Agenda 06/23/2009 Item #16B 8
Agenda Item No. 16B8
June 23, 2009
Page 1 of 23
EXECUTIVE SUMMARY
Recommendation to approve the Contract Supplemental Agreement to Contract No.
06-3931 in the amount of $573,302 with Stanley Consultants, Inc., for the re-design
of Golden Gate Boulevard from Wilson Boulevard to Desoto Boulevard, Project No.
60040.
OBJECTIVE: To receive Board approval of the negotiated Contract Supplemental
Agreement for Engineering and Permitting Services, in the amount of $573,302, to be
provided by Stanley Consultants, Inc., for the re-design from six-lanes to four-lanes of
Golden Gate Boulevard from Wilson Boulevard to Desoto Boulevard, Project No. 60040.
CONSIDERATION: The original Contract No.06-3931 called for Stanley to design
and permit Golden Gate Boulevard as a four-lane road within a six-lane right-of-way. In
December of 2008, Stanley delivered 100% plans on time and within budget. In
subsequent meetings with Transportation Administration, Transportation Planning, and
Transportation Engineering and Construction Management, it was decided due to budget
constraints and long range needs projections, Golden Gate Boulevard would only need
four lanes. It was further decided that TECM would pursue a re-design of the project to
four lanes in a four lane right-of-way section. Stanley is to deliver 60% plans and all
permits so that the County may move ahead with 100% design plans, or to construction,
as a Design/Build Project at a future time when construction funding becomes available.
The Contract Supplemental Agreement also contains an hourly rate increase to the
original Fee Schedule based on current rates under similar contracts.
The current alignment of Golden Gate Boulevard and the presence of a 36 inch water
main that belongs to the City of Naples requires that nearly all the expanded right-of-way
be taken from the property owners on the south side of the road. The four-lane right-of-
way will be less intrusive on the affected home owners.
The re-designed plans for the Golden Gate Blvd. project (4 lanes in a 4 lane right-of-way
section) will produce an estimated savings in right-of-way, construction costs, and
wetland and wildlife mitigation of $22.7 million.
FISCAL IMPACT: Funds in the amount of $573,302 are available within the
Transportation Supported Gas Tax Fund and Road Impact Fee Funds.
LEGAL CONSIDERATIONS: This item has been reviewed and approved by the
County Attorney's Office, is not quasi-judicial and requires no ex parte disclosure,
requires only a majority vote for approval, and is otherwise legally sufficient for Board
action.-SRT
",.-.,
GROWTH MANAGEMENT IMP ACT: The project is currently identified in the
Capital Improvement Element of the Growth Management Plan.
Agenda Item No. 16B8
June 23,2009
Page 2 of 23
RECOMMENDATION: That the Board of County Commissioners approve the
Contract Supplemental Agreement to Contract No. 06-3931 with Stanley Consultants,
Inc., in the amount of $573,302 for the re-design of Golden Gate Boulevard from Wilson
Boulevard to Desoto Boulevard, and authorize the Chairman to execute the Change Order
on behalf of the County.
Prepared by: Kevin H. Dugan, Project Manager, TECM
Attachments: (1) Amendment Document; (2) Contract Supplemental Agreement, Exhibit
AI-A
Page 1 of 2
Agenda Item No. 16B8
June 23,2009
Page 3 of 23
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
Item Number:
Item Summary:
16B8
Recommendation to approve the Contract Supplemental Agreement to Contract No. 06-3931
in the amount of $573,302 with Stanley Consultants, Inc" for the re-design of Golden Gate
Boulevard from Wilson Boulevard to Desoto Boulevard, Project No. 60040.
Meeting Date:
612312009 90000 AM
Approved By
Scott R. Teach
County Attorney
Assistant County Attorney
County Attorney Office
Date
619/2009 11 :34 AM
Approved By
Rhonda Rembert
Administrative Services
Contract Specialist
Purchasing
Date
6/9/2009 1 :51 PM
Approved By
Lisa Taylor
Transportation Services
Management/Budget Analyst
Transportation Administration
Date
6/10120098:44 AM
Approved By
Norm E. Feder, AICP
Transportation Division Administrator
Transportation Services Admin.
