Agenda 04/09/2019 Item #14B104/09/2019
EXECUTIVE SUMMARY
Recommendation that the Community Redevelopment Agency Board (CRAB) adopt a Resolution
recommending to the Board of County Commissioners approval of an amendment to the Collier
County Community Redevelopment Area Plan.
OBJECTIVE: To update the Community Redevelopment Plan adopted by Resolution 2000-181 to
reflect current conditions and update the vision and approach to redevelopment in the Bayshore Gateway
Triangle component area and reflect the Immokalee Redevelopment Area boundary expansion approved
in 2004.
CONSIDERATIONS: Collier County Community Redevelopment Agency was established in 2000 and
covers two redevelopment component areas: Bayshore Gateway Triangle and Immokalee. One
Community Redevelopment Plan was adopted. The 2000 adopted plan includes a separate section for
each redevelopment component area.
On January 8, 2018, the CRAB approved contract 17-7050 with TOA Design Group to draft an update to
the Bayshore Gateway Triangle CRA Redevelopment Area Plan. The contract was amended in
September 2018 to include additional services for two sub-districts: Mini-Triangle and the 17 Acre
property owned by the CRA.
The proposed Plan Amendment for the Bayshore Gateway Triangle Redevelopment Area Plan is based on
review of existing conditions, spatial and quantitative analysis, fieldwork, and public and agency
outreach.
Several public forums and meetings were held in 2018 to gather public and agency input including:
• April 25-27 - Stakeholder Meetings and Public Forum.
• September 19 public forum to review and comment on preliminary recommendations developed
from the first phases of public outreach and analysis that was conducted in April.
• October 2 regularly scheduled Bayshore Gateway Triangle Local Redevelopment Advisory Board
(Advisory Board) meeting the Community Forum results were presented as well as the draft
results from the two sub-district analysis.
• October 11 a special public meeting of the Advisory Board was held to review the draft
amendment to the Bayshore Gateway Triangle Redevelopment Area Plan.
The draft plan was presented, and public input received at the November 14 and December 4 Advisory
Board meetings. Based on comments received from the Advisory Board, the public and County staff the
plan was further revised, and the final draft was distributed at the February 5 Advisory Board meeting.
The proposed Plan Amendment also includes changes to reflect the Immokalee Redevelopment Area
Boundary expansion that was adopted by Resolution 2004-179 and Resolution 2004-384. Section 1 of the
Plan is also revised to clarify the status of the Growth Management Plan and extends the term of the
redevelopment program for both areas to 2049 to coincide with the long-range project competition dates
identified in the document.
FISCAL IMPACT: The original 2000 Community Redevelopment Plan was approved with a 30-year
term. Approximately 11 years remain. The proposed Plan Amendment extends the life of both the
Bayshore and Immokalee CRA areas by 30 years to 2049. At the end of the amended term the CRA will
have existed for 49 years.
This Plan Amendment does not obligate any funding to any projects listed. This Plan Amendment
provides a guide of both capital and non-capital projects that tax increment revenues can fund if approved
14.B.1
Packet Pg. 275
04/09/2019
by the CRAB and allocated through the standard operating and procurement guidelines adopted by the
Collier County Board of County Commissioners.
Initial receipt of TIF funding occurred in FY 2001. Through FY 2019 the Bayshore CRA has receive d
TIF funding of $22,631,017 and the Immokalee CRA has received $8,659,135. For the proposed 30-year
term TIF receipts for the Bayshore CRA are estimated to be between $154,400,000 and $183,600,000.
For Immokalee between $46,200,000 and $54,400,000.
Commencing in 2006 the Bayshore CRA entered into a series of loan arrangements to assemble strategic
properties to facilitate redevelopment. The current loan is the TD Bank Series 2017 Taxable Note. It is a
traditional 10 year fully amortized loan with a final maturity of March 1, 2027. Bayshore CRA tax
increment revenue and other CRA operating revenue are the pledged sources of repayment. The principal
balance as of is March 1, 2019 is $4,380,589. Annual principal and interest payments are approximately
$630,100. The pending sale of the Triangle properties will provide sufficient proceeds to extinguish the
debt. If the sale does not close the loan will be fully funded through annual TIF funding within the
original 30-year term of the CRA.
GROWTH MANAGEMENT IMPACT: On March 21, 2019 the Collier County Planning Commission
reviewed this Plan Amendment for consistency with the Growth Management Plan. The staff report
found the Plan Amendment to be consistent.
ADVISORY COMMITTEE RECOMMENDATIONS: The Bayshore Gateway Triangle Local
Redevelopment Advisory Board recommended approval of the amendment to the Community
Redevelopment Plan at their February 19, 2019 special meeting and the Immokalee Local Redevelopment
Advisory Board recommended approval at their February 20, 2019 regular meeting.
LEGAL CONSIDERATIONS: In accordance with Section 163.361(1), Florida Statutes, the Board of
County Commissioners may amend or modify the Community Redevelopment Plan upon the
recommendation of the Community Redevelopment Agency. This item is for such Community
Redevelopment Agency recommendation to be made by resolution. Also, Section 163.346, Florida
Statutes, requires public notice of an amendment to a Community Redevelopment Plan to each taxing
authority which levies ad valorem taxes on taxable real property contained within the geographic
boundaries of the redevelopment area. Those notices are back-up to this item. As such, this item is
approved for form and legality and requires a majority vote for Board approval. - JAB
RECOMMENDATION: That the Community Redevelopment Agency Board (CRAB) adopt a
Resolution recommending to the Board of County Commissioners approval of an amendment to the
Collier County Community Redevelopment Area Plan.
Prepared by: Debrah Forester, CRA Director
ATTACHMENT(S)
1. [Linked] CRA Adoption Resolution with Attachment A (PDF)
2. Notices Sent to Taxing Authorities (PDF)
3. [Linked] Redevelopment Plan Amendment Strike through underline version (PDF)
4. CRA Plan Powerpoint (PDF)
14.B.1
Packet Pg. 276
04/09/2019
COLLIER COUNTY
Board of County Commissioners
Item Number: 14.B.1
Doc ID: 8459
Item Summary: *** This item was continued from the March 26, 2019 BCC meeting. ***
Recommendation that the Community Redevelopment Agency Board (CRAB) adopt a Resolution
recommending to the Board of County Commissioners approval of an amendment to the Collier County
Community Redevelopment Area Plan. (This item is a companion to Item 9A)
Meeting Date: 04/09/2019
Prepared by:
Title: Manager - Technical Systems Operations – Administrative Services Department
Name: Michael Cox
03/27/2019 10:57 AM
Submitted by:
Title: – County Manager's Office
Name: Debrah Forester
03/27/2019 10:57 AM
Approved By:
Review:
County Manager's Office MaryJo Brock Director - CRAs Skipped 03/27/2019 2:01 PM
County Attorney's Office Michael Cox Level 2 Attorney of Record Review Skipped 03/27/2019 10:22 AM
County Manager's Office Michael Cox Additional Reviewer Skipped 03/27/2019 10:22 AM
Office of Management and Budget Michael Cox Level 3 OMB Gatekeeper Review Skipped 03/27/2019 10:22 AM
County Attorney's Office Michael Cox Level 3 County Attorney's Office Review Skipped 03/27/2019 10:22 AM
Budget and Management Office Michael Cox Additional Reviewer Skipped 03/27/2019 10:22 AM
Budget and Management Office Ed Finn Additional Reviewer Completed 04/02/2019 3:11 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 03/30/2019 1:09 PM
Board of County Commissioners MaryJo Brock Meeting Pending 04/09/2019 9:00 AM
14.B.1
Packet Pg. 277
14.B.1.aPacket Pg. 278Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 279Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
AMENDMENT -MARCH 2019
COLLIER COUNTY COMMUNITY REDEVELOPMENT AGENCY
COMMUNITY REDEVELOPMENT PLAN
BAYSHORE/GATEWAY TRIANGLE
Community Redevelopment Area
Dayshorc Gateway Triangle CRA •Bayshore Beautification MSTU
Haldeman Creek MSTU
,,.
' j •, �.(_r·' :�• l
Ji�'(JJ ;·�•· 1 · ,i:-' ./: [Jet,\11., -_·.;_,'9 OJ
\2f::;;.ittf��,�}75'.;,, l-�;:rr.�;,►,�-t:.�;•il f, j��
Adopted June 13, 2000
First Amendment: March 2019
IMMOKALEE
Community Redevelopment Area
Collier County Community Redevelopment Agency
IMMOKALEE CRA
i The Place to Call Home!
i IMMOKALEE CRA BOUNDARY
IMMOKALEE, FLORIDA
Attachment A
14.B.1.a
Packet Pg. 280 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Collier County Redevelopment Plan
TABLE OF CONTENTS
PAGE
SECTION 1 PLAN OVERVIEW
SECTION 1.1 INTRODUCTION 1
SECTION 1.2 FINDINGS AND CONDITIONS OF BLIGHT 3
SECTION 1.3 CONSISTENCY WITH THE COLLIER COUNTY GROWTH MANAGEMENT PLAN 4
SECTION 1.4 CONFORMANCE WITH STATUTORY REQUIREMENTS 5
SECTION 1.5 THE COMMUNITY REDEVELOPMENT AGENCY 7
SECTION 1.6 DURATION, MODIFICATION AND SEVERABILITY OF PLAN 9
SECTION 2 FINANCIAL PLAN
SECTION 2.1 FUNDING SOURCES 10
SECTION 2.2 OTHER FUNDING SOURCES 11
SECTION 3 NEIGHBORHOOD IMPACT ELEMENT 12
SECTION 4 IMMOKALEE REDEVELOPMENT AREA PLAN
SECTION 4.1 INTRODUCTION 13
SECTION 4.2 FINDINGS AND CONDITIONS OF BLIGHT 15
SECTION 4.3 CONSISTENCY WITH THE COLLIER COUNTY GROWTH MANAGEMENT PLAN 19
SECTION 4.4 COMMUNITY OBJECTIVES 26
SECTION 4.5 REDEVELOPMENT AREA CHARACTERISTICS AND ANALYSIS 28
SECTION 4.6 INFRASTRUCTURE NEEDS ASSESSMENT 31
SECTION 4.7 REDEVELOPMENT GOALS 35
SECTION 4.8 PHASE I – REDEVELOPMENT PLAN 35
SECTION 4.9 FUTURE PHASES 39
SECTION 4.10 NEIGHBORHOOD IMPACT STATEMENT 41
SECTION 4.10 PROGRAM OF PUBLIC EXPENDITURES 42
SECTION 4.11 VALUATION 47
SECTION 5 BAYSHORE/GATEWAY REDEVELOPMENT AREA PLAN
5.0 EXECUTIVE SUMMARY 5-E-1
5.01 EXECUTIVE SUMMARY 5-E-1
5.02 GOALS 5-E-1
5.03 CONCEPTUAL PLAN DIAGRAM 5-E-4
5.04 CHARACTER AREAS 5-E-7
5.05 FOCUS OF REDEVELOPMENT 5-E-9
5.06 FUNDING, PROJECTS & INITIATIVES 5-E-10
5.07 2000 & 2019 PLAN COMPARISON 5-E-14
5.1 INTRODUCTION 5-1-1
5.1.1 VISION 5-1-1
5.1.2 PROCESS 5-1-1
5.1.3 PLAN ORGANIZATION 5-1-1
5.2 BACKGROUND 5-2-1
5.2.1 CREATION OF A CRA AREA 5-2-1
14.B.1.a
Packet Pg. 281 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
5.2.2 5-2-1
5.2.3 5-2-9
5.3 5-3-1
5.3.1 5-3-2
5.3.2 5-3-75.3.3 5-3-26
5.3.4 5-3-31
5.3.5 5-3-42
5.3.6 5-3-59
5.3.7 5-3-66
5.3.8 5-3-67
5.4 5-4-15.4.1 5-4-15.4.2 5-4-15.4.3 5-4-55.4.4 5-4-17
5.5 5-5-1
5.5.1 5-5-1
5.5.2 5-5-15.5.3 5-5-1
5.5.4 5-5-1
5.5.5 5-5-15.5.6 5-5-55.5.7 5-5-5
5.6 5-6-1
5.6.1 5-6-1
5.6.2 5-6-2
5.6.3
2000 REDEVELOPMENT PLAN GOALS AND PROJECTS
BAYSHORE/GATEWAY TRIANGLE CRA 2018 PERSPECTIVE
PLANNING FRAMEWORK & ELEMENTS
CONCEPTUAL PLAN DIAGRAM
LAND USE & URBAN DESIGN
PUBLIC SPACE, PARKS, & OPEN SPACE
DEVELOPMENT
TRANSPORTATION, CONNECTIVITY, & WALKABILITY
INFRASTRUCTURE
PROCESS
CHARACTER AREAS
PRIORITIZATION PLAN
PRIORITIZATION OF PROJECTS & INITIATIVES
FINANCING PLANNING
PROJECTS & INITIATIVES PRIORITIZATION
COORDINATION & PARTNERSHIPS
GENERAL REQUIREMENTS
OVERVIEW OF RELEVANT STATUTES
CONSISTENCY WITH THE COUNTY’S COMPREHENSIVE PLAN
ACQUISITION, DEMOLITION/CLEARANCE, & IMPROVEMENT
ZONING & COMPREHENSIVE PLAN CHANGES
LAND USE, DENSITIES & BUILDING REQUIREMENTS
NEIGHBORHOOD IMPACT
SAFEGUARDS, CONTROLS, RESTRICTIONS & ASSURANCES
TAX INCREMENT & MSTU ESTIMATES
TAX INCREMENT FINANCING
MUNICIPAL SERVICE TAXING UNITS(MSTUS)
UNDERLYING ASSUMPTIONS 5-6-12
SECTION 6 RELOCATION PROCEDURES 102
FIGURES
FIGURES 1 COLLIER COUNTY MAP- 2004 2
FIGURES 2 IMMOKALEE REDEVELOPMENT AREA BOUNDARIES- 2004 14
FIGURES 3 IMMOKALEE FUTURE LAND USE MAP 24
FIGURES 4 IMMOKALEE SUBAREAS 36
APPENDIX
Appendix A Resolutions and Trust Fund Ordinance
14.B.1.a
Packet Pg. 282 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
I. 2000-82 – ESTABLISHMENT OF CRA AREA AND FINDING OF NECESSITY
AND BLIGHTED CONDITIONS REPORT
II. 2000-83-ESTABLISHING THE COMMUNITY REDEVELOPMENT AGENCY
III. 2000-181- ADOPTION OF 2000 CRA PLAN
IV. 2004-179- EXPANDING IMMOKALEE REDEVELOPMENT AREA
BOUNDARY
V. 2004-384-EXPANDING IMMOKALEE REDEVELOPMENT AREA BOUNDARY
APPENDIX B IMMOKALEE EXISTING CONDITIONS MAP
APPENDIX C BAYSHORE/GATEWAY EXISTING CONDITIONS MAPS -2000
APPENDIX D GATEWAY TRIANGLE STORMWATER MASTER PLAN TECHNICAL MEMORANDUM -2000
APPENDIX E BAYSHORE/GATEWAY ESTIMATED FUTURE DEVELOPMENT VALUE -2000
APPENDIX F 2012-2025 FUTURE LAND USE MAP
14.B.1.a
Packet Pg. 283 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Section 1
PLAN OVERVIEW
Section 1.1
Introduction
The Collier County Redevelopment Plan (CRA Plan) is a guide for the physical and economic
revitalization and enhancement of the designated redevelopment areas. This plan, with its
specific components, has been formulated in close cooperation with the members of each
community and is based on the objectives identified by community members in a series of
public workshops.
The Collier County Community Redevelopment Agency consists of two areas designated by the
Collier County Board of County commissioners as redevelopment areas under the authority of
Florida Statutes, Chapter 163, Part III, Community Redevelopment Act. The two areas depicted
on Figure 1 as amended, were identified by the presence of one or more conditions of blight as
defined in the statutes. These findings are contained in Section 1.2 and further specified in the
Appendix A and component section for each area.
The redevelopment program in Collier County provides the authority granted by the statutes, the
means to achieve growth management objectives, by redirecting growth to areas where urban
services currently are provided or are needed but currently inadequate, encourages
revitalization of once viable neighborhoods and business districts and encourages the provision
of affordable, good quality housing within centers of urban concentration.
The Collier County Growth Management Plan policies provide the rationale for the
establishment of redevelopment areas in the county and recognizes the redevelopment plan
adopted for each component area. In addition, each community has formulated their own
specific objectives. Each component section describes the history and process of community
involvement in each respective community.
The Collier County Community Redevelopment Agency approved an expansion to the
Immokalee Community Redevelopment Area boundary in 2004 (Resolution 2004-179 and
Resolution 2004-384).
In 2018, the Collier County Community Redevelopment Agency approved a contract with
Tindale Oliver Design to gathered data, perform technological analysis and seek public and
agency input in order to draft an amendment to this redevelopment plan that would lay out a
framework of goals, objectives, and strategies to continue the redevelopment efforts in the
Bayshore Gateway Triangle Community Redevelopment Area.
In 1969, the Florida State Legislature established Chapter 163, Part III, enabling local units of
government to declare a need for a Community Redevelopment Agency and outlines the
powers available to carryout community redevelopment and related activities. The overall goal
of the legislature was to encourage local initiative in downtown and neighborhood revitalization.
The Florida Legislature has made amendments to the enabling legislation over the years. This
Plan recognizes those amendments.
Figure 1 – Updated Map
1
14.B.1.a
Packet Pg. 284 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
2 14.B.1.aPacket Pg. 285Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Section 1.2
Findings and Conditions of Blight
In 1969, the Florida State Legislature established Statue 163.00 enabling local units of
government to set up Community Redevelopment Agencies (CRA). To assist in redevelopment
efforts, these local agencies were mandated to establish Redevelopment Trust Funds, which
would serve as the depository for tax increment revenues.
The overall goal of the legislature was to encourage local initiative in downtown and
neighborhood revitalization. In 1984, the Florida Legislature amended Section 163.335 to
include five primary objectives:
1.To address the physical, social, and economic problems associated with slum and blighted
areas (F.S. 163.335 (1));
2.To encourage local units of government to improve the physical environment (i.e. buildings,
streets, utilities, parks, etc.) by means of rehabilitation, conservation or clearance
/redevelopment (F.S. 163.335(2));
3.To convey to local community redevelopment agencies the powers of eminent domain,
expenditure of public funds, and all other general police powers as a means by which slum
and blighted areas can be improved (F.S. 163.335 (3));
4.To enhance the tax base in the redevelopment area by encouraging private reinvestment in
the area and by channeling tax increment revenues into public improvements within the area
(F.S. 163.335 (4));
5.To eliminate substandard housing conditions and to provide adequate amounts of housing
in good condition to residents of low or moderate income, particularly to the elderly (F.S.
163.335(5)).
To be designated as a redevelopment area, the area must meet the criteria outlined in Chapter
163.340 of the Florida Statute. The area in Collier county were designated as Blighted” which is
defined as the following:
“Blighted Area” means either:
(a)An area in which there a substantial number of slum, deteriorated, or deteriorating
structures and conditions which endanger life or property by fire or other causes or
one or more of the following factors which substantially impairs or arrests the sound
growth of a county or municipality and is a menace to the public health, safety,
morals, or welfare in its present condition and use:
1.Predominance of defective or inadequate street layout;
2.Faulty lot layout in relation to size, adequacy, accessibility, or usefulness;
3.Unsanitary or unsafe conditions;
4.Deterioration of site or other improvements
5.Tax or special assessment delinquency exceeding the fair value of the land; and
6.Diversity of ownership or defective or unusual conditions of title which prevent
the free alienability of land within the deteriorated or hazardous area; or
(b)An area in which there exists faulty or inadequate street layout; inadequate parking
facilities; or roadways, bridges, or public transportation facilities incapable of
handling the volume of traffic flow into or through the area, either at present or
following proposed construction.
3
14.B.1.a
Packet Pg. 286 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
On March 14, 2000, the Collier County Board of County Commissioners made finding of
conditions of blight and adopted Resolution 2000-82 and adopted Resolution 2000-83
establishing the Community Redevelopment Agency. Both of these resolutions are contained in
Appendix A.
Section 1.3
CONSISTENCY WITH THE COLLIER COUNTY GROWTH MANAGEMENT PLAN
The Collier County Growth Management Plan provides land use designations, which describe
the intent and allowable density and intensity of appropriate uses for future development. The
Growth Management Plan was adopted by the Board of County Commissioners in 1989 and
has been amended several times since the original adoption.
This section identifies the goals, objectives and policies that apply to both redevelopment areas.
The goals, objectives and policies that apply to each area specifically are included in Section 4
–Immokalee Redevelopment Area Plan and Section 5 – Bayshore/Gateway Triangle
Redevelopment Area Plan. This amendment recognizes that the Immokalee Redevelopment
Area Plan will be amended following the adoption of the updated Immokalee Area Master Plan
currently going through the public hearing process.
Both the Bayshore/Gateway Triangle Redevelopment Area and the Immokalee Redevelopment
Area are located in the Urban Designation as identified on the Collier County Future Land Use
Map Appendix F. As stated in the Future Land Use Element of the Growth Management Plan:
Urban Designated Areas on the Future Land Use Map include two general portions
of Collier County: areas with the greatest residential densities, and areas in close
proximity, which have or are projected to receive future urban support facilities and
services. It is intended that Urban Designated Areas accommodate the majority of
population growth and that new intensive land uses be located within them.
Accordingly, the Urban Area will accommodate residential uses and a variety of non-
residential uses. The Urban Designated Area, which includes Immokalee ,
Copeland, Plantation Island, Chok oloskee, Port of the Islands, and Goodland, in
addition to the greater Naples area, represents less than 10% of Collier County’s
land area.
The redevelopment plan allows for detailed planning that will encourage the coordination of
activities as outlined in Objective 4 of the Growth Management Plan.
OBJECTIVE 4:
Continually refine the Future Land Use Element through detailed planning in order to improve
coordination of land uses with natural and historic resources, public facilities, economic development,
housing and urban design.
Policy 4.8 recognizes the adoption of the redevelopment plans for each component area:
Policy 4.8:
The Board of County Commissioners may consider whether to adopt redevelopment plans for existing
commercial and residential areas. Such plans may include alternative land uses, modifications to
development standards, and incentives that may be necessary to encourage red evelopment. Such
redevelopment plans may only be prepared by the County or its agent unless otherwise authorized by the
Board of County Commissioners. The Bayshore/Gateway Triangle Redevelopment Plan was adopted by
the Board on June 13, 2000; it encompasses the Bayshore Drive corridor and the triangle area formed by
US41 East, Davis Boulevard an Airport-Pulling Road. The Immokalee Redevelopment Plan was adopted
4
14.B.1.a
Packet Pg. 287 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
by the Board on June 13, 2000. Other specific areas that may be considered by the Board of Count y
Commissioners for redevelopment include, but are not necessarily limited to:
a.Pine Ridge, between US41 North and Goodlette-Frank Road;
b.US 41 North in Naples Park; and
c.Bonita Beach Road between Vanderbilt Drive and the west end of Little Hickory Shores
#1 Subdivision.
The Immokalee Community is governed by the entire Growth Management Plan which includes the
Immokalee Area Master Plan (reference FLUE Policy 4.3), a separate element of the Growth
Management Plan adopted in 1991 and significantly revised in 1997 and 2007. The Master Plan
contains land use designations and policies applicable to the Immokalee area. Significant amendments to
the Immokalee Area Master Plan are under review.
A review of the land use designation and policies that apply for each area is contained in the
individual component section of this document: Section 4 – Immokalee Redevelopment Area
Plan and Section 5 – Bayshore/Gateway Triangle Redevelopment Area Plan.
Section 1.4
CONFORMANCE WITH STATUTORY REQUIREMENTS
Chapter 163, Part III of the Florida Statutes authorizes the creation of Community
Redevelopment Agencies and the development of Community Redevelopment Plans. The
legislation focuses primarily on the creation of Community Redevelopment Agencies, the
powers granted to them and specific criteria of the development of Community Redevelopment
Plans. As part of a Community Redevelopment Agency’s formation, a Community
Redevelopment Plan is created which provides the framework for effective redevelopment of the
Community Redevelopment Area.
The Community Redevelopment Plan is a comprehensive document that provides the details for
redevelopment of the area, including an extensive analysis required by Florida Statutes. In
accordance with Florida Statues, the governing body, in this case the Board of County
Commissioners, may make subsequent changes, amendments or updates to the Community
Redevelopment Plan upon recommendations of the Community Redevelopment Agency.
Modifications to the plan require a public hearing process and appropriate public notification.
The Community Redevelopment Act requires redevelopment plans to be consistent with the
comprehensive growth management plan. This plan is as a whole consistent with the Collier
County Growth Management Plan.
This plan establishes a vision for the community as a whole, the component areas and its
neighborhoods. The CRA’s vision will not be achieved overnight or even in the next five years.
This plan is intended to provide a framework for policy decisions and public improvements over
the next thirty years.
For the purposes of this plan, “encourage” means to support, recommend, endorse or seek
approval of any project, action, program or activity and can also mean to provide incentives and
allocate funds, assets and resources, including participation by staff, employees, contractors,
consultants or others if approved by the Collier County Agency (CRA) and allocated through the
standard operating and procurement guidelines adopted by the Collier County Board of
Commissioners.
5
14.B.1.a
Packet Pg. 288 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
This plan contains provisions that contemplate actions to be taken by the Board of County
Commissioners (BCC), including various agencies, departments or boards of the County. While
the BCC has adopted this Plan, any recommendations requiring further BCC action will be taken
separately to the BCC to approve and authorize implementation of any such actions.
The Private Sector
The Redevelopment Plan cannot be implemented without the predominant participation of the
private sector. The role of the private sector is to evaluate the effectiveness of an investment
risk in the Redevelopment Area and to pursue development opportunity consistent with the
Redevelopment Plan.
6
14.B.1.a
Packet Pg. 289 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Section 1.5
The Community Redevelopment Agency
The management structure established to undertake formal redevelopment activities within the
Redevelopment Area is the Community Redevelopment Agency (CRA). Pursuant to the
Community Redevelopment Act, the Collier County Board of County Commissioners declared
itself the CRA. The CRA is a legal entity, separate and distinct from the Board of County
Commissioners.
The Community Redevelopment Agency will use any and all methods of implementing the plan
as authorized by law. The CRA will exercise the powers conferred by statute to take action
within the Redevelopment Area such as will result in economic revitalization consistent with the
Plan. The Board of County Commissioners has the following powers:
•The power to determine an area to be slum or blighted or a combination thereof; to
designate such area as appropriate for a community redevelopment project; and to hold any
public hearings required with respect thereto.
•The power to grant final approval to Community Redevelopment Plans and modifications
thereof.
•The power to authorize the issuance of revenue bonds as set forth in Section 163.385,
Florida Statutes.
•The power to approve the acquisition, demolition, removal or disposal of property and the
power to assume the responsibility to bear loss as provided in Section 163.370, Florida
Statutes.
Community Redevelopment Agency Authority
This Plan will be undertaken in accordance with the provisions of the Community
Redevelopment Act of 1969. The County and the CRA may use any and all methods of
achieving revitalization of the Redevelopment Area as authorized by law. The following
sections generally describe the available development actions.
Property Acquisition
The Act authorizes the County and the Redevelopment Agency to acquire real property in the
redevelopment area by purchase, condemnation, gift, exchange or other lawful means in
accordance with this Plan. The County and CRA may acquire real property within the
redevelopment area as may be necessary for public improvements. These acquisitions will
provide sites for public facilities, eliminate unsafe conditions, removing non-conforming uses, or
overcome diversity of ownership and faulty lot layout which prevent redevelopment and
contribute to the perpetuation of blight in the area.
Whenever possible, the designated property will be acquired through negotiation with current
owners. The property will be acquired through standard Community Redevelopment Agency
procedures. In those instances where negotiation does not result in a mutually satisfactory
agreement, the properties may be acquired by eminent domain proceedings and just
compensation awarded in accordance with Chapter 170, Florida Statutes.
Areas for potential land acquisition and relocation (if necessary) are indicated in the component
sections of this plan. When necessary, as plans are further specified in Phase I (2001-2005)
particular parcels will be identified for acquisition where applicable. Such plans will be subject
to approval by the CRA Board. The following provides the policies which would govern
acquisition, disposition, or relocation activities.
7
14.B.1.a
Packet Pg. 290 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Land Acquisition Plan and Program
A land acquisition program will be designed to meet the goals and objectives of the
redevelopment plan, while minimizing disruption of the neighborhood fabric to be retained and
reinforced and minimizing acquisition costs.
A land acquisition program could consist of the following components:
•Right of Way Acquisition
•Commercial Project Acquisitions
•Residential Acquisitions for Major Projects
•Residential Acquisitions for Infill
Demolition, Site Preparation and Public Improvement
The County and the CRA may each demolish, clear or move buildings, structures and other
improvements from real property in the redevelopment area which it has acquired and as may
be necessary to carry out the purpose of this plan. In addition, the County and /or the CRA may
construct or cause to be constructed streets, sidewalks, curbs, utilities, lighting, open space,
plazas, landscaping, water elements, and other amenities deemed necessary to implement this
plan.
The County and CRA may change portions of the redevelopment area to be devoted to public
uses, public improvements, and infrastructure.
Disposition Policy
The CRA is authorized under the Act to sell, lease, exchange, subdivide, transfer, assign,
pledge encumber by mortgage or deed of trust, or otherwise dispose of any interest in real
property. To the extent permitted by law, the CRA is authorized to dispose of Real Property by
negotiated sale or lease. All real property acquired by the CRA in the redevelopment area shall
be sold or leased for development for the fair value to further the purpose of this plan and as
determined pursuant to 163.380 (2), Florida Statute ( 2018).
The CRA may reserve such powers and controls through disposition and development
document with the purchasers or lessees of real property from the CRA as may be necessary to
ensure that development begins within a reasonable period of time and that such development
is carried out pursuant to the purpose of this plan.
Interested developers will submit proposals in accordance with Section 163.380, Florida
Statues. Selected developers will be required to execute binding disposition agreements with
the CRA which will safeguard that the provisions of this plan be implemented. The property
may be transferred for fair value subject to the disposition agreement and other conditions or
covenants necessary to ensure that the purpose of redevelopment will be effectuated.
The disposition of all publicly owned or assembled land will be subject to objective and clearly
defined standards and procedures which will assure timely re-uses and improvements to
property in accordance with the plan and its development controls. Guidelines may include but
are not limited the following activities:
•Site Re-Use Guidelines
•Preferred Redeveloper Designation
•Competitive Private Developer Selection
•Terms of Property Conveyance
8
14.B.1.a
Packet Pg. 291 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
•Development Controls and Design Review
•Residential Relocation
•Commercial Relocation
The CRA’s Relocation Procedures are described in Section 6 of this Plan.
Section 1.6
Duration, Modification and Severability of the Plan
The 2000 plan was approved with a 30-year time frame. The 2019 amendment will extend the
term of this plan to 2049 as allowed by Section 163.387(2)(a), Florida Statutes. From time to
time during the term of this plan, the CRA may amend or modify this Plan.
The provisions of this Plan are severable, and it is the intention of the County and the CRA to
confer the whole or any part of the powers, goals, objectives and actions herein provided for
and if any of the provisions of this Plan or any action implementing any provisions of this Plan
shall be held unconstitutional, invalid or void by any court of competent jurisdiction, the
decisions of said court shall not affect or impair any of the remaining provisions of this Plan. It is
hereby declared to be the intent of the County and the CRA that this Plan would have been
adopted and implemented had such unconstitutional, invalid or void provision or action not been
included herein.
9
14.B.1.a
Packet Pg. 292 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Section 2
FINANCIAL PLAN
A viable financing program for redevelopment requires a strong commitment from the public and
private sector. The key to implementation the public actions called for in this plan is attracting
private market investment and the additional ad valorem tax revenue it produces. To carry out
redevelopment, the CRA will use all available sources of funding from local, state and federal
government and the private sector.
It should be noted that the following Financial Plan is intended as a guide for funding
redevelopment activities in the Redevelopment Area. Flexibility is essential. The timing, cost
and tax revenue impact of private investment is, at best, a projection based upon existing
knowledge. Interest rates, construction costs, and national economic conditions will vary and
cause revisions in investment decisions.
Section 2.1
Funding Sources
Tax Increment Financing
Redevelopment of the Redevelopment Area will require a substantial financial investment on the
part of the Community Redevelopment Agency. As provided for under the Community
Redevelopment Act of 1969, the principal source of funding for the Redevelopment Agency will
be through the mechanism of Tax Increment Financing.
Tax Increment Financing (TIF) realizes the incremental increase in property tax revenues
resulting from redevelopment and uses it to pay for public improvements needed to support and
encourage new development. TIF is designed to allow local government to finance, over a term
of years, front-end costs involved in the redevelopment of blighted areas. By using this tool a
local government can develop and adopt a redevelopment plan, repave or reroute streets,
provide other public improvements and open space, provide housing, provide redevelopment
assistance or incentives and acquire property within the redevelopment area for redevelopment.
Eligible activities, under current law, include but are not limited to, the acquisition of land and
improvements, relocation of displaced residents, demolition of deteriorated structures, site
preparation, infrastructure improvements plus housing and commercial development and other
activities implementing this plan.
Use of Tax Increment Revenues
Under Florida legislation, increment revenues can be used for the following purposes when
directly related to redevelopment:
$ Administrative and overhead expenses incidental to a redevelopment plan.
$ Redevelopment planning and analysis.
$ Acquisition of real property in the redevelopment area.
$ Clearance and preparation of redevelopment sites, and relocation costs.
$ Repayment of indebtedness and payment of expenses incidental to indebtedness.
$ Development of affordable housing within the redevelopment area.
$ Development of community policing innovations.
$ Construction streets, utilities, parks, public areas, parking garages, and other improvements
necessary to carrying out the redevelopment plan.
10
14.B.1.a
Packet Pg. 293 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
The greatest single source of funding for the Community Redevelopment Agency will come from
tax increment revenues determined by growth in certain real property tax revenues within the
Redevelopment Area. For the purpose of calculating the amount of tax increment revenues the
frozen tax base is the final 1999 tax roll.
Projected tax increment revenues for each component area is included in the Component
sections of this Plan.
Section 2.2
Other Funding Sources
To make the most effective use of Tax Increment Revenues, the CRA and the County will use
other County, State and Federal funding sources as appropriate and available to carry out the
provisions of this plan. The Financial Plan assume that funds for the public expenditures
identified in the Redevelopment Plan will be obtained from several sources in addition to Tax
Increment Financing.
Advances and Loans
The Community Redevelopment Agency shall have the power to borrow money and accept
advances from any source, public or private, including the County for any lawful purpose in
connection with the redevelopment program. Tax Increment Revenues or any other funds
deposited into the Redevelopment Trust Fund, which are not otherwise obligated shall be
available for repayment of such loans or advances.
Tax Increment Revenue Bonds
When authorized by the Board of County Commissioners, the CRA may issue redevelopment
revenue bonds, notes or other obligations to finance the undertaking of any community
redevelopment project activity, including the payment of principal and interest upon any loans
and retirement of bonds or other obligations previously issued. The security for such bonds
may be based upon the anticipated tax increment revenues and such other revenues as may be
legally available.
Grants
The Community Redevelopment Agency may apply for local, state or federal grants that may be
applicable to implementation of the redevelopment goals outlined in this Plan. Tax Increment
revenues may be used to match grant dollars if necessary.
11
14.B.1.a
Packet Pg. 294 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Section 3
NEIGHBORHOOD IMPACT ELEMENT
Since the redevelopment area contains low- and moderate-income housing, Section 163.362(3)
Florida Statutes requires that the redevelopment plan contain a neighborhood impact element
which…
describe in detail the impact of the redevelopment upon the residents of the
redevelopment area and the surrounding area in terms of relocation, traffic
circulation, environmental quality, availability of community facilities and services,
effect on school population, and other matters affecting the physical and social
quality of the neighborhood.
The structure of the Redevelopment Plan was specifically organized to minimize housing and
residential neighborhood impacts while emphasizing neighborhood enhancement, particularly in
those areas containing affordable housing stock. The intensive redevelopment activities
recommended in the plan concentrate on existing commercial and semi-industrial areas. Each
component section contains a Neighborhood Impact Element.
12
14.B.1.a
Packet Pg. 295 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 296Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 297Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 298Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 299Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 300Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 301Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 302Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 303Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 304Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 305Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 306Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 307Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 308Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 309Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 310Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 311Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 312Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 313Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 314Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 315Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 316Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 317Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 318Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 319Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 320Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 321Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 322Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 323Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 324Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 325Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 326Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 327Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 328Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 329Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 330Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 331Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Section 5
Bayshore Gateway Triangle Redevelopment Area Plan
First Amendment
Draft
March 2019
14.B.1.a
Packet Pg. 332 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Prepared for
Prepared by
DraŌ: March 2019
Cover Photo Sources: Zyscovich Architects;
Google.com ‐ Marys Palacios
14.B.1.a
Packet Pg. 333 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
i
TABLE OF CONTENTS
5.0 Executive Summary ............................................................................................ 5-E-1
5.0.1 Executive Summary ................................................................................. 5-E-1
5.0.2 Goals ........................................................................................................ 5-E-1
5.0.3 Conceptual Plan Diagram ........................................................................ 5-E-4
5.0.4 Character Areas ....................................................................................... 5-E-7
5.0.5 Focus of Redevelopment ......................................................................... 5-E-9
5.0.6 Funding, Projects & Initiatives ............................................................... 5-E-10
5.0.7 2000 & 2019 Plan Comparison.............................................................. 5-E-14
5.1 Introduction ....................................................................................................... 5-1-1
5.1.1 Vision ....................................................................................................... 5-1-1
5.1.2 Process ..................................................................................................... 5-1-1
5.1.3 Plan Organization .................................................................................... 5-1-1
5.2 Background......................................................................................................... 5-2-1
5.2.1 Creation of a CRA Area ............................................................................ 5-2-1
5.2.2 2000 Redevelopment Plan Goals and Projects ....................................... 5-2-1
5.2.3 Bayshore/Gateway Triangle CRA 2018 Perspective ................................ 5-2-9
5.3 Planning Framework & Elements ....................................................................... 5-3-1
5.3.1 Conceptual Plan Diagram ........................................................................ 5-3-2
5.3.2 Land Use & Urban Design ........................................................................ 5-3-7
5.3.3 Public Space, Parks, & Open Space ....................................................... 5-3-26
5.3.4 Development ......................................................................................... 5-3-31
5.3.5 Transportation, Connectivity, & Walkability ......................................... 5-3-42
5.3.6 Infrastructure ........................................................................................ 5-3-59
5.3.7 Process ................................................................................................... 5-3-66
5.3.8 Character Areas ..................................................................................... 5-3-67
5.4 Prioritization Plan ............................................................................................... 5-4-1
5.4.1 Prioritization of Projects & Initiatives...................................................... 5-4-1
5.4.2 Financing Planning ................................................................................... 5-4-1
5.4.3 Projects & Initiatives Prioritization ......................................................... 5-4-5
5.4.4 Coordination & Partnerships ................................................................. 5-4-17
5.5 General Requirements ....................................................................................... 5-5-1
5.5.1 Overview of Relevant Statutes ................................................................ 5-5-1
5.5.2 Consistency with the County’s Comprehensive Plan .............................. 5-5-1
5.5.3 Acquisition, Demolition/Clearance, & Improvement .............................. 5-5-1
5.5.4 Zoning & Comprehensive Plan Changes ................................................. 5-5-1
5.5.5 Land Use, Densities, & Building Requirements ....................................... 5-5-1
5.5.6 Neighborhood Impact ............................................................................. 5-5-5
5.5.7 Safeguards, Controls, Restrictions, & Assurances................................... 5-5-5
5.6 Tax Increment & MSTU Estimates ...................................................................... 5-6-1
5.6.1 Tax Increment Financing ......................................................................... 5-6-1
5.6.2 Municipal Service Taxing Units (MSTUs) ................................................. 5-6-2
5.6.3 Underlying Assumptions ....................................................................... 5-6-12
14.B.1.a
Packet Pg. 334 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 ii
This page is intenƟonally leŌ blank.
