Loading...
Agenda 12/16/2008 Item #16E18 Agenda Item No. 16E18 December 16, 2008 Page 1 of 17 EXECUTIVE SUMMARY Report and Ratify Staff-Approved Change Orders and Changes to Work Orders to Board- Approved Contracts. OBJECTIVE: To enable the Board to oversee the execution of administrative change Drders and changes to work orders, and promote accDuntability in the use of staff authority. CONSIDERATIONS: On April 22, 2003, the Soard approved a recommendation to implement a plan to enable changes to BCC-approved contracts (Section XIV. C, Collier County Purchasing Policy) Df not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff. Also included in the report are changes to Work Orders. These include work orders issued under CCNA Contracts which are less than or equal to $200,000 (Section VII.C, Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XIV. G, Collier County Purchasing Policy) which are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater). The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above. The plan calls for staff to submit a monthly report listing these change orders from the previous reporting periDd. Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders. These reports cover period October 24, 2008 through November 20, 2008. FISCAL IMPACT: The total change to contracts is a deduction of $981,454.19. The total change to work Drders is $10,324.25. GROWTH MANAGEMENT IMPACT: There is no GrDwth Management Impact associated with this action. RECOMMENDATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders Report and Administrative Changes to Work Orders Report and ratifies the listed change orders and changes to work orders PREPARED BY: Diana De Leon, Contract Technician, Purchasing Department -- ....--...)-... Page 1 of 1 Agenda Item No. 16E18 December 16, 2008 Page 2 of 17 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: Item Summary: 16E18 Report and Ratify Staff-Approved Change Orders and Changes to Work Orders to Board- Approved Contracts. Meeting Date: 12/16/2008 9:0000 AM Prepa red By Diana Deleon Administrative Assistant Date Administrative Services Purchasing 12/1/20084:03:36 PM Approved By Steve Carnell Purchasing/General SVC$ Director Date Administrative Services Purchasing 12/4/20087:39 AM Approved By Len Golden Price Administrative Sen/ices Administrator Date Administrative Services Administrative Services Admin. 12/4/2008 12:07 PM Appro\'ed By OMS Coordinator Applications Analyst Information Technology Date Administrative Services 12/4/20082:35 PM ApproV('d By Jeff Klatzkow ft.ssistant County Attorney Date County Attorney County Attomey Office 12/51'2008 2 :40 PM Approved By Laura Davisson Management & Budget Analyst Date County Manager's Office Office of Management & Budget 12/5f2008 4 :12 PM Appro,"cd Hy James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 12/9/20087:18 PM file:l/C:\AgendaTest\Export\ 118-December%20 16.%202008\ 16.%20CONSENT%20AGE... 12/1 0/2008 ---------. .----.-....-..., ---------r-.. ",oot'- ""o~ i.5~Q't: ~0~~ ~ :: 18 "Q) E ",.0 0 Q.l E - -Q) <Il U 0 UQ.)CIlcg cO ~ ~ IV ~ ~6"E <:;( UlIlO ~f5 'C 0 0 5l ~ 2: .;: c: E ~8~ Ill... 1: 0> 0 0 lij "E ~ ~o", U ~ ~ o ~ w '" '" w o '" o w o z < I U w > C < '" " ~ Z ~ o < .. o c: e 5 :! c. 0 :s g- ~ (,)8'" '" c: u ~ l!,l ~ 0 :i 15 ~ uu~ .. o U ~~ o 'C- o 0 > 0 o 0 " E Ii'" "'~ o E u ]! t ~ i1j 1O......(j 0. 0 0 o 0 0. cu", o c:i Zz QI 1: Q; QI E r: "0 E ~~go~ ..... tl U QI ..... .g <II ~ g> a; 5i "e a ~ 'e >0..(')<">0.. 2' . c E 0 ~z 'C o > 0 e 0 0.0 0. E '", t3~ '" ~ ~ ~ ~ " ~ o N " M ~ 0> '" 0; ~ o o 0; ~ '" ;;; o o ~ M ~ ~. N N ;;; o M 0> ,- '" " 00 ~ o o '" M ~ "' N "l ;;; - o :Eo "'Be:: . ~ " Q ro u " " E E o U u o W '" o ro o 0; 0; 0 Vi N ([) ~ l1)QJC'i-& .I:: ~ g>~ ~ ~ o:i 00 Jg:g g> (l)ZO()Itl~ 00 o ro N 2; rn " !!J 3 .. o o o .. o . B . 0; o . rn . . o . E ),5 o is ~ . ~ . E B .. . .. . . o . . '" @ u - " .... ~ o '" . D E " ro 0; o . rn . . o E " . u . i5. ~ u o rn '" jj . rn rn o "' . - . ~ .. o " o C, 0; .. o o . > o o ~ o .... 0; 0> o . ~ o C . o .