Date
Transportation Services
6110/200910:22 AM
Approved By
Gary Putaansuu
Principal Project Manager
Transportation Engineering and
Construction
Date
Transportation Services
6111/20097:36 AM
Approved By
Therese Stanley
T ra ns portati on
Grants Coordinator
Date
Transportation Administration
6/11/20099:38 AM
Approved By
Kelsey Ward
Contract Administration Manager
Purchasing
Date
Administrative Services
6111/20095:00 PM
Approved By
Najeh Ahmad
Director
Date
Transportation Services
Transportation Engineering &
Construction Management
6/11/2009 5:02 PM
Approved By
OMB Coordinator
OMB Coordinator
Date
County Manager's Office
Office of Management & Budget
6/16/20099:38 AM
Approved By
Susan Usher
County Manager's Office
Senior Management/Budget Analyst
Office of Management & Budget
Date
6/16/20094:48 PM
Approved By
Leo E. Ochs, Jr.
Deputy County Manager
Date
file://C:\AgendaTest\Export\ 132-J une%2023,%202009\ 16. %20CONSENT%20AG ENDA \ 1... 6/17/2009
Page 20f2
Agenda Item No. 16B8
June 23, 2009
Page 4 of 23
Board of County
Commissioners
County Manager's Office
6/17/20093:30 PM
file://C:\AgendaTest\Export\ 132-June%2023, %202009\ 16.%20CONSENT%20AGENDA \ 1... 6/17/2009
Agenda Item No. 16B8
June 23, 2009
Page 5 of 23
SCHEDULE A
SUPPLEMENTAL AGREEMENT NO.1
SCOPE OF SERVICES
06-3931 "Design and Permitting of Golden Gate Boulevard
(Wilson Boulevard to Desoto Boul.evard)", Project #60040
DESCRIPTION
This SUPPLEMENTAL AGREEMENT NO.1 between the Collier County Government (COUNTY) and
Stanley Consultants, Inc. (CONSULTANT) amends their original agreement of April 11th 2006 (Contract
No. 06-3931) for CONSULTANT to provide services to the COUNTY for Widening of Golden Gate
Boulevard (CR 876), from immediately west of Wilson Boulevard to immediately east of Desoto
Boulevard, a distance of approximately 6.0 miles (County Project #60040). Except as specifically
amended by this Supplemental Agreement, all the terms and conditions of the original Agreement shall
remain in full force and effect.
The original agreement involved preparation of final (100%) plans and environmental permitting for the
widening of Golden Gate Boulevard to six lanes. The objective of this supplemental agreement involves
preparation of 60% level plans and environmental permitting services for widening of Golden Gate
Boulevard to four lanes. Elements of work shall include, but may not be limited to: roadways,
structures, intersections, drainage, signalization, utility design, coordination and relocation, right-of-way
maps and legal descriptions, cost estimates, noise analysis, environmental permits, a public meeting,
and all necessary incidental items as listed and estimated in this scope of work and attached fee sheet.
The Scope of Services establishes which items of work described in the Florida Department of
Transportation (FOOT) Plans Preparation Manual, Collier County Land Development Code and other
pertinent manuals to accomplish the work are specifically included in this contract, and also which of
the items of work will be the responsibility of the CONSULTANT or the COUNTY.
In preparing this Scope of Services for SUPPLEMENTAL AGREEMENT NO.1, the anticipated level of
effort for the 60% design and plans preparation is assumed consistent with Table 2 - Anticipated Plan
Agenda Item No. 16B8
June 23,2009
Page 6 of 23
Sheets contained in Schedule A of the original Agreement. Based on Table 2, the 60% phase
deliverable plan set will include the following:
. Key Sheet
. Drainage maps
. Typical Sections
. General Notes Sheet
. Bridge Hydraulic Sheet
. Roadway Plan & Profile
. Conceptual Traffic Control Plan, Details, General Notes
. Project Network Control
. Intersection & Miscellaneous Details
. Drainage Structures
. Ponds - Stormwater Management Plans
. Roadway Cross Sections
. Structural Plans Set
. Conceptual Signing & Marking Plans
. Conceptual Signalization Plans
. Right-of-Way Maps (By Others)
CONSULTANT's preparation of plans under this Supplemental Agreement is to the 60% level only.
CONSULTANT does not assume any responsibility or liability for the completion of these services by
the design-build contractor, or other consultant retained by COUNTY to complete the design and plans
preparation. The design-build contractor or other consultant will indemnify and hold CONSULTANT
harmless for the services performed to complete the project construction documents,
II PRIME CONSULTANT SERVICES
Task 1)
PROJECT GENERAL TASKS
Cost Estimates
The CONSULTANT shall be responsible for producing a construction cost estimate at the 60%
submittal phase only. The detailed preliminary construction estimate will include project pay
items and corresponding quantities.
Proiect Schedule
The CONSULTANT shall provide a detailed project activity/event schedule for COUNTY and
CONSULTANT activities required to meet the completion date for design. The schedule shall
2
Agenda Item No. 16B8
June 23,2009
Page 7 of 23
indicate, at a minimum, submission dates for Draft and Final 60% Plans, The schedule shall
allow up to two weeks for the COUNTY'S review of the Draft 60% Plans.