14.B.1.a
Packet Pg. 335 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 336 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐1
5.0
5.0.1 Executive Summary
The Bayshore Gateway Triangle Redevelopment Area
Plan amendment provides an updated vision and
approach for the redevelopment of this component
area (see Map 5‐ES‐1) for the next 30 years.
The Plan brings together informaƟon gathered from
technical analysis, fieldwork observaƟon, and public
and agency outreach (documented in further detail in
a separate Assessment Memo). From these efforts and
the resulƟng themes idenƟfied, an overarching vision
emerged for the future of the Community
Redevelopment Agency (CRA) and this component
area:
The Redevelopment Area Plan lays out a framework of
goals, objecƟves, and strategies organized themaƟcally
in support of this overall vision, along with a list of
projects to carry out the framework. This plan is meant
to provide a paleƩe of opƟons, generated by the
technical analysis, fieldwork observaƟons, and public
and agency outreach, that the CRA can further
explore. Consequently, not all of these suggesƟons will
necessarily be carried through to full implementaƟon.
Full implementaƟon of approaches and projects will be
based on further study of capacity, technical
feasibility, and public prioriƟes.
5.0.2 Goals
The main goals of the Plan include:
Land Use & Urban Design
Promote a defined, harmonious, and urban visual and
land use character tailored to the CRA area, culƟvaƟng
its unique arƟsƟc and cultural idenƟty.
Public Space, Parks, & Open Space
Ensure accessible, acƟvated, and well‐maintained
public spaces, parks, and open space.
Development
Foster and guide private development to enhance
community character and provide increased stability
and prosperity for community members.
Transportation, Connectivity, & Walkability
Ensure safety, comfort, and convenience for various
methods of transportaƟon within and connecƟng with
the CRA area.
Infrastructure
Provide effecƟve infrastructure that preserves
environmental and neighborhood design quality
through coordinated improvement planning and
funding.
Process
Carry out CRA area planning and implementaƟon
efforts to engage and serve the various communiƟes
within the CRA area.
Figure 5‐ES‐1 provides a Concept Diagram focused on
locaƟon‐specific capital improvement projects,
followed by a list of non‐locaƟon‐specific capital
improvements projects and a descripƟon of non‐
capital projects (e.g., plans, studies, grant programs).
Promote quality of life and economic vitality with a
mixed-income, urban,
multi-modal community that welcomes visitors,
cultivates the area’s artistic and cultural identity,
uplifts unique local destinations, and finds balance
with the natural environment.
14.B.1.a
Packet Pg. 337 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐2
5.0
Map 5‐ES‐1: Bayshore Gateway Triangle CRA Study Area
14.B.1.a
Packet Pg. 338 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐3
5.0
This page is intenƟonally leŌ blank.
14.B.1.a
Packet Pg. 339 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐4 5.0 Figure 5‐ES‐1: Redevelopment Concept THOMASSON DR BAYSHORE DR DAVIS BLVD N Complete Streets & Trail (Neighborhood) Jeepers Dr. Complete Streets (Major) Bayshore Dr. ‐ US 41 to Thomasson Dr. Complete Streets (Major) Linwood Ave Public Space, Parks, & Open Space Triangle RetenƟon Pond Improvements Monument Sign for Gateway IntersecƟon US 41 and Bayshore Dr. AIRPORT PULLING RD 5.0.3 Conceptual Plan Diagram Figure 5‐ES‐1 provides a Concept Plan illustraƟng future land use and capital improvements with associated goals of Land Use & Design; Public Space Parks, & Open Space; Development; TransportaƟon, ConnecƟvity, & Walkability; and Infrastructure. See the map legend on the following page for project descripƟons and addiƟonal capital improvements without specified locaƟons at this Ɵme. Note that “Major Corridors” are based on highways, minor arterials, and major arterials in the CRA area. Concept Map Major Corridor Land Use & Design Public Space, Parks, & Open Focus Corridor TransportaƟon, ConnecƟvity, & Walkability Infrastructure Development 5F 5E 5G 3A 5a 4c 4E 5B 5D 1C 6A 6b 6c 7d 7b 7A 7c 4b 4d 7E 4F 4a 1B 4G 5C 1A 1F 1D 1E 8A 8B 2A 14.B.1.aPacket Pg. 340Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐5 EXECUTIVE SUMMARY Bayshore Gateway Triangle CRA Area Plan —DraŌ March 2019 5‐E‐5 5.0 5.0 This page is intenƟonally leŌ blank. Location-Specific Capital Projects 7 1 3 4 5 6 8 Land Use & Urban Design Projects Gateway IntersecƟon Design Improvements A. Davis Blvd/Airport Pulling Rd B. Davis Blvd/Shadowlawn Dr C. Davis Blvd/US 41 D. US 41/Bayshore Dr E. Thomasson Dr/Dominion Dr F. Us 41/Osceola Ave Development Development Projects Public Space, Parks, & Open Space Projects Parks improvements A. Triangle RetenƟon Pond Improvements TransportaƟon, ConnecƟvity, & Walkability Projects Complete Streets (Major) A. Linwood Ave—Phase I B. Shadowlawn Ave C. Bayshore Dr—Us 41/Thomasson Dr D. Thomasson Dr/Hamilton Ave E. Commercial Dr F. Kirkwood Ave/Kirkwood Ave ConnecƟon G. Pine St ConnecƟon Complete Streets & Trails (Neighborhood) A. Bicycle/Pedestrian Trail B. Jeepers Dr C. Linwood Ave—Phase II D. Republic Dr E. Danford St F. Bay St G. Bayshore Dr—Thomasson Dr/Holly Ave Parking A. Surface/garage parking—Mini Triangle area B. Surface/garage parking—Bayshore area C. Car/boat parking—Bayview Park area General Road Engineering Standard Improvements A. Pine Tree Dr B. Andrews Ave C. Woodside Ave D. Holly Ave E. PalmeƩo Ct Infrastructure Projects Infrastructure A. Underground/Relocate Overhead UƟlity Lines—Linwood Ave and Commercial Dr B. Underground/Relocate Overhead UƟlity Lines—Bayshore Dr A. Development of MulƟ‐Purpose Facility/Structure 2 14.B.1.aPacket Pg. 341Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐6
5.0
Non-Capital Projects
Projects and iniƟaƟves that are not capital
investments include a variety of plans, studies, and
grant programs in support of redevelopment or capital
project planning throughout the CRA area. These non‐
capital projects and iniƟaƟves include:
CRA operaƟng expenditures and administraƟve
updates
Land Development Code updates
Development support for catalyst development sites
Master planning for:
Stormwater improvements
Arts and culture‐oriented development and
redevelopment efforts
ImplementaƟon of Complete Streets projects
Community safety and clean‐up
Branding
MarkeƟng and communicaƟons
Water and fire infrastructure improvements
Feasibility studies, including:
General market study/economic profile
Bayshore Drive Complete Street technical
feasibility
Bayshore Drive Complete Streets pilot project
Triangle retenƟon pond improvements
Micro‐enterprise and arts incubator
CRA boundary expansion
Grants and funding programs, including:
ResidenƟal improvements grants/loans
Commercial façade improvements
Wall and fence funding for areas with
incompaƟble uses
Public art funding
Economic development incenƟves
Mobile home replacements
Community Land Trust housing construcƟon
Other affordable/workforce housing investments
Other non‐capital expenditures that may arise in the
future and are not yet idenƟfied
Non-Location Specific Capital Projects
Project Type Project Name
Development A. Land AcquisiƟon for Community Land Trust
TransportaƟon, ConnecƟvity, &
Walkability
A. Sidewalk Gap Improvements
B. Bicycle Infrastructure
C. Street Sign/Wayfinding Improvements
D. General MulƟ‐Modal Improvements
Infrastructure A. Water Main and Fire Suppression Upgrades
B. Stormwater Improvements
C. Upgrade Sanitary Sewer Lines
Public Space, Parks, & Open Space
A. Pocket Park Land AcquisiƟon & Development
B. General Parks Improvements
C. Community Safety/Clean‐Up and Neighborhood IniƟaƟves General Improvements
14.B.1.a
Packet Pg. 342 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐7
5.0
1 2
3 4
5 6
7
Focus Corridor
Focus Development Node/IntersecƟon
Mini Triangle/Davis
The Mini Triangle, including CRA‐owned
parcel, is a major commercial redevelopment
opportunity and Focus Development Node
Corridor commercial along Davis
Linwood Avenue another potenƟal area for
redevelopment.
Shadowlawn
Primarily a residenƟal neighborhood with mix
of apartments/duplexes and single‐family
homes around Shadowlawn Elementary
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Airport Pulling
Mix of corridor commercial, larger big‐box
style retail, and County Center
Part of area currently designated as an
AcƟvity Center in Future Land Use Map
Tamiami
Corridor commercial and residences,
including two major malls, Gulfgate Plaza and
Courthouse Shadows)
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Windstar
ResidenƟal is primarily condos and single‐
family homes in gated communiƟes
Includes golf course designated as a
commercial use
North Bayshore
Focus Corridor along Bayshore Drive with
neighborhood commercial (including
Haldeman Creek Entertainment Center near
Creek)
Mix of mulƟ‐ and single‐family residenƟal
Focus IntersecƟon at Bayshore/Thomasson
with planned roundabout
CRA‐owned Focus Development Node (17‐
Acre Site)
South Bayshore
Primarily single‐family residenƟal
neighborhood with Naples Botanical Garden
Wetland consideraƟons for development
5.0.4 Character Areas
The Redevelopment Area Plan framework can be tailored to different sub‐areas depending on their specific
character, needs, and opportuniƟes. Map 5‐ES‐2 lays out these different sub‐areas, or “Character Areas” with
accompanying descripƟons.
14.B.1.a
Packet Pg. 343 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐8
5.0
2
3
4
5
6
7 BAYSHORE DR LINWOOD AVE 1
Map 5‐ES‐2: Character Areas
14.B.1.a
Packet Pg. 344 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐9
5.0
5.0.5 Focus of Redevelopment
The following provides a focus of redevelopment for
each Character Area based on the specific
characterisƟcs described in Map 5‐ES‐2 and the most
relevant redevelopment strategies.
1. Mini Triangle/Davis
Urban‐style mixed use commercial
redevelopment, including capitalizaƟon on the
Mini Triangle as a catalyst development site and
urban‐style parking soluƟons
Park development at retenƟon pond site
Complete Streets design and commercial
redevelopment along Linwood Ave and other
nearby commercial roadways; pedestrian scale
street design between Mini Triangle, Linwood
Ave, and the proposed retenƟon pond park
Improved access to Mini Triangle development
from US 41, Davis Blvd, and Linwood Ave
MulƟ‐modal connecƟvity:
Across Davis Blvd
Between Mini Triangle, Linwood Ave,
proposed retenƟon pond park, and
eastern Triangle neighborhood
To Downtown Naples potenƟally via Davis
Blvd, US 41, and Gordon River Bridge
improvements
AddiƟonal infrastructure improvements: sanitary
sewers, electrical, stormwater
2. Shadowlawn
ResidenƟal structural enhancement and upgrades
Avoidance of incompaƟble uses
TransiƟonal elements between different uses
Infill development on vacant residenƟal lots
Flooding and drainage on neighborhood streets
Complete Street improvements along
Shadowlawn Drive
3. Airport Pulling
TransiƟons between residenƟal neighborhoods
and commercial development
Eventual street enhancements, parƟcularly
connecƟvity across Airport Pulling Rd
Commercial façade improvements
4. Tamiami
ConnecƟvity to Downtown Naples via US 41
Redevelopment of Courthouse Shadows
Tenant opportunity and site improvements for
walkable design at Gulfgate Plaza
5. Windstar
Complete Streets and MSTU improvements along
major community roadways, including Bayshore
Drive, Thomasson Drive, and Hamilton Avenue
Access to Bayview Park
6. North Bayshore
Corridor commercial development along Bayshore
Drive, including Haldeman Creek Entertainment
Center near Creek and creaƟve parking soluƟons
Larger redevelopment opportuniƟes of 17‐Acre
Site and Del’s 24 property
Arts and culture‐oriented development
TransiƟonal elements between corridor
commercial and residenƟal areas along Bayshore
Drive and Thomasson Drive
Development of vacant residenƟal lots
14.B.1.a
Packet Pg. 345 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐10
5.0
Complete Street design along Bayshore Drive and
Thomasson Drive, including Bayshore Drive/
Thomasson Drive roundabout
Neighborhood Complete Streets and trails
ConnecƟons between Sugden Regional Park and
CRA area
Water main and fire suppression upgrades
Flooding and drainage on neighborhood streets
7. South Bayshore
Mobile home and single‐family home residenƟal
improvements, upgrades, affordability
Development of vacant residenƟal lots
Access to Bayview Park
ConnecƟons between CRA and uses to the east,
including East Naples Community Park
Wetland, flooding, and site preparaƟon
consideraƟons for development
Roadway improvements to meet County
engineering standards
Neighborhood Complete Streets
5.0.6 Funding, Projects, &
Initiatives
The Redevelopment Area Plan also provides a
comprehensive list of capital projects and non‐capital
iniƟaƟves in support of the vision with a prioriƟzaƟon
plan and recommendaƟon for allocated funding .
Table 5‐ES‐1 summarizes projected revenues for
various funding sources operaƟng in the CRA area,
including Municipal Service Taxing Units (MSTUs) that
are funding sources independent of Tax Increment
Finance (TIF).
This Plan does not obligate any funding to any projects
listed. This Plan provides a guide and list of both
capital and non‐capital projects that tax increment
revenues can fund if approved by the CRA and
allocated through the standard operaƟng and
procurement guidelines adopted by the Collier County
Board of Commissioners. The Plan sets a framework
based on current condiƟons but also allows for
flexibility in the phasing of projects based on funding
opportuniƟes and community prioriƟes idenƟfied in
annual work plans and capital improvement project
lists.
Figures 5‐ES‐2 through 5‐ES‐4 summarize the funding
breakdown by Ɵmeframe and type of project/
iniƟaƟve. Note that non‐capital projects include
studies, plans, and grant programs. Table 5‐ES‐2
provides an overall summary of TIF revenues and costs
with surpluses and shorƞalls noted for each Ɵme
period (note that some projects are programmed at a
deficit because other funding partners or sources are
anƟcipated). Table 5‐ES‐3 shows CRA project costs
that may also be eligible for Bayshore BeauƟficaƟon
MSTU funds, indicaƟng the potenƟal benefit from
MSTU coordinaƟon.
14.B.1.a
Packet Pg. 346 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐11
5.0
Fund Revenue
Short Term Total Mid Term Total Long Term Total
Total
(1‐5 Yrs) (6‐15 Yrs) (16‐30 Yrs)
Tax Increment (TIF) $10,831,197 $39,256,457 $104,330,124 $154,417,778
Bayshore
BeauƟficaƟon MSTU $7,403,290 $20,956,845 $48,857,829 $77,217,964
Haldeman Creek
MSTU $644,865 $1,831,442 $4,277,648 $6,753,955
Total $18,879,352 $62,044,744 $157,465,601 $238,389,697
Table 5‐ES‐1: Revenue ProjecƟon Summary
14.B.1.a
Packet Pg. 347 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐12
5.0
Total Short‐Term Costs (1‐5 Years):
$25.0 million
Figure 5‐ES‐3: Mid‐term project costs by type
Figure 5‐ES‐2: Short‐term costs by project type
Total Mid‐Term Costs (6‐15 Years):
$57.9 million
14.B.1.a
Packet Pg. 348 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐13
5.0
Figure 5‐ES‐4: Long‐term costs by project type
Total Long‐Term Costs (16‐30 Years):
$74.5 million
Table 5‐ES‐2: Summary of CRA Project Costs and Projected TIF Revenues
Table 5‐ES‐3: Summary of MSTU‐Eligible Costs and Projected MSTU Revenues
MSTU Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ MSTU‐Eligible Projects $13,973,502 $4,121,297 $5,321,297 $4,530,908
Total Right‐of‐Way MSTU Revenue $77,217,964 $7,403,290 $20,956,845 $48,857,829
Difference $63,244,462 $3,281,993 $15,635,548 $44,326,921
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Note: Projects are considered MSTU‐eligible based on those that align with accepted uses of Bayshore Beautification MSTU funds according to Ordinance No. 2013‐68
TIF Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ North of US 41 (Triangle)$42,665,594 $4,916,110 $11,505,545 $26,243,939
Total Capital Costs ‐ South of US 41 (Bayshore)$44,859,243 $7,790,481 $24,978,149 $12,090,612
Total Capital Costs $87,524,836 $12,706,591 $36,483,694 $38,334,552
Total Non‐Capital Costs $69,915,363 $12,315,280 $21,449,912 $36,150,171
Total TIF Revenue $154,417,778 $10,831,197 $39,256,457 $104,330,124
Difference ‐$3,022,421 ‐$14,190,674 ‐$18,677,149 $29,845,401
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
14.B.1.a
Packet Pg. 349 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐14
5.0
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects
Triangle‐ Hotel/
Restaurant/
Office
Parcel at apex currently vacant; CRA‐owned
property under contract for sale and
received PUD zoning for Mixed‐Use project.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Triangle – Flex
Office/
Warehouse
Current mix of commercial and industrial
uses.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Table 5‐ES‐4: Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
5.0.7 2000 & 2019 Plan Comparison
Table 5‐ES‐4 assists in comparing the 2000 Plan to the amended Redevelopment Area Plan, showing a status
update for the various areas and iniƟaƟves idenƟfied for Tax Increment Finance (TIF) funding in the 2000 Plan, as
well as how the Redevelopment Area Plan update responds to the idenƟfied iniƟaƟves. Note that two addiƟonal
redevelopment sites, Naples Plaza and Naples Steel, were idenƟfied for private redevelopment without TIF
assistance (now Naples Bay Club/CoƩages at Naples Bay Resort and Woodspring Suites, respecƟvely). While the
2000 Plan has a strong orientaƟon around these sites and iniƟaƟves, the updated Redevelopment Area Plan is
oriented around general themes of: Land Use and Urban Design; Public Space, Parks, & Open Space;
Development; TransportaƟon, ConnecƟvity, & Walkability; Infrastructure; and Process. As a result, the amended
Redevelopment Plan contains addiƟonal consideraƟons that may not stem directly from the 2000 Plan, including
but not limited to:
A focus on the CRA‐owned 17‐Acre Site west of Sugden Regional Park for catalyst redevelopment
A focus on arts and culture in the CRA area redevelopment vision
ConnecƟons to nearby parks
Land use transiƟons between incompaƟble uses and densiƟes/intensiƟes
More comprehensive infrastructure improvements
14.B.1.a
Packet Pg. 350 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐15
5.0
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects (ConƟnued)
Town Center
(Gulfgate Plaza)
Gulfgate Plaza currently has tenants; consideraƟon
needs to be given to type of establishments
desired for this space. A small business incubator
might be a good use for vacant office on second
floor.
IdenƟfied as an opportunity for new tenancy in
second floor space and to incenƟvize opƟmal
tenant mix and walkable design; Courthouse
Shadows is another large commercial space
providing a redevelopment opportunity (SecƟon
5.3.4)
Entertainment
Center
(Haldeman
Creek)
Three60 Market has been established west of
bridge and south of creek; food truck park
recently opened on north side of creek under
same ownership as Three60 Market. Need for
commercial parking has emerged as an issue in
this area.
RecommendaƟons made to evaluate LDC
changes to facilitate commercial development
such as that in the Bayshore area (SecƟon
5.3.4); commercial parking soluƟons explored
(SecƟon 5.3.5, SecƟon 5.4)
Neighborhood Focus IniƟaƟves
Shadowlawn
The 2000 Plan iniƟaƟve included the following:
New general housing and affordable housing
RehabilitaƟon of affordable housing
Neighborhood gateway features
Traffic calming by closing part of Linwood
Extension of Pelton Ave to Linwood for
improved internal circulaƟon
Current status:
The Shadowlawn improvements delayed due to
recession, warranƟng prioriƟzaƟon of current
study and improvement implementaƟon approach
for area. However, some stormwater planning and
improvements completed for area (see General
Infrastructure Improvements secƟon below).
CRA will generally aim to conƟnue these
Neighborhood Focus IniƟaƟves. Neighborhood
enhancement focused on structural upgrades,
limiƟng uses incompaƟble with the
redevelopment vision, transiƟons between
uses/intensiƟes, infill development on vacant
lots, addressing flooding/drainage, and
complete streets/transportaƟon improvements
that will address streetscape elements such as
lighƟng and traffic calming. These
improvements will likely require strategic
property acquisiƟon and demoliƟon of
structures for redevelopment. Other relevant
iniƟaƟves include gateway design and
coordinaƟon with County sheriff, code
enforcement, and housing agencies to address
quality and supply of housing and streetlighƟng.
See secƟon 5.3 for more informaƟon.
Table 5‐ES‐4 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
14.B.1.a
Packet Pg. 351 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐16
5.0
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
Neighborhood Focus IniƟaƟves (ConƟnued)
Bayshore
The 2000 Plan iniƟaƟve included the following:
Landscaping and beauƟficaƟon along
Bayshore Drive
New affordable housing
RehabilitaƟon of market‐rate and
affordable housing
Botanical Gardens relocaƟon
Design of new neighborhood park and
connecƟon to Sugden Park site
Sabal Bay development (pending legal
acƟons)
Current related efforts include:
BeauƟficaƟon and roadway
improvements planned for Hamilton Ave
and Thomasson Dr, funded by the
Bayshore BeauƟficaƟon MSTU.
AddiƟonal stormwater planning and
improvements completed for area (see
General Infrastructure Improvements
secƟon below).
ResidenƟal units have been built;
substandard housing has been
demolished.
CRA will generally aim to conƟnue these Neighborhood
Focus IniƟaƟves. Redevelopment focus for this
neighborhood split into North and South. North focus:
commercial/catalyst site development, parking, arts
and culture, transiƟon between residenƟal and
commercial, residenƟal infill, comprehensive street
improvements that will address elements such as
streetlighƟng and traffic calming, park connecƟons
(Sugden Regional Park). South focus: residenƟal
upgrades and affordability, residenƟal infill, park access
(East Naples Community Park, Bayview Park), wetlands/
flooding consideraƟons, roadway standards. These
improvements will likely require strategic property
acquisiƟon and demoliƟon of structures for
redevelopment. Other relevant iniƟaƟves include
addiƟonal street/transportaƟon improvements to
address elements such as lighƟng and traffic calming,
as well as coordinaƟon with County sheriff, code
enforcement, and housing agencies to address quality
and supply of housing and streetlighƟng. See SecƟon
5.3 for more informaƟon.
Table 5‐ES‐4: Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
14.B.1.a
Packet Pg. 352 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐17
5.0
Table 5‐ES‐4 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
General Infrastructure Improvements
Triangle
Stormwater
Management
Plan
Need for stormwater improvements idenƟfied
for enƟre CRA area, so planning and
improvement efforts have included both
Triangle and Bayshore neighborhoods,
including the following:
Stormwater plan created for Gateway
Triangle residenƟal area in 2009 and for
Bayshore MSTU area in 2011.
Karen Dr stormwater improvements
completed in 2017.
Pineland Ave stormwater improvements
completed.
RecommendaƟon made to update stormwater
management plan for the enƟre CRA area (SecƟon
5.3.6)
Haldeman
Creek and
Canal System
Dredging Plan
Last major dredging project was in 2006.
Depth assessment will be conducted for creek,
and capital reserves currently being
accumulated for future maintenance or
dredge efforts. Advisory Board voted to
increase millage rate to create dredging plan
when major dredge will be needed; the
millage increase to 1 mil was approved at the
final budget hearing on September 20, 2018.
RecommendaƟon made to coordinate the capital
improvements of the MSTUs, including that used to
maintain Haldeman Creek, in a Capital Improvements
Plan (SecƟon 5.3.7).
Roadway Improvements
US 41 Zoning
Overlay and
Landscaping
Resurfacing and certain safety improvements
currently programmed in FDOT TransportaƟon
Improvement Program.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Davis
Boulevard
StreetlighƟng
and Zoning
Overlay
Resurfacing project beginning as part of FDOT
TransportaƟon Improvement Program
projects.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Bayshore Drive
Landscaping
Roundabout will be put in at Bayshore
and Thomasson as a Bayshore
BeauƟficaƟon MSTU project.
Bayshore Dr needs to be considered for
streetscape and roadway updates via the
Bayshore BeauƟficaƟon MSTU.
RecommendaƟon included to make Complete Streets
comprehensive roadway improvements along Bayshore
Drive and evaluate opportunity to underground
overhead uƟliƟes (see SecƟon 5.3.5, SecƟon 5.3.6, and
capital funding in SecƟon 5.4).
Botanical
Gardens
Support
Botanical Gardens is now located southwest
of the Bayshore Drive/Thomasson Drive
intersecƟon. The CRA currently owns the
17.89‐acre site (“17‐Acre Site”) west of
Sugden Regional Park; the site is targeted for
catalyst development.
Specific planning tasks included for the 17‐Acre Site
that highlight in parƟcular connecƟons to Sugden
Regional Park and a performance space (see SecƟon
5.3.4 and capital and non‐capital improvements in
SecƟon 5.4).
Other TIF‐Funded Projects
14.B.1.a
Packet Pg. 353 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 354 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
INTRODUCTION
Bayshore Gateway Triangle CRA Area Plan–DraŌ March 2019 5‐1‐1
5.1
5.1.1 Vision
The 2019 Redevelopment Area Plan provides an
updated vision and approach for the redevelopment of
the Bayshore Gateway Triangle CRA area in Collier
County (see Map 5‐1‐1). The Plan brings together
informaƟon gathered from technical analysis,
fieldwork observaƟon, and public and agency outreach
(documented in further detail in a separate
Assessment Memo). From these efforts and the
resulƟng themes idenƟfied, an overarching vision
emerged for the future of the CRA area:
This vision provides the guidance for the overall
framework and projects laid out in this
Redevelopment Area Plan for furthering the
revitalizaƟon of the CRA area. This Plan is meant to
provide a paleƩe of opƟons, generated by the
technical analysis, fieldwork observaƟons, and public
and agency outreach, that the CRA can further
explore. Consequently, not all of these suggesƟons will
necessarily be carried through to full implementaƟon.
Full implementaƟon of framework strategies and
projects will be based on further study of capacity,
technical feasibility, and public prioriƟes.
5.1.2 Process
The technical analysis involved in the Redevelopment
Area Plan process included a review of the exisƟng
plans related to the CRA area, as well as spaƟal and
quanƟtaƟve analysis of data related to the CRA area.
The study team also conducted fieldwork to collect
addiƟonal informaƟon and “ground‐truth” findings in
the data. The public and agency outreach consisted of
stakeholder and agency meeƟngs and calls, two public
workshops, and a boat tour of Haldeman Creek and
adjacent canal areas. Figure 5‐1‐1 illustrates the
complete planning process.
5.1.3 Plan Organization
The remaining secƟons of this Plan cover the following
topics:
SecƟon 5.2: Background – historical overview of
the CRA area, including the original 2000 CRA Plan
and status update
SecƟon 5.3: Plan Framework & Elements –
framework of goals, objecƟves, and strategies
related to redevelopment in the CRA area, with
supporƟng informaƟon on exisƟng condiƟons,
opportuniƟes, and approaches for carrying out
strategies
SecƟon 5.4: PrioriƟzaƟon Plan – informaƟon on
revenues; capital project funding and phasing; and
planning, administraƟve, and regulatory iniƟaƟves
SecƟon 5.5: General Requirements – informaƟon
on addiƟonal regulatory requirements for the CRA
Plan and conclusion
SecƟon 5.6: Tax Increment & MSTU EsƟmates—
provides methodology and underlying
assumpƟons for tax increment and Municipal
Service Taxing Unit (MSTU) revenues.
Promote quality of life and economic vitality with a
mixed-income, urban,
multi-modal community that welcomes visitors,
cultivates the area’s artistic and cultural identity,
uplifts unique local destinations, and finds balance
with the natural environment.
14.B.1.a
Packet Pg. 355 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
INTRODUCTION
Bayshore Gateway Triangle CRA Are Plan—DraŌ March 2019 5‐1‐2
5.1
Map 5‐1‐1: Bayshore Gateway Triangle CRA Study Area
14.B.1.a
Packet Pg. 356 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
INTRODUCTION
Bayshore Gateway Triangle CRA Area Plan–DraŌ March 2019 5‐1‐3
5.1
Figure 5‐1‐1: Planning Process
14.B.1.a
Packet Pg. 357 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 358 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐1
5.2
5.2.1 Creation of the CRA
Area
The Bayshore Gateway Triangle CRA area is located
primarily in unincorporated Collier County to the
southeast of the city of Naples (a small porƟon of the
area is in the city of Naples; see Map 5‐1‐1). It is near
the popular desƟnaƟons of Downtown Naples and
coastal beaches and is bisected by US 41, a major
regional thoroughfare. This corridor defines two major
sub‐areas within the larger CRA boundary–—the
Gateway Triangle community north of US 41 and the
Bayshore community south of US 41 (see Map 5‐1‐1
for CRA area and ResoluƟon 2000‐82, Exhibit A at end
of this document for a legal descripƟon of the CRA
boundary).
The CRA was created in 2000 under the jurisdicƟon of
Collier County to facilitate the physical and economic
revitalizaƟon and enhancement of the community. Its
creaƟon was based on documenƟng condiƟons of
blight in a Finding of Necessity study, as required by
Florida Statute 163.340. Table 5‐2‐1 provides an
overview of the findings.
5.2.2 2000 Plan Goals and
Projects
The 2000 Plan laid out visual concept goals and
corresponding redevelopment projects to improve
condiƟons in the CRA area. The projects were planned
out in phases over a 20‐year Ɵme span. Map 5‐2‐1
shows the overall Land Use Plan illustraƟng general
land uses and significant acƟvity centers. The Land Use
Plan suggested a basic regulatory framework that
would guide Future Land Use Map and zoning
amendments to support the redevelopment of the
CRA area.
In addiƟon to the Land Use Plan, the 2000 Plan
provided an Urban Design Framework to illustrate the
following:
1. Primary areas anƟcipated to undergo significant
change via redevelopment or infill development,
receive improvements via neighborhood
improvement strategies, or remain as stable and
planned development areas
2. Basic site design condiƟons recommended to
implement the vision defined in the public
outreach process
3. Primary corridors and areas recommended for
landscape/streetscape improvements in support
of the vision defined in the public outreach
The primary areas anƟcipated to undergo significant
change included:
Triangle area approximately defined by US 41,
Davis Blvd, and a line based on the projected
alignment of Pine St to the north of US 41
Naples Plaza (southwest of Davis Blvd and US 41
intersecƟon) and adjacent properƟes
Gulfgate Plaza as a Town Center
Commercial uses on Naples Steel properƟes
(along US 41) and other properƟes on Gulfgate
ResidenƟal uses south and west of Gulfgate
Infill:
MulƟ‐ and single‐family residenƟal in
Shadowlawn neighborhood
Commercial uses for Haldeman Creek
entertainment center
Mixed mulƟ‐family and commercial uses
along Bayshore Drive north of Lake View
(Lakeview) Dr
ResidenƟal and commercial at Bay Center
area (Bayshore and Thomasson)
14.B.1.a
Packet Pg. 359 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐2
5.2
Main Issue Sub‐Issue Specific LocaƟons MenƟoned
Predominance of defecƟve or
inadequate street layout
Inadequate street layout and
design (including sub‐standard
street widths)
Shadowlawn Dr
Thomasson Dr
Most local streets
Commercial parking problems
Davis Blvd
Airport Rd
Bayshore Rd
US 41
Lack of streetlights along major
arterial and most local streets
Major arterials
Most local streets
Davis Blvd
Lack of sidewalks
Shadowlawn Dr
Bayshore Rd south of
Thomasson Rd
Most local streets
Lack of neighborhood connecƟons ResidenƟal neighborhoods
Faulty lot layout in relaƟon to size,
adequacy, accessibility, or
usefulness
Commercial lots
US 41
Davis Blvd
Between Pine St and US 41
Built density far below approved
density
RMF‐6 residences in Gateway
Triangle area
Not meeƟng lot standards in at
least one respect
RMF‐6 residenƟal properƟes
Bayshore area residences
Unsanitary or unsafe condiƟons
DisproporƟonate lack of plumbing
DisproporƟonate overcrowding
2 unsafe structures
Lack of sidewalks and streetlights
DeterioraƟon of site or other
improvements
Poor drainage of local roads,
surface water management
problems
Other problems
Lack of right‐of‐way for
improvements along Shadowlawn
Dr
No public transportaƟon provided
in CRA area
Housing affordability noted as an
issue in the county and as an issue
that could get worse in the CRA
area
Table 5‐2‐1: Findings of Blighted CondiƟons in CRA Area
14.B.1.a
Packet Pg. 360 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐3
5.2
Other opportuniƟes in the Medium
Intensity residenƟal area of Land Use Plan
The public outreach of the 2000 Plan defined the
establishment of a Neighborhood Focus IniƟaƟve as a
programmaƟc objecƟve. The aim of such a program
was “to coordinate the direcƟon of a variety of public
and quasi‐public services to enhance major residenƟal
porƟons of the project area.” The primary
neighborhoods for improvements specified in the
2000 Plan included:
Bayshore
Shadowlawn
The primary areas for stability and planned
development with low‐intensity residenƟal included:
Windstar
Sabal Bay (Hamilton Bay) development
Site design standards included:
Roof paƩerns reflecƟve of Old Florida
architectural style
Placement of buildings close to street to support
pedestrian acƟvity
Use of recƟlinear block paƩern to strengthen
predominant established character of area
Placement of parking to rear of development sites
The following lays out items covered by the visual
preference statement from the public outreach effort
of the 2000 Plan, which supported the design
standards:
Buildings – represenƟng an “Old Florida” or
“Cracker” style with covered porches, metal roof,
and dormers
Signage – represenƟng low, monument‐style sign
with business logogram (representaƟve sign or
character) suppressed to design of sign’s
background and surrounding landscape planƟng
Pathways – represenƟng sidewalk set back from
curb by distance greater than width of walk and
with planƟng materials and low pedestrian
lighƟng provided between walk and curb
On‐Street Parking – represenƟng street with
narrow planted median and use of angle parking
interspersed with planƟng areas on both sides of
street
Landscaping – represenƟng street with
landscaped median and landscaping and
decoraƟve lighƟng fixtures on edges
Public Spaces – represenƟng pedestrian area with
palms and large pool with water jet fountain
In terms of landscape and streetscape improvements,
the design framework focused on:
Treatments for major roadways, including:
Davis Blvd
Airport Pulling Rd
US 41
Bayshore Dr
Thomasson Dr
Significant gateway intersecƟon designs at
intersecƟons of the above streets as well as:
Shadowlawn Dr south of Davis and North of US 41
Linwood Ave at Airport Pulling Rd
Pelton Ave north of US 41
IntersecƟon proposed at Ɵme of Sabal Bay’s main
east/west street with Bayshore Dr
14.B.1.a
Packet Pg. 361 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐4
5.2
Map 5‐2‐1: Land Use Plan from 2000 CRA Plan
Note: AddiƟonal labels have been added to clarify locaƟon of certain sites and neighborhoods.
Shadowlawn
Neighborhood
Bayshore
Neighborhood
Bayshore
Neighborhood
Windstar
Sabal Bay
Naples
Steel Site
14.B.1.a
Packet Pg. 362 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐5
5.2
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects
Triangle‐ Hotel/
Restaurant/
Office
Parcel at apex currently vacant; CRA‐owned
property under contract for sale and
received PUD zoning for Mixed‐Use project.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Triangle – Flex
Office/
Warehouse
Current mix of commercial and industrial
uses.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Town Center
(Gulfgate Plaza)
Gulfgate Plaza currently has tenants;
consideraƟon needs to be given to type of
establishments desired for this space. A
small business incubator might be a good
use for vacant office on second floor.
IdenƟfied as an opportunity for new tenancy in second
floor space and to incenƟvize opƟmal tenant mix and
walkable design; Courthouse Shadows is another large
commercial space providing a redevelopment
opportunity (SecƟon 5.3.4)
Table 5‐2‐2: Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
Table 5‐2‐2 provides a status update for the various areas and iniƟaƟves idenƟfied for Tax Increment Finance
(TIF) funding in the 2000 Plan, as well as how the Redevelopment Area Plan update responds to the idenƟfied
iniƟaƟves. Note that two addiƟonal redevelopment sites, Naples Plaza and Naples Steel, were idenƟfied for
private redevelopment without TIF assistance (now Naples Bay Club/CoƩages at Naples Bay Resort and
Woodspring Suites, respecƟvely). While the 2000 Plan has a strong orientaƟon around these sites and iniƟaƟves,
the updated Redevelopment Area Plan is oriented around general themes of: Land Use and Urban Design;
Public Space, Parks, & Open Space; Development; TransportaƟon, ConnecƟvity, & Walkability; Infrastructure;
and Process. As a result, the updated Redevelopment Plan contains addiƟonal consideraƟons that may not stem
directly from the 2000 Plan, including but not limited to:
A focus on the CRA‐owned 17‐Acre Site west of Sugden Regional Park for catalyst redevelopment
A focus on arts and culture in the CRA redevelopment vision
ConnecƟons to nearby parks
Land use transiƟons between incompaƟble uses and densiƟes/intensiƟes
More comprehensive infrastructure improvements
14.B.1.a
Packet Pg. 363 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐6
5.2
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects (ConƟnued)
Entertainment
Center
(Haldeman
Creek)
Three60 Market has been established west of
bridge and south of creek; food truck park recently
opened on north side of creek under same
ownership as Three60 Market. Need for
commercial parking has emerged as an issue in
this area.
RecommendaƟons made to evaluate LDC
changes to facilitate commercial development
such as that in the Bayshore area (SecƟon
5.3.4); commercial parking soluƟons explored
(SecƟon 5.3.5, SecƟon 5.4)
Neighborhood Focus IniƟaƟve
Shadowlawn
The 2000 Plan iniƟaƟve included the following:
New general housing and affordable housing
RehabilitaƟon of affordable housing
Neighborhood gateway features
Traffic calming by closing part of Linwood
Extension of Pelton Ave to Linwood for
improved internal circulaƟon
Current status:
The Shadowlawn improvements delayed due to
recession, warranƟng prioriƟzaƟon of current
study and improvement implementaƟon approach
for area. However, some stormwater planning and
improvements completed for area (see General
Infrastructure Improvements secƟon below).
