Agenda 02/10/2009 Item #16E 7 Agenda Item ~jo. 16E7 February 10. 2009 Page 1 of 28 EXECUTIVE SUMMARY Report and Ratify Staff-Approved Change Orders and Changes to Work Orders to Board- Approved Contracts. OBJECTIVE: To enable the Board to oversee the execution of administrative change orders and changes to work orders, and promote accountability in the use of staff authority. CONSIDERATIONS: On April 22, 2003, the Board approved a recommendation to implement a plan to enable changes to BCC-approved contracts (Section XIV. C, Collier County Purchasing Policy) of not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff. Also included in the report are changes to Work Orders. These include work orders issued under CCNA Contracts which are less than or equal to $200,000 (Section VII.C, Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XIV. G, Collier County Purchasing Policy) which are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater). The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above. - The plan calls for staff to submit a monthly report listing these change orders from the previous reporting period. Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders. These reports cover period December 15, 2008 through January 16, 2009. FISCAL IMPACT: The total change to contracts is $67,435.70. The total change to work orders is $90.561.40. GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action. RECOMMENDATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders Report and Administrative Changes to Work Orders Report and ratifies the listed change orders and changes to work orders PREPARED BY: Diana De Leon, Contract Technician, Purchasing Department .-- Page I of 1 Agenda Item No. 16E7 February 10,2009 Page 2 of 28 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: 16E7 Item Summary: Report and Ratify Staff-Approved Change Orders and Changes to Work Orders to Board- Approved Contracts. Meeting Date: 2/10/20099.0000 AM Prepared By Diana Deleon Administrative Assistant D<'Ite Administrative Services Purchasing 1/26/20093:31:17 PM Appro\-'cd By Steve Carnell Administrative Services Purchasing/General Svcs Director Purchasing Date 1i26!20Q9 3:37 PM Appro'\-'ed By Len Golden Price Administrative Services Administrator Date Administrative Services Administrative Services Admin. 1127/2009 1 :57 PM Appro\'ed B)' Jeff Klatzkow Assistant County Attorney Date County Attorney County Attorney Office 1/27/20094:53 PM Approved By OMB Coordinator OMS Coordinator Date County Manager's Office Office of Management & Budget 1/28/200910:56 AM Approved By Laura Dav!sson Management & 3udget Analyst Date County Manager's Office Office of Management & Budget 1;30/200911 :04 AM Appnn,'ed By James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 1/31/20092:49 PM file:l/C:\AgendaTest\Export\ 123-Februarv%20 1 0.%202009\ 16.%20CONSENT%20AGEND... 2/4/2009 ~g~ ~~o-"5l ,iocA~eg :i-i~c.o ~ 2:'~~ ii ~ iV(1J~o8"" ~::;; ~ 00 (1)Js 10 Q) . c: LL Q) CD Q) en!:: "- OJ !:: III Cl <( ~G"E U.O ~~ "5l u g !II ~ 0 ":; 'E E ~8: " . " , g'~ D . " E ~o'" u * . " o "- w ~ ~ w o ~ o w ~ z ~ 13 w > C ~ ~ . ~ ~ , o < "0 . > " !:: e ::l ~ C. D ::l ii ~ (.)8.... "' !:: U g ~ !!! 0 :s ~ ~ uu* ~ - . . C !:: U > ::l 'a' u e DE ';::00 c. o c.'" "'* " E u.!!! ~~E c. c . . 0 c. CU<n 0: 0: Zz Q) 'E i lJ) E !!! "'C E ~~gc5~ oug~u "'0 III .b :: lJ) a;"e- 5 ~.e >o.uuo. w . " E 0 ~z '" ::; ~ c w m <0 o ~ " w ~ cc 7) ()) 8 ~ .;, o o <0 m ~ ~. o w ~ o o o m ~ " o w ~ o o <0 m ~ " o w ~ " UU We: f- u E " Q U ~ c o U w " ro :?: -'= <n.....CO~-e ~ M Q> CV 38if:u-g ~55gst5~ 8 o ::a N ^ . m " cD " ;;; . U . "- W " ii " ~ C ro , ~ c ro D. ro 03 > o " c Q U o u ~ -" ~ ~ '" ^ o u " c Q U , ~ ~ U !'! ~ o f- 0; '" c ro ~ u '0 . . ., 0; > o ro ~ ~ o o <0 o ~. ro M ~ u . ~;,; ^" ~~ ro CL . " 03 w "~ ro ~ UZ ro o " N N '" "., 'f (~ C:) oc. o o o o '3 "i M '" ~ ::, :j ;~ 'fJ o o <0 o ~. :;; ~ ~ o o Q tn. ~ u ro ~ . C '> iil~ - "- ~2' N~&~ ~ 2' (lJ E if m g E gsu~8 0' ~ ro o '" ~ ro o ro N " m N :::' ro N ~ ~ ~ " ro w ci N ~ ~ ~ .,; o W. ~ ro N * ~ ~ '" o "' ~ ro N ~ u 1': c o u E g U , ~ W U ~ c ro o ;'ji ~ u ro n W u u ~ '0 o o :;; ~ " :;; N ~ " UU We: f- u ro o ~ ~ U o E E m I . ~ '" ro M (lJ _ :5 g ~ g> ~ lfl MCll~ ~55~6~ OJ o . . " "' ~ o f- ~ " 0; '" C . ~ U o . . E . > o ro o 03 N ~ 0' W v m cf' ~ ro o ~ W :; w. !;; ~ '" ~ ~ ro ~ ~ 00 '" u . 0- " . E . ill D. E o u -" U ~ C o u . E -" . . U ~ . ^ o o <0 o o ci ro ro '" N ci v ~. v ~ ~ o o o o o ci ro w ~ w <e. c Q U . ~ " w"- 0>0 CL ~ c ro ~ W . c '0, c w c Q ~ C . > n " lfl Cll C S ...J CV 01 0:: C'\I 0.. E l~ ~ ~~ g; :ii5~~0::~ cii286~.s m " 'S " o U :g OJ o f- 0; '" c ro ~ u '0 . . E . > o ro o CO N N v ,0 " N ~ m '" :, N a 0; " U 2 " . E w " ~ o E E o u u ro -" " rn c U c , Q " . '" ~ " . ~ ~ o E 52 ~ c ro ~ u ill ~ " '" c ~ . c 0, c . ~ w . " . -" '" c U " u u ro . " U 2 " "' . " '" c '0 $> c ~ ro U 2 ~ o u o f- ~ w " w ~. m ~ ~ '" o o w w ~. ;;; o o a o o ci ro "' ~ ~ "' :; w " v ~ '" o o <0 o o ci ro "' ~ C WCL 0>0 "- c o :ffi c . > n . ~ j ~ 01 0:: M 0.. E :f~~~~g; . m ~ t: 0:: 2 zo'~on cii28oz.s 0; '" c ro ~ u '0 . . E . > o w o N N N ~ E , ~ . D. o , ^ '0 w N " ." . u c w W " ~ -" . , u W '0 c ro ~ OJ ~ o n ro ~ :c '" . "' u .Q ~ o f- 0; '" c ro ~ u '0 . . '~ . > o "... en r:tJ l80N :;10,0....... '0 ~N 01: Gl .~ Ill> c ~i~[s ~ >>,,;;nu fi E E"-~Euc:( 2~g..gu~ -;;.0 CO 10 '" . eLL Gl CI Q) C>>C... O:l lij l'lIlll <( "'u t5"E .0 ~~ "C U c: ~: 5 .; c: E . 0 '" "'u~ ~ ~ 3 ~"E ~ "'0" u ~ . " o , w ~ ~ w o ~ o .,.....J) "" . ce~ l!:! c. 0 ~ fi ~ u8~ '" "Eue Ql: 2: :: c E , 0" Uu~ u w > ~ ~ . ~ z ~ o < ~ ]c c::: U > ::l .0, u e e 5 III ~<( "'~ 'E E f..).~ t::em <<I_V 0. C . . 0 0. cu", ci ci Zz 'E E I'll .g ~ III c:i l5 0" ii ZZ<:l Z 15 ti t& ~ti "C <P ~ c: <1) a; E ~ ~ 2' >l1.uua.. .'!l . c E 0 ~z '" '" '" 6 cf' '" '" 6 '" '" ro :;; ro N ~ '" '" 6 ~ '" z '" '" ro ~ ai N ~ '" '" ro ~ ai N ~ u . 0:0 ",c .~ "'", . CL .2 . o ~ c C . , c o ."l u c ~ ~ " . u ~ ~ '0 ~ ~ J.:: C U g::;~~c l-zzoj ro '" a; N co ro . ~ m CL '" '" '" 6 '" '" '" 6 '" '" 6 '" "'. " N ~ '" '" 6 ~ '" '" 6 '" '" o '" N ~ '" '" 6 '" '" o ~ N ~ '" '" 6 '" '" o '" N ~ c . E . ~ ry '" . E '0 N ~ C . "' oo1l~(j ~~ ~ ~ ~ ~ I ' I . '" 0. . rn . m u .i' ~ '0 o f- ~ ci. ~~ 8 g~ en ga5 ~ ~(!) :J t-- co ~ ~ ~5 ~(O'7""~~ a.9()Q)I~ 06~~~.g ~~~B~~ 0; '" c ro '" u ~ o ~ . E . > o ro e '" co ~ J' :; ,,; J' '" '" N M ~ ~ ro ~ '" ;;; '" '" ,,; ~ '" N N ~ M ~ rn ~ o ro "'. ;;; " w , . ~ m C . E c e ., c . ~ c . '" c B E W u . , e . E o c " w o ~ c o ~ c 11 . . E ~ M ~ '" '" '" 0; N ;;; '" '" 6 '" '" 6 D '" ~ . ~s: g~ "- '" c o E g " ro "- ill ~."l N"- od N (\) tIl >-Cl) N Oltt: ~ c:> ~ c 'C:: "'o,~~ O~~O(/) . ."l . " o . . '" e x ~ . . ~ ., o a. o f- 0; '" c . '" o '0 ~ . E . > o m D "' e ro .; '3 ~ . '" u . c o 'B 2 '" c o u ~ w ~ c ."l x . . E E " " o c o o " . . u " . . '" c ~ . c 0, c . ~ . m @ ~ c . m " t5 ."l .c u m ~ c w X . o f- 0; '" c . '" u ~ o ~ . E . > o '" D D 6 '" D D 6 D D 6 D '" on ;;; D D D ~ D D 6 D D N '" ;;; D D 6 D D N '" ;;; D D 0; D D N m ;;; . ~s: g~ "- c o ~ " u " U '" c " , o I . . N C ~ '<T '7 ..... Ql 5:;'7 g ~~ U g , C "T QlO;;jgo CooIDuRl '" D Oi e co '" ro D 9 '" c :0 '" ~ . c . ." ro " J' ~ M '" '" co 6 M ro ,,; D N ~ in o ;;; D D '" ~ "'. ;;; " c . E c e > c w ~ c . '" c B E 0; ~ " ~ ."l . ~ . ~ ro OJ ~ . , e . E , c " . , u . '" c o E S . . 