Agenda 07/22/2008 Item #16B 2Agenda Item No. 1662 July 22, 2008 Page 1 of 19 EXECUTIVE SUMMARY Recommendation that the Board of County Commissioners approve Change Order #1 to add $588,111 for continuing Inspection Services for Consul -Tech Construction Management, Inc. under ITN 06 -3583, "CEI Services for Collier County Road Projects" for Project No. 62081, "Santa Barbara Boulevard from Davis Boulevard to Copper Leaf Lane." OBJECTIVE: To continue professional Construction Engineering and Inspection (CEI) Services from a highly qualified firm for the Santa Barbara Boulevard 6- laning and Radio Road 4- laning project from Davis Boulevard to Copper Leaf Lane. CONSIDERATIONS: This Change Order is broken down into two parts. Part 1: Consul -Tech Construction Management, Inc. was selected for the CEI work for the Santa Barbara Boulevard Widening Project. The contract was negotiated as a time and line item (per hour for personnel) contract not a lump sum contract. The CEI contract was also negotiated using the design engineer's estimate for this project during 90% design stage, assuming construction start of August 2006 with completion in 671 days or 22 months. The general contractor has pushed to maintain construction so that they will stay on schedule or a little ahead and this has required a lot of overtime for the CEI as the contractor is working daytime and many nights in order to accomplish all that must be done with as little inconvenience to the traveling public as possible. This results in the CEI staff working two and sometimes three shifts. This additional cost amounts to $ 57,177 which will cover all costs through the original contract time of December 31, 2008. Part II: The current CEI contract of 24 months was to cover the road construction contract of 22 months. By the time the plans were completed and bid on September 28, 2006, the actual duration for construction was 31 months. The CEI contract was not adjusted to reflect the actual amount of time or money that would be needed for this change in duration and scope. Due to the extreme volume of work to be performed and the required inspections necessary to ensure we obtain the quality of work and materials that we expect, we need additional funding and time for the CEI in order to continue their services and to be able to complete this very important roadway project. The current final completion date for the road contract is August 23, 2009. However, the road contractor is ahead of schedule and we anticipate that they will complete the road work ahead of the current schedule. By extending the CEI contract by 265 days from January 1, 2009 to September 22, 2009 at the cost of $ 530,934, we anticipate that this will be enough to cover the rest of the road construction. LEGAL CONSIDERATIONS: There are no outstanding legal issues. This item is ready for Board consideration and approval. - -HFAC Agenda Item No. 16132 July 22, 2008 Page 2 of 19 FISCAL IMPACT: Funds in the amount of $588,111 are available in the Transportation supported Gas Tax Funds and Impact Fee Funds. Source of funds are gas taxes and impact fees. GROWTH MANAGEMENT IMPACT: This request is consistent with the County's Growth Management Plan. RECOMMENDATION: That the Board of County Commissioners approves the Change Order to Consul -Tech Construction Management, Inc. for the continuation of inspection services for this project and authorize its Chairman to execute this Change Order No. 1. Prepared by: Tad Pluc, Project Manager, Transportation Engineering & Construction Management Attachments: (1) Contract Modification Form; (2) Change Order /Consul -Tech Backup —Man- hours, revised schedule and cost estimate breakdown; (3) Change Order One Explanation Page I of 2 Agenda