Periodically, throughout the duration of the project, the schedule shall be reviewed and, with the
approval of the COUNTY, adjusted as necessary to incorporate changes in the work concept
and progress to date.
Submittals
A Draft and Final submittal of the plans, reports, and associated documents shall be made at
the 60% level plan development. For the Draft 60% Submittal, the CONSULTANT shall provide
the COUNTY with twelve (12) sets of 11" x 17" size plans for review and distribution. The
CONSULTANT shall incorporate comments received from the COUNTY into the Final 60%
plans, reports and documents. Electronic (digital) files of the plans, reports and associated
project documents will be submitted to the COUNTY on a compact disk (CD) or other media
approved by the COUNTY. Drawings files shall be provided in a fully functional Microstation
(.dgn) software format, and also plotted or scanned to an Adobe Acrobat (.pdt) format.
Furnishing electronic copy of CADD drawings in format other than Bentley's MicroStation will be
considered Additional Services.
Proiect Coordination & Technical MeetinQs
Includes all trips required to obtain necessary data for all elements of the project identified in
this scope of work.: Includes meetings with the COUNTY and/or Agency staff, between
disciplines and SUBCONSUL TANTS, such as local governments, progress review meetings
(phase review), and miscellaneous meetings.
Quality Assurance/Quality Control
The purpose of CONSULTANT plan reviews is to ensure that the CONSULTANT's plans follow
the plan preparation procedures outlined in the FDOT Plans Preparation Manual, that state and
federal design criteria are followed consistent with the COUNTY concept, and that the
CONSULTANT submittals are complete. The CONSULTANT shall be responsible for the
3
Agenda Item No. 16B8
June 23, 2009
Page 8 of 23
professional quality, technical accuracy and coordination of all surveys, designs, drawings,
reports and other services furnished by the CONSULTANT under this contract.
The CONSULTANT shall through all stages of design, without additional compensation, correct
all errors or deficiencies in the designs, maps, drawings, reports and/or other services
Public Involvement
Public involvement is an important aspect of the project development process. Public
involvement includes communicating to all interested persons, groups, and government
organizations information regarding the development of the project. Property owners adjacent to
project shall be kept informed about the project.
One (1) Public Meeting will be held on this project, following incorporation of 60% review
comments and per the direction of the COUNTY.
Task 2)
ROADWAY & UTILITIES
Typical Section
Design will provide for a four-lane urban roadway within the existing right of way wherever
possible and providing bike lanes and sidewalks adjacent to the outside lane on both sides of
the facility, The alignment for the four-lane roadway shall be established based upon the
ultimate six-lane facility designed under the original agreement. In consideration for the City of
Naples' 36" water main and the proximity of residences, the northern edge of pavement
established for the six-lane facility will be held for the four-lane design, east of 4th Street. This
will result in the southern edge of pavement proposed for the six-lane facility to move 22 ft. north
and the proposed right-of-way width reduced accordingly through out the project limits.
Horizontal & Vertical Master DesiQn Files
Includes all work required to develop base design files including overall Plan, Profile, Drainage,
Utility, Right of Way, and master Traffic Control files.
· Limits: Golden Gate Boulevard (CR 876), from immediately west of Wilson Boulevard to
immediately east Desoto Boulevard, a distance of approximately 6.0 miles. Within these
limits, Golden Gate Boulevard will be designed to 60% Plans.
4
Agenda Item No. 16B8
June 23, 2009
Page 9 of 23
Intersections: Improvements to the following intersections are included within this scope of
services:
· Golden Gate Boulevard and Wilson Boulevard,
· Golden Gate Boulevard and Everglades Boulevard, and
· Golden Gate Boulevard and Desoto Boulevard
Cross Section Desion Files
Includes all effort to establish roadway template and run the model to produce cross sections for
Golden Gate Boulevard, Wilson Boulevard, Everglades Boulevard and Desoto Boulevard.
Existing ground and proposed design sections will be modeled at a maximum of 100 ft. stations
taken along the center line of construction. This information will be utilized to establish the limits
of construction and proposed Right of Way for the project.
Plan Sheets
Prepare 60% level plan sheets for proposed improvements on Golden Gate Blvd, Wilson Blvd,
Everglades Blvd, and Desoto Blvd thru the project limits. Generally this includes Key Sheet and
General Notes, Plan/Profile views, Typical Sections, Drainage Structure sheets, Cross Sections
at every 100 ft., Utility Adjustment sheets and miscellaneous Details. Task includes all work to
establish and set up sheets, labeling and incorporation of information into the plans. The
anticipated plans for the 60% Phase level shall be consistent with Table 2 - Anticipated Plan
Sheets contained in Schedule A of the original Agreement, and as shown above in Section I
DESCRIPTION.