5 ~ ~ . E ~ D D oi ro N 6 '" N o ;;; M ro '" ro ai rn ~ 6 ;;; D D oi ro N o '" N 6 ;;; . ~s: g:5 "- c Q t5 2 '" c o U ~ . ro 13 ~ c o u u c ~ . o f- " '0 . ~ u .6 'l"):;~ OJ Q) N ~ Oltt: ,r; -gg"'1jij~:g roN<.o,C..c:J > Ll)OUCf.lC!l 0; '" c . '" o o ~ . E . > o m D Q; e S' . c Q m W "- o ct w c ~ c o n ."l ~ m C . E c e > c w '0 C . E ,,- ro "- . C ro ~ "g 0: . E E " . u c , C. E o o c . '" ~ " c ro 0: c o ~ . > . 0: c .Q ;5 " CL w m . E " in '" c jj " . . E " . . '" c . '" o . ~ '5O o 0. o f- 0; '" c . '" o o ~ . E . > o r'--O)Q'J t20N ,~"'~ ~N o'Ei !;'ci..&~>c ~.-i5~S ~ >>~() Q. E ;::l....'l'tiECllc( w~~e8Uj. ..... -' ....00 ;~ 10 Q) . eLL Q) C) .~ g'~1lI <{ lJ:-o u~o ~;S "0 l,) C 511 g .;: c: E (I> 0.;:( a:()~ . " c C) ell 2: ~ "E E ~o'" () ~ . ~ o , w ~ ~ w o ~ o w ~ z < I " W > ~ < " ~ ~ ~ " o < ~ . c e g l!.' c. 0 ~ g. ~ ugu. CO cue ~ ~ is - c E , 0'" uu~ " cu .iiu ';:OJ o ~- . c > ' o 0 " E ~'" "'~ c E u .!!2 t ~ iii: 1Il.....i3 ~ c . .00. cu", ci 0 Zz C " Q) 1Il Q) Q) E ... '0 E ~~gc5~ <5 I,) ~ ~ ti '0 (1),):; c: Q) a; .e- g ~.e- >a.uua. w 1i c E 0 ~z ~ ~ :? o o "' o N a5 ~ ~ ~ is " '/') o N a5 ro .., ~ ~ o N "' ro M. ~ ~ o N m ro .., ~ ~ "u "n: ~ c ." ro u " ~ o j NO :s -50;;; ~z ~ E~~~:rE ~~g:jG~8 <'5 :::J ;:: w u 5 o '" W ro 3< ; .~J ~ M o <3 M ro m ~ ~ :;of M M M '" o o .. m ~ a5 ~ ~ ro <3 ~ N N M .,. M ~ c g u , ~ . ~ ro S ~ .. '5 " ~ ~ u E . U .. E u " o ~ "V, w ~ l' . W o . o ~ n ~ . '" o o ~ ~ " . ~ o ro ~ o C o c . 0. " o f- M ro cO ro M .,. ~ M M M ~ o o cO o ~ M M ~ a5 M '" " . ,:go un: ro ~ " " 0. E o U w c o U . o 0 o .> 15 W 2 '" iil I'-. >- 25 0>.... g 000 ~~ ~;~~~ ~C!")O()l1J ;,; ~ c ~ U o o '" o . o .~ o > o N i: l' ~ ~ u ro a. ~ ~ ~~ c 0 o 0 2..r:::. " w o ~ . - o~ Cl .~ 00. - 0 " 0 o " U ~ l!!"E 00 . 0 ~ () " ~ Iii o U 0 IlJ ~ <00 iii o Q ~ ,,~ u'" ro ~ n ~:c <; g' ~2 . 0 -5i ~ E <11 2"* o " f- 0 o Qj U ~~ ~ . u 0 '01;- . u . . .E "@ ~ g. o ~ cf' o ~ ro " ro " o g o o o o -" E .2 E o e .2 .0 0" m M ~ ~ N cO o M " ~ ~ o g o o E ro " N ID o " ~ u o ro " o g ro u g o 1; 1i " . g o o o ~ m Z;; ~ " ;;; o N :e ~ m ro M '" o m o ~ C" ~. o ~ ~ o N m ~ ~ m ro M w " ()u wn: f- " " 0 o u " 0 .g, Q. ~ ~ ~....;!~~ -:= 0,..., ~ w ~ ~ ~ rn ~ ogzgD~ m o co M o m " '" c . " c ~ ~ E '" ~ o ro i=' o o "'- c g " " o " o ro += ol? o.~ . " c c ro w "2 g ~= o S o ;: E . " ~ . u 0_ o 0 (/j c ~ , u 0 3 E " ro ~~ ro _ o u ~-5 o . . ~ gg =g~ . . ~ :>, (j, "'rD ~~ . 0 " .;:: ill ~ t3 Q ~ -6-g ~ ro ro 0 . 0 ~ ~ > 0 2 ai o ~ ~ o .. Q ~.9 ~ ~ ~ c OJ' o . ~ g ":; ~ w > u o ~ ~ o " ~ u ro g " ;, 5 ;{ c ~ U '" " ;g .is m o " " cf' o o <3 cf' o o <3 ;;; ~ o <3 ~ '" o o <3 '" ;;; ;: o <3 ~ w ;;; ~ o <3 ~ '" ;;; ~ o <3 ~ ~ "u "n: iii u o U . ill " u c o E E us cD", wz m S :c c "'0 ...J:;::; ..'" -2~ m.E . 0 > 0 .'= co o ~ Ou 8 & 0 fii ~@~~ ~8~@ o o " ;! '" ~ m m cf' M o "' ~ N " ~ o m m M '" o o m N cO N '" iii ~ ro E m c a. ro o " ~ c .'" '0 . m o ro ~ o . :0 ~ " o o ~ c ro " . o o :c g '0 co . e <0 u S ~ m -ci.i u g . o ~ . ~ ro c o ~ " u ro o ~ > o 6. o f- ~ N M m ~ .; ~ M '" ~ N ill ro '" m M w ~ N M m ~ .,. ~ M ~ w m 'u E '" o Ui :0 " to o . Z E Iii ~ ill C E; <lJ .E a. ~ ~ E ~ ~]j C Vl ell W w' . E -0 N ~ B J: f?j g;,ii (I) ~"<J"~~~~ 8;;;gg6&:~ ;,; ~ c ~ u '0 . o .~ o > o o o <is :" o ~ co M ~ " m '" u . c o u ~ o . " o g ~ c ro <0 " . ~ u '0 . ~ . " . . ~ o ro " ro . '0 m o .n ~ 2 m ~ c ro m o .~ o <J .; o c J' u o ro o o "" c > '" o . ~ ro o ~ ~ ro o f- " o ro C o ,~ g . w m ~ :; ~ ,:: ;,; '" c ro " o '0 . o .~ o > o II"'" Aaenda \tem No. 16E? ~ February 10, 2009 r)age 6 of 28 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Vanderbilt Drive Pedestrian Bridges PROJECT #: 600331 PROJECT MANAGER: Jim Zuver BID/RFP#: ~MOD#:~ PO#: 4500091768 WORKOROER#: DEPARTMENT: TECM CONTRACTORfFIRM NAME: Thomas Marine Construction, Inc, Original Contract Amount: $ 607.790.00 (Starting Point) Current Bee Approved Amount: $ 607,790.00 (last Total Amount Approved by the BCC) Current Contract Amount: S 607.790.00 (Including All Changes Prior To This ModJfication) Change Amount: $ 14.489.04) Revised ContracUWork Order Amount; $ 603.300.96 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ (4.489.04) Date ofLast BCC Approval 1-15.08 Agenda Item # Percentage of the change over/under current contract amount_~ Formula: (Revised Amount! Last Bee approved amount).1 1663 % CURRENT COMPLETION DATE (5): ORIGINAL: December 2,2008 CURRENT: December 2. 2008 Describe the change(s): There were chanqes to the helical piles, addition of stone for under the pedestrian bridqes. and addition of picket tvpe raillnq to the project. However. due to reductions in overall plan quantities, there was a net overall reduction in costs. Please see the Chance Order No.1 Supplemental Information for details. Specify the reasons for the change(s) 0 1. Planned or Elective r 2. Unforeseen Conditions II 3. Quantity Adjustments C 4. Correction of Errors (Plans, Specifications or Scope of Work) e 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The FOOT criteria for handrail would not have been met due to the drop off. In addition, this chanqe will be a net reduction in the contract. This change was requested by: G Contractor/Consultant . Owner r Using Department (' CDES t) Design Professional r Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTiATIONS: r ., -c-/N res "rJX..... 0 This form is to be signed and dated, APPROVED BY:..'/' ~~ ttv~<c.--- REVIEWED By:V'~:.::J<..--6~" on ract Specialist U Date: /7-/lei/C"?," ---- I / I ~/t~/Of5 D&\-1 ~ 17..//.,[" 'l< / Ic,o- \'1- IC"! './ Date: Revised 11.19.2007 ~ :13:11 No. -:6E7 February 10, 2009 ('- Page 7 of 23 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Fence Reoalr PROJECT It. _PROJECT MANAGER: Vickv Ahmlld BIDlRFP II: D8-S062 MODI#: 1 PO#:_ 4500101951 WORK ORDER I#: DEPARTMENT: Parks & Recreation CONTRACTORIFIRM NAME: Carter Fence OrIginal Contract Amount: Current BeC Approved Amount: $ _381,500.00 (Starting Point) $_381.500.00 (Last Total Amount Approved by the BCC) $_381,500.00 (Including All Changes Prior To This Modifiealion) Current Contract Amount: Change Amount Revioed ContractlWork Order Amount: $_(32,500.00) $ 349,000.00 (including This Change Order) eumulatlve Dollar Value of Changes to this CoI1\r~ort\ Order: $_32,000.00 Date of last BCC APfWoval_7.Z2.r;.[ Agend.ltem# _16012 Percentage of the change over/under current completion dale _ (8.~ % Formula: (Revised Amount / Last BCC approved amount)-l CURRENT COMPLETION DATE (S): ORIGINAL: March 4, 2009 CURRENT: March 4. 2009 Describe the change(s): Deduct restock and repair of backstop for Vinevards Community Pari<. Specify the reasons for the change(s) C i. Planned or Elective { 2. Unforeseen Conditions x 3. Quantity Mjustmeots,' 4, C;:orre~i'>r! of I;rrors (Plans, Specification. or Scope of Worl<) ," $. VIIl\le Ad(led 6. Schedule Adjustments Note: One or more may be cheeked, depending on the nature Of the change(s). Identify all _negative !mpacts to the project if this change order were not processed: LllilltiAII feA". a+ ~ baC''',*,Du...19tava~13. ~U/V7Y ?