~ o > o " "' 00 0> " "' 00 ,,; o o o ~ N .. N ~ o o o ~ ;;; o o o o '" ;;; o o o o '" ;;; o o o o '" ;;; ~~ "" O~ .... u E ,,; . u , 0; '" rn ro o - . u , 0; '" D U " . - . '" ell (J) E <.D g',g! "'1 rn ;j ~ DO AU"" u ~ ~~ "'2 00 e M 2; N ~0 u " " ','>j ~ o 00 N o '" ~ 0> ,,; ~ " '~? ~ - u a. g .. o rn - o > U . E o D u ro . - ~ . '" rn .2 B " m o o M 00 ,,; ;; ~. ~ N ~ M ~ 00 "' co 0> ~ ~ o o M 00 m ~ ~ ~ m .. u . " 5. B . .. 3 rn is " - o ~ ~ rn o Q ro o ~ . ro ~ - ~u u '" rn ~ " rn .D " rn o o rn ~ <.Dw& ~(<):::.- Ol.!:: <t6"i"@:J Q.)<::tr--...co Ol,(')OUU) ~ E o u C rn " 6 E rn 0; ro u o 0; 0> o . D U 00 o " " . . ., 0; 6 M - E o o .D ro D , - . '" m D u rn o :E Q> .. ~ 5 ~ ~ . ~ rn E B .. o rn oi rn . o rn " o ~ " .. o . - ~ 5 o u . i5. o . 0. ),5 . u o rn . g rn "' o TI rn o .... oi 0> o . ~ o o . o 'E o > o ,oj, 1 - M ,~ o ~ ~ v O. N ~ '" ~ 8 '-j ~ ~ ',!, o o 00 ~ 00 N ~ N ,,' ~ o ~ " ~ M 0> 00' ~ o o 00 ~ 00 N ~ N m ~ ~?; ~:3 ~ o Q U 2 "' o o U <'" 0>0 00 ;:::;: u . ~ 0; . M 0: ~ 0 - m ,," '? ii5 -~ ~Bt5 00 o '" " ~ - o " " '" - . rn - o o . > rn - B C o E 0. 3 ~ . 0. Q "' o '5 . " " " ~ ~ . D U " 0. rn ~ ro " u ~ o U "" o .... 0; 0> o . " c . o .~ o > o " M N 00 ~ ~ o o ;;: ~ " ~ N ~ => ~ o o " M ,el (/, o o N ~ ~ "' 0> ". ;;; o o ;;: -i 0> N ~ o o N ~ N "' 0> m ;;; ~;:: 0" U~ o o ii: o o o u w ro ~ o '" iii o G ~ ~ "2 . " ~ o '" 6 " I.l") ~ ~ ~~ C[ m ~ ~B() 00 o <0 " ~ . rn o rn D u W 0. o U - g . " u u . - " 0> o a; ~ 15 o '5 ~ U ~ C o o . E B .. . .. .. rn '" " o rn o o '" ~ ,,; "l. ~ .. o rn '" ~ ~ "l. M - 0; .. " w rn o . u E o ~ - c " o E rn 'l i?, " o .... oi go ;;; ~ o '0 . . 't . > o COo:ll'- ...o~ ~O'-_ "Cl N Iii c ~.... r.O'!~e5 "'~fc3 R~ ~ '- E III c( E~ e~~ wE ....III ==Ql OJ 0 . -oQ)alC) ,....0 ~ i ~ iD 1ll.c'O 0) J: U .. <( UlflO ~;S "C U C = ~ 5 .; c E ~8: Gl ... C g~ 5 . " E "0.. o ~ ~ oc o ~ w oc oc w o oc o "--'l " . c e 3 2! Q, 0 :; g. ~ ug... Q) c u 5 f ~ 0 :;g~ Oo~ o w > ~ ~ oc ~ ~ z ~ o ~ iU "g'C .: g ~ 5 ~CD Co E o :~ c ~ u .!! ~~~ c. c . . c c. 00<1) ci c:i ::z Ql e G:l Q) ~ c:i C) "C ~ zz.,oz 15 '0 lil ~ti -c m.; c IV ~ "e g ~ e >o...(.)uo... . . o E c ~z <- M m ~ '" ~ :;, m ~ '" W M M W ai M ~ ~ '" o o w ai ~ N '" m v M N ,: m m ~ m v M N ,: m m ~ m v '" N ,: m m ~ . c. o uO !EO::: . e: . . . .~ ID C w ~ ~~ oz u > in . ~ , o . .0 co . 0 E 0 ~ 0 n1~ ~~ 0: ~ ~- 6" ~ Iii 01 '-cs;~ ;:! 2 _-201 ouw..::::i ro o ~ w . . 0. E 8 . .s . o o . E . E ~ . E {! . c. . ~ 15 o ~ ~ 05 . . ,S . ;; ~ . . , ~ . . . ~ c=- o o '" o o ~ 05 c. . o . e: 15 15. . o . " 05 u: . .s . . . ~ . . . > j5 . . > is. "6 c . E . u . 0. ~ ~ c . ~.t 00 ~~ ~ tl :5~ *~ W n ~ . n " e-o ..:5 Gl "3: ~~ ~ ~ o ~ ... . . E-E ~~ o. g; w ., ,;-- ~ '? w v '" ro w oi o ai ;;; ;;- v ro ro m. :0 ~ '" o o '" M <5 M M ai ;;; o m .; v w. o w .; ;;; o o '" M <5 M M ai ;;; o wo. ::>0 0. ~ o . c. E n o o OM :;:;10 u_ 00 ,,~ . . ON n~ 00 o ~ ~ . a:; ~, ~O ..~ o " " . . o:v'i: w . m m~ ~~o:. '.0: gc30 ro o " ~ ,0 ((; ~ W '" " ro M ., o M o M. o m ~ o o o ~ m N ~ . .. . c. " 15 ~ o 15. 2 .Q . o ~ . . m . E . ~ ,g c . E ~ . c. ID > 8 B . . ~ ~ . o cr u e C o u " o ~ . ;; .Q " . ~ i' . o cr " . u o . " ~ o e- o o .0 M m ai N N ;;; := M V m '" m ~ o o .0 M m ai N N, ;;; . ~~ .~ ~ ~ e . <I) . o Q 13 c o E g .9 o . o ID 2 ~ ~ 10(")0 ~ 2 ~tL ~-::;:b~:2 U)Zo(,)CO ;; m o . " u '0 . . E . > o ro o 2; <; ro . ~ . 0, c. ::> 1j o U . W '" . o o .Q a; .. ~ ". ro m e E: . . ;; E n " . . " ~ o . E 15 . ~ E o o . ;; . u o " ~ .Q ~ o . . u ~ . . " u '0 U . W o c o .;;; o . c. x . . 5 :2 " x o . ~ t3 o ~ ~ ~ . o e- ," " ~ 5 '0 S . . If Ij ;; m o . " u '0 . . 'E . > o - i~\gellGa Item ~~o. 16E 18 December 16, 2008 Page 5 of 17 I CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECTNAME: Blda."F" Generator & Electrical UDarade PROJECT#:08-5035 PROJECT MANAGER: Robert Fue_s BIDIIlFP #: ~ MOD': 2 POll: 45-00094788 WORK ORDER': NIA DEPARTMENT: Facilltfea Management CONTRACTOR/FIRM NAME: Southeastern Communications Serv. Inc. Original Contnct Amount: $ 1.226.635.00 (Starting Point) Cum>nt BCC Approved Amount: $ 1.226.635.00 (Last Total Amount Approved by the BCC) $ 895.793.10 (Including All Chang.. Prior To This Modification) $ 18.180,00 Cum>nt Contract Amount Chengo Amount: RsvlSod ContnlctlWork Ordsr Amount: $ 913.943.10 (Including Thi& Change Order) Cumulative Dollar Value of Changes to thl. ContractlWor1c Order. $ 1312.691.90 ) Dote of Loot BeC Approval 5113108 Agenclo Item # lOG ....')