Agenda 11/18/2008 Item #16E 4 Agenda Item No. 16E4 November 18, 2008 Page 1 of 34 EXECUTIVE SUMMARY Report and Ratify Staff-Approved Change Orders and Changes to Work Orders to Board- Approved Contracts. OBJECTIVE: To enable the Board to oversee the execution of administrative change orders and changes to work orders, and promote accountability in the use of staff authority, CONSIDERATIONS: On April 22, 2003, the Board approved a recommendation to implement a plan to enable changes to BCC-approved contracts (Section XIV, C, Collier County Purchasing Policy) of not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff, Also included in the report are changes to Work Orders, These include work orders issued under CCNA Contracts which are less than or equal to $200,000 (Section VII.C, Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XIV, G, Collier County Purchasing Policy) which are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater), The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above, The plan calls for staff to submit a monthly report listing these change orders from the previous reporting period, Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders, These reports cover period September 23, 2008 through October 23, 2008, FISCAL IMPACT: The total change to contracts is a deduction of $493,586,91, The total change to work orders is $63,662,90, GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action, RECOMMENDATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders Report and Administrative Changes to Work Orders Report and ratifies the listed change orders and changes to work orders PREPARED BY: Diana De Leon, Contract Technician, Purchasing Department - Page J of I Agenda Item No. 16E4 November 18, 2008 Page 2 of 34 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Meeting Date: 16E4 Report and Ratify Staff-Approved Change Orders and Changes to Work Orders to Board- Approved Contracts. 11/18/20089:00:00 AM Item Number: Item Summary: Prepared By Diana Deleon Administrative Assistant Date Administrative Services Purchasing 10/27/20083:18:05 PM Approved By Steve Carnell Purchasing/General Svcs Director Date Administrative Services Purchasing 11/3/20081:19 PM Approved By Len Golden Price Administrative Services Administrator Date Administrative Services Administrative Services Admin. 11/3/20084:12 PM Approved By OMS Coordinator Applications Analyst Date Administrative Services Information Technology 11/4/20089:20 AM Approved By Jeff Klatzkow Assistant County Attorney Date County Attorney County Attorney Office 11/4/20081:57 PM Approved By Laura Davisson Management & Budget Analyst Date County Manager's Office Office of Management & Budget 11/6/20084:45 PM Approved By James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 11/10/20086:25 PM tile://C:IAQendaTestIExnortl 116-Novemher%201 R.%20200RI 16.%?O(,ONSFNT%20AGF.. 1 1/ l?/?OOR ~OO'" OM 0_ =NO E 'M ~;<" " ~Ol E Q.l cu_"O ..of'lllt:!:... ..'!! E 'g1 ~ e g - <l:I:I C. 0 ro Q)..c 0 Q. E -o>UEllICC c: 0 ~ 0 g lit- Q)Z J:1II Ol <{ o & ~ i CD o~~ ~ U " C:.!!! 0 ~; -gg~ .~ E ~ o 0 ~ ~u~ ~Qj~ ; "E ~ ~O~ u ~ " ~ o " w ~ " w o " o ~ z ~ u w > " < ~ 00 z , o < ~ o > - _ 0 c C " 0 o 00 " 0 E :s III oCt ug.... m i: tl E ~ ~ ~ " c E o 0 ~ uu~ iG -g'E c u > ::I ~~ K ~ o ~: " 0_ . ~ e ~ 0_ 0 o c 0 o 0 0 ouoo o ' ~~ E . ~ ~ E ~~go~ aU~~u "0 ClI ... C III ;'e5~e >D..Uuo.. o " " E 0 gz ~ ;;; .; # 8 o M m ~ ; i, '. :;; o o 6 ~ o o N ~ ~, 0; M :;; M m ~ ; .; w '. :;; o o o w ~ '" m w ~ c . ~u ~~ o o " ~ . o ~ .. o o . .. ;::- m~ D.~ D.. - ,.... IY E I '<t <Il '" 0 ~ ~ ~ ::'.g ~ O~~6~~ ~ o " N a o ~ " . ~ o U c o ~ o c o ~ 2 o " o . " 0 E a; i5. g's> 00 ~ - o 0 o~ ~ g o . .~ ~ o ~ > 0 o E E . o o " . . ~ o ~ E o ~ ;:: ~ '" u ~ " c o E o m ~ . ~ o ~ . ~ o ~ ~ , o w E c 2 " E ~ o o . o o ~ . o ~ > ~ E . ~ o " e c o o o " E , . ~ S ~ " N o ~ ~ N o ~ o o '" N ~ 0; ~ ~ o o o o o "' ~ o o 1> ~ ;" ~ o o ~ N ~ .; ~ ~ o a 1> ~ .; ~ ~ c 5 m ~ J ~ j; 'iii ro ~ -~ g- co <V '" <! :2 ~ ~ ~~d;jg-8 <(Zo0iX ~ o iii ~ o N o g ~ w , . . o , <5 . ~ o ~ , E o o ~ E . o o o . ~ c o ~ o ~ ~ o ~ " E . ~ o E , o . o , " o " 15 c o " * o c ~ . E C o E o ~ o ~ o o ~ ~ c E ~ ~ . 0 e :5i: C3 8 ~~ m .2 ~ . 0, . . . ~ ~ ~ g "2 " . 1jjri oS ~ - ";:; ~ o . 0.."0 ~1jj E . ~ o _ m 0 c . o . ~ 0 o ~ 150 ~ g "E ~ ~ "'5< o . * ~ * N ~ o ~ . ~ m '" . M N ~ a o g ~ "' :;; a w ~ ~ " ~ N ~ ~ . . m o ::i M :;i o o o o o '" w ~. :;; . o ..(lJ .-:, o ~ o ~ x o "- c o u ~ > . ~ w "0 N ~ ~ - C "0 00 IlJ OJ Iii 0 "<I" !2' E:' C,'<ClC?iC S' :E~8uL1J ~ o g ~ o M " & ~ ~ # g o w m w ;; m '" ~ co ~ N - W c .0 U o ~ o ~ E 2 ~ o o E E o o . o c o . o > . o o o o > o j o o ~ il N '" ~ ~ ~ ~ ~ w oi ~ o ;;i o o ~, N ~ N '" ~ . o :'::Ill C:-, o ~ o ~ . . o " o 8 . c ~ o o ~ o E ~ ~ Q u ~ o " ONE:! U ..,. <I> l..L. ~8~ ~~ ~~15065 . ~ . ~ o " . m o o ~ o 1; . . ~ . > o ~ ~ , a . " ~ . ,. N . ~ ~ m ;; "' . ;:I; cD o . o '" N ~ ~ . .; ~ . ~ . . ;; . E . E ~ ~ o o c . > o ~ o ~ o . . o ~ ~ 2 ii: ~ 8 ~ ~ , " <j . . ~ U . " N ~ .; M '. ~ . ~ N o .; M . i . ~ ~u ~~ o '" .. ~ u . " ~o: . 0 o 0 ~o [ D.. ~ ~oo 2 i w~ o ~ c c 0 jo ,....~~ ~gg~~~ E ;;; "? <c '0 -g <1looco..<: '" t\I Ir-oUI:t..... . '" . ~ o 1; . . ~ > o m ~ o 23 ~ ~ o o " '5 ~ .; . ~ ~ ~ o o . 2 o o o .; . " ~ . o o U . 1l o jJ .; ~ o ~ . " ~ 2 '" , . 1l ~ . . ~ . . . > ~ ~ " c ~ o ~ o . o " . ~ o . , c o . '" o o . 2 , . . E " . "- o o . . " . o o . ~ o . ~ o , -" o c . . . . - . > 0 , ~ 3~ ~"'''' 00? , o~ , NO <Xi'" .u~Q) ~Q) E Q.J co- "0 Q.).ol&i ~ c ~Ela5~g CO ID.c (.) i E "0 > U E < c: 0 ae. e 8'" wZ -m Q) <( . ~ ~ la m .~~ ~" - ".0 ~~ "Cue :: E 2: "> C E &8~ II> ... g ~ . 0 C~~ . " ~o u ~ - " o " w " " w o " o ~ . _ ~ c: c _ , . ~ 0 :: Cl. E , . < 08'" m C tl 5 ~ ~ ~ 88~ u w > " ~ " " z , o < "iii ale '~8 e g '0:; m 2:~ o <~ 10 CI _ iii € ~! . _ 0 ~ c . . 0 ~ OU" o . z~ E . ~ :g E ~~go~ o tl e ~u "0 4l _ c: Q> ;'~ g ~ ::: > l1. 0 0.0.. . " " E 0 ~z ~ m ~ * e_ rn ~ e " m - ci m ro ~ o ~ ; ro c: ~ '" o o ci M W <i N " ;;; o o ci M W <i N " ;;; o o ci M W <i N " ;;; . ~?= ~" ~~ ~ o < 00 . c Q " o c E E o u E * c... 1\I l() ~ '",~ al <") 01:; III ~ ~ ~ ai ~ c, cJ5z~6~:3" ro Q - Q o w jj '0 u . w '" o " . c . '" " ~ M ci " c: M ~ :;; w <i m - c: ;;; N W N m N ;;; o o oi W N c: ~ N c: ;;; N m M ~ <i ro - c: ;;; ,,; . ~ 2 ~ 8 m w N g N c: ;;; . ~?= ~~ ~ * c ~ ~ . 5. " ~ . '" . c E E i5 " " " o u 01: " o " c o I o u .. ~ u . . ~ ~~ .Q 10<1>'" ~ ~ ~ g>~ c: 0 , III III l\IN<D-'=J:: ><noUU) 0; m c . U 15 . . ., . > o ro o ij; o ~ - m ~ OS . c Q . . [) " ~ ci " ~ ci " c E E . 5> o Q, " ~ c . ~ . " . 5. " . c . ~ .. c g ~ ~ . ~ c . . ~ e . ~ . ;; 2 . . ~ . . ~ 5 e u ,,; . 5 ~ ~ ~ go . '5 ~ ~ . ~ . ~ c ~ o ~ . :ffi . . E ~ c . . ~ .. c o . i3 ~ . ~ > o 5. o " o o :5 ro ;t w ~ 8 ~ - ~ " M ~ o o ci - M, ;;; W ~ o o ~ '" ;;; w ~ o o ~ - " ;;; N ~ . . ~~ u ~ . ~ u ;; ~ vi ~ U . .s ::i ~ ~ ~ (J)~~ s;:o * ~ OIl ~~~~~ Wll)OUCl 0; ~ c . ~ u 15 . . E . > o ro o ij; o a ro oJ- ~ N 'C ~ " . . ;; . c E o '5 u ~ u . .. ~ . u " 8 # o o 9 M ~ <i m ro g N ri M ~ 2 " c " . u . ~ c !!! ~ c . c .2 . ~ :!; . ~ . c . ~ .e o u ,,; ~ c . .. u ~ . ~ " . o " c . . " ~ . E ~ o C "C .~ . . ~ -c o 5 ~~ 2 . . ~ ~ f5 ~ '" -, . ~ E o ~ .~ "C . - '0 ~ 5. 0 ~ ~ g i :g .Q ." ~ .~ ~~ o . ....~ " c . . ~E c . . . ~ . u . o ~ ~ ~ .~ ~ . ~ > C o . o o o o o c: o ~ - ro o ~ N N M .. M ~ M ~ <i rn ro oi o ~ ri M ~ o o g ri M ~ <i M ~ . . ~~ . ~ ~ . u c ~ o > U Q.; ~ (fJ "' "=" i:)' c - c o '" oJ) III U 0 go. Cl ~~~~~ l<'::lOOr.)u.J ro ~ a rn # N ro " " ~ o M ro rn rn m. ;g M ri M ~ <i M M J: E o Q . .~ u . c c o u ~ c . .~ j' " . E ~ 5 ~ . ~ . . u ~ . ~ c i3 o " " . " . u ~ c . E E 8 c T o ~ M o ci ~ ;;; - ro o ~ N N M ~. M ~ M ~ w m ro oi o N ri M ~ 8 oj ~ ri M ~ 05 M ~ . . .-= u "Qa: . ~ 5 . .1: " c Q .. " u . ;; i3 . " o " . " . u . c u .Q :; U Q.; ~ (Jj v. U">i)' C - C o 0> (ll 4.1 ;;~~~~ r:~";'.cE "ll)OUW 0; ~ c . ~ u o . . E . > o ro o a a e . . o ~ " . ~ . c . o . ~ . c ~ t . ~ . ~ ~ ~ l " o 11 .. . 