<,)oU1d ;Ja..y mo,e& THHN jlJECES"JA '-.Y Ie) r!-(}!lI fl/..&rc rHc PI:(tJJt3"d;T This change was requested by: X Contractor/Consultant Owner ,., Using Department r CDES Coesign Professional Regulatory Agency (Specify) X Other (Specify) Purchaslno CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: Yes XNo I I I This fonn is to be signed and elated. ~} , /' (' A APPROVED BY: Vi m d' Project Ma~nager I ' REVIEWED BY: Lvn Wood M))1 iJ /'07/( Contract S ~ /7 , Date: /c2;;j;b? / 1~7/Q!? Date: . CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM !\.,-pn___1a Il.;:.,"n 1"0 ~I.;:::;:::~I ""J ,0~1"....l Il_ll \j "v~ 1 A. =~h"'aIfYJOO~ 2 o0:1~n.'9 - [!L~~~8 ...~ RECflVED 111 fc9/I? joY PROJECT NAME: Rattlesnake Hammock Road PROJECT #: 60169 PROJECT MANAGER: James Zuver BIDIRFP #: 05-3583 MOD #: 5 (five) DEPARTMENT: TEeM PO#: 4500101437 WORK ORDER #: CONTRACTORlFIRM NAME: Wilson Miller Original Contract Amount: $ 2.517.581.00 (Starting Poinl) $ 2.851.609.53 (Last Total Amount Approved by the Bee) Current Bce Approved Amount: Current Contract Amount: $ 2.851.609.53 (Including All Changes Prior To This Modification) Change Amount: $ 23.684.75 $ 2.875294.28 (Including This Change Order) Revised ContractIWork Order Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ 357.713.28 Date of Last Bee Approval 9f14/2005 Agenda Item # 10B Percentage of the change over/under current contract amount 83 % Formula: (Revised Amount I Last Bce approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: 02113/08 CURRENT: 12/31/08 Describe the change(s): To add $23,684.75 to the CEI Support Services contract. The original construction contract has been extended thirty three (35) additional days via change orders. The anticipated final acceptance date is January 9th 2009 which is over the allowable construction days. This totals an additional 381 construction days from the allowable construction completion date and therefore an additional 78 days for CEI Services are required to provide eEl services until 12/31108. $23,684.75 is an estimated amount needed to continue eEl Services for 322 days, from the original CEl completion date of 02113/08, through a projected complction dale of 12/31108. Specify the reasons for the change(s) r L Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added (;" 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: terminated on this Droiect due to lack of fundino. GEl Services would be This change was requested by: rlContractor/Consultant PI Owner II Using Department C COES CDesign Professional rJRegulatory Agency (Specify) I Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: Ry es IN o This form is to be signed and dated. Revised 11.19.2007 Date /J-.//rO~ o "., :411~i CONTRACTfWORK ORDER MODIFICATION CHECKLIST FORM ,L\aenca Ittim No" 1GE? ~" February 10. 2009 Page 9 of 28 ., PROJECT NAME: NCRWTP Lab Ventilation ImDrovements PROJECT #: 700952 PROJECT MANAGER: Tom Chmelik BID/RFP #: 06-3946R MOD #: 2 PO#: 4500079831 WORK ORDER #: NA DEPARTMENT: PUED CONTRACTOR/FIRM NAME: D.N. Hiaains. lnc, Original Contract Amount: $ 683.000.00 (Starting Point) .:xr.. (f/c/ ;"1.143.1~ /'1?,~ (Jf70.001Y" (Last Total Amount Approved by the BCC) Current BGe Approved Amount: $ Current Contract Amount: $ 741.143.12 (Including All Changes Prior To This Modification) Change Amount: $ 6.458.55 Revised ContractIWork Order Amount: $ 747,601.67 (Including This Change Order) Cumulative Dollar Value of Changes t!rD this ContractIWork Order: $ 64.601.67 ~ t'l _ it!. ~;{,/ Date of Last BCC Approval 3/13/07 Agenda Item # 16.C.3 % over rg-i/ Percentage of the change over/under current contract amount '1 ~ <HfT Formula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 2/1/08 CURRENT: 1/1/09 Describe the change(s): Add a reinforcing steel structure according to TLC Engineering sketch SSK-1, and required modifications to existing surroundings. SpeCify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) ~ 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: If this change were not carried out, permitting would be in jeopardy. and a potentially unsafe condition would result. This change was requested by: ~ontractor/Consultant r! Owner r! Using Department C CDES CDesign Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes ~ No APPROVED BY: Date: ~/$- \zfnjCf?, /CA/d.2/0'l I / I ! , I Date: REVIEWED B1'\. Date: Revised 2-22-08 ,-----"- CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM Agenda item ~..Jo" 16E7 February 10, 2009 Page 10 of 28 PROJECT NAME: NCRWTP Lab Ventilation Improvements PROJECT #: 700952 PROJECT MANAGER: Tom Chmelik BID/RFP #: 06.3946R MOD #: 3 PO#: 4500079831 WORK ORDER #: NA DEPARTMENT: PUED CONTRACTOR/FIRM NAME: D_N. Hiaains Inc. Original Contract Amount: $ 683.000.00 (Starting Point) Current BCC Approved Amount: $ HI8!U7 c,R.'3i ()()().D" 11;1/ (Last Total Amount Approved by the BCC) Current Contract Amount: $ 747 .601.67 (Including All Changes Prior To This Modification) Change Amount: $ 1.766.00 Revised ContractlWork Order Amount: $ 749.367.67 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractlWork Order: $ 66.367.67 Ii ~ Date of Last BCC Approval 3/13/07 Agenda Item # 16.C.3 Percentage of the change over/under current contract amount Of, 7~ % over ~/ Formula: (Revised Amount I Last BCC approved amount).1 CURRENT COMPLETION DATE (S): ORIGINAL: 2/1/08 CURRENT: 1/1/09 Describe the change(s): Relocate lighting above air handler. Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) X 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: If this change were not carried out, permitting would be in jeopardy, and a potentially unsafe condition wouid result. This change was requested by: )lliJ,contractor/Consultant rI Owner rI Using Department r CDES r Design Professional r1Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r rv Yes )f' No Date: 0(1 APPROVED B Date: \-z.!z ?)O <f, REVIEWED B'\(' Date: Ia!a~/of Revised 2-22-08 /~\aend3 Item N'J. 16E7 ( ~ February 10, 2009 I./' Page 11 of 28 CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Landscape Maintenance for Parks PROJECT #: BID/RFP #: N/A MOD#: PO#:_45.102414 PROJECT MANAGER:_Kerry Runyon_ WORK ORDER #: DEPARTMENT:_Parks & Rec CONTRACTOR/FIRM NAME: Tech of Collier County, Inc. ~ri9inal Contract Amount: I Current BCC Approved Amount $_N/A (Last Total Amount Approved by the BCG) I $ _28,518.00 (Starting Point) Current Contract Amount: $_28,518.00 (Including ""'11 Changes Prior To This Modification) Change Amount: $_-0. $_28,518.00 (Including This Change Order) Revised ContractIWork Order Amount: Cumulative Dollar Value of Changes to this Contract'Work Order: $ -n"- Date of Last Bee Approval_N/A Agenda Item # Percentage of the change over/under current contract amount_O Formula: (Revised Amount I Last BCC approved amount)-l % CURRENT COMPLETION DATE (S): ORIGINAL: 9/30109 CURRENT: 9/30/09 Describe the change(s):_ To clarify paragraphs 1 and 2 of the Agreement Specify the reasons for the changers) x 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction Df ErrDrs (Plans. SpecificatiDns Dr SCDpe Df Work) r 5. Value Added r 6. Schedule Adjustments NDte: One Dr mDre may be checked, depending Dn the nature Dfthe change(s). Identify all negative impacts tD the project if this change Drder were nDt prDcessed: _Tech invoices would not be processed. This change was requested by: rlContractDr/CDnsultant x Owner rI Using Department C CDES CDesign Professional rJRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: x Yes r ND APPROVED BY: This fDrm is to be signed and datecY. ,',,/ ' ,,..