Agenda 04/23/2019 Item #16G2 (Change Order #2 - Agreement #18-7332)04/23/2019 EXECUTIVE SUMMARY Recommendation that the Board, acting as the Collier County Airport Authority, approve the attached Change Order #2 to the Hangar Repair Contract with Alen Construction Group, Inc., to extend the schedule provided in Agreement No. 18-7332 by twenty-five days. OBJECTIVE: To authorize a change order that will provide sufficient time for the contractor to repair hangars at the Marco Island (MKY) and Everglades (X01) Airports damaged by Hurricane Irma to pre - storm condition. CONSIDERATIONS: On December 10, 2018 (Agenda Item 16G2), the Board of County Commissioners (“Board”), acting as the governing body of the Collier County Airport, approved Agreement No. 18-7332 with Alen Construction Group, Inc. to repair the hangars damaged by hurricane Irma at the Everglades Airpark and the Marco Island Executive Airport for $541,296. The repairs were to be completed in one hundred and twenty (120) days. Change Order #1 added a task to replace two (2) damaged I-beams and extended the schedule by twenty- four (24) days to provide sufficient time for installation of the I-beams and delivery of the hangar door motor mechanisms. Weather-related logistics in the Midwest has caused further delays in the manufacturing and delivery of the motor mechanisms. The contractor has requested an additional twenty- five (25) days to allow for the manufacture and delivery of the materials necessary to complete the repairs. Staff has reviewed this request and recommends approval of attached Change Order #2. FISCAL IMPACT: There is no fiscal impact associated with this Change Order. GROWTH IMPACT: There is no growth impact associated with this Executive Summary. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -SRT RECOMMENDATION: To approve attached Change Order #2 to Agreement # 18-7332 for Alen Construction to extend the schedule by twenty-five (25) days and authorize the Chairman to sign the attached Change Order. PREPARED BY: Justin Lobb, Airports Manager, Airport Authority ATTACHMENT(S) 1. 18-7332 CO #2-time extension only (PDF) 2. 18-7332AlenConstruction_Contract_20180802144051.528_X (PDF) 3. 50154 4500192361_CO#1_fully executed (PDF) 16.G.2 Packet Pg. 2397 04/23/2019 COLLIER COUNTY Board of County Commissioners Item Number: 16.G.2 Doc ID: 8363 Item Summary: Recommendation that the Board, acting as the Collier County Airport Authority, approve the attached Change Order #2 to the Hangar Repair Contract with Alen Construction Group, Inc., to extend the schedule provided in Agreement No. 18-7332 by twenty-five days. Meeting Date: 04/23/2019 Prepared by: Title: Operations Coordinator – Airport Authority Name: Debra Brueggeman 03/19/2019 5:07 PM Submitted by: Title: Division Director - Operations Support – Growth Management Department Name: Gene Shue 03/19/2019 5:07 PM Approved By: Review: Growth Management Department Gene Shue Additional Reviewer Completed 03/21/2019 3:39 PM Growth Management Department Christine Arnold Level 1 Reviewer Completed 03/25/2019 1:40 PM Growth Management Operations Support Christopher Johnson Additional Reviewer Completed 03/25/2019 1:54 PM Capital Project Planning, Impact Fees, and Program Management Rookmin Nauth Additional Reviewer Completed 03/26/2019 6:11 AM Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 03/27/2019 2:01 PM Procurement Services Sara Schneeberger Additional Reviewer Completed 04/01/2019 2:06 PM Procurement Services Catherine Bigelow Additional Reviewer Completed 04/01/2019 2:33 PM Procurement Services Ted Coyman Additional Reviewer Completed 04/01/2019 4:31 PM Airport Authority Justin Lobb Additional Reviewer Completed 04/01/2019 4:59 PM Growth Management Department Thaddeus Cohen Department Head Review Completed 04/02/2019 4:30 PM Growth Management Department Jeanne Marcella Deputy Department Head Review Skipped 04/03/2019 4:19 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 04/05/2019 4:31 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 04/08/2019 8:19 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 04/12/2019 7:40 AM Budget and Management Office Ed Finn Additional Reviewer Completed 04/12/2019 10:07 AM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 04/15/2019 2:28 PM 16.G.2 Packet Pg. 2398 04/23/2019 Board of County Commissioners MaryJo Brock Meeting Pending 04/23/2019 9:00 AM 16.G.2 Packet Pg. 2399 16.G.2.a Packet Pg. 2400 Attachment: 18-7332 CO #2-time extension only (8363 : Alen Construction Time Extension) 16.G.2.a Packet Pg. 2401 Attachment: 18-7332 CO #2-time extension only (8363 : Alen Construction Time Extension) SchneebergerSara Digitally signed by SchneebergerSara Date: 2019.03.18 13:31:24 -04'00' 16.G.2.c Packet Pg. 2402 Attachment: 50154 4500192361_CO#1_fully executed (8363 : Alen Construction Time Extension) 16.G.2.c Packet Pg. 2403 Attachment: 50154 4500192361_CO#1_fully executed (8363 : Alen Construction Time Extension)