CONTRACTOR PRESENTATION FORM
Board Presentation Date: January 27, 2009
Contract Number, Project Title, Project Number: 07-4124 Collier Boulevard 6 lane
improvements (US 41 to Davis Boulevard)
Finn Name: Better Roads Inc.
Project Manager: Robbie Powell
Project Description: Widening from eXIstIng 4-lane to 6-lane divided roadway,
drainage improvements, lighting, bike lanes, sidewalk, and pathway.
Original Start Date: lOll 12007
Notice to Proceed Issuance Date: 8-16-2007
Original Completion Date: 9-29-2009
Revised Completion Date: 9-29-2009
Reason(s) for Variance: N/A
Original Budget: $24,955,329.69
Revised Budget: $25,096,34769
Reason(s) for Variance: Added fiber
optic cable to contract for IT department.
Actions
Variance:
Plannedrraken
N/A
to
Minimize Actions Plannedrraken to Minimize
Variance: NI A
Current Project Status:
Drainage in median is completed, paved 5.5 mile from inside lanes, completing lime rock
base and curb north of Business Circle Road. The lighting is installed on approximately
% of the project. The signalization is scheduled to be completed by the end of February.
Pathway construction was delayed due to the overlapping work with Ackermann, the
utility contractor installing water line for Utility Division, but it is now underway and
proceeding quickly. Based on days to original dollars contractor is approximately 14%
behind but the majority of dollars is in milling and paving. These activities are yet to
come and should bring the percentage in line for on time completion.
Agenda Item No. 50
January 27, 2009
Page 2 of 3
Contract Work Complete (December 31, 2008): $10,941,524.43 (48.56%) of the
actual contract work completed, (Allowances not included)
Contract Time Elapsed: 458 days of 730 days (62.74%) as of 12-31-08
Better Roads Presentation Notes:
The original contract amount:
$24,955,329.69
The original contract Allowances:
$3,700,000.00
The original contract work to be performed:
$21,255,329.69
The current contract amount:
$25,096,347.69
The current contract Allowances:
$2,566,373.08
The actual contract work to be performed:
$22,529,974.61
The actual contract work performed has increased by $1,274,644.92/ or by 5.99% with
no additional time added to the contract.
The original contract time:
730 days
The current recorded rain days:
57 days
The current days used:
458 days
The actual days used for critical work progress:
time.
458 days / or 62,74% of contract
~
Contract team: KCCS (Trey Barclay) / Better Roads (Superintendent - Vic
Holcomb & Project Manager - Richard Yukob) / Collier County (Tad Pluc)
The Roadway construction of the project is progressing within 8% of our original
schedule. The project did not progress as quickly as anticipated due to significant rainfall
during the summer months. The pathway portion of the project ran into delays which
have caused an overall delay to the project, most of these delays have been resolved and
the pathway is progressing quickly. Outside of the percentages of time and money
presented to the Board we feel the current progress of this is going well. The project has
been a cooperative effort between Better Roads, KCCS, and Collier County.
Page I of I
Agenda Item No. 5D
January 27,2009
Page 3 of 3
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
Item Number:
Item Summary:
5D
Meeting Date:
Presentation on progress of widening Collier Boulevard {US 41 to Davis Boulevard) from
eXisting 4 lanes to 6 lanes divided roadway. drainage improvements, lighting, bike lanes,
sidewalk and pathway.
1/27/200990000 AM
Prepared By
Tad Plue
Engineer
Transportation Engineering and
Construction
Date
Transportation Services
1/12/20098:14:14 AM
Approved By
Steve Ritter
Manager-Road Construction
Transportation Engineering and
Construction
Date
Transportation Services
1/14/200910:11 AM
Approved By
Brian Hancock
Operations Support Manager
Transportation Administration
Date
Transportation Division
1/14/200911:13 AM
Appro\"cd By
Norm E. Feder, Ale?
Transportation Division Administrator
Transportation Services Admin.
Date
Transportation Services
1/1412009 1 :15 PM
Approved By
Najeh Ahmad
Director
Date
Transportation Services
Transportation Engineering &
Construction Management
1/14/20094:01 PM
Approvcd By
Usa Taylor
ManagemenUBudget Analyst
Date
Transportation Services
Transportation Administration
1/14120094:45 PM
Appro\-'cd By
Pat Lehnhard
Executive Secretary
Date
Transportation Services
Transportation Services Admin
1/15/20098:58 AM
ApproVl'd By
OMS Coordinator
OMS Coordinator
Date
County Manager's Office
Office of Management & Budget
1/15/20093:28 PM
Appro\'cd By
Susan Usher
Senior Management/Budget Analyst
Office of Management & Budget
Date
County Manager's Office
1/15/20094:38 PM
A pproVl'd By
James V. Mudd
County Manager
Date
Board of County
Commissioners
County Manager's Office
1/15/20097:07 PM
file://C:IAgendaTestIExportl 122-January%2027 ,%202009105. %20PRESENT A TI ONSI5DI5... 1/21/2009