Agenda 09/29/2009 Item #16B 5
Agenda Item No. 1685
September 29, 2009
Page 1 of 29
EXECUTIVE SUMMARY
Recommendation to approve the contract #09-5340 between Collier Metropolitan Planning
Organization (MPO) and Tindale-Oliver and Associates (TOA) for the Transit
Development Plan (TDP) Major Update in an amount of $129,550.
OBJECTIVE: To obtain approval from the Board of County Commissioners for the Transit
Development Plan (TDP) Major Update contract.
CONSIDERATION: In order to receive State Block Grant Funds for system operations, each
transit agency must conduct a TDP Major Update every five years. The TDP Major Update is
due in September, 2010. A TDP Major Update is a strategic guide for public transportation in the
community over the next ten years. It represents the transit agency's vision for public
transportation in its service area during this time period. Generally, the TDP process includes an
assessment of overall transit-related needs in the community along with a phased implementation
plan of recommended improvements to address those needs. A TDP Major Update also includes
a public involvement strategy, an analysis of demographic and travel behavior characteristics, a
performance evaluation of existing services, transit goals and objective for the system, a
development of proposed transit enhancements and ten-year financial plans.
Under the Collier MPO General Planning Contract for services (07-4198), the MPO can only use
Dyer, Riddle, Mills and Precourt (DRMP) and AIM Engineering (AIM), as consultants. The
MPO contacted both AIM and DRMP to do the TDP, however they indicated that they are not
interested in doing the project for the budgeted amount. The negotiations with AIM and DRMP
which did not result in an agreed to work order, left the MPO without the option of advertising
and soliciting proposals through the Request For Proposal (RFP) process. The TDP is due in
September of 2010 and the work effort to complete the TDP takes one full year. The RFP
process takes at a minimum four months to complete.
The MPO cannot use the Collier County GPC because it was not advertised according to MPO
requirements or approved by the Florida Department of Transportation (FDOT) and the Federal
Highway Administration (FHW A). The MPO's only alternative was to use another approved
MPO contract. The Lee County MPO's current General Planning Contract with Tindale-Oliver
and Associates (TOA) (Contract #2009-001) has been approved by both FDOT and FHW A.
Collier MPO and the Alternative Transportation Modes (A TM) Department do not have the
capabilities to take on this size task and have requested the help of TOA. TOA submitted the
attached scope of service for the TDP. The Collier MPO approved the scope of work attached as
well as using the standard Collier County approved contract. MPO staff received FDOT
concurrency to use TOA for this task and FDOT also approved the scope.
The services to be provided pertain to transportation planning and do not require a licensed
professional as specifically identified under the Consultants Competitive Negotiation Act. Hence,
the procurement of this agreement is governed primarily by the requirements of the Board's
purchasing policy.
Agenda Item No. 1685
TOA is not a consultant firm currently in our General Planning Contract; therefo~;~e1s2?~~
using the standard Collier County Professional Services Contract for this task. While this co~~actO
was negotiated based upon a similar agreement with the Lee County MPO, the fact that staff has
negotiated the use of Collier County's form of contract is prompting staff to recommend that the
Board waive formal competition as part of the award of the enclosed contract to TOA.
FISCAL IMPACT: There will be no fiscal impact for Collier County Board of County
Commissioners. The fiscal impact is budgeted and will be funded from the MPO budget
established in the MPO's Unified Planning Work Program (UPWP). The scope of services is
consistent with the Unified Planning Work Program (UPWP).
LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County
Attorney's Office and is a legally sufficient agenda-SRT.
GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan
related to this action.
RECOMMENDATION: That the Board of County Commissioners waive the formal
competition requirement for this contract, approve the contract with TOA, and authorize the
Chairn1an to sign the standard contract after County Attorney approval.
Prepared by: Lorraine M. Lantz, MPO Principal Planner, MPO
Attachment: (I) Schedules A, Band C to the contract
Page 1 of2
Agenda Item No. 1685
September 29, 2009
Page 3 of 29
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
Item Number: 1685
Item Summary: Recommendation to approve the contract between Collier Metropolitan Planning
Organization (MPO) and Tindale Oliver and Associates (TOA) for the Transit Development
Plan (TOP) Major Update in an amount of $129,550.