..'5.'-\:"\ Porconblgo of tho chango over/under cum>nt contract omount lID-ll Fonnula: (Revised Amount I Last BCC epproved emounl)-2 CURRENT COMPLETION DATE (S): ORIGINAL: TBD CURRENT: TBD Doscrlbe the change(s): Uncler Grouncl Tank for fuel cllesel storage for the existing generator neeclsto be blken out.ncl replacing with new generator with belly blnk, unclergrouncl tank will bocome unusable ancl a liability. Specify the reasons for the chang'ls). 1. Planned or Electiv. r 2. Unforeseen Conclitions ("> 3. Quantity Acljuatments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Velue Aclded r 6. Schedule Adjustments Note: One or more may be checked, depencllng on the nature of the change(s). k1enlify all nlllative impacts to the project if this change order were not procB$8ecl: This c~ needed to make room for new aenerator end conduits which are In the Dath of the blnk.~ /J.JL I~ . This change was requested by: rContractor/Consulblnt ~ Owner rl Using Department r: CDES r Other (Specify) · Ves r No REVIEWED BY: Project Manager ~/J1~ act Specialist lo/~8/oY Date: Date: Revised 11.19.2007 II Agenda Item No. 16E 18 ;;;z. December 16, 2008 Page 6 of 17 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Tourism Research Services PROJECT#: PROJECT MANAGER:_Jack Wert BID/RFP #: 07-4169 MOD#: 1 PO#: 45000098805 WORK ORDER #: DEPARTMENT: Tourism CONTRACTOR/FIRM NAME: Research Data Services Inc. Original Contract Amount: $_113,100.00 (Starting Point) Current BCC Approved Amount: $ 113,100.00 (Last Tolal Amount Approved by the BCC) Current Contract Amount: $ 113,100.00 (Including All Changes Prior To This Modification) (/,1$0.00 11,183.00 1:2</, c2S-0. 00 :l-2.4,16Ci.ficr. - (Including This Change Order) Change Amount: $ $ Revised ContractIWork Order Amount, Cumulative Dollar Value of Changes to this ContractIWork Order: $ 1'.100.1lU 1/. IS'''. (lCJ .. Date of Last BCC Approval 912512007 Agenda Item # 16F6 Percentage of the change over/under current contract amount ~ tJ. ~ L- % Formula: (Revised Amount 1 Last BCC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: onaoina CURRENT: Describe the change(s): · Draft and communicate International discussion guide to project team; finalize research objectives and topics. . Revise discussion guide to reflect team feedback. . Participate in International round table sessions. . Debrief project team regarding key issues. · Analyze and synthesize session recordings; prepare group abstracts and summaries of key findings. . Communicate results to project team. Specify the reasons for the change(s) r 1. Planned or Elective ,.. 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be cheeked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: This would significantly impede our efforts to attract international visitors to our destination This change was requested by: r1Contractor/Consultant 't- Owner r Design Professional r[Regulatory Agency (Specify) rJ Using Department r CDES CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: This form is to be signed and dated. r r OttJr (Specify) Yes ~o APPROVED BY: Date /tJ-3/-CJS Date: / /) -.J.I-of REVIEWED BY: Contrac Rcviscd 11.19.2007 -- -----'1' CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item t-.Jo. 16E 18 "2 December 16, 2008 . Page 7 of 17/ PROJECT NAME: South Reqional Library PROJECT #: 54003 PROJECT MANAGER: Hank Jones BID/RFP #: 07-4176 MOD #:11 PO#: 4500087770 WORK ORDER #: N/A DEPARTMENT: Facilities Manaoement CONTRACTOR/FIRM NAME: DeAnqelis Diamond Construction. Inc. Original Contract Amount: $ 6.519,813.00 (Starting Point) Current BCC Approved Amount: $ 6.519,813.00 (last Total Amount Approved by the BCC) Current Contract Amount: $ 5,956.843.42 (Including All Changes Prior To This Modification) Change Amount: $ -13.830.62 Revised ContractIWork Order Amount: $ 5,943,012.80 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ -576.800.20 Date of Last BCC Approval: September 11. 