Agenda 12/01/2009 Item #16B 4 EXECUTIVE SUMMARY Agenda Item No. 1684 December 1, 2009 Page 1 of 7 .-', Recommendation to approve a Change Order and authorize the County Manager, or his designee, to sign Change Order #2 for Kelly Brothers, Inc. for the County Bridge Repair and Restoration Program, Project #66066, Contract #08-5135 in the amount of $44,302.00 for additional repairs needed to both the Chokoloskee and Oil Well Road Bridges. OBJECTIVE: Recommendation to approve Change Order #2 extending the construction services that includes additional erosion control, adjusted quantities and additional contract time. CONSIDERATIONS: On March 23, 2009, the Board of County Commissioners (BCC) awarded Contract #08-5135 to Kelly Brothers, Inc. in the amount of $771,546.00 {Agenda Item l6(B)(5)}. Notice to Proceed was given on May 11,2009. On July 7, 2009, Change Order #1 in the amount of$57,720.00 was approved for repairs to seawall caps and the guardrail system. - The contract plans are developed based on the visual inspection of the bridges by the designer and the findings provided in the FDOT Inspection Reports. It is in the process of making the repairs to the bridges during construction that the full extent of deficiencies become known. At the Chokoloskee Bridge the competency of the concrete was worse than the visual inspection or FDOT Inspection Reports indicated. The full extent of the repairs became apparent when the jackhammer was put to the concrete. Additional cracking of the bridge was discovered requiring the installation of a 4" thick layer of concrete to complete the repair. The undermining of the end bents on the Oil Well Road Bridge was below the water surface and not apparent by inspection or the FDOT Inspection Report. Pressure grouting underneath the bridge bents was needed to repair the bridge. Upon completion of this change order, staff will issue a substantial completion of this project. The cumulative total of Change Orders #1 and #2 is $102,022.00, which is 13.2% above the BCC approved contract amount. County purchasing policy requires that any change order amount above 10% of the BCC approved contract amount must be approved by the Board of County Commissioners. FISCAL IMPACT: Funds in the amount of $44,302.00 are available trom gas taxes. Source of funds are gas taxes. LEGAL CONSIDERATIONS: This item bas been reviewed and approved by the County Attorney's Office and is legally sufficient-SRT. GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this Executive Summary. RECOMMENDA nON: Recommendation to approve a Change Order authorizing the County Manager, or his designee, to sign Change Order #2 for Kelly Brothers, Inc. for the County Bridge Repair and Restoration Program, Proj ect #66066, Contract #08-513 5 in the amount of $44,302.00 for additional repairs needed to both the Chokoloskee and Oil Well Road Bridges. ..- Prepared by: Eddie Martin, Project Manager, TECM Attachments: (I) Change Order #2; (2) Contract Modification n_ __"""_"_~'_ _.. ,.,~. '" , 4" ,- .,."'.-.-----... Agenda Item No. 1684 December 1, 2009 Page 2 of 7 "- COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: Item Summary: 16B4 Meeting Date: Recommendation to approve a Change Order and authorize the County Manager, or his designee, to sign Change Order #2 for Kelly Brothers, Inc. for the County Bridge Repair and Restoration Program, Project #66066, Contract #08-5135 in the amount of $44,302.00 for additional repairs needed to both the Chokoloskee and Oil Well Road Bridges. 12/1/20099:00:00 AM ._'_.__.~~---- - .-..--.----.-.-,-' --~"._~""-,,_. ~..,- -",...,~._~.- - Agenda 11em No. 1684 December 1, 2009 Page 3 of7 Pat Lehnhard Ex.ecutlve Secretary Date Transportation Division Transportation Administration 11/18/20091:21 PM Approved By OMS Coordinator Date County Attorney County Attorney 11/19/20091:48 PM Approved By Susan Usher ManagemenUBudget Analyst, Senior Date Office of Management & Budget Office of Management & Budget 11/19/2009 5:S2 PM Approved By Mark Isackson Management/Budget Analyst, Senior Date Office of Management & Budget Office of Management & Budget 11/19/20095:58 PM CONTRACT MODIFICATION CHECKLIST FORM Agenda Item No. 16B4 December 1, 2009 Page 4 of 7 PROJECT NAME: Bridge Repairs (Chokoloskee, Green Blvd. and Oilwell RoadO PROJECT #:66066 PROJECT MANAGER: Eddie Martin BID/RFP #: 08.5135 MOD #: 2 PO#:4500106688 DEPARTMENT: TECM CONTRACTOR/FIRM NAME: Kelly Brothers Inc. Original Contract Amount: $771,546.00 (Starting Point) Current BeC Approved Amount: $771,546.00 (Last Total Amount Approved by the BCC) Current Contract Amount: $829,266.00 (Including All Changes Prior To This Modification) Change Amount: (add) $ 44,302.00 Revised Contract Amount: $873,568.00 (Including This Change Order) Cumulative Dollar Value of