Loading...
#15-6382 WO (Humiston & Moore - Wiggins Pass Dredging) ,/ WORK ORDER/PURCHASE ORDER Contract 15-6382"Professional Services—Architect&Engineering" Contract Expiration Date: June 8,2019 i This Work Order is for Professional Engineering Services for work known as: Wiggins Pass Interim Dredging Project Name: Wiggins Pass Interim Dredging Project No: 195-80288 The work is specified in the proposal dated May 3, 2019 which is attached hereto and made a part of this Work Order. In accordance with Terms and Conditions of the Agreement referenced above, this Work Order/Purchase Order is assigned to: Humiston &Moore Engineers. / Scope of Work: As detailed in the attached proposal and the following: * Task 1 Plans, Permit Coordination, Specs, Opinion of Costs * Task 2 Bid Phase Services * Task 3 Pre-Construction Services * Task 4 Construction Phase Services & Project Certification Schedule of Work: Complete work within 365 days from the date of the Notice to Proceed which is accompanying this Work Order. The Consultant agrees that any Work Order that extends beyond the expiration date of Agreement No. 15-6382 will survive and remain subject to the terms and conditions of that Agreement until the completion or termination of this Work Order. Compensation: In accordance with the Agreement referenced above, the County will compensate the Firm in accordance with following method(s): Negotiated Lump Sum (NLS) CLump Sum Plus Reimbursable Costs (LS+RC) Time & Material (T&M) (established hourly rate— Schedule B) ❑ Cost Plus Fixed Fee (CPFF), (define which method will be used for which tasks) as provided in the attached proposal. Task 1 $21,726.00 (T&M)' Task 2 $ 2,300.00 (T&M)' Task 3 $ 3,812.00 (T&M)i Task 4 $19,140.00 (T&M)' TOTAL FEE $46,978.00 (T&M) • PREPARED BY: /"L C . Gary Alpin, CZM,C anager Da e APPROVED BY: 0%7/1,2L � �, -(- L.4 4.- i- 6/1-1, . // // Amy Patteson, Department Director Date APPROVED BY: I� haddeus L. Cohen, Department Head GMD Date Page 1 of 3 ill By the signature below, the Firm (including employees, officers and/or agents) certifies, and hereby discloses, that, to the best of their knowledge and belief, all relevant facts concerning past, present, or currently planned interest or activity(financial,contractual,organizational,or otherwise)which relates to the proposed work; and bear on whether the Firm has a potential conflict have been fully disclosed. Additionally,the Firm agrees to notify the Procurement Director, in writing within 48 hours of learning of any actual or potential conflict of interest that arises during the Work Order and/or project duration. ACCEPTED BY: Humisto �: More Engineers B D. Moore, P.E., D.CE. President Date Page 2 of 3 ATTEST: BOARD OF C F ' : i MISSIONERS Crystal K. Kinzel, C k Collier Coujy, 1 r - / mr OA lerk - Willia L. McDaniel,Jr. \\ \ - \ Attest as:to Chairman's Chairman .. ''tkinfthire only. ATTEST: By: (Print Name/Title Approved as to Form and gality: cau-an2--- ssistant County Attorney Page 3 of 3 Wiggins Pass Interim Dredging Engineering,Permitting,and Construction Phase Services Prepared by Humiston&Moore Engineers 5-03-2019 SCOPE OF WORK WIGGINS PASS INTERIM DREDGING CONTRACT 15-6382 MAY 3,2019 The following is a scope of services for engineering, permitting, and construction phase services for the proposed 2019/2020 interim maintenance dredging of a portion of the Wiggins Pass Navigation Channel. In all cases herein, County refers to Collier County, Park refers to Delnor Wiggins State Park, DEP refers to Department of Environmental Protection, USACE refers to the U.S. Army Corps of Engineers, and Engineer refers to Humiston & Moore Engineers. The estimated duration is 365 days. Construction bidding is to be combined with Water Turkey Bay dredging for cost savings. Background:State and federal permits are in place at this time for ongoing maintenance dredging of Wiggins Pass. Construction plans for interim dredging will be based on the most recent available data from monitoring and post construction surveys at Wiggins Pass and the adjacent beach area. With the planning of the maintenance dredging of Water Turkey Bay