Item No. 16B2 July 22, 2008 Page 3 of 19 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: 16132 Item Summary: Recommendation to approve Change Order #1 to add $588,111 for continuing Inspection Services for Consul -Tech Construction Management, Inc. under ITN 06 -3583 CEI Services for Collier County Road Projects for Project No. 62081, Santa Barbara Boulevard from Davis Boulevard to Copper Leaf Lane. Meeting Date: 7/22/2008 9:00:00 AM Prepared By Tad Pluc Engineer Date Transportation Engineering and Transportation Services 6/11/200810:39:49 AM Construction Approved By Lisa Taylor Management/Budget Analyst Date Transportation Services Transportation Administration 612412008 6:33 AM Approved By Najeh Ahmed Director Date Transportation Engineering & Transportation Services Construction Management 612612008 8:01 AM Approved By Steve Ritter Manager -Road Construction Date Transportation Engineering and Transportation Services Construction 612612008 8:51 AM Approved By Rhonda Rembert Contract Specialist Date Administrative Services Purchasing 6/26/2008 9:13 AM Approved By Steve Cannel/ Purchasing/General Svcs Director Date Administrative Services Purchasing 612712008 3:52 PM Approved By Sharon Newman Accounting Supervisor Date Transportation Services Transportation Services Admin 6/30/2006 1:47 PM Approved By Norm E. Feder, AICP Transportation Division Administrator Date Transportation Services Transportation Services Admin. 711/2008 8:31 AM Approved By Heidi F. Ashton Assistant County Attorney Date fife://C:\AgendaTest \Export\1 I I - July %2022, %202008\ 16. %2000NSENT %20AGENDA\ 1... 7/15/2008 Page 2 of 2 Agenda Item No. 16B2 July 22, 2008 Page 4 of 19 County Attorney County Attorney Office 713/2008 9:01 AM Approved By Pat Lehnhard Executive Secretary Date Transportation Services Transportation Services Admin 7/312008 9:36 AM Approved By OMB Coordinator OMB Coordinator Date County Manager's Office Office of Management & Budget 71312008 10:36 AM Approved By Susan Usher Senior Management/Budget Analyst Date County Manager's Office Office of Management & Budget 71712008 8:43 PM Approved By James V. Mudd County Manager Date Board of County County Manager's Office 71812008 9:59 AM Commissioners file: / /C:AAgendaTest \Export\111 -July% 2022,% 202008 \16 %2000NSENT %20AGENDA \l ... 7/15/2008 SCHEDULE C PROJECT SCHEDULE Agenda Item No. 1682 July 22, 2008 Page 5 of 19 Original Required Adjusted navc Days Days Task 1. Manaclement Encilneerina Services 730 995 265 Construction coordination Complete record keeping of all activities and events Document all significant changes to the project Contract, plan, and specification interpretation Dispute resolution solutions (contractor and the public) Maintain required level of surveillance of contractors activities Prepare and document monthly pay requests Web site management and public relations Task 2. Inspector Services 730 1 995 265 Maintenance of Traffic Erosion, sedimentation and pollution control Embankment, base, and pavement structure Signing and marking plan conformance Utility inspection personnel provided Task 3. Testing Services As Needed • Field Sampling and material testing Task 4. Survev Services Horizontal and vertical control verifications pre- construction and post - construction. Needed Agenda Item No. 1682 July 22, 2008 SCHEDULE Page 6 of 19 B - ATTACHMENT A SCHEDULE OF FEES FOR BASIC SERVICES AS OF FEBRUARY 29, 2008 Remaining Required Adjustment Needed Task 1 Management Engineering Services $299,223 $626,965 $327,742 Construction coordination Complete record keeping of all activities and events Document all significant changes to the project Contract, plan, and specification interpretation Dispute resolution solutions (contractor and the