Meeting Date: 9/29/2009 9:00:00 AM
Prepared By
Lorraine Lantz Right Of Way Coordinator Date
Transportation Services TECM-ROW 9/16/20091:13:35 PM
Approved By
Caroline Soto Administrative Assistant Date
Transportation Services Transportation Engineering and 9/16/20094:20 PM
Construction
Approved By
Therese Stanley Grants Coordinator Date
Transportation Transportation Administration 9/16/20094:42 PM
Approved By
Nick Casalanguida MPO Director Date
Transportation Services Transportation Planning 9/17/20097:53 AM
Approved By
Phill Tindall Principal Planner Date
Transportation Services Transportation Planning 9/17/20098:35 AM
Approved By
Najeh Ahmad Director Date
Transportation Services Transportation Engineering &
Construction Management 9/17/2009 3:35 PM
Approved By
Rhonda Rembert Contract Specialist Date
Administrative Services Purchasing 9/17/20094:20 PM
Approved By
Steve Carnell Purchasing/General Svcs Director Date
Administrative Services Purchasing 9/18/20098:27 AM
Approved By
Scott R. Teach Assistant County Attorney Date
County Attorney County Attorney Office 9/18/2009 8:57 AM
file://C:\Agendatest\export\135-September 29,2009\16. CONSENT AGENDA\16B. TRAN... 9/23/2009
Page 2 of2
Agenda Item No. 1685
September 29,2009
Page 4 of 29
Approved By
Michelle Edwards Arnold Alternative Transportation Modes
Director Date
Transportation Services Alternative Transportation Modes 9118/20099:10 AM
Approved By
Pat Lehnhard Executive Secretary Date
Transportation Services Transportation Services Admin 9/18/20099:51 AM
Approved By
OMB Coordinator OMB Coordinator Date
County Manager's Office Office of Management & Budget 9/18/200910:38 AM
Approved By
Mark Isackson Budget Analyst Date
County Manager's Office Office of Management & Budget 9121120099:26 AM
Approved By
Leo E. Ochs, Jr. Deputy County Manager Date
Board of County County Manager's Office
Commissioners 9/22/2009 1 :49 PM
file://C:\Agendatest\export\135-September 29,2009\16. CONSENT AGENDA\16B. TRAN... 9/23/2009
~..,-'" -_........~ __'+','~.,._M__
Agenda Item No. 1685
September 29, 2009
Page 5 of 29
SCHEDULE A
Scope of Services
Collier County Major Update of Ten-Year Transit Development Plan
(prepared by Tindale-Oliver & Associates, Inc. - August 19, 2009)
Tindale-Oliver & Associates, Inc. (TOA) is pleased to offer a scope of services for
preparing a major update of the Ten-Year Transit Development Plan (TDP). This effort
will result in a strategic transit plan for the community and ensure compliance with the
new TDP Rule, as adopted February 20,2007.
- The State of Florida Public Transit Block Grant Program was enacted by the Florida
Legislature to provide a stable source of state funding for public transportation. The
Block Grant Program requires public transit service providers to develop and adopt a
ten-year TDP, per the requirements set forth in Chapter 14-73, Florida Administrative
Code (FAC). Annual progress reports also must be submitted to the Florida
Department of Transportation (FDOT) by September 1 sl of each year. A major update
is required every five years and the annual progress reports are required annually
between major updates.
The ten-year TDP is a strategic guide for public transportation in the community over
the next ten years. It represents the transit agency's vision for public transportation in
its service area during this time period.
Generally, the TDP process includes an assessment of overall transit-related needs in
the community along with a phased implementation plan of recommended
improvements for helping address those needs. Specifically, a TDP includes the
following major elements:
. Public involvement plan and process
. Base data compilation and analysis (review of demographic and travel behavior
characteristics of the service area)
. Performance evaluation of existing services
. Situation appraisal (transit agency strengths and weaknesses; external barriers
and opportunities; estimation of community demand for transit)
. Goals and objectives
. Transit demand and mobility needs
Agenda Item No. 1685
September 29, 2009
Page 6 of 29
. Oevelopment of proposed transit enhancements (funded and unfunded)
. Ten-year implementation plan
. Annual farebox recovery ratio report
. Ten-year financial plan (projected costs and revenues)
. Other strategic issues specific to a given study area
Consistent with the TOP preparation guidelines from FOOT, it is understood that the
initial five years of the plan will be characterized by substantially greater detail than the
subsequent five years. The latter part of the planning horizon is intended to be more
strategic in nature.
- -
As indicated previously, new TOP requirements were formally adopted by FOOT on
February 20,2007. For those familiar with the previous TOP requirements, major
changes to the rule include the following:
. Extends the planning horizon from five years to ten years.
. Requires major updates every five years rather than every three years.
. Requires a public involvement plan to be developed and approved by FOOT or
consistent with the approved metropolitan planning organization (MPO) public -
involvement plan.
. Requires that FOOT, the regional workforce development board, and the MPO
be advised of all public meetings where the TOP is presented and discussed
and that these entities be given the opportunity to review and comment on the
TOP during the development of the mission, goals, objectives, alternatives, and
ten-year implementation program.
. Requires the estimation of the community's demand for transit service (10-year
annual projections) using the planning tools provided by FOOT or a demand
estimation technique approved by FOOT.
This scope of services ensures that the major update of the TOP will comply with all
requirements of the new TOP rule.
In addition to the new TOP rule, HB 985 requires that transit agencies submit an annual
farebox recovery ratio report. This scope of services ensures that the major update of
the TOP will comply will all requirements of HB 985.
-
Agenda Item No. 1685
September 29,2009
Page 7 of 29
SPECIFIC SCOPE OF SERVICES
The following scope of services describes the tasks and resulting deliverables that will
be necessary to complete a major update of the TDP. The scope is organized into nine
major tasks, as listed below.
. Task 1: Establish Review Committee & Prepare for Kickoff
. Task 2: Establish Baseline Conditions
. Task 3: Facilitate Public Involvement
. Task 4: Update Evaluation of Existing Transit Services
. Task 5: Estimate D~ll1and & Mobility Needs
. Task 6: Conduct Situation Appraisal
. Task 7: Develop Goals & Objectives
. Task 8: Prepare Ten-Year Transit Development Plan
. Task 9: Facilitate Meetings & Presentations
Each of the nine tasks is summarized in the remainder of this scope of services. It is
important to note, however, that every community has unique issues and
characteristics. As a result, the TDP planning process must be flexible to adapt to
issues specific to a given study area.
Task 1: Establish Review Committee and Prepare for Kickoff
A Review Committee will be established at the outset of the project to monitor and
provide input throughout the study and to evaluate the deliverables produced by the
Consultant. The composition of the Review Committee will be determined
cooperatively by the transit agency and Consultant team. The Consultant will respond
to all recommendations from the committee. After the committee has been established,
a kick-off meeting for the project will be scheduled and conducted. In addition to the
Review Committee, a distribution list will be developed to facilitate a broader
distribution of draft deliverables (FDOT District One, Workforce Development Board,
and others).