Utility Coordination
The CONSULTANT shall schedule (time and place), notify participants, and conduct two (2)
utility meetings with all affected UAO(s) for the purpose of presenting the project, review the
current design schedule, evaluate the utility information collected, provide follow-up information
on compensable interest requests, and discuss any future design issues that may impact
utilities. This is also an opportunity for the UAO(s) to present proposed facilities. At a minimum
of three (3) weeks prior to the meeting(s), the CONSULTANT shall transmit two (2) complete
5
Agenda Item No. 16B8
June 23, 2009
Page 10 of 23
sets of project plans to each UAO having facilities located within the project limits, and one set
to the COUNTY Offices as required by the COUNTY. The CONSULTANT shall schedule (time
and place), notify participants, and conduct the Utility meeting with all affected UAO(s). The
CONSULTANT shall be prepared to discuss drainage, traffic signalization, maintenance of
traffic (construction phasing), review the current design schedule and letting date, evaluate the
utility information collected, provide follow-up information on compensable interest requests.
The CONSULTANT shall keep accurate minutes of all meetings and distribute a copy to all
attendees.
Utilitv Desion (Collier County 30" raw water)
Prepare 60% plans for relocation of the Collier County raw water main (30") on Wilson Blvd.
through the proposed construction limits in consideration for other utilities and right-of-way
limitations. The intent of the relocation is to move the raw water main from under the proposed
roadway pavement. Preparing a relocation plan for other COUNTY utilities, such as potable
water, sanitary sewer, storm sewer, reclaimed water, etc. is not anticipated or included in this
scope of services and will be considered Additional Services.
Task 3)
SIGNALIZATION ANALYSIS & PLANS
This Scope of Services includes the design for three (3) signalized intersections:
1. Wilson Boulevard and Golden Gate Boulevard
2. Everglades Boulevard and Golden Gate Boulevard
3. Desoto Boulevard and Golden Gate Boulevard (a new signal will be designed)
All signals will be designed as mast arm systems. The CONSULTANT shall provide 60%
signalization plans to include mast arm tabulation, assemblies and sign layout for each
signalized intersection.
No Signal Warrants have been included in this Scope of Services to evaluate the need for
additional signalization. Signal Warrants and Signal Designs (in addition to those mentioned
above) will be considered Additional Services. Signal specifications and control cabinet details
shall not be included in this Scope of Services.
6
Agenda Item No. 16B8
June 23, 2009
Page 11 of 23
Task 4)
SIGNING & MARKING PLANS
PRELIMINARY LAYOUT & CONCEPTUAL PLANS
CONSULTANT shall develop pavement marking plans suitable to adequately depict the laneage
and turning lanes at intersections throughout the project limits. This information will be
incorporated into the graphical exhibits prepared for the Public Involvement Meeting. Final 60%
plans submittal shall include conceptual plans component for the roadway signing & marking
design. The anticipated scale of the plan sheets is 1" = 60 ft. Quantities for signing & marking
shall not be indicated or tabulated in the plans.
Task 5)
STRUCTURES
BridQe Development Report
The Consultant shall provide letter addendum to the original Bridge Development Report (BDR)
prepared under the original agreement for the six-lane roadway. The BDR addendum shall only
address changes that will be necessary when converting from a six-lane bridge to a four-lane
bridge. No alternative analysis will be prepared,
Medium Span Concrete BridQes
The design of three (3) medium span concrete bridges is anticipated as part of this scope of
services. For each bridge the typical section, location, length, and other pertinent information to
describing the proposed bridge work is included. The CONSULTANT shall prepare plans for
the Medium Span Concrete Bridges consistent with the level of detail previously submitted at
60% Phase under the original contract. Reinforcing Bars will not be detailed at 60%, however
The CONSULTANT shall provide Design Documentation to the COUNTY with each submittal
consisting of structural design calculations and other supporting documentation developed
during the development of the plans. The design calculations submitted shall adequately
address the complete design of all structural elements. These calculations shall be neatly and
7
Agenda Item No. 16B8
June 23, 2009
Page 12 of 23
logically presented on 8W'x11" paper (where possible) and all sheets shall be numbered. All
computer programs and parameters used in the design calculations shall include sufficient
backup information to facilitate the review task. The design of the three (3) medium span
concrete bridges shall utilize the existing AASHTO beam design developed under the original
agreement for a six lane facility. Beam spacing shall be based on current spacing developed
under the original contract or as best determined to minimize overhang dimensions, The
following design assumptions are noted below:
A. Slab design will not require change. Overhang lengths will increase, but will be less than 6'
maximum from SDG 4.2.48. Overhang at water main will require additional reinforcement,
but is not included in this estimate.