-- Date: REVIEWED BY: Date: , v 'V\. I' Revised 2-22.08 L Agen::.la Item No. ~i 6E.? February :0.2009. Page 12 of 28-1 CHANGE ORDER CHANGE ORDER NO. CONTRACT NO. N/A BCC Ost.: - N/~ Agenda llam: N/A_ TO: " Tech ofColllerCountv, Inc. 39B4 ArnBfd Avenue Naolas. FL 34104 OATE: December 11. 2008 PROJECT NAME: landsCBofno Maintenance ServIces Under our AGREEMENT daled _October 1 .200S. You hereby are aulholizeci and dlre<:led to make the followlng chango(s) In accordance w\th teons and oondlUons of the Agr&8msnt: To dartfy paragraphs 1 and 2 of Ale AgraemeoL Worda &truck. through have been deleted Bnd warda underlined have been addac:l. 1. The COUNTY hereby engages the CONTRACTOR and the CONTRACTOR hereby agrees to perform l&lndacapa maintenance !wee! employln.g a maximum or f!v& (5) CONTRACTOR'S workers: ~for a mlnimum of three and one-half (3.5) hours per day, five (5) days per weal<. lOr each worker. at the COUNTY parks and olher locations as desIgnated by the COUNTY's Public Services AdminIstrator Or ner desIgnee. 2. The COmRACTOR shall receive compensatlQn for prov\dlng sald services durtng 1M period of time set forth above, as rOIlOW6: Sbc donors and 6ewnty,,"\ne cents ($6.79) per hour for up (0 five (5) workera~ for three and ona-haU' (3.5) hours per ~[~9{k~6r.",tl)I1.!1!!l]1.t!>t..a! ~n]llllt~ - --{ D.le.ted:_.k for servk;as lmdbr IhI& Agreement not to exceed Twenty-eieht thoUi:;ond fIv8 hundred eIghteen dollars ($28,618.00) per year. Your acceptance of thIs Change Order sheill consUlu1c:l a modUlcatlon to our Agroement and will be periormed GUbJecl to all the samf) telMs and condlllona aa conlalned In our Agreement IndIcated above, as fufly as If the same were repeated 111 this acceptance. Ac<:epi,d: ()~ I g' .2008 CONTRACTOR: Tech of COUlor CounlYl loa. OWNSR: BOARD OF COUNTY COMMISSlONSRS B;c OF CO)~I:R_~OUNT120R: Kerl)' Runyon, roJecl Manager -_.~_._-- --_.._-'_.,._,--~--'",~- CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM t';~t'~ HM07-06 ('J,jJ.9!~rV PROJECT NAME: 2007 HOME Construction/Fire Sprinklers CHDO Set Aside PROJECT #: PROJECT MANAGER: Rosa Munoz BID/RFP #: M07-UC-12-0017 MOD #: -LPO#: 4500101479 WORK ORDER #: N/A DEPARTMENT: Housina and Human Services CONTRACTOR/FIRM NAME: Bip Cvpress Housinp Corporation Original Contract Amount: $ 250.000 (Starting Point) Current BCC Approved Amount: $ 250.000 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 250,000 (Including All Changes Prior To This Modification) Change Amount: $ 0 Revised ContractlWork Order Amount: $ 250.000 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractlWork Order: $ 0 Date of Last BCC Approval November 13 2007 Agenda Item # 16028 Percentage of the change over/under current contract amount Formula: (Revised Amount / Last BCC approved amount).l o % CURRENT COMPLETION DATE (8) ORIGINAL: 6-15.2008 CURRENT: 6-15-2009 Describe the change(s): To provide a time extension of six months to the contract's performance and work schedule. A Zero dollar chanae was aranted on June 3. 2008 till December 31. 2008. This extension will run throuah June 15.2009. Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added [gj 6. Schedule Adjustments Note: One or more may be cheeked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The delav in the proiect is a result of numerous permittina and environmental issues. and natural disasters. This change was requested by: nContractor/Consultant [ZJ Owner n Using Department C CDES r Design Professional nRegulatory Agency (Specify) I2SJOther (Specify) Developer CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r No REVIEWED BY: 12-09.08 Date: ~(30(O.t CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM l\genda Item No, 16E7 February 10. 2009 Page 14 of 28 ., ,,' PROJECT NAME: Sheriff Fleet Facility PROJECT #: 52009 PROJECT MANAGER: Claude Nesbitt BIDIRFP #: 02-3422 MOD #: 24. CO 24 PO#:45-00100620 DEPARTMENT: Facilities Manaoement CONTRACTOR/FIRM NAME: Disnev & Associates. P. A. Original Contract Amount: $ 500,000.00 (Starting Point) Current BCC Approved Amount: $1,080,159.73 (Last Total Amount Approved by the BCC) I Current Contract Amount: Change Amount: $1,129,009.73 (Including All Changes Prior To This Modification) Revised ContractlWork Order Amount: $22,576.00 $1,151,585.73 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractfWork Order: $651,585.73 Date of Last BCC Approval 07124/07 Agenda Item # 16 E 2 ~rcentage of the change over/under current contract amount 6.61 % Formula: (Revised Amount 1 Last BCC approved amount).l CURRENT COMPLETION DATE (S): ORIGINAL: 12/25108 CURRENT: 04125109 Describe the change(s): Extend Architectural and related Engineering Services to concur with the extended construction schedule Specify the reasons for the change(s) r 1. Planned or Elective ~ 2. Unforeseen Conditions r 3. Quantity ~<!iustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added LV 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Without Architectural and Engineering Administration available, no changes (permitting or otherwise,) or request for information could be processed. This change was requested by: rlContractorlConsultant J71 Owner rI Using Department r CDES JZJ)esign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r No This form is to be signed and dated. APPROVED BY: ~ SA V1 ~ \; \- ProTect Mahager Date: 0 \ - 010 - ;;l.,ooq REVIEWED BY: Date: /-(p-()f Revised 1 J .19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM ~':'.\!a It;<'m irl."Yl~' <7 :-eD1-lJary 1.6,;2y / Page I~ ; PROJECT NAME: 2004 Eden Gardens 55-Units PROJECT #: CD04-14 PROJECT MANAGER: R. Munoz BIDIRFP #: B04-UC-12-0016 MOD #: -LPO#: 4500100065 WORK ORDER #: NIA DEPARTMENT: Housina and Human Services CONTRACTOR/FIRM NAME: Bia Cvpress Housina Comoration Original Contract Amount: $ 192.000 (starting Point) Current BCC Approved Amount: $ 192.000 (last Total Amount Approved by the BCC) Current Contract Amount: $ 192.000 (Including All Changes Prior To This Modification) Change Amount: $ 0 Revised ContractlWork Order Amount: $ 192.000 (Including This Change Order) Cumulative Dollar Value of Changes to th is GontractlWork Order: $ 0 Date of last BCG Approval Julv 24 2007 Agenda Item # 16011 Percentage of the change over/under current contract amount Formula: (Revised Amount I last BCC approved amount)-1 o % CURRENT COMPLETION DATE (8): ORIGINAL: 6.30.2008 CURRENT: 4-30.2009 Describe the change(s): To provide a time extension on the contract's performance and work schedule. A Zero dollar chanae was aranted on December 29. 