This task also includes preparation for a kickoff meeting, including an agenda, scope
overview, detailed project schedule, milestones, deliverables, Review Committee and
distribution list, and other items as necessary.
Agenda Item No. 1685
September 29,2009
Page 8 of 29
Responsibilities of Consultant
. Establish Review Committee and distribution list for draft deliverables.
. Prepare for kickoff meeting.
Responsibilities of Collier County Staff
. Work with Consultant to establish a Review Committee and distribution list.
Task 2: Establish Baseline Conditions
The Consultant will collect demographic, socio-economic, land-use, transportation, and
transit data for the study area with assistance from the transit agency, the metropolitan
planning organization (MPO), and other agencies as appropriate.
Collier County will provide an inventory of all existing public and private transportation
services operating in the study area. The inventory effort will include providers of
service to the transportation disadvantaged, intercity bus operators, charters, and taxis.
To the extent possible, and dependent on the participation of the individual providers,
the following information will be provided by Collier County:
. Facilities: location, age, and condition
. Type of Operation (previous and current)
. Service area, service frequency, destinations and number of riders
. Equipment: type, age and condition
. Rolling stock: type, age, special accessories
. Affiliated groups and programs with a role in public transit
To establish the baseline conditions for transit in the study area, demographic, socio-
economic, and various transportation data will be collected to provide historical
background and a description of the area. The latest data from the Census of
Population and Housing and the Bureau of Economics and Business Research (BEBR)
of the University of Florida will be used as primary data sources. These data will be
supplemented by other data available from the transit agency, MPO, counties, cities,
and other sources, as available. Data to be compiled include the following:
. physical description of area
,~.,_. ....0- ,~-~-,..,.-.-
Agenda Item No. 1685
September 29, 2009
Page 9 of 29
. population by age and income
. population density
. housing density
. employment density
. labor force
. auto ownership
. tourist and visitor levels
. transportation disadvantaged population
. land uses and densities
. major trip generators
. area roadway and traffic conditions, including levels Qf.~ervice, current or
projected capacity deficiencies, and current and planned transit routes
Responsibilities of Consultant
. Review/update the description of the transit service area.
. Review and summarize relevant plans & studies.
. Inventory existing services, resources, and assets.
. Review/update legislative/administrative requirements.
. Collect and analyze operating data.
. Compile baseline conditions.
Responsibilities of Collier County Staff
. Coordinate with Consultant regarding collection of data and baseline conditions.
. Provide a description of the transit service area.
. Provide documented legislative/administrative requirements.
. Provide analyses of operating data.
Task 3: Facilitate Public Involvement
At the direction of County staff, the Consultant will seek FDOT approval for using the
MPO's adopted Public Involvement Plan as the guide for public involvement techniques
to be used to support the preparation of the TDP.
The Consultant will lead all public involvement activities, such as stakeholder
interviews and discussion group workshops. The following sub-tasks outline the effort
required for this task.
Agenda Item No. 1685
September 29,2009
Page 10 of 29
Task 3.01: Obtain FDOT Approval of Public Involvement Plan - Consistent with the
TDP rule, the public involvement plan shall be approved by FDOT or be consistent with
the MPO's public involvement plan. A brief memo will be prepared and submitted to
FDOT District One, along with the MPO's adopted PIP. The memo will identify the
public involvement techniques within the PI P that will be applied in the transit
development planning process.
Throughout the plan development process, coordination will occur with FDOT District
One, the Collier County MPO, the regional workforce board, and other stakeholders
identified in cooperation with County staff. In particular, coordination will occur as it
relates to public involvement opportunities and review of the draft TDP. Review and
input will include the mission, goals, and objectives; transit alternatives; and the ten-
year implementation program. The public involvement plan will include numerous
public involvement techniques, as described in the remainder of this task description.
Task 3.02: Conduct Stakeholder Interviews - Through a series of ten stakeholder
interviews, the Consultant will assess the attitudes of key local officials and community
leaders regarding current transit service. The interviews will seek to assess political
leaders' views on transit's current and future role in the community, transit finance and
governance, and other issues relevant to the transit plan. An interview script will be
developed for use in guiding the interviews. It is assumed that the ten interviews will
be conducted via telephone for budgetary purposes.
Task 3.03: Conduct On-Board Survey - The Consultant will develop an on-board
survey designed to capture demographic, travel behavior, and rider satisfaction data
from CAT fixed-route bus riders. This information will enable Collier County to focus on
relevant transit needs and issues such as modifying bus schedules, locating bus stops,
modifying fare structure, planning, focusing marketing campaigns, and identifying
historical trends.
The on-board survey methodology and implementation will be closely coordinated with
County staff to ensure that study objectives are met and that data collection efforts are
efficiently integrated with CAT operations.
The survey will be performed on a 50-percent sample of all fixed-route runs for a typical
Agenda Item No. 1685
September 29,2009
Page 11 of 29
weekday, Saturday, and Sunday of service. Trained surveyors will hand out surveys to
all riders (available in English and Spanish). The surveyors will also be available to
assist with filling out the surveys as necessary.
The Consultant will be responsible for printing and distributing on-board survey
instruments to bus patrons according to the identified sampling requirement. Survey
recipients will be given instructions to complete the surveys on the bus and return them
to a surveyor or driver, or mail them back to Collier County. Surveys will be collected
and organized according to the route and run. In addition, the Consultant will recruit
and train on-board survey personnel and assign them to survey runs during a typical
weekday, Saturday, and Sunday for a portion of a one-week period for survey
distribution. All bus riders will have an equal chance of receiving a survey form during
each run. The Consultant will offer cash incentives to survey personnel to encourage
worker retention and active participation throughout the data collection time frame.
