Agenda 10/27/2009 Item #16B 7Agenda Item No. 16137
October 27, 2009
Page 1 of 16
EXECUTIVE SUMMARY
Recommendation to approve a work order in the amount of $269,010.00 to Post, Buckley,
Schuh & Jernigan, Inc. (PBS &J) under contract #06 -3969 Fixed Term Professional
Engineering Services utilizing the Best Value Offer process (BVO #06- 3969 -9) for design
and permitting of the Lely Area Stormwater Improvement Project (LASIP) Naples Manor
Ditch and US 41 Ditch Design (Project No. 51101).
OBJECTIVE: To approve a work order to assist the Transportation Services Division,
Stormwater Management Section in the design and permitting of the LASIP Naples Manor Ditch
and US 41 Ditch Design. The need for these services is described in greater detail on the
attached Professional Engineering Services for LASIP Naples Manor Ditch and US 41 Ditch
Design - Scope of Work.
CONSIDERATION: The purpose of the LASIP project is to provide a comprehensive
stormwater outfall system for the area of East Naples, which has experienced an increasing level
of drainage related problems as growth has continued in the area. The drainage area of LASIP
consists of about 11,135 acres and consists of two sub - basins known as the Lely Canal Basin
system and the Lely Manor Basin system. The Lely Canal Basin discharges into an estuarine
coastal zone along the intercoastal waterway near Dollar Bay. The Lely Manor Canal discharges
into an estuarine coastal zone near the headwaters of Sandhill Bay and eventually into Rookery
Bay. The Naples Manor Ditch and US 41 Ditch Design is the next phase of LASIP to be
designed in the scheduled Stormwater LASIP program.
Pursuant to the contract, a summary of work was provided to all qualified firms under the fixed
term professional engineering services contract. Four proposals were received and ranked by an
informal selection committee on September 10, 2009, under the Best Value Offer process. The
final ranking is shown below:
FINAL RANKING
Name of Company
Rankin
PBS &J, Inc.
I" Place
Q Grady Minor and Associates, Inc.
2a
TBE Group, Inc.
3r Place
Agnoli, Barber and Brundage, Inc.
4 Place
It is important to have this element of LASIP approved to continue the progress that the
Stormwater Management Section has achieved over the past three years. Many portions
including the larger, downstream outfall canals have been successfully constructed. The
Environmental Resource Permit to construct LASIP, which was issued jointly by the US Army
Corps of Engineers and the South Florida Water Management District, will expire on July 25,
2015. If the entire LASIP project is not completed by that date, modified permit requirements,
if allowed, could require additional costs, mitigation, and delays.
Agenda Item No. 1667
October 27, 2009
Page 2 of 16
FISCAL IMPACT: Funding in the amount of $269,010.00 is available in the Stormwater
Capital Projects Fund (325) LASIP (Project No. 51101).
LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County
Attorney's Office and is legally sufficient for Board action —SRT.
GROWTH MANAGEMENT IMPACT: The LASIP Naples Manor Ditch and US 41 Ditch
Design project is in accordance with the goals and objectives of the Drainage Sub - element of the
Growth Management Plan for Collier County Stormwater Management.
RECOMMENDATION: That the Board of County Commissioners approve a work order for
the Lely Area Stormwater Improvement Project ( LASIP) Naples Manor Ditch and US 41 Ditch
Design in the amount of $269,010.00 with PBS &J, Inc.
Prepared By: Margaret A. Bishop, Senior Project Manager, Stormwater Management Section
Attachments: (1) Work Order, Professional Engineering Services for LASIP Naples Manor
Ditch and US 41 Ditch Design – Scope of Work
Page 1 of 2
Agenda Item No. 16B7
October 27, 2009
Page 3 of 16
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
Item Number: 16B7
Item Summary: Recommendation to approve a work order in the amount of $269,010.00 to Post, Buckley,
Schuh & Jernigan, Inc. (PBS &J) under contract #06 -3969 Fixed Term Professional
Engineering Services utilizing the Best Value Offer (BVO #06- 3969 -9) for design and
permitting of the Lely Area Stormwater Improvement Project (LASIP) Naples Manor Ditch
and US 41 Ditch Design (Project No. 51101).