2008 till January 31. 2009. This extension will run throuah April 30. 2009. Specify the reasons for the change(s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added k;J 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(sJ. Identify all negative impacts to the project if this change order were not processed: The delav in the proiect is a result of numerous permittina and environmental issues, and natural disasters. This change was requested by: r1Contractor/Consultant 0 Owner 171 Using Department r CDES r Design Professional r1Regulatory Agency (Specify) COther (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes r;; No This form is to be signed and dated. . ./ ./ ~ - ~ APPROVED BY: Rosa Munoz 0)/;<.: Project Manager REVIEWED BY cont;~~JaI2)7 Y'(~{'-t7{ Date: 12-29-08 Date: / - /l-c 9 Agenda It8m t-Jo, 16E7 February 10,2009 Page 16 of 28 /1 , j - CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Sheriff's Special Operations BuildinQ PROJECT #: 52002 PROJECT MANAGER: Hank Jones BIDIRFP #: 06-4025 MOD #: 11 PO#: 4500073809 WORKORDER#: N/A DEPARTMENT: Facilities ManaQement CONTRACTOR/FIRM NAME: Vanderbilt Bav Construction Original Contract Amount $10.250.269.00 (Starting Point) Current BCC Approved Amount: $ 10.250.269.00 (Last Total Amount Approved by the BCG) Current Contract Amount: $ 10.798.631.83 (Including All Changes Prior To This Modification) Change Amount: $1.575.00 Revised ContractIWork Order Amount:: $ 10,800.206.83 (Including This Change Order) Cumulative Dollar Value of Changes to this ContracllWork Order: $ 549.937.83 Date of Last BCC Approval: October 24. 200S Agenda Item #: 10B Percentage of the change over/under current contract amount 5.37% Fonnula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: 3/22/08 CURRENT: 12/31108 Describe the change(s): All additional time and costs (not-to,exceed) associated with chanoes as outlined in: 1) COP #79- Research. orovide notions and amend the existina Storm Water Pollution Prevention Plan for the oroiect to reaain comoliance with the NPDES cermit issued bv the Florida DeDartment of Environmental Protection Specify the reasons for the cbange(sl'~ 1. Planned or Elective ,- 2. Unforeseen Conditions 3. Quantity Adjustments C. Conection of Errors (plans, Specifications or Scope ofWoli<) r 5, Value Added ,- 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change{s), Identify all negative impacts to the project if this change order were not processed: Non compliance with FDEP oennit and reaulations This change was requested by: CContractor/Consultant C Owner C Using Department C CDES C Design Professional ri Regulatory Agency (Specify) i Other (Specify) APPROVED BY/ Han ,I CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: ~. -.. \ "'-. , rincipal Project Mana~er ) L',fJ l od, Contract Specialist I'" Yes ';j No REVIEWED BY: Date: Ilq(01 Date: . (7 </ j- I -..(J . Revised 11.19.2007 Acenja item NO.1 fjE7 ~ February 10, 200'1 ( Page 17 01211 I CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: US~orth Water Source Conversion PROJECT #: 163820 PROJECT MANAGER: Bob Petersen BID/RFP #: 08-5091 MOD #: 02 PO#: 4500101847 WORK ORDER #: DEPARTMENT: Transportation, A TM Dep!. landscape CONTRACTORiFIRM NAME: Hannula landscapina. Inc. Original Contract Amount: $ 51.386.20 (Starting Point) Current BCC Approved Amount: $ 51 ,386.20 (Last Total Amount Approved by the BGe) Current Contract Amount: $ 51.386.20 (Including All Changes Prior To This Modification) Change Amount: $ (-3.180.201 Revised ContractIWork Order Amount: $ 48.206.00 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ (.3.180.20) Date of Last BCe Approval Agenda Item #__ Percentage of the change over/under current contT'3ct amount Formula: (Revised Amount I Last Bee approved amount).1 -6.19% CURRENT COMPLETION DATE (5): ORIGINAL: 09/16/2008 CURRENT: 01/07/2009 Describe the changers): Scope and auantity chan~es were sug~ested hv Design Architect and Proiect Manager. Specify the reasons for the changers) r 1. Planned or Elective X 2. Unforeseen Conditions X 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change{s). //J r n~ocesse tv./ 'J" i . co I This change was requested by: r1Contractor/Consultant r[ Owner reSign Professional rJRegulatory Agency (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rI Using Department C CDES r Other (Specify) r- Yes , r;< No Date: I"~-U? t'o_; I' Date: \-. ~ ~ Revised 1].19.2007 PROJECT NAME: Emeraencv Service Center PROJECT #: Agenda Item No. 16E7 ( d- ~JPMJJ - ~ RECErVEOU 52160 PROJECT MANAGER: Hank Jones CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM BIDIRFP #: 04-3609 MOD #: 11 PO#: 4500030516 WORK ORDER #: NIA DEPARTMENT: Facilities Manaaement CONTRACTOR/FIRM NAME: Kraft Construction Comoanv, Inc. I Original Contract Amount: $ 38,533,902.00 (Starting Point) Current BeC Approved Amount: $ 34,322.150.87 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 33,374.382.83 (Including All Changes Prior To This Modification) Change Amount: $ 8,564.00 $ 33,382.946.83 (Including This Change Order) Revised ContractlWork Order Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ 15.150.955.17) Dale of Last BCC Approval: September 25, 2007 Agenda Item # 16E7 Percentage ofthe change over/under current contract amount .2.74% Formula: (Revised Amount I Last Bee approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 12/2008 CURRENT: 03/2009 Describe the change(s): Furnish all labor, material, tools and eauipment necessary to furnish and install reauired electric receptacles for power to 4 additional TV consoles. Specify the reasons for the change(s) r- 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjustments r 4, Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). I Identify all negative impacts to the project if this change order were not processed: W ~ ~ ~P~I This change was requested by: rlContractor/Consultant PI Owner rt Using Department C CDES CDesign Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes r No REVIEWED BY: Date: l laiD r /)3 !c) 9 , . APPROVED BY: Date: Revised 11.19.2007 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM ~' a tarn yr~. ..16El " . ~kr~/'!~'l/€ .. ~ R~l'fCU8 @ ; /I~ lor! l'~ PROJECT NAME: Golden Gate Pedestrian Bridae 2- PROJECT #:600501 PROJECT MANAGER: James Zuver BID/RFP #: 08.6014 MOD#: PO#: 4600091536 WORK ORDER #: DEPARTMENT: TECM CONTRACTOR/FIRM NAME: Quality Enterprises USA. Inc. Original Contract Amount: $ 389.576.20 (Starting Point) Current Bee Approved Amount: $ 389.576.20 (Last Total.A.mount ,A,pproved by the BCe) Current Contract Amount: $ 404.540.60 (Including All Changes Prior To This Modification) Change Amount: $ 17.761.64 Revised ContractIWork Order Amount: $_ 422.302.24 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ 32.726.04 Date of Last BCC Approvai 1/15/08 Agenda Item # 1684 Percentage of the change over/under current contract amount Formula: (Revised Amount I Last Bee approved amount)-1 8.4 % CURRENT COMPLETION DATE (S): ORIGINAL: December 2, 2008 CURRENT: December 31. 