Loading...
Agenda 06/23/2009 Item #16A13 EXECUTIVE SUMMARY Agenda Item No. 16A 13 June 23, 2009 Page 1 of 7 Recommendation to approve final acceptance of the water and sewer utility facilities for Runaway Bay at Fiddler's Creek, Parcel 31 OBJECTIVE: The Board of County Commissioners, Ex-Officio the Governing Board of the Collier County Water-Sewer District, to accept final and unconditional conveyance of these water and/or sewer facilities. CONSIDERATIONS: 1) The Developer of Runaway Bay at Fiddler's Creek, Parcel 31, has constructed the water and sewer facilities within dedicated easements to serve this development. See attached location map. 2) Preliminary acceptance of these utility facilities was approved by the Engineering and Environmental Services Department staff on June 26, 2007. At that time, the value of these utility facilities (assets) was $57,551.50 for the water facilities and $136,065.75 for the sewer facilities (see attachment[s]). This final acceptance is in accordance with Collier County Ordinance No. 2004-31, as amended. 3) Staff recorded all preliminary acceptance documents in the public records of Collier County, which have been reviewed and approved by the County Attorney's office as to form and legal sufficiency. 4) The water and sewer facilities have been operated and maintained by the Collier County Water-Sewer District during, not less than, the required one (1) year warranty period. 5) A final inspection to discover defects in materials and workmanship has been conducted by the Engineering and Environmental Services Department staff, and these facilities have been found to be satisfactory and acceptable. 6) The PUD Monitoring staff has reviewed this request in relation to possible issues raised by the applicable Home Owners Association (HOA). Staff is unaware of any issues that would serve to negate the recommendation to release the applicable security. FISCAL IMPACT: Approval of this Executive Summary will have no specific financial impact. However, approval of this Executive Summary will result in the Collier County Water-Sewer District receiving unconditional title to the utility facilities, which at the time of preliminary acceptance, had a total (undepreciated) value of $193,617.25. GROWTH MANAGEMENT IMPACT: Approval of this Executive Summary will have no growth management impact. -, Agenda Item No. 16A 13 June 23, 2009 Page 2 of 7 LEGAL CONSIDERATIONS: The elements necessary to accept final and unconditional conveyance of those water and/or sewer facilities have been met. This item is not quasi-judicial and as such ex parte disclosure is not required. This item requires a majority vote only. There is no additional legal review from the County Attorney to complete this final acceptance. - JBW RECOMMENDATION: That the Board of County Commissioners, Ex-Officio the Governing Board of the Collier County Water-Sewer District, authorize final acceptance of these water and sewer utility facilities for Runaway Bay at Fiddler's Creek, Parcel 31, and authorize the County Manager, or his designee, to release any Utilities Performance Security (UPS) to the Project Engineer or the Developer's designated agent. PREPARED BY: Jodi P. Hughes, Technician ,..-, ,- Item Number: Item Summary: Meeting Date: Page 1 of 2 Agenda Item No. 16A13 June 23, 2009 Page 3 of 7 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 16A13 Recommendation to approve final acceptance of the water and sewer utility facilities for Runaway Bay at Fiddler's Creek, Parcel 31, 6/23/20099:0000 AM Prepa red By Jodi Pannullo Community Development & Environmental Services Administrative Assistant Date CDES Engineering Services 5112120099:01:09 AM Approved By MaryAnn Devanas Community Development & Environmental Services Date Senior Planner CDES Engineering 5112/20092:14 PM Approved By Stephen L. Nagy Public Utilities Wastewater Collections Manager WasteWater Date Approved By 5/1312009 9:43 AM Pamela Libby Public Utilities Water Operations Manager Water Date 5/1312009 11 :04 AM Approved By Paul Mattausch Public Utilities Water Director Date Water 5/131200911 :12 AM Date Approved By Donald Edwards Public Utilities Operations Manager Wastewater 5/18/20094:18 PM Approved By Judy Puig Community Development & Environmental Services Operations Analyst Community Development & Environmental Services Admin. Date 5/19120092:09 PM Approved By G, George Yilmaz Public Utilities WasteWater Director Date Approved By WasteWater 5121/200911:13 AM Phil E. Gramatges, P.E. Public Utilities Sr. Project Manager Public Utilities Planning and Project Management Department Date 5/21/20091 :16 PM Date Approved By Jeff Klatzkow County Attorney County Attorney County Attorney Office 5/2812009 10:39 AM Approved By file:IIC:\AgendaTest\Export\ 132-June%2023,%202009\ 16.