'c ~ .. 8 w . " .. ~ o " 0; ~ c . o u 15 . . ., . , o ~C07 OM 0_ =NQ It .U') ~;"'Q) ~Ol E (j) CU_"D .nl'lll~~- 2E'g'~eS - III ~ Co 0 CO Q) .c () Co E -o>UElll<e c:: 0 ~ 08'" wZ ~CD Ol <1: . ~ :? i ; .~~ ~ u " u.o ~;s ~~g .~ E ~ ~8~ ~c;g i "E ~ ~o., u ~ " " o " " " " " o " o " o Z ., r o " ~ " " " ~ Z " o ., ~ . c e g . .0 :: Co E o . ., U~... m e ti g Ql ~ 0 ~g~ UU~ ~- . . C .~tj e 5 ';: m ~~ o .,~ " . - ~~~ . - " . c . .0. 00"' o ci Zz Ql ~:>> <l> E . .. '0 E :i~go:i o <:i ~ & ti '0 Ql.... l: <l> ~'eg2e ;>a.uuc.. . ~ o E 0 ~z " ~ N * ~ o o M 00 N 00 M .; ~ M ri M ~ o o ri 00 M ,; ;;; ~ 00 g N N M .; M ~ M 00 00 00 00 .; ~ M ri M ~ o o " o 00 ri M ~ oj M ~ . . ~ii . " ~ . o ~ is ~ '5 <ll ~ <D~ o ~ 0 o 0> Q) 0.> (j 0 ~ Ol 0> ~~~~~ ~.oouw 00 o " ~ * ~ o * M o o o o ~ o 00 '" m 00 :;i o o ~ ~ 00 ~ ~ . ~ i5 ., " > " o ~ u o . . > . ~ i5 o o ~ " o g i5 u . " o ~ u o . ci o " o o :c i " . . '" " ~ ~ " , ~ u " ;;; s o o . ;;; ~ o " o o ~ 00 00 '" M 00 :;i o o ~ 00 '" 00 00 N ~ o o o o " g ;;; . . ':::u "5n-: . " ~ " x o ~ . 0 " ., o 0 . 15 N ~ U M Q) 0 ~~~ ~~ 0. ~ o..c:: Q (I).riOUU ,; 00 c . ~ " o , . .~ > o 00 o M 25 ~ ~ ::: o * o o o o o M N 00. 0; ;j; o o o ~ o o ~ 00. 0; ~ ~ . o . E a o u o 2 U . 15 6. . ~ o ~ E ~ ~ , . 9 . u < ~ ~ o ~ ~ o 6. , ~ ~ . . o , o ~ o o o M N 00. 0; ~ ~ o o M N 00. 0; ~ ~ 00 ~" u ~ " ~ . E . ~ ~ . " C> '" u:; ] ~ ~~ ~ ~:.6 .~ <5 UZOUI- ,; 00 c . ~ " '0 , . ., . > o 00 o <D " ~ m > ~ ~ ~ > u o $ ~ ~ ~ ~ ,; * M 00 ~ M ~ ~ ,,; M ~ ~ 8 o ~ ,,; ~ ~ 00 o " ~ " . ~ o o o o o <0 ~ ~ ~ s . u . E e c o " U ~ . ~ o ~ ~ M m <0 00 m ~ o o o 8. o ~ ~ ~ ~ . ~ ~ u u . 9 " , " 8 ~ 2 . > . u iD m " x " > x " u . ~ ~ . ~ u ~ o " . . ~ii . " 1) 2 ~ ~ ro ~ Q.; -;; g 'i m . u . . ~ N . -, 0 <ll U) o 8 ~ g>~ .S! ~ M ~ ~ ><noOUl ,; 00 c . ;:; '0 , . , . > o 00 o <D " ~ * ~ * o 0; . ~ . 15 . c . . E u c o " ~ ~ o o '" ~ m <0 ~ 00 " ~ o o o ~ 00 N ~ o 2 . u ~ i5 o E o o ~ 00 '" M 00 N ~ ~ . g o , ;;; . " . o ~ o " g u c o o ~ . 5 2 . o . C ~ o 6. o " , " ~ . . o < ~ " o 2 i5 o . . o ., K o " o o m o 00 '" ~ 00 N ~ o o 0; 8. o 00 ;; . . ~~ . " ~ " x o ~ . c " ., ~ N ~ M . 0 "''''.... 0>"<: ~~~~~ (JJu;ouu ,; 00 o . ~ " 15 , . "E . > o ro o ~ " ~ E o , " ;; . c . 00 x ~ c ., . 5 9 " . " . '6' . ~ " , . o " ~ . " i5 . "' o .~ x . ~ " o " ,; 00 c . ~ " '0 , . ., . > o ~gs~ 0_ ~< -N 0 ",'" ~::: ~ E OJ roc 'i ID..c tg,. OZI > c ==E;~K5 ro Q.l .c U li E "0 > 0 E 0( CO;ae 08 tII- O)Z .t:ctl '" <( . 11, ~ ; :>> ~t5'E u .0 ~:,s ;:'gg ~ E ~ ~8: CI .. g ~~ ~ ~o" u ~ ~ ~ o ~ w ~ ~ w o ~ o ~ . , - _ 0 C C > , . ~ 0 :: Co E , '" u8w m E ti ~ CD ~ 0 ~~~ uu~ J W > ~ ~ ~ ~ z " o < 'ii ijle -ij,8 e 5 -;: III l5:~ o <~ " . - Eti~ - . . .... .. .- . _ u ~ C . . 0 ~ <>u~ ci ci Zz Ql ~ i5 III E .... -0 E ~~go~ ~ ti ~ & ti ~ '~g ~ ';; >c..UUll.. . " <> E 0 ~z ~ ~ ~ ~ ~ ;; 0; N . ~ ~ ~ ~ ,,; ~ 8 ;; M ai :;; o o ,; ;; a; ;;; ,,; ~ N . ~ M ~ ai M ~ ,,; ~ o o ,; ;; a; ;;; ,,; ~ . . ~~ . ~ c Q I o u ~ o E . is io . D " ~ o 0"5 ~ . ~ fe <l> 0:: ~8~ ~~ Ql ~ r--...c 0 OlOOUU) ~ e ;; ~ ~ ~ ~ M ,; .. C . ~ C . . ~ c ;;; . c . ~ o ~ ,j c ~ ~ ~ . u ~ & , ~ C ~ . ~ ~ " ~ o u ~ o o ~ .. " E . " .. ~ :E g R . ~ ~ . .; C E o '8 ~ ~ M o ~ 0; ~ ;; ;1; o . . ~. . :;; o N ~ ~ ~ a; 00 M ~ o N ,,; ~ ~ a; 00 M ~ o N ~ ~ ~ a; 00 M ~ 6 'C . " . ~ . & o u u o " ,; c " ;;; 2 ;; " . ;; g~ . tj"iii o . D.V . " u c .!2 8 ~~ ~-g ~-g . q;-'" g>~ . ~ ~ c U 0 o~ . B .~ .~ . , , 0 o E ~u ~o: ~ . ~ ~ ro c . ~ 3l ~ c . ~ ~ 2 Ql 4 ,-~ W .. ~;;;; Cl a; ~g~~ii O",oU(.9 00 ~ " ~ ~ fo M ~ * fc M ~ 00 M ,,; 8 ai o o oi ~ ~ W M . "' M " o ~ ~ . . ;f oi ~ o ~ ,,; :J; . . oi ~ o w ,,; . . .. ~ oi ~ . 1i ~ . . ~2i . ~ ~ E ~ u . ); 11, . ~ o . . > . 1: ~ , ~ o . . u ~ ~ .8 IJJ '1: <D ';;; ~ ~ ~ g' 0 ~<:t:"t~~ <l:Z6u!.'5 " :g . o ~ ;; o c . ~ u 15 . . .~ . , o 00 e N " ~ ;; ,,; 00 ~ '" ; . " ~ c 8 " ~ ~ o ~ " . E 2 . . u > ~ .. o 2 . ~ . . " . ~ o ~ . ;; e " 3 B ~ E' iE 13 ;; o c . ~ u 15 . . .~ ~ o ~ Agenda Item No, 16E4 November 18, 2008 Page 7 of 34 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Gordon River Water Qualltv Park (Freedom Park) PROJECT#51018 PROJECT MANAGER: Maraaret Blshoo BIDIRFP #: 05-3774 MOD #: 12-,PO#: 4500046366 WORK ORDER #:N/A DEPARTMENT: Road Maintenance CONTRACTOR/FIRM NAME: CH2M Hill. Ine, Original Contract Amount: $ 599.850,00 (Starting Point) Current BCC Approved Amount: $ 1 ,391 ,682,00 (Last Total Amount Approved by the BCC) Current Contract Amount: $1,454,417.93 (Includin9 All Changes Prior To This Modification) Change Amount: $ 0.00 Revised ContractIWork Order Amount: $1.454.417.93 (Including This Change Order) Cumulative Dollar Value of Changes to this ContracllWork Order: $ 854,567,93 Date of Last BCC Approval 6/12/07 Agenda Item # 16B5 . #.5/ Percentage of the change over/under current contract amountK:...% Formula: (Revised Amount I Last BCC approved amount}-l CURRENT COMPLETION DATE (S): ORIGINAL: Seotember 19, 2008 CURRENT: March 19, 2009 Describe the change(s): The SFWMD reauested additional information to process the pennit modification for the pump station for the Gordon River Water Qualitv Proiect, Additional review and desian time is necessary to complete the submittal. Specify the reasons for the change(s) r 1. Planned or Elective r 2, Unforeseen Conditions r 3. Quantity Adjustments r 4, Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r; 6. Schedule Adjustments Note: One or more may be checked. depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: information was received from the SFWMD for the pumo station penn it modification, submitted. the permit will not be issued. A reauest for additional If the information Is not This change was requested by: rlContractor/Consuttant PI Owner "Using Department C COES Coesign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: p- Ves r No Contract Specialist Oate: <t-rr --0 '/(' Date: 1k61f)~ I , REVIEWED BV: L u Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No. 16E4 /) November 18, 2008 "'- Page 8 of 34 PROJECT Njl.ME: Roberts Ranch Drivewav Entrance PROJECT #: 08-5056 PROJECT MANAGER: TImothy England BIDIRFP #: 0&-5056 MOD #: ~POtt:450009449_WORK ORDER #:_N/A_ DEPARTMENT:_Museum_ CONTRACTOR/FIRM NAME: Ace Asohalt I) 7'rLV~ ~ Original Contract Amount: $ 74.828.00 (Starting Point) Current BCC Approved Amount: $ 74.828.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 74.828.00 (Including All Changes Prior To This Modification) Change Amount: $_6000,00 Revised ContractlWork Order Amount: $ 80.828.00 (including This Change Order) Cumulative Dollar Value of Changes to this ContractlWork Order: $ f.,., 000. 00 Date of last BCC Approval_May 13 2008 Agenda Item 16 03_ Percentage of the change under current contract amount ~.02_ % Formuia: (Revised Amount I Last sec approved amount)-1 .)tJf(' CURRENT COMPLETION DATE (S): ORIGINAL: [Ie~,~~t 3 esse CURRENT: October 3 2008 Describe the change(s):_ Provide additional asphalt, limerock, excavation, labor and equipment related to said project to; widen small section of Driveway, to improve safety and access to large Tour and school Buses, This section is to be designated by Director and New Project Manager. '11....6 ~/lh 'lI 6' (!p ~('.~~ J.,.... b..