CRA will generally aim to conƟnue these
Neighborhood Focus IniƟaƟves. Neighborhood
enhancement focused on structural upgrades,
limiƟng uses incompaƟble with the
redevelopment vision, transiƟons between
uses/intensiƟes, infill development on vacant
lots, addressing flooding/drainage, and
complete streets/transportaƟon improvements
that will address streetscape elements such as
lighƟng and traffic calming. These
improvements will likely require strategic
property acquisiƟon and demoliƟon of
structures for redevelopment. Other relevant
iniƟaƟves include gateway design and
coordinaƟon with County sheriff, code
enforcement, and housing agencies to address
quality and supply of housing and streetlighƟng.
See secƟon 5.3 for more informaƟon.
Table 5‐2‐2 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
14.B.1.a
Packet Pg. 364 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐7
5.2
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
Neighborhood Focus IniƟaƟves (ConƟnued)
Bayshore
The 2000 Plan iniƟaƟve included the following:
Landscaping and beauƟficaƟon along
Bayshore Drive
New affordable housing
RehabilitaƟon of market‐rate and
affordable housing
Botanical Gardens relocaƟon
Design of new neighborhood park and
connecƟon to Sugden Park site
Sabal Bay development (pending legal
acƟons)
Current related efforts include:
BeauƟficaƟon and roadway
improvements planned for Hamilton Ave
and Thomasson Dr, funded by the
Bayshore BeauƟficaƟon MSTU.
AddiƟonal stormwater planning and
improvements completed for area (see
General Infrastructure Improvements
secƟon below).
ResidenƟal units have been built;
substandard housing has been
demolished.
CRA will generally aim to conƟnue these Neighborhood
Focus IniƟaƟves. Redevelopment focus for this
neighborhood split into North and South. North focus:
commercial/catalyst site development, parking, arts
and culture, transiƟon between residenƟal and
commercial, residenƟal infill, comprehensive street
improvements that will address elements such as
streetlighƟng and traffic calming, park connecƟons
(Sugden Regional Park). South focus: residenƟal
upgrades and affordability, residenƟal infill, park access
(East Naples Community Park, Bayview Park), wetlands/
flooding consideraƟons, roadway standards. These
improvements will likely require strategic property
acquisiƟon and demoliƟon of structures for
redevelopment. Other relevant iniƟaƟves include
addiƟonal street/transportaƟon improvements to
address elements such as lighƟng and traffic calming,
as well as coordinaƟon with County sheriff, code
enforcement, and housing agencies to address quality
and supply of housing and streetlighƟng. See SecƟon
5.3 for more informaƟon.
Table 5‐2‐2 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
14.B.1.a
Packet Pg. 365 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐8
5.2
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
General Infrastructure Improvements
Triangle
Stormwater
Management
Plan
Need for stormwater improvements
idenƟfied for enƟre CRA area, so planning and
improvement efforts have included both
Triangle and Bayshore neighborhoods,
including the following:
Stormwater plan created for Gateway
Triangle residenƟal area in 2009 and for
Bayshore MSTU area in 2011.
Karen Dr stormwater improvements
completed in 2017.
Pineland Ave stormwater improvements
completed.
RecommendaƟon made to update stormwater
management plan for the enƟre CRA area (SecƟon
5.3.6)
Haldeman
Creek and
Canal System
Dredging Plan
Last major dredging project was in 2006.
Depth assessment will be conducted for
creek, and capital reserves currently being
accumulated for future maintenance or
dredge efforts. Advisory Board voted to
increase millage rate to create dredging plan
when major dredge will be needed; the
millage increase to 1 mil was approved at the
final budget hearing on September 20, 2018.
RecommendaƟon made to coordinate the capital
improvements of the MSTUs, including that used to
maintain Haldeman Creek, in a Capital Improvements
Plan (SecƟon 5.3.7).
Roadway Improvements
US 41 Zoning
Overlay and
Landscaping
Resurfacing and certain safety improvements
currently programmed in FDOT
TransportaƟon Improvement Program.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Davis
Boulevard
StreetlighƟng
and Zoning
Overlay
Resurfacing project beginning as part of FDOT
TransportaƟon Improvement Program
projects.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Bayshore Drive
Landscaping
Roundabout will be put in at Bayshore
and Thomasson as a Bayshore
BeauƟficaƟon MSTU project.
Bayshore Dr needs to be considered for
streetscape and roadway updates via the
Bayshore BeauƟficaƟon MSTU.
RecommendaƟon included to make Complete Streets
comprehensive roadway improvements along Bayshore
Drive and evaluate opportunity to underground
overhead uƟliƟes (see SecƟon 5.3.5, SecƟon 5.3.6, and
capital funding in SecƟon 5.4).
Botanical
Gardens
Support
Botanical Gardens is now located southwest
of the Bayshore Drive/Thomasson Drive
intersecƟon. The CRA currently owns the
17.89‐acre site (“17‐Acre Site”) west of
Sugden Regional Park; the site is targeted for
catalyst development.
Specific planning tasks included for the 17‐Acre Site
that highlight in parƟcular connecƟons to Sugden
Regional Park and a performance space (see SecƟon
5.3.4 and capital and non‐capital improvements in
SecƟon 5.4).
Other TIF‐Funded Projects
Table 5‐2‐2 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
14.B.1.a
Packet Pg. 366 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐9
5.2
SƟmulaƟng investment and capitalizing on
development opportuniƟes while also providing
support and protecƟons for exisƟng residents
NavigaƟng various percepƟons of and visions for the
area and incorporaƟng arts and culture into the
vision; markeƟng this vision
TransiƟon between higher‐density mulƟ‐family housing and
lower‐density single‐family housing
ArƟsƟc and cultural elements of the CRA area include murals
SecƟon 5.2.3 and SecƟons 5.3 and 5.4 provide more
informaƟon on these addiƟonal consideraƟons and their
basis.
5.2.3 Bayshore Gateway
Triangle CRA 2019
Perspective
Many of the challenges and efforts idenƟfied in the
2000 Plan are sƟll relevant today. The following are
some of the major ideas emerging from the
Redevelopment Area Plan update process, which
provided the basis for the goals, objecƟves, and
strategies underlying the framework (see SecƟon 5.3)
for this Redevelopment Area Plan:
Improving the compaƟbility of uses and appearance
of the public realm
TransiƟoning between suburban and urban
development style
Balancing regional vs. local transportaƟon needs
and related transportaƟon safety concerns along
major roadways; incorporaƟng a focus on mulƟ‐
modal transportaƟon
Developing in the context of natural condiƟons and
hazards (wetlands, Coastal High Hazard Area,
flooding), including how to address increased
density/intensity
Capitalizing on the valuable assets of the area or
nearby, including parks, natural areas such as the
canal system and Naples beaches, proximity to
Downtown Naples, and tourism while also creaƟng
public spaces that can be claimed by the community
14.B.1.a
Packet Pg. 367 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 368 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐1
5.3
This page is intenƟonally leŌ blank.
14.B.1.a
Packet Pg. 369 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS 5.3 Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐2 Figure 5‐3‐1: Redevelopment Concept Public Space, Parks, & Open Space Triangle RetenƟon Pond Improvements THOMASSON DR BAYSHORE DR N Complete Streets & Trail (Neighborhood) Jeepers Dr. Complete Streets (Major) Bayshore Dr. ‐ US 41 to Thomasson Dr. Complete Streets (Major) Linwood Ave Monument Sign for Gateway IntersecƟon US 41 and Bayshore Dr. DAVIS BLVD AIRPORT PULLING RD Major Corridor Land Use & Design Public Space, Parks, & Open Focus Corridor TransportaƟon, ConnecƟvity, & Walkability Infrastructure Development Concept Map 5.3.1 Conceptual Plan Diagram The planning framework and elements cover a broad range of themes that make up the overall redevelopment approach. Figure 5‐3‐1 provides a Concept Plan illustraƟng aspects of the framework through future land use and capital improvements with associated goals that are more capital intensive, including Land Use & Design; Public Space Parks, & Open Space; Development; TransportaƟon, ConnecƟvity, & Walkability; and Infrastructure. See the map legend on the following page for project descripƟons, addiƟonal capital improvements without specified locaƟons at this Ɵme, and future land use details. The reminder of this chapter provides lays out the framework in more detail by goal. Note that “Major Corridors” are based on highways, minor arterials, and major arterials in the CRA area. 5F 5E 5G 3A 5a 4c 4E 5B 5D 1C 6A 6b 6c 7d 7b 7A 7c 4b 4d 7E 4F 4a 1B 4G 5C 1A 1F 1D 1E 8A 8B 2A 14.B.1.aPacket Pg. 370Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS Bayshore Gateway Triangle CRA Area Plan —DraŌ March 2019 5‐3‐3 5.3 PLANNING FRAMEWORK & ELEMENTS Bayshore Gateway Triangle CRA Area Plan —DraŌ March 2019 5‐3‐4 5.3 This page is intenƟonally leŌ blank. Location-Specific Capital Projects 7 1 3 4 5 6 8 Land Use & Urban Design Projects Gateway IntersecƟon Design Improvements A. Davis Blvd/Airport Pulling Rd B. Davis Blvd/Shadowlawn Dr C. Davis Blvd/US 41 D. US 41/Bayshore Dr E. Thomasson Dr/Dominion Dr F. Us 41/Osceola Ave Development Development Projects Public Space, Parks, & Open Space Projects Parks improvements A. Triangle RetenƟon Pond Improvements TransportaƟon, ConnecƟvity, & Walkability Projects Complete Streets (Major) A. Linwood Ave—Phase I B. Shadowlawn Ave C. Bayshore Dr—Us 41/Thomasson Dr D. Thomasson Dr/Hamilton Ave E. Commercial Dr F. Kirkwood Ave/Kirkwood Ave ConnecƟon G. Pine St ConnecƟon Complete Streets & Trails (Neighborhood) A. Bicycle/Pedestrian Trail B. Jeepers Dr C. Linwood Ave—Phase II D. Republic Dr E. Danford St F. Bay St G. Bayshore Dr—Thomasson Dr/Holly Ave Parking A. Surface/garage parking—Mini Triangle area B. Surface/garage parking—Bayshore area C. Car/boat parking—Bayview Park area General Road Engineering Standard Improvements A. Pine Tree Dr B. Andrews Ave C. Woodside Ave D. Holly Ave E. PalmeƩo Ct Infrastructure Projects Infrastructure A. Underground/Relocate Overhead UƟlity Lines—Linwood Ave and Commercial Dr B. Underground/Relocate Overhead UƟlity Lines—Bayshore Dr A. Development of MulƟ‐Purpose Facility/Structure 2 14.B.1.aPacket Pg. 371Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐5
5.3
Project Type Project Name
Development A. Land AcquisiƟon for Community Land Trust
TransportaƟon, ConnecƟvity, &
Walkability
A. Sidewalk Gap Improvements
B. Bicycle Infrastructure
C. Street Sign/Wayfinding Improvements
D. General MulƟ‐Modal Improvements
Infrastructure A. Water Main and Fire Suppression Upgrades
B. Stormwater Improvements
C. Upgrade Sanitary Sewer Lines
Public Space, Parks, & Open Space
A. Pocket Park Land AcquisiƟon & Development
B. General Parks Improvements
C. Community Safety/Clean‐Up and Neighborhood IniƟaƟves General Improvements
Non-Location Specific Capital Projects
Non-Capital Projects
Projects and iniƟaƟves that are not capital
investments include a variety of plans, studies, and
grant programs in support of redevelopment or
capital project planning throughout the CRA area.
These non‐capital projects and iniƟaƟves include:
CRA operaƟng expenditures and administraƟve
updates
Land Development Code updates
Development support for catalyst development sites
Master planning for:
Stormwater improvements
Arts– and culture‐oriented development and
redevelopment efforts
ImplementaƟon of Complete Streets projects
Community safety and clean‐up
Branding
MarkeƟng and communicaƟons
Water and fire infrastructure improvements
Feasibility studies, including:
General market study/economic profile
Bayshore Drive Complete Street technical
feasibility
Bayshore Drive Complete Streets pilot project
Triangle retenƟon pond improvements
Micro‐enterprise and arts incubator
CRA boundary expansion
Grants and funding programs, including:
ResidenƟal improvements grants/loans
Commercial façade improvements
Wall and fence funding for areas with
incompaƟble uses
Public art funding
Economic development incenƟves
Mobile home replacements
Community Land Trust housing construcƟon
Other affordable/workforce housing investments
Other non‐capital expenditures that may arise in the
future and are not yet idenƟfied
14.B.1.a
Packet Pg. 372 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐6
5.3
Future Land Use DensiƟes
Mixed Use AcƟvity Center
A. Mixed Use—Bayshore/Gateway Triangle Overlay
B. ResidenƟal—Bayshore/Gateway Triangle Overlay; 16 UPGA for area outside of
overlay
Redevelopment Overlay—
ProperƟes with access to US 41
East/Bayshore Dr/Davis Blvd (84)/
west side of Airport‐Pulling Rd1
12 UPA via density pool units (with cap of 97 density pool units per project); limits apply
for projects that do not comply with the requirements for this density increase. The Mini
Triangle Catalyst Site is an excepƟon with a maximum of 12 UPA and is not subject to the
density pool unit requirements. Within this site, there is a Mini‐Triangle Subdistrict that
was approved through Ordinance No. 2018‐23 which amended the Growth
Management Plan and Ordinance No. 2018‐25 which amended the Land Development
Code creaƟng the Mini‐Triangle MPUD to allow for construcƟon of up to, with a mix to
be determined by maximum allowable traffic generaƟon, the following development
plan:
377 mulƟ‐family dwelling units
228 hotel suites
150 assisted living units
200,000 square feet of commercial uses inclusive of 60,000 square feet of self‐
storage and 30,000 square feet of car dealership
Redevelopment Overlay—
ProperƟes having frontage on
one or more of Bayshore Drive,
Davis Boulevard, Airport‐ Pulling
Road (west side only) or US 41
East2
ResidenƟal only: 8 UPA via use of density bonus pool (with cap of 97 density pool units
per project). Eligibility requires that the project:
1. shall be a Planned Unit Development (PUD)
2. shall be a minimum of 3 acres
3. shall be redevelopment of a site
4. consist of all market‐rate units
Limits apply for projects that do not comply with the requirements for this density
increase.
Urban ResidenƟal Subdistrict
(outside Redevelopment Overlay)
Maximum residenƟal density determined through Collier County’s Density RaƟng
System, but shall not exceed 16 UPA except in accordance with Transfers of
Development Rights in the Land Development Code.
Urban Coastal Fringe Subdistrict
(outside of Redevelopment
Overlay)
To facilitate hurricane evacuaƟon and protect the adjacent environmentally sensiƟve
ConservaƟon designated area, residenƟal densiƟes within the Subdistrict shall not
exceed a maximum of 4 UPA, except as allowed in the Density RaƟng System to exceed 4
UPA through provision of Affordable Housing and Transfers of Development Rights, and
except as allowed by certain Future Land Use Element Policies under ObjecƟve 5 in the
Growth Management Plan. New rezones to permit mobile home development within
this Subdistrict are prohibited. Rezones are recommended to be in the form of a PUD.
Future Land Use Densities
The following table shows Future Land Use densiƟes corresponding to designaƟons on the Concept Map (Figure
5‐3‐1). Note that certain projects in the Redevelopment Overlay are eligible for addiƟonal units from a pool of
388; these units are referred to as “density pool units” below. Also note that the enƟre CRA area lies in the
Coastal High Hazard Area, which deducts one unit per gross acre (UPGA) from the eligible base density of four
units per acre (UPA) and does not permit rezones for mobile home development.
1This definiƟon is interpreted broadly to mean properƟes that can gain access to the road(s), whether directly (access point on the road) or via one or more
other roads; it is not viewed narrowly to mean have an access point onto the road(s). As a result, this definiƟon encompasses all properƟes in the Bayshore
Gateway Triangle Redevelopment Overlay except those on east side of Airport Road.
2According to Collier County Growth Management staff, such properƟes must literally have frontage on (abut) one or more of the specified roads.
14.B.1.a
Packet Pg. 373 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐7
5.3
5.3.2 Land Use & Urban Design
The Growth Management Plan and Land Development
Code (LDC) provide tools to shape land use and urban
design, which have a direct impact on the built
environment of an area. This secƟon highlights exisƟng
condiƟons related to various land use types, as well as
ways to promote a defined, harmonious, and urban
visual and land use character tailored to the CRA area,
culƟvaƟng its unique arƟsƟc and cultural idenƟty.
Promote a defined, harmonious, and urban visual
and land use character tailored to the CRA area,
cultivating its unique artistic and cultural identity.
14.B.1.a
Packet Pg. 374 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐8
5.3
Mobile home
Small single‐family near large new single‐family with guest house
Small mulƟ‐family housing
Single‐family housing
Gated community housing
MulƟ‐family housing
Existing Residential Land Use Characteristics
The CRA area has 3,814, dwelling units according to Florida Department of Revenue 2017 data. These units include a
range of housing types from mobile to larger single‐family to mulƟ‐family homes (see Map 5‐3‐2 and corresponding
images). This diversity of types, when coupled with a range of price points, can accommodate a diversity of residents
living in the community. Currently, streets such as Jeepers Drive (picture 3 below) show areas of transiƟon between
larger residenƟal and smaller residenƟal, as well as between smaller single‐family residenƟal and mulƟ‐family on
nearby streets. The vision set forth in the Redevelopment Area Plan aims to guide these transiƟons towards the desired
built environment character laid out for different sub‐areas (see SecƟon 5.3.8).
1 2
3 4
5 6
14.B.1.a
Packet Pg. 375 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐9
5.3
1
4
3
6
5
2
Map 5‐3‐2: ExisƟng ResidenƟal Land Use CharacterisƟcs; Data source: 2017 Florida Department of Revenue
14.B.1.a
Packet Pg. 376 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐10
5.3
Existing Commercial & Industrial Land Use Characteristics
As with housing types, there are a range of commercial types in the CRA area (see Map 5‐3‐3 and corresponding
images). Many commercial sites include on‐site, street‐facing surface parking. The area contains two major mall‐style
commercial spaces, Gulfgate Plaza and Courthouse Shadows. Uses range from restaurants and retail stores to heavier
uses such as auto services. Industrial uses are also present in the Triangle area and northwest of Sugden Park.
New neighborhood commercial on Bayshore Drive— Three60 Market
Mall commercial—Courthouse Shadows
MulƟ‐story strip commercial
Mall commercial—Gulfgate Plaza
Linwood Avenue commercial
VerƟcal mixed‐use
1 2
3 4
5 6
14.B.1.a
Packet Pg. 377 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐11
5.3
1
2
3
5
6
LINWOOD AVE BAYSHORE DR 4
Map 5‐3‐3: Commercial & Industrial Land Use CharacterisƟcs with Non‐ResidenƟal ExisƟng Land Use; Data source: 2017 Florida Department of Reve‐
nue
14.B.1.a
Packet Pg. 378 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐12
5.3
Existing Community-Oriented Uses
Community‐oriented uses support community‐building and provide services via government, faith‐based, non‐profit,
and other enƟƟes. The Redevelopment Area Plan aims to preserve and enhance these uses. Government
establishments in the area include the Bayshore Gateway Triangle CRA Area office, a Naples Fire Rescue staƟon, and
the County Center (see Map 5‐3‐4 and corresponding images). Schools in and near the area include Avalon Elementary,
Shadowlawn Elementary, and The Garden School of Naples (a Montessori school). There are also various arts‐oriented
spaces, places of worship, and non‐profit service providers. EvaluaƟng locaƟons for a library or other public meeƟng
space can also facilitate the addiƟon of community services and spaces.
Bayshore Gateway Triangle CRA Area Office
1
Avalon Elementary School
2
Opera Naples
3
East Naples BapƟst Church
4
Greater Naples Fire Rescue—StaƟon #22
5
Catholic ChariƟes
6
14.B.1.a
Packet Pg. 379 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐13
5.3
1
2
3
4
5
6
Map 5‐3‐4: Community Oriented Land Use CharacterisƟcs with Non‐ResidenƟal ExisƟng Land Use; Data source: 2017 Florida Department of Revenue
14.B.1.a
Packet Pg. 380 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐14
5.3
Objective 1: Promote urban-style
development.
Strategy 1: Coordinate with Collier County Growth
Management and Zoning Divisions to pilot
innovaƟve land use and zoning approaches to
promote more urban‐style development in the
LDC. These approaches might include:
Increasing mixed use designaƟons
Focus increased densiƟes/intensiƟes
along improved roadways (with
consideraƟon of Coastal High Hazard Area
restricƟons)
Roadway design standards to support
mulƟ‐modal transportaƟon (see SecƟon
5.3.5)
Reduced building setbacks
Zoning for live/work spaces
Zoning and incenƟves for accessory
dwelling units
Flexible parking regulaƟons
Strategy 2: In awarding density pool units,
establish eligibility requirements and/or
performance metrics that promote these urban
approaches.
14.B.1.a
Packet Pg. 381 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐15
5.3
Local Mix Use
Promote use of guest houses (shown here in back of main house) as a
way to provide addiƟonal density and potenƟally address
affordability
Local mulƟ‐family housing styles
Character Images
14.B.1.a
Packet Pg. 382 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐16
5.3
Objective 2: Achieve consistent land uses in the CRA
area and sub-areas.
Strategy 1: Use sub‐area (“Character Area”) characterisƟcs
(see SecƟon 5.3.8) to guide land use vision in the CRA area.
Strategy 2: Amend the LDC to limit heavy commercial and
manufacturing/warehouse/storage uses throughout the CRA
area; evaluate incenƟves to encourage transiƟons away from
heavy commercial and manufacturing/warehouse/storage
uses.
Strategy 3: IdenƟfy elements in the LDC to create clear
transiƟonal areas and land use buffers between uses that are
incompaƟble (see Figure 5‐3‐2); coordinate buffers with
related improvements, such as landscaping improvements
via the Bayshore BeauƟficaƟon MSTU.
Strategy 4: Provide funding through CRA‐funded grant
programs for transiƟonal structures (e.g., walls and fences)
between incompaƟble uses. Provide guidance in the
program guidelines to coordinate with related elements,
such as design standards and Bayshore BeauƟficaƟon MSTU
improvements.
Strategy 5: Provide clear guidance in the LDC for new and
emerging uses to ensure consistency with the respecƟve
Character Areas.
14.B.1.a
Packet Pg. 383 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐17
5.3
Land Use Transition Types
There are four main types of land use strategies to transiƟon between differing land use types (Figure 5‐3‐2).
Factors affecƟng use of any given type might include characterisƟcs of the parƟcular site or the general Character Area.
Figure 5‐3‐2: Land Use TransiƟon Types
Building
Parking Lot/Landscape
Intensity of Use
Green/Open Space
14.B.1.a
Packet Pg. 384 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐18
5.3
Focus: transiƟon from interior residenƟal area of Triangle to the major commercial corridors
surrounding it
Strategies:
Put in place land use transiƟon areas of lighter commercial or mulƟ‐family residenƟal near single‐
family residenƟal areas
Promote use of physical barriers/buffers between heavier commercial uses and residenƟal uses
Limit heavier industrial and commercial uses in the Triangle area
Focus: transiƟon from commercial to residenƟal and between different residenƟal densiƟes
Strategies:
Establish land use transiƟon areas to transiƟon from commercial and denser mulƟ‐family along
Bayshore Drive to moderately dense mulƟ‐family residenƟal to single‐family residenƟal
Focus: put in place transiƟon strategies to mesh new development coming online with exisƟng uses
Strategies:
Establish land use transiƟon areas
Needed Land Use Transitions: Uses
Elements to facilitate transiƟons can be helpful where there are dissimilar uses, built forms, or development styles.
Strategies range from land use buffers (e.g., gradual transiƟon in density/intensity, open space buffers; see Figure 5‐3‐2),
physical barriers (e.g, walls, fences, landscaping), or limitaƟons placed on uses incompaƟble with the area’s land use vision.
Map 5‐3‐5 shows the generalized base zoning districts, highlighƟng areas with use boundaries that might benefit from
transiƟon strategies. The highlighted areas are described further below.
1
2
3
14.B.1.a
Packet Pg. 385 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐19
5.3
1
2
3
Map 5‐3‐5: Needed Land Use TransiƟons with Base Zoning
14.B.1.a
Packet Pg. 386 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐20
5.3
Needed Land Use Transitions: Building Heights
IdenƟfying boundaries between different exisƟng zoned building heights can indicate areas where land use transiƟon
approaches may be helpful. Map 5‐3‐6 shows the applicable Mixed Use Overlay Districts that provide more detailed
design standards for the CRA area with highlighted transiƟon areas from Map 5‐3‐4 and maximum zoned heights of
buildings in the table below. Note that there are excepƟons for certain structures in the code (e.g., church spires,
antenna). PUD sites are governed by zoning in their respecƟve ordinances.
Maximum Zoned Height of Building in Feet
House Rowhouse Apartment Mixed‐Use Commercial Civic &
insƟtuƟonal
BMUD‐NC 42 42 42 56 56 42
BMUD‐W 42 42 42 56 56 42
BMUD‐R1 35 35 35 35
BMUD‐R2 35 35 35 35
BMUD‐R3 35 35 35 35
Mixed Use
Overlay
DesignaƟon Mobile
Home
30
BMUD‐R4 35 35
GTMUD‐MXD 42 42 42 56 56 42
GTMUD‐R 35 35 35 35
Needed TransiƟon Area
14.B.1.a
Packet Pg. 387 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐21
5.3
Map 5‐3‐6: Mixed Use Overlay Districts in the CRA Area
14.B.1.a
Packet Pg. 388 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐22
5.3
Strategy 6: Evaluate opportuniƟes for arts‐oriented
code flexibility that will incorporate exisƟng arts
acƟvity such as gallery space.
Objective 3: Achieve a consistent design
character in the CRA area and sub-areas
that cultivates the area’s unique artistic and
cultural identity.
Strategy 1: As part of a CRA‐specific Arts and
Culture Plan (see SecƟon 5.3.4, ObjecƟve 1,
Strategy 5), develop a comprehensive design
approach for the public realm with reference to
specific Character Areas. The approach might
consider:
Architectural styles, including resilient
designs that beƩer manage natural
hazards such as flooding
TransiƟonal elements between Character
Area designs, building mass types, etc.
(see SecƟon 5.3.8)
Design consideraƟons for gateway/focus
intersecƟons
Design consideraƟons for public art
IdenƟficaƟon of public art opportuniƟes
and incenƟves
Design consideraƟons for streetscape
improvements in coordinaƟon with the
Bayshore BeauƟficaƟon MSTU Master Plan
Design consideraƟons for CRA‐funded
grants for façade and other exterior
improvements
IncorporaƟon of urban‐style development
design standards (see SecƟon 5.3.2,
ObjecƟve 1)
Airport Zone height restricƟons
Strategy 2: Fund a commercial façade grant
program for exterior improvements to commercial
buildings not targeted for major redevelopment.
Character Images for Design Style
A number of buildings in the CRA establish a modern
architectural style that the CRA can promote in public
realm design; there are a number of residences with a
more tradiƟonal Florida style that the CRA can also
promote. Art that is incorporated into private
development, but visible in the public realm, can also
contribute to the community character conveyed in
the physical environment (see the character photos on
the facing page). In addiƟon to architectural style, sign
styles can be considered as part of public realm design.
Figure 5‐3‐3 provides potenƟal sign design opƟons for
the Bayshore neighborhood of the CRA area, reflecƟng
the style of exisƟng infrastructure. The CRA can
promote a more modern design for the Triangle area
in the commercial areas targeted for redevelopment.
14.B.1.a
Packet Pg. 389 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐23
5.3
Local residence with modern design style
Opera Naples with modern design style
Modern design of Ankrolab Brewing Co. (Source: Hlevel
Architects, hƩp://hlevel.info/project/ankrolab_bre)
wing_co/)
Local residenƟal design
Local residenƟal design Local residenƟal design
Modern design of The Garden School (Source: Corban
Architecture/Planning/Sustainability, hƩp://
www.davidcorban.com/the‐garden‐school/)
Figure 5‐3‐3: Sign Design Examples
Local residenƟal design
Art in the public realm on Bayshore Dr
14.B.1.a
Packet Pg. 390 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐24
5.3
ExisƟng gateway design near US 41 and Bayshore Drive
Bayshore Drive/Thomasson Drive roundabout rendering
Bayshore Drive flag, lighƟng, bike lane, landscaping, pavement
treatments
Design Treatments & Attributes
Public realm design in the area is important given the emphasis on arts‐oriented development and input from public
outreach efforts indicaƟng architectural style as a way of building a sense of place and community. The Bayshore
BeauƟficaƟon MSTU has contributed significantly to the design of the southern porƟon of the CRA area with streetscape
improvements including lighƟng, flags, landscaping, and the design of the Bayshore/Thomasson roundabout. The CRA
should coordinate with the MSTU for further improvements, including the design of major gateway intersecƟons that can
include signs and public art (see Map 5‐3‐7 for opportuniƟes). Note that gateway intersecƟon opportuniƟes north of US 41
would not qualify for Bayshore BeauƟficaƟon MSTU funds, yet the northern Triangle area can explore the creaƟon of its own
MSTU to fund these and other types of improvements (see SecƟon 5.3.7, ObjecƟve 3, Strategy 2).
MSTU Improvements
Gateway Design OpportuniƟes
1
2
3
14.B.1.a
Packet Pg. 391 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐25
5.3
3
1 BAYSHORE DR HAMILTON AVE THOMASSON DR
2
Map 5‐3‐7: Design Treatments & AƩributes
14.B.1.a
Packet Pg. 392 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐26
5.3
5.3.3 Public Space, Parks,
& Open Space
Public space, parks, and open space types of land use
that serve an important community‐building purpose
with parƟcular design consideraƟons given the variety
of acƟvity they can support. This secƟon focuses on
how to ensure accessible, acƟvated, and well‐
maintained public spaces, parks, and open space.
Ensure accessible, activated, and well-maintained
public spaces, parks, and open space.
Objective 1: Increase access to parks and
public gathering places in the CRA area.
Strategy 1: Coordinate with Collier County Road
Maintenance Division and Parks & RecreaƟon
Division to increase the number and quality of
bicycle and pedestrian connecƟons 1) between
the Bayshore Dr area and neighboring County
parks, including Bayview Park, East Naples
Community Park, and Sugden Regional Park and 2)
running north/south from neighboring County
parks to increase accessibility to the Triangle area
(see SecƟon 5.3.5, ObjecƟve 1, Strategy 6).
Strategy 2: Coordinate with Collier County Road
Maintenance Division and Parks & RecreaƟon
Division in conjuncƟon with Thomasson Ave and
Hamilton Ave MSTU improvements to evaluate
opportuniƟes for 1) maintaining car and boat
parking at Bayview Park and 2) operaƟonal
maintenance at Bayview Park.
Strategy 3: Coordinate with Collier County Public
Services Department to evaluate opportuniƟes for
a park and/or public meeƟng space (e.g., library)
in the CRA area.
Strategy 4: Create a site‐specific park plan for the
exisƟng retenƟon pond in the Triangle area.
Strategy 5: Evaluate opportuniƟes for “pocket
parks” (very small neighborhood park spaces).
Strategy 6: Coordinate with Collier County Parks &
RecreaƟon Division on any general parks
improvements related to CRA development/
redevelopment sites and efforts, including the 17‐
Acre Site (see SecƟon 5.3.4).
Objective 2: Support events in park spaces
geared towards the CRA community.
Strategy 1: Coordinate with Collier County Parks &
RecreaƟon Division to promote park spaces as
venues for CRA community events.
Pedestrian connecƟon between Bayshore neighborhood and Sugden
Regional Park that can serve as an example for addiƟonal connecƟons
14.B.1.a
Packet Pg. 393 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐27
5.3
Park and Connectivity Design
Concepts
The potenƟal park design concept
shown in Figure 5‐3‐4 for the Triangle
stormwater retenƟon pond is based on
previous planning and design efforts for
the pond, with more consideraƟon
given to increasing visibility to enhance
safety in the pond area (a concern
menƟoned during public outreach).
The rendering includes a consideraƟon
for idenƟfying sites for consolidated
public parking, which may take the form
of a garage.
Figure 5‐3‐4: PotenƟal Triangle Stormwater Pond Design Concept
14.B.1.a
Packet Pg. 394 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐28
5.3
Sugden Regional Park: County park that provides inland water access
and water recreaƟon programming. Image source: Collier County
Parks & RecreaƟon Division
Bayview Park: County park that provides access to Haldeman Creek,
the local canals, and the Gulf of Mexico.
Park Opportunity at Stormwater Pond: potenƟal for design, traffic
flow, safety, and flood management improvements.
East Naples Community Park: County park that houses 38 pickleball courts for
sports tourism and local recreaƟonal use; hosts the annual US Open Pickleball
Championship and other pickleball tournaments. Image source: Collier
County Parks & RecreaƟon Division
Naples Botanical Garden: a non‐profit 170‐acre botanical garden with
over 220,000 visitors per year. Also includes meeƟng spaces.
Parks & Open Space
The Redevelopment Area Plan update process idenƟfied parks and open spaces as important community assets,
providing event spaces and opportuniƟes to build a sense of place and community. Park access can be improved by
providing beƩer connecƟons to parks and capitalizing on opportuniƟes for new parks (such as at the Triangle retenƟon
pond and small pocket parks). Expansion of the CRA area to include the parks to the east should also be evaluated since
it may facilitate making connecƟons and other improvements. See Map 5‐3‐8 for exisƟng parks and opportuniƟes.
1 2
3 4
6
Haldeman Creek and Canals: provide access to the Bayshore Drive
commercial area and the Gulf of Mexico. The Haldeman Creek MSTU
funds periodic dredging and maintenance.
5
14.B.1.a
Packet Pg. 395 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐29
5.3
1
2
3
4
6
5
Map 5‐3‐8: Parks & Open Space
14.B.1.a
Packet Pg. 396 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐30
5.3
Objective 3: Ensure a clean and well maintained public realm.
Strategy 1: Coordinate with the Collier County Sheriff’s Office, Collier County Code Enforcement Division,
service providers in the CRA area, and residents and business owners in the CRA area to develop a proacƟve
community safety and clean‐up strategy (inclusive of private property along the canal network) with an aim
at reducing reliance on case‐by‐case enforcement. This effort should focus on residenƟal properƟes and
coordinate with the Community Standards Liaison pilot program of the Collier County Community & Human
Services Division.
Strategy 2: IdenƟfy and document a strategy for canal maintenance in the right‐of way, including seawalls
and mangroves, in coordinaƟon with the Haldeman Creek MSTU Advisory Board.
Table 5‐3‐1 indicates the amount of parks and open space that are in and bordering the CRA area.
DesignaƟon LocaƟon Acreage EsƟmate
Total publicly‐owned
open space within CRA
area
RetenƟon pond site
(northern Triangle area)
6.48
(includes pond)
AddiƟonal open space or
green space in the CRA
area
Botanical Garden
(non‐profit owned) 168
Total open space/green
space in CRA area 174.48
Park space adjacent to
CRA area
Bayview Park
East Naples Community Park
Sugden Regional Park
6.27
120
173.27
Total park, open, or
green space within or
adjacent to CRA area
347.75
Table 5‐3‐1: Amount of Parks and Open Space.
Source: 2017 Florida Department of Revenue and Google Earth calculaƟon
14.B.1.a
Packet Pg. 397 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐31
5.3
5.3.4 Development
Development and redevelopment can improve the
quality and aestheƟcs of the built environment, as well
as generate tax revenue and benefits to property
owners through increased property values. This
development and redevelopment acƟvity also needs to
include protecƟons for exisƟng community members
who may face burdens from the increase in property
values, such as increased costs for renters. This secƟon
provides an approach to foster and guide private
development to enhance community character and
provide increased stability and prosperity for community
members. Also documented are more specific planning
and visioning efforts for two key development
opportuniƟes, at the Mini Triangle and 17‐Acre sites.
Foster and guide private development to enhance
community character and provide increased
stability and prosperity for community members.
Mini Triangle site rendering excerpt; Source: Zyscovich Architects
14.B.1.a
Packet Pg. 398 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐32
5.3
Objective 1: Improve the marketing,
branding, and communication approach for
the CRA area.
Strategy 1: Create a branding strategy for the CRA
area to establish a community vision and
character. This strategy should coordinate with
the Arts and Culture Plan and the Market Study
for the CRA (see SecƟon 5.3.4, ObjecƟve 1,
Strategy 5 and SecƟon 5.3.4, ObjecƟve 3, Strategy
1).
Strategy 2: Create a markeƟng and
communicaƟon strategy for the CRA area to
communicate vision and character with effecƟve
tools (e.g., website, social media, branding
materials). This strategy should coordinate with
the comprehensive design approach developed
for the CRA area (see SecƟon 5.3.2, ObjecƟve 3,
Strategy 1), as well as improved communicaƟon
efforts between the CRA and the community (see
SecƟon 5.3.7, ObjecƟve 1).
Strategy 3: Provide CRA administraƟve materials
(e.g., Advisory Board agendas, budgets, annual
reports) in an accessible and easy‐to‐understand
way.
Strategy 4: Coordinate with the Collier County
Tourist Development Council, Collier County Parks
& RecreaƟon Division, and other jurisdicƟons to
promote the CRA area and its local business and
commercial establishments as part of tourism
development efforts in the area. This should
include coordinaƟon with Collier County Parks &
RecreaƟon related to East Naples Community Park
master planning and pickleball sports tourism.
Strategy 5: Create an Arts and Culture Plan for the
CRA area to incorporate into the overall CRA area
vision. This effort should:
Consider prior arts and culture planning efforts,
such as those related to the Bayshore Cultural
District (ResoluƟon No 2008‐60).
Incorporate an inventory of exisƟng arƟsƟc and
cultural features of the community to elevate.
Include a comprehensive public realm design
approach for the CRA area and sub‐areas (see
SecƟon 5.3.2, ObjecƟve 3, Strategy 1).
Consider housing needs and economic incenƟves
related to arts and culture‐oriented development
(see SecƟon 5.3.4, ObjecƟves 3 and 5).
Include administraƟve needs of implemenƟng the
plan (e.g., an arts commiƩee, addiƟonal staff).
Coordinate with countywide arts and culture
strategic planning efforts.
14.B.1.a
Packet Pg. 399 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐33
5.3
Objective 2: Streamline and clarify the
development process
Strategy 1: Coordinate with Collier County Zoning
Division to clarify LDC requirements related to
development in the CRA area, parƟcularly related
to:
RelaƟonship of overlay zoning to base
zoning
RelaƟonship of various applicable codes to
each other (e.g., LDC, fire code, building
code)
Allowable uses
Strategy 2: Coordinate with Collier County Zoning
Division to evaluate approaches to streamline and
shorten the development review process.
Approaches might include:
DedicaƟng County staff to review projects
within the CRA area and expedite them
through the development process.
Improving coordinaƟon and communicaƟon
between enƟƟes overseeing applicable
codes (e.g., Zoning, Fire Marshall).