public) Maintain required level of surveillance of contractors activities Prepare and document monthly pay requests Task 2. Inspector Services $510,004 756,373 $246,369 Maintenance of Traffic Erosion, sedimentation and pollution control Embankment, base, and pavement structure Signing and marking plan conformance Utility inspection personnel provided Complete roadway and bridge widening inspection Task 3 Testing Services $7,190 $21,190 $14,000 Field sampling and material testing Task 4. Survey Services $34,778 $34,778 None Bench mark verification and placement Horizontal and vertical control verifications pre- construction and post- construction. Task 5. Expenses $49,032 $49,032 None Rent Phone /Fax/DSL Line Electric Cleaning Services Copier (Rental & Maint.) Total for Task 1 through 5 $900,227 $1,488,338 $588,111 — — July 22, 200E G `fOa9e��e I. CONTRACTIWORK ORDER MODIFICATION C t CHECKLIST FORM PROJECT NAME: Santa Barbara Boulevard from Davis Boulevard to Cooper Leaf Lane PROJECT #: 62081 PROJECT MANAGER: Tad Plue 62 BID/RFP #: 063583 MOD #:. Y,PO#: 4500063796 WORK ORDER #: DEPARTMENT: TECM CONTRACTOR/RRM NAME: Consul-Tech Construction Management, Inc. Original Contract Amount: $ 2.405.006.00 (Starting Point) Current BCC Approved Amount, $ 2.405.0106.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 2.405.006.00 (Including All Changes Prior To This Modification) Change Amount: $ 588.111.00 Revised Contract/Work Order Amount: $ 2.993.117.00 (Including This Change Order) Cumulative Dollar Value of Changes to this Contract/Work Order: S 588,111.00 Date of Last BCC Approval May 9. 2006 Agenda Item # 10G Percentage of the change overlunder current contract amount % ;?4, 5 /� Formula: (Revised Amount / Last BCC approved amount) -1 CURRENT COMPLETION DATE (S): ORIGINAL: 12131/06 CURRENT: 09/22/09 Describe the change(s): The CEI contract was negotiated using the design engineer's estimate for this project during 90% design stage, assuming construction start of August 2006 with completion in 671 days or 22 months and using an estimate of 38 million for the construction contract. By the time the plans were completed and bid on 9/28/06 the actual duration for construction was 31 months and 62 million dollars. The CEI contract was not adjusted to reflect the actual amount of time or money that would be needed for this change in duration and scope. The general contractor has pushed to maintain construction so that they will stay on schedule or a little ahead and this has required lots of overtime for the CEI as the contractor is working daytime and many nights in order to accomplish all that must be done with as little inconvenience to the traveling public as possible. This results in the CEI staff working two and sometimes three shifts. Specify the reasons for the change(s) I7 1. Planned or Elective G 2. Unforeseen Conditions C 3. Quantity Adjustments E'.. 4. Correction of Errors (Plans, Specifications or Scope of Work) Co S. Value Added C 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project If this change order were not processed: _Without the Inspection services to monitor the roadway construction, _the quality of the final product and the schedule of the project might be jeopardized. This change was requested by: ft- ontrector /Consultant rl Owner rl Using Department r CDES l= Design Professional rlRegulatory Agency (Specify) riOther (Specify) Revised 11.19.2007 Agenda Item No. 16132 july 2, Page 8 of 19 CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes W No This form Is to be signed and dated. APPROVED BY: MSpecialist Date: � /I o �� /1l /,()/ REVIEWED BY: Date: ° v Revised 11.19.2007 21M1-iILIWE DUN Page 9 of 19 CHANGE ORDER CHANGE ORDER NO. 01 CONTRACT NO._06 -3583 BCC Date: Agenda Item: TO: Consul -Tech Construction Management, Inc. 319 Airport Road North Naples, FL 34104 DATE: May 12, 2008 PROJECT NAME: Santa Barbara Boulevard from Davis Boulevard to Copper Leaf Lane PROJECT NO.: 62081 Under our AGREEMENT dated May 31, 2006 You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: The CEI contract was negotiated using the design engineer's estimate for this project during 90% design stage, assuming construction start of August 2006 with completion in 671 days or 22 months and using an estimate of 38 million for the construction contract. By the time the plans were completed and bid on 9/28/06 the actual duration for construction was 31 months and 62 million dollars. The CEI contract was not adjusted to reflect the actual amount of time or money that would be needed for this change in duration and scope. The general contractor has pushed to maintain construction so that they will stay on schedule or a little ahead and this has required lots of overtime for the CEI as the contractor is working daytime and many nights in order to accomplish all that must be done with as little inconvenience to the traveling public as possible. This results in the CEI staff working two and sometimes three shifts. Due to the extreme volume of work to be performed and the required inspections necessary to ensure we obtain the quality of work and materials that we expect, we need additional funding and time for the CEI in order to continue their services and to be able to complete this very important roadway project. FOR THE (Additive Sum of: ($ 588,111 1. Original Agreement Amount $ 2.405,006 Sum of Previous Changes $ 0 This Change Order (Add) $ 588.111 Present Agreement Amount $ 2.991117 The time for completion shall be (increased by 265 calendar days due to this Change Order. Accordingly, the Contract Time is now 995 calendar days. The substantial completion date is N/A and the final completion date is September 22, 2009. 1 of 2 SANTA BARBARA ROAD WIDENING MANPOWER LOADING FOR CONTRACT Fd7ENWON P.M.1.1 Mm lwtrn pm mash Year aooa CU..ifi°dO°r i s a 4 5 6 1 ] a 9 ,o BebmblVmi limier peps Prahns Jeho 63 66 66 66 66 66 66 M 66 66 66o Bowes, PE PmjeRAdmWeaato, Into wwdnoo 165 165 165 165 165 365 365 165 165 065 1,65o Office Mawg. B.Wy 065 166 165 165 165 065 065 165 165 165 1,65o 60aiorbupz 065 065 065 065 165 ,65 r65 065 r65 165 4650 SM Se I-PMor J 165 065 365 065 660 ln.p m 065 ,65 365 166 66o s b -ptu�. 365 065 165 065 165 ass lwpbOor put Plaxma 165' 165 063 065 065 165 165 365 165 365 465o lnrpector 165 165 065 165 065 266 165 065 165 065 4650 Jame W fwpe FAMSYDINT 065 065 365 365 165 am Jan Feb $far Apr M 1 Jun Jul Avg B P Ocl Nw 14c TOTAL o 0 455$ 1,%0 1,551 4550 2,221 892 890 891 891 691 MRS. Pav9lmel Meo-bo9npa nd, V....9 Abmtal Veu elwomao bw 11 Ut S 4 U 16 17 19 19 a Bmiw Plojed Fe)2aa jam KDwa PE 66 66 66 66 66 66 66 661 66 591 P.)J Aao b w Tm 065 165 065 065 365 165 10 4090 om& 6tewBer Healy modly 065 065 065 065 16$ 065 063 165 r23 idyl Bann lope rrr 365 065 ,65 365 065 165 i65 4a 4r95 Sem.lnq sor 0 J= W6e lmpa ]aOrr Burke o 1--P O Cbulkb0,rr o boo ul loepecror 165 165 i65 066 065 065 166 40 4095 10upm°r 165 165 165 363 065 065 066 4o 4095 t ups. o M J. Feb Mar Apr M Y a. Jul A1g Sep TOTAL a" 891 690 69s 8 Bqi 766 %1 167 0 0 0 6.65o Pelwm,el OweiRodow Total Mo. �� p1e t�yoe Cwt Task 1. Management Englneerli �ertanbr� 1«�� 1,a54 2140... a175.56e Aojecl A,iWnleVtlor 68. 4m5.op 22644.. Tim Woodrum From Schedule B - Atiacament A - Re $299,275 - S 621 Task 2. Inspector Services Omro Mmm6e+ 6ev'ertY Morky 3.091 sa5.00 e37o,o9g Semorimpwor sane C. ,. 