-" ..../J.JJ_<( Specify the reasons for the change(s) r 1. Planned or Electiv@2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: _The Driveway would be Restricted to smaller vehicles. large group visitors maybe put off from coming to the Pioneer Museum due to reduced access. Safety issues may rise, if the section of driveway is not widened. This change was requested by: r1Contractor/Consultant rl Owner P'I Using Department r CDES r Design Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: P Yes r No APPROVED BY: ~ bL-'1 J-rm~ Date: 9ILf~(/V , REVIEWED BY: Revised 11.19.2007 Agenda Item No. 16E4 3 t}ovREctNkB PROJECT NAME: EmerQencv Service Complex PROJECT #: 52160 PROJECT MANAGER: Hank Jones 9/!iJ(. BIDIRFP #: 03-3448 MOD #: ~ PO#: 4S00012091 WORK ORDER #: r -ti/J DEPARTMENT: Facilities ManaQement CONTRACTOR/FIRM NAME: Harvard Jollv Of CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Original Contract Amount: $ 1.859.000,00 (Starting Point) Current BCC Approved Amount: $ 2.187.297,50 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 2.333.094.47 (Including All Changes Prior To This Modification) Change Amount: $ 16.830 $ 2.349.924,47 (Including This Change Order) Revised ContracUWork Order Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ 490.924.47 Date of Last BCC Approval September 13 2005 Agenda Item # 10H Percentage of the change over/under current contract amount Fonnula: (Revised Amount / Last BCC approved amount)-1 7.44 % CURRENT COMPLETION DATE (S): ORIGINAL: 1/02/06 CURRENT: 4/2009 Describe the change(s): Preoare furniture bid documents. coordinate furniture vendor review and recommend furniture selection. Includino in the prooosal are three new orofessional oositions and thev are 11 Director of Interior of Deslon @ $100 oer hour, 21 Tech III @ $85 oer hour and 31 Desion Assistant@ $55 oer hour. Specify the reasons for the change(s) G 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5, Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Bid documents will not be oreoared and may delav of tenets movinQ into the ESC, This change was requested by: r1ContractorlConsultant f'1 Owner n Using Department n CDES rDesign Professional r1Regulatory Agency (Specify) rOther (Specify) E"yes CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r No APPROVED BY: Oate: 1/3.(ql/ , REVIEWED BY: Date: 9 (3iJ1UiJ1 Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No. 16E4 LI November 18, 2008 I Page 10 of 34 PROJECT NAME: Sheriff Fleet PROJECT #: 52009 PROJECT MANAGER: Claude Nesbitt BID/RFP #: 06-3914 MOD #: 002 PO#:45-91804 WORK ORDER #: DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Wriaht Construction Original Contract Amount: $ 9,272,848,00 (Starting Point) Current BCC Approved Amount: $9,272,848,00 (Last Total Amount Approved by the BCC) Current Contract Amount: $8,963,588,76 (Including All Changes Prior To This Modification) Change Amount: $(32,429,26) Revised ContractIWork Order Amount: $8,931,159,50 (Including This Change Order)- Cumulative Dollar Value of Changes to ( 31'1 J h ~ 1': So) this ContractIWork Order: $(33e,668.&Q) . Date of Last BCC Approval January 15, 2008 Agenda Item # 10 A Percentage of the change over/under current contract amount -3.68% Formula: (Revised Amount I Last BCC approved amount}-1 CURRENT COMPLETION DATE (S): ORIGINAL: Mav 2009 CURRENT: Mav 2009 Describe the change(s): DMP - Fabricated fire prevention systems materials Specify the reasons for the Change(S),e( 1. Planned or Elective 0 2. Unforeseen Conditions 0 3. Quantity Adjustments 0 4. Correction of Errors (Plans, Specifications or Scope of Work) 0 5. Value Added o 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: omission of a cost saving opportunity This change was requested by: CIContractor/Consultant vd' Owner C'I Using Department n CDES "'Design Professional CIRegulatory Agency (Specify) COther (Specify) Dyes JrNO CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: This form is to be signed and dat~ APPROVED BY: tl\~~,i./1 k Vi projec~nager /., YJ Specialist Oate: 1~-b3>-2E)O~ REVIEWED BY: Date: 10 -3 -;;2CJoY , Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No, 16E4 ~dV~JftJ~~ a2icJ !: PROJECT NAME: Radio Road MSTU Phase One Landscaoa and Irrlaatlon Proiect PROJECT#:158-152522.763100-4 PROJECT MANAGER: Oarrvl Richard BIDIRFP #: 08-5004 MOD #: 110nel POt: 4500091106 WORK ORDER #: nla DEPARTMENT: Altemative Tranaoortatlon Modes CONTRACTORlFIRM NAME: Hannula Landacaaina. Inc. Original Contract Amount: $ 464,434.62 (Starting Point) ~.434,62 (Last Total Amount Approved by the BCC) $464,434.62 . (Including All Changes Prior To This Modification) $1-19,114,951 DELETE Currant BCC Approved Amount: Currant Contract Amount: Changa Amount: "R8vloed ContractIWOrk Order Amount: ~.319.67 (Including This Change Order) RECEIVED Cumulative Dollar Value of Changes to thlaContractIWorkOrder: $ (-19.114.951 SEP 3 0 :~OC;3 'J'ransportation ATM Dart. Date of Laat BCC Approval. Dee, 11 , 2007 Agenda Item # ~em 16,B,4 Percentage of the change over/under currant contract amount -4.1i (under contract) % Fonnula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 7-29-08CURRENT: 10-10-08 fincludes davs added for edministrative orocessinol Describe the change(s): (1) Plant Material Deletes. 121 Plant Material Adds. (31 Add HOPE Class 150 SOR 11 for Irrlaatlon sleeves. 14) Add Blow Off Assemblv at Devonshire Blvd. 151 Delete Pavers. (51 Add Valv88. 171 Add Electrical Work at Mlxlna chamber. lal Relocate Ex. CraDe Mvrtles. 191 Add bubblers. (101 Add flll dirt. 111\ Add Flush Assemblv Isee attached tabulation for auantitles and valuesl Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeaeen Conditions . 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work). 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative Impacts to the project if this change order were not processed: Not Drocessina chanae would result In material belna Durchased which could not be Installed due to TECM Chanaes In roadwav construction. Irriaatlon svstem would not function DroDerlv. LandscaDlna Installation would not be comDlete. This change was requested by: J'7Jcontractor/Consultant n Owner n Using Department r: COES Eoeslgn Professional nRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes P' No This fonn is to be signed ~ APPROVED BY: Date: q 09 , M Dept . REVIEWED BY: Date: /0 - 3 -ot Contr ct ecialist, Rhonda Cummings, Purchasing Dept Revised 1 L19.200lf' (Ji .~, j, /l . /~ fl(/L?- U{//yv}'VL.v.'-'}:1 ) (j Agenda Item No. 16E4 b November 18", LUUl:S Page 12 of 34 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECTNAME: Blda, UF" Generator & Electrical UDarade PROJECT#:08-5035 PROJECT MANAGER: Robert Fuentes BIDIRFP #: ~ MOD #: 1 Revised PO#: 45-.00094798 WORK ORDER #: NIA DEPARTMENT: Facilities Management CONTRACTOR/FIRM NAME: Southeastern Communications Servo Inc: Original Contract Amount: $ 1.226,635,00 (Starting Point) Cur"'nt BCC Approved Amount: $ 1 ,226.635,00 (Last Total Amount Approved by the BCC) $ 1 ,226.635,00 (Including All Changes Prior To This Modification) Current Contract Amount: Change Amount: $ ( 330.841.90 I Revised ContractlWork Order Amount: $ 895.793,10 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ ( 330.841.90) Date of last BCC Approval 5/13/08 Agenda Item # 10G Percentage of the change over/under current contract amount.~ ./ ]Jc,.q1 Formula: (Revised Amount 1 Last BCC approved amount)-1 CURRENT COMPLETiON DATE (S): ORIGINAl: TBD CURRENT: TBD Describe the change(s): Direct Purchase of Cummins Generator and Transfer switches. Equipment costs $312,115.00. Sales tax Savings is $18,726.90. Specify the reasons for the change(s)" 1. Planned or Elective r 2. Unforeseen Conditions c:: 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r' 5. Value Added . ("' 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: NIA This change was requested by: rlcontractor/Consultant 11'I Owner rI Using Department C COES Coesign Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECI NEGOTIATIONS: .. Yes r No Th is form is to APPROVED f Date: ~$ 10/q/OO , REVIEWED BY: Date: Revised 11.19,2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No. 16E4 7 November 18. 2008 Page 13 of 34 PROJECT NAME: Sheriffs Special Operations Buildlna PROJECT #: 52002 PROJECT MANAGER: Hank Jones BID/RFP #: 06-4025 MOD #: 10 PO#: 4500073809 WORK ORDER #: N/A DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Vanderbilt Bav Construction Original Contract Amount: $ 10.250.269.00 (Starting Point) Current BCC Approved Amount: $ 10.250.269.