Agenda 10/28/2008 Item #16A10 Agenda Item No. 16A 10 October 28,2008 Page 1 of 16 EXECUTIVE SUMMARY Recommendation to grant final approval of the roadway (private) and drainage improvements for the final plat of Fiddler's Creek Phase Four, Unit One. The roadway and drainage improvements will be privately maintained by the Fiddler's Creek Community Development District. OBJECTIVE: That the Board of County Commissioners (Board) grant final approval of the infrastructure improvements associated with that subdivision known as Fiddler's Creek Phase Four, Unit One. CONSIDERATIONS: 1. On July 7, 2005, the Board of County Commissioners granted preliminary acceptance of the roadway and drainage improvements in Fiddler's Creek Phase Four, Unit One. 2. The roadway and drainage improvements will be maintained by the project developer or assigns, I"'.....-~ 3. The required improvements have been constructed in accordance with the Land Development Code. The Engineering and Environmental Services Department has inspected the improvements and is recommending final acceptance of the improvements, 4. A resolution for final acceptance has been prepared and approved by the County Attorney's Office. A copy of the document is attached. 5. On March 21, 2005, the Board entered into a Construction and Maintenance Agreement for Subdivision Improvements with the developer. The developer has fulfilled his commitments with respect to the Construction and Maintenance Agreement. 6. This PUD has been found to be in substantial compliance. FISCAL IMPACT: The roadway and drainage improvements will be maintained by the project's Community Development District. ,- Agenda Item No. 16A 10 October 28, 2008 Page 2 of 16 GROWTH MANAGEMENT IMPACT: There is no growth management impact. LEGAL CONSIDERATIONS: The County Attorney's Office has reviewed and approved the Resolution for legal sufficiency, This item is ready for Board consideration and approval. 8TW RECOMMENDATION: That the Board of County Commissioners grant final acceptance of the roadway and drainage improvements in Fiddler's Creek Phase Four, Unit One and release the maintenance security. 1. Authorize the Chairman to execute the attached resolution authorizing final acceptance. 2. Authorize the release of the maintenance security. PREPARED BY: John Houldsworth, Senior Engineer, Engineering and Environmental Services Department ,- Item Number: Item Summary: Meeting Date: Page lof2 Agenda Item No. 16A 10 October 28,2008 Page 3 of 16 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 16A 1 0 Recommendation to grant final approval of the roadway (private) and drainage improvements for the final plat of Fiddlers Creek Phase Four, Unit One, The roadway and drainage improvements will be privately maintained by the Fiddlers Creek Community Development District. 10128/20089:00:00 AM Prepared By John Houldsworth Community Development & Environmental Services Senior Engineer Date Approved By Engineering Services 10/7/200810:40:38 AM Judy Puig Community Development & Environmental Services Operations Analyst Community Development & Environmental Services Admin. Date Approved By 10/71200810:46 AM Steven Williams Attorney's Office Assistant County Attorney Date Attorney's Office 1017/200810:51 AM Approved By MaryAnn Devanas Community Development & Environmental Services Senior Planner Date Approved By CDES Engineering 10/10/20088:58 AM Joseph K. Schmitt Community Development & Environmental Services Community Development & Environmental Services Adminstrator Date Community Development & Environmental Services Admin. 