2,845 575.50 S95.5o — X44967 Smi.r Loup for 660 57550 59550 + $56,133 J. Gile From Schedule B - Awrchment A - Rr $510,004 -67% 1.'r,or V Bor4e 660 $58,5. $8450 . $44,167 b -p-tor 660 55650 $9450 S"J87 C4ur0e M61. + Adjustment! =C 1,855 $5850 E845. + $IDU.r9a Task 6' Task 2 f' lwpa Jam. mfty w 2.845 $5850 $94.50 $190,473 IwP w am $5850 $841. $55,234 rs her TOTAL $ TOTAL 17,375 e/ s1.189Sda Item No. 1682 July 22, 2008 Page 10 of 19 1g Services = Total $ 626,965 quill - Remaining w Adjustment Needed .,965 w S 527,742 quint . Remsinlna a Adimtment Needed 175 • S 246,$69 Jwded for Task 1 and Task 2 !27,742 246,169 $74,111 Mo bawd. 165 W m9rM' (Addjustmont Required for Task 3 - Tasting Services is not a.,ar...lawn n tcs a magm true m.n h.. included in the amounts show above. See Schedule 13 . Attachment A) Agenda Item No. 1662 July 22, 2008 Page 11 of 19 R SCHEDULE B - ATTACHMENT A SCHEDULE OF FEES FOR BASIC SERVICES AS OF FEBRUARY29, 2008 Remaining Required Adjustment Needed Task 1. Management Engineering Services $299,223 $626,965 $327,742 Construction coordination Complete record keeping of all activities and events Document all significant changes to the project Contract, plan, and specification interpretation Dispute resolution solutions (contractor and the public) Maintain required level of surveillance of contractors activities Prepare and document monthly pay requests _Task 2. Inspector Services $510,004 756,373 $246,369 Maintenance of Traffic Erosion, sedimentation and pollution control Embankment, base, and pavement structure Signing and marking plan conformance Utility Inspection personnel provided Complete roadway and bridge widening inspection Task 3. Testing Services $7,190 $21,190 $14,000 Field sampling and material testing Task 4. Survey Services $34,778 $34,778 None Bench mark verification and placement Horizontal and vertical control verifications pro-construction and post-construction. Task 5. Expenses $49,032 $49,032 None Rent Phone /Fax/DSL Line Electric Cleaning Services Copier (Rental & Maint.) Total for Task 1 through 5 $900,227 $1,488,338 $588,111 Agenda Item No. 16B2 -- July 22, 2008 Page 12 of 19 Your acceptance of this Change Order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, K any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs. Prepared by: Date: �® John L. P.E. o , P ct Manager Consul -Tech Construction Management, Inc. Reviewed by: -7L& T-,! u Tad Pluc, Project Manager, Collier County, T.E.C.M Approved by: S Steve Ritter, Manager — Road Construction, Collier County, Approved by: Jay Am Dire '7, Collier C unty, T.E.C.M. Date: Date: G- 3- o T.E.C.M. Date: t �� Authorized by: Date: Norman E. Feder, Administrator, Transportation Administration 2 of 2 L Agenda Item No. 16132 . ouly 44, LVVo Page 13 of 19 SCHEDULE C PROJECT SCHEDULE Original Required Adjusted Days Days Days Task 1. Management Engineering Services 730 995 265 • Construction coordination • Complete record keeping of all activities and events • Document all significant changes to the project • Contract, plan, and specification interpretation • Dispute resolution solutions (contractor and the public) Maintain required level of surveillance of contractors • activities Prepare and document monthly pay requests Web site management and public relations Task 2. Inspector Services 7301 995 1 265 • Maintenance of Traffic • Erosion, sedimentation and pollution control • Embankment, base, and pavement structure • Signing and marking plan conformance • Utility inspection personnel provided Task 3. Testing Services As Needed • Field Sampling and material testing Task 4. Survey Services As Needed Bench mark verification Horizontal and vertical control verifications pre - construction and post - construction. CHANGE ORDER CHANGE ORDER NO. 01 TO: Consul-Tech Constru Management Inc 319 Airport Road North Naples FL 34104 DATE: May 12, 2008 Agenda