The Consultant will collect completed survey forms and organize them for data
processing and analysis. Data entry and analysis will be performed to create selected
cross-tabulations and statistics that support the TOP. The Consultant will be
responsible for quality control and accuracy throughout the data entry and statistical
analysis process.
Documentation of the on-board survey will describe the survey methodology, data
collection approach, findings, and conclusions. Key findings, conclusions, and
summary statistics will be presented in a user-friendly manner with easy-to-understand
charts and graphs.
To summarize, TOA will be responsible for:
. Developing the sampling plan and on-board survey instrument
. Recruiting and training survey personnel
. Establishing the schedule for data collection
. Supervising the data collection effort
. Overseeing the completed survey data entry effort
. Cross-tabulating and evaluating the on-board survey results
. Preparing a memorandum to document the survey results
Agenda Item No. 1685
September 29, 2009
Page 12 of 29
Task 3.04: Conduct Discussion Group Workshops - The Consultant will seek to
identify and assess general community perceptions of transit to help identify issues and
opportunities for the transit agency. Although there are several methodologies for
collecting such information, one of the more cost-effective methods of obtaining public
input on transit is through the use of discussion group workshops. Although not
intended to provide a statistically valid sample, a discussion group is an excellent tool
for revealing the attitudes of a particular group because of the open-ended nature of
group discussions. For the TOP update, it is proposed that a total of four workshops be
held around the County to ensure geographic distribution of the participants. At least
one of the workshops will be conducted using current transit riders to help represent
the "user" perspective. In addition, at least one of the workshops will consist of
members from the business, health, and education communities, as well as local
chambers of commerce, to help represent the views of informed "non-users." The
Consultant will work with County staff to identify participants and venues for the
workshops. For budget purposes, it is assumed that the four workshops will be held on
two separate days, with two workshops being conducted on each day.
Task 3.05: Prepare Technical Memorandum No.1 - Oraft Technical Memorandum
No.1 will be prepared to compile data and results from Tasks 1 through 3. The draft
tech memo will summarize the study area's baseline conditions, including demographic,
economic, and transportation information; the attitudes of local officials and leaders in
the community based on the stakeholder interviews; the results of the on-board survey;
and the findings from the series of discussion group workshops. The draft tech memo
will be disseminated to the Review Committee for consideration and comment. All
comments and modifications recommended by the committee will be incorporated into
the tech memo in preparation for inclusion in the draft final TOP document.
Responsibilities of Consultant
. Prepare memo to FOOT/obtain FOOT approval for public involvement plan.
. Conduct stakeholder interviews (10 by telephone).
. Perform comprehensive system-wide on-board survey.
. Conduct discussion group workshops. (4 workshops - 2 trips)
. Review/integrate other public input.
. Prepare Technical Memorandum No.1 (Tasks 1-3).
Responsibilities of Collier County Staff
>"~-'~'.,~'" -..-
Agenda Item No. 1685
September 29, 2009
Page 13 of 29
. Review public involvement plan.
. Participate in public involvement activities.
. Review Technical Memorandum NO.1 (Tasks 1-3).
Task 4: Update Evaluation of Existing Transit Services
The Consultant will review and evaluate existing transit service in the study area. The
following sub-tasks outline the effort required for this task.
Task 4.01: Update Trend Analysis of Existing Transit Service - The Consultant will
perform a trend analysis of existing fixed-route transit service in the study area. This
review of the transit agency will be undertaken to assess the performance of the system
over time using measures falling into three major categories: system performance,
effectiveness, and efficiency. This evaluation will be conducted using both historical as
well as the most current validated data available from the National Transit Database
(NTD). As part of the overall performance review of the system, this analysis will be
used to help assess the extent to which the transit agency is meeting the stated goals
and objectives for transit service.
Task 4.02: Conduct Peer Review Analysis of Existing Transit Service - The
Consultant will perform a peer review analysis for CAT fixed-route bus service. A peer
review compares the transit agency's fixed-route services with other systems that have
similar agency features located elsewhere in Florida and throughout the southeastern
United States. This cross-sectional evaluation will be conducted for a single year using
the most current validated data available from the National Transit Database (NTD).
Common performance indicators and measures are summarized in Table 1.
Task 4.03: Conduct Capacity/Supply Evaluation of Existing Transit Service - The
consultant will conduct a general system-wide capacity/supply evaluation of the existing
fixed-route service by estimating and comparing passenger miles and seat miles for the
system. This analysis will provide a measure of the extent to which available capacity
is currently being utilized.
Agenda Item No. 16B5
September 29,2009
Page 14 of 29
Table 1
Common Transit Performance Evaluation Indicators and Measures
(Trend and Peer Review Analyses)
Performance Indicators Effectiveness Measures Efficiency Measures
. passenger trips . vehicle miles per capita . operating expenses per
. passenger miles . passenger trips per capita
. vehicle miles capita . operating expenses per
. revenue miles . passenger trips per passenger trip
. vehicle hours revenue mile . operating expenses per
- . route miles . passenger trips per passenger mile
. operating expenses vehicle hour . operating expenses per
. capital expenses . revenue mileage revenue mile
. operating revenues between incidents . farebox recovery ratio
. total employees . revenue mileage . revenue miles per
. vehicles available for between roadcalls vehicle mile
maximum service . revenue miles per
. fuel consumption vehicle
. revenue hours per
employee
. passenger trips per
employee
. vehicle miles per gallon
. average fare
Responsibilities of Consultant
. Conduct trend analysis of fixed-route transit service.