Meeting Date: 10/27/2009 9:00:00 AM
Approved By
Margaret A. Bishop
Project Manager
Date
Transportation Services
Stormwater Management
10/8/2009 12:07 PM
Approved By
Scott R. Teach
Assistant County Attorney
Date
County Attorney
County Attorney Office
10/8/2009 3:48 PM
Approved By
Caroline Soto
Administrative Assistant
Date
Transportation Engineering and
Transportation Services
Construction
101812009 4:33 PM
Approved By
John Vliet
Roads Maintenance Superintendant
Date
Transportation Services
Road Maintenance
10/8/2009 4:47 PM
Approved By
Jeff Klatzkow
County Attorney
Date
County Attorney
County Attorney Office
101912009 11:21 AM
Approved By
Norm E. Feder, AICP
Transportation Division Administrator
Date
Transportation Services
Transportation Services Admin.
1019/2009 3:32 PM
Approved By
Therese Stanley
Grants Coordinator
Date
Transportation
Transportation Administration
1011312009 10:47 AM
Approved By
Gerald Kurtz
Senior Engineer
Date
Transportation Services
Stormwater Management
10,'14/2009 12:06 PM
Approved By
Rhonda Rembert
Contract Specialist
Date
file: / /CAAgendaTest \Export \137- October 27,2009\16. CONSENT AGENDA \16B. TRAN... 10/21/2009
Administrative Services Purchasing
Page 2 of 2
Agenda Item No. 16B7
October 27, 2009
Page 4of16
10/14/2009 1:34 PM
Approved By
Steve Carnell Purchasing /General Svcs Director Date
Administrative Services Purchasing 10114/2009 4:30 PM
Approved By
Pat Lehnhard Executive Secretary Date
Transportation Services Transportation Services Admin 10/14/2009 5:04 PM
Approved By
OMB Coordinator OMB Coordinator Date
County Manager's Office Office of Management & Budget 10115/2009 10:48 AM
Approved By
Susan Usher Senior Management/Budget Analyst Date
County Manager's Office Office of Management & Budget 10/16/2009 1:12 PM
Approved By
Mark Isackson Budget Analyst Date
County Manager's Office Office of Management & Budget 10/16/2009 2:18 PM
fil e:HC:\AgendaTest\Export\ 13 7 -October 27, 2009 \16. CONSENT AGENDA \16B. TRAN... 10/21/2009
Agenda Item No. 16137
October 27, 2009
Page 5 of 16
WORK ORDER #
Under Contract # 06 -3969
Agreement for Fixed Term Professional Engineering Services
This work order is for professional engineering services on behalf of Collier
County (Contract # 06- 3969), for work known as Lely Area Stormwater Improvement
Naples Manor Ditch and US 41 Ditch Project #51101 Engineering Services.
The work is specified in the BVO submittal dated September 2, 2009, which is
hereto attached and made a part of this work order. In accordance with the "Terms
and Conditions" within the Agreement for Fixed Term Professional Engineering
Services (hereafter, Agreement) referenced above, Work Order # is
assigned to PBS &J, Inc.
Scope of Work:
Task 1: Surveying
Task 2: Surveying/Field Crew Work/Geotech/Subsurface Utility Exploration
Task 3: Design/Utility Coordination/Structures
Task 4: Permitting
Task 5: Bidding Assistance
Task 6: Construction Assistance
Task 7: Meeting Attendance and Preparation
Task 8: Reimbursable
More detail and explanation can be found in the attached proposal.
Schedule of Work: Complete all work as directed within 1095 days of receipt of
the "Notice to Proceed" which will contain a Collier County purchase order
number.
Compensation: In accordance with "Article Five" of the Agreement, the County
will compensate the designated firm in accordance with the negotiated T &M
amount provided below (use the established hourly rate(s) as enumerated in
"Schedule A" of the Agreement).
Task 1:
Surveying
$ 7,000
Task 2:
Surveying/Field Crew Work/Geotech/Subsurface Utility Exploration
$56,000
Task 3:
Design/Utility Coordination/Structures
$156,915
Task 4:
Permitting
$12,345
Task 5:
Bidding Assistance
$ 5,000
Task 6:
Construction Assistance
$10,000
Task 7:
Meeting Attendance and Preparation
$14,250
Task 8:
Reimbursable
$ 7,500
TOTAL
$269,010
Agenda Item No. 1667
October 27, 2009
Page 6 of 16
Any change within monetary authority of this work order made subsequent to
final department approval will be considered an additional service and charged
according to "Schedule A" of the Agreement.
