Agenda 01/27/2009 Item #16A 3 AgEnda Item No, 16A3 January 27, 2009 Page 1 of 6 EXECUTIVE SUMMARY Recommendation to approve final acceptance of the sewer utility facility for Treviso Bay at Southwest Boulevard OBJECTIVE: The Board of County Commissioners, Ex-Officio the Governing Board of the Collier County Water-Sewer District, to accept the conveyance of the sewer facility, CONSIDERATIONS: 1) The Developer of Treviso Bay at Southwest Boulevard has constructed the sewer facility within dedicated easements to serve this development. See attached location map. 2) Preliminary acceptance of this utility facility was approved by the Engineering and Environmental Services Department staff on August 24, 2007. At that time, the value of this utility facility (asset) was $51,788,89 (see attachment(s)), This Final Acceptance is in accordance with Ordinance 2004-31, as amended, 3) Staff has recorded all preliminary acceptance documents in the public records of Collier County, which have been reviewed and approved by the County Attorney's office as to form and legal sufficiency, 4) The sewer facility has been operated and maintained by the Collier County Water- Sewer District during, not less than, the required one (1) year warranty period, 5) A final inspection to discover defects in materials and workmanship has been conducted by the Engineering and Environmental Services Department staff and this facility has been found to be satisfactory and acceptable, 6) The PUD Monitoring staff has reviewed this request in relation to possible issues raised by the applicable Home Owners Association (HOA), Staff is unaware of any issues that would serve to negate the recommendation to release the applicable security, FISCAL IMPACT: Approval of this Executive Summary will have no specific financial impact. However, approval of this Executive Summary will result in the Collier County Water-Sewer District receiving unconditional title to utility facility, which at the time of preliminary acceptance had a total (undepreciated) value of $51,788,89, GROWTH MANAGEMENT IMPACT: Approval of this Executive Summary will have no growth management impact. LEGAL CONSIDERATIONS: The elements necessary to accept final and unconditional conveyance of these water and/or sewer facilities have been met. This item is not quasi-judicial and as such ex parte disclosure is not required, This item requires a majority vote only, There is no additional legal review from the County Attorney required to complete this final acceptance, - JAB Agenda Item No, 16A3 January 27,2009 Page 2 of 6 RECOMMENDATION: That the Board of County Commissioners, Ex-Officio the Governing Board of the Collier County Water-Sewer District, to accept final and unconditional conveyance of the sewer utility facility for Treviso Bay at Southwest Boulevard, and authorize the County Manager, or his designee, to release any Utilities Performance Security (UPS) to the Project Engineer or the Developer's designated agent. PREPARED BY: Jodi P. Hughes, Technician Item Number: Item Summary: Meeting Date: Page 1 of2 Agenda Item No, 16A3 January 27. 