IdenƟfying opportuniƟes to increase
reliance on defined criteria for development
approval (as opposed to discreƟonary
approval)
Encouraging design‐build approaches.
Strategy 3: Establish a formal role for the CRA in the
development review process to facilitate
development of projects in the CRA area.
Clearer LDC guidance would help new uses such as microbreweries
US Open Pickleball Championships at East Naples Community Park.
Source: Collier County Parks & RecreaƟon Division, hƩps://
www.facebook.com/CollierParks/photos/
a.852037184807466.1073741827.118036328207559/19606389606
13944/?type=3&theater
ExisƟng arƟsƟc features, such as murals, should be considered in the
Arts and Culture Plan
14.B.1.a
Packet Pg. 400 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐34
5.3
Objective 3: Incentivize desired types of
development.
Strategy 1: Conduct a market study, including
informaƟon on owners of second homes, which is
not captured in typical data sets, to determine
what development will be supported in the CRA
area.
Strategy 2: IdenƟfy incenƟves and targeted
assistance (see Development Assistance and
IncenƟves Examples) for a range of development
and redevelopment, including consideraƟon of
the following types of development and addiƟonal
desirable development supported by the market
study:
Local neighborhood commercial
establishments
Social enterprises and business
opportuniƟes for those with tenuous
livelihoods
Larger catalyst development projects
Arts‐oriented development
Strategy 3: Evaluate and amend as needed current
grant program offerings to reflect new incenƟves
and assistance approaches from SecƟon 5.3.4,
ObjecƟve 3, Strategy 2.
Objective 4: Capitalize on current and
potential real estate and development
opportunities.
Strategy 1: Facilitate tenancy, development, and
redevelopment, parƟcularly for opportuniƟes
along US 41, Linwood Ave and neighboring non‐
residenƟal areas, and Bayshore Dr, through
incenƟves and communicaƟon efforts (see
Development Assistance and IncenƟves
Examples).
Strategy 2: ConƟnue to facilitate exisƟng catalyst
project opportuniƟes on the Mini Triangle and 17‐
Acre sites (see Map 5‐3‐10) to strengthen and
solidify development interest in the CRA area.
Efforts might include assisƟng with coordinaƟon
of property owners in target areas, negoƟaƟng
desired ameniƟes to be incorporated into
proposed development, and providing incenƟves
(see Development Assistance and IncenƟves
Examples).
Strategy 3: Evaluate alternaƟve funding
opportuniƟes, such as private funding and
donaƟons, for capital projects.
Strategy 4: Assess development opportuniƟes for
the AcƟvity Center area, including the Courthouse
Shadows site.
Strategy 5: Evaluate concepts to expand the CRA
boundaries . ConsideraƟons might include the
incorporaƟon of new development opportuniƟes,
such as areas along Thomasson Drive, and the
incorporaƟon of County parks.
14.B.1.a
Packet Pg. 401 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐35
5.3
Development Assistance and Incentives Examples
Density/intensity increases
Impact fee offsets or payment over Ɵme
TIF rebates and TIF money for infrastructure
Land acquisiƟon through CRA for targeted needs,
such as parking and stormwater infrastructure, and
to facilitate redevelopment
Tenant aƩracƟon and relocaƟon support
Micro‐enterprise incubator and technical assistance
support in partnership with other local enƟƟes
PotenƟal Partnership OpportuniƟes for
Micro‐Enterprise Incubator
Incubators can provide workspace and assistance to
micro‐enterprises, parƟcularly small businesses, looking
to get their start in the CRA area. The CRA could
potenƟally partner with exisƟng efforts or collaborate
on new efforts to support the work of incubators. For
example, the Naples Accelerator
(hƩps://naplesaccelerator.com/) provides office space
and ameniƟes and connecƟons to local economic
resources to assist its member businesses. There may
also be interest from other local enƟƟes, such as St.
MaƩhew’s House, in partnering to start a new
incubator. Such partnerships can bring together
organizaƟons to pool capacity and funding to carry out
incubator efforts and can also be used to support arƟsts
and arts‐oriented development, a key aspect of the
CRA’s vision.
Other Partnership OpportuniƟes: Business AssociaƟons
The CRA encourages businesses operaƟng in the area to
form associaƟons and business districts to coordinate
development efforts and potenƟal funding tools such as
MSTUs. Such associaƟons can also serve as important
partners to the CRA in its implementaƟon of
development assistance and incenƟves. Areas where
these associaƟons might be parƟcularly beneficial are
among the Bayshore Drive businesses, the Mini
Triangle are property owners, and the property
owners along Linwood Avenue and Kirkwood
Avenue.
14.B.1.a
Packet Pg. 402 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐36
5.3
Development and Redevelopment Potential
Figure 5‐3‐5 provides a general indicaƟon of the development opportuniƟes in the CRA area, showing vacant land
acreage and the corresponding number of vacant parcels by land use type that could potenƟally be developed
and indicaƟng that most of the vacant acreage is residenƟal. Map 5‐3‐9 indicates where these parcels are located.
As the map indicates, the parcel sizes can run fairly small, so assembly may be a consideraƟon for developers. The
background analysis for the Redevelopment Area Plan also indicates a sizable number of parcels with structures,
parƟcularly single‐family and mobile homes, that might benefit from upgrades to improve their structural
condiƟon. These efforts should take into account any potenƟal increases in prices and costs when units are
upgraded to avoid pricing out residents who find the new price and cost points unaffordable.
Total Vacant Acreage: 186
Figure 5‐3‐5: Vacant Land Acreage DistribuƟon by Land Use Type .
*Note: A 32.5‐acre parcel northwest of the Bayshore/Thomasson intersecƟon is coded as Vacant InsƟtuƟonal but is owned by MaƩamy Naples LLC. (Source:
2017 Florida Department of Revenue)
14.B.1.a
Packet Pg. 403 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐37
5.3
Map 5‐3‐9: Vacant Land Parcels in CRA Area . Note: Vacant insƟtuƟonal land northwest of Bayshore Dr/Thomasson Dr intersecƟon is coded as Va-
cant InsƟtuƟonal but it owned by MaƩamy Naples LLC. (Source: 2017 Florida Department of Revenue)
14.B.1.a
Packet Pg. 404 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐38
5.3
Development & Real Estate Opportunities
The CRA can facilitate development, redevelopment, and tenancy of vacant spaces through incenƟves and
improvements to the surrounding areas. Map 5‐3‐10 and corresponding images show some of the key
opportuniƟes in the CRA area; note that the Mini Triangle site and the 17‐Acre Site contain parcels currently
owned by the CRA.
Linwood Avenue commercial corridor redevelopment
Gulfgate Plaza office tenant opportunity
Del’s 24 redevelopment opportunity
Bayshore Drive commercial corridor redevelopment (including Halde‐
man Creek Entertainment District near Creek)
Courthouse Shadows redevelopment
1
4 3
2
5
14.B.1.a
Packet Pg. 405 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐39
5.3
3
2
Map 5‐3‐10: Development & Real Estate OpportuniƟes with Non‐ResidenƟal ExisƟng Land Use; Data source: 2017 Florida Department of Revenue
LINWOOD AVE BAYSHORE DR 4
5
1
14.B.1.a
Packet Pg. 406 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐40
5.3
Collier County Mobile Home Upgrade Program
Collier County Community & Human Services Division
currently oversees a program that uses State Housing
IniƟaƟves Partnership (SHIP) program funds to replace
mobile homes with more sturdy single‐family modular
homes in response to hurricane damage. In Everglades
City, these homes are elevated on sƟlts. The Bayshore
Gateway Triangle CRA may be able to refine this pro‐
gram to meet the needs of the community to encour‐
age replacement with a more suitable building type for
the area.
Residential Renovation & the FEMA 50% Rule
The FEMA 50% Rule requires that any exisƟng building
within an idenƟfied FEMA Flood Zone will have to be
upgraded to meet current flood standards if improve‐
ments are made that are in excess of 50% of the struc‐
ture value. When determining structure value, only the
value of the improvement itself (exclusive of land value)
is considered. During the building permit review pro‐
cess, the County will require anyone located within a
flood zone to go through a review process to ensure
that proposed improvements are not worth in excess of
50% of the building value. The CRA may consider devel‐
oping partnerships/grants to assist in replacing struc‐
tures to encourage bringing exisƟng buildings up to
code and maintain affordability.
Impact Fee Deferral for Income-Restricted Units
Several ciƟes and counƟes in Florida, including Collier
County, offer impact fee incenƟves for affordable and/
or workforce housing. In Collier County, for‐purchase
and rental units for households with incomes less than
120% of median income in the county qualify for impact
fee deferrals. Deferrals are equivalent to up to 3% of
the prior year’s total impact fee collecƟons, a cap insƟ‐
tuted to minimize revenue lost through the program.
Objective 5: Incorporate protections in de-
velopment efforts to enhance existing
community character and support existing
CRA area residents.
Strategy 1: Establish assistance programs and
incenƟves to protect and enhance exisƟng com‐
munity‐oriented uses and local neighborhood
commercial and single‐family neighborhoods off
the main corridors. Assistance and incenƟve dis‐
tribuƟon might account for building age, struc‐
tural quality, and means of property owners.
Strategy 2: In coordinaƟon with the Collier Coun‐
ty Affordable Housing Advisory CommiƩee, pro‐
mote strategies to maintain current affordable
housing availability in the CRA while improving
baseline quality condiƟons. Strategies to consider
include:
Community land trust
CoordinaƟng with Collier County Com‐
munity & Human Services Division for
mobile home upgrades and replace‐
ments with alternaƟve unit types (see
Housing Assistance and IncenƟves Exam‐
ples)
ResidenƟal renovaƟon loan/grant pro‐
gram
Encouraging use of Collier County’s im‐
pact fee deferral program for income‐
restricted units (see Housing Assistance
and IncenƟves Examples)
14.B.1.a
Packet Pg. 407 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐41
5.3
The County also limits to 225 the number of rental units
receiving deferrals. Impact fees are deferred for owner‐
occupied units unƟl the owner sells, refinances, or
moves out of the home, at which Ɵme fees are due with
interest. Rental unit fees are deferred for a 10‐year pe‐
riod. Historically, this level of deferral has allowed the
program to defer impact fees on approximately 100
homes per year. A pilot program for payment of impact
fees by installments collected through property tax bills
(as an alternaƟve to making the enƟre payment up‐
front) was also planned for the Immokalee CRA area.
The Bayshore Gateway Triangle CRA could support or
replicate the County’s program to defer fees in the
Bayshore Gateway Triangle CRA area; this approach
could also be used to incenƟvize other types of desired
development, as well.
Case InformaƟon Source: Tindale Oliver (August 2017), Impact Fee Incen‐
Ɵves for Affordable/Workforce Housing.
14.B.1.a
Packet Pg. 408 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐42
5.3
5.3.5 Transportation,
Connectivity, & Walkability
Having a variety of transportaƟon opƟons that are
easy and desirable to use are important for all who
live and work in the CRA area. TransportaƟon systems
not only cater to local needs between the CRA area
and places such as Downtown Naples and local work‐
places, but also to more regional traffic moving
through the CRA area on major roadways. In light of
the various needs, this secƟon aims to ensure safety,
comfort, and convenience for various modes within
and connecƟng with the CRA area.
Ensure safety, comfort, and convenience for various
modes within and connecting with the CRA area.
14.B.1.a
Packet Pg. 409 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐43
5.3
Objective 1: Increase safety, comfort, and
connectivity for active transportation modes
(e.g., walking and biking).
Strategy 1: Create a strategy to implement discrete
transportaƟon improvements and more
comprehensive Complete Streets corridor
improvements.
Strategy 2: The effort undertaken for Strategy 1
should include development of a sidewalk master
plan with inclusion of the following:
Visibility assessment related to landscaping
ConsideraƟon of connecƟons to
neighboring parks (see SecƟon 5.3.3,
ObjecƟve 1, Strategy 1 and Strategy 6 in
this secƟon)
CoordinaƟon with roadway and
infrastructure improvements planned and/
or approved for implementaƟon, including
those that may stem from this
Redevelopment Area Planning process or
other agency planning and implementaƟon
efforts (e.g., County and CRA stormwater
master planning).
Strategy 3: IdenƟfy opportuniƟes to coordinate
transportaƟon capital improvements with County/
MPO improvements along major arterials.
Strategy 4: Pilot transportaƟon improvements, such
as elements of Complete Streets corridor
improvements, elements of Bayshore Dr road diet
(traffic lane consolidaƟon), reduced turning radii at
intersecƟons to slow traffic, and addiƟonal
pedestrian crossings, with temporary installaƟons.
These efforts should incorporate community input
and feedback to gauge response to more urban‐
style development and any parƟcular concerns to
address or opportuniƟes on which to capitalize.
These installaƟons can be incorporated into
community events that include educaƟonal
elements on, for example, Complete Streets, the
Vision Zero effort to eliminate bicycle and
pedestrian fataliƟes, and roundabouts.
Strategy 5: Based on input from temporary
installaƟons from Strategy 4, move forward with
veƫng of Bayshore Dr road diet concept scenarios
and traffic analysis.
Strategy 6: Evaluate opportuniƟes for a north/
south bicycle and pedestrian connector in the
eastern Bayshore area with connecƟons to Sugden
Park and East Naples Community Park (see SecƟon
5.3.3, ObjecƟve 1, Strategy 1).
What are Complete Streets?
Streets that “serve the transportaƟon needs of
transportaƟon system users of all ages and abiliƟes,
including pedestrians, bicyclists, transit riders,
motorists, and freight handlers. A transportaƟon
system based on Complete Streets principles can help
to promote safety, quality of life, and economic
development.” ‐ FDOT, CompleƟng Florida’s Streets,
hƩp://www.flcompletestreets.com/files/FDOT‐
CompleteStreets‐Brochure.pdf.
14.B.1.a
Packet Pg. 410 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐44
5.3
Existing Transportation Conditions
Map 5‐3‐11 highlights exisƟng transportaƟon condiƟons idenƟfied by fieldwork. Roadways in the CRA area range from large
arterials carrying regional traffic to small neighborhood streets, many of which dead‐end throughout the CRA area. During
fieldwork, cyclists were noted on the sidewalks of larger arterials such as Davis Boulevard and Airport Pulling Road, and
many bikes were parked at Gulfgate Plaza off of US 41. The MPO and FDOT also idenƟfied Airport Pulling Road and US 41 as
high bike/pedestrian crash corridors. RelaƟve to other streets, Bayshore Drive has a number of improvements, including
bike lanes, sidewalks, and transit shelters, yet it sƟll experiences a lack of parking. There are limited pedestrian connecƟons
to parks from streets off Bayshore Drive; one connecƟon is at Republic Drive. Note that these exisƟng condiƟons are a
general, preliminary assessment, with more detailed measures of exisƟng condiƟons such as trip counts and traffic
modeling anƟcipated as part of follow‐up strategy– and project‐specific evaluaƟon prior to a decision to implement.
Divided arterial with street‐fronƟng parking
Bayshore Drive with sidewalks and bike lanes
Dead‐end neighborhood street
Cyclist on sidewalk of arterial
Bus shelter at Bayshore Drive and Thomasson Drive
Pedestrian bridge to East Naples Community Park
1
3
2
4
5 6
14.B.1.a
Packet Pg. 411 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐45
5.3
1
2
3
4
5
6
Map 5‐3‐11: ExisƟng TransportaƟon CondiƟons with Roadway ClassificaƟons
14.B.1.a
Packet Pg. 412 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐46
5.3
Bicycle & Pedestrian
Curb extensions
General bike accessibility
Pedestrian crossing(s)
Bike lanes
General connecƟvity, walkability
North/south connecƟvity
East/west connecƟvity
Sidewalk(s)
Wayfinding
LighƟng
Road diet (lane reducƟon)
Traffic
Traffic circulaƟon along corridor, including
intersecƟons
Traffic calming
Connect street
Parking
Commercial parking
Parking including boat parking
Specific Transportation Needs & Considerations
Fieldwork, discussions with CRA staff, public outreach, and specific project recommendaƟons from the 2018 Blue
Zones Project/Dan Burden East Naples Discovery Report informed locaƟon‐specific, discrete transportaƟon needs and
consideraƟons in the CRA area (Map 5‐3‐12). Many of these needs and consideraƟons will be addressed through
Complete Streets projects recommended in this Redevelopment Area Plan. Other transportaƟon improvements such as
addressing sidewalk and bike infrastructure gaps, providing parking infrastructure, and providing wayfinding signs will
be addressed through separate project recommendaƟons. Note that “Major Corridors” are designated based on
highways, minor arterials, and major arterials in the area. “Needs Corridors” are designated where needs idenƟfied are
generalized along the length of a roadway segment (related needs are those where labels intersect the corridor on
Map 5‐3‐12).
1
2
3
1
2
Major Corridor Needs Corridor
1
2
3
4
5
6
7
8
9
10
11
14.B.1.a
Packet Pg. 413 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐47
5.3
4 8
3
2
2
8
DAVIS BLVD BAYSHORE DR 7
THOMASSON DR HAMILTON AVE 2
1
1
1
1
1
3
1
3
1
2
1
2
1 10
2
7
7
7
6
7
6
9
5
2
1
11
10 AIRPORT RD S Map 5‐3‐12: TransportaƟon Needs & ConsideraƟons
14.B.1.a
Packet Pg. 414 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐48
5.3
Regional & County Transportation Projects
The projects shown in Map 5‐3‐13 are those idenƟfied in the Collier Metropolitan Planning OrganizaƟon’s Fiscal Year
2017/18 to 2021/22 TransportaƟon Improvement Program (which also features the Collier County five‐year program)
and the trail recommendaƟons from the Comprehensive Pathways Plan update process. These projects will thus be
overseen by regional and county transportaƟon agencies. The full set of recommendaƟons from the Comprehensive
Pathways Plan, once finalized, should also be considered in conjuncƟon with transportaƟon planning and
improvements led by the CRA.
Major Corridor
FDOT TIP Projects
US 41 resurfacing
US 41 signal Ɵming improvements
Davis Boulevard resurfacing
1
3 MPO Pathways Plan Proposed Trail Improvements
Naples Bay Greenway (Sun Trail)
2 County TIP Projects
Davis Boulevard/Airport Pulling Road
intersecƟon improvement
14.B.1.a
Packet Pg. 415 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐49
5.3
DAVIS BLVD BAYSHORE DR THOMASSON DR NAPLES BAY GREENWAY (SUN TRAIL) 3
1 2 AIRPORT PULLING RD Map 5‐3‐13: Regional & County TransportaƟon Projects
14.B.1.a
Packet Pg. 416 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐50
5.3
Potential CRA Complete Streets Projects & Trails
Complete Streets is an approach to comprehensive corridor improvements tailored to the size and land use context of the
corridor. This approach can address many of the major needs and consideraƟons idenƟfied in Map 5‐3‐13, including traffic
calming, sidewalks, bike lanes, lighƟng, wayfinding, on‐street parking, and landscaping. Complete streets improvements can
also be coordinated with other infrastructure improvements, such as water main, fire suppression, and drainage upgrades.
The CRA can take the lead on Complete Streets projects, focusing on the streets listed below categorized. Fieldwork, staff
discussions, public outreach, and prior planning efforts informed which streets were targeted for these improvements.
Map 5‐3‐14 shows recommended projects for neighborhood streets and busier corridors (“Major Complete Streets”).
Suggested improvements for Major Complete Streets corridors may include changes to the roadway for vehicles (such as
the addiƟon of on‐street parking). Neighborhood Complete Streets & Trails recommendaƟons focus primarily on
improvements for pedestrians, cyclists, and other acƟve transportaƟon (see the remainder of SecƟon 5.3.5 for examples of
suggested improvements). ConnecƟvity in terms of desƟnaƟons and network connecƟons was a key consideraƟon in
selecƟon and prioriƟzaƟon of these projects. Note that the length of the bicycle and pedestrian trail will depend on
consideraƟons such as available right‐of‐way; the SecƟon 5.4 capital planning provides an esƟmate for a secƟon between
East Naples Community Park and Sugden Regional park. Also note that the Kirkwood Avenue “connecƟon” between Pine
Street and Shadowlawn and the Pine Street “connecƟon” between Davis and Linwood refer to proposed roadway
extensions that that do not have exisƟng right‐of‐way.
Major Corridor
Major Complete Streets
Linwood Avenue—Phase I
Shadowlawn Drive
Bayshore Drive (north of Thomasson Drive)
Thomasson Drive
Commercial Drive
Kirkwood Ave/Kirkwood Ave ConnecƟon to
Shadowlawn Drive
Pine Street ConnecƟon
2 Neighborhood Complete Streets & Trails
Bay Street
Linwood—Phase II
Danford Street
Hamilton Avenue
Jeepers Drive
Republic Drive
Bayshore Drive (south of Thomasson Drive)
Bicycle/Pedestrian Trail
1
14.B.1.a
Packet Pg. 417 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐51
5.3 HAMILTON BAY ST
JEEPERS
LINWOOD AVE SHADOWLAWN DR 1
DAVIS BLVD
2 BAYSHORE DR THOMASSON DR
2 COMMERCIAL DR 2 BICYCLE & PEDESTRIAN 1 AIRPORT PULLING RD DANFORD
REPUBLIC DR
KIRKWOOD AVE PINE ST 2
Map 5‐3‐14: PotenƟal Complete Streets Projects
14.B.1.a
Packet Pg. 418 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐52
5.3
Character Images for Complete Streets Improvements and Connections
The following images illustrate Complete Streets elements from prior planning efforts for Bayshore Dr and Complete Streets
improvements elsewhere.
These efforts and examples inspired the renderings of possible transformaƟons for Linwood Ave, Bayshore Dr, and Jeepers
Dr (shown in Figures 5‐3‐6 through 5‐3‐9) suggested as part of this Redevelopment Area Plan update effort. As corridors for
potenƟal commercial redevelopment, the Linwood Ave and Bayshore Dr renderings highlight an emphasis on ample
sidewalk space along the landscaping and storefronts. Linwood Ave might promote a more modern design style for lighƟng
and streetscape features as shown in Figure 5‐3‐6 and potenƟally further inspired by the modern style images on page 5‐3‐
22. Bayshore Dr might retain the exisƟng style of streetscape elements in the lighƟng and signs. These renderings can
provide a starƟng point for Complete Streets designs of other busier corridors (see “Major Complete Streets” on Map 5‐3‐
49), with the Linwood Ave design parƟcularly suited as a basis for the suggested re‐designs of Commercial Dr and Kirkwood
Ave.
As a less traveled residenƟal street type, Jeepers Dr shows how people biking, walking, and playing can share the street
space with cars accessing residences. Given that many streets dead‐end and do not allow for through traffic, more
simplified pedestrian infrastructure may be promoted over formal sidewalks. For example, the pedestrian space in the
PotenƟal cross secƟon for Bayshore Dr road diet, as proposed in Trebilcock’s 2017 Parking Needs Analysis. ExisƟng cross secƟon is four‐lane
road with bike lanes and sidewalks
Complete Streets improvement
examples (LeŌ image source:
Wikimedia Commons)
14.B.1.a
Packet Pg. 419 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐53
5.3
Figure 5‐3‐6: PotenƟal Cross SecƟon of Linwood Ave
rendering might be indicated with road paint. The swales have also been retained for water quality consideraƟons, but
incorporate vegetaƟon to improve the visual appearance of swales. Porous pavement may also be an opƟon for the areas
where swales are represented, which might require different maintenance costs (an aspect that would be addressed with a
more detailed follow‐up design evaluaƟon as noted below). LighƟng in provided on one side given the limited road space,
similar to improvements made on Lunar St in the CRA area. This type of design might serve as a starƟng point for the re‐
design of other neighborhood Complete Streets projects (see Map 5‐3‐49).
Note that these proposed cross secƟons are only intended for general, iniƟal illustraƟve purposes; final designs would need
to account for a more detailed study and analysis of factors including engineering consideraƟons, impacts, miƟgaƟon
needs, and potenƟally the increase of alternaƟve transportaƟon methods (see ObjecƟve 2, Strategy 1 of this secƟon for
examples). For example, a follow‐up analysis of a lane reducƟon proposal on Bayshore Drive would need to account for
impacts to Level of Service standards on the roadway and on connecƟng roadways such as US 41, air quality, freight and
evacuaƟon routes, and a variety of other factors. It would also study whether addiƟonal easements would be needed or
desired for a re‐design. PiloƟng temporary versions of these improvements also provides a way to vet the design. This plan
accounts for this follow‐up analysis need and piloƟng with budgeted items for a Bayshore Drive technical feasibility study, a
Complete Streets ImplementaƟon Plan that would provide a next‐level feasibility analysis for these projects, and a Bayshore
Drive pilot project with opportuniƟes for addiƟonal pilots as part of the “other” non‐capital projects budget item (see
SecƟon 5.4 for more informaƟon).
14.B.1.a
Packet Pg. 420 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐54
5.3
Figure 5‐3‐8: PotenƟal Cross SecƟon for Jeepers Dr
Figure 5‐3‐7: PotenƟal Cross SecƟon for Bayshore Dr
14.B.1.a
Packet Pg. 421 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐55
5.3
Figure 5‐3‐9: PotenƟal Aerial Rendering for Jeepers Dr
14.B.1.a
Packet Pg. 422 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐56
5.3
Objective 2: Increase and enhance
alternative vehicle mode options within and
connecting with the CRA area.
Strategy 1: Evaluate opportuniƟes for alternaƟve
transportaƟon methods (e.g., golf carts, electric
shuƩles, other neighborhood/electric vehicles,
shared and/or autonomous vehicles, bikeshare,
water‐borne transportaƟon), including
consideraƟons for partnerships with neighboring
communiƟes.
Strategy 2: Coordinate with Collier County Public
Transit & Neighborhood Enhancement
Department for transit service and faciliƟes
improvements (e.g., more frequent service and
transit stop shelters).
Strategy 3: Evaluate opƟon to expand
TransportaƟon Concurrency ExcepƟon Area
(TCEA) to include enƟre CRA area.
Objective 3: Improve parking options in
commercial areas.
Strategy 1: Evaluate parking concepts for the
Bayshore Dr and Mini Triangle/Linwood Ave
commercial areas, which may include:
Shared parking with shuƩle service,
parƟcularly to meet peak‐season demand
Reduced design requirements for parking
On‐street parking as part of the Bayshore
Dr road diet
Parking garages
Parking miƟgaƟon fee (development pays
for construcƟon of public parking in lieu
of providing parking spaces)
ConsideraƟons for changes in alternaƟve
transportaƟon methods such as those
noted in ObjecƟve 2, Strategy 1 of this
secƟon.
14.B.1.a
Packet Pg. 423 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐57
5.3
Transportation Concurrency Exception Area (TCEA)
Policy 5.4 of the TransportaƟon Element in the Growth Management Plan created the South US 41 TCEA. This
designaƟon allows commercial and residenƟal developments an excepƟon to meeƟng transportaƟon
concurrency standards, which relate to the Ɵming and programming of necessary transportaƟon faciliƟes to
ensure they are generally provided in a Ɵmeframe comparable to the development. (see Policy 5.3 of the Capital
Improvement Element for more details). The strategies developers can use to obtain the excepƟon are intended
to reduce trips or miles traveled in single‐occupancy vehicles, such as incenƟves and ameniƟes to promote
transit, carpooling, telecommuƟng, walking, and biking. This Redevelopment Area Plan reinforces these strategies
by promoƟng mixed‐used and urban land use types that support alternaƟve transportaƟon (see SecƟon 5.3.2).
ObjecƟves 1 and 2 of this secƟon also promote improved faciliƟes for walking, bilking, and transit use. A potenƟal
opƟon to further align the redevelopment efforts of the CRA and the goals of the TCEA is to expand the TCEA to
include all of the CRA area, expanding the excepƟon applicability to further encourage alternaƟve transportaƟon.
South US 41 TCEA (Source: Collier County Growth Management Plan, TransportaƟon Element, Map TR-4)
14.B.1.a
Packet Pg. 424 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐58
5.3
Downtown Naples Mobility and Connectivity Study
This study, completed in 2017, included a recommendaƟon for an improved bicycle and pedestrian pathway on the Gordon
River Bridge (5th Avenue/US 41) that connects Downtown Naples and the Triangle area. The proposed design calls for
narrower travel lanes and removal of the road shoulder to increase the bicycle and pedestrian pathway to 14 feet on either
side of the bridge. If implemented, the responsibility for carrying out the project would be FDOT.
Proposed typical secƟon for Gordon River Bridge bicycle and pedestrian improvement from 2017 Downtown Naples Mobility and ConnecƟvity Study
(Source: City of Naples, hƩps://www.naplesgov.com/sites/default/files/fileaƩachments/streets_amp_stormwater/project/3351
city_council_presentaƟon_201710_final_revisions.pdf)
Objective 4: Improve transportation connections with Downtown Naples.
Strategy 1: Coordinate with the City of Naples to explore and partner on transportaƟon improvements and
approaches serving both Downtown Naples and the CRA area noted in ObjecƟve 2, Strategy 1 of this secƟon.
14.B.1.a
Packet Pg. 425 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐59
5.3
5.3.6 Infrastructure
Infrastructure can be key to facilitaƟng development,
providing the services communiƟes need to funcƟon.
Certain infrastructure, such as for stormwater
management, is parƟcularly important in the CRA
area, which grapples with natural environmental
factors including storms and flooding but also
benefits from a healthy natural environment due to
quality of life factors and tourism. As a result, the
framework for this secƟon aims to provide effecƟve
infrastructure that preserves environmental and
neighborhood design quality through coordinated
improvement planning and funding.
Provide effective infrastructure that preserves
environmental and neighborhood design quality
through coordinated improvement planning and
funding.
Objective 1: Ensure that infrastructure
provided will effectively achieve its primary
purpose without significantly compromising
environmental and neighborhood design
quality.
Strategy 1: Develop a stormwater master plan for
comprehensive infrastructure improvements that
incorporates consideraƟon for the following:
Flood plain designaƟons, including FEMA
flood designaƟons and Coastal High
Hazard requirements
Building and site plan design to respond
to flooding
Primary, secondary, and terƟary
infrastructure improvements (both short‐
and long‐term)
PotenƟal for a bicycle and pedestrian
pathway in easement of north/south
drainage ditch along Sugden Regional Park
Shared maintenance and maintenance
funding between County and CRA
Water quality
Use/design of right‐of‐way areas on local
streets, including an evaluaƟon of turf
block (see page 5‐3‐58)
InnovaƟve techniques to pilot in CRA area,
including green infrastructure
Strategy 2: Coordinate stormwater infrastructure
planning with design of new parks (see SecƟon
5.3.3, ObjecƟve 1).
Strategy 3: Integrate green infrastructure
improvements into landscaping and drainage
improvements, including those funded by the
Bayshore BeauƟficaƟon MSTU.
14.B.1.a
Packet Pg. 426 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐60
5.3
Green Infrastructure Examples
Green infrastructure aims to reduce stormwater runoff and
treat it closer to its source while providing environmental,
social, and economic benefits. The following examples create
surfaces or collecƟon structures that allow stormwater to
infiltrate the underlying or surrounding ground. They also can
help manage stormwater flows and improve water quality of
runoff and oŌen can be combined with vegetaƟon and
landscaping.
InfiltraƟon basin/retenƟon pond – shallow basins or
ponds that collect stormwater and can allow it to
infiltrate the underlying ground
Permeable pavement – pavement that allows water to
flow through and infiltrate the underlying ground
Rain garden – shallow planted basins that allow water to
infiltrate the ground
Bioswales – vegetated or soŌ‐lined channels that collect
and convey, slow, and clean water and let it infiltrate into
the ground
Vegetated planter boxes and bulb‐outs– infiltraƟon areas
with raised edges that can be incorporated into roadway
design features
Tree planƟngs
Vegetated infiltraƟon area in roadway bulb-out in PalmeƩo, FL at
10th Ave W and 5th St W (Source: Google Maps, hƩps://
www.google.com/maps/@27.5151522,-
82.575633,3a,60y,118.29h,75.57t/data=!3m6!1e1!3m4!
1slahgGjvzSzLDetQ43h5HQg!2e0!7i13312!8i6656)
Kissimmee Lakefront Park rain gardens (Source: City of Kissimmee,
hƩps://www.kissimmee.org/Home/Components/News/
News/2208/263?backlist=%2F)
RetenƟon pond ameniƟes in Tampa at E Dr MarƟn Luther King Jr. Blvd and N 19th St (Source: Google Maps, hƩps://www.google.com/maps/@27.9815571,
-82.4391844,3a,60y,90t/data=!3m6!1e1!3m4!1sQJ3uI3LDTatc2Vr7pkfflg!2e0!7i13312!8i6656)
14.B.1.a
Packet Pg. 427 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐61
5.3
Objective 2: Coordinate with other
jurisdictions and government entities for
infrastructure planning and funding.
Strategy 1: IdenƟfy addiƟonal funding
opportuniƟes to supplement capital
improvements funds (e.g., grants).
Strategy 2: Document the project prioriƟzaƟon
strategy to upgrade water lines and fire
suppression systems in coordinaƟon with the City
of Naples.
Strategy 3: As part of the stormwater master plan
(ObjecƟve 1, Strategy 1 of this secƟon),
coordinate with Collier County Stormwater
Management to integrate CRA stormwater
infrastructure planning with County stormwater
planning efforts.
Strategy 4: As part of the stormwater master plan
effort (ObjecƟve 1, Strategy 1 of this secƟon),
coordinate with Collier County Zoning Division to
create right‐of‐way design guidelines for
development that coordinate with Complete
Streets concepts for neighborhood streets.
Strategy 5: Coordinate with Collier County
agencies and uƟlity providers to idenƟfy and
improve other infrastructure including sanitary
sewer lines, roadways that fail to meet minimum
standards, and electrical uƟliƟes idenƟfied to be
placed underground or relocated.
Turf block, shown in the right-of-way area immediately bordering the
street in the photo above, has been used in certain developments in the
Bayshore neighborhood to allow for use of right-of-way space for park-
ing. This opƟon should be evaluated as part of the right-of-way design
consideraƟons in the stormwater master plan update.
14.B.1.a
Packet Pg. 428 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐62
5.3
Need for culverts for flooding,
RetenƟon pond area improvements needed—lighƟng, security, barriers/gates to direct car traffic,
pump improvements for flooding issues
Flooding issues and need for drainage
Flooding issues and need for drainage on side streets off of Bayshore Drive. Note that Pine Tree
Drive, Andrews Avenue, and Woodside Avenue have been idenƟfied as below County standards
(involving for example sufficient right‐of‐way, drainage, paving, or similar elements) in ResoluƟon
2011‐097. These streets should be a focus in stormwater and infrastructure planning to bring
them up to standards.
Flooding issues and need for drainage on Holly Avenue. Holly Avenue also idenƟfied as below
County standards and in need of road engineering improvements (see Item 4 above).
PalmeƩo Court idenƟfied as below County standards and in need of road engineering
improvements (see item 4 above).
Upgrades needed to sanitary sewer capacity in the Triangle area to support new development.
OpportuniƟes to place overhead electric uƟliƟes on Linwood Avenue and Commercial Drive
underground or relocate them.
Infrastructure—Stormwater, Roadway Engineering, Sanitary Sewer, Electric
Stormwater and flooding are major challenges in the CRA area, requiring special aƩenƟon be paid to stormwater
management projects. The CRA has already overseen a successful drainage improvement project on Karen Drive, and
moving forward, will coordinate with the County Stormwater Management SecƟon. Map 5‐3‐15 shows where further
stormwater management improvements are needed based on public outreach. AddiƟonal needs should be idenƟfied
through an updated stormwater master plan for the area. Other idenƟfied infrastructure needs on the map include
upgrading certain roads to meet County standards, upgrading capacity of sanitary sewer infrastructure in certain areas,
and placing underground or relocaƟng overhead electric uƟliƟes in certain areas.
1
2
3
4
5
6
7
14.B.1.a
Packet Pg. 429 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐63
5.3
6
7
9
1
2
3
4
5
6
7
Map 5‐3‐15: Infrastructure Needs—Stormwater, Roadway Engineering, Sanitary Sewer, Electric
14.B.1.a
Packet Pg. 430 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐64
5.3
Water Infrastructure
The City of Naples provides water and water infrastructure for the CRA area, which also supports fire suppression
systems such as fire hydrants. The fire suppression infrastructure can influence the insurance raƟngs for an area. On a
scale of 1 to 10 (with 1 being the best), the CRA area currently has an Insurance Service Office (ISO) raƟng of 4.
according to the Greater Naples Fire Rescue District. In pracƟce, the District typically assigns raƟngs of 4, 9, or 10.
The City is currently in the process of upgrading neighborhood water lines to support hydrants for fire suppression.
Areas highlighted in red on Map 5‐3‐16 indicate water mains that do not meet the standard fire flow requirements
determined by the City of Naples’ potable water model. These mains have potenƟal for replacement to upgrade for fire
flow improvements. However, note that other secƟons of the water mains in the CRA area are older and will need to be
replaced eventually.
There is conƟnued interest on the part of the CRA to idenƟfy and obtain grants to complete this work in partnership
with the City of Naples.
14.B.1.a
Packet Pg. 431 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐65
5.3
Map 5‐3‐16: Water Infrastructure
Areas highlighted in red
indicate water mains that
do not meet the standard
fire flow requirements
determined by the City of
Naples’ potable water
model. These mains have
potenƟal for replacement
to upgrade for fire flow
improvements. However,
note that other secƟons of
the water mains in the CRA
area are older and will
need to be replaced even‐
tually.
14.B.1.a
Packet Pg. 432 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐66
5.3
5.3.7 Process
The substance of the CRA’s planning and
implementaƟon is important, as is the way it carries
out this planning and implementaƟon. In view of the
diversity of communiƟes living and working in the CRA
area, this secƟon lays out a framework to carry out
CRA area planning and implementaƟon efforts to
engage and serve the various communiƟes within the
CRA area.
Carry out CRA area planning and implementation
efforts to engage and serve the various
communities within the CRA area.
Objective 1: Improve approaches and tools
for communicating with communities in the
CRA area and the general public.
Strategy 1: As part of the markeƟng and
communicaƟon strategy (see SecƟon 5.3.4,
ObjecƟve 1, Strategy 2), evaluate communicaƟon
mechanisms and tools that will most effecƟvely
communicate with the various communiƟes in
the CRA area.
Strategy 2: Coordinate with schools and other
community partners to improve outreach and
communicaƟon between the CRA and harder‐to‐
reach populaƟons.
Strategy 3: Provide mulƟ‐lingual communicaƟons
and materials.
Strategy 4: Create a CRA‐specific Capital
Improvement Plan to idenƟfy, prioriƟze, and
effecƟvely communicaƟon near‐term capital
improvements . Coordinate with MSTUs
operaƟng in the CRA area for relevant capital
improvement projects.
Objective 2: Ensure a targeted and
balanced distribution of CRA planning and
implementation efforts.
Strategy 1: Account for both need‐based and
geographic consideraƟons in the distribuƟon of
planning and implementaƟon efforts.
Strategy 2: IdenƟfy street blocks for targeted
comprehensive improvements, with a focus on
blocks that have already received some
improvements and consideraƟon for balanced
distribuƟon of these targeted blocks throughout
the enƟre CRA area.