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $10.786.439.21 (Including All Changes Prior To This Modification) Change Amount: $ 12.192.62 Revised ContractIWork Order Amount: $10.798.631.83 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ 548.362.83 Date of Last BCC Approval: October 24. 2006 Agenda Item #: lOB Percentage of the change over/under current contract amount 5.35% Formula: (Revised Amount 1 Last BCC approved amount)-l CURRENT COMPLETION DATE (5): ORIGINAL: 3/22/08 CURRENT: 4/9/08 Describe the change(s): All additional time and costs associated with chanaes as autlined in: 1) COP #77 Reaal Electric Time & Material Chanaes includina addition of a fiaa Dole Iiaht IDer VL memo dated 4/24/081. chanaino out the hiah bav Iiaht fixtures IH & H11 in the hanoar to metal halide provided bv SESCO. add two (2) 20 amp circuits with breakers to aaraae 147 and installation of revised snook liahts (oer SCODe of work on voided COP 71 ); and 2) additional aenerator tesUna and reDroarammina. Specify the reasons for the change(s) r. 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments 4. Correction of Errors (Plans, Specifications or Scope of Work) r. 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the changers). Identify all negative impacts to the project if this change order were not processed: Non compliance with fire. landsc80ina mechanical and electrical codes. ooerational requirement. potential structural defects, and aesthetical imorovements This change was requested by: PIContractor/Consultant Owner 171 Using Department C CDES Design Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r;;- Yes r No APPROVED BY: Date: / d/r; I tJ D' /~/ 'f/oS REViEWED BY: Date: Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No. 16E4 g November 18, 2008 Page 14 of 34 DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: BSSW Architects. Inc. PROJECT MANAGER: Hank Jones .. f!J ~Ci [0/;1/' WORK ORDER #: N/A BID/RFP #: 03-3489 MOD #: 6 PROJECT #: 54261 PO#: 4500015812 PROJECT NAME: Golden Gate Librarv Original Contract Amount: $ 281.275.00 (Starting Point) Current Bee Approved Amount: $ 651.375.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 651.375.00 (Including All Changes Prior To This Modification) Revised Contract/Work Order Amount: $ 33.475.00 $ 684.850.00 (Including This Change Order) Change Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ 403.575.00 Date of Last BCC Approval: Julv 25.2006 Agenda Item # 16.E.1 Percentage of the change over/under currenfcontract amount 5.14% Formuia: (Revised Amount 1 Last BCC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 01128/2006 CURRENT: 07/12/2008 Describe the change(s): Architectural and EnClineerinCl services to relocate dumpster enclosure. traffic islands. curbs, drainalle, irriClation and landscapinCl. Correction of a defective column at the entry and revisions of easement leClal descriptions. revision of turnover documents. revisions of as built drawlnqs. coordination of client contractor utilitv efforts and additional construction administration services for punch list corrections and construction defects corrections. . Specify the reasons for the change(s) ~ 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r: 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order Were not processed: Inadequate 1 non-functional site desiqn and unacceptable project aesthetics. This change was requested by: rlContractor/Consultant 171 Owner rI Using Department r: CDES rDesign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: ~Y es r No .- REVIEWED BY: Dale: J.Qj ~ 10 15-j Dale:~ Revised 11.19.2007 ~JPQd~~O. 16E4 /0 1~~~8. 2008 Q ~ RECEPft~". of 34 -, CONTRACTIWORK ORDER MODIFICATION _ IV r;u CHECKLIST FORM VJ I' / PROJECT NAME: Emeroencv Service Center PROJECT #: 52160 PROJECT MANAGER: Hank Jones f--V BID/RFP #: 04.3609 MOD #: 14 PO#: 4500030516 WORK ORDER #: N/A DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Kraft Construction Comoanv. Inc. Original Contract Amount: $ 38.533.902.00 (Starling Point) Current BCC Approved Amount: $ 34.322.150.87 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 33.509.896.43 (Including All Changes Prior To This Modification) Change Amount: $ (300.000.00) Revised ContractIWork Order Amount: $ 33.209.896.43 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ (5.324.005.571 Date of Last BCC Approval: September 25. 2007 Agenda Item # 16E7 Percentage of the changeover/under current contract amount ~3.24% Fonnula: (Revised Amount I Last BGe approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: 12/2008 CURRENT: 0312009 Describe the change(s): Credit to delete the buill-in command center includina associated eauipment. wirina. and connections in the EOC room A.336. This amount was Included as an Allowance to our BldQ GMP. Sp;.cify the reasons for the change(s) (.' 1. Planned or Elective C 2. Unforeseen Conditions r 3. Quantity Adjustments 0 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s}. Identify all negative impacts to the project if this change order were not processed: Credit was not realized. This change was requested by: CIContractor/Consultant PI Owner rI Using Department C CDES rDesign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes r No APPROVED BY: Date: /I)(/i>( ors' . IvfrlJ!og I I REViEWED BY: Date: Revised 1 Ll9.2007 PROJECT NAME: Emeraencv Service Center PROJECT #: 52160 PROJECT MANAGER: Hank Jones Agenda Item No 16E4 10 Nove~~~pJ~~ ~ Rce_ CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM BID/RFP #: 04-3609 MOD#: 15 PO#: 4500030516 WORK ORDER #: N/A DEPARTMENT: Facilities Manaoement CONTRACTOR/FIRM NAME: Kraft Construction Comoanv. Inc. Original Contract Amount: $ 38.533.902,00 (Starting Point) Current BCC Approved Amount: $ 34.322.150.87 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 33.209.896.43 (Including All Changes Prior To This Modification) Change Amount: $145.103,40 Revised ContractIWork Order Amount: $ 33.354.999.83 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractlWork Order: $ 15.178.902.17\ Date of Last BCC Approval: Seotember 25.2007 Agenda Item # 16E7 Percentage of the change over/under current contract amount -2.82% Fonnula: (Revised Amount I Last BCe approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: 1212008 CURRENT: 0312009 Describe the change(s): Void - PaQe Mechanical 1 Apolied Dehumidification PO for Material Value and Tax Value. Specify the reasons for the change(s) @ 1. Planned or Elective C 2. Unforeseen Conditions r 3. Quantity Adjustments r: 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Nole: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: This change was requested by: r1Contraclor/Consultant 171 Owner rI Using Department !: CDES CDesign Professional CIRegulalory Agency (Specify) rOther (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r No APPROVED BY: Date: !O~(J joy . /J /;0 lot I I REVIEWED BY: ! Contract Specialist &4fl~ Date: Revised 11.19.2007 .Agenda Item No, 16E4 I \ November 18. 2008 (V'it g pfdg- CONTRACTIWORK ORDER MODIFICATION {' I PROJECT NAME: Emeraencv Service Center PROJ::::K~:::OF::~ECT MANAGER: Hank Jones~ R~IVEO BID/RFP #: 04-3609 MOD #: 16 PO#: 4500030516 WORK ORDER#: N/A DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Kraft Construction Comoanv.lnc. - Original Contract Amount: $ 38.533.902.00 (Starting Point) Current Bee Approved Amount: $ 34.322.150.87 (Last Total Amount Approved by the BCG) Current Contract Amount: $ 33.354.999.83 (Including A1i Changes Prior To This MOdification) Change Amount: $ 19.383,00 Revised ContractIWork Order Amount: $ 33.374.382.83 (Inctuding This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ (5.159.519.171 Date of Last BCC Approval: Seatember 25.2007 Agenda Item # 16E7 Percentage of the change over/under current contract amount -2.76% Formula: (Revised Amount I Last Bee approved amount}-1 CURRENT COMPLETION DATE (5): ORIGINAL: 12/2008 CURRENT: 0312009 Describe the change(s): Furnish all labor. materials. tools. and eQuipment necessary to furnish and install RCO 081 and RCl1074R. drvwall. fire caulk. aalntlno. blockin". 