%20CONSENT%20AGENDA \1... 6/17/2009 Jennifer A. Belpedio County Attorney Page 2 of2 Agenda Item No. 16A 13 June 23,2009 Page 4 of 7 Assistant County Attorney County Attorney Office Date 5/28/2009 2:02 PM Approved By Environmental Services Director Date William D. Lorenz, Jr., P.E. Community Development & Environmental Services " Environmental Services 6/5/200911 :54 AM Approved By Joseph K, Schmitt Community Development & Environmental Services Community Development & Environmental Services Adminstrator Date Community Development & Environmental Services Admin. 618/20093;00 PM OMS Coordinator Date Approved By OMS Coordinator County Manager's Office Office of Management & Budget 6/9/2009 10;31 AM Approved By Randy Greenwald County Manager's Office Management/Budget Analyst Office of Management & Budget Date 6/16/200910:03 AM Approved By Winona W. Stone Board of County Commissioners Assistant to the County Manger Date County Manager's Office 6/1612009 1 : 32 PM file:IIC:\AgendaTest\Export\132-June%2023,%202009\ 16.%20CONSENT%20AGENDA\1... 6/17/2009 ('f)OH.... ..,-0_ <(00 --'0 N L{) MOl NOl LOlCll co.. E::l 2~ Cll "0 .- Q) en <( I ..~ .,~,=~, ~.'I ~" \ ) / ni~ ~ jh ~ ,,~ JTr>S OJ. "01< / - " ~ ~~ ~~A ~ ir " ;;; ~ to' ~ d~ j Ui ! \, ~ ~. ~ c ~ " c.. <( :E W t- - en ./- :..:: w w a:: (.) y> 0:: ~i '""" Q (Y) .. 1 _ -I OJ @' U >- '\ i6 ~ 0.. ~ <, ~, ~' ;::), 0::1 fl. <( :2 z o - l- e:( U o ....J CERTIFICATION OF CONTRIBUTORY ASSETS Agenda Item No, 16A 13 June 23, 2009 Page 6 of 7 PROJECT NAME: FIDDLERS CREEK PARCEL 31- RUNAWAY BAY NAME & ADDRESS OF OWNER: GB Peninsula, Ltd. 3470 Club Center Boulevard, Naples, FL 34114 TYPE OF UTILITY SYSTEM: SANITARY SEWER (Materials) Revised Pump Station Complete 8' wetwell, 2-10 HP pumps 8' Dia. 1 E.A. $58.900.00 $58,900.00 4" Force Main DR-18 4" 2750 LF $4.20 $11,550.00 4" Force Main DR-14 4" 45 LF $5.95 $267.75 Air Release Valve Force Main 2" 4 EA $1,370.00 $5.480.00 8" PVC SDR-26 Sanitary Sewer 8" 4080 LF $4.60 $18,768.00 Manhole, lET Lined, 4' Diameter 4' 20 EA $1,790.00 $35,800.00 Drop Manhole Connection 8" 2 EA $400.00 $800.00 Single Sanitary Sewer Service wI Cleanout 6" 9 EA $100.00 $900.00 Double Sanitary Sewer Service wI Cleanout 6" 20 EA $180.00 $3,600.00 TOTAL COST $136,065.75 I do hereby certify that the quantities of material described above are true and accurate representation the as-installed cost of the system being contributed to Collier County Utilities, Incoo ::ERTIFYING: Aaron Hunt-Branch, P.E. Project Manager ~~~ OF: Guymann Construction of FL, INC. STATE OF FLORIDA ) COUNTY OF COLLIER) The foregoing instrument was signed and acknowledged before me this 11th day of June, 2009 by aron Hunt-Branch who is personally known to me and who did not take an oath. SEAL \\\\\1 11111/ 11111111 \\,\ w.E. 111.1 ~'S)l>- ,..,... * /~ ~ \>" ..~\AES '. ""-::. g 0' .':#'1-()09 -i.., %, ~ ---.~c'V ~.o-:: :::j:~" '*~:~:: = LlJ .~o.. . t:S ~. ..... :: - ::.:: . <.> u..l ~ ~o.::. -. a _ ~ '. ~<P ~ g: t:.:' 2 ~ -. *~ .,~"''?. N ~ ~ -.. So"t1eOt\t~. ~ .s- ~ ..... '.....' ~~-!$' "~,""'- NOTA"'( '?~ ",,,, 'I" "\\\ '1111111" III I \\\ fJl. . CERTIFICATION OF CONTRIBUTORY ASSETS Agenda Item No. 16A 13 June 23,2009 Page 7 of 7 PROJECT NAME: FIDDLERS CREEK PARCEL 31- RUNAWAY BAY NAME & ADDRESS OF OWNER: GB Peninsula, Ltd. 3470 Club Center Boulevard Naples, FL 34114 coPy TYPE OF UTILITY SYSTEM: POTABLE WATER (Materials) S" DR-18 PVC Water Main 8" 4545 LF $9.50 $43,177.50 S" Water Main DR14 8" 70 LF $11.20 $784.00 Single Water Service Complete 1.5" 6 EA $200.00 $1,200.00 Double Water Service Complete 2" 22 EA $315.00 $6,930.00 8" Gate Valve 8" 6 EA $650.00 $3,900.00 Permanent Bacterial Sampling Point 3/4" 1 EA $800.00 $800.00 Air Release Valve WM 1" 1 EA $760.00 $760.00 TOTAL COST: $57,551.50 I do hereby certify that the quantities of material described above are true and accurate _ representation of the as-installed cost of the system being contributed to Collier County Utilities, Jnc.. CERTIFYING: Aaron Hunt-Branch E.!. Project Manager ~~'-l~ OF: Guymann Construction of FL, INC. STATE OF FLORIDA ) ) SS: COUNTY OF COLLIER) The foregoing instrument was signed and acknowledged before me this 1st day of Mav, 2006 by Aaron Hunt-Branch who is personally known to me and who did not take an oath. ~ I?//~ I otary Public SEAL: i"'~jj\. 8eYeIty R. HIIrriI . ~ .; My CommIlIlIion 00257ilO3 '\ .....'" Expires JllnlHlry HI. 2008 Page 1