14.B.1.a
Packet Pg. 433 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐67
5.3
Strategy 3: Update rules and procedures for the CRA
Advisory Board for legal consistency and with
consideraƟon given to a balanced distribuƟon of
planning/implementaƟon efforts and diverse
representaƟon.
Objective 3: Coordinate with MSTUs in the
area and explore opportunities for new
MSTUs.
Strategy 1: Incorporate Haldeman Creek and
Bayshore BeauƟficaƟon MSTU Advisory Boards into
planning and implementaƟon processes for CRA
improvements.
Strategy 2: Explore the opƟon of creaƟng an MSTU
for capital improvements in the Triangle area north
of US 41.
5.3.8 Character Areas
In addiƟon to a diversity of communiƟes in the CRA
area, there is also a diversity of built character.
This secƟon tailors the themaƟc goals, objecƟves, and
strategies of the previous secƟons to specific character
areas within the CRA area as a whole.
The character areas numbered on the Map 5‐3‐17 are
defined by the land use characterisƟcs discussed in the
preceding maps. Key focus nodes, intersecƟons, and
corridors within the character areas that have potenƟal
for redevelopment are noted on the map with the
asterisks and doƩed lines.
For each Character Area, a brief descripƟon is provided
as well as a focus for redevelopment efforts to prioriƟze
framework elements for each area.
14.B.1.a
Packet Pg. 434 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐68
5.3
1 2
3 4
5 6
7
Focus Corridor
Focus Development Node/IntersecƟon
Mini Triangle/Davis
The Mini Triangle, including CRA‐owned
parcel, is a major commercial redevelopment
opportunity and Focus Development Node
Corridor commercial along Davis
Linwood Avenue another potenƟal area for
redevelopment.
Shadowlawn
Primarily a residenƟal neighborhood with mix
of apartments/duplexes and single‐family
homes around Shadowlawn Elementary
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Airport Pulling
Mix of corridor commercial, larger big‐box
style retail, and County Center
Part of area currently designated as an
AcƟvity Center in Future Land Use Map
Tamiami
Corridor commercial and residences,
including two major malls, Gulfgate Plaza and
Courthouse Shadows)
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Windstar
ResidenƟal is primarily condos and single‐
family homes in gated communiƟes
Includes golf course designated as a
commercial use
North Bayshore
Focus Corridor along Bayshore Drive with
neighborhood commercial (including
Haldeman Creek Entertainment District near
Creek)
Mix of mulƟ‐ and single‐family residenƟal
Focus IntersecƟon at Bayshore/Thomasson
with planned roundabout
CRA‐owned Focus Development Node (17‐
Acre Site)
South Bayshore
Primarily single‐family residenƟal
neighborhood with Naples Botanical Garden
Wetland consideraƟons for development
14.B.1.a
Packet Pg. 435 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐69
5.3
2
3
4
5
6
7 BAYSHORE DR LINWOOD AVE 1
Map 5‐3‐17: Character Areas
14.B.1.a
Packet Pg. 436 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐70
5.3
Focus of Redevelopment
The following provides a focus of redevelopment for
each Character Area based on the specific characteris‐
Ɵcs described for Map 5‐3‐17 and the most relevant
strategies.
1. Mini Triangle/Davis
Urban‐style mixed use commercial redevelop‐
ment, including capitalizaƟon on the Mini Triangle
as a catalyst development site and urban‐style
parking soluƟons
Park development at retenƟon pond site
Complete Streets design and commercial redevel‐
opment along Linwood Ave and other nearby
commercial roadways; pedestrian scale street de‐
sign between Mini Triangle, Linwood Ave, and the
proposed retenƟon pond park
Improved access to Mini Triangle development
from US 41, Davis Blvd, and Linwood Ave
MulƟ‐modal connecƟvity:
Across Davis Blvd
Between Mini Triangle, Linwood Ave, pro‐
posed retenƟon pond park, and eastern
Triangle neighborhood
To Downtown Naples potenƟally via Davis
Blvd, US 41, and Gordon River Bridge im‐
provements
AddiƟonal infrastructure improvements: sanitary
sewers, electrical, stormwater
2. Shadowlawn
ResidenƟal structural enhancement and upgrades
Avoidance of incompaƟble uses
TransiƟonal elements between different uses
Infill development on vacant residenƟal lots
Flooding and drainage on neighborhood streets
Complete Street improvements along Shadow‐
lawn Drive
3. Airport Pulling
TransiƟons between residenƟal neighborhoods
and commercial development
Eventual street enhancements, parƟcularly con‐
necƟvity across Airport Pulling Rd
Commercial façade improvements
4. Tamiami
ConnecƟvity to Downtown Naples via US 41
Redevelopment of Courthouse Shadows
Tenant opportunity at Gulfgate Plaza
5. Windstar
Complete Streets and MSTU improvements along
major community roadways, including Bayshore
Drive, Thomasson Drive, and Hamilton Avenue
Access to Bayview Park
6. North Bayshore
Corridor commercial development along Bayshore
Drive, including Haldeman Creek Entertainment
District near Creek and creaƟve parking soluƟons
Larger redevelopment opportuniƟes of 17‐Acre
Site and Del’s 24 property
Arts and culture‐oriented development
TransiƟonal elements between corridor commer‐
cial and residenƟal areas in along Bayshore Drive
and Thomasson Drive
Development of vacant residenƟal lots
Complete Street design along Bayshore Drive and
14.B.1.a
Packet Pg. 437 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐71
5.3
Thomasson Drive, including Bayshore Drive/
Thomasson Drive roundabout
Neighborhood Complete Streets and trails
ConnecƟons between Sugden Regional Park and
CRA area
Water main and fire suppression upgrades
Flooding and drainage on neighborhood streets
7. South Bayshore
Mobile home and single‐family home residenƟal
improvements, upgrades, affordability
Development of vacant residenƟal lots
Access to Bayview Park
ConnecƟons between CRA and uses to the east,
including East Naples Community Park
Wetland, flooding, and site preparaƟon considera‐
Ɵons for development
Roadway improvements to meet County engineer‐
ing standards
Neighborhood Complete Streets
14.B.1.a
Packet Pg. 438 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐72
5.3
This page is intenƟonally leŌ blank.
14.B.1.a
Packet Pg. 439 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 440 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐1
5.4
5.4.1 Prioritization of Projects
& Initiatives
The CRA will need to evaluate and implement or
coordinate on a number of capital improvement
projects and planning, administraƟve, and regulatory
iniƟaƟves to carry out the framework of goals,
objecƟves, and strategies presented in SecƟon 5.3.
Since these projects and iniƟaƟves cannot be
evaluated and carried out all at once, this secƟon
presents a prioriƟzaƟon plan in terms of amount of
funds programmed and project/iniƟaƟve Ɵming. A key
consideraƟon for prioriƟzaƟon is the amount of
funding available for these projects and iniƟaƟves,
discussed more in SecƟon 5.4.2. Other prioriƟzaƟon
criteria to consider that were primarily highlighted in
the public outreach process include:
Funding availability from dedicated or outside
sources (aside from CRA funds)
Magnitude of anƟcipated impact and mulƟplier
effects
Whether planning has already been undertaken or
completed
Other consideraƟons that received sizable posiƟve
responses during the public outreach process
included:
Project Ɵming consideraƟons independent of
prioriƟzaƟon (e.g., Haldeman Creek dredging
should account for Ɵmeframe of sediment build‐
up, a stormwater master plan should be
completed before stormwater improvement
projects)
Ability to address health/safety concerns
AddiƟonal consideraƟons recommended by the
project team based on the Redevelopment Area Plan
update process include:
Degree of need
Geographic distribuƟon of projects in the CRA
area
PrioriƟes idenƟfied during public outreach for the
Redevelopment Area Plan
5.4.2 Financing Plan
The primary funding source for the CRA is Tax
Increment Financing (TIF) revenue generated by the
property within the CRA area. The Bayshore Gateway
Triangle CRA area is able to use County ad valorem tax
revenues generated above the base‐year amount (the
increment) to apply to projects and iniƟaƟves
idenƟfied in this Redevelopment Area Plan.
Figure 5‐4‐1 shows the historic revenue trends and
projected revenues through 2048 based on a low
growth scenario that follows the County’s historic
growth trends with a 4.8% assumed growth rate, a
medium growth scenario that assumes a 5.2% growth
rate, and a high growth scenario that assumes a 5.7%
growth rate. For more informaƟon on the
development of growth scenarios, methods of
revenue calculaƟon, and detailed revenue tables, see
SecƟon 5.6.
Certain parts of the CRA area are also designated as
Municipal Service Taxing Units (MSTUs), which uƟlize
an addiƟonal ad valorem tax for specific purposes.
The CRA can evaluate the opportunity to coordinate
with the MSTUs to provide eligible projects proposed
in this CRA plan.
The Bayshore BeauƟficaƟon MSTU, created in 1997,
applies to most of the CRA area south of US 41 (see
Map 5‐4‐1); revenues from this tax are focused on
streetscape and right‐of‐way improvements (including
right‐of‐way maintenance), with some addiƟonal
provisions for use of funds on other public realm
improvements in the MSTU area. Figure 5‐4‐2 shows
projected revenues through 2048 using the same
growth scenarios developed for the TIF revenue
calculaƟons (see SecƟon 5.6 for more informaƟon and
detailed revenue tables).
A Haldeman Creek MSTU (see Map 5‐4‐2) was created
in 2006 for maintenance dredging and navigaƟonal
marker maintenance within the MSTU boundary.
Figure 5‐4‐3 shows projected revenues through 2048
using the same growth scenarios developed for the TIF
revenue calculaƟons (see SecƟon 5.6 for more
informaƟon and detailed revenue tables).
Other potenƟal funding sources that may be idenƟfied
to supplement the funds above include grants and
funding from partnerships (other agencies and private
14.B.1.a
Packet Pg. 441 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐2
5.4
Map 5‐4‐1: Bayshore BeauƟficaƟon MSTU Area
Note: includes a boundary extension on Thomasson east of the CRA boundary that was pending approval during the development of this Redevelop‐
ment Area Plan.
14.B.1.a
Packet Pg. 442 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐3
5.4
Figure 5‐4‐1: CRA TIF Revenue Scenarios
Figure 5‐4‐2: Bayshore Beau. f caƟon MSTU Revenue Scenarios
Figure 5‐4‐3: Haldeman Creek MSTU Revenue Scenarios
14.B.1.a
Packet Pg. 443 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐4
5.4
Map 5‐4‐2: Haldeman Creek MSTU Area
14.B.1.a
Packet Pg. 444 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐5
5.4
funders). There may also be opportuniƟes in the
future to take on addiƟonal debt to pay for capital
projects with a plan for repayment. More informaƟon
on coordinaƟon and partnerships, including those for
funding opportuniƟes, is discussed in SecƟon 5.4.4.
5.4.3 Projects & Initiatives
Prioritization
Based on available funding and prioriƟzaƟon
consideraƟons, the following sets out the phasing for
recommended projects and iniƟaƟves with
descripƟons. Note that the sunset date for the TIF
Trust Fund is in 2060 (42 years), while the funding
Ɵmeframe for this plan is for 30 years through 2048 .
AddiƟonally, this plan should be re‐evaluated regularly
(e.g., every five years) to keep it relevant and updated
if redevelopment circumstances evolve.
This Plan does not obligate any funding to any projects
listed. This Plan provides a guide and list of both
capital and non‐capital projects that tax increment
revenues can fund if approved by the CRA and
allocated through the standard operaƟng and
procurement guidelines adopted by the Collier County
Board of Commissioners. Projects may require
addiƟonal veƫng and piloƟng to beƩer understand
technical feasibility, impacts, and broader County
implementaƟon prioriƟes prior to approval for
implementaƟon. To this end, planned projects include
technical feasibility studies and pilot projects. As a
result, this capital and non‐capital funding plan is
subject to change as it is re‐evaluated. AddiƟonally,
the Plan sets a framework based on current condiƟons
but also allows for flexibility in the phasing of projects
based on funding opportuniƟes and community
prioriƟes idenƟfied in annual work plans and capital
improvement project lists.
Table 5‐4‐1 summarizes projected revenues for the
30‐year plan period for various funds operaƟng in the
CRA area (including MSTUs). Note that following the
successful sale of the Mini Triangle property
anƟcipated in the first five years, it is expected that
the CRA will have addiƟonal funds of $350,000
available that are currently being held in reserve due
to loan requirements.
Figures 5‐4‐4 through 5‐4‐6 summarize capital and
non‐capital project costs for different increments of
the 30‐year plan period, followed by Tables 5‐4‐2
through 5‐4‐4 which provide a detailed list of projects
and iniƟaƟves. Table 5‐4‐5 compares projected
revenues to esƟmated costs to show deficits and
surpluses. Note that the capital planning includes a
built‐in deficit to indicate where other agencies would
likely help fund projects or other revenue sources
might be sought. Regarding maintenance costs,
maintenance of standard capital improvements is
anƟcipated to be provided and funded by relevant
County agencies, while maintenance for capital
improvements above and beyond County standards
are anƟcipated to be funded by the CRA.
Short Term (1-5 years)
Capital Projects
Linwood Ave Complete Street Phase I – major
Complete Street improvement between
Commercial Dr and Wild Pines Ln including on‐
street parking, lighƟng, sidewalk widening, and
any addiƟonal needed infrastructure
improvements
Thomasson Dr and Hamilton Ave Improvements –
Bayshore BeauƟficaƟon MSTU anƟcipated to fund
project, but any shorƞall could trigger partnership
with CRA funding porƟon
Republic Dr Complete Streets Improvements –
neighborhood‐level Complete Streets
improvements between Bayshore Dr and East
Naples Community Park, including lighƟng,
14.B.1.a
Packet Pg. 445 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐6
5.4
possible sidewalk expansion, any necessary
drainage improvements, and an improved
pedestrian bridge connecƟon to East Naples
Community Park
Danford St Complete Streets Improvements –
neighborhood‐level Complete Streets
improvements between the end of the roadway
and Hamilton Ave
General Parks Improvements in Bayshore Area—
general item to address connecƟons to parks and
ameniƟes, including any associated with the 17‐
Acre Site and Sugden Regional Park
Community Safety/Clean‐Up and Neighborhood
IniƟaƟves General Improvements—general item to
address capital improvements from Community
Safety & Clean‐Up Strategy and Neighborhood
Focus IniƟaƟves; may include projects idenƟfied
based on neighborhood interest to coordinate with
the Sheriff’s Department and Code Enforcement to
educate and provide small capital improvements
Land AcquisiƟon for a Community Land Trust—may
support maintenance of current affordable housing
availability in the CRA area while improving
baseline quality condiƟons; may also support
housing for arƟsts
Bay St Complete Street Improvements –
neighborhood‐level Complete Streets
improvements between Hamilton Ave and the end
of the roadway
Surface Parking Lot in Bayshore Area – to increase
available commercial parking
General Road Engineering Improvements on Pine
Tree Dr and Andrews Dr – to bring these roadways
up to minimum County standards
Jeepers Dr Complete Street Improvements –
neighborhood Complete Streets improvements
between Bayshore Dr and Sugden Regional Park,
including walk lane striping, upgraded bioswales,
lighƟng, and a pedestrian connecƟon to Sugden
Regional Park
Gateway IntersecƟon Design Improvements at US
41/Shadowlawn Dr/Bayshore Dr – sign
improvements in the right‐of‐way and median
areas with an opportunity to showcase public art
Street Sign/Wayfinding Improvements in CRA area
– signs to address branding and bicycle/pedestrian
movement
Sidewalk/Bicycle Infrastructure Program – program
to address gaps in the pedestrian and bicycle
infrastructure networks that are not addressed
through Complete Streets improvements
Other General MulƟ‐Modal Improvements—for
addiƟonal mulƟ‐modal ameniƟes (e.g., bus
shelters)
Stormwater Infrastructure Upgrades/
Improvements
Sanitary Sewer Line Upgrades in Triangle Area – to
increase capacity
Water Line and Fire Suppression Upgrades—to
address infrastructure age and flow requirements
Non-Capital Expenditures
Ongoing OperaƟng Expenses for CRA, including
staff and administraƟon costs
Process Improvements – updated bylaws for CRA
Advisory Board
Land Development Code Updates‐ based on
recommendaƟons from CRA Plan Update
Mini Triangle Development – funding for incenƟves
and other needed support for the development of
the Mini Triangle
17‐Are Development—funding for incenƟves and
other needed support for the development of the
17‐Acre Site.
Gateway Property Development – funding for
potenƟal incenƟve in support of the project at the
apex of Davis Boulevard and Us 41.
Stormwater Master Plan Update – idenƟfy primary,
secondary, and terƟary improvements needed in
the CRA area with a prioriƟzaƟon plan
14.B.1.a
Packet Pg. 446 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐7
5.4
Arts and Culture Plan for CRA Area
Complete Streets ImplementaƟon Plan
Bayview Parking Study – concepts and outreach in
coordinaƟon with Parks & RecreaƟon Division
Community Safety & Cleanup Strategy – strategy to
address code enforcement issues and community
safety
Branding Strategy
MarkeƟng and CommunicaƟon Strategy –
strategies to communicate outcomes from the
branding effort and connect with the various
communiƟes in the CRA area (including hard‐to‐
reach groups) with updated tools including the
website, e‐blast templates, markeƟng materials,
etc.
Market Study/Economic Profile
Bayshore Dr Pilot project – for Complete Street
implementaƟon
Water & Fire Update Strategy – documentaƟon of
what mains and hydrants will be updated and
phasing
Triangle RetenƟon Pond Feasibility Study – finalized
design and engineering for passive park
improvements
Other Non‐Capital OperaƟons and Study
Expenditures—may include a study to expand the
CRA boundary, non‐capital costs associated with
Community Safety & Clean‐Up Plan, non‐capital
costs from Neighborhood Focus IniƟaƟves, or other
expenditures that may arise in the future and are
not yet idenƟfied.
Grants and Programs
ResidenƟal Grant/Loan Programs – for
structural improvements to single‐family
homes
Commercial Façade Program – for areas
that are not a major focus for commercial
redevelopment but that can be enhanced
with exterior façade and structural
improvements
Wall & Fence Funding – for transiƟonal
structures between incompaƟble uses
Public Art Funding –for public art pieces and events
Economic Development IncenƟves Program – for
economic development incenƟves related to
SecƟon 5.3.4 of the Redevelopment Area Plan
Bayshore Bicycle/Pedestrian Feasibility Study
Mobile Home Replacement Fund ‐ for transiƟon of
mobile homes to modular homes or other
appropriate structures
Community Land Trust Housing ConstrucƟon
Other Affordable/Workforce Housing Investments
Mid Term (6-15 years)
Capital Projects
Triangle RetenƟon Pond Improvements ‐
implementaƟon of passive park improvements at
the pond site with any necessary drainage and
connecƟvity improvements
Land AcquisiƟon for Two Pocket Parks (small
neighborhood parks)
Community Safety/Clean‐Up and Neighborhood
IniƟaƟves General Improvements
Land AcquisiƟon for a Community Land Trust
Surface Parking Lot in the Mini Triangle area to
support commercial uses
Development of MulƟ‐Purpose Facility/Structure—
may occur on currently CRA‐owned 17‐Acre Site;
potenƟal uses of the facility/structure may include
a CRA office and/or arts/incubator space
Bicycle and Pedestrian Trail ‐ along Sugden
Regional Park Drainage Ditch to provide north/
south connecƟvity
Commercial Parking Garage on Bayshore Dr ‐
possibly on surface lot included in short‐term
capital projects for commercial parking
14.B.1.a
Packet Pg. 447 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐8
5.4
Bayshore Dr Complete Street – major Complete
Street improvement between US 41 and
Thomasson Dr, including possible lane reducƟon,
on‐street parking, and any addiƟonal needed
infrastructure improvements
Kirkwood Ave Complete Street—Complete Street
improvement potenƟally similar to Linwood Ave
Phase I with potenƟal Shadowlawn Dr connecƟon
Commercial Dr Complete Street—Complete Street
improvement potenƟally similar to Linwood Ave
Phase I
Linwood Ave Complete Street Phase II—
neighborhood Complete Street improvements
between Wild Pines Ln and Airport‐Pulling Rd
Shadowlawn Dr Complete Street – major roadway
Complete Street improvement between Davis Blvd
and US 41, including lighƟng and any addiƟonal
needed infrastructure improvements
Gateway IntersecƟon Design Improvements –
signage and potenƟal public art opportuniƟes for:
Davis Blvd/Airport‐Pulling Rd
Davis Blvd/Shadowlawn Dr
Davis Blvd/US 41
Thomasson Dr/Dominion Dr
US 41/Osceola Ave
General Road Engineering Improvements – to bring
the following roads up to minimum County
standards:
Woodside Ave
Holly Ave
Sidewalk/Bicycle Infrastructure Program
Other General MulƟ‐Modal Improvements
Water Line and Fire Suppression Upgrades—to
address age and flow requirements
Stormwater Infrastructure Upgrades/
Improvements
Undergrounding UƟliƟes along Bayshore Dr—
between US 41 and Thomasson Dr , coordinated
with the Complete Streets project and Bayshore
BeauƟficaƟon MSTU
Non-Capital Expenditures
Ongoing OperaƟng Expenses for CRA
Land Development Code Updates
Bayshore Dr Technical Feasibility Study – for
Complete Street implementaƟon
Microenterprise and Arts Incubator Study—for
concepts and implementaƟon, which could include
an arts focus and/or arts space
Other Non‐Capital OperaƟons and Study
Expenditures—other expenditures that may arise
in the future and are not yet idenƟfied
Grants and Programs
ResidenƟal Grant/Loan Programs – for
structural improvements to single‐family
homes
Commercial Façade Program – for areas
that are not a major focus for commercial
redevelopment but that can be enhanced
with exterior façade and structural
improvements
Wall & Fence Funding – for transiƟonal
structures between incompaƟble uses
Public Art Funding –for public art pieces
and events
Economic Development IncenƟves
Program –for economic development
incenƟves related to SecƟon 5.3.4 of the
Redevelopment Area Plan
Mobile Home Replacement Fund ‐ for
transiƟon of mobile homes to modular
homes or other appropriate structures
Community Land Trust Housing
ConstrucƟon
Other Affordable/Workforce Housing
Investments
14.B.1.a
Packet Pg. 448 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐9
5.4
Long Term (16-30 years)
Capital Projects
Bayshore Dr Complete Street Improvement
between Thomasson Dr and Holly Ave –
neighborhood‐level Complete Street, including any
drainage improvements and connecƟons to
potenƟal Naples Bay Greenway Sun Trail
improvements
Commercial Parking Garage in Mini Triangle Area
possibly on Surface Lot included in Mid‐Term
Capital Projects– to address commercial parking
needs
Pine Street ConnecƟon—between Davis Blvd and
Linwood Ave
Sidewalk/Bicycle Infrastructure Program
Other General MulƟ‐Modal Improvements
Land AcquisiƟon and Development of 4 Pocket
Parks (small neighborhood parks)
Community Safety/Clean‐Up and Neighborhood
IniƟaƟves General Improvements
Water Line and Fire Suppression Upgrades—to
address infrastructure age and flow requirements
Stormwater Infrastructure Upgrades/
Improvements
Underground/Relocate Overhead UƟlity Lines—
Linwood Ave and Commercial Dr
General Road Engineering Improvements – to bring
the following roads up to minimum County
standards:
PalmeƩo Ct
Undergrounding UƟliƟes along Bayshore Dr—
between Thomasson Dr and Holly Ave, coordinated
with Complete Streets project and Bayshore
BeauƟficaƟon MSTU
Non-Capital Expenditures
Ongoing OperaƟng Expenses for CRA
Land Development Code Updates
Other Non‐Capital OperaƟons and Study
Expenditures—other expenditures that may arise
in the future and are not yet idenƟfied
Grants and Programs
ResidenƟal Grant/Loan Programs – for structural
improvements to single‐family homes
Commercial Façade Program – for areas that are
not a major focus for commercial redevelopment
but that can be enhanced with exterior façade and
structural improvements
Wall & Fence Funding – for transiƟonal structures
between incompaƟble uses
Public Art Funding –for public art pieces and events
Economic Development IncenƟves Program –for
economic development incenƟves related to
SecƟon 5.3.4 of the Redevelopment Area Plan
Other Affordable/Workforce Housing Investments
14.B.1.a
Packet Pg. 449 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐10
5.4
Figure 5‐4‐4: Short‐term costs by project type
Total Short‐Term Costs
(1‐5 Years):
$25.0 million
Figure 5‐4‐5: Mid‐term project costs by type
Total Mid‐Term Costs
(6‐15 Years):
$57.9 million
Figure 5‐4‐6: Long‐term costs by project type
Total Long‐Term Costs
(16‐30 Years):
$74.5 million
Short Term Total Mid Term Total Long Term Total
(1‐5 Yrs)(6‐15 Yrs)(16‐30 Yrs)
Tax Increment Financing (TIF)$10,831,197 $39,256,457 $104,330,124 $154,417,778
Bayshore Beautification MSTU $7,403,290 $20,956,845 $48,857,829 $77,217,964
Haldeman Creek MSTU $644,865 $1,831,442 $4,277,648 $6,753,955
TotalFund Revenue
Table 5‐4‐1: Summary of Projected Revenue Estimates
14.B.1.a
Packet Pg. 450 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐11
5.4
Land Use & Urban Design Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Gateway Intersection Design Improvements
Gateway Sign ‐ Davis Blvd/Airport Pulling Rd $17,250 $17,250
Gateway Sign ‐ Davis Blvd/ Shadowlawn Dr $17,250 $17,250
Gateway Sign ‐ Davis Blvd/US 41 $17,250 $17,250
Street Sign/Wayfinding Improvements
Wayfinding Sign Improvements $52,500 $52,500
$104,250 $52,500 $51,750 $0
Public Space, Parks, & Open Space Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Park Improvements
Triangle Retention Pond Improvements $752,605 $752,605
Land Acquisition for Pocket Parks (2 parks)$918,750 $431,250 $487,500
Development of Pocket Parks (2 parks)$169,705 $169,705
Public Space Improvements
Community Safety/Clean‐Up and Neighborhood
Initiatives General Improvements $75,000 $25,000 $25,000 $25,000
$2,916,060 $25,000 $1,208,855 $682,205
Transportation, Connectivity, & Walkability Projects Total Short Term (1‐5 Years)Mid‐Term (6‐15 Years)1 Long Term (16‐30 Years)2
Complete Streets ‐ Major
Linwood Ave. (Phase I)$1,925,186 $1,925,186
Shadowlawn Drive ‐ Installation of Streetlights $379,500 $379,500
Commercial Drive $1,750,961 $1,750,961
Kirkwood Ave./Kirkwood Ave Connection $2,003,588 $2,003,588
Pine Street Connection $2,299,326 $2,299,326
Complete Streets & Trails ‐ Neighborhood
Linwood Ave. (Phase II)$2,046,448 $2,046,448
Parking
Surface Parking Lot ‐ Land Acquisition $862,500 $862,500
Surface Parking Lot – Mini Triangle Area ‐ excludes land
acquisition cost $351,290 $351,290
Commercial Parking Garage (possibly on surface lot) –
Triangle ‐ excludes land acquisition cost $12,374,050 $12,374,050
General Mutli‐Modal Improvements
General Sidewalk/Bicycle Infrastructure Improvements $2,747,555 $430,622 $932,931 $1,384,002
Other General Multi‐Modal Improvements $862,500 $250,000 $287,500 $325,000
$27,602,904 $2,605,808 $8,614,718 $16,382,379
North of US 41 (Triangle)
Sub‐Total
Sub‐Total
Sub‐Total
Table 5‐4‐2: Capital Improvements Project Matrix—North of US 41 (Triangle)
14.B.1.a
Packet Pg. 451 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐12
5.4
Infrastructure Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Other Infrastructure Improvements
Upgrade Sanitary Sewer Lines $1,000,000 $1,000,000
Stormwater Infrastructure Upgrades/Improvements $5,825,000 $250,000 $575,000 $5,000,000
Underground Utility Lines ‐ Linwood Avenue $931,913 $931,913
Underground Utility Lines ‐ Commercial Drive $247,443 $247,443
Water Line and Fire Suppression Upgrades $4,038,023 $482,801 $555,222 $3,000,000
$12,042,379 $1,732,801 $1,130,222 $9,179,356
Total North $43,665,594 $4,916,110 $11,505,545 $26,243,939
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Sub‐Total
Table 5‐4‐2 (continued): Capital Improvements Project Matrix—North of US 41 (Triangle)
14.B.1.a
Packet Pg. 452 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐13
5.4
Table 5‐4‐3: Capital Improvements South of US 41 (Bayshore)
Land Use & Urban Design Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Gateway Intersection Design Improvements
Gateway Sign Improvements at US 41 and Bayshore3 $15,000 $15,000
Gateway ‐ Thomasson Dr/Dominion Dr3 $17,250 $17,250
Gateway US 41/Osceola3 $17,250 $17,250
Street Sign/Wayfinding Improvements
Wayfinding Sign Improvements3 $52,500 $52,500
$102,000 $67,500 $34,500 $0
Public Space, Parks, & Open Space Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Park Improvements
Land Acquisition for Pocket Parks (2 parks)$975,000 $975,000
Development of Pocket Parks (2 parks)$169,705 $169,705
General Parks Development/Improvements $1,000,000 $1,000,000
Public Space Improvements
Community Safety/Clean‐Up and Neighborhood
Initiatives General Improvements $75,000 $25,000 $25,000 $25,000
$2,219,705 $1,025,000 $25,000 $1,169,705
Development Projects Total Short Term (1‐5 Years)Mid‐Term (6‐15 Years)1 Long Term (16‐30 Years)2
Land Acquisition for Community Land Trust $1,000,000 $500,000 $500,000
Development of Multi‐Purpose Facility/Structure $2,250,000 $2,250,000
$3,250,000 $500,000 $2,750,000 $0
South of US 41 (Bayshore)
Sub‐Total
Sub‐Total
Sub‐Total
14.B.1.a
Packet Pg. 453 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐14
5.4
Transportation, Connectivity, & Walkability Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Complete Streets ‐ Major
Bayshore Drive Complete Street – between US 41 and
Thomasson3 $2,875,000 $2,875,000
Thomason Drive and Hamilton Improvements3 $500,000 $500,000
Complete Streets & Trails ‐ Neighborhood
Bicycle and pedestrian trail along Sugden drainage ditch3 $394,073 $394,073
Jeepers Drive Complete Street Improvements3 $491,849 $491,849
Republic Drive Complete Streets improvements3 $506,849 $506,849
Danford Street Complete Streets3 $689,329 $689,329
Bay Street Complete Street Improvements3 $491,849 $491,849
Bayshore Drive Complete Street ‐ Thomasson Dr/Holly
Ave3 $2,600,000 $2,600,000
Parking
Surface Parking Lot at Bayshore and Coco $351,290 $351,290
Commercial Parking Garage (possibly on surface lot) –
Bayshore Drive $11,377,525 $11,377,525
General Road Engineering Standard Improvements
General Road Engineering Improvements – Pine Tree
Drive3 $346,649 $346,649
General Road Engineering Improvements ‐ Andrews
Drive3 $346,649 $346,649
General Road Engineering Improvements ‐ Woodside
Avenue3 $398,647 $398,647
General Road Engineering Improvements ‐ Holly Avenue3 $398,647 $398,647
General Road Engineering Improvements ‐ Palmetto
Court3 $221,905 $221,905
General Multi‐Modal Improvements
General Sidewalk/Bicycle Infrastructure Improvements3 $2,747,555 $430,622 $932,931 $1,384,002
Other General Multi‐Modal Improvements3 $862,500 $250,000 $287,500 $325,000
$25,600,317 $4,405,088 $16,664,322 $4,530,908Sub‐Total
Table 5‐4‐3 (continued): Capital Improvements South of US 41 (Bayshore)
14.B.1.a
Packet Pg. 454 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐15
5.4
Infrastructure Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Other Infrastructure Improvements
Stormwater Infrastructure Upgrades/Improvements3 $5,150,000 $250,000 $2,300,000 $2,600,000
Water Line and Fire Suppression Upgrades $6,317,221 $1,542,894 $1,774,328 $3,000,000
Underground Utility Lines ‐ Bayshore Drive3 $2,220,000 $1,430,000 $790,000
$13,687,221 $1,792,894 $5,504,328 $6,390,000
$44,859,243 $7,790,481 $24,978,149 $12,090,612
$88,524,836 $12,706,591 $36,483,694 $38,334,552
$69,915,363 $12,315,280 $21,449,912 $36,150,171
$158,440,199 $25,021,871 $57,933,606 $74,484,723
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
3 Potentially MSTU‐eligible project; requires coordination and approval of Bayshore Beautification MSTU Advisory Board.
Sub‐Total
Total South
Overall Capital Costs Total
Non‐Capital Costs Total
Total Costs
Table 5‐4‐3 (conƟnued): Capital Improvements South of US 41 (Bayshore)
14.B.1.a
Packet Pg. 455 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐16
5.4
Project Total Short Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Process Improvements – updated bylaws for CRA Advisory Board $25,000 $25,000
Staff and Operating (salaries, benefits, rent, etc.)$53,625,363 $7,110,280 $14,714,912 $31,800,171
Land Development Code Updates‐ based on recommendations from CRA Plan Update $100,000 $25,000 $25,000 $50,000
Mini Triangle Development Support $500,000 $500,000
17‐Acre Development Support $500,000 $500,000
Gateway Property Support $100,000 $100,000
Stormwater Master Plan Update $200,000 $200,000
Arts and Culture Plan for CRA $75,000 $75,000
Complete Streets Implementation Plan $50,000 $50,000
Bayview Parking Study – concepts and outreach in coordination with Parks & Recreation
Division $25,000 $25,000
Community Safety & Cleanup Strategy to address code enforcement issues and community
safety. $15,000 $15,000
Marketing, Branding and communication strategy – website update, e‐blast templates,
marketing materials, etc. $50,000 $50,000
Market Study/Economic Profile $50,000 $50,000
Bayshore Drive Technical Feasibility Study $40,000 $40,000
Bayshore Drive Pilot project $15,000 $15,000
Water & Fire Update Strategy – document what mains and hydrants will be updated and
phasing $50,000 $50,000
Triangle Retention Pond Feasibility Study $25,000 $25,000
Microenterprise and arts incubator Study for concepts and implementation $20,000 $20,000
Other non‐capital operations and study expenditures $750,000 $250,000 $250,000 $250,000
Project Total Short Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Residential Grant/Loan Programs – for structural improvements to single‐family homes $750,000 $125,000 $250,000 $375,000
Commercial Façade Program $1,500,000 $250,000 $500,000 $750,000
Wall & Fence Funding – for funding transitional structures between incompatible uses $750,000 $125,000 $250,000 $375,000
Public Art – funding for public art pieces and events $450,000 $75,000 $150,000 $225,000
Economic Development – funding for economic development incentives listed in
Development Section $750,000 $125,000 $250,000 $375,000
Mobile Home Replacement Fund $1,500,000 $500,000 $1,000,000
Community Land Trust Housing Construction $4,800,000 $1,800,000 $3,000,000
Other Affordable/Workforce Housing Investments $3,200,000 $250,000 $1,000,000 $1,950,000
Totals $69,915,363 $12,315,280 $21,449,912 $36,150,171
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Non‐Capital Expenditures (Studies, Plans, Other)
Grants and Programs
Operations and Studies
Table 5‐4‐4: Non Capital Expenditures
14.B.1.a
Packet Pg. 456 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐17
5.4
5.4.4 Coordination & Partnerships
Many of the items listed in the SecƟon 5.3 framework and capital and non‐capital projects listed in this secƟon
require the CRA to seek approval from and coordinate with other agencies and enƟƟes, which may include
planning and process approval and/or coordinaƟon and idenƟfying opportuniƟes for shared funding.
CoordinaƟon also includes instances in which another agency or enƟty oversees a project or iniƟaƟve directly
with the CRA assisƟng.
As menƟoned in SecƟon 5.4.3, the framework and projects idenƟfied in this plan are suggesƟons to be further
veƩed prior to approval for implementaƟon. This includes review and approval from relevant County staff and
elected officials. Planning and implementaƟon may also include broader coordinaƟon with agencies. Examples
include coordinaƟon with the Collier MPO to share local needs that might inform a state roadway improvement,
as well as coordinaƟng with other Collier County agencies on topics such as Land Development Code changes,
park access, community safety, transit and transportaƟon, and stormwater. The CRA also has opportuniƟes to
coordinate with the City of Naples on transportaƟon planning and water main upgrades. This type of
coordinaƟon might involve design review for projects led by the CRA and seƫng up meeƟngs coinciding with
regular planning and project cycles prior to finalized design phases. Key planning cycles for coordinaƟon include
the TransportaƟon Improvement Program planning by the MPO and capital improvement planning for Collier
County. When working with agencies to idenƟfy shared funding opportuniƟes as a part of these planning and
implementaƟon processes, it is important to recognize exisƟng funding commitments, as well as limitaƟons on
the use of funds. For example, road impact fees in Collier County must be used for capacity expansion, such as
adding a new road or new lanes to an exisƟng road.
Aside from government agencies, the CRA may also have opportuniƟes to partner with local enƟƟes such as
private firms and non‐profits to realize some of its strategies and projects, as well as seek private sponsorships
Examples include potenƟally partnering with the Naples Accelerator , St. MaƩhew’s House, and/or the United
Arts Council on a business/art incubator idea. There may also be opportuniƟes to partner with companies such
as Slidr for alternaƟve vehicle transportaƟon in the area. CoordinaƟon and funding opportuniƟes may also be
idenƟfied as part of private development projects.
TIF Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ North of US 41 (Triangle)$42,665,594 $4,916,110 $11,505,545 $26,243,939
Total Capital Costs ‐ South of US 41 (Bayshore)$44,859,243 $7,790,481 $24,978,149 $12,090,612
Total Capital Costs $87,524,836 $12,706,591 $36,483,694 $38,334,552
Total Non‐Capital Costs $69,915,363 $12,315,280 $21,449,912 $36,150,171
Total TIF Revenue $154,417,778 $10,831,197 $39,256,457 $104,330,124
Difference ‐$3,022,421 ‐$14,190,674 ‐$18,677,149 $29,845,401
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Table 5‐4‐5: Summary of CRA Project Costs and Projected TIF Revenues
14.B.1.a
Packet Pg. 457 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐18
5.4
Lastly, as menƟoned at the beginning of this secƟon, the CRA should look for opportuniƟes to
coordinate with the MSTUs operaƟng in the area to implement capital improvements. Table 5‐4‐6
shows the costs for projects in the CRA prioriƟzaƟon plan that may qualify for Bayshore BeauƟficaƟon
MSTU funds and compares them to the projected revenues for the MSTU. The comparison shows that
the money available would cover these project costs with a sizable amount of funds remaining for other
MSTU projects. Note that the MSTU Advisory Board would need to approve any process or funding
coordinaƟon.