Item No. 1662 July 22, 2008 Page 14 of 19 CONTRACT NO._06 -3583 BCC Date: Agenda Item: PROJECT NAME: Santa Barbara Boulevard from Davis Boulevard to Cooper Leaf Lane PROJECT NO.: 62081 Under our AGREEMENT dated May 31, 2006 You hereby are authorized and directed to make the following change(s) in accordance with terns and conditions of the Agreement: The CEI contract was negotiated using the design engineer's estimate for this project during design stage, assuming construction start of August 2006 with completion in 671 days or 22 months and using an estimate of 38 million for the construction contract. By the time the plans were completed and bid on 9/28106 the actual duration for construction was 31 months and 62 million dollars. The CEI contract was not adjusted to reflect the actual amount of time or money that would be needed for this change in duration and scope. The general contractor has pushed to maintain construction so that they will stay on schedule or a little ahead and this has required lots of overtime for the CEI as the contractor is working daytime and many nights in order to accomplish all that must be dome with as little inconvenience to the traveling public as possible. This results in the CEI staff working two and sometimes three shifts. Due to the extreme volume of work to be performed and the required inspections necessary to ensure we obtain the quality of work and materials that we expect, we need additional funding and time for the CEI in order to continue their services and to be able to complete this very important roadway project. FOR THE (Additive) Sum of. 1$ 588,111 1. Original Agreement Amount $ 2,405.006 Sum of Previous Charges $ 0 This Change Order (Add) $ 588.111 Present Agreement Amount $ 2.993.117 The time for completion shall be (increased by 265 calendar days due to this Charge Order. Accordingly, the Contract Time is now 995 calendar days. The substantial completion date is NIA and the final completion date is September 22. 2009. loft Agenda Item No. 16132 July 22, 2008 Your acceptance of this Change Order shall constitute a modification to our Agreement arf 9difl be)f 19 performed subject to all the some terms and conditions as contained in our Agreement indicated above, as fully as if the some were repeated in this acceptance. The adjustment, If any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, inciud'sg claims for impact and delay costs. Prepared by. Date: Shelog John L P.E., P ' t Manager Consul -Tech Construction Management, Inc. Reviewed by: L' Tt� ie � Tad Pluc, Project Manager, Collier County, T.E.C.M Approved by: SittM e� Steve Ritter, Manager — Road Construction, Collier County, Approved by: Jay /J ma , Direol , Collier Cdunty, T.E.C_M. Date: Date: G- 3- o T.E.C.M. Date: e<+ n Authorized by: Date: Norman E. Feder, Administrator, Transporta ion Administration 2 of 2 SANTA BARBARA ROAD WIDENING Agenda Item No. 16B2 July 22, 2008 MANPOWER LOADING FOR CONTRACT EXTENSION Page 16 of 19 Part I Funding to original CEI Contract completion date December 31, 20o8 Personnel Classifications Man -hours per month Year 2008 Personnel Classifications Overtime Total Hours Regular Rate Rate labor Cost Senior Project Engineer (rho 1 2 3 4 5 6 7 8 9 10 Subtotal Year 1 Senior Pmject Engineer John SI -3250 66 66 66 66 66 66 66 66 66 66 66o Rowell, P.E. Senior Inspector 1,650 $7550 S9.5 -50 $140,333 Steve Cummings Project Administrator 165 165 165 165 165 165 165 165 165 165 1,650 Tim Woodrum 66o S58 50 $84.50 544.187 Larn Burke Inspector 66o $58.50 Office Manager $44.187 Charlie Miller 165 165 165 165 165 165 165 165 165 165 1,650 Beverly Morley Inspector 1,650 S58.50 $8450 $110,468 James Withrow Senior Inspector Inspector 165 165 165 165 165 165 165 165 165 