2009 Page 3 of6 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 16A3 Recommendation to-approve final acceptance of the sewer utility facility for Treviso Bay at Southwest Boulevard 1/27/200990000 AM Prepa red By Jodi Pannullo Community Development & Environmental Services Administrative Assistant Date COES Engineering Services 12/4/20087:39:11 AM Approved By MaryAnn Devanas Community Development & Environmental Services Senior Planner Date CDES Engineering 12/5/200810:11 AM Approved By William D. Lorenz, Jr., P.E. Community Development & Environmental Services Environmental Services Director Date Environmental Services 1215/200812:28 PM Approved By Judy PUlg Community Development & Environmental Services Operations Analyst Community Development & Environmental Services Admin. Date 12/5/2008 4 :51 PM Approved By Donald Edwards Public Utilities Operations Manager Date Wastewater 12/9/2008 3: 16 PM Approved By Stephen L. Nagy Public Utilities Wastewater Collections Manager Date WasteWater 12l9/2008 4:09 PM Approved By G. George Yilmaz Public Utilities WasteWater Director Date WasteWater 12/11/20082:22 PM Approved BJ Phil E. Gramatges, P.E. Public Utilities Sr. Project Manager Public Utilities Planning and Project Management Department Date 12/15/20083:03 PM Approved BJ Jennifer A. Belpedio County Attorney Assistant County Attorney Date County Attorney Office 12130/20088:37 AM Approved By Joseph K. Schmitt Community Development & Environmental Services Adminstrator Date Community Development & Community Development & file://C:\AgendaTest\Export\ 122-January%2027, %202009\ 16.%20CONSENT%20AGEND... 1/21/2009 Page 20f2 Agenda Item No, 16A3 January 27,2009 Page 4 of 6 Environmental Services Environmental Services Admin. 12/30/20088:32 PM Approved By OMS Coordinator OMS Coordinator Date County Manager's Office Office of Management & Budget 1/8/200911:13 AM Approved By Randy Greenwald County Manager's Office Management/Budget Analyst Office of Management & Budget Date 1/9/20091 :17 PM Approved By James V. Mudd County Manager Date Board of County Commissioners County Manager's Office 1/14/20097:44 PM fi le://C :\Agenda Test\Export\ 122.January%2027, %202009\ 16. %20CONSENT%20AG EN D.., 1/21/2009 MOHO 4:0_ cc..P 0 IL{) (]) ~ ' OJ E ~~ QJIU ~" -C lUlU 10-' C (]) OJ 4: i , , ~ z r- ,----------, /~~j'1~ >~~€~" ~ ~ /' "/ I . ~ j / ---..j / j (, \ @ " ~ ~ . ~ z ~ ...."., ill ,,'" / ____ - ~ , l!~ . OoI~hn_ ""-'11>> 1'11.1(;) l .' iI, z !~ II' , . j 1 i i I I' ~z 00 w- o~ {1 II': 0 -/ 0....J ::l f '-,.~ /1 ... /,1 // i"e ' // ,/ ~~~. i C I ~~ " " " , ) !, '\ I, \' ~ '\ , , ),,(, jJ''' /r !' ;'0 - / ~, . \ ~ )>1 ~ , j ; 11 , , " I 0 I j - ~ " .. , , l ; (--~ Fi.// ./ 'rj A ~\ 11. ct: ::E w .... en -e " > Ql :; S ~ VI ~ .c '5 o en - " >, ~ g .~ t= 11. ct: ::E z o .... <( U o ...J . . Agenda Item No, 16A3 January 27, 2009 Page 6 of 6 CERTIFICATION OF CONTRIBUTORY ASSETS - COUNTY PROJECT NAME: Treviso Bay at Southwest Boulevard LOCATION: SECTION 32, TOWNSHIP 50 S.. RANGE 26 E. NAME & ADDRESS OF OWNER: TREVlSO BAY DEVELOPMENT, LLC 19275 W. CAPITAL DR. BROOKFIELD, WISCONSIN 53045 ""1. L-OPy TYPE OF UTILITY SYSTEM: SANITARY SEWER (MATERIALS ONLY) QUAN. UNIT 2660 LF 60 LF 75 LF 1 EA 1 EA 1 EA 1 EA COST $12,90 $1424 $160,45 $1,051.00 $2,204,12 $846,52 $485.10 TOTAL I $34,314,00 $854,40 $12,033,75 $1,051.00 $2,204,12 $846,52 $485,10 liTEM 10- PVC DR-18 FM 10" PVC DR-14 FM 24" JACK & BORE CASING 10" PLUG VALVE 10"X10" TAPPING SLEEVE & VALVE 10"x 6" POLY LINED TEE 6" PLUG VALVE TOTAL COST $51,788,89 I do hereby certify that the quantities of materials described above are a true and accurate representation of the system, CERTIFYING: ~ Brenda K. Merchant Authorized Agent OF: Haleakala Construction, Inc, 5758 Taylor Road Naples, Florida 34109.1829 STATE OF FLORIDA ) )SS: COUNTY OF COLLIER ) The foregoing Instrument was signed and acknowledged before me this 22nd day of AUGUST, 2007 by Brenda K. Merchant who is personally known to me and who did not take an oath, af~ ~ SEAL: Linda Mahon DO 628677 NOTARY 1'1J1lLlC . STATE OF Fl.ORlDA ""'''''''''0 Linda Mahon ~ W j Comrnissioo # DD62S677 ...., ,,': Expires: FER 21, 2011 llOND'ED THRU ATLAlITIC BONDING CO. me.