MSTU Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ MSTU‐Eligible Projects $13,973,502 $4,121,297 $5,321,297 $4,530,908
Total Right‐of‐Way MSTU Revenue $77,217,964 $7,403,290 $20,956,845 $48,857,829
Difference $63,244,462 $3,281,993 $15,635,548 $44,326,921
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Note: Projects are considered MSTU‐eligible based on those that align with accepted uses of Bayshore Beautification MSTU funds according to Ordinance No. 2013‐68
Table 5‐4‐6: Summary of MSTU‐Eligible Costs and Projected MSTU Revenues
14.B.1.a
Packet Pg. 458 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐19
5.4
This page is intenƟonally leŌ blank.
14.B.1.a
Packet Pg. 459 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 460 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐1
5.5
5.5.1 Overview of Relevant
Statutes
Community redevelopment areas are created on the
basis of a finding of blight or slum condiƟons, as noted
in SecƟon 163.355 of Florida Statute. Table 5‐2‐1
provided detailed blight condiƟons for the Bayshore
Gateway Triangle CRA area, summarizing informaƟon
from the 2000 Plan. Table 5‐5‐1 shows how the
framework in this Redevelopment Area Plan addresses
the main blight factors idenƟfied. Related capital and
non‐capital projects can also be found in SecƟon 5.4.
In addiƟon, secƟons 163.360 and 163.362 of Florida
Statutes contain specific requirements for community
redevelopment plans. Tables 5‐5‐2 and 5‐5‐3 provide
an overview of the requirements from these statutes
and the locaƟon in this Redevelopment Area Plan
where the relevant informaƟon can be found to saƟsfy
these requirements.
5.5.2 Consistency with the
County’s Comprehensive Plan
This Redevelopment Area Plan sets forth a vision for
the CRA area centered on fostering more urban‐style
development, including mulƟ‐modal corridors, mixed
use projects, and building out to allowable densiƟes.
The Collier County Growth Management Plan largely
supports this vision with the Bayshore Gateway
Triangle Redevelopment Overlay provisions and the
AcƟvity Center designaƟon. The Mixed Use overlays
provided in the Land Development Code further
support these efforts. Development and
redevelopment are thus largely intended to be
completed within the provisions of the Growth
Management Plan as they exist now or indicate where
future amendments may be needed in order to carry
out implementaƟon of acƟon items.
5.5.3 Acquisition, Demolition/
Clearance, & Improvement
In the future, the Redevelopment Agency may choose
to pursue a program of property acquisiƟon and/or
consolidaƟon to realize the redevelopment objecƟves.
These objecƟves might relate to facilitaƟng private
development and providing idenƟfied needed public
uses. If a property is designated for acquisiƟon, the
process must comply with County requirements and/
or State statutes.
The Redevelopment Agency is authorized to demolish,
clear, or move buildings, structures, and other
improvements from any real property acquired in the
redevelopment project area, subject to obtaining
necessary permits.
The CRA may also engage in or assist in site
preparaƟon improvements on properƟes it already
owns or properƟes it acquires in the future to
facilitate development. Other improvements include
general infrastructure and streetscape improvements
that indirectly support development. See SecƟon 5.4.3
for those improvements that are planned for the CRA
to fund. All of these improvements are subject to
obtaining necessary permits.
SecƟon 1.5 further outlines the Agency’s authoriƟes
that governs this area.
5.5.4 Zoning & Comprehensive
Plan Changes
No Growth Management Plan or Land Development
Code changes were brought through an approval
process as part of this planning effort, and no Land
Development Code or Comprehensive Plan changes
are being adopted with the adopƟon of this
Redevelopment Area Plan. However, recommended
changes will be brought for iniƟal consistency review
by Collier County staff and the Collier County Planning
Commission following adopƟon of this plan.
5.5.5 Land Use, Densities, &
Building Requirements
As noted in SecƟon 5.5.4, no Land Development Code
or Comprehensive Plan changes are being adopted
with the adopƟon of this Redevelopment Area Plan.
Consequently, the Redevelopment Area Plan will
follow the land uses, densiƟes, and building
requirements provided in the Growth Management
Plan and the Land Development Code for the Ɵme
being. However, recommended changes will be
brought forth for iniƟal consistency review by Collier
14.B.1.a
Packet Pg. 461 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐2
5.5
Main Issue Relevant Plan SecƟon(s)
Predominance of
defecƟve or inadequate
street layout
SecƟon 5.3.5 addresses street design primarily with Complete Streets iniƟaƟves;
there are addiƟonal improvements for addressing bicycle and pedestrian gaps,
commercial parking need, and addiƟonal bicycle and pedestrian connecƟons.
Faulty lot layout in
relaƟon to size,
adequacy, accessibility,
or usefulness
SecƟon 5.3.4 focuses on specifically on facilitaƟng private development. As part of
these efforts, the CRA can acquire property to merge lots and make them more
easily developed. AddiƟonally, SecƟon 5.3.2 lays out examples of mulƟ‐family
residenƟal that provide examples to achieve higher residenƟal densiƟes where
approved densiƟes are not realized.
Unsanitary or unsafe
condiƟons
SecƟons 5.3.3 and 5.3.4 contain strategies to address structural upgrades and public
realm clean‐up and improvements. SecƟons 5.3.2 and 5.3.4 also address residenƟal
types and approaches to affordability that can address overcrowding. SecƟon 5.3.5
highlights lighƟng and other transportaƟon safety improvements, parƟcularly for
cyclists and pedestrians.
DeterioraƟon of site or
other improvements
(drainage and surface
water management)
SecƟon 5.3.6 focuses on infrastructure improvements, including those for
stormwater.
Other problems: Lack of
right‐of‐way for
Shadowlawn Drive
improvements
SecƟon 5.3.5 includes improvements for Shadowlawn Drive.
Other problems: Lack of
public transportaƟon SecƟon 5.3.5 includes a coordinaƟon strategy for public transit in the CRA area.
Other problems: housing
affordability SecƟon 5.3.4 includes example strategies to address housing affordability issues.
Table 5‐5‐1: SecƟons of Redevelopment Area Plan that address blight condiƟons
14.B.1.a
Packet Pg. 462 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐3
5.5
SecƟon 163.360, F.S. Requirements Relevant Redevelopment Area
Plan SecƟon
Conformity to the Growth Management Plan SecƟon 5.5.2
Zoning and planning changes SecƟon 5.5.4
Land uses, maximum densiƟes, and building requirements
SecƟon 5.3.1, Maps 5‐3‐5 and 5‐
3‐6, SecƟon 5.5.5; for general
consideraƟons to guide these
requirements, see SecƟon 5.3.2
Land acquisiƟon, demoliƟon, clearance and site preparaƟon,
redevelopment, improvements, and rehabilitaƟon proposed to carry out
the Redevelopment Area Plan
SecƟons 5.4.3 and 5.5.3
Affordable housing provision SecƟon 5.3.4‐ ObjecƟve 5
Table 5‐5‐2: SecƟon 163.360, F.S. Requirements for Redevelopment Area Plan
14.B.1.a
Packet Pg. 463 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐4
5.5
SecƟon 163.362, F.S. Requirements Relevant Redevelopment Area
Plan SecƟon
Legal descripƟon of CRA area boundaries and reason behind establishing
such boundaries
ResoluƟon 2000‐82, Exhibit A at
end of this document and
ResoluƟon 2000‐83
Approximate amount of open space to be provided shown by diagram and
in general terms
SecƟon 5.3.3‐Table 5‐3‐1 and
Map 5‐3‐8
Property intended for parks and recreaƟon space shown by diagram and in
general terms SecƟon 5.3.3‐Map 5‐3‐8
Street layout and property intended for streets shown by diagram and in
general terms SecƟon 5.3.5‐Map 5‐3‐14
LimitaƟons on the type, size, height, number, and proposed use of
buildings shown by diagram and in general terms
SecƟon 5.3.1, Maps 5‐3‐5 and 5‐
3‐6, SecƟon 5.5.5; for general
consideraƟons to guide these
requirements, see SecƟon 5.3.2
The approximate number of dwelling units shown by diagram and in
general terms SecƟon 5.3.2‐Map 5‐3‐2
Replacement housing and relocaƟon SecƟon 5.3.4, SecƟon 6
Property intended for public uƟliƟes shown by diagram and in general
terms
SecƟon 5.3.6‐Maps 5‐3‐15 and 5
‐3‐16
Property for public improvements of any nature shown by diagram and in
general terms
SecƟon 5.3.1‐Map 5‐3‐1 ,
SecƟon 5.4.2; addiƟonal details
in SecƟon 5.3.2‐Map 5‐3‐7,
SecƟon 5.3.3‐Map 5‐3‐8, SecƟon
5.3.4‐Map 5‐3‐10, SecƟon 5.3.5‐
Maps 5‐3‐12 and 5‐3‐14, SecƟon
5.3.6‐Maps 5‐3‐15 and 5‐3‐16
Neighborhood impact element describing impacts on residents of CRA area
and surrounding areas in terms of relocaƟon, traffic circulaƟon,
environmental quality, availability of community faciliƟes and services,
effect on school populaƟon, and other maƩers affecƟng the physical and
social quality of the neighborhood
SecƟon 5.5.6
Publicly funded capital improvements to be undertaken in the CRA area SecƟon 5.4.2
Safeguards, controls, restricƟons/covenants SecƟon 5.5.7
Replacement housing for relocaƟon of displaced persons from housing
faciliƟes SecƟon 6
ResidenƟal use element SecƟon 5.3.2, SecƟon 5.3.4‐
ObjecƟve 5
Projected costs of redevelopment SecƟon 5.4.3
Redevelopment Area Plan duraƟon and Ɵme certain for redevelopment
financed by increment revenues SecƟon 1.6
Table 5‐5‐3: SecƟon163.362, F.S. Requirements for Redevelopment Area Plan
14.B.1.a
Packet Pg. 464 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐5
5.5
County staff and the Collier County Planning
Commission.
5.5.6 Neighborhood Impact
The Redevelopment Area Plan focuses on improving
structural quality of buildings, compaƟbility of uses,
and urban design, as well as promoƟng more urban‐
style development and mulƟ‐modal transportaƟon. As
of right now, there is housing available at lower income
levels, yet this may be due to lower structural quality
based on findings from the background analysis for the
Redevelopment Area Plan. As improvements are made
in the area, there is a potenƟal risk of property values
rising to make housing substanƟally less affordable.
Consequently, protecƟve measures are being
considered to maintain the affordability of these units
while improving their quality (see SecƟon 5.3.4,
ObjecƟve 5). Temporary relocaƟon of residents in
lower quality units may be required to make building
improvements.
An addiƟonal consideraƟon for lower income
households with improvements to the CRA area is the
availability of community faciliƟes and services. These
uses may also risk displacement if property values
increase rapidly or dramaƟcally. This Redevelopment
Area Plan includes provisions to support community‐
oriented uses that include these faciliƟes and services
so that they can remain a part of the community (see
SecƟon 5.3.4, ObjecƟve 3, Strategy 2).
With more urban‐style development and mulƟ‐modal
improvements, traffic circulaƟon may change. There
may be increased congesƟon on roadways and at major
state road intersecƟons in making them safer for non‐
automobile modes and pursuing catalyst development
opportuniƟes. Any development would need to go
through the exisƟng Collier County process to assess
and miƟgate for Level of Service changes on roadways.
Ensuring low‐cost transportaƟon alternaƟves may also
support affordable mobility for lower income
households and community members.
Regarding impacts on other faciliƟes, such as schools,
any new development would need to go through the
exisƟng Collier County process to assess and miƟgate
for Level of Service changes.
Regarding environmental quality, water quality is a key
consideraƟon for stormwater management
improvements. Water quality impacts can be evaluated
through exisƟng Collier County processes. AddiƟonally,
this Redevelopment Area Plan encourages green
infrastructure techniques that may help provide certain
levels of localized water treatment and ground
infiltraƟon prior to arriving at major collector sites.
5.5.7 Safeguards, Controls,
Restrictions, & Assurances
Redevelopment acƟviƟes idenƟfied in this
Redevelopment Area Plan will not be iniƟated unƟl
they are found to be consistent with the Collier County
Growth Management Plan and applicable land
development regulaƟons. The Community
Redevelopment Agency, working collaboraƟvely with
County agencies, may propose amendments to the
Growth Management Plan and the Land Use
Development Code, including design criteria, building
heights, land coverage, setback requirements, special
excepƟons, traffic circulaƟon, traffic access, and other
development and design controls necessary for proper
development of public and private projects.
To leverage the increment revenues, Collier County
may consider non‐ad valorem assessments. For
example, during the Redevelopment Area Plan update
process, the County was working on a stormwater
uƟlity fee that, if adopted, would apply to the CRA area.
The imposiƟon of special assessments for capital
improvements and essenƟal services is covered by well
seƩled case law and specific statutory provisions
authorizing collecƟon of non‐ad valorem assessments
on the same bill as ad valorem taxes. Such provisions
require extraordinary noƟce to all affected property
owners.
Issues concerning restricƟons on any property acquired
for community redevelopment purposes and then
returned to use by the private sector will be addressed
14.B.1.a
Packet Pg. 465 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐6
5.5
on a case‐by‐case basis to ensure all acƟviƟes
necessary to perpetuate the redevelopment iniƟaƟve
are advanced in a manner consistent with this
Redevelopment Area Plan and any amendment to it.
Such restricƟons or controls would be expected in the
form of covenants on any land sold or leased for
private use as provided for in the Community
Redevelopment Act, SecƟon 163.380, F.S.
To assure that redevelopment will take place in
conformance with the projects, objecƟves and
strategies expressed in this Redevelopment Area Plan,
the Redevelopment Agency will uƟlize the regulatory
mechanisms used by the County to permit
development and redevelopment within its
jurisdicƟon. These mechanisms include but are not
limited to the Growth Management Plan; the Land
Development Code; adopted design guidelines;
performance standards; and County‐authorized
development review, permiƫng, and approval
processes and any other adopted codes, standards,
and policies.
14.B.1.a
Packet Pg. 466 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐7
5.5
This page is intenƟonally leŌ blank.
14.B.1.a
Packet Pg. 467 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 468 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-1
5.6
5.6.1 Tax Increment Financing
The Redevelopment Area is dependent upon the use of
increment revenue financing for funding. Using this
method, the County froze all taxable values within the
Redevelopment Area at the 2000 rate to establish a base
collection amount. Millages are applied through the General
Fund (001) and the Unincorporated Area General Fund
(111). The future taxes collected (associated with tax base
and property value increases) are placed into a separate
account and designated for specific uses. The funds can be
dedicated to transportation or general improvements, or
placed in the general fund with the base ad valorem
revenues.
The analysis is based on the historical tax roll data obtained
from the Florida Department of Revenue (FDOR) and
population projections for Collier County obtained from the
Bureau of Economic and Business Research (BEBR). Specific
increases in the tax base are shown in terms of expected
development and its value. This expected development is
based exclusively on past patterns of activity adjusted for
anticipated community redevelopment activities within the
Redevelopment Area. These programmatic assumptions
offer a baseline for comparison with future potential
development.
For this analysis, the Bayshore CRA’s current millage rates
have been used, and were held constant over the planning
horizon.
As for the structure of the revenues which may accrue, only
the taxable value(s) net of the base year taxable value is
considered in calculating current or future increment
revenues.
The general procedures used to calculate available
revenues are shown in the following calculations:
• Assessed values, including new construction –
Exemptions or exclusions = Current taxable values.
• Current taxable values – Established base year taxable
values = Net valuations subject to applicable
jurisdictional millages.
• Net valuations × by applicable millages = increment
revenues. Pursuant to the Community Redevelopment
Act, Section 163.387, F.S., the maximum revenue
available to the Redevelopment Trust Fund will be 95
percent of the calculated increment revenues.
Note that the first five years of projected values are
obtained from Florida’s Office of Economic & Demographic
Research (EDR) Revenue Estimating Conference. The
conference produces detailed projections of the “County
Taxable Value” for each county in Florida. The values
projected by EDR were used for each CRA tax increment
scenario with the low, medium, high growth scenarios
starting in 2025. For projection purposes past 2025, three
different scenarios were developed that reflect different
future growth rates for taxable values in the
Redevelopment Area. Additional details for each scenario
are presented below and in Tables 5-6-1 through 5-6-3.
Scenario #1
Ad valorem revenues associated with the increment
revenue financing for the Redevelopment Area were
estimated using the projected growth of the taxable values
for residential and non-residential developments. The
average taxable values were indexed annually based on the
positive correlation between population growth and taxable
value increases discussed previously, along with the
historical growth trends of taxable values in the
Redevelopment Area, by land use. Based on these
projections, if the current millage is held constant (3.5645
mils for fund 001 and 0.8069 mils for fund 111), the ad
valorem taxes used for the Redevelopment Area fund are
estimated to generate approximately $154.4 million
between through 2048.
Additional growth scenarios are presented in this report
that reflects more aggressive growth rates in taxable values
and potential revenues. Although more aggressive than the
growth rates in Scenario #1, these scenarios still present
revenue projections that can reasonably be obtained. Since
1976, the taxable value for residential property in Collier
County has averaged a 10 percent annual increase, and
commercial property has averaged a 9 percent annual
increase. Within the CRA, taxable values (all property) have
averaged a 5 percent annual increase.
Scenario #2
Scenario #2 reflects increased growth rates that are
consistent with the historical growth rates in taxable values
for the entire CRA area. This scenario estimates slightly
higher taxable value growth than Scenario #1, with a
projected average annual taxable value growth rate of 5.2
percent (as opposed to Scenario #1 at 4.8 percent). As CRA
properties are redeveloped, it is reasonable to assume that
taxable values will increase at or above historical growth
rates. Using these higher annual growth rates, the Scenario
#2 increment revenue financing option would generate
approximately $165.4 million through 2048.
14.B.1.a
Packet Pg. 469 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-2
5.6
Scenario #3
Additionally, an optimistic growth rate scenario was
developed. Scenario #3 has increased growth rates that are
more than Scenarios #1 and #2, bringing the average
growth rate for all land uses more in line with the
recent growth rates of the entire county seen over the
last few years. This scenario projects the growth in
taxable values for all property to average
approximately 5.7 percent, annually. Using these rates,
the increment revenue financing option generated
approximately $183.7 million through 2048.
For each of the following scenarios, the following
apply:
• Projected total taxable value of all properties
within Redevelopment Area. Projected growth
rates by land use are consistent with historical
growth rates observed between 2000 and 2017
within Redevelopment Area. All figures rounded to
nearest thousand.
• Difference between total taxable value (Item 1) for
each year and base year (2000).
• For projection purposes, millage rates are assumed
to remain the same through 2048.
• Increment revenue by year (Item 2), divided by
1,000, multiplied by total millage rate, and reduced
by 5 percent for budgeting purposes.
5.6.2 Municipal Service Taxing
Units (MSTUs)
There are two MSTUs that overlap with the CRA area –
the Bayshore Beautification MSTU and the Haldeman
Creek MSTU. The Bayshore Beautification MSTU was
created to provide certain streetscape and right-of-way
improvements in the CRA area generally south of US
41. The Haldeman Creek MSTU was created for
maintenance dredging and navigational marker
maintenance. Projected revenues for these two MSTUs
are based on the same scenarios described for the TIF
calculations above (see Tables 5-6-4 through 5-6-6 for
Bayshore Beautification MSTU and 5-6-7 through 5-6-9
for Haldeman Creek MSTU). Note that revenues stem
directly from millages (as opposed to an increment
difference with a base year as in the case of the TIF
revenues).
14.B.1.a
Packet Pg. 470 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-3
5.6
Table 5-6-1: Scenario #1 Projected TIF Revenues
Notes:
1. Source: Scenario #1 projected taxable values for the Bayshore CRA. Average annual growth at 4.8%. Note that the first five years of projected values
are obtained from Florida’s Office of Economic & Demographic Research (EDR) Revenue Estimating Conference. http://edr.state.fl.us/Content/
conferences/advalorem/index.cfm
2. Taxable value for each year (Item 1) less the base year taxable value of $288,081,106
3. For each fund, the tax increment for the previous year multiplied by the millage, divided by 1,000 and reduced by 5%. Note that the revenues for each
year are offset against the tax increment changes due to timing of collections (i.e., the revenue for 2019 is based on the ta x increment change from
2017 to 2018
Fund 001 Fund 111 Fund 001 Fund 111 Total
2019 $761,806,000 $473,724,894 3.5645 0.8069 $1,398,514 $316,583 $1,715,097
2020 $810,239,000 $522,157,894 3.5645 0.8069 $1,604,162 $363,136 $1,967,298
2021 $861,111,000 $573,029,894 3.5645 0.8069 $1,768,171 $400,263 $2,168,434
2022 $914,322,000 $626,240,894 3.5645 0.8069 $1,940,438 $439,259 $2,379,697
2023 $970,752,000 $682,670,894 3.5645 0.8069 $2,120,623 $480,048 $2,600,671
2024 $1,062,117,000 $774,035,894 3.5645 0.8069 $2,311,712 $523,305 $2,835,017
2025 $1,109,715,000 $821,633,894 3.5645 0.8069 $2,621,100 $593,341 $3,214,441
2026 $1,158,389,000 $870,307,894 3.5645 0.8069 $2,782,277 $629,827 $3,412,104
2027 $1,208,139,000 $920,057,894 3.5645 0.8069 $2,947,101 $667,139 $3,614,240
2028 $1,258,967,000 $970,885,894 3.5645 0.8069 $3,115,570 $705,275 $3,820,845
2029 $1,310,871,000 $1,022,789,894 3.5645 0.8069 $3,287,685 $744,237 $4,031,922
2030 $1,363,851,000 $1,075,769,894 3.5645 0.8069 $3,463,447 $784,024 $4,247,471
2031 $1,417,909,000 $1,129,827,894 3.5645 0.8069 $3,642,854 $824,637 $4,467,491
2032 $1,473,043,000 $1,184,961,894 3.5645 0.8069 $3,825,907 $866,075 $4,691,982
2033 $1,529,253,000 $1,241,171,894 3.5645 0.8069 $4,012,606 $908,338 $4,920,944
2034 $1,586,541,000 $1,298,459,894 3.5645 0.8069 $4,202,951 $951,427 $5,154,378
2035 $1,644,905,000 $1,356,823,894 3.5645 0.8069 $4,396,942 $995,341 $5,392,283
2036 $1,704,346,000 $1,416,264,894 3.5645 0.8069 $4,594,579 $1,040,080 $5,634,659
2037 $1,764,863,000 $1,476,781,894 3.5645 0.8069 $4,795,862 $1,085,645 $5,881,507
2038 $1,826,457,000 $1,538,375,894 3.5645 0.8069 $5,000,791 $1,132,035 $6,132,826
2039 $1,889,128,000 $1,601,046,894 3.5645 0.8069 $5,209,365 $1,179,250 $6,388,615
2040 $1,952,876,000 $1,664,794,894 3.5645 0.8069 $5,421,586 $1,227,291 $6,648,877
2041 $2,017,700,000 $1,729,618,894 3.5645 0.8069 $5,637,453 $1,276,157 $6,913,610
2042 $2,083,601,000 $1,795,519,894 3.5645 0.8069 $5,856,965 $1,325,848 $7,182,813
2043 $2,150,579,000 $1,862,497,894 3.5645 0.8069 $6,080,124 $1,376,365 $7,456,489
2044 $2,218,633,000 $1,930,551,894 3.5645 0.8069 $6,306,928 $1,427,707 $7,734,635
2045 $2,287,764,000 $1,999,682,894 3.5645 0.8069 $6,537,379 $1,479,874 $8,017,253
2046 $2,357,971,000 $2,069,889,894 3.5645 0.8069 $6,771,475 $1,532,867 $8,304,342
2047 $2,429,256,000 $2,141,174,894 3.5645 0.8069 $7,009,218 $1,586,685 $8,595,903
2048 $2,501,617,000 $2,213,535,894 3.5645 0.8069 $7,250,606 $1,641,328 $8,891,934
$125,914,391 $28,503,387 $154,417,778
Revenue (3)Millage
Year Tax Increment(2)
Total
Taxable Value(1)
14.B.1.a
Packet Pg. 471 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-4
5.6
Table 5-6-2: Scenario #2 Projected TIF Revenues
Notes:
1. Source: Scenario #2 projected taxable values for the Bayshore CRA. Average annual growth at 5.2%. Note that the first five years of projected val-
ues are obtained from Florida’s Office of Economic & Demographic Research (EDR) Revenue Estimating Conference. http://edr.state.fl.us/Content/
conferences/advalorem/index.cfm
2. Taxable value for each year (Item 1) less the base year taxable value of $288,081,106
3. For each fund, the tax increment for the previous year multiplied by the millage, divided by 1,000 and reduced by 5%. Note that the revenues for
each year are offset against the tax increment changes due to timing of collections (i.e., the revenue for 2019 is based on the tax increment change
from 2017 to 2018
Fund 001 Fund 111 Fund 001 Fund 111 Total
2019 $761,806,000 $473,724,894 3.5645 0.8069 $1,398,514 $316,583 $1,715,097
2020 $810,239,000 $522,157,894 3.5645 0.8069 $1,604,162 $363,136 $1,967,298
2021 $861,111,000 $573,029,894 3.5645 0.8069 $1,768,171 $400,263 $2,168,434
2022 $914,322,000 $626,240,894 3.5645 0.8069 $1,940,438 $439,259 $2,379,697
2023 $970,752,000 $682,670,894 3.5645 0.8069 $2,120,623 $480,048 $2,600,671
2024 $1,028,659,000 $740,577,894 3.5645 0.8069 $2,311,712 $523,305 $2,835,017
2025 $1,086,938,000 $798,856,894 3.5645 0.8069 $2,507,799 $567,693 $3,075,492
2026 $1,146,540,000 $858,458,894 3.5645 0.8069 $2,705,150 $612,368 $3,317,518
2027 $1,207,463,000 $919,381,894 3.5645 0.8069 $2,906,977 $658,056 $3,565,033
2028 $1,269,707,000 $981,625,894 3.5645 0.8069 $3,113,279 $704,757 $3,818,036
2029 $1,333,274,000 $1,045,192,894 3.5645 0.8069 $3,324,057 $752,471 $4,076,528
2030 $1,398,162,000 $1,110,080,894 3.5645 0.8069 $3,539,310 $801,198 $4,340,508
2031 $1,464,372,000 $1,176,290,894 3.5645 0.8069 $3,759,040 $850,938 $4,609,978
2032 $1,531,904,000 $1,243,822,894 3.5645 0.8069 $3,983,245 $901,692 $4,884,937
2033 $1,600,757,000 $1,312,675,894 3.5645 0.8069 $4,211,925 $953,458 $5,165,383
2034 $1,670,932,000 $1,382,850,894 3.5645 0.8069 $4,445,081 $1,006,238 $5,451,319
2035 $1,742,429,000 $1,454,347,894 3.5645 0.8069 $4,682,713 $1,060,031 $5,742,744
2036 $1,815,247,000 $1,527,165,894 3.5645 0.8069 $4,924,821 $1,114,837 $6,039,658
2037 $1,889,387,000 $1,601,305,894 3.5645 0.8069 $5,171,404 $1,170,657 $6,342,061
2038 $1,964,849,000 $1,676,767,894 3.5645 0.8069 $5,422,463 $1,227,489 $6,649,952
2039 $2,041,632,000 $1,753,550,894 3.5645 0.8069 $5,677,997 $1,285,335 $6,963,332
2040 $2,119,738,000 $1,831,656,894 3.5645 0.8069 $5,938,007 $1,344,194 $7,282,201
2041 $2,199,165,000 $1,911,083,894 3.5645 0.8069 $6,202,493 $1,404,065 $7,606,558
2042 $2,279,913,000 $1,991,831,894 3.5645 0.8069 $6,471,454 $1,464,951 $7,936,405
2043 $2,361,983,000 $2,073,901,894 3.5645 0.8069 $6,744,891 $1,526,849 $8,271,740
2044 $2,445,375,000 $2,157,293,894 3.5645 0.8069 $7,022,804 $1,589,760 $8,612,564
2045 $2,530,089,000 $2,242,007,894 3.5645 0.8069 $7,305,192 $1,653,685 $8,958,877
2046 $2,616,125,000 $2,328,043,894 3.5645 0.8069 $7,592,056 $1,718,623 $9,310,679
2047 $2,703,482,000 $2,415,400,894 3.5645 0.8069 $7,883,396 $1,784,573 $9,667,969
2048 $2,792,161,000 $2,504,079,894 3.5645 0.8069 $8,179,211 $1,851,537 $10,030,748
$134,858,385 $30,528,049 $165,386,434
Revenue (3)
Tax Increment(2)
Millage
Year
Total
Taxable Value(1)
14.B.1.a
Packet Pg. 472 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-5
5.6
Table 5-6-3: Scenario #3 Projected TIF Revenues
Notes:
1. Source: Scenario #3 projected taxable values for the Bayshore CRA. Average annual growth at 5.70%. Note that the first five years of projected values
are obtained from Florida’s Office of Economic & Demographic Research (EDR) Revenue Estimating Conference. http://edr.state.fl .us/Content/
conferences/advalorem/index.cfm
2. Taxable value for each year (Item 1) less the base year taxable value of $288,081,106
3. For each fund, the tax increment for the previous year multiplied by the millage, divided by 1,000 and reduced by 5%. Note t hat the revenues for each
year are offset against the tax increment changes due to timing of collections (i.e., the revenue for 2019 is based on the tax increment change from
2017 to 2018
Fund 001 Fund 111 Fund 001 Fund 111 Total
2019 $761,806,000 $473,724,894 3.5645 0.8069 $1,398,514 $316,583 $1,715,097
2020 $810,239,000 $522,157,894 3.5645 0.8069 $1,604,162 $363,136 $1,967,298
2021 $861,111,000 $573,029,894 3.5645 0.8069 $1,768,171 $400,263 $2,168,434
2022 $914,322,000 $626,240,894 3.5645 0.8069 $1,940,438 $439,259 $2,379,697
2023 $970,752,000 $682,670,894 3.5645 0.8069 $2,120,623 $480,048 $2,600,671
2024 $1,054,119,000 $766,037,894 3.5645 0.8069 $2,311,712 $523,305 $2,835,017
2025 $1,119,750,000 $831,668,894 3.5645 0.8069 $2,594,015 $587,210 $3,181,225
2026 $1,187,573,000 $899,491,894 3.5645 0.8069 $2,816,259 $637,520 $3,453,779
2027 $1,257,587,000 $969,505,894 3.5645 0.8069 $3,045,925 $689,510 $3,735,435
2028 $1,329,792,000 $1,041,710,894 3.5645 0.8069 $3,283,012 $743,179 $4,026,191
2029 $1,404,190,000 $1,116,108,894 3.5645 0.8069 $3,527,521 $798,529 $4,326,050
2030 $1,480,778,000 $1,192,696,894 3.5645 0.8069 $3,779,450 $855,559 $4,635,009
2031 $1,559,559,000 $1,271,477,894 3.5645 0.8069 $4,038,801 $914,268 $4,953,069
2032 $1,640,531,000 $1,352,449,894 3.5645 0.8069 $4,305,573 $974,658 $5,280,231
2033 $1,723,694,000 $1,435,612,894 3.5645 0.8069 $4,579,766 $1,036,727 $5,616,493
2034 $1,809,049,000 $1,520,967,894 3.5645 0.8069 $4,861,381 $1,100,476 $5,961,857
2035 $1,896,596,000 $1,608,514,894 3.5645 0.8069 $5,150,416 $1,165,906 $6,316,322
2036 $1,986,334,000 $1,698,252,894 3.5645 0.8069 $5,446,873 $1,233,015 $6,679,888
2037 $2,078,264,000 $1,790,182,894 3.5645 0.8069 $5,750,751 $1,301,804 $7,052,555
2038 $2,172,385,000 $1,884,303,894 3.5645 0.8069 $6,062,051 $1,372,273 $7,434,324
2039 $2,268,698,000 $1,980,616,894 3.5645 0.8069 $6,380,771 $1,444,423 $7,825,194
2040 $2,367,202,000 $2,079,120,894 3.5645 0.8069 $6,706,913 $1,518,252 $8,225,165
2041 $2,467,898,000 $2,179,816,894 3.5645 0.8069 $7,040,476 $1,593,761 $8,634,237
2042 $2,570,786,000 $2,282,704,894 3.5645 0.8069 $7,381,460 $1,670,950 $9,052,410
2043 $2,675,865,000 $2,387,783,894 3.5645 0.8069 $7,729,865 $1,749,819 $9,479,684
2044 $2,783,135,000 $2,495,053,894 3.5645 0.8069 $8,085,692 $1,830,367 $9,916,059
2045 $2,892,598,000 $2,604,516,894 3.5645 0.8069 $8,448,940 $1,912,596 $10,361,536
2046 $3,004,251,000 $2,716,169,894 3.5645 0.8069 $8,819,609 $1,996,505 $10,816,114
2047 $3,118,097,000 $2,830,015,894 3.5645 0.8069 $9,197,699 $2,082,094 $11,279,793
2048 $3,234,133,000 $2,946,051,894 3.5645 0.8069 $9,583,211 $2,169,362 $11,752,573
$149,760,050 $33,901,357 $183,661,407
Revenue (3)
Taxable Value (1)Tax Increment(2)
Millage
Year
Total
14.B.1.a
Packet Pg. 473 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-6
5.6
Table 5-6-4: Bayshore Beautification MSTU Scenario #1 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $591,115,003 95%2.3604 $1,325,504
2020 $625,527,320 95%2.3604 $1,402,670
2021 $660,034,619 95%2.3604 $1,480,048
2022 $694,831,419 95%2.3604 $1,558,076
2023 $730,024,175 95%2.3604 $1,636,992
2024 $765,674,832 95%2.3604 $1,716,934
2025 $801,819,577 95%2.3604 $1,797,984
2026 $838,478,945 95%2.3604 $1,880,188
2027 $875,663,295 95%2.3604 $1,963,570
2028 $913,375,780 95%2.3604 $2,048,136
2029 $951,615,129 95%2.3604 $2,133,883
2030 $990,376,372 95%2.3604 $2,220,800
2031 $1,029,652,374 95%2.3604 $2,308,872
2032 $1,069,434,646 95%2.3604 $2,398,079
2033 $1,109,713,336 95%2.3604 $2,488,399
2034 $1,150,478,225 95%2.3604 $2,579,809
2035 $1,191,719,137 95%2.3604 $2,672,287
2036 $1,233,425,692 95%2.3604 $2,765,809
2037 $1,275,588,082 95%2.3604 $2,860,353
2038 $1,318,196,940 95%2.3604 $2,955,898
2039 $1,361,243,853 95%2.3604 $3,052,426
2040 $1,404,721,160 95%2.3604 $3,149,919
2041 $1,448,622,279 95%2.3604 $3,248,362
2042 $1,492,941,782 95%2.3604 $3,347,743
2043 $1,537,675,538 95%2.3604 $3,448,053
2044 $1,582,820,738 95%2.3604 $3,549,286
2045 $1,628,375,926 95%2.3604 $3,651,438
2046 $1,674,341,360 95%2.3604 $3,754,510
2047 $1,720,718,577 95%2.3604 $3,858,505
2048 $1,767,510,764 95%2.3604 $3,963,431
Total -FY 2019-48:$77,217,964
14.B.1.a
Packet Pg. 474 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-7
5.6
Table 5-6-5: Bayshore Beautification MSTU Scenario #2 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $606,549,761 95%2.3604 $1,360,115
2020 $647,828,592 95%2.3604 $1,452,678
2021 $688,973,702 95%2.3604 $1,544,941
2022 $730,242,846 95%2.3604 $1,637,482
2023 $771,769,450 95%2.3604 $1,730,600
2024 $813,623,294 95%2.3604 $1,824,453
2025 $855,837,738 95%2.3604 $1,919,113
2026 $898,423,883 95%2.3604 $2,014,608
2027 $941,377,891 95%2.3604 $2,110,927
2028 $984,686,255 95%2.3604 $2,208,041
2029 $1,028,328,725 95%2.3604 $2,305,904
2030 $1,072,280,092 95%2.3604 $2,404,459
2031 $1,116,512,185 95%2.3604 $2,503,645
2032 $1,160,994,826 95%2.3604 $2,603,392
2033 $1,205,696,625 95%2.3604 $2,703,630
2034 $1,250,585,657 95%2.3604 $2,804,288
2035 $1,295,630,050 95%2.3604 $2,905,295
2036 $1,340,798,359 95%2.3604 $3,006,579
2037 $1,386,060,036 95%2.3604 $3,108,073
2038 $1,431,385,662 95%2.3604 $3,209,711
2039 $1,476,747,194 95%2.3604 $3,311,428
2040 $1,522,118,310 95%2.3604 $3,413,168
2041 $1,567,474,241 95%2.3604 $3,514,873
2042 $1,612,792,344 95%2.3604 $3,616,493
2043 $1,658,052,037 95%2.3604 $3,717,983
2044 $1,703,234,847 95%2.3604 $3,819,300
2045 $1,748,324,458 95%2.3604 $3,920,408
2046 $1,793,306,734 95%2.3604 $4,021,275
2047 $1,838,170,219 95%2.3604 $4,121,876
2048 $1,882,905,417 95%2.3604 $4,222,189
Total -FY 2019-48:$83,036,927
14.B.1.a
Packet Pg. 475 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-8
5.6
Table 5-6-6: Bayshore Beautification MSTU Scenario #3 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $618,846,476 95%2.3604 $1,387,689
2020 $666,424,041 95%2.3604 $1,494,376
2021 $714,013,673 95%2.3604 $1,601,090
2022 $761,898,751 95%2.3604 $1,708,467
2023 $810,218,308 95%2.3604 $1,816,817
2024 $859,037,223 95%2.3604 $1,926,288
2025 $908,377,891 95%2.3604 $2,036,928
2026 $958,236,209 95%2.3604 $2,148,730
2027 $1,008,590,342 95%2.3604 $2,261,643
2028 $1,059,406,499 95%2.3604 $2,375,592
2029 $1,110,642,628 95%2.3604 $2,490,483
2030 $1,162,251,104 95%2.3604 $2,606,209
2031 $1,214,180,327 95%2.3604 $2,722,654
2032 $1,266,376,232 95%2.3604 $2,839,697
2033 $1,318,783,498 95%2.3604 $2,957,214
2034 $1,371,346,270 95%2.3604 $3,075,079
2035 $1,424,008,878 95%2.3604 $3,193,169
2036 $1,476,716,929 95%2.3604 $3,311,361
2037 $1,529,416,999 95%2.3604 $3,429,534
2038 $1,582,057,896 95%2.3604 $3,547,575
2039 $1,634,590,626 95%2.3604 $3,665,373
2040 $1,686,968,643 95%2.3604 $3,782,825
2041 $1,739,148,306 95%2.3604 $3,899,831
2042 $1,791,089,012 95%2.3604 $4,016,302
2043 $1,842,753,405 95%2.3604 $4,132,153
2044 $1,894,107,627 95%2.3604 $4,247,309
2045 $1,945,121,181 95%2.3604 $4,361,701
2046 $1,995,767,160 95%2.3604 $4,475,268
2047 $2,046,022,279 95%2.3604 $4,587,959
2048 $2,095,866,709 95%2.3604 $4,699,730
Total -FY 2019-48:$90,799,046
14.B.1.a
Packet Pg. 476 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-9
5.6
Table 5-6-7: Haldeman Creek MSTU Scenario #1 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $121,367,536 95%1.0000 $115,299
2020 $128,526,521 95%1.0000 $122,100
2021 $135,704,827 95%1.0000 $128,920
2022 $142,942,896 95%1.0000 $135,796
2023 $150,262,704 95%1.0000 $142,750
2024 $157,677,032 95%1.0000 $149,793
2025 $165,193,225 95%1.0000 $156,934
2026 $172,815,346 95%1.0000 $164,175
2027 $180,545,373 95%1.0000 $171,518
2028 $188,383,756 95%1.0000 $178,965
2029 $196,329,988 95%1.0000 $186,513
2030 $204,382,850 95%1.0000 $194,164
2031 $212,540,650 95%1.0000 $201,914
2032 $220,801,394 95%1.0000 $209,761
2033 $229,162,805 95%1.0000 $217,705
2034 $237,622,632 95%1.0000 $225,742
2035 $246,178,462 95%1.0000 $233,870
2036 $254,827,995 95%1.0000 $242,087
2037 $263,568,960 95%1.0000 $250,391
2038 $272,399,253 95%1.0000 $258,779
2039 $281,316,833 95%1.0000 $267,251
2040 $290,320,002 95%1.0000 $275,804
2041 $299,407,206 95%1.0000 $284,437
2042 $308,577,110 95%1.0000 $293,148
2043 $317,828,658 95%1.0000 $301,937
2044 $327,161,143 95%1.0000 $310,803
2045 $336,574,094 95%1.0000 $319,745
2046 $346,067,305 95%1.0000 $328,764
2047 $355,641,019 95%1.0000 $337,859
2048 $365,295,793 95%1.0000 $347,031
Total -FY 2019-48:$6,753,955
14.B.1.a
Packet Pg. 477 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-10
5.6
Table 5-6-8: Haldeman Creek MSTU Scenario #2 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $124,558,218 95%1.0000 $118,330
2020 $133,140,017 95%1.0000 $126,483
2021 $141,695,436 95%1.0000 $134,611
2022 $150,277,871 95%1.0000 $142,764
2023 $158,914,679 95%1.0000 $150,969
2024 $167,620,097 95%1.0000 $159,239
2025 $176,400,756 95%1.0000 $167,581
2026 $185,258,652 95%1.0000 $175,996
2027 $194,192,721 95%1.0000 $184,483
2028 $203,199,877 95%1.0000 $193,040
2029 $212,275,571 95%1.0000 $201,662
2030 $221,414,344 95%1.0000 $210,344
2031 $230,610,047 95%1.0000 $219,080
2032 $239,856,126 95%1.0000 $227,863
2033 $249,145,751 95%1.0000 $236,688
2034 $258,472,054 95%1.0000 $245,548
2035 $267,828,164 95%1.0000 $254,437
2036 $277,207,234 95%1.0000 $263,347
2037 $286,602,686 95%1.0000 $272,273
2038 $296,008,161 95%1.0000 $281,208
2039 $305,417,647 95%1.0000 $290,147
2040 $314,825,418 95%1.0000 $299,084
2041 $324,226,118 95%1.0000 $308,015
2042 $333,614,832 95%1.0000 $316,934
2043 $342,987,111 95%1.0000 $325,838
2044 $352,338,908 95%1.0000 $334,722
2045 $361,666,688 95%1.0000 $343,583
2046 $370,967,365 95%1.0000 $352,419
2047 $380,238,358 95%1.0000 $361,226
2048 $389,477,595 95%1.0000 $370,004
Total -FY 2019-48:$7,267,918
14.B.1.a
Packet Pg. 478 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-11
5.6
Table 5-6-9: Haldeman Creek MSTU Scenario #3 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $127,106,206 95%1.0000 $120,751
2020 $136,994,758 95%1.0000 $130,145
2021 $146,888,010 95%1.0000 $139,544
2022 $156,844,298 95%1.0000 $149,002
2023 $166,892,038 95%1.0000 $158,547
2024 $177,044,257 95%1.0000 $168,192
2025 $187,305,175 95%1.0000 $177,940
2026 $197,673,490 95%1.0000 $187,790
2027 $208,144,221 95%1.0000 $197,737
2028 $218,709,954 95%1.0000 $207,774
2029 $229,361,500 95%1.0000 $217,893
2030 $240,088,574 95%1.0000 $228,084
2031 $250,880,014 95%1.0000 $238,336
2032 $261,724,194 95%1.0000 $248,638
2033 $272,609,257 95%1.0000 $258,979
2034 $283,523,220 95%1.0000 $269,347
2035 $294,454,148 95%1.0000 $279,731
2036 $305,390,372 95%1.0000 $290,121
2037 $316,320,528 95%1.0000 $300,505
2038 $327,233,622 95%1.0000 $310,872
2039 $338,119,195 95%1.0000 $321,213
2040 $348,967,293 95%1.0000 $331,519
2041 $359,768,601 95%1.0000 $341,780
2042 $370,514,490 95%1.0000 $351,989
2043 $381,196,966 95%1.0000 $362,137
2044 $391,808,847 95%1.0000 $372,218
2045 $402,343,563 95%1.0000 $382,226
2046 $412,795,427 95%1.0000 $392,156
2047 $423,159,430 95%1.0000 $402,001
2048 $433,431,416 95%1.0000 $411,760
Total -FY 2019-48:$7,948,927
14.B.1.a
Packet Pg. 479 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-12
5.6
5.6.3 Underlying Assumptions
The following charts show underlying population and tax value trends that inform and contextualize the revenue
projections calculations presented in this section. Figure 5-6-1 shows that the rate of population growth for
Collier County has decreased sizably since 2002/2003, with a more gradual decrease projected out from
2017/2018 for the next few decades.