Changes to $ 102,022.00 this Contract: (add) Date of Last BCC Approval: March 24'" 2009 Agenda Item#'16. (B).5 Percentage of the change under current contract amount: 13.22% ", Formula: (Revised Amount I Last BCC approved amount).' CURRENT COMPLETION DATE (S): ORIGINA(/",)!6RRENT: fa \ 'l ( 01 Describe the change(s): Chokoloskee Bridge (1) Correct the erosion that was discovered after the MAT installation. (2) Additional crack repair was needed to complete the seawall repair. Oil Well Road Bridge (1) Pressure grouting to fill in voids that were discovered after removal of the rubble was remove under the bridge. (2) Extra turbidity barrier had to be added due to high water elevation at time of repair. Specify the reasons for the change(s) 1. Planned or Elective 2.X Unforeseen Conditions 3.X Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Bridge failure, Slope pavement erosion, safety for the public and possible pollution fines from BCB (Okaloachoochee Slough) and the National Park (Chokoloskee Bay). This change was requested by: rlContractor/Consultant 171 Owner rI Using Department r CDES X Design Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: P' Yes r No This form is to be signed and dated. ," f ~ , , '" . .- ~ 'I .- APPROVED BY: ' ?', " /,,' //. ,. ;:,{..:_ Date: '-=.~dJ=.r.1)rtin, pr~ect Mfrnager ,""'_' REVIEWED BY: '1 ~bu...) il (-i.{1l1'[v:f\ ~ Date: JRhonda Cumrii1ngs, Contract 1?eCi~list Revised 11.l9 .2007 ~,/ / j- t. - {} ? I Ie :0 Ie ( , ~ . .,. ~'''''''__ _. ._..~...m -,,_.' , ...-.--.-.--. Agenda Item No. 1684 December 1, 2009 Page 5 of 7 CHANGE ORDER CHANGE ORDER NO. , - CONTRACT NO. 08-5135 BCC Date: 3/24/2009 Agenda Item: 16B5 TO: Kellv Brother Ine, 15775 Pine Ridge Rd Fl Mvers, FL 33908 DATE: November 4th, 2009, . PROJECT NAME: Bridge Repairs ((l1okol-""h.ec,.grecn,BouJg}'~[d. An.<1. Oil Wel!Jl.olld) PROJECT NO. 66066 Under our AGREEMENT dated: April 13", 2009 You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: Reference to the recommendations of Cardno TBE, Collier County Design Engineers and the Engineer of Record on the project: 1.0 Install a 4"Thick layer of 4000 PSI concrete between the edge of asphalt and the ARM. This layer of concrete should extend underneath the bridge between the abutment and the ABM and round the area between where the water pipe penetration in the ground. 2.0 Place#57 stone in the space between blocks of the ABM to provide additional UV protection to the filter fabric underneath the blocks. 3.0 Provide non-erodible backfill from the edge of pavement down to the end ofbulhead. 4.0 Additional Turbidity Barrier at Oilwell Road bridges. 5.0 Pressure grouting underneath the bents on Oilwellroad Bridge (Per EORMemo) includes drilling on top of approach slab, arrange rubble riprap and patch drilled holes. 6.0 Additional crack repair of Chokoloskee Bridge. 400-135 Clean & repair cracks overruns. FOR THE (Additive) (Deductive) Sum of: Original Agreement Amount $ ------- __77L~_.~9-00 ____ --------_.~ Sum of Previous Changes $ 57.720.00 This Change Order Add $ 44.302.00 ~- - Present Agreement Amount $ ~._--_._--- 873,568.00 The time for completion shall be increase by 90_ calendar days due to this Chan~e Order. Accordingly, the Contract Time is now December 7th, 2009 (21 []) calendar da) s. Tt,c substantial completion date is November 22nd, 2009 and the final completion date isJ1ccenlber "lh.:C009. Your acceptance of this Change Order shall constitute a modification to our Agreement and \"\I]J he pl,,;'rfnnneJ subject 10 all the same terms and conditions as contained in our Agreement indicated ahove. as fully as if the same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a futl and final settlement of any and all O~ Agenda Item No. 1684 December 1, 2009 Page 6 of 7 -. claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted: ,20 CONTRACTOR: Kelly Brothers, lnc 15775 Pine Ridge Road Ft. Myers FI. 33908 " J .-..~.,.,-~ / ' BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA /;/,_., By: '#r7;~'c.~__: /" Ic'~~" ~ - / / , i I i By: -~, , ~ ,--- ----- Chri;; Bautista Authoril~d SiQ.nature Eddie Martin, Project Manager TEC'vl -- . /' By: S./ -{ ,- ( Steve Ritter Manat!er-Road Construction - , /1 By: / _. /~-..::- p , Jav AI\JTlad. T'I:CvllJirector DEPARTMENT DIRECTOR 1//5fo'j "A~'" ,.,,'- . / ./ ' . ,lte " -c...) _. By: Norman Feder, DN ION ADMINI /' ~" / I '~: cAin By. '.._. Rho Ida Cummings CONTRACT SPECL<\UST , I .- ,__"__,,,_,~"___",d, ' ""....-...<',_....,_..~., -,.' .",.<^._._._~...'>.,., ,~._.__._<"..- , -."..-."-- ... -- Dale: ATIllST: Dwight E. Brock, CIezk BY: Appnwed As To Form IDd Lepl SafIlcioacy: . ~ -". .----... Agenda Item No. 1684 December 1.2 q _._. Page 7 of 7 BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY FLORIDA BY: D-..... Fiala, CbairmIIl ~ I