2008 Describe the change(s): Additional fill and sidewalk was added to ensure the approach slopes met the FDOT and ADA criteria. Additional sod and fence removal was necessary to prevent erosion and increase safety respectivelv. There was also a deduction in the amount of chain link fence Installed. Specify the reasons for the change(s)' 1. Planned or Elective. 2. Unforeseen Conditions . 3. Quantity Adjustments" 4. Correction of Errors (Plans, Specifications or Scope of Work). 5. Value Added C 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). This change was requested by: rlContractor/Consultant ~ Owner n Using Department r CDES CDesign Professional nRegulatory Agency (Specify) r Other (Specify) I I II I I I Identify all negative impacts to the project if this change order were not processed: Without the additional fill and sidewalk Quantities. the FDOT and ADA criteria would not have been met. If the criteria were not me~ the County would not be reimbursed for this LAP project. The additional sod will prevent soil erosion alon the sidewalk edqes. CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes -NO This form is to be signed and dated. cl-'II APPROVED BY: ..i',:li. <c. :; i'N'<_" Bate: /Moje t ManagJ!( f} .' / REViEWEDS(}i'YltrVt/LvlfrnJYJt ,}! Date Contract Specialist (~)' /h/0,/ ////1)01 f , Revised I J.I9.2007 b I /\gsnda Item N:J, 16E7 /4' cebruary ~'O, 2009 -~Fage 2iJ ot 28 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM . , \.\''- ~~,~i~CT' NAME:~ ~Yshore 'Drive' Bridae liahtino & Lan~scalJe Installation, ." PR,OJECT #: PROJECT MANAGER: Pamela lullc" . '~.':'- I,' ,Ie,' ,. " ' , I',," . 81DIR.FP. #: ~ ' . Mob #: M PO#: 4500098683 WORK ORDER #: ",?r{PA.RTMENT' Tr.n.portaUon"ATM'Deot.l.and~c.pe CONT~CTORIFIRIoI1 N~E: E.8. Slmmonde Eleclrlcal.lnc. > :"\-;:,i~ '\i~: r _;.; ", .' , ,',." " " , ..,' ." " '-'" ,""<.' ,.'.':'''' ' " ";,+1',;,' ' , , ' " . .:' ,',' '"..>,~ ',,": ''', -. " " ' " " "~,. , . ~~;fy the reas~ns for the change{s) r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantity Adjuslments . t 4. Correction 'of Errol"9 (PI.ns, Specifica~ons or Scope of Work) r 5. V.lue Added If. 6. Schedule Adjustmenl>i Note: On't')r more, msy be checked. depending on the nature of the ch.ng~~s). . ' . " ~ ~ . 'lde~IKi .11 negative.i acts t~ the p j . t ifthis c 'We ord r were not processed: C.cw " ., . 0 . ~ . ' .~:f, ~~',~,.,~, :',', ", ,','':c'", ", . 'p.,'gi,ijal Contract Amount:,! ' ' j,t~,;'H'~I':" ,':."," ',I '_,.-,., , ':" cu'm;nl acc' Approved Amount:. " I:',' ,~", "". !"," ',,' " :- : ,:"", '"':".:.~ ~:'~" . "/' :..- : ",' ." I', ..,.~iirre[lt Contract Amo'unt: :: $ 70.071.31 . (Starting Point) , " $ 70.071,31 {Last Total Amount Approved by the acC),"_'" $' 70.071.31 . (Including All Changes Prior To Th',s MOdification)" . $ 0.00 . chang,'Amount,. ; -. ~,. ',:, ~' , ,.', ;:' " 0 Revised ContractIWork Order' ,Amount: $ 70.071.31 (tndluding This Change Order) . . ~ " ",' C~rnt~tlv., Dollar Value iiCh~~g8S to tIl.l. ContracllWori< Order: .f;\~,"4. !"" $ 0,00 ~,~--'-'::-'." ," . , "- ~ - ,Dl!b> of La~l Bee Approval 712212008 .. ~;~--.~~~- ':,'. .i' ,;' ,.', ',.,'., Pem.r~g. of the change over/under current contract amount " FO!T!1ula: (Revised Amount / Lasl BCC approved amount)-1 _>,€'" ~', ," ":.," ;' I,' ", " ,;' "',; CURRENT COMPLETION DATE (5): ORIGINAL: 0112~I2009 Agendeltem # '16B-3 Q}l ;: ,-, 'i',~~ CURRENT: 'r ' 0312612009 . ".r,;, :j',":" ,_" . .' Describe the change(s): . ..' , '" ' ' " ~ Possible cliimfle in scooe oflandl:capinf! material Deliverv dat: extension needed for delaved deliverv on/fiN /Joles, Thlii'change was requ'esled by:.~onlractorlConsultanl rJ Owner n Using Department C. CDES -''to,','. _ CDesign Professional r1Regulatory Agency (Specify) , . ,j-; - "" r: Other (Specify) . 'CON,TRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r, Yes · 'No . , Th,iS .form is to be Signid and dated. /""'} r ,_-". .. /' ,/. .~ I .c . -"I ,r' . p,r~ 'A?PROVEDSV, r~~ . P la Lulich. Lardscape Operations Manager Date: 0 i~ 9. , ' / / Date: / f ? IftL . REVIEWED BY:: Revi~edl1.19.2007 ;" CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM /i.gDnda item !\Jo. 1~4: February 10. 2utl9 Page 21 of 28 PROJECT NAME: Palm River Estates Unit 4 N/S Stonnwater Improvements PROJECT #: 511411 PROJECT MANAGER: Val Prince BID/RFP #: 08-5052 MOD #: 2 PO#: 4500097298 WORK ORDER #: N.A. DEPARTMENT: Stormwater CONTRACTOR/FIRM NAME: Dave Foot Environmental Construction, Inc. Original Contract Amount: $ 354.763.25 (Starting Point) Current BCC Approved Amount: $354.763.25 (Last Total Amount Approved oy the Bee} Current Contract Amount: $ 363.838.25 (Including All Changes Prior To This Modification) Change Amount: $ 25.219.00 Revised ContractIWork Order Amount: $ 3B9.057.25 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractIWork Order: $ 34.294.00 Date of Last BCC Approval July 24, 2007 & June 10. 200B "'" Agenda Item # 16 B -. Percentage of the change over/under current contract amount ~% 1./. b 7 % Formula: (Revised Amount I Last Bee approved amount)~1 CURRENT COMPLETION DATE (S): ORIGINAL: Stonnwater Segment - 12/23/0B CURRENT: Storm water _ 01113/09 Park Entry Segment -12/23/0B Park Entry _ 01/13/09 Describe the change(s): 1. Add Paver Work "" Provide additional Pavers'" $3.750,00 & Clear & Grub at North End alJowina for LandsC3Dina of Easement to the East::: $2.740,00: 2. Add Vinvl Coated Fence = $1,012,50: 3. AddiHonal Clear & Grub. Gradina & Sod Work East Side of Channel = $10,964.00. 4. Extension of time.:::: Zero Cost: 5. Additional Clearina & GrubbinQ. Shaoino & Soddioo alooo West Side of Channel.:::: $6.752.50. Specify' the reasons for the change(s} r 1. Planned or Elective r 2. Unforeseen Conditions r 3. Quantitv Adiustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: Incomplete sidewalk to Park, Delay in neighborhood scheduled improvements, Dissatisfaction to area residents This change was requested by: rlContractor/Consultant PI Owner rI Using Department C CDES r'Design Professional rlRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r , Yes '"' j..... No APPROVED BY: Date: L,:A/t.:. r I /11:'/ tJ9 ( , REVIEWED BY: A$JIl '(ft;i11:JfVo Contract Specialist ( Revised 11.19.2007 , Date: I"-OHO ~N --~O C 6N . m ~ ~ " " ~--..,...N ~ 0 " " " ~ " " c , :0> ro N ro 0 M ;>-'" . 0 ~ ~ N N ~ E ~:n ~ E ~ ~ " :: on (1) (1) u 0 ~ 2::;0.... .g ~ ~.o E D 10" , eLL . '" .. . ~ c 0 OJ .-~ " '" " 0" " '" . <( ~~" 0 ~ ~ ~ ill " 1::1:0 :0> ro 0 mO~ 0 0 ~ . . E " '" ~ ~ ~ m iii u,g~ ~ - ~ ~ ro . ~ . 0 . C :0 0 0 0 0 0 . ~ 1! 0 ~ 0 0 ~ . , $ 0 m ,; ~ 0 . 0 0 ~ '" '" - ~ a ., ~ .I' m 0' . 0 '" ,; " w '" ~ * " N ro ~ ;;; ;;; ~ ~ ~ ~ ~ '" 8 ~ .. '0 0 . c 0 . 0 -~ 0 0 0 0 0 0 .. " . " , 0 0 ~ 0 0 0 E :0 ~O 0 ,; 0 :0 0 M 0 ~ c ~ E ~ 0 0 ~. 0 ~ . '" ~ ~ ~ 0 u '" ~ 0 ., w w '" :0 w " ~ ;;; ,; m U ~ ~ ~ ~ ~ . ~ ~ ~ u , " . 0 0 .. i . C :0 0 "- 0 0 0 " 0 .. C 1! 