Channel for 2019, an opportunity is established for combining this work at Wiggins Pass and share the mobilization costs. Shoaling has occurred in the channel and dredging of that sand can be placed in the north nearshore disposal area being used for Water Turkey Bay Channel dredging. There also exists an accreted sand spit on the south shoreline of the inlet with opportunity to excavate and place that sand in the adjacent areas in need of sand below Mean High Water along the Park beach and inlet shoreline. Any necessary permit modification to the Wiggins Pass Maintenance Dredging permits to accomplish this task can be included with the state request for the Water Turkey Bay project. It is intended that the bidding and construction phase for the Wiggins Pass Interim Dredging project will be combined with the Water Turkey Bay Channel dredging project and South Marco Beach Restoration. The Water Turkey Bay project involves nearshore sediment disposal and may be conducted during the latter portion of the 2019 sea turtle nesting season. Upon completion of the work at the Water Turkey Bay Channel, the pipeline will be in place for disposal the north nearshore disposal area for the work at Wiggins Pass. Upon completion of this work, the selected Contractor may then mobilize to the South Marco Beach Restoration project site at the south end of Marco Island for completion of that work outside the sea turtle nesting season after November 1, 2019 and prior to April 15, 2020. Combining these projects with one selected Contractor should result in reduced Contractor mobilization costs than if constructed separately by different contractors. Additionally,costs for Engineering Services during the bid phase and pre-construction phase services when provided for the combined projects will result in cost savings to the County. Services provided by H&M will be Time and Materials. Page 1 of 4 F:\Collier\200-Wiggins-Pass\Contract\2019 Project\2019-Interim Dredging Wiggins Pass SOW.docx 1 Wiggins Pass Interim Dredging Engineering,Permitting,and Construction Phase Services Prepared by Humiston&Moore Engineers 5-03-2019 Task 1:Plans, Regulatory Coordination and Preparation of Technical Specifications, Bid Schedule and Opinion of Probable Costs Construction Plans and Agency Coordination: Engineer shall prepare updated construction plans and specifications for the interim dredging at Wiggins Pass based on available and any updated bathymetric and topographic data from the County. Pre and post construction surveys will be required by the Contractor prior to construction. Areas designated for dredging and redistribution are highlighted on the attached figure with this Scope of Work. Upon completion of the plans and acceptance by the County, Engineer will coordinate with County and Park staff and meet with state and federal agencies to initiate review. Following pre- application meetings, plans will be filed with both the State DEP and USACE for processing. Technical Specifications, Bid Schedule: Based on feedback from state and federal agencies, Engineer will prepare Technical Specifications and a bid schedule to be included with the county contract documents for bidding. Engineer will review permits for any additional clarity required in Technical Specifications for consideration of qualifications and multiple project coordination for bidding with County staff. It is expected that dredging within the navigation channel is to be done with a hydraulic dredge while redistribution of sand on the south shoreline at the Park may be conducted mechanically. As noted above, it is expected that this set of specifications will be coordinated with the Water Turkey Bay dredging project located just south of this project area east of the Park in north Collier County as a combined bid package. Technical specifications will require the selected Contractor to complete pre and post dredging and beach construction surveys. Opinion of Probable Costs(OPC).: Prepare a final opinion of probable construction costs based on the final design. This will include potential cost savings from combining this project with the Water Turkey Bay