. Due to conservative budgetary practices, AIM's current project personnel funds will last through August of 2008, while the expense funds have already been depleted. The funding portion of this change order will fund the last 6 months of the project personnel, and the last 9 months of the expenses. The amount associated with this is $357,971.20. Specify the reasons for the change{al \' 1. Planned or Elective x 2. Unforeseen Conditions (" 3, QUlmtlty Adjustments x 4. Correction of Errors (Plans, Speclflcations or Scope of Work) r 5. Value Added x 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project If this change order were not processed: The contractor would continue worklna without 8 CEI to Insoect the work or administer the contract OPS TRACK CATEGORIES: MUST PICK ONLY ONE OF FOUR x Value Added/Unavoidable i" Value Added/Avoidable r No Value Ad~avoldable r No Value Added/Avoidable This change was requested by: r Contractor/Consultant x Owner r Using Department r COES r Design Professional r Regulatory Agency (Specify) r Other (Specify) Revised 10.30.2007 Agenda Item No. 1662 June 24, 2008 Page 5 of 9 ) '(1-' I! APPROVED BY: REVIEWED BY: ; ~vised 10,30.2007. .~~,;; Date: 3~ /-08 ~)I /O~ Date: Agenda Item No. 16B2 Page 6 of 9 Agenda Item No. 1682 June 24, 2008 Page 7 of 9 Change Order No. 5 Change Order #5 Funding Sheet TO: Aim Engineering & Surveying, Inc. FROM: 5300 Lee Bouleyard Post Office Box 1235 Lehigh Acres, Florida 33970-1235 Collier County Transportation Engineering & Construction Management Department 2675 South Horseshoe Drive, Suite #401 Naples, Florida 34104 Project Name: Vanderbilt Beach Road, from Airport Pulling Rd (CR 31) to Collier Blyd (CR 951) Contract Agreement Dated: February 3, 2005 Contract No.: 04-3583 Change Order No.: 05 Date: April 18, 2008 DESCRIPTION: 1. This project will not be completed within it's currently approved time frame due to deiays, and lack of production by the Contractor, that could not be anticipated prior to the work. The current CEi contract expires 30 days after the contractors approyed time runs out. The CEI portion of the project will not be completed on May 12th, 2008 as the contract currently states. The contracto~s current CPM schedule shows a completion date of January 22, 2009. This change order will extend the CEI contract by 285 days, or 30 days past the scheduled project compietion date. 2. Due to conservative budgetary practices, AIM's current project personnel funds will last through August of 2008, while the expense funds have already been depleted. The funding portion of this change order will fund the iast 6 months of the project personnel, and the last 9 months of the expenses. The amount associated with this is $357,971.20. TOtai amount for this Change OrdeiJs $357,971.20. FUNDING: ENGINEERING AND MANAGEMENT Ori~inal Bud~et $ 823,174.47 PreYious Chan~e Orders $ 306,716.00 This Chan~e Order $ ... . '" '. '. 164.,840,00 BALANCE $ 1,314,730.47 INSPECTION SERVICES Orioinal Budoet $ 1,101,929.53 Previous Chanoe Orders $ 612,198.00 This Chan~e Order :> '. , ... '.' .............-. 144,34'MO BALANCE $ 1,858,475.53 SURVEY 4-MAN PARTY DAYS Orioinal Budaet $ 31,920.00 PreYious Chanae Orders This Chanoe Order . .. . BALANCE $ 31,920.00 TESTING SERVICES Ori~inal Bud~et $ 34,030.00 Previous Chanae Orders $ 3,200.00 This Chanoe Order $,.(' ... .:",',.. ,.""",..,",p ",,04,000,.44 BALANCE $ 41,230.44 Agenda Item No. 16B2 June 24, 2008 Page 8 of 9 Page 2 Fundin Sheet Change Order No.5 EXPENSES $ $ $ TOTAL FUNDS: $ $ $ $ 83,488.00 11,015.00 119,285.76 2,074,542.00 933,129.00 357971,20 3,365,642.20 Schedule of Fees for: ITN #04-3583 (Professional Construction En~ Insp.) eEl Major Contract Vanderbilt Beech Road Six lanIng Project from Airport Rd. to Collier Blvd. Collier County Project 63051 Total Estimated Roadway Fee for the Remainder of the Project Position Employee Sr. Project Engineer Dennis Roza Project Engineer Jim Shuler Office Engineer Karl Vieth Secretary/ ReO Vonda Welky Sr. Inspector Mathew Distel Inspector Jerrod Thompson Plant Inspector Mark Gibson Total CEI Straight Time Costs Sr. Inspector Mathew Distel Inspector Jerrod Thompson Total eEl Overtime Costs Lump Sum Expenses Costs Allied Engineering & Testing, Inc. Total Testing CO&ts Total Maximum Fee Straiaht Time Hours Total MBnhour. 211 1056 212 1056 1056 880 105 Premium aT Hours Total Manhours 132 110 Hourly Fee $108.00 S9200 $77.00 $46.00 $67.00 S5l00 $67.00 Hourly Fee $100.50 $76.50 Total Fee S22.788.00 $97,152,00 $16.324.00 $48,576.00 $70,752.00 S44.SS0.00 S7.035.00 5307,507.00 Total Fee $13,266.00 $8,415.00 $21,681.00 524,782. 76 Quality Assurance & Material T estina ---H.QQ.0.44 $4,000.44 $357,971.20 Agenda Item No. 1682 June 24, 2008 Page 9 of9 Toclays Date: 4/18/08 Lumo Sum Exoenses includes copier lease, rent, Cleaning, electric, and telephone expenses $24,782.76