Agenda 05/26/2009 Item #16A 7 Agenda Item No. 16A7 May 26, 2009 Page 1 of 7 EXECUTIVE SUMMARY Recommendation to approve final acceptance of the water and sewer utility facilities for Heritage Bay, Phase 1 B-2 (Lion's Bay Court) OBJECTIVE: The Board of County Commissioners, Ex-Officio the Governing Board of the Collier County Water-Sewer District, to accept final and unconditional conveyance of these water and/or sewer facilities. CONSIDERATIONS: 1) The Developer of Heritage Bay, Phase 1 B-2 (Lion's Bay Court), has constructed the water and sewer facilities within dedicated easements to serve this development. See attached location map. 2) Preliminary acceptance of these utility facilities was approved by the Engineering and Environmental Services Department staff on April 9, 2007. At that time, the value of these utility facilities (assets) was $51,734.50 for the water facilities and $151,308 for the sewer facilities (see attachment[s]). This final acceptance is in accordance with Collier County Ordinance No. 2004-31, as amended. 3) Staff recorded all preliminary acceptance documents in the public records of Collier ,_ County, which have been reviewed and approved by the County Attorney's office as to form and legal sufficiency. 4) The water and sewer facilities have been operated and maintained by the Collier County Water-Sewer District during, not less than, the required one (1) year warranty period. 5) A final inspection to discover defects in materials and workmanship has been conducted by the Engineering and Environmental Services Department staff, and these facilities have been found to be satisfactory and acceptable. 6) The water utility infrastructure connected beyond the master meter is owned and maintained by the owner. 7) The PUD Monitoring staff has reviewed this request in relation to possible issues raised by the applicable Home Owners Association (HOA). Staff is unaware of any issues that would serve to negate the recommendation to release the applicable security. .- FISCAL IMPACT: Approval of this Executive Summary will have no specific financial impact. However, approval of this Executive Summary will result in the Collier County Water-Sewer District receiving unconditional title to the utility facilities, which at the time of preliminary acceptance, had a total (undepreciated) value of $203,042.50. GROWTH MANAGEMENT IMPACT: Approval of this Executive Summary will have no growth management impact. Agenda Item No, 16A7 May 26,2009 Page 2 of 7 LEGAL CONSIDERATIONS: The elements necessary to accept final and unconditional conveyance of these water and/or sewer facilities have been met. This item is not quasi-judicial and as such ex parte disclosure is not required. This item requires a majority vote only. There is no additional legal review from the County Attorney required to complete this final acceptance. - JAB RECOMMENDATION: That the Board of County Commissioners, Ex-Officio the Governing Board of the Collier County Water-Sewer District, authorize final acceptance of these water and sewer utility facilities for Heritage Bay, Phase 1 B-2 (Lion's Bay Court), and authorize the County Manager, or his designee, to release any Utilities Performance Security (UPS) to the Project Engineer or the Developer's designated agent. PREPARED BY: Jodi P. Hughes, Technician Item Number: Item Summary: Meeting Date: Page 10f2 Agenda Item No. 16A7 May 26, 2009 Page 3 of 7 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 16A7 Recommendation to approve final acceptance of the water and sewer utility facilities for Heritage Bay, Phase 1 B-2 (Lion's Bay Court). 5/26/20099:00:00 AM Prepared By Jodi Pannullo Community Development & Environmental Services Date Administrative Assistant CDES Engineering Services 5/12/20099:08:05 AM Approved By William D. Lorenz, Jr., P.E. Community Development & Environmental Services Date Environmental Services Director Environmental Services 5/12/200910:40 AM Approved By Judy Puig Community Development & Environmental Services Date Operations Analyst Community Development & Environmental Services Admin. 