Agenda 11/18/2008 Item #16D24 Agenda Item No, 16024 November 18, 2008 Page 1 of 7 EXECUTIVE SUMMARY Recommendation that the Board of County Commissioners approve and authorize the Chairman to sign Change Order No. 1 to File No. DRI 05-06 with Inspired Woodworking for Project 4984 23RD Court SW, Naples, Florida (Folio No. 36110800009) and ratify Staff approval of project expenditures. OBJECTIVE: To increase the scope of work under File No, DRI 05-06 with Inspired Woodworking for Project 4984 23rd Court SW, Naples, Florida 34116 and ratify Staff approval of project expenditures, CONSIDERATIONS: On March 3, 2008, the Department of Housing and Human Services, DRI Program Participant William Szempruch, and Contractor Inspired Woodworking entered into a Contract for Rehabilitation of Owner-Occupied Dwelling Unit for residential rehabilitation of 4984 23rd Court SW, Naples, Florida 34116, During construction, the contractor encountered unanticipated mold damage caused by Hurricane Wilma which required extensive mold mitigation, In order to complete and correct the existing health and safety issues on subject property, additional rehabilitation is required and included in Change Order No, 1, which is attached and itemizes the changes required, ..- FISCAL IMPACT: The fiscal impact of Change Order No, 1 is $35,050,00 and sufficient grant funds have been committed to fully fund the project, as amended, Source of Funds are Distaster Recovery Initiative (DRI) grant funds, No general funds are being used, GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this action, LEGAL CONSIDERATIONS: Some of work being authorized with this change order has already been completed based on Staff direction, If the Board of County Commissioners denies this change order, the contractor may have a claim for the fair market value of his work based on quantum meruit. This is not an opinion of the sufficiency of the claim but notice to the Board that such a claim may exist. The Board may legally approve this change order and ratify Staff actions, - CMG RECOMMENDATION: That the Board of County Commissioners approve and authorize its Chairman to signed Change Order No, 1 to Fiie No, DRI 05-06 with Inspired Woodworking and ratify Staff approval of project expenditures, Prepared by: Frank Rarnsey, Housing Manager, Housing and Human Services Agenda Item No, 16024 November 18, 2008 Page 2 of? CHANGE ORDER CHANGE ORDER NO,: 1 FILE NO,: DRI 05-06 BeC Date: November 18, 2008 Agenda Item: 16D- TO: Inspired Woodworking 2805 S, Horseshoe Drive #3 Naoles. Florida 341 04 DATE: November 18.2008 PROJECT NAME: William Szempruch - 4984 23" Court SW. Naoles, Florida 34116 PROJECT NO,; DR! 05-06 Uoder our AGREEMENT dated March 3, 2008, You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: Changes are detailed in Exhibit "A", FOR THE Additive Sum of: Thirty Five Thousand Fifty and 00/100 Dollars ($35,050,00), Original Agreement Amount $50,000,00 $0,00 Sum of Previous Changes This Change Order $35,050,00 Present Agreement Amount $85,050,00 The time [or completion shall be increased by two hundred forty (240) calendar days due to this Change Order, Accordingly, the Contract Time is now three hundred thirty (330) calendar days, The substantial completion date is January 1,2009 and the final completion date is January 31, 2009, Your acceptance of this Change Order shall constitute a modification to our Agreement and will be performed subject to all the same tenns and conditions as contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance, The adjustment, if any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs, Accepted: November 18, 2008 OWNER: By: By; VUJ;.fJ.--. ~ William Szmpruc By; J.-, '---"'- Date: November 18. 2008 A TrEST: Dwight E, Brock, Clerk BY: Approved As To Fonn and Legal Sufficiency: rj) C~~ , " ;' , . , " 'Plint Name: Colle6n Greene - ~';:': :.. '.:: ~:::istant County Attorney . .. .,. . .. ... . . . . . . . , , . . . . . .Agenda Item No, 16024 November 18, 2008 Page 3 of 7 DIVISION ADMINISTRATOR "~%- arla Ramsey ~ECIALfST .- fb.,,-wY) Tammar Hammer BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY FLORIDA BY: Tom Henning. Chairman Collier County Housing and Human Services Disaster Recovery Initiative 3301 E Tamiami Trail Building H Room 211 Naples, Florida 34112 EXHIBIT "A" Client File # DRI 05-06 Contractor: Property Address: William Szempruch Inspired Woodworking 4984 23rd Court SW Naples, Florida 34116 Rehabilitation Contract Date: 3-Mar-08 Homeowner: The following change{s} is/are authorized to the above identified Rehabilitation Contract: Agenda Item No. 16024 November 18, 2008 Page 4 of 7 Item Mold Mediation Dumpster Exterior Exterior Exterior Entry Door Permit Recording Fee Mold Mediation Dumpster Mold Abatement Mold Remediation Interior Interior Plumbing AIC Interior Exterior Kitchen Interior Entry Door Electrical Bathroom 1 Bathroom 2 TOTAL PAGE ONE Original Cost Descri tion of Chao e Initial Mold Assessment Test Dumpster Rental Vinyl Siding wi House Wrap Aluminum Soffit Frame Front Door Exterior Door Repair Permit Fee Notice of Commencement Mold Assessment with Report Dumpster Pull Additional Mold Abatement Remediation of Water & Mold Replace Insulation Replace Floor and Tile Replumb Water to Home Replace AlC Drywall Replacement Seal Exterior per Mold Assessment Replace Cabinet Trim and Door Package Door Repair Minor Electrical Repair Damaged Bathroom Shower Stall Repair $ $ S $ $ $ $ $ $ $ S $ $ $ $ S S $ $ $ $ $ $ $ , > "';;:?ii.