. Conduct peer review analysis of fixed-route transit service.
. Conduct capacity/supply evaluation of fixed-route transit service.
Responsibilities of Collier County Staff
. Coordinate with Consultant staff in the evaluation of fixed-route transit services.
Task 5: Evaluate Demand & Mobility Needs
The Consultant will estimate demand for the transit agency's fixed-route transit services
*"----'" -_.- . -._-
Agenda Item No. 1685
September 29,2009
Page 15 of 29
over a ten-year period using various methodologies. Using this future demand
information, in conjunction with the public input collected previously, the transit-related
needs of the study area will be assessed.
Task 5.01: Estimate Demand for Transit Services - The Consultant will use two key
analytical tools to assess traditional and discretionary transit markets in Collier County.
These tools include:
. Traditional market assessment of existing conditions through a Transit
Orientation Index (TOI) - potential for traditional transit use (elderly, youth, low-
income, no vehicle).
· - Existing and future discretionary market assessment through a Oensity
Threshold Assessment (OT A) - potential for traditional and choice transit use
(dwelling unit and employment density thresholds compared to existing and
future densities)
Task 5.02: Estimate Demand for Transit Services (T-BEST) - The Consultant will
project ridership demand for fixed-route transit services over a ten-year plan period,
assuming the maintenance of existing service levels and the implementation of the ten-
year TOP. Ten-year projections of the community's demand for transit service (ten-
year annual projections) must be developed using the planning tools provided by FOOT
or a demand estimation technique approved by FOOT. T-BEST, a ridership projection
tool developed by FOOT, will be used to prepare the ten-year annual transit demand
projections.
Task 5.03: Identify & Assess Needs for Transit Services - The Consultant will
utilize the results of the previous tasks, including the findings from the public
involvement activities, to assess the need for improved transit services. This needs
assessment will take into account major activity centers, geographic areas served by
the transit system, frequency and hours of service currently provided, and demographic
characteristics of residents in the study area. Potential target markets for new or
expanded transit service will be identified and assessed. The needs assessment also
will include an examination of possible intermodal connections and the coordination of
service with adjacent transit operators. In addition, the needs assessment will, to the
extent possible, present an analysis of any variation between identified needs and
available services. Alternative methods of addressing deficiencies will be identified
Agenda Item No. 1685
September 29,2009
Page 16 of 29
and assessed. The needs assessment will be coordinated with the Transit Element of
the 2035 Regional Long Range Transportation Plan, which is being developed
concurrently with the TDP.
Task 5.04: Identify & Evaluate Alternatives - Based on the previous study tasks and,
in particular, the assessment of needs and potential opportunities, the Consultant will
identify and evaluate alternatives for transit operation in the study area. Alternatives
may range from the status quo (maintaining the existing mix of services) to the
consideration of new and innovative service concepts.
The alternatives will be identified and developed in conjunction with the transit agency
and the Review Committee, and will support the community's and agency's vision of
where it wants to be in ten years. The alternatives will be identified and analyzed at
this stage without regard for costs, in line with the strategic intent of the TDP and the
express wishes of FDOT in encouraging the TDP process. An evaluation framework
will be established by the Consultant that will help prioritize the alternatives.
Task 5.05: Prepare Technical Memorandum No.2 (Tasks 4 & 5) - Draft Technical
Memorandum NO.2 will be prepared to compile data and results from Tasks 4 and 5.
The draft tech memo will summarize the performance review of the transit agency's
fixed-route services. The performance review will include the trend analysis, peer
review analysis, and capacity/supply analysis results. In addition, the draft tech memo
will summarize the results of the demand estimation, needs assessment, and
alternatives evaluation, and will include the results of the ridership demand projections
(assuming existing services are maintained throughout the ten-year planning horizon)..
The draft tech memo will be disseminated to the Review Committee for consideration
and comment. All comments and modifications recommended by the committee will be
incorporated into the tech memo in preparation for inclusion in the draft final TDP
document.
Responsibilities of Consultant
. Conduct transit demand analyses (Transit Orientation Index and Density
Threshold Assessment)
. Estimate demand using FDOT approved tool, T-BEST.
. Identify & assess needs for transit services.
. Identify & evaluate alternatives.
.. .-
Agenda Item No. 1685
September 29, 2009
Page 17 of 29
. Prepare Technical Memorandum No.2 (Tasks 4 & 5).
Responsibilities of Collier County Staff
. Coordinate with Consultant as necessary in assessing demand and identifying
alternatives.
. Review Technical Memorandum NO.2 (Tasks 4 & 5).
Task 6: Conduct Situation Appraisal
A situation appraisal will be conducted to document and understand the environment in
which the transit system operates.
-
Task 6.01: Document Relevant Plans, Policies, and Trends - The Consultant will
review local plans and documents, including county and local government
Comprehensive Plans, the previous TOP, the MPO long-range transportation plan, and
the Transportation Disadvantaged Service Plan, to identify and compile community
goals and objectives relating to transit and mobility.
Task 6.02: Integrate Transit Demand Assessment - The Consultant will integrate
the transit demand assessment into the situation appraisal process. The implications
of the estimated transit demand will be assessed and documented as part of this task.
Task 6.03: Perform Situation Appraisal- A situation appraisal can be viewed as an
assessment process that continues the theme of strategic planning. At a minimum, the
TOP rule requires that the situation appraisal address the following factors:
. Assess the strengths and weaknesses of the transit organization, as well as
external barriers and opportunities that impact the delivery of transit services.