PREPARED BY: /0
Margaret (bishop P.E.,Seniorl7Project Manager Date
Stormwater Management Section
REVIEWED BY: � 6 - 5 - C3C-i
Jerry Kurtz, P.E., Principle Project Manager Date
Stormwater Management Section
REVIEWED BY: /-� Z-- 71 Ic /v p
o Vliet, Director ate
oad Maintenance Department
APPROVED BY:
Norman Feder, Administrator
Transportation Services Division
Date
ACCEPTED BY: PBS &J, Inc.
Company Name (�
Authorized Company Officer Date
Mark D. Micikas, P.E. /Vice President_
Type or Print Name and Title
Date:
Agenda Item No. 16137
October 27, 2009
Page 7 of 16
ATTEST: BOARD OF COUNTY COMMISSIONERS OF
C
Dwight E. Brock, Clerk OLLIER COUNTY FLORIDA
I:
Approved As To Form
and Legal Sufficiency:
Print Name: t--
Assis County Attorney
o`r'ti-Y
I:•
Donna Fiala, Chairman
Contract 06- 3969 -9
Professional Engineering Services
For
Naples Manor Ditch and US 41 Ditch Design
Agenda Item No. 16137
October 27, 2009
Page 8 of 16
SCOPE -OF -WORK
In accordance with Collier County Contract Number 06 -3969 "Fixed Term Professional
Engineering Services ", PBS &J (CONSULTANT) is pleased to provide the following scope of
work for professional engineering services for the design and support services of Lely Area
Stormwater Improvement Project (LASIP) sections 17 and 18, also known as, BVO # 06- 3969 -9,
Naples Manor Ditch and US 41 Ditch Design.
SCOPE OF WORK
Task 1— Surveying (PSM Document Preparation)
Task 1.1 — Legal Description and Sketches
CONSULTANT shall prepare legal descriptions and sketches needed for the expanded
drainage easements. It is estimated that there are 43 parcels impacted at this time. The
sketches will be prepared in accordance with Ch. 61 G -17 F.A.C., and Collier County Right
- . of Way Department Standards.
Task 2 — Surveyine/Field Crew Work/Geotech/Subsurface Utility Exploration
Task 2.1 — Survey/Field Crew Work
Task 2. 1.1 — Control/Baseline
Establish horizontal and vertical control through the project limits. This shall be inclusive
of two (2) project survey baselines, stationed at 100 foot intervals. The horizontal datum
shall be NAD 83, the vertical datum shall be NAVD 88.
Task 2.1.2 — Basemap Preparation
CONSULTANT shall prepare a project basemap that will be inclusive of the underlying
plats, rights of way, existing lot lines, existing utilities, existing drainage easements,
existing utility easements and survey benchmarks. CONSULTANT shall research parcel
records from the Collier County Property Appraisers website, and plot the existing lot
configurations. The folio number, owner information and recording information will be
shown on each parcel.
Naples Manor Ditch and US 41 Ditch Design
► y 1• ,
Contract 06- 3969 -9
Agenda Item No. 16B7
October 27, 2009
Page 9 of 16
SCOPE -OF -WORK
Task 2.1.3 — Property Corner Recovery
In order to produce the easements necessary, and in order to verify property data,
establish rights of way, the CONSULTANT shall recover and locate as many existing
property corners as possible. The majority of those will be along the road right of way
due to the existing canals in the rear of the lots. The CONSULTANT shall look for, and
try to recover monumentation that may exist in the rear, possibly set on an offset to the
platted rear lot line.
Task 2.1.4 — Topography
The CONSULTANT shall perform cross sections along the US 41 baseline,
approximately 5850 linear feet, every 100 feet, and extending 30 feet beyond the top of
bank on each side of the existing ditch. The CONSULTANT shall perform cross sections
along the Naples Manor Canal baseline, approximately 2600 linear feet, (generally
located between McCarty and Warren Streets) every 100 feet, and extending 30 feet
beyond the top of bank on each side of the existing canal. Both baselines will be extended
100 feet in both directions, and cross sections performed. Additional information will be
needed to illustrate irregularities in the canals, road way intersections, drive aprons,
existing culverts, visible above ground appurtenances associated with existing utilities,
and will be considered supplemental to the 100 foot cross sections.