10110120088:29 PM Approved By William D. Lorenz, Jr., P.E. Community Development & Environmental Services Environmental Services Director Date Approved By Environmental Services 10/14/200810:56 AM OMB Coordinator Administrative Services Applications Analyst Date Information Technology 10/1612008 8:34 AM Approved By Mark Isackson County Manager's Office Budget Analyst Date Office of Management & Budget 10116/200811:22AM file:IIC:\AgendaTest\Export\ 115-0ctober%2028, %202008\ 16. %20CONSENT%20AGEN... 10/2212008 Page 2 of2 Agenda Item No. 16A 10 October 28,2008 Page 4 of 16 Approved By James V, Mudd County Manager Date Board of County Commissioners County Manager's Office 10/16/20086:41 PM fiIe:IIC:\AgendaTest\Export\115-0ctober%2028, %202008\ 16.%20CONSENT%20AGEN.., 10/22/2008 Agenda Item No. 16A 10 October 28, 2008 Page 5 of 16 MEMORANDUM TO: -".gJ"YtHughes Engineer FROM: John R. Houldsworth Engineer RE: Verification of Security Amount for "F>ld'Uer's'Creek Phase Four, Unit '. D.J::le" .." DATE: December 2, 2004 ------------------------------------------------------------------ The developer proposes to post security for the referenced project so that the plat can be recorded. Please verify that the amount of the security will cover the cost of construction of the items remaining to be completed or, if applicable, that all construction is complete. A detailed list is attached for your use. Attachment J u L y\ ~ ('j / ~ (). k. o avo' Y f f?-/z) 0,/ Q. GRADY MINOR & ASSOCIATES, P.A. Civil Engineers. Land Surveyors. Planners Agenda Item No. 16A10 October 28, 2008 Page 6 of 16 MARK W. MrNOR, P.E. NORMAN J. TREBILCOCK, A.LC.P., P.E. C. DEAN SMITH, P.E. DAVID W. SCHMITT, P.E. MICHAELJ. DELATE, P.E. MATIHEWJ. HERMANSON, P.E. MICHAEL T. HERRERA, P.E. November 30, 2004 D. WAYNE ARNOLD, A.LCl ROBERT "BOB" THINNES, A.LCP. THOMAS J. GARRIS, P.5.M. STEPHEN v. BURGESS, P.S.M. ALAN V. ROSEMAN CHRISTOPHER C HAYES, P.E. IVY WYLIE, P.E. Mr, John R. Houldsworth, Senior Engineer Collier County Development Services 2800 North Horseshoe Drive Naples, FL 34104 RE: Fiddler's Creek Unit Four Phase One AR-4082 Dear Mr. Houldsworth: We gained approval of the construction plans and final subdivision plat for this project anticipating that we would record the plat upon completion of the subdivision improvements. It is now our intent to record the plat prior to completion of the improvements. Enclosed please find the following items: 1. Revised Engineer's Opinion of Probable Costs, cost to complete, and bond calculations, 2. Construction Maintenance Agreement. Please review and if these documents are acceptable we will request the bond and have the Construction Maintenance Agreement executed, / If you have any questions or need additional info ation, please contact our office, -- --- -- MWM:dr Enclosure cc: Jack McKenna (239) 947-1144 . FAX (239) 947-0375 . E-Mail: engineering@gradyminor.com 3800 Via Del Rey _ Bonita Springs, Florida 34134-7569 _ EB/LB 0005151 F:\JOB\M.ARKHAM\MARKl \M\VM\JH4 ] 130L.doc Agenda Item No. 16A 10 October 28,2008 Page 7 of 16 Prepared by: Q. Grady Minor & Associates, P.A. Civil Engineers - Land Surveyors - Planners 3800 Via Del Rey Bonita Springs, Florida 34134 (239) 947-1144 (239) 947-0375 (Fax) November 29, 2004 ,/ ... ..,,- \ \ \ 't.:J\.J ~ Agenda Item No, 16A 10 October 28. 2008 Page 8 of 16 FIDDLER'S CREEK UNIT FOUR PHASE ONE ENGINEER'S OPINION OF PROBABLE COST SCHEDULE "A" UPDATED: 2/19/03, 11/29/04 EARTHWORK & SITE PREP Clearing, grubbing and preparation of roadway rights-of-way, and easements areas as designated by the Engineer in the field including chipping and grinding of all materials on the Owner's property and then disposal of all residue off the Owner's property, all as specified, per acre complete. All work in right-of-way is subject to inspection by the owner, Collier County DOT and FDOT contingent on final acceptance of improvements as shown and specified on the contract documents, ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE A-I Fill (on-site) CY 81,900 $2,00 $163,800,00 A-2 Silt Fence LF 10,800 $2,00 $21,600.00 TOTAL $185,400.00 COST TO COMPLETE 10% remaining x $185,400.00 = $18,540.00 I Agenda Item No. 16A10 October 28, 2008 Page 9 of 16 FIDDLER'S CREEK UNIT FOUR PHASE ONE ENGINEER'S OPINION OF PROBABLE COST UPDATED: 10/22/2003, 11/29/04 SCHEDULE "C" W ASTEW A TER COLLECTION Includes furnishing and handling of all required materials, joint restraint, thrust blocks, connections to other pipelines, all excavation (including rock and over-excavation if necessary), dewatering, bedding material (if necessary), pipeline installation, back filling (imported fill if necessary), compaction, compaction testing in roadway areas, pressure testing, flushing, clean-up including resodding areas previously sodded, seeding all areas disturbed by construction, providing complete as-built drawings and other items necessary to complete the system and provide the Owner, DEP and Collier County with a complete working wastewater collection system as shown on the drawings and specifted in these contract documents. ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE C-I 6" PVC (DR18) LF 1700 $11.50 $19,550.00 C-2 6" PVC (DR14) LF 50 $13.40 $670.00 C-3 Pump Station EA 2 $110,000.00 $220,000.00 C-4 6" Plug Valve & Box EA 3 $1,130.00 $3,390.00 C-5 manhole 0'_6' cut EA 15 $2,052.00 $30,780.00 C-6 manhole 6'_8' cut EA 9 $2,432.00 $21,888.00 C-7 manhole 8'-10' cut EA 4 $3,064.00 $12,256,00 C-8 manhole 10'-12' cut EA 3 $3,768.00 $11,304.00 C-9 manhole 12'-14' cut EA 6 $4,382,00 $26,292.00 C-IO manhole 14'-16' cut EA 3 $5,240.00 $15,720.00 C-ll manhole 16'-18' cut EA 4 $6,200.00 $24,800.00 C-12 manhole 18'-20' cut EA 1 $7,350.00 $7,350,00 C-13 8" pvc(SDR 26) O'-6'cut LF 1,578 $17.20 $27,141.60 C-14 8" pvc (SDR 26) 6'-8'cut LF 2,879 $22.20 $63,913.80 C-15 8" pvc (SDR 26) 8'-10'cut LF 1,646 $30,70 $50,532.20 C-16 8" pvc (SDR 26) 10'-12'cut LF 1,170 $41. 00 $47,970.00 C-17 8" pvc (SDR 26)12'-14'cut LF 238 $49,00 $11,662.00 C-18 8" pvc (SDR 26) 14'-16'cut LF 1,043 $58.00 $60,494.00 C-19 8" pvc (SDR 26) 16'-18'cut LF 564 $69,00 $38,916.00 C-20 concrete encase 8" pvc LF 40 $75.00 $3,000.00 C-21 6" sewer laterals LF 2,492 $12.50 $31,150.00 C-22 sewer c1eanouts EA 76 $87,00 $6,612.00 C-23 Television Inspection (2) LS 1 $26,500.00 $26,500.00 ALTERNATE Blasting or Mechanical C-24 Excavation LS 1 $7,500,00 $7,500.00 TOTAL $769,391.60 COST TO COMPLETE 50% remaining x $769,391.60 = $384,695.80 Agenda Item No. 16A 10 October 28, 2008 Page 10 of 16 FIDDLER'S CREEK UNIT FOUR PHASE ONE ENGINEER'S OPINION OF PROBABLE COST UPDATED: 2/19/2003. 11/29/04 SCHEDULE "D" POTABLE WATER DISTRIBUTION Includes furnishing and handling of all required materials, joint restraint, thrust blocks, connections to other pipelines, all excavation (including rock and over-excavation if necessary), dewatering, bedding material (if necessary), pipeline installation, back filling (imported fill if necessary), compaction, compaction testing in roadway areas, pressure testing, disinfecting pipelines, flushing, clean-up including resodding areas previously sodded, seeding all areas disturbed by construction, providing complete as-built drawings and other items necessary to complete the system and provide the Owner, DEP and Collier County with a complete working water distribution system as shown on the drawings and specified in these contract documents. ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE D-I 10" Gate Valve & Valve Box EA 20 $1,384.00 $27,680.00 D-2 10" CL 150 PYC (DR 18) LF 10,872 $24.90 $270,712.80 D-3 10" CL 200 PVC (DR ]4) LF 380 $27,10 $10,298.00 D-4 Temporary Blow-off wi gate valve EA 1 $] ,710,00 $1,710.00 D-5 3/4" water service wi meter box EA 76 $1,350.00 $102,600,00 D-6 4" conduit for water service crossing LF 1230 $5.50 $6,765.00 D-7 Temporary Bacterial Sample Point EA 2 $370.00 $740.00 D-8 Permanent Bacterial Sample Point EA 2 $890.00 $1,780.00 D-9 Fire Hydrant Assembly Complete EA 34 $2,130,00 $72,420.00 ALTERNATE D-lO Blasting or Mechanical Excavation LS 1 $3,500.00 $3,500.00 TOTAL $498,205.80 COST TO COMPLETE 50% remaining x $498,205.80 = $249,102,90 Agenda Item No. 16A 10 October 28, 2008 Page 11 of 16 FIDDLER'S CREEK UNIT FOUR PHASE ONE ENGINEER'S OPINION OF PROBABLE COST UPDATED: 2/19/2003,11/29/04 SCHEDULE "E" IRRIGATION DISTRIBUTION Includes furnishing and handling of all required materials, joint restraint, thrust blocks, connections to other pipelines, all excavation (including rock and over-excavation if necessary), dewatering, bedding material (if necessary), pipeline installation, back filling (imported fill if necessary), compaction, compaction testing in roadway areas, pressure testing, disinfecting pipelines, flushing, clean-up including resodding areas previously sodded, seeding all areas disturbed by construction, providing complete as-built drawings and other items necessary to complete the system and provide the Owner, DEP and Collier County with a complete working water distribution system as shown on the drawings and specified in these contract documents. ITEM DESCRIPTION UNIT QTY UNIT PRlCE TOTAL PRICE E-l 12" PVC DR-18 LF 9297 $24.90 $231,495.30 E-2 12" PVC DR-14 LF 280 $27.50 $7,700.00 E-3 12" Gate Valve EA 20 $1,384,00 $27,680.00 E-4 Connect to existing Irrigation main LS 2 $500,00 $ I ,000.00 E-5 Temporary Blow-off wI gate valve EA 2 $1,750,00 $3,500.00 ALTERNATE I E-6 Blasting or Mechanical Excavation LS 1 I $6,500,00 I $6,500.00 I I TOTAL I $277,875.30 COST TO COMPLETE 50% remaining x $277.875.30 = $138,937.65 Agenda Item No. 16A 10 October 28, 2008 Page 12 of 16 FIDDLER'S CREEK UNIT FOUR PHASE ONE ENGINEER'S BID TAB SCHEDULE "F" STORM DRAINAGE UPDATED: 2/19/2003, 11129/04 Includes furnishing and handling of all required materials, dewatering, bedding material (if necessary), rock removal and disposal off-site (if necessary), installation, backfilling, compaction, compaction testing in road- way areas, final grading, coordinating with other contractors and utility companies, flushing, clean-up, seeding, sodding of all arcas disturbed by construction, repair of any damage caused by construction and other items necessary to complete the system and provide the owner, Collier County DOT and FDOT with a complete working drainage system as shown on the drawings and specified on these contract documents. Pipe measurement is to the outside of the structures. ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE F-l 15" RCP LF 512 $22.60 $11,571.20 F-2 18' RCP LF 2,342 $26.40 $61,828.80 F-3 24" RCP LF 209 $33.90 $7,085.10 F-4 30" RCP LF 607 $41. 80 $25,372.60 F-5 36" RCP LF 684 $51,60 $35,294.40 F-6 42" RCP LF 190 $69.80 $13,262.00 Type 'CO Ditch Bottom Inlet $1,140.00 $3,420.00 F-7 complete wi grate EA 3 F-8 Valley Gutter Inlet - complete EA 42 $1,765.00 $74,130.00 F-9 18" Flared End EA 10 $950.00 $9,500.00 F-IO 24" Flared End EA 6 $1,000.00 $6,000.00 F-II 30" Flared End EA 3 $1,200.00 $3,600,00 F-12 36" Flared End EA 3 $1,500.00 $4,500.00 F-13 42" Flared End EA 1 $1,900,00 $1,900.00 F-14 Control Structure EA 1 $2,500.00 $2,500.00 ALTERNATE F-15 Maintenance of Traffic LS I $1,500,00 $1,500.00 Blasting or Mechanical F-16 Excavation L8 1 $5,500.00 $5,500.00 F-17 Flowable Fill CY 300 $50.00 $15,000.00 TOTAL $281,964.10 COST TO COMPLETE 50% remaining x $281,964.10 = $140,982.05 Agenda Item No. 16A10 October 28, 2008 Page 13 of 16 FIDDLER'S CREEK UNIT FOUR PHASE ONE ENGINEER'S OPINION OF PROBABLE COST UPDATED: 2/19/03,11/29/04 SCHEDULE liB" PAVING Clearing, grubbing and preparation of roadway rights-of-way, and easements areas as designated by the Engineer in the field including chipping and grinding of all materials on the Owner's property and then disposal of all residue off the Owner's property, all as specified, per acre complete, All work in right-of-way is subject to inspection by the owner, Collier County DOT and FOOT contingent on final acceptance of improvements as shown and specified on the contract documents. ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE B-1 2' Valley Gutter LF 19,688 $4.75 $93,518.00 B-2 Type "E" Curb LF 1,350 $6,80 $9,180,00 B-3 1-1/2" Asphaltic Concrete (Type S-III) SY 28,700 $4.30 $123,410.00 B-4 8" Limerock Base (compacted and primed) SY 38,533 $7.90 $304,410.70 B-5 12" Stabilized Subgrade SY 32,550 $1.50 $48,825.00 B-5 Brick Pavers SF 88,500 $0.34 $30,090.00 B-6 Road Prep & Final Grading SY 32,500 $1.00 $32,500.00 B-7 Stabilized Access Road SY 13,489 $2.00 $26,978.00 B-8 4" Concrete Sidewalk (5' wide) SY 4,538 $15,10 $68,523.80 B-9 4" Concrete Sidewalk (6' wide) SY 6,150 $15,10 $92,865.00 B-lO Signing & Pavement Markings LS 1 $12,000.00 $12,000.00 B-Il Bahia Sod SY 14,000 $0.32 $4,480.00 B-12 Maintenance of Traffic LS 1 $5,500,00 $5,500.00 B-13 Street Lights EA 40 $2,000.00 $80,000.00 B-14 Landscape and Irrigation LS 1 $40,000,00 $40,000.00 TOTAL $972,280.50 COST TO COMPLETE 90% remaining x $972,280.50 = $875,052.4.5 LOCATION MAP Agenda Item No 16A 10 Oclober 28, 2008 Page 14 of 16 '-"" - ","",,-y- ..""""'...... ""'.. ,- ...... 1L1'.1lelI:Itt .........- SITE MAP FIlDLER'S CREEK lNT FlXR. PHASE ONE Agenda Item No. 16A 10 October 28, 2008 Page 15 of 16 RESOLUTION NO. 08-_ A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA AUTHORIZING FINAL ACCEPTANCE OF CERTAIN ROADWAY AND DRAINAGE IMPROVEMENTS IN FIDDLER'S CREEK PHASE FOUR, UNIT ONE, ACCORDING TO THE PLAT THEREOF RECORDED IN PLAT BOOK 43, PAGES 55 THROUGH 61; RELEASE OF THE MAINTENANCE SECURITY; AND ACCEPTANCE OF THE ~NTENANCE RESPONSIBILITY FOR THE ROADWAY AND DRAINAGE IMPROVEMENTS THAT ARE NOT REQUIRED TO BE MAINTAINED BY THE FIDDLER'S CREEK COMMUNITY DEVELOPMENT DISTRICT WHEREAS, the Board of County Commissioners of Collier County, Florida, on April13, 2004 approved the plat of Fiddler's Creek Phase Four, Unit One for recording; and WHEREAS, the Developer has constructed and maintained the roadway and drainage improvements in accordance with the approved plans and specifications as required by the Land Development Code (Collier County Ordinance No. 04-41, as amended); and WHEREAS, the Developer is requesting final acceptance of the roadway and drainage improvements and release of his maintenance security; and WHEREAS, the Engineering and Environmental Services Section of the Development Services Department has inspected the roadway and drainage improvements, and is recommending acceptance of said facilities. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA, that final acceptance is hereby granted for those roadway and drainage improvements in Fiddler's Creek Phase Four, Unit One, pursuant to the plat thereof recorded in Plat Book 43, pages 55 through 61, and the Clerk is hereby authorized to release the maintenance security. Agenda Item No. 16A 10 October 28,2008 Page 16 of 16 BE IT FURTHER RESOLVED AND ORDERED that the County accept the future maintenance and other attendant costs for those roadway and drainage improvements that are not required to be maintained by the Fiddler's Creek Community Development District. lbis Resolution adopted after motion, second and majority vote favoring same, this day of ,2008, DATE: ATTEST: D~GHTE.BROCK,CLERK BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA By: TOM HENNING, CHAIRMAN , Deputy Clerk Approved as to form and legal sufficiency: ~ 7 w'il Steven T. Williams Assistant Collier County Attorney