. Consider the effects of land use, state and local transportation plans, other
governmental actions and policies, socioeconomic trends, organizational issues,
and technology on the transit system.
. Estimate the community's demand for transit service using the planning tools
provided by FOOT, or a Department-approved transit demand estimation
technique with supporting demographic, land use, transportation, and transit
data. The result of the transit demand estimation process shall be a ten-year
annual projection of transit ridership (addressed in Task 5 of this scope of
services ).
Agenda Item No. 1685
September 29,2009
Page 18 of 29
. Assess the extent to which land use and urban design patterns in the transit
agency's service area support or hinder the efficient provision of transit service,
including any efforts being undertaken by the transit operator or local land use
authorities to foster a more transit-friendly operating environment.
The results of Tasks 1 through 6 will be used to support the identification of the key
components of the situation appraisal. Results will be integrated into a technical
memorandum as part of Task 7.
Responsibilities of Consultant
. Document relevant plans, policies, and trends.
-
. Integrate transit demand assessment.
. Perform situation appraisal.
Responsibilities of Collier County Staff
. Support Consultant in the compilation of plans, policies, and trends.
. Coordinate with Consultant in the documentation of the situation appraisal.
Task 7: Develop Goals and Objectives
The Consultant, with assistance from County staff, will develop goals and objectives for
transit in the study area. Goals and objectives will be consistent with the goals of the
local community with respect to transportation and land use, in general, and specifically
to transit service. The goals and objectives prepared for the previous major update of
the TOP (if applicable) will be used as a starting point for this process. The Consultant
also will work closely with the transit agency in delineating a vision of where transit
wants to be in ten years. While this step is implicit in each task outlined in this scope
of services, it is specifically mentioned here in conjunction with the goals and
objectives.
Task 7.01: Integrate Situation Appraisal & Previous Public Input - The Consultant
will review the results of Task 2 (particularly the attitudes of local officials and
community leaders towards transit) and Task 6 (situation appraisal), to gain a better
understanding of community goals and objectives relating to transit and mobility.
Task 7.02: Develop Draft Goals & Objectives - Based on the previous sub-tasks, the
.
Agenda Item No. 1685
September 29, 2009
Page 19 of 29
Consultant will develop draft goals and objectives for the transit agency. The draft
goals and initiatives will be disseminated to the Review Committee for review and
approval.
Task 7.03: Prepare Technical Memorandum No.3 - Draft Technical Memorandum
NO.3 will be prepared to compile the data and results from Tasks 6 (situation
appraisal) and 7 (goals and objectives). The draft tech memo will document the
situation appraisal and outline the goals and objectives for the transit agency. The
draft tech memo will be disseminated to the Review Committee for consideration and
comment. All comments and modifications recommended by the committee will be
incorporated into the tech memo in preparation for inclusion in the draft final TDP
document. -.
Responsibilities of Consultant
. Integrate situation appraisal and public input.
. Develop draft goals & initiatives.
. Prepare Technical Memorandum No.3 (Tasks 6 & 7).
Responsibilities of Collier County Staff
. Review Technical Memorandum NO.3 (Tasks 6 & 7).
Task 8: Prepare Ten-Year Transit Development Plan
Based on the results of Tasks 2 through 6 and input from the Review Committee, the
Consultant will prepare a ten-year TOP. This will not be a service plan since
operational analysis and route-specific changes are not within the scope of the TOP.
Instead, the TOP will be policy-oriented and strategic in nature. The TOP also will
contain policies and strategies to implement the proposed plan, including the
consideration of new funding sources. It also will be important to coordinate the transit
development planning process with the Transit Element of the MPO's 2035 long-range
transportation planning process.
Task 8.01: Prepare Ten-Year Transit Improvement Program - The Consultant will
prepare the draft ten-year TOP report, including the implementation plan and
supporting financial plan. The following elements will be included in the plan:
Agenda Item No. 1685
September 29,2009
Page 20 of 29
. Institutional, organizational, and management structure, documenting any
possible changes as a result of the planning process.
. Alternatives and recommendations for meeting transit needs and deficiencies.
. Ten-year service and capital improvements, including funded and unfunded
needs.
. Ten-yearfinancial plan, including projected operating and capital expenses, and
projected revenue by source and funding. A discussion of financial capacity will
be included.
. A list of recommendations for which no funding source is identified.
. A policy element ensuring that transit goals and objectives are consistent with
and support the local comprehensive plans, the MPO's Long Range
-
Transportation Plan, and other relevant planning initiatives.
Task 8.02: Prepare Performance Monitoring Program - The Consultant will develop
a basic monitoring program to track performance, efficiency, and effectiveness of the
transit agency's routes and service. The program will include measures and
threshold(s) for when a route should be considered for elimination or restructuring.
Also included will be a step-by-step route elimination/restructuring process to be
proposed for adoption by the governing authority for implementation.
Task 8.03: Prepare Annual Farebox Recovery Ratio Report - The Consultant will
prepare a short analysis of farebox recovery in accordance with legislative and FOOT
requirements.
Task 8.04: Conduct Public Workshops - During the course of the study effort, the
Consultant will schedule and coordinate with transit agency staff two public workshops
to obtain input from the general public about the TOP update process (one early in the
process to collect input on needs and the other later on to collect input on potential
alternative improvements). To maximize opportunities for citizen participation,
locations will be selected to ensure geographic coverage and, to the extent possible,
piggyback on other community events.
Task 8.05: Prepare TDP Presentation - A user-friendly, graphical presentation will be
incrementally developed to support the communication and adoption of the TOP. The
presentation will also be available for use by Collier County staff beyond the adoption
of the TOP.