B. AASHTO beams will be shifted laterally to produce overhangs of equal length. The beam
spacing will not be changed, but the composite dead load will be distributed to fewer beams.
The existing beam designs will be checked for the increased dead loads. Note that SDG 2.8
now distributes barrier and railing loads in accordance with LRFD 4.6.2.2.
C. End bents and intermediate bents will be shortened by 22' and some piles removed. If
possible, the piles will not be modified and the resulting overhang on the south side will be
used. However, at the Golden Gate intermediate bents and the Miller end bents a pile is
currently located 22' from the south end. The pile spacing and STAAD model will need to be
revised at these locations.
D. The lateral forces applied to the bents will change due to the narrower bridge and fewer
beams. The ST AAD models will be revised to reflect these forces and the lateral shift of the
beams. STAAD models will be rerun to verify the adequacy of the piles. No revisions will be
made unless deemed necessary.
E. The capacity of the cap with the existing reinforcement will be checked against the forces
reported by the revised STAAD runs. No revisions will be made unless deemed necessary.
The design of miscellaneous structure services, Le., culvert extensions, foundations, mast arms,
etc., is anticipated as part of this Scope of Services. Any miscellaneous structure longer than 20
ft required for this project will be considered Additional Services.
The design of new box culvert(s) is not anticipated as part of this Scope of Services and will be
considered Additional Services.
Task 6)
DRAINAGE PLANS & PERMITS
8
Agenda Item No. 16B8
June 23,2009
Page 13of23
Stormwater Manaqement Facilities
Task involves all plans preparation effort required to incorporate stormwater management
design into 60% plan sheets. This includes plans and details for roadway conveyance ditches,
offsite ponds, outfalls and roadway storm drainage system as determined with subconsultant
GEl (see Section III SUBCONSUL TANT SERVICES).
Permits
The CONSULTANT and SUBCONSUL TANTS (GEl and SCHEDA see Section III
SUBCONSUL T ANT SERVICES) will:
· Identify all needed permits.
. Obtain COUNTY approval on decisions regarding, or modifications to, permits.
. Obtain COUNTY review prior to submittal of applications and designs to the permitting
agency.
. The SUBCONSUL TANTS will be responsible for performing all required environmental
assessments and surveys. Phase II Surveys (Environmental) and Specific Species (T&E)
Surveys, if required, will be considered Additional Services
. Obtain all necessary permits including, but not limited to Environmental Resource Permit
(ERP) from the South Florida Water Management District and the Army Corps of Engineers.
A COUNTY representative will be present at all meetings with regulatory agencies.
In addition to permit coordination, this task includes signing and sealing permitting documents
required for agency approval, preparing dredge and fill sketches for wetland impact exhibits,
and attendance at technical meetings.
Task 7)
NOISE ANALYSIS & REPORT
The CONSULTANT will revise the previously submitted Noise Study Report utilizing updated
projected traffic data provided by the COUNTY and reflecting the revised corridor width for the
four-lane roadway. The updates to the report will be made via letter addendum to the original
report.
9
Task 1)
Task 2)
Task 3)
Agenda Item No. 16B8
June 23, 2009
Page 14 of 23
III SUBCONSUL T ANT SERVICES
RIGHT OF WAY MAPPING
Revise Sketch and Description - Lane Re-desiqn (225)
1.1 Prepare 225 revised sketch and legal descriptions for the re-design from six
to four lanes.
Revise ROW Map - Lane Re-desiqn
2.1 Prepare revised right-of-way map for the re-design from six to four lanes
ENVIRONMENTAL PERMITTING & DRAINAGE
Scheduled Public Meetinqs and Presentations
GEl will attend scheduled meetings with the general public and county officials to
clarify and define development goals and requirements for the Project. This
includes communicating with interested persons, groups and government
organizations as required. At this time, no public meetings are planned for this
project. If required, meetings will be provided on a hourly basis, plus
reimbursable expenses.
MeetinQs with ReQulatorv Aqencies
GEl, together with other members of the ERP permitting Team will attend a number of
meetings with agencies, including the Lower West Coast Service Center of the South
Florida Water Management District, The Big Cypress Basin Naples office and the US
Army Corp of Engineers in Fort Myers. The meetings included in this budget will be part
of the permitting process with regulatory agencies and allow an informal exchange and
input into the ongoing design and permitting process. At this time, two (2) meetings are
anticipated.