0 0 N 0 :;; " 0 . , .; 0 oj ,; ~ ~ ~ 0 0 m ~ 0 ~ ~ N 0 0 N . ~ E M 0 U ~ ~ ,: ~ . , ., '" .; '" ,: ;:> 0 ,: .c u 0 N ~ C m -0 . ~ ~ ~ E ~ . ~ ~ '" E ~ 1j " 2 . E ~ -0 0 os ~ . w ~ 0 . '5 " ~ . 0 !! 0 0 0 ~ " c . C :0 ~ 0 <': 0 ,; 0 ., . w e , .; 0 0 ,; . oj " ~ u 0 g . " ., .E 0 ~ ~ 0 u ;; " u ~ Z , m ~E M 2 ~ . ~ e z '" .E ~ 0 ~., '" '" 3 '" ~ c ~ U ., ~ N 0 ~ ro 0 ~ ~ ;; " ~ E ~ ~ ~ . ~ 0 . ~ . . 0 ~ ;;: u . ~ . 0 ~ " c ~. ro .2 0 0 . , 0 D " . . C :0 0 ~ 0 0 . 0 E 0 > .. ~ g 0 0 ~ " ro , ~ ,; " 0 . 0 0 ~ 0 " , .= ~ 0 ~ ~ ~ s 0 m 0 73 ;; e '" " ~ ~- E M ~ ~ ~ c 0 " 0; N ._ C ~ ~ ~ 0 z 0 0 ., '" J' '" " '" 2 ,: " m .~ ,: ~ < U N ~ ~ 0 m I ~ ~ .. ~ ~ ~ N ~ U .; ~ .2 . . < . u 0 . . ~ . " w . . ;; f- 0 ~ > u . " c . . ;; u 0 . " " . " < . ~ c ~ " E ~ - 0 0 c . m ~ " " S m j;' 0 0 " w ~ m .;:; 0 ;; " ~ "" ~ 0 0 '0. Z c w " " ~ " w ~ " " "- . ;; 2 u .g ~ '0 e ~ ;; 0 0 ~ :J <L ;; N " N " :J <L N " u 0 U '" CL 0 U ~ . u ~ 0 ~ ~ c CL 0 ~ U ~ 0 0 . 0 . 0 < , ., 0 " m ro Q . ~ .. ~ t5 . < 9 u , C ~ . . O! ~ 0 2 m '5 0 '" E . E m .S ~ 0 a; ~ U . E ;:; 0 < ~ m ~ 0 . N . > 0; 0 ~ u ro g 0 .~ x . 0 " . 0 '" '" . " z w .. '" 0 .. . 0 ~ ~ ~ '" ~ EO " ~ ~ . z ~ 'i ~ EO ~ . " 0 " 1! 0 " . m . ~ ., ~ f- ~ . :; M . N 0 0; ~ 5 ;; N m 0 " U a; C ~ ~ 'g ~ ~ , 0 ~ " m ] 0 0 . ~ . . 0; ~ . ~ 0; ~ c on ~ . " :; ~ ~ :; . M 8 0; M ~ E 0 0 f- '" . w "- W "- ~ 0 '" ~ ~ 0 '" w " 'o! 0 ~ '5 ~ U 0 u U 0 B ~ 0 ~ ~ 0 " 0 0 0 ~ 0 ro ~ . . . E ii . 0 C m ~ E 0 0> . 0 .S " e ~ :0 u ro . W . 0 m . ~ ~ . ~ " u 0 > 0 ~ ~ " m "' " m 51 E ro u ~ c ~ ~ ro . ~ . 0> . " ~ 0 . 0 c "' S m ~ 0 . " '" g ro . . 0 . z . . ~ . ., ~ . 0 0 c ~ .S < 0 0 0 . ~ . U 0 .. Q ~ . . . ~ ~ ~ w 0 0 'E . c . i5 W m 0 ~ .. . , E u 5> . 0 . < ~ . " " " 0 ~ E C c ~ ~ N . > . . " - , m 0 0 0 . " ~ 0 > . . " . O! E m , . w o. 0 x . . . 0 0 z z z - 0 , ~ W M CL . M '" . 5> - ~ 0 N , 0 m c 0 - " " < 0> 0 U 0 " 0 . c - 0 . . . . "7 > " ~~ ~ ~ . m w 0 ~ " ~ ~ 0 " .~ ~ ~ ~ m ~ m ~ ~ on g> ~ " 0 rn o '" w rnu 0 oN 0 0 rn 0 . . ~ . 0 . '" 0 0 ~ . 0 M " 0 ~ 0 ~:t ~ c ~ E:;: . a E 'f c u c ~ . c .e ~ 0 " o. " ro . . 0 m 0 ~ o ro m ~ ~ . rn .'" ~ i~ . " .~ ~ . 1;: m~ u 0 0 0 . 0 I' ~ o~ . ro 0 on Z ~~ 0 .0 iJ U x 0 ~ . 0 (; > "- u w ~U UU> f- U m UU roU m <L f- X U <D . u~ on W f- U" " f- ~ 0; ;; ;; ;; ;; ;; 0 ~ rn ~ rn m ~ ~ c :ii c c c c 2 . ro ro m ro ro ~ m ~ m ~ rn ~ m ~ m ~ . 0 u 0 0 0 0 0 u :;: u 0 u . . N "6 "' 0 "' '0 a; "6 0 " - " N e e e , " N . . . . . . 0 0 0; 0> " 0 0; . " . 0; 0> U .~ ~ .~ ~ ~ ~ ro E . ~ 0 . 0> . ~ 0 0 > > > > " z 0' 0 0 0 ~ 0 ,0 0 ~ 0 ~ item N~. 16'=.7 Fsbrcary 10. 2009 Page 23 of 23 CONTRACTfWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Collier County Landfill Scalehouse PROJECT #. 59005 PROJECT MANAGER:_Dayne Atkinson_ BID/RFP #: 06.3916 MOD #: ~PO#:~ 4500081753 WORK ORDER #: ICTSCADA-EMA-3916-07-08_ DEPARTMENT: PUED CONTRACTOR/FIRM NAME: EMA r~riginal Contract ;~:~nt: I Current BCC Approved Amount: I I $ 25,394.61 (Starting Point) $ 25,394.61 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 25,394.61 (Including All Changes Prior To This Modification) Change Amount: $ 1,570 Revised ContractlWork Order Amount: $ 26,964.61 (Including This Change Order) Cumulative Dollar Value of Changes to this ContracUWork Order: $ 1,570 ----.J Date of Last BCC Approval Agenda Item # Percentage of the change overfunder current contract amount Formula: (Revised Amount / Last BCe approved amount)-1 6, '! % CURRENT COMPLETION DATE (S): ORIGINAL: _3L24/08 ___.CURRENT: 3/24/09 Describe the change(s): Additional cables needed to complete data communication with the new weather station and H2S monitorinQ system f$15701 Specify the reasons for the change(s) r 1. Planned or Elective (- 2. Unforeseen Conditions r 3. Quantity Adjustments i- 4. Correction of Errors (Plans, Specifications or Scope of Work) r. 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: system installation would not have been able to be completed. The monitorinQ This change was requested by: IIContractor/Consultant PI Owner II Using Department r CDES rDesign Professional IIRegulatory Agency (Specify) '-Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r- Yes r- No This form is to il~te J;)JiE,/D B APPROVED BY "'"0"';;)( / ..-j .. 17' A j Lf::. - REVIEWED ---: '~YJ,//LCX!,,/ / --K;f~ Contract SpeciahS{ (' v Date: / //'D Date (?;/c3-~O Revised 2-22.08 L~r((i~ ~Jo.16E7 - Fmnn[~7100'llOV IIlcl'ege 2,/UJl1s ,1 v CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: CD.JJ~ '?AoZ-\<. BID/RFP #: 'I i - '-I1.,1MOD #: :; DEPARTMENT: C 2-"1 S~ PROJECT It. q OO.:;.<:t ., PROJECT MANAGER: o..-rNrt'e... "'>~ P01I:.,JS-lOO'Z-18wORKORDER#:-G/ .-t'5~UC-;"~- 153- o -cJI CONTRACTOR/FIRM NAME:~~ ~~.ac....;s-w.-: Current BCC Approved Amount: $ ~ iSD. 0'0 (Starting Point) A 5,. ISD. DO (Last Total Amount Approved by the BCC) 7,q 07-0.00 (Including All e'hanges Prior To This Modification) $ 0/Soo.00 $ ~. CS2.D. 00 (Including This hange Order) $ Original Contract Amount: $ Current Contract Amount: Change Amount: Revised ContractlWork Order Amount: Cumulative OollarValue of Changes to thi. ContractlWork Order: $ ~.fIO.C)U / Date of Laat BCC Approval I 1- .0/.0 7 Agenda Item # Percentage of the change over/under current contract amount '&..Ii % Formula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (5): ORIGINAL: ru. { (. oB CURRENT: (p. 3>0. oq Describethechange(s): f(ovmF_ 1~I>CAl- F'~5LV<-\'1' ~E:~ "S~u::.+:.-S TO ~f.b<>.,jrp, r...,~A-L PLAN" ld-z:n+ I ~H-n:>-l, ~<;'"_ Specify the reasons for the change(s) r 1. Planned or Elective. 2. Unforeseen Conditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work). 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: G-,c:l:S ~. SDf' 'P~SS [Arl..L &E REJ~b-C> '&'1 C.DGS D'-1.e. To Lee- vCOLA-nr:>t-.l~_ This change was requested by: ~ractor/consultant II Owner n Using Department ~ES Coesign Professional nRegulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes -NO This fonn is to be signed and dated. APPROVED BY: ~~ Project ger Date: I.':; .oJ REVIEWED BY: Date: / --(;- of' ,ism i'~o. "ICE? Fsbrusry 10, 2009 Page 25 of 23 -::0 CONTRACTIWORK ORDER MODIFICATION , _ I CHECKLIST FORM ~V~~ ~+J..ad PROJECT NAME: f>A.o=-Jt;"RE.=:NE PROJECT It P/:X=>/i:=. I PROJECT MANAGER: ~T' ~~ BID/RFPtI: o1-0.:fiMODtI: ~ PO#: 4S.IW-z.Z;Z. WORKORDER#: :J>=.-ff- 19 ~e.. ~/.53- OJ'" -02- DEPARTMENT: L. 2.l>1 CONTRACTOR/FIRM NAME: ~SCVJ ~~Ip'PI"::J, Original Contract Amount: $ ce~ q CO. 00 (Starting Pint) 6~qoo. 00 (Last Total Amount Approved by the BCC) 'iq, C;oB. 'UJ (Including All Changes Prior To This MOdification) ~/ 50/. .c:j-v $ <17,t.{r;,,<1. bo (Including This Change Order) $ . Current BCC Approved Amount: Current Contract Amount: $ Change Amount: $ Revised Contract/Work Order Amount: Cumulative Dollar Value of Changes to $ ("2;:;._ r- /' r::i ~ / 0 thia ContractlWork Order: <... :::> ""=.1- "" Date of Last BCe Approval l O. Z-& .cr-r Agenda Item # Percentage of the change over/under current contrad amount_ 7~ 2 ~ % Fonnula: (Revised Amount I Last BCC approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 1"L .'Z-j.bl!; CURRENT: ~ . ;?l7. CCf Describe the change(s): ?