2007 Agenda Item #: 10E Percentage of the change over/under current contract amount - 8.85% Formula: (Revised Amount I last BeC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 11/1/2008 CURRENT: 11/1/2008 Describe the change(s);,All additional time and costs associated with the changes as outlined in: I) Adjustment to owner contract allowance for People Counters to credit back the unused balance (as outlined in PCO #17 dated 3/17/08); 2) Make the required lighting changes in bathrooms 105 & 106 per direction received as part of RFI #128 (as outlined in PCO #47 dated 10/9108): 3) Adjustment to owner contract allowance for additional interior signage to credit hack the unused balance (as outlined in PCO #48 dated I all 7/Qn Specify the reasons for the changers) r 1, Planned or Elective r 2. Unforeseen Conditions r. 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the changers). Identify all negative impacts to the project if this change order were not processed: This change was requested by: rtContraclor/Consultant rr Owner r Using Department r CDES PIDesign Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: ryes po No Dale: '0/vg fiI-1/()( ~ APPROVED B REVIEWED BY: ri cipal Project Manager /! (f . /--t~-1--1._/'I. ~.ate: Rhonda Cummings, Contract Spec' i Revised 11.19.2007 - CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda Item No. 16E18 December 16, 2008 Page 8 of 17 1./ PROJECT NAME: Sheriff Fleet PROJECT #: 52009 PROJECT MANAGER: Claude Nesbitt BID/RFP #: 06-3914 MOD #: 003 PO#:45-100673, replaces 45-091804 WORK ORDER #: DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Wriaht Construction Original Contract Amount: $ 9,272,848.00 (Starting Point) Current BCC Approved Amount: $9,272,848.00 (Last Total Amount Approved by the BCG) Current Contract Amount: $8,931,159.50 (Including All Changes Prior To This Modification) Change Amount: $(110,115.00) Revised ContractIWork Order Amount: $8,821,044.50 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWor1< Order: $(451,803.50) Date of Last BCC Approval January 15, 2008 Agenda Item # 10 A Percentage of the change over/under current contract amount -4.87% Formula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (8): ORIGINAL: Mav 2009 CURRENT: Mav 2009 Describe the change(s): DMP - Auto shop equipment Specify the reasons for the change(s)!9'" 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: exclusion of a cost saving opportunity This change was requested by: rlContractor/Consultant ~owner rl Using Department r CDES !:Design Professional r[Regulatory Agency (Specify) r other (Specify) r Yes .~ CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: This form is to be signed and dated. APPROVED BY \>>.L'J\ Jl/1 """" tt- Project rvlBnager '\ Date: \' \Ii\ \ ~09C( \ \ REVIEWED BY: ~ iJ Date: II /10 ~ I Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM ,l'oenda item No. 16E18 it 2?b'~I~r PROJECT MANAGER: Adonis Martinez ~ :J PROJECT NAME: CDES Division Software PROJECT #: BID/RFP #: 06-3962 MOD #: 5 PO#: 4500078532 WORK ORDER #: DEPARTMENT: CDES CONTRACTOR/FIRM NAME: Municipal Software Corporation Original Contract Amount: $ 1 ,996.272.00 (Starting Point) Current BCC Approved Amount: $ 1 ,996,272.