project. Development of opinion of probable construction costs will include review of county records for dredging at Wiggins Pass and recent costs for similar construction. Engineer will forward the final Opinion of Probable Costs with final construction plans and technical specifications to county for bid purposes. Deliverable: Plans,Technical Specifications, and OPC. Task 1 (TM) $21,726 Task 2 Bid Phase Services Pre-Bid Conference, Technical Support and Addenda to Bid Package: Engineer will coordinate with County staff in preparation of responses to inquiries from potential bidders and attend a pre-bid conference with representatives of county and prospective bidders and suppliers for this project combined with Water Turkey Bay Dredging and South Marco Beach Restoration.Engineer will prepare addenda to bid documents and responses to requests for information from Page 2 of 4 F:\Collier\200-Wiggins-Pass\Contract\2019 Project\2019-Interim Dredging Wiggins Pass SOW.docx Wiggins Pass Interim Dredging Engineering, Permitting,and Construction Phase Services Prepared by Humiston&Moore Engineers 5-03-2019 prospective Bidders at the request of the County on an as needed basis. Engineer will provide updated plans and technical specifications as needed during this process to support the Bid Phase for this project. Bid Qualification: Evaluate bidders' qualifications, contact references, and prepare a formal recommendation to County regarding awarding of the construction contract. Bid Phase services provided when combining projects for bidding will be adjusted accordingly to ensure no redundancy in services for reduced costs. Deliverable: Bid recommendation. Task 2(TM)$2,300 Task 3 Pre-Construction Services Pre-Construction Regulatory Requirements and Agency Meeting: Engineer will coordinate with Contractor and County staff in ensuring sufficiency of required items in Technical Specifications for fulfillment of pre-construction state and federal regulatory requirements for issuance of a Notice to Proceed. Engineer and County staff will conduct a pre-construction meeting with the state and federal agencies and their respective resource agencies to present the combined projects, intended performance, understanding of permit requirements, and schedule. The selected contractor will be present for this meeting. Engineer will provide required notices of commencement to respective state and federal agencies. Pre-construction phase services provided when combining projects for bidding will be further adjusted, if needed, to ensure no redundancy in services which will result in lower costs. Deliverable: Summaries of Meetings (state and federal) Task 3 (TM) $3,812 Task 4 Construction Observation Support Construction Observation Support: Engineer will provide updated plans utilizing pre-dredge, pre- disposal, and Park beach survey data to be collected by the Contractor. Engineer shall support the County with supplemental coordination and periodic site reviews with the Contractor throughout construction. County staff will be on-site daily, and Engineer shall support County staff on as-needed basis during construction and coordinate meetings with Contractor, County staff, and Park staff, as necessary, weekly throughout the construction project. Engineer shall review daily reports from Contractor and conduct construction observation services as necessary to assess construction performance in reference to technical specifications and regulatory compliance and provide reviews of contractor pay requests for the County. This will include: • Review of daily dredged tracking records and beach disposal. • Review progress surveys from Contractor, monitor production rates and review Contractor Pay Requests with County. • Periodic photos to document progress and daily coordination with County staff. Page 3 of 4 F:\Collier\200-Wiggins-Pass\Contract\2019 Project\2019-interim Dredging Wiggins Pass SOW.docx Wiggins Pass Interim Dredging Engineering, Permitting,and Construction Phase Services Prepared by Humiston&Moore Engineers 5-03-2019 • Submit turbidity reports from Contractor as required in state and federal