-"""'"
Agenda Item No. 1685
September 29,2009
Page 21 of 29
Task 8.06: Prepare Draft TDP Document - The Consultant will produce and submit
an electronic copy (PDF) of the Draft TDP for dissemination, review, comment, and
acceptance. Comments on the Draft TDP will be addressed for the final version of the
plan.
Task 8.07: Prepare Draft Executive Summary for TDP - A concise executive
summary of the Draft TDP will be prepared along with the full document to facilitate
more widespread dissemination of the TDP. An electronic copy (PDF) of the Draft TDP
Executive Summary will be provided to the transit agency with the Draft TDP for
dissemination, review, and comment. Comments on the Draft TDP Executive Summary
will be addressed for the final version of the plan.
Task 8.08: Prepare Final TDP Document - Following presentation, review, and
acceptance of the Draft TDP and Draft TDP Executive Summary, the Consultant will
prepare and submit the Final TDP documents. A total of 10 printed copies of the Final
TDP and Final TDP Executive Summary will be prepared by the Consultant and
provided to the transit agency for consideration and adoption by the appropriate
governing board. The consultant also will prepare and provide one CD containing the
TDP documentation (including all associated graphics) in both Microsoft Word and
PDF format.
Responsibilities of Consultant
. Prepare ten-year transit improvement program.
. Prepare performance monitoring program.
. Prepare annual farebox recovery ratio report.
. Conduct 3 public workshops. (3 trips)
. Prepare TDP presentation.
. Prepare draft TDP document.
. Prepare draft TDP executive summary.
. Prepare final TDP documentation.
Responsibilities of Collier County Staff
. Participate in public workshops.
. Review draft TDP presentation.
. Review draft TDP document.
. Review draft executive summary.
Agenda Item No. 1685
September 29,2009
Page 22 of 29
Task 9: Facilitate Meetings & Presentations
The Consultant will prepare for and participate in up to five meetings with Collier
County staff and up to three presentations. Presentations will be made at the direction
of Collier County staff and audiences may include:
. MPO Technical Advisory Committee
. MPO Citizens Advisory Committee
. MPO Board
. Others as requested
Responsibilities of Consultant
. Prepare for and facilitate up to 5 meetings with staff.
. Prepare for and make up to 3 presentations.
Responsibilities of Collier County Staff
. Participate in meetings and presentations as appropriate.
PROJECT SCHEDULE
According to the TOP rule, Collier County's major TOP update is due by September 1,
2010. The project schedule for this scope of services assumes the successful
completion of the project within 10 months of notice to proceed. This assumes a start
date in September 2009, with a goal of adopting the TOP in June 2010. Since the
update is due to FOOT by September 1, 2010, this schedule provides some flexibility
should unforeseen circumstances result in any delays to the project. A detailed project
schedule will be prepared and discussed at the kickoff meeting.
PROJECT BUDGET
The lump-sum budget for the preparation of the TOP is provided in Table 2.
.' .~."""" ..."..~.~ '-
Agenda Item No. 1685
September 29, 2009
Page 23 of 29
SCHEDULE B
BASIS OF COMPENSATION
LUMP SUM
1. MONTHLY STATUS REPORTS
B.1.1 As a condition precedent to payment, CONSUL T ANT shall submit to OWNER as
part of its monthly invoice a progress report reflecting the Project design and
construction status, in terms of the total work effort estimated to be required for the
completion of the Basic Services and any then-authorized Additional Services, as of the
last day of the subject monthly billing cycle. Among other things, the report shall show
all Service items and the percentage complete of each item.
B1.1.1 All monthly status reports and invoices shall be mailed to the
attention
of Lorraine Lantz, Principal Planner, 2885 South Horseshoe Drive, Naples, FL
34104
2. COMPENSATION TO CONSULTANT
B.2.1. For the Basic Services provided for in this Agreement, OWNER agrees to make
the lump sum payments to CONSULTANT in accordance with the terms stated below.
Payments will be made in accordance with the following Schedule; however, the
payment of any particular line item noted below shall not be due until all services
associated with any such line item have been completed to OWNER'S reasonable
satisfaction.
TAS TASK DESCRIPTION TOTAL COST PAYMENT SCHEDULE
K
1. Establish Review $ 2,015.00 Monthly based upon percent
Committee/Prepare for kickoff complete
2. Establish Baseline Condition $ 10.405.00 Monthly based upon percent
complete
3. Facilitate Public Involvement $ 37,805.00 Monthly based upon percent
complete
4. Update Evaluation of Existing $ 7.170.00 Monthly based upon percent
Transit Services complete
5. Estimate Demand & Mobility $ 26.200.00 Monthly based upon percent
Needs complete
6. Conduct Situation Appraisal $ 6.340.00 Monthly based upon percent
complete
7. Develop Goals & Objectives $ 6.010.00 Monthly based upon percent
complete
Agenda Item No. 1685
September 29, 2009
Page 24 of 29
8. Prepare Ten-Year TOP $ 20.765.00 Monthly based upon percent
complete
9. Facilitate Meetings & $ 12.840.00 Monthly based upon percent
Presentations complete
TOTAL FEE (Total Items 1-9) $129.550.00
B.2.2. The fees noted in Section 2.1. shall constitute the lump sum amount of One
hundred twentv nine five hundred fiftv Dollars ($129.550.00) to be paid to
CONSUL T ANT for the performance of the Basic Services.