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 2,194,141.00 (Including All Changes Prior To This Modification) Change Amount: $ (33,600.00) Revised ContracllWork Order Amount: $ 2,160,541.00 (Including This Change Order) Cumulative Dollar Value of Changes to this ContracllWork Order: $ 164.269.00 Date of Last BCC Approval 7/22/08 Agenda Item # 16E7 Percentage of the change over/under current contract amount Formula: (Revised Amount 1 Last BCC approved amount)-1 823 % CURRENT COMPLETION DATE (5): ORIGINAL: 11/1/08 CURRENT: 11/1/08 Describe the change(s): Municipal Chanoe order #3 and #5. orioinallv added to the contract on Modification #3, Chanoe Order #1, are not proceedino. The reason thev are not proceedino is because those two chanoe orders are not part of the proiect, thev are with Code Enforcement, and due to new manaoement within Code Enforcement, thev are reviewino their workflow and chanoes mav be forthcomino. Proiect Manaoement does not want to pav for chanoe orders when the workflows mioht be chanoed. Specify the reasons for the change(s) (0 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: If this chanoe order is not processed, the proiect will be pavino for workflows that mioht be chanoed in the near future due to Code Enforcement analvzino its' processes. Code Enforcement will pav for workflow chanoes if reouired. This change was requested by: rlContractor/consultan~ner n Using Department E: COES COesign Professional nRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: (\ This form is to be Sig~e~ a^nd dated. APPROVED BY: _~ ~ Project ,anager ~~ - \/1/1 REVIEWED BY: L~ ) r I Contrdcl (jP8dCiiisl r Yes P' No Date: \ 0/2 i.f/(j t , ,)'J_ f) t /M'-t{ Date: I. /, pl I/I(~ OQ I ~ , . Revised 2-22-08 CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM Agenaa Item I~o. 1tJ1::1~ L.. December 16, 2008 V Page 10 of 17 PROJECT NAME: Sidewalk Reolacement and Liahtina Installation on Davis Blvd rSR84\ PROJECT#: _NA_ PROJECT MANAGER: John W. Miller BIDIRFP #: 07-4107 MOD#:...L PotI: 4500090798 WORK ORDER #:_ NA_ DEPAR1l\lENT: Traffic Ooeratlons CONTRACTOR/FIRM NAME: Qualltv Enterorlses USA. Inc. Original Contract Amount: $ 997.213.49 (Starting Point) Current BCC Approved Amount: 'U j;v 1Lh/l~ tOrft, ~.f-s. Current Contract Amount: $ 997.213.49 (Including All Changes Poor To This Modification) Change Amount: $ -258.600.13 Revised ContractlWork Order Amount: $ 738.613.36 (Including This Change Order) Cumulative DoUar Value of Changes to this ContractlWork Order: $ -258.800.13 Date of Last BCC Approval Seotember 25. 2007 Agenda Item # 16 B5 Percentage of the change over/under current contract amount Formula: (Revised Amount I Last BCC approved amount}-l -25.93 '10 CURRENT COMPLETION DATE (5): ORIGINAL: November 1. 2006 CURRENT: November 1. 2008 Describe the change(s): Saw cuttlna the drlvewavs alona Davis Blvd to install the conduit and conductors for the Roadwa Li htln . After Ian a roval b FOOT and be innin of construction e were notified b FOOT that the drivewavs could not be removed because limited rlaht-of-wav SDace Dre ented the reDlacement of the driveway frDm meeting current Americans with Disabilities Act IADl reauirements and saw cutting a twelve (12) inch wide "Maintenance Slot" In existlna drivewavs would be reaulred for Installation of the lIahtina conduit and conductors. The overall deduction Is a result of the amount of concrete reaulred beina less than that estimated and not reDlaclna drlvewavs as a Dart of the sidewalk reDlacement construction. Specify the reasons for the change(s) n 1. Planned or Elective Cl 2. Unforeseen Conditions II 3, Quantity Adjustments C 4. Correction of Errors (Plans, Specifications or Scope of Work) C 5. Value Added r:: 6. Schedule Adjustments Nots: One or more may be checked, depending on the nature of the changers). Identify all negative impacts to the project If this change order were not processed: If this madlficatlon Is not Drocessed there will be no Drovislons to Dav the contractor for lealtimate work he was reauired to DtIrform. This change was requested by: DlcontractorlConsultant DI Owner I!I Using Department !J. CDES DOesign Professional DlRegulatory Agency (Specify) OOther (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: n Yes ~NO APPROVED BY. Date: ;;f~);8 APjOVED BY: / If If) (?9PROVED I3Y: Date: Director REVIE\oVED BY: r"\_~_, L.lQU:::. o tract SpeCialist Revised 11.19.2007 Administrator ____~..___U" CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM j",oenda !tsm !