In terms of historic tax value growth rates since 2000, Figure 5-6-2 shows that there was an increase during the
lead up to the recession, followed by a drop during the recession itself. In recent years, the rate has gradually
risen.
Given the sizable changes during the lead-up to the recession and the recession itself, the model used to
generate TIF projections was matched to longer historical trends in County taxable values, from the 1970s
through 2003/2004 historical taxable value for Collier County. Figure 5-6-3 shows the historical trend used for
guidance in blue; this trend is continued for comparison to projection calculations (in this case, for the low
revenue projections, shown by the grey line through 2048). The orange line indicates historic data that was
excluded from the historic trend basis since it was considered an anomaly.
Figure 5-6-1: Population Growth Rate Trends and Projections (2000-2045)
Source: BEBR, Volume 51, Bulletin 180, January 2018
14.B.1.a
Packet Pg. 480 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-13
5.6
Figure 5-6-2: Trends in Tax Value Growth Rates (2000-2017)
Source: Florida Property Valuations and Tax Databook & EDR Ad Valorem Revenue Estimating Conference
Figure 5-6-3: Historic and Projected TIF Revenue Trend Comparison for Low Revenue Projection
Source: Florida Property Valuations and Tax Databook & EDR Ad Valorem Revenue Estimating Conference
y = 67,809,839.76x2 -717,793,067.39x + 6,145,364,420.48
R² = 0.95
$0
$50,000,000,000
$100,000,000,000
$150,000,000,000
$200,000,000,000
$250,000,000,000
$300,000,000,000
$350,000,000,000
14.B.1.a
Packet Pg. 481 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-14
5.6
Conclusion
With the recovery from the recession of 2008, the CRA
area is poised for revitalization via investment,
development, and redevelopment. With this update,
the CRA will be able to continue the general mission of
redevelopment that it set out when the Bayshore
Gateway Triangle redevelopment area was first created
in 2000.
The CRA can move forward with the more detailed
planning and evaluation for the suggested
implementation items of this Redevelopment Area Plan
with the guidance of the overall vision, allowing for
change and also protecting and enhancing what
defines the area and makes it unique.
14.B.1.a
Packet Pg. 482 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.a
Packet Pg. 483 Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 484Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 485Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 486Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 487Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 488Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 489Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 490Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 491Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 492Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 493Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 494Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 495Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 496Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 497Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 498Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 499Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 500Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 501Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 502Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 503Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 504Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 505Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 506Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 507Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 508Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 509Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 510Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 511Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 512Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 513Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 514Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 515Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 516Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 517Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 518Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 519Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 520Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 521Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 522Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 523Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 524Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 525Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 526Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 527Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 528Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 529Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 530Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 531Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 532Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 533Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 534Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 535Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 536Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 537Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 538Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 539Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 540Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 541Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 542Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 543Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 544Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 545Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 546Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 547Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 548Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 549Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 550Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 551Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 552Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 553Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 554Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 555Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 556Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 557Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 558Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
14.B.1.aPacket Pg. 559Attachment: [Linked] CRA Adoption Resolution with Attachment A (8459 : CRA Plan Amendment)
Letters to Taxing Authorities
14.B.1.b
Packet Pg. 560 Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 561Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 562Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 563Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 564Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 565Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 566Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 567Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
14.B.1.bPacket Pg. 568Attachment: Notices Sent to Taxing Authorities (8459 : CRA Plan Amendment)
COLLIER COUNTY COMMUNITY REDEVELOPMENT PLAN AMENDMENT
Collier County Board of County
Commissioners
March 26, 2019
14.B.1.d
Packet Pg. 569 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
CRA BACKGROUND
1
14.B.1.d
Packet Pg. 570 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COLLIER COUNTY CRA
2
Established Community Redevelopment Agency by Resolution 2000-83
•Declared BCC as Community Redevelopment Agency
•Separate, legal, entity
•Established local advisory boards
Adopted Collier County Community Redevelopment Plan by Resolution
2000-181
•Section 4 -Immokalee Redevelopment Area Plan
•Section 5 -Bayshore Gateway Triangle Redevelopment Area Plan
•CCPC found the plan consistent with the Collier County Comprehensive Plan
•Duration –30 years
14.B.1.d
Packet Pg. 571 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COLLIER COUNTY CRA PLAN AMENDMENT
3
Proposed Changes
•Section 1:
•Updated language regarding Consistency with the Growth Management Plan
•Incorporated Immokalee Boundary Expansion adopted in 2004
•Duration of CRA –extended time frame to 30 years (Maximum allowed under
F.S. 163, Part III
•Section 4:
•Immokalee Redevelopment Area Plan -Updated Maps
•Figures and Appendices
Updated to reflect historic references and current conditions
14.B.1.d
Packet Pg. 572 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
SECTION 5 -BAYSHORE GATEWAY TRIANGLE REDEVELOPMENT AREA PLAN UPDATE
4
14.B.1.d
Packet Pg. 573 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
2000 REDEVELOPMENT PLAN: LAND USE
5
Land Use Plan: projects and focus areas
•Catalyst Projects
•Triangle –Hotel/Restaurant/Office
•Triangle –Flex Office/Warehouse
•Town Center (Gulfgate Plaza)
•Entertainment Center (Haldeman Creek)
•Neighborhood Focus Initiatives
•Shadowlawn
•Bayshore
Shadowlawn
Neighborhood
Bayshore
Neighborhood
Bayshore
Neighborhood
Naples Steel
Site
Naples
Plaza
Town Center
(Gulfgate)
Hotel/
Restaurant/
Office
Office/
Warehouse/
Showroom
Entertainment
Center
(Haldeman
Creek)
Courthouse
Shadows
County
Center
Botanical
Gardens/
Avalon Park
Lake
Bay Center
14.B.1.d
Packet Pg. 574 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
2000 REDEVELOPMENT PLAN: LAND USE
6
•Infrastructure
•Triangle Stormwater Management Plan
•Haldeman Creek and Canal System
Dredging Plan
•Roadway
•US 41 Zoning Overlay and Landscaping
•Davis Streetlighting and Zoning Overlay
•Bayshore Dr Landscaping
•Other TIF Projects
•Botanical Gardens Support
Shadowlawn
Neighborhood
Bayshore
Neighborhood
Bayshore
Neighborhood
Naples Steel
Site
Naples
Plaza
Town Center
(Gulfgate)
Hotel/
Restaurant/
Office
Office/
Warehouse/
Showroom
Entertainment
Center
(Haldeman
Creek)
Courthouse
Shadows
County
Center
Botanical
Gardens/
Avalon Park
Lake
Bay Center
14.B.1.d
Packet Pg. 575 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
2000 REDEVELOPMENT PLAN: URBAN DESIGN
7
Urban Design Framework: additional guidance
•Areas of Stability/Change
•Site Design
•Old Florida architecture
•Small front setbacks, parking in rear
•Rectilinear block pattern
•Landscape/Streetscape Improvements
•Gateway Intersection Designs
Image Source: MHK Architecture & Planning, http://www.mhkap.com/residential/
14.B.1.d
Packet Pg. 576 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
2000 REDEVELOPMENT PLAN: PROGRESS HIGHLIGHTS
8
Private Development
•Haldeman Creek commercial
•Naples Steel, Naples Plaza developed
•New market-rate residential
•Density pool units from Botanical Gardens
Roadway/Infrastructure
•Davis Boulevard Improvements
•Neighborhood stormwater plans
•Stormwater, water/fire projects
•Haldeman Creek dredge
•Removal of substandard housing
Catalyst Sites
•17-Acre Site acquired (former Botanical
Garden site)
14.B.1.d
Packet Pg. 577 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
2000/2019 PLAN COMPARISON
9
14.B.1.d
Packet Pg. 578 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
HOW DOES 2019 PLAN COMPARE TO 2000?
10
New Vision & Plan Framework
•Vision statement, including arts and culture focus
•Goals, objectives, policy framework by theme
•Character/redevelopment overview by sub-area (Character Areas)
New/Updated Non-Capital Initiatives
•Branding, Marketing, Communications
•Community Safety & Clean-Up Strategy
•Housing upgrade/façade improvement grants
•Public arts grant program
14.B.1.d
Packet Pg. 579 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
HOW DOES 2019 PLAN COMPARE TO 2000?
11
New/Expanded Transportation/Infrastructure Considerations
•Continued focus on walkability/connectivity
•Additional focus on parks access
•Expanded scope of roadway improvements –Complete Streets -neighborhood
and major
•Commercial parking needs and alternatives
•Expanded infrastructure considerations –geographic and type
Expanded/New Design Considerations
•Expanded gateway intersection treatments
•Inclusion of modern design style for Triangle
•Public arts grant program
14.B.1.d
Packet Pg. 580 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
HOW DOES 2019 PLAN COMPARE TO 2000?
12
Updated Neighborhood Improvements
•Continues Neighborhood Focus Initiatives
•Additional infrastructure, design, land use compatibility, and Complete
Streets considerations
•Support for neighborhood-identified projects/initiatives
Updated Catalyst Projects
•Key focus on CRA-owned sites in Mini Triangle and 17-Acre
•Potential to include multi-purpose facility (arts, incubator, CRA offices)
•Fostering private efforts –ex: Gulfgate , Courthouse, Haldeman Creek
commercial
14.B.1.d
Packet Pg. 581 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
2019 PLAN OVERVIEW
13
14.B.1.d
Packet Pg. 582 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
VISION CONCEPT
14
Promote quality of life and economic vitality with a
mixed -income, urban, multi-modal community
that welcomes visitors , cultivates the area’s artistic
and cultural identity, uplifts unique local
destinations , and finds balance with the natural
environment.
14.B.1.d
Packet Pg. 583 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
LAND USE & DESIGN
Goal: Promote a defined, harmonious, and
urban visual and land use character
tailored to the CRA area, cultivating its
unique artistic and cultural identity.
15
14.B.1.d
Packet Pg. 584 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
LAND USE & DESIGN: STYLE
16 Image Source: Bottom left -Modern design of The Garden School (Source: Corban Architecture/Planning/Sustainability, http://www.davidcorban.com/the-garden-school/)
14.B.1.d
Packet Pg. 585 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
LAND USE & DESIGN: URBAN FORM
17
14.B.1.d
Packet Pg. 586 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
LAND USE & DESIGN: PUBLIC ART & GATEWAY
18
14.B.1.d
Packet Pg. 587 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
LAND USE & DESIGN: TRANSITIONS
19
Needed Land
Use Transitions
Building
Green/Open Space
Parking/Landscape
Intensity
14.B.1.d
Packet Pg. 588 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PUBLIC SPACE, PARKS, & OPEN SPACE
20
Goal: Ensure accessible, activated, and
well -maintained public spaces, parks, and
open space.
14.B.1.d
Packet Pg. 589 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PUBLIC SPACE, PARKS, & OPEN SPACE
21 Images: East Naples Community Park and Sugden Regional Park –Collier County Parks & Recreation Division
Gateway
Triangle Pond
Design
14.B.1.d
Packet Pg. 590 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
DEVELOPMENT
Goal: Foster and guide private
development to enhance community
character and provide increased stability
and prosperity for community members.
22
14.B.1.d
Packet Pg. 591 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
DEVELOPMENT
23
Linwood Ave
Gulfgate Plaza
Del’s 24
Bayshore Dr
Courthouse Shadows
1
43
2
5
Development/
Tenancy
Opportunities
14.B.1.d
Packet Pg. 592 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
TRANSPORTATION & WALKABILITY
Goal: Ensure safety, comfort, and
convenience for various modes within and
connecting with the CRA area.
24
14.B.1.d
Packet Pg. 593 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
25
TRANSPORTATION & WALKABILITY
Images: Slidr -https://www.paradisecoast.com/profile/slidr/1726, parking garage -https://www.naplesdowntown.com/transportation.htm,
Complete Streets
Recommendations
14.B.1.d
Packet Pg. 594 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
26
TRANSPORTATION & WALKABILITY: MAJOR COMPLETE STREET
14.B.1.d
Packet Pg. 595 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
27
TRANSPORTATION & WALKABILITY: NEIGHBORHOOD COMPLETE STREET
14.B.1.d
Packet Pg. 596 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
INFRASTRUCTURE
Goal: Provide effective infrastructure that
preserves environmental and neighborhood
design quality through coordinated
improvement planning and funding.
28
14.B.1.d
Packet Pg. 597 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
INFRASTRUCTURE
29 Images: fire suppression construction –Bayshore/Gateway Triangle CRA, Palmetto green infrastructure bulb-out –Google Maps
14.B.1.d
Packet Pg. 598 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PROCESS
Goal: Carry out CRA area planning and
implementation efforts to engage and
serve the various communities within the
CRA area.
30
14.B.1.d
Packet Pg. 599 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PROCESS
31
14.B.1.d
Packet Pg. 600 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
32
14.B.1.d
Packet Pg. 601 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
CHARACTER AREAS
33
1.Mini Triangle/Davis
2.Shadowlawn
3.Airport Pulling
4.Tamiami
5.Windstar
6.North Bayshore
7.South Bayshore
Focus Corridor Focus Development
Node/Intersection
14.B.1.d
Packet Pg. 602 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COST & FUNDING SUMMARY: SHORT-TERM
34
Total Short-Term Costs
(1-5 Years):
$25.0 million
14.B.1.d
Packet Pg. 603 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PROJECT SUMMARY: SHORT-TERM
35
Total Short-Term Costs
(1-5 Years):
$25.0 million
Capital Projects:
•Complete Street Initiative:
•Linwood Avenue -Commercial to Wild Pines
•Republic Dr. –Bayshore to East Naples
Community Park
•Danford Street –Bayview Park to Hamilton
•Connection to Sugden Park
•Community Safety/Neighborhood Focus Initiatives
•Surface Parking Lot
•General Road Improvements
•Gateway Intersection
•Street Sign/Wayfinding
•Multi-modal amenities
•Stormwater Improvements
•Water line and Fire Suppression Upgrades
•Sanitary Sewer Line Upgrades
Non-Capital:
•Complete Street Feasibility Study
•Land Development Code Updates
•Triangle Retention Pond Feasibility Study
•Stormwater Master Plan Update
•Arts and Cultural Master Plan
•Branding/Marketing/Communication Strategy
•Residential Grants/Loans
•Incentives/Grants for Commercial
Development
•Staff and Administrative Costs
14.B.1.d
Packet Pg. 604 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COST & FUNDING SUMMARY: MID-TERM
36
Total Mid-Term Costs
(6-15 Years):
$57.9 million
14.B.1.d
Packet Pg. 605 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PROJECT SUMMARY: MID-TERM
37
Capital Projects:
•Triangle Retention Pond Improvements
•Bicycle and Pedestrian Trail along Sugden Park
•Community Safety/Neighborhood Focus Initiatives
•Surface Parking Lot in Mini-Triangle area
•Construction of multi-purpose facility –arts
incubator/CRA Office
•Commercial Parking Garage
•Local Street Improvements
•Gateway Intersection Design Improvements
•General Road Engineering improvements
•Water line and Fire Suppression Upgrades
•Sanitary Sewer Line Upgrades
•Undergrounding Utilities along Bayshore
Non-Capital:
•Land Development Code Updates
•Complete Streets Feasibility Study
•Microenterprise and art incubator study
•Continued and expanded grant programs
•Staff and Administrative Costs
Total Mid-Term Costs
(6-15 Years):
$57.9 million
14.B.1.d
Packet Pg. 606 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COST & FUNDING SUMMARY: LONG-TERM
38
Total Long-Term Costs
(16-30 Years):
$74.5 million
14.B.1.d
Packet Pg. 607 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
PROJECT SUMMARY: LONG-TERM
39
Capital Projects:
•South Bayshore Drive Complete Street Improvements
•Commercial Parking Garage –Mini Triangle
•Sidewalk/Bicycle Infrastructure
•Land Acquisition for pocket parks
•Community Safety/Neighborhood Focus Initiatives
•Local Street Improvements
•Gateway Intersection Design Improvements
•General Road Engineering improvements
•Water line and Fire Suppression Upgrades
•Sanitary Sewer Line Upgrades
•Undergrounding Utilities along Linwood/Commercial
Non-Capital:
•Studies/Analysis as identified
•Complete Street Feasibility Studies
•Continued and expanded grant programs
•Staff and Administrative Costs
Total Long-Term Costs
(16-30 Years):
$74.5 million
14.B.1.d
Packet Pg. 608 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COST & FUNDING SUMMARY: TIF FUNDING SUMMARY
40
TIF Funding Summary Total Overall Short-Term
(1-5 Years)
Mid-Term
(6-15 Years)1
Long Term
(16-30 Years)2
Total Capital Costs -North of US 41 (Triangle)$42,665,594 $4,916,110 $11,505,545 $26,243,939
Total Capital Costs -South of US 41 (Bayshore)$44,859,243 $7,790,481 $24,978,149 $12,090,612
Total Capital Costs $87,524,836 $12,706,591 $36,483,694 $38,334,552
Total Non-Capital Costs $69,915,363 $12,315,280 $21,449,912 $36,150,171
Total TIF Revenue $154,417,778 $10,831,197 $39,256,457 $104,330,124
Difference -$3,022,421 -$14,190,674 -$18,677,149 $29,845,401
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
14.B.1.d
Packet Pg. 609 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
COST & FUNDING SUMMARY: PROJECTED REVENUES
41
Fund Revenue
Short Term
Total
Mid
Term Total
Long
Term Total Total
(1-5 Yrs )(6-15 Yrs )(16-30 Yrs )
Tax Increment Financing (TIF)$10,831,197 $39,256,457 $104,330,124 $154,417,778
Bayshore Beautification MSTU $7,403,290 $20,956,845 $48,857,829 $77,217,964
Haldeman Creek MSTU $644,865 $1,831,442 $4,277,648 $6,753,955
14.B.1.d
Packet Pg. 610 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
FURTHER CONSIDERATIONS
•The original CRA was approved in 2000 for 30 years –approximately 11 years remain in
the lifetime. Plans are reevaluated every five years.
•The proposed Plan Amendment would extend the life by 30 years to 2049.
•The proposed Plan Amendment does not obligate funding to listed projects, but serves as
a guide for capital and non-capital projects that TIF can fund if approved.
•Section 4 –Immokalee Redevelopment Plan update is planned in FY20 –per F.S. 163,
extension can be considered any time the plan is amended.
42
14.B.1.d
Packet Pg. 611 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
TIF REVENUE CONSIDERATIONS
43
•Initial TIF funding occurred FY01 –through 2019:
•Bayshore: $22,631,017
•Immokalee: $8,659,135
•Est. TIF for the proposed 30 year term:
•Bayshore: $154,400,000 -$183,600,000
•Immokalee: $46,200,000 -$54,400,000
•Bayshore CRA holds current debt of $4,380,589 –will be satisfied
by sale of Triangle Properties or within original CRA term
$8,659,135 $22,631,017
$46,200,000
$154,400,000
Immokalee Bayshore
TIF Revenue
2000-2019 2019-2049 (est.)
14.B.1.d
Packet Pg. 612 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
CRA EXTENSION OPTIONS
44
OPTION 1:Adopt the redevelopment plan amendment as is and extend the life of the CRA
until 2049.
OPTION 2:Adopt the proposed plan amendment with no time extension and wait for
completion of the Immokalee Redevelopment Plan update (est.FY20)to consider
extension of the term of the CRA.
OPTION 3:Adopt the proposed plan amendment with no time extension and evaluate
progress on the plan in 5 years as prescribed to consider any extension then.
14.B.1.d
Packet Pg. 613 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
ANY QUESTIONS?
Recommendation:
Board of County Commissioners adopt a Resolution amending the
Collier County Community Redevelopment Plan.
Presentation | Date45
14.B.1.d
Packet Pg. 614 Attachment: CRA Plan Powerpoint (8459 : CRA Plan Amendment)
On March 14, 2000, the Collier County Board of County Commissioners made finding of
conditions of blight and adopted Resolution 2000-82 and adopted Resolution 2000-83
establishing the Community Redevelopment Agency. Both of these resolutions are contained in
Appendix A.
Section 1.3
CONSISTENCY WITH THE COLLIER COUNTY GROWTH MANAGEMENT PLAN
The Collier County Growth Management Plan provides land use designations, which describe
the intent and allowable density and intensity of appropriate uses for future development. The
Growth Management Plan. was adopted by the Board of County Commissioners in 1989. and
has been amended several times since the original adoption . scheduled to be in effective as
the basis for comparison •.vith the Rede•.ielopment Plan is the Groi.vth Management Plan
adopted in 1 Q8Q and revised in 1 QQ7 based on the 1 QQ6 Evaluation and Appraisal Report
(EAR).
This section identifies the goals, objectives and policies that apply to both redevelopment areas.
The goals, objectives and policies that apply to each area specifically are included inJAe
Section 4 -lmmoklaeelmmokalee Redevelopment Area Plan and Section 5 -
Bayshore/Gateway Triangle Redevelopment Area Plan. This amendment recognizes that the
lmmokalee Redevelopment Area Plan will be amended following the adoption of the updated
lmmokalee Area Master Plan currently going through the public hearing process.
Both the Bayshore/Gateway Triangle Redevelopment Area and the lmmokalee Redevelopment
Area are located in the Urban Designation as identified on the Collier County Future Land Use
Map Appendix F. As stated in the Future Land Use Element of the Growth Management Plan:
Urban Designated Areas on the Future Land Use Map include two general portions
of Collier County: areas with the greatest residential densities, and areas in close
proximity, which have or are projected to receive future urban support facilities and
services. It is intended that Urban Designated Areas accommodate the majority of
population growth and that new intensive land uses be located within them.
Accordingly, the Urban Area will accommodate residential uses and a variety of non
residential uses. The Urban Designated Area, which includes lmmokalee.
Copeland, Plantation Island, Chokoloskee, Port of the Islands, and Goodland. in
addition to the greater Naples area, and Marco Island, represents less than 10% of
Collier County's land area.
The redevelopment plan allows for detailed planning that will encourage the coordination of
activities as outlined in Objective 4 of the Growth Management Plan.
OBJECTIVE 4:
Continually refine the Future Land Use Element through detailed planning in order to improve
coordination of land uses with natural and historic resources. public facilities. economic development.
housing and urban design. In order to impro>Je coordination of land uses with natural and historic
resources, public facilities, economic de>Jelopment, housing and urban design, the Future Land Use
Element shall be continually refined through detailed planning. Future studies might address specific
geographic or issue areas. All future studies must be consistent with the Growth Management Plan and
further its intent.
Policy 4.8 recognizes the adoption of the redevelopment plans for each component area:
Policy 4.8:
4
Section 5
Bayshore Gateway Triangle Redevelopment Area Plan
First Amendment
Draft
March 2019
Prepared for
Prepared by
DraŌ: March 2019
Cover Photo Sources: Zyscovich Architects;
Google.com ‐ Marys Palacios
i
TABLE OF CONTENTS
5.0 Executive Summary ............................................................................................ 5-E-1
5.0.1 Executive Summary ................................................................................. 5-E-1
5.0.2 Goals ........................................................................................................ 5-E-1
5.0.3 Conceptual Plan Diagram ........................................................................ 5-E-4
5.0.4 Character Areas ....................................................................................... 5-E-7
5.0.5 Focus of Redevelopment ......................................................................... 5-E-9
5.0.6 Funding, Projects & Initiatives ............................................................... 5-E-10
5.0.7 2000 & 2019 Plan Comparison.............................................................. 5-E-14
5.1 Introduction ....................................................................................................... 5-1-1
5.1.1 Vision ....................................................................................................... 5-1-1
5.1.2 Process ..................................................................................................... 5-1-1
5.1.3 Plan Organization .................................................................................... 5-1-1
5.2 Background......................................................................................................... 5-2-1
5.2.1 Creation of a CRA Area ............................................................................ 5-2-1
5.2.2 2000 Redevelopment Plan Goals and Projects ....................................... 5-2-1
5.2.3 Bayshore/Gateway Triangle CRA 2018 Perspective ................................ 5-2-9
5.3 Planning Framework & Elements ....................................................................... 5-3-1
5.3.1 Conceptual Plan Diagram ........................................................................ 5-3-2
5.3.2 Land Use & Urban Design ........................................................................ 5-3-7
5.3.3 Public Space, Parks, & Open Space ....................................................... 5-3-26
5.3.4 Development ......................................................................................... 5-3-31
5.3.5 Transportation, Connectivity, & Walkability ......................................... 5-3-42
5.3.6 Infrastructure ........................................................................................ 5-3-59
5.3.7 Process ................................................................................................... 5-3-66
5.3.8 Character Areas ..................................................................................... 5-3-67
5.4 Prioritization Plan ............................................................................................... 5-4-1
5.4.1 Prioritization of Projects & Initiatives...................................................... 5-4-1
5.4.2 Financing Planning ................................................................................... 5-4-1
5.4.3 Projects & Initiatives Prioritization ......................................................... 5-4-5
5.4.4 Coordination & Partnerships ................................................................. 5-4-17
5.5 General Requirements ....................................................................................... 5-5-1
5.5.1 Overview of Relevant Statutes ................................................................ 5-5-1
5.5.2 Consistency with the County’s Comprehensive Plan .............................. 5-5-1
5.5.3 Acquisition, Demolition/Clearance, & Improvement .............................. 5-5-1
5.5.4 Zoning & Comprehensive Plan Changes ................................................. 5-5-1
5.5.5 Land Use, Densities, & Building Requirements ....................................... 5-5-1
5.5.6 Neighborhood Impact ............................................................................. 5-5-5
5.5.7 Safeguards, Controls, Restrictions, & Assurances................................... 5-5-5
5.6 Tax Increment & MSTU Estimates ...................................................................... 5-6-1
5.6.1 Tax Increment Financing ......................................................................... 5-6-1
5.6.2 Municipal Service Taxing Units (MSTUs) ................................................. 5-6-2
5.6.3 Underlying Assumptions ....................................................................... 5-6-12
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 ii
This page is intenƟonally leŌ blank.
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐1
5.0
5.0.1 Executive Summary
The Bayshore Gateway Triangle Redevelopment Area
Plan amendment provides an updated vision and
approach for the redevelopment of this component
area (see Map 5‐ES‐1) for the next 30 years.
The Plan brings together informaƟon gathered from
technical analysis, fieldwork observaƟon, and public
and agency outreach (documented in further detail in
a separate Assessment Memo). From these efforts and
the resulƟng themes idenƟfied, an overarching vision
emerged for the future of the Community
Redevelopment Agency (CRA) and this component
area:
The Redevelopment Area Plan lays out a framework of
goals, objecƟves, and strategies organized themaƟcally
in support of this overall vision, along with a list of
projects to carry out the framework. This plan is meant
to provide a paleƩe of opƟons, generated by the
technical analysis, fieldwork observaƟons, and public
and agency outreach, that the CRA can further
explore. Consequently, not all of these suggesƟons will
necessarily be carried through to full implementaƟon.
Full implementaƟon of approaches and projects will be
based on further study of capacity, technical
feasibility, and public prioriƟes.
5.0.2 Goals
The main goals of the Plan include:
Land Use & Urban Design
Promote a defined, harmonious, and urban visual and
land use character tailored to the CRA area, culƟvaƟng
its unique arƟsƟc and cultural idenƟty.
Public Space, Parks, & Open Space
Ensure accessible, acƟvated, and well‐maintained
public spaces, parks, and open space.
Development
Foster and guide private development to enhance
community character and provide increased stability
and prosperity for community members.
Transportation, Connectivity, & Walkability
Ensure safety, comfort, and convenience for various
methods of transportaƟon within and connecƟng with
the CRA area.
Infrastructure
Provide effecƟve infrastructure that preserves
environmental and neighborhood design quality
through coordinated improvement planning and
funding.
Process
Carry out CRA area planning and implementaƟon
efforts to engage and serve the various communiƟes
within the CRA area.
Figure 5‐ES‐1 provides a Concept Diagram focused on
locaƟon‐specific capital improvement projects,
followed by a list of non‐locaƟon‐specific capital
improvements projects and a descripƟon of non‐
capital projects (e.g., plans, studies, grant programs).
Promote quality of life and economic vitality with a
mixed-income, urban,
multi-modal community that welcomes visitors,
cultivates the area’s artistic and cultural identity,
uplifts unique local destinations, and finds balance
with the natural environment.
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐2
5.0
Map 5‐ES‐1: Bayshore Gateway Triangle CRA Study Area
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐3
5.0
This page is intenƟonally leŌ blank.
EXECUTIVE SUMMARY Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐4 5.0 Figure 5‐ES‐1: Redevelopment Concept THOMASSON DR BAYSHORE DR DAVIS BLVD N Complete Streets & Trail (Neighborhood) Jeepers Dr. Complete Streets (Major) Bayshore Dr. ‐ US 41 to Thomasson Dr. Complete Streets (Major) Linwood Ave Public Space, Parks, & Open Space Triangle RetenƟon Pond Improvements Monument Sign for Gateway IntersecƟon US 41 and Bayshore Dr. AIRPORT PULLING RD 5.0.3 Conceptual Plan Diagram Figure 5‐ES‐1 provides a Concept Plan illustraƟng future land use and capital improvements with associated goals of Land Use & Design; Public Space Parks, & Open Space; Development; TransportaƟon, ConnecƟvity, & Walkability; and Infrastructure. See the map legend on the following page for project descripƟons and addiƟonal capital improvements without specified locaƟons at this Ɵme. Note that “Major Corridors” are based on highways, minor arterials, and major arterials in the CRA area. Concept Map Major Corridor Land Use & Design Public Space, Parks, & Open Focus Corridor TransportaƟon, ConnecƟvity, & Walkability Infrastructure Development 5F 5E 5G 3A 5a 4c 4E 5B 5D 1C 6A 6b 6c 7d 7b 7A 7c 4b 4d 7E 4F 4a 1B 4G 5C 1A 1F 1D 1E 8A 8B 2A
EXECUTIVE SUMMARY Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐5 EXECUTIVE SUMMARY Bayshore Gateway Triangle CRA Area Plan —DraŌ March 2019 5‐E‐5 5.0 5.0 This page is intenƟonally leŌ blank. Location-Specific Capital Projects 7 1 3 4 5 6 8 Land Use & Urban Design Projects Gateway IntersecƟon Design Improvements A. Davis Blvd/Airport Pulling Rd B. Davis Blvd/Shadowlawn Dr C. Davis Blvd/US 41 D. US 41/Bayshore Dr E. Thomasson Dr/Dominion Dr F. Us 41/Osceola Ave Development Development Projects Public Space, Parks, & Open Space Projects Parks improvements A. Triangle RetenƟon Pond Improvements TransportaƟon, ConnecƟvity, & Walkability Projects Complete Streets (Major) A. Linwood Ave—Phase I B. Shadowlawn Ave C. Bayshore Dr—Us 41/Thomasson Dr D. Thomasson Dr/Hamilton Ave E. Commercial Dr F. Kirkwood Ave/Kirkwood Ave ConnecƟon G. Pine St ConnecƟon Complete Streets & Trails (Neighborhood) A. Bicycle/Pedestrian Trail B. Jeepers Dr C. Linwood Ave—Phase II D. Republic Dr E. Danford St F. Bay St G. Bayshore Dr—Thomasson Dr/Holly Ave Parking A. Surface/garage parking—Mini Triangle area B. Surface/garage parking—Bayshore area C. Car/boat parking—Bayview Park area General Road Engineering Standard Improvements A. Pine Tree Dr B. Andrews Ave C. Woodside Ave D. Holly Ave E. PalmeƩo Ct Infrastructure Projects Infrastructure A. Underground/Relocate Overhead UƟlity Lines—Linwood Ave and Commercial Dr B. Underground/Relocate Overhead UƟlity Lines—Bayshore Dr A. Development of MulƟ‐Purpose Facility/Structure 2
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐6
5.0
Non-Capital Projects
Projects and iniƟaƟves that are not capital
investments include a variety of plans, studies, and
grant programs in support of redevelopment or capital
project planning throughout the CRA area. These non‐
capital projects and iniƟaƟves include:
CRA operaƟng expenditures and administraƟve
updates
Land Development Code updates
Development support for catalyst development sites
Master planning for:
Stormwater improvements
Arts and culture‐oriented development and
redevelopment efforts
ImplementaƟon of Complete Streets projects
Community safety and clean‐up
Branding
MarkeƟng and communicaƟons
Water and fire infrastructure improvements
Feasibility studies, including:
General market study/economic profile
Bayshore Drive Complete Street technical
feasibility
Bayshore Drive Complete Streets pilot project
Triangle retenƟon pond improvements
Micro‐enterprise and arts incubator
CRA boundary expansion
Grants and funding programs, including:
ResidenƟal improvements grants/loans
Commercial façade improvements
Wall and fence funding for areas with
incompaƟble uses
Public art funding
Economic development incenƟves
Mobile home replacements
Community Land Trust housing construcƟon
Other affordable/workforce housing investments
Other non‐capital expenditures that may arise in the
future and are not yet idenƟfied
Non-Location Specific Capital Projects
Project Type Project Name
Development A. Land AcquisiƟon for Community Land Trust
TransportaƟon, ConnecƟvity, &
Walkability
A. Sidewalk Gap Improvements
B. Bicycle Infrastructure
C. Street Sign/Wayfinding Improvements
D. General MulƟ‐Modal Improvements
Infrastructure A. Water Main and Fire Suppression Upgrades
B. Stormwater Improvements
C. Upgrade Sanitary Sewer Lines
Public Space, Parks, & Open Space
A. Pocket Park Land AcquisiƟon & Development
B. General Parks Improvements
C. Community Safety/Clean‐Up and Neighborhood IniƟaƟves General Improvements
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐7
5.0
1 2
3 4
5 6
7
Focus Corridor
Focus Development Node/IntersecƟon
Mini Triangle/Davis
The Mini Triangle, including CRA‐owned
parcel, is a major commercial redevelopment
opportunity and Focus Development Node
Corridor commercial along Davis
Linwood Avenue another potenƟal area for
redevelopment.