~oyroeo.. ADo-c:r.<z:>.lA1- ~ cc.AL- Res~.J.I.' ~. \"l..o.I'~ M~~. Mt> r~D.=4Ifrtn.l W~ (~'o.S1j -S"TkW R:>;l.. ~0I.l~=_ Specify the reasons for the change(s) (' 1. Planned or Elective. 2. Unforeseen Conditions r 3. Quantity Adjustments (' 4. Correction of Errors (Plans, Specifications or Scope of Work} r 5. Value Added C 6. Schedule Adjustments Note: One or more may be checked, depending on the nature ofthe change(s). Identify all negative impacts to the project if this change order were not processed: ~ c-u~e.Jt" K""'"?~ ?~$S l<<lOJW> H-t.--E. ?~~ Re..::r~ Do",,- Ib :Pc4o,t f1eoa=.Du~e: Y.D:::>L.A.TXP>-lS t:>~~~ ~ ~e.5 P\...AN,.Jt'1'J6f ?R.~e:s. I This change was requested by: lIcontractor/Consultant n Owner n Using Department . CDES Ibesign Professional IIRegulatory Agency (Specify) rOther (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: rYes -NO This fonn is to be signed and dated. APPROVED BY: ~ Project ger REVIEWED BY: ~.' I > 71 Yt /~-tl-l C nt a Specialist Date: I.'.i;. O'J Date: / - C; .' {)P I III C :;rr79lJllrJ, iiiaJ q j(' P~ge 26 of 28 Revised ContractJWork Order Amount CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM I-IvAC- PROJECT#: IV/A PROJECT MANAGER: 301.'\1 CLu.,~NI5 . , L PO#: 'fS--/oJ97? WORKORDER#: 4,f- /0;" i'?3 frn ~"t4 7EJolr.JJC;;NTRACTORlFIRM NAME: H S A . $ 7, (;, DO ' 0 0 (Starling Point) $ (Last TO::: L:rrt Approved by the BCG) $ ,,{..,OO,O'O (IncludIng All Changes Prior To This Modification) $ 8)5""00 , 0 0 $ //2 /00 (InclUding1l.is Change Order) PROJECT NAME: r - ( BIDIRFP #: 0 (" - 3 q 7CMOD #: DEPARTMENT: FAc., i...,liii Original Contract Amount Current BCC Approved Amount: Cunent Contract Amount: Change Amount Cumulative Dollar Value of Changes to this ContractJWork Order: $ 'is) S-O\). 0 0 Date of Last BCC Approval NJ It Agenda Item # ~/ 14 Percentageoflhechangeoverlundercurrentconlractamount / / /, 8'1 % Formula: (Revised Amount! Last BCC approved amount).l CURRENT COMPLETION DATE (S): ORIGINAL: ffi..fJ:, 17, dODl CURRENT: 1/ I Oescribethe change{s): CO""pLfJ( Hi/tile.. t: VI'tLu I4TiA-.. ();:. C-l lAX Cou.<..T.,,,, Specify the re!,s9/1S for the change(s) r 1. Planned or Elective.~ Unforeseen Conditions r 3. Quantity Adjustments y.- 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: C U sTo r>- (" So w I"LL " No! HAM.. f{\ofr.... c'IT\71\.tR. of AI~ -)(",,{JfATv.--- !1N{) A/A QUftL,T1 '/ This change was requested by: r1ContractorlConsultant pf Owner n Using Department C CDES Loeslgn Professional rrRegulalory Agency (Specify) IOther (Specify) CONTRACT SPECIALIST PARTICI r Yes YNO Th is form is to be si APPROVED BY: Date' REVIEWED BY: Date: j-9-{)9 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM /'.oenda item [\lo. 16E7 ~ ;:8br~ary 1 0, 2008:'"~- Page 27 of 2B-' PROJECT NAME: SCRWTP Wellfield Exoansion portion of the Wellfield Reliabilitv Improvements and Expansion Proaram PROJECT #: 70892 PROJECT MANAGER: Ronald F. ~illard BIDIRFP #: 04-3593 MOD #: --L PO#: 4500101578 DEPARTMENT: PUED WORK ORDER #: 04.01 CONTRACTORlFIRM NAME: Camp Dresser & McKee, Inc. Original Contract Amount: $ 4.999.218 (Starting Pomt) Current Bee Approved Amount: $ 4.999.218 (Last Total Amount Approved by the BCC) Current Contract Amount: $ 5.137.681 (including All Changes Prior To This Modification) Change Amount: $ 61.430 $ 5.199.111 (Including This Change Order) j Revised ContractIWork Order Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ 199.893 Date of Last BCC Approval 6.8.04 Agenda Item # 10 D (.2e- Percentage of the change over/under current contract amount ,4:{1 % Formula; (Revised Amount Il..ast Bee approved amount)-1 CURRENT COMPLETION DATE (S): ORIGINAL: 12-18.06 CURRENT: 2-15-09 Describe the change(s): Provide enqtneerinq services beyond the completion date identified in the enqineerinq services aqreement and previous chanoe orders. Prepare olans and permit modifications for improved wet weather access. Provide enqineerinq services related to motor failures. The first and third of these three tasks will be funded by liquidated damaoes withheld from the construction contract Specify the reasons for the change(s) r 1. Planned or Elective r. 2. Unforeseen Conditions r 3. Quantity Adjustments C 4. Correction of Errors (Plans, Specifications or Scope of Work) (0" 5. Value Added '" 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: The desiqn enqineer would not provide enqineerinq services throuqh completion of the proiect for access improvements, or for review of motor failure issues. This change was requested by: rlContractorlConsultant II Owner PI Using Department C CDES FDesign Professional rlRegulatory Agency (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Other (Specify) P' r Yes No This form is to be signed and dated. APPROVED BY: Date' I :2 -.!f.~ APPROVED BY Date: 12 1\ \ /09- . REVIEWED B Oate- I-/~-cq Revised 2.22.08 item ~~o" i6E? "-'be >',ry 10 ?Ooj' ,:-",u~. ',__ ~ Page 28 of 23 CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: Marco Breakwater & Groins Evaluation PROJECT#: 195-90500.1 PROJECT MANAGER:~ MeA/Din BIDIRFP #: 06-3902 MOD #: 1 PO#: 45-102105 WORK ORDER #: 45-102105 DEPARTMENT: Coastal Zone ManaQement CONTRACTOR/FIRM NAME: Humiston & Moore ! Original Contract Amount: I $ 7,525.00 (Starting Point) rJtflr (Last T tai Amount Approved by the BCG) Current Bee Approved Amount: $ I Current Contract Amount: $ 7 525_00 (Including All Changes Prior To This Modification) Change Amount: $ 6.000.00 Revised ContracUWork Order Amount: $ 13.525.00 (Including This Change Order) Cumulative Dollar Value of Changes to this ContracliWork Order: $ 6,000.00 Date of Last BCC Approval N/A Agenda Item # NIA Percentage of the change over/under current contract amount Formula: (Revised Amount I Last Bee approved amount)~ 1 7971'(. CURRENT COMPLETION DATE (S): ORIGINAL: 5/9/09 CURRENT: 5/9/09 Describe the change(s):Task 1: Prepare response to Joe Chesler who is Coordinatina the FEMA application for fundina for South Marco Proiect: revise drawinQ for additional breakwater, research material costs, prepare spreadsheet and submit. Prepare response to follow up auestions from FEMA per discussion with Ken Humiston 12-19-08 additional budQet of $6,000 Specify the reasons for the change(s) r 1. Planned or Elective" 2. Unforeseen Conditions r 3. Quantity .AdjOstments r 4. Correction of Errors (Plans, Specifications or Scope of Work) r 5. Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this change order were not processed: sent to FEMA for fundina and Questions have been asked. this Work Order will application. Application has been facilitate FEMA to fund This change was requested by: PContractor/Consultant r Owner r Using Department C CDES CDesign Professional r Regulatory Agency (Specify) r Other (Specify) CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: .- I Yes .- I No APPROVED BY: This form is to be signed and dated. 9rf~ Ml~ Ga(yMcAlp n, eZM Dire tor '. /J .,/ Date: I /,t!uo1 I I REVIEWED BY Date: (-/<I-v l' Lyn Wo Revised 2-22.08