2 additional LCD displavs (ii)911. and 2 additional VGA's displavs l!il911 room A307. Specify the reasons for the change(s) (.' 1. Planned or Elective C 2. Unforeseen Conditions r 3. Quantity Adjustments C 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: This change was requested by: r1Contractor/Consultant P"I Owner rI Using Department C CDES CDesign Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTiATIONS: l' Yes r No This form is to be si Date:~ /6 /3 /Og/ I ' Ie' APPROVED B I I I I I I REVIEWED BY: Revised 11.19,2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Courthouse Annex PROJECT #: 52533 PROJECT MANAGER:Henrv Jones. P.E. BID/RFP #: 00-3173 MOD #: ~PO#:45-100619 WORK ORDER #:N/A DEPARTMENT:Facilities Manaoement CONTRACTOR/FIRM NAME:Spillis Candela DMJM Original Contract Amount: $ 190, 000,00 (Starting Point) Current BCC Approved Amount: $2,936,994.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $2.966,951,00 (Including All Changes Prior To This Modification) Change Amount: $855.00 Revised ContractIWork Order Amount: $2,967,8196,00 \?V (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $2,777,806.00 Date of Last BCC Approval 05/0912007 Agenda Item # 16 E 2 Percentage of the change over/under current contract amount 1.05% Formula: (Revised Amount 1 Last BCC approved amount}-1 CURRENT COMPLETION DATE (5): ORIGINAL: mu~i-phase CURRENT: multi-phase Agenda Item No, 16 4 f ~ ltiovem~r 18. 8 r-:&efJ 34 ~ Describe the change(s): Additional services to revise permitted Fire Protection Documents ,Specify the reasons for the change(S)~. Planned or Elective r 2. Unforeseen Conditions ,p/ 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Fire Protection revisions must be detailed by the Engineer of Record (EOR) and will not be permitted without the participation of sadi EOR This change was requested by: rk;ontractor/Consultant rl Owner rJ Using Department J2" CDES ~Sign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PART IPATION IN NEGOTIATIONS: r Yes r No Date: /4 u/o( Date I b (1& (Di APPROVED BY, REVIEWED BY: Revised 11.19,2007 Agenda Item No, 16E4 3 November 18, 2008 ,( Page 19 of 34 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Toll Feaslbllitv Studv for the Jollev Brldoe PROJECT #: NIA PROJECT MANAGER: Brandv Otero BID/RFP #: 06.3999 MOD #: LPO#: '-{I)- &'?JD2. WORK ORDER #: DEPARTMENT: MPO CONTRACTOR/FIRM NAME: Cambrldoe Svstematlcs. Inc. Original Contract Amount: $481,823 (Starting Point) Current BCC Approved Amount: $481,823 (Last Total Amount Approved by the BCG) Currant Contract Amount: $481,823 (Including All Changes Prior To This Modification) Change Amount: $0 Revised ContractJWork Order Amount: 5481,823 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $0 Date of Last BCC Approval~2I2I07 Agenda Item # 16B7_ Percentage of the change over/under current contract amount_O Fonmula: (Revised Amount 1 Last BCC approved amount)-1 % CURRENT COMPLETION DATE (8): ORIGINAL: June 30, 2008 CURRENT: July 1, 2009 Describe the change(s): Increase contract time bv 366 davs. The contract allows for Phase two to be added. The MPO Board will not make a decision to move to Phase two until after March 2009. Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r. 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The contract will be eXDired whenlif the MPO Board makes the decision to move forward with phase two. The second phase of the studv mav have to 00 out to RFP aaain. This change was requested by: ['lcontractor/Consultant 171 Owner rJ Using Department C COES COesign Professional rJRegulatory Agency (Specify) C Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r;;y es r No APPROVED BY: ~ Date: IDjl6lo~ U,t11~:te: [ D fir; ( () i () I I I REVIEWED BY: " Contract Specialist Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No, 16E4 f LJ November 18. 2008 -, Page 20 of 34 PROJECT NAME :Sheriff SDecial Operations PROJECT #: 52002 PROJECT MANAGER: Hank Jones tlJP BIOIRFP #:03. MOD #: f.. PO#:4500035136 WORK ORDER #: DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Victor J. Latavish Architect. PA Original Contract Amount: $ 670.000.00 (Starting Point) Current BCC Approved Amount: $ 670.000.00 (Last Total Amount Approved by the BCC) Current Contract Amount: S 680.163.75 (Including All Changes Prior To This Modification) Change Amount: $ 55.280.00 Revised ContractIWork Order Amount: $ 735.443.75 (Inciuding This Change Order) Cumulative Dollar Value of Changes to .J 7 S/" this ContractIWork Order: S ,7s....--T tP.5; it VJ. ~ Date of Last Bee Approval 9/21/04 Agenda Item # 16 E 7 Percentage of the change over/under current contract amount 9.77% Formula: (Revised Amount / Last BCC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 4/1712008 CURRENT: 4/31/2009 Describe the change(s): Proposal (dated 10/8/081 for Architectural and EnQineerinQ services for the proposed second floor interior improvements for CCSO offices. restrooms. and modifications to the second means of eQress. Additional Construction Administration services and additional services for CCSO and NAA revisions are included. DesiQn services include Architectural. Structural. PlumbinQ. HVAC. Fire Protection. and Electrical desiQn. plus coordination with the furniture supplier: final desiQn to be delivered to Collier Countv within 45 days from NTP. Specify the reasons for the change(s): County wants to occupy the second floor shell space. Identify all negative impacts to the project if this change order were not processed: Added lease costs. This change was requested by: r Contractor/Consultant r. Owner r Using Department C CDES C Design Professional r Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes P' No Date: / ~ /,(, /0 i I ' /0//';/06" REVIEWED BY: Date: Revised 5,21.2007 CONTRACTIWORK ORDER MODI FICA TION CHECKLIST FORM 15 Agenda Item No, 16E4 Novembelia81 ~Q.Qif D <V ~ Page 'f1'~' p R"' - , ~....D e!;U.L1-_ ""2( PROJECT NAME: Courthouse Annex PROJECT #: 52533 PROJECT MANAGER:Henrv Jones. P,E. BID/RFP #: 00-3173 MOD #: ~PO#:45-100619 WORK ORDER #:N/A DEPARTMENT:Facilities Manaaement CONTRACTOR/FIRM NAME:SDillis Candela DMJM Original Contract Amount: $190.000,00 (Starting Point) Current BCC Approved Amount: $2,936,994,00 (Last Total Amount Approved by the BCC) Current Contract Amount: $2.967,806,00 (Including All Changes Prior To This Modification) Change Amount: $2,850.00 Revised ContractIWork Order Amount: $2,970,656,00 (Including This Change Order) Cumulative DollarValue of Changes to this ContractIWork Order: $2,780,656.00 Date of Last BCC Approval 05/0912007 Agenda Item # 16 E 2 oll- Percentage of the change over/under current contract amount ~ Formula: (Revised Amount / Last BCC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: multi-phase CURRENT: multi-phase Describe the change(s): Additional services to revise permitted civil drawings to show modifications to the exterior grading and the sidewalk adjacent to the Annex generator room. . ,Specify the reasons for the change(S)? 