B.2.3. For Additional Services provided pursuant to Article 2 of the Agreement, if any,
___ OWNER agrees to pay CONSULTANT a negotiated total fee and Reimbursable
Expenses based on the services to be provided and as set forth in the
Amendment authorizing such Additional Services. The negotiated fee shall be
based upon the rates specified in Attachment 1 to this Schedule B and all
Reimbursable Expenses shall comply with the provision of Section 3.4.1 below.
There shall be no overtime pay on Additional Services without OWNER'S prior
written approval.
B.2.4. The compensation provided for under Sections 2.1 of this Schedule B, shall be
the total and complete amount payable to CONSUL T ANT for the Basic Services
to be performed under the provisions of this Agreement, and shall include the
cost of all materials, equipment, supplies and out-of-pocket expenses incurred in
the performance of all such services.
B.2.5 Notwithstanding anything in the Agreement to the contrary, CONSUL TANT
acknowledges and agrees that in the event of a dispute concerning payments for
Services performed under this Agreement, CONSULTANT shall continue to
perform the Services required of it under this Agreement, as directed by
OWNER, pending resolution of the dispute provided that OWNER continues to
pay to CONSULTANT all amounts that OWNER does not dispute are due and
payable.
3. SCHEDULE OF PAYMENTS:
B.3.1. CONSUL T ANT shall submit, with each of the monthly status reports provided for
under Section 1.1 of this Schedule B, an invoice for fees earned in the
performance of Basic Services and Additional Services during the subject billing
month. Notwithstanding anything herein to the contrary, the CONSUL T ANT
shall submit no more than one invoice per month for all fees earned that month
for both Basic Services and Additional Services. Invoices shall be reasonably
substantiated, identify the services rendered and must be submitted in triplicate
in a form and manner required by Owner. Additionally, the number of the
purchase order granting approval for such services shall appear on all invoices.
-,....,~-"..... -~"'~-,~ '-....-...
Agenda Item No. 1685
September 29, 2009
Page 25 of 29
8.3.2. Invoices not properly prepared (mathematical errors, billing not reflecting actual
work done, no signature, etc.) shall be returned to CONSULTANT for correction.
Invoices shall be submitted on CONSULTANT'S letterhead and must include the
Purchase Order Number and Project name and shall not be submitted more than
one time monthly.
8.3.3 Payments for Additional Services of CONSULTANT as defined in Article 2
hereinabove and for reimbursable expenses will be made monthly upon
presentation of a detailed invoice with supporting documentation.
8.3.4 Unless specific rates have been established in Attachment 1, attached to this
Schedule 8, CONSULTANT agrees that, with respect to any subconsultant or
subcontractor to be utilized by CONSUL TANT for Additional Services,
CONSUL T ANT-shall be limited to a maximum markup of 5% on the fees and
expenses associated with such subconsultants and subcontractors.
8.3.4.1 Reimbursable Expenses associated with Additional Services must
comply with section 112.061, Fla. Stat., or as set forth in the
Agreement, be charged without mark-up by the CONSULTANT, and
shall consist only of the following items:
8.3.4.1.1. Cost for reproducing documents that exceed the number of
documents described in this Agreement and postage and
handling of Drawings and Specifications.
8.3.4.1.2. Travel expenses reasonably and necessarily incurred with
respect to Project related trips, to the extent such trips are
approved by OWNER. Such expenses, if approved by
OWNER, may include coach airfare, standard accommodations
and meals, all in accordance with section 112.061, F.S. Further,
such expenses, if approved by OWNER, may include mileage
for trips that are from/to destinations outside of Collier or Lee
Counties. Such trips within Collier and Lee Counties are
expressly excluded.
8.3.4.1.3. Permit Fees required by the Project.
8.3.4.1.4 Expense of overtime work requiring higher than regular rates
approved in advance and in writing by OWNER.
8.3.4.1.5 Expense of models for the County's use.
8.3.4.1.6 Other items on request and approved in writing by the OWNER.
8.3.4.2 Should a conflict exist between the dollar amounts set forth in Section
Agenda Item No. 1685
September 29, 2009
Page 26 of 29
112.061, F.S., and the Agreement, the terms of the Agreement shall
prevail.
-'-
.-
-..-.,.
Agenda Item No. 1685
September 29, 2009
Page 27 of 29
SCHEDULE B
ATTACHMENT II
CONSUL TANT'S EMPLOYEE HOURLY RATE SCHEDULE
Professional Cateqorv Hourlv Rate
Principal 195.00/hr
Project Manager 170.00/hr
-
Senior Planner 140.00/hr
Planner 100.00/hr
GIS Technician 90.00/hr
Administrative Assistant 60.00/hr
END OF SCHEDULE B
Agenda Item No. 1685
September 29,2009
Page 28 of 29
SCHEDULE C
PROJECT MILESTONE SCHEDULE
Upon the Notice to Proceed issued by OWNER, a final Transit Development
Plan approved by the following entities including the Collier County Board of
County Commissioners, Metropolitan Planning Organization and Florida
Department of Transportation shall be submitted to OWNER within three
hundred twenty four (324) days after the date of such Notice.
Task Descriptions Calendar Days
--
. Task 1: Establish Review Committee & Prepare for Kickoff 8 days
. Task 2: Establish Baseline Conditions 30 days
. Task 3: Facilitate Public Involvement 96 days
. Task 4: Update Evaluation of Existing Transit Services 18 days
. Task 5: Estimate Demand & Mobility Needs 72 days
. Task 6: Conduct Situation Appraisal 17 days
. Task 7: Develop Goals & Objectives 17 days
. Task 8: Prepare Ten-Year Transit Development Plan 50 days
. Task 9: Facilitate Meetings & Presentations 16 days
~",.-- -
Agenda Item No. 1685
September 29,2009
Page 29 of 29