\Jo. l6E1S ~ December 16, 2008 Page 11 of 17 7 BIDIRFP #: 06-3996R MOD #: 4 PROJECT#: 70151, 70152, & 70153 PO#: 4500101541 PROJECT MANAGER: Ronald F. Dillard PROJECT NAME: C.R. 951 Water Main WORK ORDER #: NIA DEPARTMENT: PUED CONTRACTOR/FIRM NAME: Akerman Construction Comoanv. Inc, Original Contract Amount: $ 18.330,133.00 (Starting Point) Current BCC Approved Amount: $ 18.330.133.00 (last Total Amount Approved by the BCC) Current Contract Amount: $18.601.648.90 (Including Ail Changes Prior To This Modification) Change Amount: $ 1581,968.44\ $18.019.680.46 (Including This Change Order) Revised ContractIWork Order Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ (310.452J~W' Date of last BCC Approval 9-26-06 Agenda Item # 10-1 Percentage of the change over/under current contract amount (01.69) % Formula: (Revised Amount I Last Bce approved amount}.1 CURRENT COMPLETION DATE (S): ORIGINAL: 11-20-07 CURRENT: 10-20-08 Describe the change(s): Balance all contract Quantities to the final contract Quantities. Specify the reasons for the change(s) 0 1. Planned or Elective D 2. Unforeseen Conditions EJ 3. Quantity Adjustments D 4. Correction of Errors (Plans, Specifications or Scope of Work) D 5. Value Added ~ 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Proiect closeout could not Qff.!!L This change was requested by: EIcontractorlConsultant EJ Owner 0 Using Department 0 CDES DDesign Professional DRegulatory Agency (Specify) Cather (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: El Yes ,-, EJNo This form is to be signed and dated. APPROVED BY: ';(!,y>..LL / ~ ~ Ronald F Dillard, Senior Project Manager UJ0 '- PGr Engineering Director Date: If-;:?~og APPROVED BY: Date: {(-I<{-or /1-('-//0'9 REVIEWED BY. Date: v Revised 2-22-08 Agenda Item ~Jo. 16E18 'if December 16, 2008 Page 12 of 17 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECTNAME: Bld"."F" Generator & Electrical Uo"iade PROJECT#:08-5035 PROJECT MANAGER: Robert Fuentes BID/RFP #: 08-5035 MOD #: 3 POI: 45-00094798 WORK ORDER #: N/A DEPARTMENT: Facilities Management CONTRACTOR/FIRM NAME: Southeastern Communications Servo Inc. Original Contract Amount: $ 1,226.635.00 (Starting Point) $ 1.226,635.00 (Last Total Amount Approved by the BCC) $ 913.943.10 (Including All Changes Poor To This Modification) C;:urrent BCC Approved Amount: Current Co~tract Amount: . Change Amount: $ 112.640.001 Revised ContracUWork Order Amount: $ 901.303.10 (including This Change Order) Cumulative Dollar Value of Changes to this ContracUWork Order: $ 1325.331.901 Date of Last BCC Approval 5/13/08 Agenda Item # lOG Percentage of the change over/under current contract amount ~ Formula: (Revised Amount I Last BCC approved amount)-2 ,'J.L,.S'" , CURRENT COMPLETION DATE (5): ORIGINAL: TBD CURRENT: TBD Describe the change(s): The additional 'A duct bank for Sub-Station "A" was installed for any future expansion of electrical service. On the specifications (3) three manholes were to be required, during the excavation process Engineer realized that only (1) one was needed. Specify the reasons for the change(s)" 1. Planned or Elective r 2. Unforeseen Conditions . 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added C 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s}. Identify all negative impacts to the project if this change order were not processed: This chanae is needed to increase electrical load for any future expansion in the site. This change was requested by: r1Contractor/Consultant "" Owner rI Using Department r COES !lOeslgn Professional r1Regulatory Agency (Specify) rOther (Specify) REVIEWED BY: .. Yes r No Date: 11~~8 I I (11;;tcveJ Y I I I I I . I ---J Date: Revised 11.19.2007 ----, -.... :()OJf'- ~~ LL>O _ i3:.N 0 ~.(1') ~~ """'>..... Q) ~"'OJ t!.'.o '" (J)EQ. -", ",u '0'" ~O ii) OJ <( l' . 1Il ~ "'C cf. ~:s 0 .u~ 13 E (; ,g~ ;; ~ c . Q) .- '0 ~.~O cf.lllO~ '" E ~ O,g~ . -g5~ .~ ~ E e 0 <( "';:'" .s~c ~o 6 c ~ E 10 cc u;:'" ~ '" o ~ w '" '" w o '" o '" '" o " o ~ w w " z <> U '" ~ ~ eo w z ~ =< . 'E c'E :::I ~ ~ ~ ::::I (; 0:( u;:", c -g'E ~ u ~ 6 - (..) ... E ::I aJ :5:< u <'" - - c . u , c . c :!? 