1. Planned or Elective r 2.Unfores~.9-Conditions r 3. Quantity Adjustments [' 4. Correction of Errors (Plans, Specifications or Scope of Work)lv 5. Value Added r 6. Schedule Adjustments Note: One or more may be cheeked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Civil revisions must be detailed by the Engineer of Record (EOR) and will not be permitted without the participation of said EOR This change was requested by: rlContractor/Consultant ~owner rj Using Department C CDES ~eSign Professional rJRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes r No APPROVED BY: Date, 1()/~,lo'j( f to {2-( /()~ REVIEWED BY: r~ Date: Revised 11.19.2007 BID/RFP #: 07-4176 MOD #:10 PO#: 4500087770 WORK ORDER #: N/A Agendati Nov CONTRACTIWORK ORDER MODIFICATION ... CHECKLIST FORM t!J PROJECT NAME: South Reaional Librarv PROJECT #: 54003 PROJECT MANAGER: Hank Jones . DEPARTMENT: Facilities Manaoement CONTRACTOR/FIRM NAME: DeAnoells Diamond Construction. Inc. Original Contract Amount: $ 6.519.813.00 (Starting Point) Current BCC Approved Amount: $ 6.519.813,00 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 5,938.539.42 (Including All Changes Prior To This Modification) Change Amount: $ 18.304.00 Revised ContractIWork Order Amount: $ 5.956.843.42 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ 59S.Sii.SB -!>;"~'1t:,1. 5'ft !;:t-- Date of Last BCC Approvat: September 11. 2007 Agenda Item #: 10E Percentage of the change over/under current contract amount - 8.63% Formula: (Revised Amount / Last BCC approved amount)-1 SURRENT COMPLETION DATE (S): ORIGINAL: 11/1/2008 CURRENT: 11/1/2008 Describe the change(s): All additional time and costs associated willi the changes as outlined in: ~ Add Face Block Under Exterior Siding at Lowered Sidewalks PCO#036 08/14/08; t) Adding y," Stucco Finish Over Concrete at Base of Exterior Colurrms PCO #38 08/21/08: !() Add one Fixture Tvoe XI Exit Light per Fire Inspector's Request PCO #39 08/23/08' Delete Metal Hood Cover for Overhead Door Mark #163 PCO #46 09/10/08' Raise han .n Infini Ceiling Grid PCO #41 08/27/08; '6) Shorten Resin Screen Panels on Circulation Desk PCO# 42 08/28/08: ) Add Corian Sill at Pass-through Window PCO #43 09/02/08;0.6) Move Circulation Desk PCO #044 09/24/08: iflAdd Concrete Slabs at Exit Doors pea #45 09/02/08. Specify the reasons for the change(s) (0' 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: This change was requested by: rlcontractor/Consultant 171 Owner r Using Department C CDES rlDesign Professional rJRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r;;- No , PPROVED BY: Date: {o\'VO( bi/ ID/'2/ !bt I REVIEWED BY: Date: Revised 1 L19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKUSTFORM ~~6E4 /1 ~ R~f~~:;ff PROJECT NAME: Golden Gate Pedestrian Bridae PROJECT II: 600501 PROJECT MANAGER: James Zuver BIDlRFP II: 08-5014 MOD': 1 lone) PO#; 4500091536 WORK ORDER II: DEPARTMENT: TECM CONTRACTOR/FJRM NAME: "'~11tv Entel'llriae USA. Inc. Original Contract Amount: $ 389.576.20 (Starting Point) $ 389.576.20 (Last Total Amount Approved by lhe BCC) $ 389.576.20 (Including All Changes Prior To This Modification) $ 14.964.40 CUmin! BeC Approved Amount: CUmin! Contract Amount: Change Amount: Revised ContractlWork Order Amount: $ 404.540.60 (Including This Change Order) Cumulative Dollar Value of Changes 10 this ContractlWork Order: $ 14.964.40 Data of Last Bee Approval 1/1512008 Agenda II&m # 1684 3,84 % Percentage of the change overlunder CUmlnt contract amount Formula: (Revised Amount / Last BCC approved amounl)-1 CURRENT COMPLETION DATE (S): ORIGINAl: 12/2/2008 CURRENT: 12l2J2fJ08 Describe the change(sl: To add 18 Inches of Rip RaD per review of the allO-t8chnlcal datil to the oltalnaJ 18 inch RID Rao at the oriainal bid Dries of $39.38. ThiB would add 380 SY to Item #10 RiD RaD for a tollIl ;i 780 SY. Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions (0" 3. Quantity Adjustments r 4. Cornet/on of Errors (Plans, Specifications or Scope of Work) r 5. Valua Added r 6. Schedule Adjustments Note: One Dr more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The aeo technical reaulrements would not be met This change was requested by: r1Contractor/Consultant n Owner rI Using Department C. CDES Eoesign Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r;; No This form is to be signed and dated. APPROVED BY: Date: It? /7/0'f5 / ( /O/~I /<< . I REVIEWED BY: Date: Revised I L19,2007 Agenda Item No, 16E4 / November 18, 2008 ~ Page 24 of 34 CONTRACTIWDRK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Janitorial Services BIDIRFP II: 07-4126 MOD#: 1 PROJECT #: . PROJECT MANAGER: Damon Gonzales PO#: ?t<;- 99"(~~ORKORDERII: - - DEPARTMENT:]acilities Management CONTRACTOR/FIRM NAME: ABM Janitorial Services Original Contract Amount: $ 2,144,446.60 (Starting Paint) Current BCC Approved Amount: $ 2,144,446.60 (Last Total Amounl Approved by the BCC) Current Contract Amount: $ 2,144,446,60 (Including All Changes Prior To This Modification) Change Amount: $ (136,438.22) Revised ContractIWork Order Amount: $ 2,008,006.38 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $_(136,438.22) Date of Last BCC Approval_9/12/07 Agenda Item # _10G Percentage of the change over/under current contract amount_~ ( G;# '3(Q) % Formula: (Revised Amount / Last BCC approved amount}-l CURRENT COMPLETION DATE (S): ORIGINAL: CURRENT: Annual Contract_ Describe the change(s):_Decrease in annual services to meet budget constraints. Specify the reasons for the change(s) x 1. Planned or Elective 0 2. Unforeseen Conditions 0 3. Quantity Adjustments 0 4. Correction of Errors (Plans, Specifications or Scope of Work) 0 5. Value Added o 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: _There would not be enough funding approved to maintain current level of service. This change was requested by: llContractor/Consultant x Owner rl Using Department C CDES CDesign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: l Yes x No Date: IV /;;'1 lol- I I 10/ ;{ (/ Or / :U)/~ Date: Revised 11.19,2007 -- Jgg;~ ,0>0_ ~O ~-'" c;gD", zg: Q) E '" 0> ",.0 cu "'En. cu'" ",> cO "'Z 0> <( ~ ~ o ~ w ~ ~ w o ~ o ~ ~ ~ o ~ w w " Z < I o W > ~ < ~ w Z ~ o < o . cP ~ "CI ~.e ~ ~ 0 .u~ ~ E 0 .....g!: ;; " o . III .- "C ~.g>o ~1ll0.llC ~ e " t),g~ .0 ] 'E: ::l .~ :; ~ IV 0 < ";=~ .e.gi: &55 o ~ e ~ 0-< u;=~ . 0 c'E: :I ~:; ~ , " '" (,)~M o .U tu 'Ill U 'i tl c: .:: e! 5 .!2l C E 58:; o E l.l:; i~~ c. 0 . . 0 c. ou"' o z , c ,gz o ~ ~c ;=8 o z . .. E 0 'E ~ ~zoz , .- o (,) lJ) () "C ~ Cell ii e ~'e >l1.Ull. $ . o e ~~ J< a, M o ~ N o M " W M m' w ;;; o ~ M :;; W o W M V ~ ro w ;;; "0- . 0 > ' o 0 , e ~'" "'~ '" z " o ~ w o w- w ;;; u . ~ "" . "Ill .~ "-~ M o 00 9 "' ~ m ~U) ~~ ~~ , m OM 000 ,"0 ~ ro "- "0 o o L " U ~ o L m m" l") Qi S a> Z 10 ~ m<ll ~8ffi~ cs~Bo 00 '2 :; 2> ;f. m N o 13 ~ " o u . E 9 . ~ . "0 0; "0 o o " u "' "- o > ~ J< m N <0 o o ;: v '" o ~ "" o o ~ o o w ~ m' w "0 "0 . 9 "0 o . ;; -" "" ~ o o "0 "0 o o u o . o E " o o o E ro 13 o "0 o "0 9 oi o o N " o o E c. o ~ o "0 o o o " ~ ro a. o E o o o N ~ v' m w o o o N ~ '" m ~ o o <0 N ~ '" m w o w ,,"- "-0 N o 00 o " 00 ~ M ,..:.~ '7~ WM '"" rO E g ~ ro , ro ~ C ~ ~ o ~ 9 o " rn . " u o " o r "0 > a; . , ~ row om E5 . 0 0_ u w 0 E"<t c=U o ro" gR..... ~.2 2C>/lQ.l~-g o I!'l 01 c::: w:3ffi~E 000"<::+=0 I-r--U:J,:: 0; m o ro ~ u '0 . . "E . > o 00 ~ o 2> N o o E m '" "0 9 . o ~ U " m " , o ;; ro , "0 o ro m " , g> ;;: x o o jj " "0 ID ~ 9 . o u e- o . rn " " o o '" o W g '5 o u ro ~ ~ o "0 "' > oa; "0 . ;; :;: o ro "-0 o 0 - 0 ~~ "09 "013 . 0 0" r "- Hi==' 1;,0 cO . ~ L - U Q em , t . 0 "E ft ~ rn 0;0 '6 C o E t . ~ o o ro "0 ~ u: "0 o . o c. o "- S " 5 u u o " . 13 " o o u t J< a, w <0 ;f. m w o " " <0 ~ M, M W o o o o o '" w o o <0 v M ro N w '" z o o o V M ro N w "OJ N~ u~ :; 00 o N " 00 ~N r" ~rn 'M " ' Ii': ~ o > 5 U) ~ g o o " o o(j N <.l t: c:"<t ro 8- ~ ~ ~2 <lJ "E ~ is S ~ ::J en J:: 0 c I....UU)rn o a o " 00 o N o 2> M E o " ;; o o ~ ~ " o 2> a o E , "0 o "0 o U " '6 o . . , L U EO , . o u e- o . '6 o ~ o u . o S o " " . m " l . . .0 "0 o . . o o " e- o "0 o U , 9 . " "0 ~ o " o . . c o ~ ii "0 ro m 15 o 9 o -" E " s . c o u i, o . . "0 , o "- o ~ 0; ~::= ro . L;; U ~ o~ , 0 .u .