~?M" ft~-'.::'~~:':~'\Ot'~':i'~""'-'"-"_ I", _ .,,..";\'." Page One Total Total New Contract Amount Increase Decrease $ 660,00 $ 358,00 $ 11,392,00 $ 1,984,00 $ 556,00 $ 376,00 $ 150,00 $ 12.50 S 563,00 $ 358,00 $ 1,947,00 $ 12,916,00 $ 978.00 $ 10,784,00 $ 378,00 $ 2,461,00 $ 5,684,00 $ 325.00 $ 10,316,00 $ 6,364.00 $ 126,00 $ 1,933,00 $ 1,226.50 $ 460,00 $ 72,308.00 Reason for Chao e Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage ..::,~~~'";.;.: ~:. ",;l::::~-ir-" ~ ;-., $72,308.00 $72,308.00 EXHIBIT "A" Client File" DRI 05-06 William 5zempruch Inspired Woodworking 4984 23rd Court SW Naples, Florida 34116 Rehabilitation Contract Date: 3-Mar-08 Homeowner: Contractor: Property Address: The following change(s) is/ate authorized to the above identified Rehabilitation Contract: Original Cost Item Descri tien of Chan e Replace Mirrors Paint Water Damage Replace Damaged Appliances Replace Lanai Structure and screens Interior Interior Appliances Lanai TOTAL PAGE TWO s s s s ',' ': >. ;:;L,:L ~ ~} ".- I :~.:~.::... Page One Total Page Two Total Total New Contract Amount Signed: ~- Contractor ~~ Increase Decrease S 500,00 S 4,923,00 S 2,100,00 S 5,219,00 $ 12,742.00 Agenda Item No. 16024 November 18, 2008 Page 5 of 7 Reason for Chan e Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage Hurricane Wilma Damage $72,308.00 $12,742.00 $85,050,00 II /U/ ~1( Date . I II -/O-80C{} Date 11/'O/r,UXJ8 Date' I Agenda Item No. 16024 November 18, 2008 Page 6 of? Ud71L,:",u; -;;- 13 (!. c. /1/1'8'/08' CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAMe; ~984 23r'1t Court SW. Nanles FL 34116 PROJECT #: DRl 05-06 PROJECT MANA.GER: Frank Ramsev BIO/RFP #: !J$, MOO #: ~ Po.: 4500099680 WORK ORDER #: NfA OEPARTMENT: Housina and Human Servir.:e$ CONTRACTOR/FIRM NAME~ Inspired Woodwor..!ili1g Original COl1lract Amount $ 50,000.00 (Starting Point) Current Bee Approved Amount: $SO.OOO.OO (Last Tetal AmalIn! Approved by the Bee) Current Contract Amount $50,DOO.OO (Inctuding All Changes Prior To This Modlflealion) Change Amount: $35,050.00 Revised CcntractlWork Order Amount: $85,050.00 (Including This Change Order) Cumula.tive Dollar Valullt of Chlil "g88 to this Contraet!Work Order: $35,050.00 Date ofLaat BCe Approval: 4/22/2006 Agenda Item # 10F Percentage of the change overJunder current contract amount 70.00% Formula: (Revised Amount I Lasl BCC approved amount}-1 CURRENT COMPLETION DATE (S): OR.IGINAL: ~v 31 2D07 CURRE~ Januarv 31 20dSXXX 2009 Doscribe the change(s): Correct ertenslve damaoe resultino from damaaa from Hurricane Wilma. SpecIfy the reasons for the chang&{s) r 1. Planned or ElectIve r. 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors {Plans, Specifications or Scope of Work} r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checkedt depending on the nature- of the change(sl. Identify all negative impacts to the project If this change order were. not processed: Unable to complete work in progress; clienl health and safety negaHvely impacted: client dislocation from home; surrounding neIghborhood heallh and safety negatively impacted. This change was requested by: Pk;ontractorfConsultant PI Owner n Using Department C. COES COeslgn Professional rlRegulatory Agency (Specify) ;- Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: ~ Yes r No ,.his form is to be signed and dated. APPROVED BY:~ . ~ P'o' 01 ager1=(ltl\ t:: 'SWI Date: l\ h-lzo0'6 1/-7-(J!5 REVIEWED BY: Date: Con Revised 2':22-08 Page 1 of I Agenda Item No. 16024 November 18, 2008 Page 7 of 7 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: Item Summary: 16024 Approve Change Order No 1 to File No DRI 05-06 with Inspired Woodworking for Project 4984 23RD Court SW Naples, Florida (Falla No. 36110800009) and Ratify Prior and Future Project Expenditures Meeting Date: 11/18/2008 90000 AM Prepared By Frank Ramsey SHIP Program Coordinator Date Public Services Housing and Human Services 11/11120083:59:47 PM Approved By Marcy Krumbine Director Date Public Services Housing & Human Services 11/11/20089:01 PM Approved By Marla Ramsey Public Services Administrator Date Public Services Public Services Admin. 11/12/20088:35 AM Approved By Steve Carnell Purchasing/General Svcs Director Date Administrative Services Purchasing 11/12/20081:18 PM Approved By OMS Coordinator Applications Analyst Date Administrative Services Information Technology 11/12120081:27 PM Approved By Colleen Greene Assistant County Attorner Date County Attorney County Attorney Office 11/12/20084:00 PM Approved B}' Sherry Pryor Management & Budget Analyst Date County Manager's Office Office of Management & Budget 11/12/20084:01 PM Approved By James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 11/12/20034:44 PM file://C:\AgendaTest\Export\ 1 16-November%20 18,%202008\ 16,%20CONSENT%20AGL, 11/1212008