permits. • Prepare as-built drawings based on progress surveys from Contractor. It is estimated that construction of this interim project will take 45 days, or less to complete. Post Protect Certifications: Upon nearing project completion, the Contractor, Engineer and County staff will review the project to determine if the Work is substantially complete and develop a punch list for the Contractor. Once the contractor addresses all of the items on the punch list and has provided sufficient survey data post dredge, post fill placement, and following sand redistribution at the Park along with related survey certifications,Engineer can recommend to the County that the project construction be deemed substantially complete so the contractor may demobilize, upon acceptance by the County. Upon completion of the project and review of post construction survey data provided by Contractor, H&M as Engineer of Record,will provide all necessary project certifications including beach profile surveys and post dredge as-built surveys to the County, DEP and USACE for project and permit compliance. Post construction report will include a summary of dredge tracking data and turbidity monitoring, and project certifications will include reference to a set of record as- built construction plans. Deliverable:As-built drawings and project certifications. Task 4 (TM) $19,140 Sincerely yours, HUMISTON & MOORE ENGINEERS C)(-17-7,,,,,,N.,/ .- i Brett D. Moore, P.E., D.CE. President Page 4 of 4 F:\Collier\200-Wiggins-Pass\Contract\2019 Project\2019-Interim Dredging Wiggins Pass SOW.docx i 1 South Marco Beach Project 5/6/2019 Prepared by Humiston Moore Engineers ./ . 1 ._ _—i.._--- _ / Date:M 3,2019 Wiggins Pass interim Dredging t ESTIMATE Tasks for En ineerig,Permit Coordination,Construction Phase H& _.__ i� _-- _ _ __ �_— H&M Services _ i 1-Plans.PermitCoord nation.Specs,Opinion of Costs TM 21 726.00 !Co ion Plans&Agency i Opinion riProbable Casats Coordination `_-- --- ;— —Y no ofl Probable Ca and Bid Schedule t --- 2-Bid Phase Services TM 2,300.00 I i Rerew bid package with County staff,Pre bid conference,_Adenda, Meetings ___iiBid Qualification _ r— f 3-Pre-C nstruction Services TM 3,812.00 Work Plan Details,Pm-Construction Conference 4-Con r ion Phase Services&Project Certification i i TM _19 140.00 Plan update Construction Obseation,com fiance review,pay review _ Post Construction Certifications i Total H&M ._ryTM __48.978.0Q/ i i • Summary Breakdown of Costs RATE/UNIT HOURS/0 i COST MARKUP AMOUNT_ Princi•le En.ineer 206, 661 13,596•00, — Senior Engineer 157 T 01 — 000'; Project Manager 147 o j 000! Engineer 1 123;/ 206! 25,338.077- Senior Designer _ 114±/ 0 0.00' Designer , 941 — 46--- ----- 4,324.001:. Senior Technician 85 8, 680.00 Inspector 1 t 76 40; 3,040.001 Technician 72 Oi 0.001_.. . - --- - --- _ III Gadd Technician } 81 0 0.001 Clerical/Administrative 62 0 .--.-..._ ,___- 0.000;— SDL_.-.—.. .._... -4--11 j 0 0 0.00` - EXPENSE!; -- , O. Q 1 fi Pro ect Total: 1 46.978.OQ ___ 1 F:\Collier1200-Wiggins-Pass\Contract\2019 Project\2019 Interim Dredging Wiggins Pass Engineering-Construction Phase Costs 1 of 1 SCHEDULE B RATE SCHEDULE Title Rate Principal $206.00 Senior Project Manager $172.00 Project Manager $147.00 Senior Engineer $157.00 Engineer $123.00 Senior Inspector $96.00 Inspector $76.00 Senior Planner $139.00 Planner $110.00 Senior Designer $114.00 Designer $94.00 Environmental Specialist $109.00 Senior Environmental Specialist $134.00 Scientist/Geologist $93.00 Senior Scientist/Geologist $118.00 Marine Biologist/Hydrogeologist $110.00 Senior Marine Biologist/Hydrogeologist $138.00 Senior GIS Specialist $139.00 GIS Specialist $102.00 Clerical/Administrative $62.00 Senior Technician $85.00 Technician $72.00 Surveyor and Mapper $120.00 CAD Technician $81.00 Survey Crew-2 man $130.00 Survey Crew-3 man $161.00 Survey Crew-4 man $189.00 Senior Architect $154.00 Architect $121.00 This list is not intended to be all inclusive. Hourly rates for other categories of professional, support and other services shall be mutually negotiated by Collier County and firm on a project by project basis as needed. B-1 _