~ ~ > 0 Ou J< N N ~ J< w o w ~ v o o <0 m v "' m w o o <0 " w, w ~ o o <0 m m m' 00 w '" Z o o o w ~ "' ;;; m " , E au in" 00 o "' o 6 m N M e-o ~m 'N "M o~ 00 m " . E o 0 '" ';::: U) c " 0 >- M:;;e 16;;; &Ct.l ~ ~ (') c::::> 2 ::~:2a. Ol()UOE i': " o 2> v o o o ~ ~ N ;;; o o <0 w N w w ,; o Ie ~ o E '6 rn o ii "0 i5 ~ o E 9 o o "0 . o o ~ ii o o U "0 o rn o ro L u ~ o . 1:5 o ~ 9 . o . a. o S o " "0 ~ o "0 o . -" ~ o E ~ " . o r o o <0 w ~ .,; v w o o o w ~ "' v w "OJ N~ u~ :; 00 o '" w v e-M ~w 0:;r W~ Uo o o ~ o ro ~ x W ~ ro N,,- Iii 01 & Q) in ('") c c: III 0 o:u c; 8g58 rn o g o o '" o W . rn o ro ~ u '6 . o .~ . > o i'l 00 o a w J< w 00 o N '" m ~ :;; o o o N o '" ~ w .; c o o u u " g o Q " t o ~ . o g "0 o . o . a. o ~ ~ . "0 o " "0 o U o ro ~ o o o ro o "0 " o "- 9 "0 o . vi W o U e g . " o o E o u . o , . 9 "0 o o ~ ~ 9 . o u e- o . " o o ~ U "0 . . "0 , o "- o r 0; C> o . L o '0 . o E . > o ~~ ~o -<<;> ?ON or- '""U~'" E"'''' ",.0 ro "'ED. ro'" ,,> c: 0 "'z '" <C 'l: :; eIIf'E ~OD ~ ~ 0 '''" ~ E 0 '-J,g3: " C . .-"C ~ ~.~o .0" .c E " (),g~ " . C 'O'E ::I :: 00 >: ~ <E . 0 ";:~ o . -"C C . - , 0>00 ; ~ E .co< .,;:~ - " o ~ ill " " ill o " o ~ " ~ m'l: 'l:'E ::I ~ ~ ~ 8~~ 1: "g1: f () ~ 2: ... () ... E 8 aJ ~< <~ " " z ~ ~ U ill > ~ ~ ~ ~ z ~ o ~ "iii ti. 5 .5 .:: 0 geE o8~ C . " E u iO '5 g.u 0. C . . 0 0. OUV> o z _ 0 ~z o E ~'l: ;:8 o z - . .. E "C E ~~o~ o u & ti "'CI !!!. C ell c:: 0 ~.O' ~Q:uQ: . . " E ~~ '" 00 " ,,; ~ "- <D ,; M M " " o " M .0 ~ ~ " " o " " ,; M ~ " " o " M .0 ;;; " " o " M ,; ~ o o o o M ,; ;;; ::;", N~ .,~ M o do o " ~ ~ e'M ,,~ 0~ UJ ' ,,~ E o 0= ~ ~ &!~ .co. ~ ~ ~ ~ N~~ ID-e <Il -rn ~ ~~ ~ ~g~iija Uo>O>U co E 0; . C 6> C UJ 00 " ro o 2; w "- ~ "- ~ M 00 o N .; o m ,; m ~ " N 00 N O. ;;; ,; ~ . "C S & C .. "C ~ "C C , .c o ! o " o 00 00 '" 00 ~ o o o " m ..; 00 ~ ~ D .. . "C C o 'ai 0. E o o . E "C C .. . . .9 l' . .,; co E ;; . E .,; ~ . e , . .,; co c ~ "C C ~ ro , c. . o " o o . "C , o 0. o >- o o o o m ..; 00 ~ ::;;: N::; ,,~ N o do o " ~ ;;M e'~ ,,~ -'-"1 UJ~ ~" co " ~ . c 6> " c " UJ NO. a""" Q) ~ ~ g ~.~ .com>- .QgB~ ;; 0> C . .c o '0 ~ . .~ . > o 00 o '" N 2; ~ . c o N . " " m N ~ ~ ..; ~ ~ . . 0. .. . ro c 6> c o . E c "5 , " .9 " o " 0. ro c o .c i5 "C . . . " 0. " o .E .9 C. . o c o o c co . . "C .. . .. . c .. ro "C . o c . > "C . . "C , o 0. o >- 5 o c .;( . 0; "C :5 " <5 ;: .9 . . :? ~ G ro a >- ;; co c . .c o '0 ~ . '~ . > o CONTRACT/WORK ORDER MOD/FICA. TlON CHECKLIST FORM r,genda item No, 16E4 November 18, 2008 Page 27 of 34 I PROJECT NAME: Oakes Nelahborhood Park PROJECT #: 800341 PROJECT MANAGER: Vickv Ahmad WORK ORDER i/; BCBfl~S-08-03 BlDlRFP i/; 06-3971S MOD i/; 3 POI: -450009'>'" DEPARTMENT: Parb and Recreation CONTRACTORIFIRM NAME: Bradanna. Inc. ~tc~ /o/;:'q} raY o7r Original Contract Amount: $ 156,067.00 - (Starting Point) $ NlA --O:astTotaI Amount Approved by the BCC) $ 158,743,60 - (Including Atl Changes Prior To Tl1is Modification) CUmlnt BCC Approved Amount: Current Contract Amount: Change Amount RevIsed COnlractlWork Order Amount: $_613.70 $ 159,357.30 (including Tl1is Change Order) Cumulallve Dollar Value or Changes to thla COnlracllWork Order: $_3,290.30 Date or Last BCC Approval_NlA Agenda Item # _N1A Percentage of the change over1under current contrac::t amount Fonnula: (Revised Amount / Last BCC approved amount)-l U1" . 3'1 % CURRENT COMPLETION DATE (8): ORIGINAL: October 6 2008 CURRENT: October 31. 2006 Describe the change: Moved location of the 4' wide gate to keep the ramp away from the playground equipment fall zone, deduct $98.00 for the second density test as back charge to the contractor and add 25 calendar days to the contract for closing the documents. - Specify the reasons for the change(s}' 1. Planned or Elective'. 2. Unforeseen Conditions 3, Quantity ~justments c. 4. Correction of Errors (Plans, Specifications or Scope of Work) r' 5. Value Added '. 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The 4' aate will not be in Ii!l!!l! with the ramp and add more calendar days to the contract for close out documents. This change was requested by: "!contractor/Consultant ,',; I Owner "1 Using Department '.:.. COES CJ:lesign Professional '-IRegulatory Agency (Specify} Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: Yes :;;; No APPROVED BY: Date: 1~l,fr g- /blll JY , REVIEWED BY: Date: CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM ~da Item No, 16E4 2- ~vllC8V!D lOll lO~Jf PROJECT #: 70045 & 73045 PROJECT NAME: Utilitv Relocations for Davis Blvd. from Radio Road to CR 951 PROJECT MANAGER: Ronald F. Dillard BID/RFP #: 05-3785 MOD #: .1 PO#: 4500093804 WORK ORDER #: TBE-FT-3785-08-02 DEPARTMENT: PUED CONTRACTOR/FIRM NAME: TBE Group. Inc. Original Contract Amount: $ 94.720 (Starting Point) Current BCC Approved Amount: $ 94.720 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 94.720 (Including Ail Changes Pnor To This Modification) Change Amount: $ 9.751 Revised ContractIWork Order Amount: $ 104.471 (including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ 9.751 Date of Last BCC Approval N/A Agenda Item # N/A Percentage of the change over/under current contract amount ~ (() . "2.-'l % Formula: (Revised Amount / Last BCC approved amount)-l SURRENT COMPLETION DATE (S): ORIGINAL: 1-25-10 CURRENT: 1.25-10 Describe the change(s): Add task C to provide SUE services to field locate existinq water and wastewater facilities to determine if conflicts will occur with proposed FOOT proiect to widen Davis Blvd. Specify the reasons for the change(s) r 1. Planned or Elective ~ 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) ~ 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: A chanqe order to the construction contract would be needed if conflicts were discovered durinq construction instead of before. This change was requested by: rlContractor/Consultant n Owner n Using Department r CDES KDesign Professional rlRegulatory Agency (Specify) r other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes ~o This form is to be signed and dated. PPROVED BY: Date: /o-I-OfJ APPROVED BY: Date: lO{l/o" _ 1011/06 REVIEWED BY: Date: Revised 2-22-08 Agenda Item No, 16E43 November.1S.200g..:_ Page 29 of 34 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: South Marco Monitorina Survev & Reoor! PROJECT #:195-905421 PROJECT MANAGER: Garv McAloin BIO/RFP #: 06~902 MOD #: --LPO#: 45-97123 WORK ORDER #: HM-FT-3902-08-01 DEiPARTMEiNT: Coastal Zone Manaaement CONTRACTOR/FIRM NAME: Humiston & Moore Enaineers Original Contract Amount: $ 28.340.00 (Starting Point) $ N/A (Last Total Amount Approved by the BCG) $ 28.340.00 (Including All Changes Prior To This Modification) Change Amount $3.000.00 tJ,g ~~~tfP I~ Current BCC Approved Amount Current Contract Amount: Revised ContractIWork Order Amount: $31.340.00 (Including This Change Order) Cumulative Dollar Value of Changes to this ContracllWork Order: $3.000.00 Dale af Last BCC Approval n/a n/a Agenda Item # Ic,5'i Percentage of the change over/under current contract amount~I,/. Formula: (Revised Amount / Last BCC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: 12/14/08 CURRENT: 12/14108 Describe the change(s): Task 1: Sub-consultant fee to obtain additional survev data to include the T-Groins and breakwaters within the scooe of services which was not included in the oriainal reauest from Collier county Staff. Specify the reasons for the change(s) r 1. Planned or Elective (" 2. Unforeseen Conditions C 3. Quantity Adjustments (0' 4. Correction of Errors (Plans, Specifications or Scope of Work) (" 5. Value Added (", 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: .C/u ~vey d Ai:L. I. 117. t1.R ~ (l1l1'rO,r., This change was requested by: []Contractor/Consultant rl Owner PI Using Department C CDES r Other (Specify) !:Design Professional rlRegulatory Agency (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes C No This form is to be signed and dated. APPROVED BY: Date: Itl/z,/ tJ i I , REVIEWED BY;. ( Best, Contract Specialist Date: /d/'3(6<{ { / Revised 2-22-08 Agenda Item No, 16E4 4 November 18. 