'E E o8~ 'E E u ]! t:: ~"i III _'(:3 0. C . . C 0. oucn c Z c ~z ~ ;:; :;~ o 5 ;:u c z E ~ ~I ~~oz o u ~ U "'C .S!. C lP ~ e ~"e >a..ua.. . ;; o E ~~ 0' o N ~ " " N .. o o 00 N o M' 00 .. o o o ~ ~ cO .. o o ~ N cri 00 .. '" z o o 00 ~ N cri 00 .. ~ " ~ M o 00 9 ~ 00 M '" ~ ~ >~ ~~ 13 jj ~ o o o o , " > E . N ~L ~<1:~~ :s:zGiil 00 P 6 M 2> . l' m E m > o 0. " ~ cii " :;, ~ ~ N " o ~ ;; o o ;:' 00 '" N .. ~ o '6 c , e ~ ;; c g '6 ~ m ~ o m ~ g m " . u iii o g '6 ~ . ,; u ;: m . iii u o " m W 9 . o Q ro u '" ~ o E ~ ~ " rr ~ L U .c . o o o M o ,0 .. o o o ~ 00. N .. o o o M M ~. ;;; o o g M ~. .. " ...0 <'" w "' o ~ m M '*~ ,,;; Ory ~ ~ ~m ~ 5. 'i rr m o '6 ~ a Q ro 5 '" C o u ~ D > o 0. o ... ~- o m '" ~ OL <Ii '50.... m m 0 m c;: Q g ~ m <I> S2 b 4l 2: :ii <6 r0Jja:: %l g, &,@ ~~~~al :2zuo:2 0; a c m L u '0 . . .~ . > o 00 m '" co N " N o 00 " N o cri ~ N 00 ~ ~ ,0 .. ~ N .. ~ ~ .. o o ~ M o ,0 .. o o ~ M o ,0 .. o o ~ M o m .. ~ o is 5 u ~ " >< m C '6 ~ 9 . m u > " . o ~ "' m ~ iii o Q ~ ~ u m ;; > o 0. o ~ . 0. o U ~ ~U ~"' N o 00 9 00 00 ~ M 00 ~oo 17~ w~ ~ 0 . u > o m m 0 ~ 0 01 E c ~ ~ g iiJ m ro ~ ~~ ~, ~:: E ~ g ~ ~ ~~~.g;-g u...Z()(f)-=:i . a o , U o . . .~ . > o 00 o -i 00 M u > a; ~ N .. N M .; '" " D E ~ ~ m ro E ;;: m W o 0> ~ :5 m > o D m ~ ~ 'i rr ~ a E " ~ m 0; ~ " u ~ ~ m I? ~ g "' " ~ :5 ~ .< C> 0; a c m L u a . . .; 0; > o " o ~." S .:) ~, CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM .L\genda item 1'0. 16E18 ,0"d^Y;;W~ PROJECT NAME: 600 MHz Site ImDrovements PROJECT #:,w'}V FT 9971 98 Qi PROJECT MANAGER:_John Daly BIDIRFP #:01.: . 7yCJ'1 / MOD #: I PO#: WORK ORDER #:_WJV-FT-3791-06"()3 DEPARTMENT: Information Technology CONTRACTORlFIRM NAME: William J Varian Construction Co. Original Contract Amount: $ _$69,278 (Starting poin;, $ (Last TOla~O~pproved by the BCC) $ 89,278 (Including All Changes Prior To This Modification) Current BeC Approved Amount: Current Contract Amount: Change Amount: $_$3,750.00 Revised ContractlWork Order Amount: $ $93.026 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractJWorl< Order: $ 93,028 Date of Last BCC Approval viR . t Agenda Item # ;J /,A I lco Percentage of the change over/under current contract amount_ 4 . '1 Formula: (Revised Amounti Last BCC approved amount)-1 % CURRENT COMPLETION DATE (5): ORIGINAL: 5/23/08 CURRENT: 10115108 Describe the change(s):_ Final configuration of radio equipment in the room required modifications to electrical service, additional cable trays and additional grounding. This change order did not alter the completion date. Contractor was unable to complete construction until installation of new radio equipment and removal of old equipment was complete allowing final configuration of the air conditioning system. . Specify the reasons for the change(s) 0 1. Planned or Elective 0 2. Unforeseen Conditions C 3. Quantity Adjustments 0 4. Correction of Errors (Plans, Specifications or Scope of Work) Ji( 5. Value Added o 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The final confiQuration of the radio system eauioment renuin::>.n mnr1if;(,,;:lrirm t-n t-hp Alo,...f-r;,.....;:;:,1 noco},...,..... to ~Tgnidc power to the equipment. Without the chang~me equiPment would not ~ ~J2~~tional This change was requested by: Clcontractor/Consultanf ~ Owner L1 Using Department Tl GOES . LDesign Professional C1Regulatory Agency (Specify) COther (Specify) Date: ,/c.'" ,,-- y. ..,';',Jo- REVIEWED BY: 1 Date 10" ?CJ-tJf{ Revised 11.19.2007 ....'....-.. CONTRACT/WORK ORDER MODIFICATION CHECKUST FORM /~.]enda !lem No. 16E 18 /) - December 16, 2008 0'.. L I r3g,~ 1~Of 17 ~ +~ L~''1ED PROJECT NAME: Desion Services - Radio Road Median Renovation Phsse 1 PROJECT #: 4500100241 PROJECT MANAGER: Darrvl Richard BID/RFP #: 04-3614 MOD #: lonel~ PO#:UOOO&li311QII4500100241 WORK ORDER #: TlO-MA-3614-06-16 DEPARTMENT: Alternative TransDortalfon Mod... CONTRACTOR/FIRM NAME: McGee & Associates Cum>nt BCC Approved Amount: $ 17.330.00 (Starting Point) $ 17.330.00 . (Last Total Amount Approved by the 00 $ ;I~~:~:PJI~? !