Task 2.1.5 — Deliverables
CONSULTANT shall prepare a three dimensional CADD file, inclusive of a digital
terrain model, of the topographic survey. Included in this file shall be the overall
basemap, including the property ownership data. CONSULTANT shall provide a
Surveyors Report, signed and sealed by a licensed Florida Land Surveyor, and in
accordance with Ch. 61 G -17, F.A.C.
Task 2.2 — Geotechnical
CONSULTANT will setup, perform, and provide reports on five (5) soil borings in the
US41 -Ditch work zone at the box - culvert locations, and three (3) soil borings in the Naples
Manor Ditch work zone. Environmental Classifications will be accomplished to determine
the appropriate classification of concrete to use. This information will establish the
geotechnical data upon which to base the design.
Naples Manor Ditch and US 41 Ditch Design PW
Agenda Item No. 16137
October 27, 2009
Page 10 of 16
Contract 06- 3969 -9 SCOPE -OF -WORK
Task 2.3 — Subsurface Utility Exploration (SUE)
CONSULTANT shall locate and map the known utilities at the S intersections of US 41,
and the platted streets, along with the four roadway crossings and the Naples Manor Canal.
Due to the difficulty associated with vacuum excavation in limits of project the
CONSULTANT will complete SUE utilizing Ground Penetrating Radar, with approximate
depths. For any identified conflicts from the design, and data provided from utilities and
Ground Penetrating Radar the CONSULTANT will complete up to four (4) vacuum
excavations. If any additional conflict locations are identified, prior to the commencement of
such additional work, CONSULTANT shall coordinate with the owner and establish an
agreement for the appropriate level of compensation.
Task 3 — DesiBnfUtility Coordination/Structures
CONSULTANT will provide the following professional services for preparation of 30 %, 60 %,
and final construction design plans to the County, based on the conceptual design plans, prepared
by Agnoli, Barber, and Brundage, provided by the County.
Task 3.1 — Drainage Design
CONSULTANT will complete the design of the drainage improvements, including LASIP
Section 17 travelway for access and maintenance, for the following locations:
• LASIP Section 17 — The existing ditch located in the Naples Manor Subdivision
between Warren Street and McCarty Street, from US41 to north of Carolina Avenue.
• LASIP Section 18 — The existing ditch along the north side of US41 that currently
conveys stormwater out of Naples Manor in a southeasterly direction towards the
Naples Manor Outfall ditches located south of US41 and parallel to Myrtle Lane in
Myrtle Cove Acres.
During the design process, the CONSULTANT will recreate this project's portion of the
conceptually permitted SWMM model to verify the results of the conceptual permit and to
optimize the proposed design. Based on the results of the analysis and the width of the final
ditch cross sections the CONSULTANT will identify and provide details of all necessary
temporary and permanent easements.
Naples Manor Ditch and US 41 Ditch Design
KI
i-
Contract 06- 3969 -9
Agenda Item No. 16137
October 27, 2009
Page 11 of 16
SCOPE -OF -WORK
The CONSULTANT will coordinate with FDOT during the design process to accommodate
and attempt to reduce impacts to the existing mast arm in the northwest corner of Broward
and US41. CONSUTLANT will prepare construction recommendations for the contractor to
maintain signal operations during construction and mast arm integrity after construction. If
and signal design or modification are determined necessary the CONSULTANT will provide
recommendations and coordinate with COUNTY on fee for those services.
During the design of LASIP Section 17 the CONSULTANT will coordinate with the Hydro
Conduit Stormceptor representatives to develop the structural details for the required water
quality improvement along the Naples Manor ditch.
Task 3.2 — Utility Coordination
CONSULTANT will identify within the final contract plans the existing utilities based on
available information provided by existing utilities within the project limits.
CONSULTANT will resolve any conflicts with the proposed stormwater facilities and
existing utilities through relocation of the proposed stormwater facilities or providing
relocation recommendations to the affected utility owners. CONSULTANT will also begin
utility coordination with all existing utilities upon completion of 30% plans. Upon
completion of the 30% plans, the CONSULTANT will schedule and hold one (1) utility
kickoff meeting with all known utility owners and will continue to coordinate with utility
owners throughout the design process. The CONSULTANT will obtain in writing from the
identified utilities, either utility relocation schedules or No Conflict Letters for the project
limits. CONSULTANT will not be responsible for the design of any relocation plans for any
of the utilities within the project limits.