2008 , Page 30 of 34 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM 11/19/07 PROJECT NAME; Old US 41 Stormwater Imorovements PROJECT #: 511331 PROJECT MANAGER: Val Ponce BID/RFP #: 01-3290 MOD #: ~ PO#: 4500058884 WORK ORDER #: OGM-FT-3290-06-08 DEPARTMENT: Stormwater Manaaement Section CONTRACTOR/FIRM NAME; OGM & Associates. P A Original Contract Amount: $ 16,750.00 (Starting Point) $N.A. (Last Total Amount Approved by the BCC) Change Amount; Revised ContracllWork Order Amount: $ 6.500.00 $ 96.490,00 (Including this Change Order) Current BCC Approved Amount: Current Contract Amount: $ 89.990.00 (Including All Changes Prior To This Modification) CUDmulative Value of Changes to This ContractIWork Order: $ 79.740.00 Date of Last BCC Approval: NA Agenda Item #:!:f4. . Percentage of the change over/under current contract amount: 7, .~p.. Formula: (Revised Amount I Last BCe approved amount)-1 (?c.-- CURRENT COMPLETION DATE (5): ORIGINAL: 07113106 CURRENT: 06/30/09 Describe the change(s): To add to Seooe: Task No. 12 - Survev/Uodate of Plans in the amount of 54.000.00 IT & Ml and Task No. 13 - Proiect Re-biddina in the amount of $2500.00 IT & M) to the current W.o. as an added cost resultina from the reauirement of Purchasina to fe-bid the oroiect. Agenda Item No, 16E4 November 18, 2008 Page 31 of 34 /fer Specify the reasons for the change(s): r 1. Planned or Elective '" 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) (' 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative Impacts to the project if this change order were not processed: Will not be able to re-bid an uo-to-date/most accurate set af bid olans and 'Nill not be able to Dav vendor for additional services now beino reauired. This change was Department (Specify) rellf!ested by: r1Contraclor/Consultant 171 Owner rI Using ~ - CDES !Evesign Professional r1Regulatory Agency r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r No APPROVED BY: Date: c,~~;6 '8 /0/7/o,r/ REVIEWED BY: Date: I ~ CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: r n......FlL ~o....l sz:z:>l PROJECT It. c; 0 d3 "1.1 PROJECT MANAGER:c:..J.:a"J\..p" I? 1'....".) BIDIRFPf:01-'-ll'3'\ MOOt/: -1- pot:4G-B""o=rwoRKORDER":"'C;::~ -P-r-~ IS~ -08-0 I DEPARTMENT: C. Z-l'1 CONTRACTOR/FIRM NAME:C/.IA""""'" E.W~.....li Original Contract Amount: $ ~ <S" '1-'SO. 00 (Starting Point) $--=15, 1- 50. 00 (Last Total Amount Approved by the BCC) $ ~ I. -z.,.-:;o.oo (Induding All Changes Prior To This Modification) $ I"Z.-, '":frO. 00 $ -=1-;"',020.00 (Including This Change Order). Agenda Item No, 16E4 November 18. 2008 Page 32 of 34 :5"'--' Current BCC Approved Amount: ... 'f!1 RECEIVED lo/f'"lo'( :at Current Contract Amount: Change Amount: Revised ContracllWork Order Amount: Cumulative Donar Value of Chang.. to this ContracllWork Order: $ ~F3>, 'Z-?-D. 00 Date of Last BeC Approval I 'Z-. err. o":f- Agenda Item # /~I ""0 .:lo.i5 Percentage of the change over/under current contract amount lP~1 % Fonmula: (Revised Amount/ Lest BCC approved emount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: Or;. .II.O~ CURRENT: (2-. '3>1.06 Describe the change(s): ADDt;"\"l:O~ ?,<U)F'e.~.s=~P.l.- ~z::>Jee.e.~~ Di!.SZbI.J SeP12-"a::.E.,S' P'e-q<.)~...o "'{'t> ~e!;.'S~[) T'D u...IFO.P=-.;:P.....l r~()~ '\ e:NH-~ L-A+-lPS~e. \>\..A..l" AN.!) ''"TlC-A'''.s~:n:\''ra:w ~;-r= col.l4-l'T'S," , Specify the Alasons for the change(s) r 1. Planned or Elective. 2. Unforeseen Conditions r'.3. Quantity Adjustments r 4. Correction of Errors (Plans. Specifications or Scope of Work) r 5. Value Added r, 6. Schedule Adjustments Note: One or mOAl may be checked, depending on the natuAl of the change(s). Identify all negative impacts to the project if this change order weAl not processed: RE..:;! ~I ~ 0 F 5DPA- 'P~OCP '5<;; .J()lJ- RG'''SPoIJS't;\/e;:. At.,.,......) I'!:> R~ <::DMMa..rr$. This change was requested by: Clcontractor/Consultant r! OWner r! Using Department C CDES ~ign Professional rlRegulatory Agency (SPecify) r Other (Specify) r Yes ~o CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: This fonn is to be signed and dated. REVIEWED BY: Date: lo-or.CfB APPROVED BY: Date: I D Iri O'Y . DEPARTMENT: C. 'Z-~ /JA9/.:nda Item NO,~4 ~<ULN?~~73!~~ CONTRACTIWORK ORDER MODIFICATION ,;;;.as.: CHECKLIST FORM ~ J PROJECT #: 'I oo4~.1 PROJECT MANAGER: c.LrJr. ~M Jl:>;lP/Pl.6. ' PO#:~ WORKORDER#:C.E-e--f'-r-4Isa-o&-o,3 / C)(YU-'!, CONTRACTORTFIRM NAME: r"""~ ~.lr., r~c:.tU~-r.t. & PROJECT NAME: ~ iZ ....Ic.o BIDJRFP #: D"'"1- 4' I S":3MOD #: ~ Ch...ge Amount: Revl_ ContractlWork Order Amount: $ 10 ~OO.oo (Starling Point) $ \0 ~GlO. ..0 (Last1-otal Amount Approved by the BCC) C 00 1-....., :>00. (Including All Changes Prior To This Modification). 0-0 ?c::?, cOO. ~05, ~. 00 (Including This Change Order) . $ Original Contract Amount: $ Current BCC Approved Amount: Current Contract Amount: $ Cumulative Dollar Value of Changes to this ContractlWork Order: - oc:> $ ~?/ 000. Date of Last BCe Approval IO"-Z.? 01=.. Agenda Item # Percenl8ge olthe change overfund.. current contract amount -? ~O lei ~ .Ob Fonmula: (Revtsed Amount / Last BeC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: ,. t c;.. .og CURRENT: 0 S. l'2-. oq PHIi\SJS. -.:1+' - Describe the change(s): YIU:>vI:Dt= .ADO~AI:- ?Jl.DFe.,SSCQ-li'\L. D~ j;;'..,.16..0Jeo;oea'1 ~\-tl.117......a.-t_ S~r:r:;.r;~<: ""T'O lSU"t'..!,jD" J ~"'~"Mlrt.--~lU-ID~~., "~.lA'S.>-\~S'l A1-IC> ~ ~c..oHP~ t>1t'f2. e. 'B-./'O.J)p.yS TI:> co~~::S:=.oPe oFS'~. Specify the reasons for the change(s) (" 1. Planned or Elective I' 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work). 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: r .........~.J c:F O~""D-1AL- ~ IOIt p~ 5Sz:o,...lAL- ~.i#(I!Vl7' c: <; .J-r:! L NOI B.GL h-l<Ir;F~B(). This change was requested by: ["lcontractor/Consultent ~ner rJ Using Department C. CDES ~ign Professional rJRegulatory Agency (Specify) rOther (Specify) CONTRACT SPECIAUST PARTICIPATION IN NEGOTIATIONS: r Yes ~ This fonn is to be signed and dated. APPROVED BY:~: anager Date: leJ. 111.-013 REVIEWED BY: Date: (fJ -/7 -()O o ~a Item No, ~~ r CONTRACTIWORK ORDER MODIFICATION ve~~IJ:%lo) CHECKLIST FORM (})t.c/, PROJECT NAME: I7tJ..fv~ ~Il~ PROJECTft.6a?bo.! PROJECTMANAGER:t!L~~;:""; BIDIRFPf: 01-0.( 15"1 MOD #: -z,. POtI: ~-/e>r:'Z'Z-Z-woRKORDERtI: ::JI'$.-r- P'f: JI4 ~ 1/53-0t-02. DEPARTMENT: C.2n CONTRACTOR/FIRM NAME::::J ..;SO,.{ e,J. ~ Orlglnlll Contract Amount: $ (Sta~g~~:a>. 00 $ flJ3. qp,;? "0 (Last Total Amount Approved by the BCC) $ If1 ~60. "'0 (Including All Changes Prior To This Modification) $ ? 0 ;l.6. yO $ "ldl. ?O~. 'Z--&> (Including This Change Order) Current Bce Approved Amount: Current Contract Amount: Change Amount: Revlaed Contract/Work Order Amount: Cumulative Donar Value of Cheng.. to till. ContractlWork Order: $ % pp iI. vP DB of Last Bec Approval Agenda Item # ~ , . ~.--3" I. ''-I '10 Percentage of the chan"e over/under current contract amount Fonnula: (Revised Amount / Last BCC approved amount)-l CURRENT COMPLE1l0N DATE (8): ORIGINAL: IZ,. 7-/. ~ CURRENT: ('1-.7-/,06 Describe the change(s): Pl24Jt/17O;1L Af)~DTn>'/1tt- ?,e../7r.$S"PI,./,M... ~ dr;~ ~ (t) ?/2O./tD6: 17....1lhtirlc;.r;;..r, ,4L-TlPfhiR71E. <;;;rnz. f)~~ 4'~ Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work). 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: 7?fF. t::)A :1~ ~~~Aj;;~~:f'~~~~ Pu4bS€ -m 7?JP- This change was requested by: C'lcontractor/Consultant . Owner n Using Department C CDES !:Design Professional rlRegulatory Agency (Specify) r Other (Specify) ryes r;;: CONTRACT SPECIAUST PARTICIPATION IN NEGOTIATIONS: This form is to be signed and dated. APP~OVED BY: ~ proje ager REVIEWED BY: * /r1 'V) ~ c t Specialist Date: /cJ.7.-/.09 Date: 10 -d.:r-oV