165 1,650 Steve Cummings $851,128 Senior Inspector 165 165 165 165 66o Juan Calle Inspector 165 165 165 165 66o Larry Burke Inspector 165 165 165 165 66o Charlie Miller Inspector 165 165 165 165 165 165 165 165 165 165 1,650 Gus Pastrana Inspector 165 165 165 165 165 165 165 165 165 165 1,65o James Withrow Inspector 165 165 165 165 165 825 Edgar Sypher Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec TOTAL 1,551 1,551 1,551 1,551 1,056 891 891 891 891 891 11,715 Personnel Classifications Overtime Total Hours Regular Rate Rate labor Cost Senior Project Engineer (rho S140.00 592,400 John Rowell, P.E. Project Administrator r,65o 8105.00 SI -3250 Tim Woodrum Office Manager Beverly 1,65o, 855.00 500,750 Murlev Senior Inspector 1,650 $7550 S9.5 -50 $140,333 Steve Cummings Senior Inspector 66o $75_50 $9550 $56,i33 .Juan Calle Inspector 66o S58 50 $84.50 544.187 Larn Burke Inspector 66o $58.50 584.50 $44.187 Charlie Miller Inspector 66o $,58.50 $8450 $44,187 Gus Pastrana Inspector 1,650 S58.50 $8450 $110,468 James Withrow Inspector 8z5 558.5o $84.50 555.234 Edgar Svphcr TOTAL 11,715 $851,128 1 CF 4 4 Revised Manpower Loading 06 -30 -08 Part I Cost Summary Marc7o" gh Dece Blance Remaining Contract AMT After Feburary Billing Agenda Item No. 1682 July 22, 2008 Page 17 of 19 Change Order Amount Mgmt Eng. Services Man -hours per month Year 2009 Personnel Classifications $ 356,400.00 $ 299,223 $ 57,177.00 Inspection Sere. Road $ 494,728 $ 510,004 12 $ Testing Services '15 16 17 18 $ 7,190.00 $ 7,190.00 $ - Survey Services 66 66 66 66 $ 66 $ - 66 66 Expenses 594 John Rowell, P.E. $ 24,516.00 $ 24,516.00 $ - TOTAL COST ESTIMATE PART I $ 882,833.75 $ 840,933.00 $ 57,177.00 SANTA BARBARA ROAD WIDENING MANPOWER LOADING FOR CONTRACT EXTENSION Part II Funding to original CEI Contract completion date Funding From January through September 2009 2 OF 4 4 Revised Manpower Loading 06 -30 -08 Man -hours per month Year 2009 Personnel Classifications 11 12 13 14 '15 16 17 18 19 Subtotal Year Senior Project Engineer 66 66 66 66 66 66 66 66 66 594 John Rowell, P.E. Project Administrator 165 165 165 165 165 165 qo 1,030 Tim Woodrum Office Manager 165 165 165 165 165 165 165 165 121 1,441 Beverly Morley Senior Inspector 165 165 165 165 165 165 165 40 1,195 Steve Cummings Inspector 165 165 165 165 165 165 165 40 1,195 Gus Pastrana Inspector 165 165 165 165 165 165 165 40 1,195 James Withrow Jan Feb Mar Apr May Jun Jul Aug Sep TOTAL 891 891 891 891 891 891 766 351 187 0 0 0 6,65o Personnel Classifications Total Hours Overtime Regular Rate Rate Labor Cost Senior Project Engineer 594 $140.00 "3,160 John Rowell, P.E. Project Administrator 1,030 $105.00 $toft,l5o Tim Woodrum Office Manager Beverly 1,441 $55.0o $79,255 Morley Senior inspector 1,195 $7a "50 $9550 $to1,635 Steve Cummings 2 OF 4 4 Revised Manpower Loading 06 -30 -08 Inspector 1.195 5,58.50 $84.50 $80,005 Gus Pastrana through Inspector 11195 558.50 584.50 $80,005 James Withrow 2009 TOTAL 6,65o $532,210 Man -hours based on 165 per month' Overtime man -hours at 10% of straight time man hours Part II Cost Summary Agenda Item No. 1682 July 22, 2008 Page 18 of 19 ADD 265 CONTACT DAYS January BI: Remaining Change Order Amount through September Con retr MT After Feburary BilBng 2009 Mgmt Eng. Services $ 270,565.00 $ $ 270,565.00 Inspection Serv. Road $ 261,645 $ 15,276.00 $ 246,369.00 Testing Services $ 14,000.00 $ - $ 14,000.00 Survey Services $ 34,788.00 $ 34,778.00 $ - Expenses $ 24,516.00 $ 24,516.00 $ - TOTAL COST ESTIMATE PART II $ 605,514.00 8 74,570.00 E 530,934.00 TOTAL ACCUMLATIVE COST ESTIMATE PART I AND PART It $ 688,111.00 3 OF 4 4 Revised Manpower Loading 06 -30 -08 Agenda Item No. 16B2 July 22, 2008 Page 19 of 19 4 OF 4 4 Revised Manpower Loading 06 -30 -08