Proiect Team Meetinqs
As part of the project design team, GEl will attend meetings to coordinate permitting
strategies and resolve design issues as they arise during the processs.
ENVIRONMENTAL ASSESSMENT
Update Environmental Permits
Scheda will update the Environmental Resource Permit document originally prepared for
the 6-lane roadway design to accommodate the new 4-lane roadway design.
10
Agenda Item No. 16B8
June 23,2009
Page 15 of 23
Review Dredae and Fill Sketches
Scheda will review draft wetland impact exhibits to ensure they accurately depict
jurisdictional wetland boundaries and impact areas. If revisions are necessary, Scheda
will provide markups and written comments.
Technical Meetinas
Scheda will prepare for and attend a maximum of four technical meetings. These
meetings may include regulatory agency meetings, progress meetings, public
information meetings, or meetings with Collier County staff or other agencies.
Reauest for Additional Information
Scheda will provide answers to the environmental questions for two RAls.
Mitigation Reauirements for Protected Species
Scheda will provide a technical memorandum discussing the impacts to protected
wildlife associated with the new 4-lane proposed roadway design. This will include
mitigation options available to Collier County for species such as the Florida panther
(Puma concolor coryl) and wood stork (Mycteria Americana).
Mitigation Requirements for
IV SERVICES PROVIDED BY COUNTY
For this SUPPLEMENTAL AGREEMENT NO.1 between the Collier County Government (COUNTY)
and Stanley Consultants, Inc. (CONSULTANT) the terms and conditions of the original Agreement
regarding Services Provided by County shall remain in full force and effect.
11
Agenda Item No. 16B8
June 23, 2009
Page 16 of 23
SCHEDULE B
SUPPLEMENTAL AGREEMENT NO.1
BASIS OF COMPENSA liON
DIRECT LABOR COSTS PLUS REIMBURSABLE EXPENSES
1. MONTHLY STATUS REPORTS
8.1.1 As a condition precedent to payment, CONSULTANT shall submit to OWNER as part of
its monthly invoice, a progress report reflecting the current status, in terms of the total
work effort estimated to be required for the completion of SUPPLEMENTAL
AGREEMENT NO. 1 and any then-authorized Additional Services, as of the last day of
the subject monthly billing cycle. Among other things, the report shall show all Service
items and the percentage complete of each item.
81.1.1 All monthly status reports and invoices shall be mailed to the attention of
Kevin Dugan, Project Manager, Collier County Government, Transportation
Division, 2885 Horseshoe Drive South, Naples, 34104.
2. COMPENSATION TO CONSULTANT
B.2.1. For the Basic Services provided for in this Supplemental Agreement, OWNER agrees to
make monthly payments to CONSULTANT based upon CONSULTANT'S Direct Labor
Costs and Reimbursable Expenses in accordance with the terms stated below.
Provided, however, in no event shall such compensation exceed the amounts set forth in
the table below.
i NOT TO
ITEM DESCRIPTION EXCEED
AMOUNT:
Task 1 - 60% Draft and Final Submittal $ 536,213 I Monthly based
7 I upon percent
I complete
I Reimbursables I $37,089 j Monthly based
I i on time and
i I material
!
i Total Fee I $ I --
573,302 I
B,2.2. Direct Labor Costs mean the actual salaries and wages (basic, premium and incentive)
paid to CONSULTANT'S personnel, with respect to this Supplemental Agreement,
including all indirect payroll related costs and fringe benefits, all in accordance with and
not in excess of the rates set forth in the Attachment B to this Schedule B,
B.2.3. With each monthly Application for Payment, CONSULTANT shall submit detailed time
records, and any other documentation reasonably required by OWNER. regarding
CONSULTANT'S Direct Labor Costs incurred at the time of billing, to be reviewed and
approved by OWNER.
B.2.4 For Additional Services provided pursuant to Article 2 of the Agreement, OWNER agrees
to pay CONSULTANT a negotiated total fee and Reimbursable Expenses based on the
services to be provided in compliance with the provisions of Section 3,5.1 below, There
8
Agenda Item No. 16B8
June 23,2009
Page 17 of 23
shall be no overtime pay on Basic Services or Additional Services without OWNER'S
prior written approval.
8.2.5. The compensation provided for under Sections 2.1 of this Schedule B, shall be the total
and complete amount payable to CONSULTANT for the Basic Services to be performed
under the provisions of this Agreement, and shall include the cost of all materials,
equipment, supplies and out-of-pocket expenses incurred in the performance of all such
services.