Task 3.3 — Box Culvert Design
CONSULTANT will provide the structural details for six (6) concrete box culvert locations
listed below:
• Broward Street at US 41
• Martin Street at US41
• Entrance Street at US 41
• Johns Street at US41
Naples Manor Ditch and US 41 Ditch Design
4
Contract 06- 3969 -9
• Confederate Drive at US41
• Northside of US 41 Parallel to roadway
Agenda Item No. 1687
October 27, 2009
Page 12 of 16
SCOPE -OF -WORK
The box culvert designs will be prepared according to FDOT Design Standards. Box culvert
data sheets will be included in the plans according to FDOT standards.
Task 3.4 — Constructability Review
CONSULTANT will complete a constructability review of plans prior to completion of the
final signed and sealed contract documents. The constructability review will be completed
by construction staff not involved in the design process to identify any potential construction
conflicts.
Task 3.4 — Deliverables
Plans will be prepared as follows:
• Utilizing current design standards and specifications set by the Florida Department of
Transportation (FDOT), to the greatest extent possible
• Required plan production software is Autodesk AutoCAD /Civil 3D, following the
NCS "CAD Standards ".
• On plans, identify all needed parcels for permanent as well as temporary easements,
providing, "Sketches and Legals"
At the 30 %, 60 %, and the CONSULTANT will provide the following:
• Ten (10) Complete Sets of Contract Plans
• Ten (10) Design Documentation Reports
• Ten (10) Engineer's Opinion of Probable Cost
• One (1) CD containing all current electronic project files per Collier County
Transportation Services Division Standards
For Final Construction/Bidding Documents the CONSULTANT will provide
• Two (2) Signed and Sealed Sets of Plans
• One (1) Final Design Documentation Report, including the approved SFWMD Permit
Modification.
• One (1) CD containing all final and complete project files per Collier County
Transportation Services Division Standards.
• One (1) Quantity Takeoff/Bid Schedule Document in Excel Format
Naples Manor Ditch and US 41 Ditch Design
5 PW
Agenda Item No. 1667
October 27, 2009
Page 13 of 16
Contract 06- 3969 -9
SCOPE -OF -WORK
• One (1) Final Engineer's Opinion of Probable Cost
Task 4 — Permitting
Task 4.1 — Wetland/Other Surface Water (OSW) Delineation
CONSULTANT will perform field reviews to delineate the boundaries of other surface
waters (OSWs). They will also verify that there are no wetlands within the project limits, as
shown in the conceptual permit.
Task 4.2 — Threatened & Endan Bred Species
CONSULTANT will perform field reviews to determine the potential for the existence of
threatened and endangered species habitats within the project limits. Notes will be developed
for the plans that will direct the Contractor on how to handle encountering any of these
species.
Task 4.3 — South Florida Water Management District SFWMD Environmental Resource
Permit (ERP)
CONSULTANT will complete the permit application to modify the South Florida Water
Management District ( SFWMD) conceptual permit ( #1 1- 01140 -S) for Segments 17 and 18 of
the Lely Area Stormwater Improvement Project (LAS1P). CONSULTANT will perform the
following tasks, which are anticipated to be necessary to obtain the permit modification:
• Schedule and hold a pre - application meeting with SFWMD staff to describe the
proposed project and how it ties into the conceptual permit. CONSULTANT will
develop the necessary exhibits for this meeting.
• Complete application forms.
• Recreate the applicable portion of the conceptually permitted SWMM model and
develop figures to explain how the design shown in the contract plans meet or exceed
the permit requirements.
• Develop a technical drainage report describing the proposed design.
Task 4.4 — Florida Department of Environmental Protection (FDEP)
If necessary, the CONSULTANT shall prepare and submit the FDEP wastewater permit.
Task 4.5 — Florida Department of Transportation (FDOT) Drainage. Connection Permit
Naples Manor Ditch and US 41 Ditch Design
6 pw
Agenda Item No. 16137
October 27, 2009
Page 14 of 16
Contract 06- 3969 -9 SCOPE -OF -WORK
CONSULTANT will complete the permit application for a drainage connection permit for
the proposed ditch work on US 41. CONSULTANT will perform the following tasks, which
are anticipated to be necessary to obtain the drainage connection permit:
• Schedule and hold a pre - application meeting with FDOT staff as well as Collier
County operations staff (Collier County handles operations and maintenance of state
roads in Collier County for the FDOT) to describe the proposed project.