5/12/200911:11 AM Approved By Joseph K. Schmitt Community Development & Environmental Services Community Development & Environmental Services Adminstrator Date Community Development & Environmental Services Admin, 5/12/200911 :19 AM Date Approved By MaryAnn Devanas Community Development & Environmental Services Senior Planner CDES Engineering 5/12/20092:13 PM Approved By Stephen L. Nagy Public Utilities Date Wastewater Collections Manager WasteWater 5/13/20099:43 AM Approved By Date Pamela Libby Public Utilities Water Operations Manager Water 5/13/2009 11 :03 AM Date Approved By Paul Mattausch Public Utilities Water Director Water 5/13/200911:10 AM Date Approved By Phil E. Gramatges, P.E. Public Utilities Sr. Project Manager Public Utilities Planning and Project Management Department 5/13/20095:08 PM Date Approved By Jeff Klatzkow County Attorney file://C:\AgendaTest\Export\ 130-May%2026,%202009\16.%20CONSENT%20AGENDA \1... 5/20/2009 Page 20f2 Agenda Item No. 16A7 May 26,2009 Page 4 of 7 County Attorney County Attorney Office 5/14/20094:46 PM Approved By OMB Coordinator County Manager's Office OMB Coordinator Date Office of Management & Budget 5/15/20094:36 PM Approved By G. George Yilmaz Public Utilities WasteWater Director Date WasteWater 5/15/20095:03 PM Approved By Randy Greenwald County Manager's Office ManagemenUBudget Analyst Office of Management & Budget Date 5/15/20095:13 PM Approved By Winona W. Stone Assistant to the County Manger Date Board of County Commissioners County Manager's Office 5/18/20091:21 PM file://C:\AgendaTest\Export\ 130-May%2026, %202009\16. %20CONSENT%20AGENDA \ 1... 5/20/2009 I'--Q)f'-. ~go 'II.{) 0'w ZN g' >= iU'D.. 22 ro Ll c w en <( d i OWI\3lr1Cl8 ",Yfl ~J.~)" :>SOU"" / .... - z- ! N m '" i:I E 5~ ~~ ~l r ::: .. N N ~ ~~~ ~ " t d ~; ~ ^~NnO) 331 ~ ::' :!l ~ ~. ~ ~~ ~ i U i " :: N~~ i ~ ~ . O! ~~ ~" ~; ~ i~ <tl tD (j) ~c: o ~ .~ ~ ~I :r:" e :COpy e Agenda Item No. 16A7 May 26, 2009 Page 6 of 7 CERTIFICATION OF CONTRIBUTORY ASSETS- COUNTY PROJECT NAME: Heritage Bey Phase 1 B (Uon's Bay Court) LOCATION: Section 23. Township 48 South. Range 26 East Collier County. Florida OWNER: Bayvest, LLC 10492 Six MUe Cypress Parkway Fort Myers, FL 35912 TYPE OF UTILITY SYSTEM: POTABLE WATER ITEM sIZe UNIT # UNIT Unit Price TOTAL 10" PVC CL150 Water Main 10" LF 2230 $ 16.15 $37,352.50 10. FtVC CL200 Water Main 10. LF 92 $ 17.25 $1.587.00 10. Gate Valve 10" EA 3 $ 800.00 $2,400.00 Perm. Sample Point 10" EA 1 $ 775.00 $775.00 Sinale Wate!' Service 1" EA 5 $ 520.00 $2.600.00 Double Water Service 1" EA 13 $ 540.00 $7 ,020.00 TOTAL COST $51,734.50 I do hereby certify that the quantities of materIal described above are a true and accurate I'9presentation of the as-installed cost of the system being contnbuted. CERTIFYING: ~/ OF: MItchell & stark Construction Co. fnc. 6001 Shirley Street Naples. FL 34109 STATE OF FLORIDA ) )ss: COUNTY OF COUIER ) The for strument was signed and acknowledged before me this _9th_ day of _June_, an Penner 0 Is personally known to me and who did not take an oath. SEAL: RIJll8SU..H. DE .IONOI m M'( CQIAlIIISION' 001S8117 . - ~AuIUIl11,201O 1IalIM'1lW-,..~ _.11III1OYr....A/IOl.l.AIlO c:AlNS __ .ElIBII.I_ e e Agenda Item No. 16A7 May 26, 2009 Page 7 of 7 .rr-<:>OPV' ,~ N ',' , ~~ '\.'._ >, ,I " CERTIFICATION OF CONTRIBUTORY ASSETS.. COUNTY PROJECT NAME: Heritage Bay Phase 1 B (Lion's Bay Court) LOCATION: Section 23. Townshlp 48 South, Range 26 East Collier County. Florida OWNER: Bayvest, LLC 10492 Six Mile Cypress Parkway Fort Myers. Fl 35912 TYPE OF UTILITY SYSTEM: SANITARY SEWER ITEM SIZE UNfT # UNIT U nit Price TOTAL 4" '0\'''' '''''150 Force Main 4" LF 600 3.75 $2,250.00 4" PVC CL200 Force Main 4" LF 46 4.25 5195.50 !r' PVC G 0'_6' cut au LF 492 7.50 13.690.00 8" PVC G ewer '6'--8' cut 8" l..F 306 7.50 -~,~95.00 8"P CGre.. I sewer 8'.10' cut\ 8" LF 797 7.50 $5,971.50 8" P' CGravi ' Sewer 10'.12' out) 8" LF 424 7.50 ,180.00 Man ~Ie Q'-E cut) 4' EA 3 $ 1,700.00 ,100.00 Manhole S'.8' cut) 4' EA 2 $ 3.400.00 ,800.00 Manhole 8'-10' cut)' 4' 'EA 3 3,800.00 $1 1 ,40lJ.OO Manhole 10'.12' cut) 4' EA 1 4,800.00 $4,800,00 Uft Station 8' EA 1 96.500.00 $9 6,500.00 Slnole SanitBrv Sewer Lateral 6" EA 12 $ 400.00 $4.800.00 Double Sanibary' Sewer L.ateral 6" EA 9 $ 480.00 $4,320.00 TOTAL COST $151,308.00 I do hereby certtfy that the quantities of material described above are a true and accurate representation of the as-installed cost of the system being contributed. CERTIFYING: ~k- rian Penner OF: Mitchell & Stark Conswction Co. Inc. 6001 Shlrtey Street Naples, Fl 34109 STATE OF FLORIDA ) )88: COUNTY OF COLLIER ) The . instrument was signed and acknowledged before me this 9th_ day of _June_. 20 rian Pen who is personally known to me and who did not take an oath. SEAL: RlJ56&H. afoKlNEIE tit COI6ISSION. DO 53t111 . z ElCPIflEB: AlOS 11. 2010 IIoIIdIIcIlJIIII""'PlIIlIic>~ _.1_0~""lllllUlHIl CAIU _-.001'_'_