B.2.6 Notwithstanding anything in this Agreement to the contrary, CONSULTANT
acknowledges and agrees that in the event of a dispute concerning payments for
Services performed under this Agreement, CONSULTANT shall continue to perform the
Services required of it under this Agreement, as directed by OWNER, pending resolution
of the dispute provided that OWNER continues to pay to CONSULTANT all amounts that
OWNER does not dispute are due and payable.
3. SCHEDULE OF PAYMENTS
B.3.1. CONSULTANT shall submit, with each of the monthly status reports provided for under
Section 1.1 of this Schedule B, an invoice for fees earned in the performance services
during the subject billing month. Notwithstanding anything herein to the contrary, the
CONSULTANT shall submit no more than one invoice per month for all fees and
Reimbursable Expenses earned that month for both Basic Services under this
SUPPLEMENTAL AGREEMENT NO. 1 and any agreed upon Additional Services.
Invoices shall be reasonably substantiated, identify the services rendered and must be
submitted in triplicate in a form and manner required by Owner. Additionally, the number
of the purchase order granting approval for such services shall appear on all invoices.
B.3.2. Invoices not properly prepared (mathematical errors, billing not reflecting actual work
done, no signature, etc.) shall be returned to CONSULTANT for correction. Invoices
shall be submitted on CONSULTANT'S letterhead and must include the Purchase Order
Number and the Project name and shall not be submitted more than one time monthly.
B.3.3 Notwithstanding anything herein to the contrary, in no event may CONSULTANT'S
monthly billings, on a cumulative basis, exceed the sum determined by multiplying the
applicable not to exceed task limits set forth in the table in Section 2.1 by the percentage
Owner has determined CONSULTANT has completed such task as of that particular
monthly billing,
8.3.4 Payments for Additional Services of CONSULTANT as defined in Article 2 hereinabove
and for reimbursable expenses will be made monthly upon presentation of a detailed
invoice with supporting documentation.
8.3.5 Unless specific rates have been established in Attachment B, attached to this Schedule
B, CONSULTANT agrees that, with respect to any subconsultant or subcontractor to be
utilized by CONSULTANT for Additional Services, CONSULTANT shall be limited to a
maximum markup of 10% on the fees and expenses associated with such
subconsultants and subcontractors.
B.3.5.1 Reimbursable Expenses associated with Additional Services must comply with
section 112.061, Fla. Stat., or as set forth in the Agreement, be charged
c
Agenda Item No. 16B8
June 23, 2009
Page 18 of 23
without mark-up by the CONSULTANT, and shall consist only of the following
items:
B.3.5.1.1. Cost for reproducing documents that exceed the number of
documents described in this Agreement and postage and hanrllinn
of Drawings and Specifications. B-2
8.3.5.1.2. Travel expenses reasonably and necessarily incurred with respect
to Project related trips, to the extent such trips are approved by
OWNER. Such expenses, if approved by OWNER, may include
coach airfare, standard accommodations and meals, all in
accordance with section 112.061, F.S. Further, such expenses, if
approved by OWNER, may include mileage for trips that are from/to
destinations outside of Collier or Lee Counties. Such trips within
Collier and Lee Counties are expressly excluded.
B.3.5.1.3. Permit Fees required by the Project.
B.3.5.1.4 Expense of overtime work requiring higher than regular rates
approved in advance and in writing by OWNER.
B.3.5.1.5 Expense of models for the COUNTY's use.
B.3.5.1.6 Other items on request and approved in writing by the OWNER.
8.3.5.2 Should a conflict exist between the dollar amounts set forth in Section 112.061,
F.S., and the Agreement, the terms of the Agreement shall prevail.
D
SCHEDULE B
SUPPLEMENTAL AGREEMENT NO.1
ATTACHMENT A
SUMMARY OF FEE ESTIMATE
pROJECT SUMMARY
Task I and Task II
Task 1 - General Tasks & Ex enses
Ri ht Of Wa Ma ing - RWA
Task 2 - Roadway, Utilities
Task 3 - S.[gnalization Analysis & Plans
__!~~~_~__=-~!gning_~_M~r.k.!,-,-g_~/~,-,-~_____
Task 5 - Structures
Task 6 - Draina e & Permits
ERP & Drainage - GEl
Environ. Assessment - SEA
._"--,.._-".._.~----
Task 7 - Noise Analysis & Rep-ort
Reimbursables - based on
Time and Material
Total for Tasks 1 - 7 plus reimbursables
- Not to Exceed
BASIC SERVICES
Not to Exceed
Amount
Agenda Item No. 16B8
June 23,2009
Page 19 of 23
i
-----.--1
I
I
----r-.-- ----
I
~~- --~
r-
!