~~. ~ndffi03tlon~ $ 6,030.00 '. _' , $ 23.360.00 :!2.f"'? C?7(), .Ml (Including This CFiang/ ckrr- I ~ ~ Original Contract Amount: Cum>nt Contract Amount: Change Amount: Revised ContractIWork Order Amount: Cumulative Dollsr Value of Changes to this ContractIWork Order: $ 8.0e8,So. j(J,W!Ot 00 ~ Date of Lest BCC Approval 9/21/04 Agenda Item #16.E.8 Percentage of the change over/under current contract amount If; l,J#) % '':2.1.49 (0 Formula: (Revised Amount I Last BCC approved amO\Jnt)-1 ' CURRENT COMPLETION DATE (S): ORIGINAL: Januarv 29, 2007: CURRENT: November Ii 2008 , Describe the change{s):_ Due to TECM Department modifications to existing curbing as part of Traffic Calming Project, Irrigation and Landscape plans require modification to not be in conflict with TECM Changes. Additional design time for PrincipaVSenior Landscape Architect at 48 hrs. at $110.00 per hour; Additional TechnicaVCAD time for CAD Technician at 8 hrs. at $60,00 per hour; Additional Administrative time for Administrative Assistant at 6 hrs. at $45.00 per hour. Total Change is $6,030.00 additional in design fee. Rates are based on contract 04-3614 Landscape Architectural Services Specify the reasons for the change{s) r 1. Planned or Elective r- 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: _ If change order were not to be executed the design plans would not be modified to reflect current TECM Project changes and would, therefore, result in conflict in installation of irrigation sleeves, and laterals necessary for irrigation and landscaping installation would conflict with current TECM Project. This change was requested by: rlcontractor/Consultant rJ Owner 1"'1 Using Department r CDES ~Design Professional rJRegulatory Agency (Specify) rOther (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: ryes P' No RECEIVED OCT 2 9 2008 This form Is to be signed and dated. Revised 11.19.2007 I'T8ns p'--~rt3. t lr...:1'~ ACrM Dept. APPROVED BY: REVIEWED BY: Revised 11.19.2007 Date: Date: lo-ir,03 I J-~{)( Agenda Item No. 16E18:;( December 16, 2008 CI" Page 16 of 17 RECEIVED OCT 2 9 2008 TransportatIon ATM Dept. - "..,.,"."._,--~~"-"""-,,--~-,~,,,,," .[~genda Item No. 16E 18 December 16, 20083 Page 17 of 17 CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Sidewalk Replacement and LiQhtlnQ Installation on Davis Blvd CSR841 PROJECT MAfGER: Jpbn W. Miller ~ -358"15 BIDIRFP #:.li- MOD #:...L PQ#: 4500093515 PROJECT #: _NA_ oft -02- WORK ORDER #:_ FEI-FT.35BB-02_ OEPARTMENT: Traffic Operations CONTRACTOR/FIRM NAME: ForQe EnalneerlnQ. Inc. Original Contract Amount: $ 6.035.00 (Starting Point) Current BCC Approved Amount: $ 6,035.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 6.035.00 (Including All Changes Prior To This Modification) Change Amount: $ 544.25 Revised Contracl/Work Order Amount: $ 6.579.25 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractlWork Order: $ 544.25 Oale of Last BCC Approval NA Agenda Item # NA Percentage of the change overlunder current contract amount .~ q, ~ Formula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: November 1, 2008 CURRENT: November 1, 2008 Describe the change{s): additional sets of concrete testlna were reouired above the oriQinal estimated number. Specify the reasons for the change(s) n 1. Planned or Elective C 2. Unforeseen Conditions X 3. Quantity Adjustments C 4. Correction of Errors (Plans, Specifications or Scope of Work) C 5. Value Added C 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: If this modification is not processed there will be no provisions to pay the contractor for leoltimate work he was reoulred to perform. This change was requested by: rlcontractor/Consultant rl Owner X Using Department C CDES CDesign Professional r1Regulalory Agency (Specify) r Other (Specify) rYes "f<NO CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: APPROVED ate: Ill],/;g APPROVED BY: f{l;~ I / REVIEWED BY: Jl ~/ } I 15 D ~PROVED BY: Contract Spe alist ( ) '--...../ Date: Director Date: Administrator Revised 11.19.2007