CONSULTANT will develop the necessary exhibits for this meeting.
• Complete application forms
• Conduct a Rule 14 -86 Critical Duration analysis with the SWMM model to
demonstrate to the FDOT that the post - development discharge rates that leave the
proposed project are not greater than the pre- development rates for the 2 -year, 5 -year,
10 -year, 25 -year, 50 -year, and 100 -year storm frequencies.
• Develop a technical drainage report describing the proposed design and the Critical
Duration analysis.
Task 4.6 — Florida Department of Transportation (FDOT) Right of way Use Permit
CONSULTANT will coordinate with FDOT and complete and submit the permit application
for a Right -of -way Use permit for the proposed ditch work on US 41.
Task 4.7 — Dewatering Permit
CONSULTANT will coordinate with the County to complete application for securing a
dewatering permit for this project. If the County determines that they would prefer the
contractor obtain the dewatering permit, the CONSULTANT will add the necessary notes to
the plans that will prevent the need for Collier County to obtain the dewatering permit. These
notes will require the Contractor to obtain any dewatering permits.
Task 4.8 — United States Army Corps of En!ineers ( USACOE) permit
CONSULTANT will meet the conformance requirements of the approved drawings of the
SFWMD and USACOE construction permit ( #SAJ- 2002 -2436 (IP -JMD). The
CONSULTANT in addition to the meeting the above stated conformance requirements will
also include providing the Contractor with educational materials (in the form of notes in the
plans) informing them of the measures that should be taken to protect any threatened or
endangered species encountered on the project site.
Naples Manor Ditch and US 41 Ditch Design
7
�� it
Agenda Item No. 1687
October 27, 2009
Page 15 of 16
Contract 06- 3969 -9
SCOPE -OF -WORK
Task 5 — Bidding Assistance
CONSULTANT will during the bidding phase of the project provide the following services:
• Compile and organize all electronic files and hard copies of all necessary documents for
the construction bid package.
• Attend pre -bid meeting.
• Respond to contractors' bid questions.
• Prepare any necessary addendums to the bid documents.
• Review bids and provide an award recommendation to the County project manager.
Task 6 — Construction Assistance
CONSULTANT will during the construction phase of the project provide the following services:
• Provide engineering and design clarification /advice to contractor Requests for Additional
Information (RAI's)
• Provide Shop Drawing reviews and approvals services
• Complete and provide any plan revisions necessary during construction due to changes in
field conditions and/or direction from the County.
Task 7 — Meeting Attendance and Preparation
CONSULTANT will conduct a kick -off meeting and monthly progress meetings with the County
Project Manager and any additional stakeholders. CONSULTANT will prepare for and assist the
County with up to three (3) public information meetings. CONSULTANT will also attend 30%
and 60% design progress meeting with county staff and reviewers to discuss comments provided
during the review of the submitted plans.
SCHEDULE
The above scope is based on the requirements outlined by the County. Per the County's
anticipated 10 month schedule, and based on Notice to Proceed in October 2009 the
CONSULTANT has prepared a design schedule to complete design plans by July 2010. It is
assumed that construction will not begin until January 2012 with a construction completion date
of June 2012.
Naples Manor Ditch and US 41 Ditch Design %7���
8 "�"`� s
Contract 06- 3969 -9
BUDGET
Agenda Item No. 16137
October 27, 2009
Page 16 of 16
SCOPE -OF -WORK
In accordance with Collier County Contract Number 06- 3969 -9 compensation for the above
scope of work will be based on a billing type listed below.
Task 1 — Surveying (PSM Document Preparation)
$
7,000
Task 2 — Surveying/Field Crew Work/Geotech/Subsurface Utility Exploration
$
56,000
Task 3 — Design/Utility Coordination/Structures
$
156,915
Task 4 — Permitting
$
12,345
Task 5 — Bidding Assistance
$
5,000
Task 6 — Construction Assistance
$
10,000
Task 7 — Meeting Attendance and Preparation
$
14,250
Task 8 — Reimbursable
$
7,500
Grand Total for entire Work Order
$ 269,010
Naples Manor Ditch and US 41 Ditch Design