$ 37,089
$ 573,302
8-4
E
SCHEDULE B
SUPPLEMENTAL AGREEMENT NO.1
ATTACHMENT B
EMPLOYEE HOURLY RATE SCHEDULE
(PRIME CONSULTANT)
Project Principal/Principal Engineer $198.00
Project Manager $148.00
Senior Engineer $148.00
Engineer $111.00
Chief Engineer $171,00
Senior Designer $129.00
Graphics Technician $103.00
Administrative Assistant $54.00
END OF SCHEDULE B
Agenda Item No. 16B8
June 23,2009
Page 20 of 23
F
8-5
Agenda Item No. 16B8
June 23, 2009
Page 21 of 23
SCHEDULE C
PROJECT MILESTONE SCHEDULE
Schedule is based on the number of calendar days from issuance of Notice to Proceed.
1. TASK 1- DRAFT 60% SUBMITTAL
120 Days
2. TASK 11- FINAL 60% SUBMITTAL
240 Days
C-1
Agenda Item No. 16B8
June 23, 2009
Page 22 of 23
Agenda Item No. 16B8
June 23, 2009
Page 23 of 23
EXlUBIT A -1 COIItl'lld S.pp~.'" Acre-". 16-1931
"DeMp ..d .w.w Sen-.. .... RoIIdwlIY capldrr ,.prove.... Geldell Gate Blvd
(m. WD_ Blvd. to ..... .......)..
niI..P......IaI............ ....... . ., to.... nfe....ceII ..-e.t
...a Nit)' ... ....... 1M........... .... ........................., eou.l......1Itc.. (m
be ....... tII .. "OI1II....1d") ... CeIIier c..cr, ll'Jerida, (tII lie ............ .. ·
.eo..fy").
Sta~t oIU.............
8: ContrlICt II 0603931 "Desip 11I4 ReIlJlld SeMceI for Roedway CapIctt;y ImprovemeDtl
Golden Cia Blvd. (fiom WilIoa Blvd. to DeSoto B1Wo)"
The lbllowiq ohangc to tha IbcM: n:fi:n:nccd ApemIal ba boeo D1IIt\MIIy .... to by the
CoDMIlalm aDd the CouIII)':
.lD __ to ccmlinue the lI:IVice8 providDcl. for ita the oriaiDaI CouUKt documeat refr:reDced
.eboYe, the CoIIIuItllnt 1&f'CO. to add tile Su,pll1JllDll1 Apornant tIO tile above ftlt'et'cuccd
ConlrIer II per the ftlqujnmlllaD of Artlalc two (2) AcIdil:iaMl~. Thil SuppJamatal
~Dt IIbaIl al.o OCMII' bourIr I'IIIl!I i_ to the oriIiM1 Colier Cowrty Propmal Fee
ScbeduIe B. .,... 011 cunent ~ UIIder IimiII!r CODII'ICtI. 1... SuppIaaxGGl ~
bJelucUoa tho I1IIW r1llO IOboduIc, ExhI1:rit "AI-A" ill aUaabed to tI:Ua Supp1lmntal A&r--nt and
i_rpor8lIId blreia by 1'8""--
All other termS and amdilicms oft'- ~t 8hlIlI J'lllDIiII in forae.
IN WITNESS WHEREOF. the Consultant IIId the Cowdy law each. mpoctiYI'Jly. by III
IIlIboriZllCl perIOD or.Dt. bercuDdcr set their bends m1-.111 on the dlJe(lI) indiCI&lId below.
Acceplled :
,2009
CONTRACTOR:
s....., C_........IDc.
....
TsbIb E.. Dcmnia, PE
Via: President
By;
ATTEST;
OWNF.R:
Dwight E. Brock. Cleric
BOARD OF COUNTY
COMMlSSlONERS
COLUER COUNTY. f'I.ORIDA
By:
Doma Fiala, Chairman
Approved lIS to ronn Md
LepllUfftcieaor~ ~
~~~A~
'D<<Y"'h;
,- /-
P,OJBCT MAN~GER
^d~
',' ,-;1 //
BYY~~-1." .~ ~<J'"
KevIl1Du //' /
( -'"
;ii/
PlUNCll"AL PROJECT
MANAGER
By. ~.(~--:"
Oaty Pu&anwu
DEPARTM ENT~n1RECTOR,
~ . /
By; ~ ? "
-'lay AbmIId.. PE:' ,
.' \
DlVlSlON ADMlNJSTRA TOR
By:
No_ Feder