Shadowlawn
Primarily a residenƟal neighborhood with mix
of apartments/duplexes and single‐family
homes around Shadowlawn Elementary
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Airport Pulling
Mix of corridor commercial, larger big‐box
style retail, and County Center
Part of area currently designated as an
AcƟvity Center in Future Land Use Map
Tamiami
Corridor commercial and residences,
including two major malls, Gulfgate Plaza and
Courthouse Shadows)
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Windstar
ResidenƟal is primarily condos and single‐
family homes in gated communiƟes
Includes golf course designated as a
commercial use
North Bayshore
Focus Corridor along Bayshore Drive with
neighborhood commercial (including
Haldeman Creek Entertainment Center near
Creek)
Mix of mulƟ‐ and single‐family residenƟal
Focus IntersecƟon at Bayshore/Thomasson
with planned roundabout
CRA‐owned Focus Development Node (17‐
Acre Site)
South Bayshore
Primarily single‐family residenƟal
neighborhood with Naples Botanical Garden
Wetland consideraƟons for development
5.0.4 Character Areas
The Redevelopment Area Plan framework can be tailored to different sub‐areas depending on their specific
character, needs, and opportuniƟes. Map 5‐ES‐2 lays out these different sub‐areas, or “Character Areas” with
accompanying descripƟons.
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐8
5.0
2
3
4
5
6
7 BAYSHORE DR LINWOOD AVE 1
Map 5‐ES‐2: Character Areas
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐9
5.0
5.0.5 Focus of Redevelopment
The following provides a focus of redevelopment for
each Character Area based on the specific
characterisƟcs described in Map 5‐ES‐2 and the most
relevant redevelopment strategies.
1. Mini Triangle/Davis
Urban‐style mixed use commercial
redevelopment, including capitalizaƟon on the
Mini Triangle as a catalyst development site and
urban‐style parking soluƟons
Park development at retenƟon pond site
Complete Streets design and commercial
redevelopment along Linwood Ave and other
nearby commercial roadways; pedestrian scale
street design between Mini Triangle, Linwood
Ave, and the proposed retenƟon pond park
Improved access to Mini Triangle development
from US 41, Davis Blvd, and Linwood Ave
MulƟ‐modal connecƟvity:
Across Davis Blvd
Between Mini Triangle, Linwood Ave,
proposed retenƟon pond park, and
eastern Triangle neighborhood
To Downtown Naples potenƟally via Davis
Blvd, US 41, and Gordon River Bridge
improvements
AddiƟonal infrastructure improvements: sanitary
sewers, electrical, stormwater
2. Shadowlawn
ResidenƟal structural enhancement and upgrades
Avoidance of incompaƟble uses
TransiƟonal elements between different uses
Infill development on vacant residenƟal lots
Flooding and drainage on neighborhood streets
Complete Street improvements along
Shadowlawn Drive
3. Airport Pulling
TransiƟons between residenƟal neighborhoods
and commercial development
Eventual street enhancements, parƟcularly
connecƟvity across Airport Pulling Rd
Commercial façade improvements
4. Tamiami
ConnecƟvity to Downtown Naples via US 41
Redevelopment of Courthouse Shadows
Tenant opportunity and site improvements for
walkable design at Gulfgate Plaza
5. Windstar
Complete Streets and MSTU improvements along
major community roadways, including Bayshore
Drive, Thomasson Drive, and Hamilton Avenue
Access to Bayview Park
6. North Bayshore
Corridor commercial development along Bayshore
Drive, including Haldeman Creek Entertainment
Center near Creek and creaƟve parking soluƟons
Larger redevelopment opportuniƟes of 17‐Acre
Site and Del’s 24 property
Arts and culture‐oriented development
TransiƟonal elements between corridor
commercial and residenƟal areas along Bayshore
Drive and Thomasson Drive
Development of vacant residenƟal lots
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐10
5.0
Complete Street design along Bayshore Drive and
Thomasson Drive, including Bayshore Drive/
Thomasson Drive roundabout
Neighborhood Complete Streets and trails
ConnecƟons between Sugden Regional Park and
CRA area
Water main and fire suppression upgrades
Flooding and drainage on neighborhood streets
7. South Bayshore
Mobile home and single‐family home residenƟal
improvements, upgrades, affordability
Development of vacant residenƟal lots
Access to Bayview Park
ConnecƟons between CRA and uses to the east,
including East Naples Community Park
Wetland, flooding, and site preparaƟon
consideraƟons for development
Roadway improvements to meet County
engineering standards
Neighborhood Complete Streets
5.0.6 Funding, Projects, &
Initiatives
The Redevelopment Area Plan also provides a
comprehensive list of capital projects and non‐capital
iniƟaƟves in support of the vision with a prioriƟzaƟon
plan and recommendaƟon for allocated funding .
Table 5‐ES‐1 summarizes projected revenues for
various funding sources operaƟng in the CRA area,
including Municipal Service Taxing Units (MSTUs) that
are funding sources independent of Tax Increment
Finance (TIF).
This Plan does not obligate any funding to any projects
listed. This Plan provides a guide and list of both
capital and non‐capital projects that tax increment
revenues can fund if approved by the CRA and
allocated through the standard operaƟng and
procurement guidelines adopted by the Collier County
Board of Commissioners. The Plan sets a framework
based on current condiƟons but also allows for
flexibility in the phasing of projects based on funding
opportuniƟes and community prioriƟes idenƟfied in
annual work plans and capital improvement project
lists.
Figures 5‐ES‐2 through 5‐ES‐4 summarize the funding
breakdown by Ɵmeframe and type of project/
iniƟaƟve. Note that non‐capital projects include
studies, plans, and grant programs. Table 5‐ES‐2
provides an overall summary of TIF revenues and costs
with surpluses and shorƞalls noted for each Ɵme
period (note that some projects are programmed at a
deficit because other funding partners or sources are
anƟcipated). Table 5‐ES‐3 shows CRA project costs
that may also be eligible for Bayshore BeauƟficaƟon
MSTU funds, indicaƟng the potenƟal benefit from
MSTU coordinaƟon.
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐11
5.0
Fund Revenue
Short Term Total Mid Term Total Long Term Total
Total
(1‐5 Yrs) (6‐15 Yrs) (16‐30 Yrs)
Tax Increment (TIF) $10,831,197 $39,256,457 $104,330,124 $154,417,778
Bayshore
BeauƟficaƟon MSTU $7,403,290 $20,956,845 $48,857,829 $77,217,964
Haldeman Creek
MSTU $644,865 $1,831,442 $4,277,648 $6,753,955
Total $18,879,352 $62,044,744 $157,465,601 $238,389,697
Table 5‐ES‐1: Revenue ProjecƟon Summary
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐12
5.0
Total Short‐Term Costs (1‐5 Years):
$25.0 million
Figure 5‐ES‐3: Mid‐term project costs by type
Figure 5‐ES‐2: Short‐term costs by project type
Total Mid‐Term Costs (6‐15 Years):
$57.9 million
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐13
5.0
Figure 5‐ES‐4: Long‐term costs by project type
Total Long‐Term Costs (16‐30 Years):
$74.5 million
Table 5‐ES‐2: Summary of CRA Project Costs and Projected TIF Revenues
Table 5‐ES‐3: Summary of MSTU‐Eligible Costs and Projected MSTU Revenues
MSTU Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ MSTU‐Eligible Projects $13,973,502 $4,121,297 $5,321,297 $4,530,908
Total Right‐of‐Way MSTU Revenue $77,217,964 $7,403,290 $20,956,845 $48,857,829
Difference $63,244,462 $3,281,993 $15,635,548 $44,326,921
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Note: Projects are considered MSTU‐eligible based on those that align with accepted uses of Bayshore Beautification MSTU funds according to Ordinance No. 2013‐68
TIF Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ North of US 41 (Triangle)$42,665,594 $4,916,110 $11,505,545 $26,243,939
Total Capital Costs ‐ South of US 41 (Bayshore)$44,859,243 $7,790,481 $24,978,149 $12,090,612
Total Capital Costs $87,524,836 $12,706,591 $36,483,694 $38,334,552
Total Non‐Capital Costs $69,915,363 $12,315,280 $21,449,912 $36,150,171
Total TIF Revenue $154,417,778 $10,831,197 $39,256,457 $104,330,124
Difference ‐$3,022,421 ‐$14,190,674 ‐$18,677,149 $29,845,401
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐14
5.0
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects
Triangle‐ Hotel/
Restaurant/
Office
Parcel at apex currently vacant; CRA‐owned
property under contract for sale and
received PUD zoning for Mixed‐Use project.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Triangle – Flex
Office/
Warehouse
Current mix of commercial and industrial
uses.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Table 5‐ES‐4: Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
5.0.7 2000 & 2019 Plan Comparison
Table 5‐ES‐4 assists in comparing the 2000 Plan to the amended Redevelopment Area Plan, showing a status
update for the various areas and iniƟaƟves idenƟfied for Tax Increment Finance (TIF) funding in the 2000 Plan, as
well as how the Redevelopment Area Plan update responds to the idenƟfied iniƟaƟves. Note that two addiƟonal
redevelopment sites, Naples Plaza and Naples Steel, were idenƟfied for private redevelopment without TIF
assistance (now Naples Bay Club/CoƩages at Naples Bay Resort and Woodspring Suites, respecƟvely). While the
2000 Plan has a strong orientaƟon around these sites and iniƟaƟves, the updated Redevelopment Area Plan is
oriented around general themes of: Land Use and Urban Design; Public Space, Parks, & Open Space;
Development; TransportaƟon, ConnecƟvity, & Walkability; Infrastructure; and Process. As a result, the amended
Redevelopment Plan contains addiƟonal consideraƟons that may not stem directly from the 2000 Plan, including
but not limited to:
A focus on the CRA‐owned 17‐Acre Site west of Sugden Regional Park for catalyst redevelopment
A focus on arts and culture in the CRA area redevelopment vision
ConnecƟons to nearby parks
Land use transiƟons between incompaƟble uses and densiƟes/intensiƟes
More comprehensive infrastructure improvements
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐15
5.0
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects (ConƟnued)
Town Center
(Gulfgate Plaza)
Gulfgate Plaza currently has tenants; consideraƟon
needs to be given to type of establishments
desired for this space. A small business incubator
might be a good use for vacant office on second
floor.
IdenƟfied as an opportunity for new tenancy in
second floor space and to incenƟvize opƟmal
tenant mix and walkable design; Courthouse
Shadows is another large commercial space
providing a redevelopment opportunity (SecƟon
5.3.4)
Entertainment
Center
(Haldeman
Creek)
Three60 Market has been established west of
bridge and south of creek; food truck park
recently opened on north side of creek under
same ownership as Three60 Market. Need for
commercial parking has emerged as an issue in
this area.
RecommendaƟons made to evaluate LDC
changes to facilitate commercial development
such as that in the Bayshore area (SecƟon
5.3.4); commercial parking soluƟons explored
(SecƟon 5.3.5, SecƟon 5.4)
Neighborhood Focus IniƟaƟves
Shadowlawn
The 2000 Plan iniƟaƟve included the following:
New general housing and affordable housing
RehabilitaƟon of affordable housing
Neighborhood gateway features
Traffic calming by closing part of Linwood
Extension of Pelton Ave to Linwood for
improved internal circulaƟon
Current status:
The Shadowlawn improvements delayed due to
recession, warranƟng prioriƟzaƟon of current
study and improvement implementaƟon approach
for area. However, some stormwater planning and
improvements completed for area (see General
Infrastructure Improvements secƟon below).
CRA will generally aim to conƟnue these
Neighborhood Focus IniƟaƟves. Neighborhood
enhancement focused on structural upgrades,
limiƟng uses incompaƟble with the
redevelopment vision, transiƟons between
uses/intensiƟes, infill development on vacant
lots, addressing flooding/drainage, and
complete streets/transportaƟon improvements
that will address streetscape elements such as
lighƟng and traffic calming. These
improvements will likely require strategic
property acquisiƟon and demoliƟon of
structures for redevelopment. Other relevant
iniƟaƟves include gateway design and
coordinaƟon with County sheriff, code
enforcement, and housing agencies to address
quality and supply of housing and streetlighƟng.
See secƟon 5.3 for more informaƟon.
Table 5‐ES‐4 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐16
5.0
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
Neighborhood Focus IniƟaƟves (ConƟnued)
Bayshore
The 2000 Plan iniƟaƟve included the following:
Landscaping and beauƟficaƟon along
Bayshore Drive
New affordable housing
RehabilitaƟon of market‐rate and
affordable housing
Botanical Gardens relocaƟon
Design of new neighborhood park and
connecƟon to Sugden Park site
Sabal Bay development (pending legal
acƟons)
Current related efforts include:
BeauƟficaƟon and roadway
improvements planned for Hamilton Ave
and Thomasson Dr, funded by the
Bayshore BeauƟficaƟon MSTU.
AddiƟonal stormwater planning and
improvements completed for area (see
General Infrastructure Improvements
secƟon below).
ResidenƟal units have been built;
substandard housing has been
demolished.
CRA will generally aim to conƟnue these Neighborhood
Focus IniƟaƟves. Redevelopment focus for this
neighborhood split into North and South. North focus:
commercial/catalyst site development, parking, arts
and culture, transiƟon between residenƟal and
commercial, residenƟal infill, comprehensive street
improvements that will address elements such as
streetlighƟng and traffic calming, park connecƟons
(Sugden Regional Park). South focus: residenƟal
upgrades and affordability, residenƟal infill, park access
(East Naples Community Park, Bayview Park), wetlands/
flooding consideraƟons, roadway standards. These
improvements will likely require strategic property
acquisiƟon and demoliƟon of structures for
redevelopment. Other relevant iniƟaƟves include
addiƟonal street/transportaƟon improvements to
address elements such as lighƟng and traffic calming,
as well as coordinaƟon with County sheriff, code
enforcement, and housing agencies to address quality
and supply of housing and streetlighƟng. See SecƟon
5.3 for more informaƟon.
Table 5‐ES‐4: Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
EXECUTIVE SUMMARY
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐E‐17
5.0
Table 5‐ES‐4 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
General Infrastructure Improvements
Triangle
Stormwater
Management
Plan
Need for stormwater improvements idenƟfied
for enƟre CRA area, so planning and
improvement efforts have included both
Triangle and Bayshore neighborhoods,
including the following:
Stormwater plan created for Gateway
Triangle residenƟal area in 2009 and for
Bayshore MSTU area in 2011.
Karen Dr stormwater improvements
completed in 2017.
Pineland Ave stormwater improvements
completed.
RecommendaƟon made to update stormwater
management plan for the enƟre CRA area (SecƟon
5.3.6)
Haldeman
Creek and
Canal System
Dredging Plan
Last major dredging project was in 2006.
Depth assessment will be conducted for creek,
and capital reserves currently being
accumulated for future maintenance or
dredge efforts. Advisory Board voted to
increase millage rate to create dredging plan
when major dredge will be needed; the
millage increase to 1 mil was approved at the
final budget hearing on September 20, 2018.
RecommendaƟon made to coordinate the capital
improvements of the MSTUs, including that used to
maintain Haldeman Creek, in a Capital Improvements
Plan (SecƟon 5.3.7).
Roadway Improvements
US 41 Zoning
Overlay and
Landscaping
Resurfacing and certain safety improvements
currently programmed in FDOT TransportaƟon
Improvement Program.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Davis
Boulevard
StreetlighƟng
and Zoning
Overlay
Resurfacing project beginning as part of FDOT
TransportaƟon Improvement Program
projects.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Bayshore Drive
Landscaping
Roundabout will be put in at Bayshore
and Thomasson as a Bayshore
BeauƟficaƟon MSTU project.
Bayshore Dr needs to be considered for
streetscape and roadway updates via the
Bayshore BeauƟficaƟon MSTU.
RecommendaƟon included to make Complete Streets
comprehensive roadway improvements along Bayshore
Drive and evaluate opportunity to underground
overhead uƟliƟes (see SecƟon 5.3.5, SecƟon 5.3.6, and
capital funding in SecƟon 5.4).
Botanical
Gardens
Support
Botanical Gardens is now located southwest
of the Bayshore Drive/Thomasson Drive
intersecƟon. The CRA currently owns the
17.89‐acre site (“17‐Acre Site”) west of
Sugden Regional Park; the site is targeted for
catalyst development.
Specific planning tasks included for the 17‐Acre Site
that highlight in parƟcular connecƟons to Sugden
Regional Park and a performance space (see SecƟon
5.3.4 and capital and non‐capital improvements in
SecƟon 5.4).
Other TIF‐Funded Projects
INTRODUCTION
Bayshore Gateway Triangle CRA Area Plan–DraŌ March 2019 5‐1‐1
5.1
5.1.1 Vision
The 2019 Redevelopment Area Plan provides an
updated vision and approach for the redevelopment of
the Bayshore Gateway Triangle CRA area in Collier
County (see Map 5‐1‐1). The Plan brings together
informaƟon gathered from technical analysis,
fieldwork observaƟon, and public and agency outreach
(documented in further detail in a separate
Assessment Memo). From these efforts and the
resulƟng themes idenƟfied, an overarching vision
emerged for the future of the CRA area:
This vision provides the guidance for the overall
framework and projects laid out in this
Redevelopment Area Plan for furthering the
revitalizaƟon of the CRA area. This Plan is meant to
provide a paleƩe of opƟons, generated by the
technical analysis, fieldwork observaƟons, and public
and agency outreach, that the CRA can further
explore. Consequently, not all of these suggesƟons will
necessarily be carried through to full implementaƟon.
Full implementaƟon of framework strategies and
projects will be based on further study of capacity,
technical feasibility, and public prioriƟes.
5.1.2 Process
The technical analysis involved in the Redevelopment
Area Plan process included a review of the exisƟng
plans related to the CRA area, as well as spaƟal and
quanƟtaƟve analysis of data related to the CRA area.
The study team also conducted fieldwork to collect
addiƟonal informaƟon and “ground‐truth” findings in
the data. The public and agency outreach consisted of
stakeholder and agency meeƟngs and calls, two public
workshops, and a boat tour of Haldeman Creek and
adjacent canal areas. Figure 5‐1‐1 illustrates the
complete planning process.
5.1.3 Plan Organization
The remaining secƟons of this Plan cover the following
topics:
SecƟon 5.2: Background – historical overview of
the CRA area, including the original 2000 CRA Plan
and status update
SecƟon 5.3: Plan Framework & Elements –
framework of goals, objecƟves, and strategies
related to redevelopment in the CRA area, with
supporƟng informaƟon on exisƟng condiƟons,
opportuniƟes, and approaches for carrying out
strategies
SecƟon 5.4: PrioriƟzaƟon Plan – informaƟon on
revenues; capital project funding and phasing; and
planning, administraƟve, and regulatory iniƟaƟves
SecƟon 5.5: General Requirements – informaƟon
on addiƟonal regulatory requirements for the CRA
Plan and conclusion
SecƟon 5.6: Tax Increment & MSTU EsƟmates—
provides methodology and underlying
assumpƟons for tax increment and Municipal
Service Taxing Unit (MSTU) revenues.
Promote quality of life and economic vitality with a
mixed-income, urban,
multi-modal community that welcomes visitors,
cultivates the area’s artistic and cultural identity,
uplifts unique local destinations, and finds balance
with the natural environment.
INTRODUCTION
Bayshore Gateway Triangle CRA Are Plan—DraŌ March 2019 5‐1‐2
5.1
Map 5‐1‐1: Bayshore Gateway Triangle CRA Study Area
INTRODUCTION
Bayshore Gateway Triangle CRA Area Plan–DraŌ March 2019 5‐1‐3
5.1
Figure 5‐1‐1: Planning Process
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐1
5.2
5.2.1 Creation of the CRA
Area
The Bayshore Gateway Triangle CRA area is located
primarily in unincorporated Collier County to the
southeast of the city of Naples (a small porƟon of the
area is in the city of Naples; see Map 5‐1‐1). It is near
the popular desƟnaƟons of Downtown Naples and
coastal beaches and is bisected by US 41, a major
regional thoroughfare. This corridor defines two major
sub‐areas within the larger CRA boundary–—the
Gateway Triangle community north of US 41 and the
Bayshore community south of US 41 (see Map 5‐1‐1
for CRA area and ResoluƟon 2000‐82, Exhibit A at end
of this document for a legal descripƟon of the CRA
boundary).
The CRA was created in 2000 under the jurisdicƟon of
Collier County to facilitate the physical and economic
revitalizaƟon and enhancement of the community. Its
creaƟon was based on documenƟng condiƟons of
blight in a Finding of Necessity study, as required by
Florida Statute 163.340. Table 5‐2‐1 provides an
overview of the findings.
5.2.2 2000 Plan Goals and
Projects
The 2000 Plan laid out visual concept goals and
corresponding redevelopment projects to improve
condiƟons in the CRA area. The projects were planned
out in phases over a 20‐year Ɵme span. Map 5‐2‐1
shows the overall Land Use Plan illustraƟng general
land uses and significant acƟvity centers. The Land Use
Plan suggested a basic regulatory framework that
would guide Future Land Use Map and zoning
amendments to support the redevelopment of the
CRA area.
In addiƟon to the Land Use Plan, the 2000 Plan
provided an Urban Design Framework to illustrate the
following:
1. Primary areas anƟcipated to undergo significant
change via redevelopment or infill development,
receive improvements via neighborhood
improvement strategies, or remain as stable and
planned development areas
2. Basic site design condiƟons recommended to
implement the vision defined in the public
outreach process
3. Primary corridors and areas recommended for
landscape/streetscape improvements in support
of the vision defined in the public outreach
The primary areas anƟcipated to undergo significant
change included:
Triangle area approximately defined by US 41,
Davis Blvd, and a line based on the projected
alignment of Pine St to the north of US 41
Naples Plaza (southwest of Davis Blvd and US 41
intersecƟon) and adjacent properƟes
Gulfgate Plaza as a Town Center
Commercial uses on Naples Steel properƟes
(along US 41) and other properƟes on Gulfgate
ResidenƟal uses south and west of Gulfgate
Infill:
MulƟ‐ and single‐family residenƟal in
Shadowlawn neighborhood
Commercial uses for Haldeman Creek
entertainment center
Mixed mulƟ‐family and commercial uses
along Bayshore Drive north of Lake View
(Lakeview) Dr
ResidenƟal and commercial at Bay Center
area (Bayshore and Thomasson)
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐2
5.2
Main Issue Sub‐Issue Specific LocaƟons MenƟoned
Predominance of defecƟve or
inadequate street layout
Inadequate street layout and
design (including sub‐standard
street widths)
Shadowlawn Dr
Thomasson Dr
Most local streets
Commercial parking problems
Davis Blvd
Airport Rd
Bayshore Rd
US 41
Lack of streetlights along major
arterial and most local streets
Major arterials
Most local streets
Davis Blvd
Lack of sidewalks
Shadowlawn Dr
Bayshore Rd south of
Thomasson Rd
Most local streets
Lack of neighborhood connecƟons ResidenƟal neighborhoods
Faulty lot layout in relaƟon to size,
adequacy, accessibility, or
usefulness
Commercial lots
US 41
Davis Blvd
Between Pine St and US 41
Built density far below approved
density
RMF‐6 residences in Gateway
Triangle area
Not meeƟng lot standards in at
least one respect
RMF‐6 residenƟal properƟes
Bayshore area residences
Unsanitary or unsafe condiƟons
DisproporƟonate lack of plumbing
DisproporƟonate overcrowding
2 unsafe structures
Lack of sidewalks and streetlights
DeterioraƟon of site or other
improvements
Poor drainage of local roads,
surface water management
problems
Other problems
Lack of right‐of‐way for
improvements along Shadowlawn
Dr
No public transportaƟon provided
in CRA area
Housing affordability noted as an
issue in the county and as an issue
that could get worse in the CRA
area
Table 5‐2‐1: Findings of Blighted CondiƟons in CRA Area
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐3
5.2
Other opportuniƟes in the Medium
Intensity residenƟal area of Land Use Plan
The public outreach of the 2000 Plan defined the
establishment of a Neighborhood Focus IniƟaƟve as a
programmaƟc objecƟve. The aim of such a program
was “to coordinate the direcƟon of a variety of public
and quasi‐public services to enhance major residenƟal
porƟons of the project area.” The primary
neighborhoods for improvements specified in the
2000 Plan included:
Bayshore
Shadowlawn
The primary areas for stability and planned
development with low‐intensity residenƟal included:
Windstar
Sabal Bay (Hamilton Bay) development
Site design standards included:
Roof paƩerns reflecƟve of Old Florida
architectural style
Placement of buildings close to street to support
pedestrian acƟvity
Use of recƟlinear block paƩern to strengthen
predominant established character of area
Placement of parking to rear of development sites
The following lays out items covered by the visual
preference statement from the public outreach effort
of the 2000 Plan, which supported the design
standards:
Buildings – represenƟng an “Old Florida” or
“Cracker” style with covered porches, metal roof,
and dormers
Signage – represenƟng low, monument‐style sign
with business logogram (representaƟve sign or
character) suppressed to design of sign’s
background and surrounding landscape planƟng
Pathways – represenƟng sidewalk set back from
curb by distance greater than width of walk and
with planƟng materials and low pedestrian
lighƟng provided between walk and curb
On‐Street Parking – represenƟng street with
narrow planted median and use of angle parking
interspersed with planƟng areas on both sides of
street
Landscaping – represenƟng street with
landscaped median and landscaping and
decoraƟve lighƟng fixtures on edges
Public Spaces – represenƟng pedestrian area with
palms and large pool with water jet fountain
In terms of landscape and streetscape improvements,
the design framework focused on:
Treatments for major roadways, including:
Davis Blvd
Airport Pulling Rd
US 41
Bayshore Dr
Thomasson Dr
Significant gateway intersecƟon designs at
intersecƟons of the above streets as well as:
Shadowlawn Dr south of Davis and North of US 41
Linwood Ave at Airport Pulling Rd
Pelton Ave north of US 41
IntersecƟon proposed at Ɵme of Sabal Bay’s main
east/west street with Bayshore Dr
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐4
5.2
Map 5‐2‐1: Land Use Plan from 2000 CRA Plan
Note: AddiƟonal labels have been added to clarify locaƟon of certain sites and neighborhoods.
Shadowlawn
Neighborhood
Bayshore
Neighborhood
Bayshore
Neighborhood
Windstar
Sabal Bay
Naples
Steel Site
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐5
5.2
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects
Triangle‐ Hotel/
Restaurant/
Office
Parcel at apex currently vacant; CRA‐owned
property under contract for sale and
received PUD zoning for Mixed‐Use project.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Triangle – Flex
Office/
Warehouse
Current mix of commercial and industrial
uses.
Specific planning tasks included for Mini Triangle and
larger Triangle area with associated improvements
(primarily roadway, infrastructure, and land use
transiƟons) and incenƟves idenƟfied that are generally
supported by the Redevelopment Area Plan (see
SecƟons 5.3.2, 5.3.4, 5.3.5, and 5.3.6); general
development support is also funded in the non‐capital
projects (see SecƟon 5.4)
Town Center
(Gulfgate Plaza)
Gulfgate Plaza currently has tenants;
consideraƟon needs to be given to type of
establishments desired for this space. A
small business incubator might be a good
use for vacant office on second floor.
IdenƟfied as an opportunity for new tenancy in second
floor space and to incenƟvize opƟmal tenant mix and
walkable design; Courthouse Shadows is another large
commercial space providing a redevelopment
opportunity (SecƟon 5.3.4)
Table 5‐2‐2: Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
Table 5‐2‐2 provides a status update for the various areas and iniƟaƟves idenƟfied for Tax Increment Finance
(TIF) funding in the 2000 Plan, as well as how the Redevelopment Area Plan update responds to the idenƟfied
iniƟaƟves. Note that two addiƟonal redevelopment sites, Naples Plaza and Naples Steel, were idenƟfied for
private redevelopment without TIF assistance (now Naples Bay Club/CoƩages at Naples Bay Resort and
Woodspring Suites, respecƟvely). While the 2000 Plan has a strong orientaƟon around these sites and iniƟaƟves,
the updated Redevelopment Area Plan is oriented around general themes of: Land Use and Urban Design;
Public Space, Parks, & Open Space; Development; TransportaƟon, ConnecƟvity, & Walkability; Infrastructure;
and Process. As a result, the updated Redevelopment Plan contains addiƟonal consideraƟons that may not stem
directly from the 2000 Plan, including but not limited to:
A focus on the CRA‐owned 17‐Acre Site west of Sugden Regional Park for catalyst redevelopment
A focus on arts and culture in the CRA redevelopment vision
ConnecƟons to nearby parks
Land use transiƟons between incompaƟble uses and densiƟes/intensiƟes
More comprehensive infrastructure improvements
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐6
5.2
2000 Plan Projects Status 2019 Redevelopment Area Plan Update Response
Catalyst Redevelopment Projects (ConƟnued)
Entertainment
Center
(Haldeman
Creek)
Three60 Market has been established west of
bridge and south of creek; food truck park recently
opened on north side of creek under same
ownership as Three60 Market. Need for
commercial parking has emerged as an issue in
this area.
RecommendaƟons made to evaluate LDC
changes to facilitate commercial development
such as that in the Bayshore area (SecƟon
5.3.4); commercial parking soluƟons explored
(SecƟon 5.3.5, SecƟon 5.4)
Neighborhood Focus IniƟaƟve
Shadowlawn
The 2000 Plan iniƟaƟve included the following:
New general housing and affordable housing
RehabilitaƟon of affordable housing
Neighborhood gateway features
Traffic calming by closing part of Linwood
Extension of Pelton Ave to Linwood for
improved internal circulaƟon
Current status:
The Shadowlawn improvements delayed due to
recession, warranƟng prioriƟzaƟon of current
study and improvement implementaƟon approach
for area. However, some stormwater planning and
improvements completed for area (see General
Infrastructure Improvements secƟon below).
CRA will generally aim to conƟnue these
Neighborhood Focus IniƟaƟves. Neighborhood
enhancement focused on structural upgrades,
limiƟng uses incompaƟble with the
redevelopment vision, transiƟons between
uses/intensiƟes, infill development on vacant
lots, addressing flooding/drainage, and
complete streets/transportaƟon improvements
that will address streetscape elements such as
lighƟng and traffic calming. These
improvements will likely require strategic
property acquisiƟon and demoliƟon of
structures for redevelopment. Other relevant
iniƟaƟves include gateway design and
coordinaƟon with County sheriff, code
enforcement, and housing agencies to address
quality and supply of housing and streetlighƟng.
See secƟon 5.3 for more informaƟon.
Table 5‐2‐2 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐7
5.2
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
Neighborhood Focus IniƟaƟves (ConƟnued)
Bayshore
The 2000 Plan iniƟaƟve included the following:
Landscaping and beauƟficaƟon along
Bayshore Drive
New affordable housing
RehabilitaƟon of market‐rate and
affordable housing
Botanical Gardens relocaƟon
Design of new neighborhood park and
connecƟon to Sugden Park site
Sabal Bay development (pending legal
acƟons)
Current related efforts include:
BeauƟficaƟon and roadway
improvements planned for Hamilton Ave
and Thomasson Dr, funded by the
Bayshore BeauƟficaƟon MSTU.
AddiƟonal stormwater planning and
improvements completed for area (see
General Infrastructure Improvements
secƟon below).
ResidenƟal units have been built;
substandard housing has been
demolished.
CRA will generally aim to conƟnue these Neighborhood
Focus IniƟaƟves. Redevelopment focus for this
neighborhood split into North and South. North focus:
commercial/catalyst site development, parking, arts
and culture, transiƟon between residenƟal and
commercial, residenƟal infill, comprehensive street
improvements that will address elements such as
streetlighƟng and traffic calming, park connecƟons
(Sugden Regional Park). South focus: residenƟal
upgrades and affordability, residenƟal infill, park access
(East Naples Community Park, Bayview Park), wetlands/
flooding consideraƟons, roadway standards. These
improvements will likely require strategic property
acquisiƟon and demoliƟon of structures for
redevelopment. Other relevant iniƟaƟves include
addiƟonal street/transportaƟon improvements to
address elements such as lighƟng and traffic calming,
as well as coordinaƟon with County sheriff, code
enforcement, and housing agencies to address quality
and supply of housing and streetlighƟng. See SecƟon
5.3 for more informaƟon.
Table 5‐2‐2 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐8
5.2
2000 Plan
Projects Status 2019 Redevelopment Area Plan Update Response
General Infrastructure Improvements
Triangle
Stormwater
Management
Plan
Need for stormwater improvements
idenƟfied for enƟre CRA area, so planning and
improvement efforts have included both
Triangle and Bayshore neighborhoods,
including the following:
Stormwater plan created for Gateway
Triangle residenƟal area in 2009 and for
Bayshore MSTU area in 2011.
Karen Dr stormwater improvements
completed in 2017.
Pineland Ave stormwater improvements
completed.
RecommendaƟon made to update stormwater
management plan for the enƟre CRA area (SecƟon
5.3.6)
Haldeman
Creek and
Canal System
Dredging Plan
Last major dredging project was in 2006.
Depth assessment will be conducted for
creek, and capital reserves currently being
accumulated for future maintenance or
dredge efforts. Advisory Board voted to
increase millage rate to create dredging plan
when major dredge will be needed; the
millage increase to 1 mil was approved at the
final budget hearing on September 20, 2018.
RecommendaƟon made to coordinate the capital
improvements of the MSTUs, including that used to
maintain Haldeman Creek, in a Capital Improvements
Plan (SecƟon 5.3.7).
Roadway Improvements
US 41 Zoning
Overlay and
Landscaping
Resurfacing and certain safety improvements
currently programmed in FDOT
TransportaƟon Improvement Program.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Davis
Boulevard
StreetlighƟng
and Zoning
Overlay
Resurfacing project beginning as part of FDOT
TransportaƟon Improvement Program
projects.
RecommendaƟon to coordinate on future
improvements with FDOT to develop and incorporate a
community vision for comprehensive Complete Streets
improvements along this corridor (see SecƟon 5.3.5).
Bayshore Drive
Landscaping
Roundabout will be put in at Bayshore
and Thomasson as a Bayshore
BeauƟficaƟon MSTU project.
Bayshore Dr needs to be considered for
streetscape and roadway updates via the
Bayshore BeauƟficaƟon MSTU.
RecommendaƟon included to make Complete Streets
comprehensive roadway improvements along Bayshore
Drive and evaluate opportunity to underground
overhead uƟliƟes (see SecƟon 5.3.5, SecƟon 5.3.6, and
capital funding in SecƟon 5.4).
Botanical
Gardens
Support
Botanical Gardens is now located southwest
of the Bayshore Drive/Thomasson Drive
intersecƟon. The CRA currently owns the
17.89‐acre site (“17‐Acre Site”) west of
Sugden Regional Park; the site is targeted for
catalyst development.
Specific planning tasks included for the 17‐Acre Site
that highlight in parƟcular connecƟons to Sugden
Regional Park and a performance space (see SecƟon
5.3.4 and capital and non‐capital improvements in
SecƟon 5.4).
Other TIF‐Funded Projects
Table 5‐2‐2 (conƟnued): Status of Key Land Use Areas and IniƟaƟves of the 2000 Plan
BACKGROUND
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐2‐9
5.2
SƟmulaƟng investment and capitalizing on
development opportuniƟes while also providing
support and protecƟons for exisƟng residents
NavigaƟng various percepƟons of and visions for the
area and incorporaƟng arts and culture into the
vision; markeƟng this vision
TransiƟon between higher‐density mulƟ‐family housing and
lower‐density single‐family housing
ArƟsƟc and cultural elements of the CRA area include murals
SecƟon 5.2.3 and SecƟons 5.3 and 5.4 provide more
informaƟon on these addiƟonal consideraƟons and their
basis.
5.2.3 Bayshore Gateway
Triangle CRA 2019
Perspective
Many of the challenges and efforts idenƟfied in the
2000 Plan are sƟll relevant today. The following are
some of the major ideas emerging from the
Redevelopment Area Plan update process, which
provided the basis for the goals, objecƟves, and
strategies underlying the framework (see SecƟon 5.3)
for this Redevelopment Area Plan:
Improving the compaƟbility of uses and appearance
of the public realm
TransiƟoning between suburban and urban
development style
Balancing regional vs. local transportaƟon needs
and related transportaƟon safety concerns along
major roadways; incorporaƟng a focus on mulƟ‐
modal transportaƟon
Developing in the context of natural condiƟons and
hazards (wetlands, Coastal High Hazard Area,
flooding), including how to address increased
density/intensity
Capitalizing on the valuable assets of the area or
nearby, including parks, natural areas such as the
canal system and Naples beaches, proximity to
Downtown Naples, and tourism while also creaƟng
public spaces that can be claimed by the community
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐1
5.3
This page is intenƟonally leŌ blank.
PLANNING FRAMEWORK & ELEMENTS 5.3 Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐2 Figure 5‐3‐1: Redevelopment Concept Public Space, Parks, & Open Space Triangle RetenƟon Pond Improvements THOMASSON DR BAYSHORE DR N Complete Streets & Trail (Neighborhood) Jeepers Dr. Complete Streets (Major) Bayshore Dr. ‐ US 41 to Thomasson Dr. Complete Streets (Major) Linwood Ave Monument Sign for Gateway IntersecƟon US 41 and Bayshore Dr. DAVIS BLVD AIRPORT PULLING RD Major Corridor Land Use & Design Public Space, Parks, & Open Focus Corridor TransportaƟon, ConnecƟvity, & Walkability Infrastructure Development Concept Map 5.3.1 Conceptual Plan Diagram The planning framework and elements cover a broad range of themes that make up the overall redevelopment approach. Figure 5‐3‐1 provides a Concept Plan illustraƟng aspects of the framework through future land use and capital improvements with associated goals that are more capital intensive, including Land Use & Design; Public Space Parks, & Open Space; Development; TransportaƟon, ConnecƟvity, & Walkability; and Infrastructure. See the map legend on the following page for project descripƟons, addiƟonal capital improvements without specified locaƟons at this Ɵme, and future land use details. The reminder of this chapter provides lays out the framework in more detail by goal. Note that “Major Corridors” are based on highways, minor arterials, and major arterials in the CRA area. 5F 5E 5G 3A 5a 4c 4E 5B 5D 1C 6A 6b 6c 7d 7b 7A 7c 4b 4d 7E 4F 4a 1B 4G 5C 1A 1F 1D 1E 8A 8B 2A
PLANNING FRAMEWORK & ELEMENTS Bayshore Gateway Triangle CRA Area Plan —DraŌ March 2019 5‐3‐3 5.3 PLANNING FRAMEWORK & ELEMENTS Bayshore Gateway Triangle CRA Area Plan —DraŌ March 2019 5‐3‐4 5.3 This page is intenƟonally leŌ blank. Location-Specific Capital Projects 7 1 3 4 5 6 8 Land Use & Urban Design Projects Gateway IntersecƟon Design Improvements A. Davis Blvd/Airport Pulling Rd B. Davis Blvd/Shadowlawn Dr C. Davis Blvd/US 41 D. US 41/Bayshore Dr E. Thomasson Dr/Dominion Dr F. Us 41/Osceola Ave Development Development Projects Public Space, Parks, & Open Space Projects Parks improvements A. Triangle RetenƟon Pond Improvements TransportaƟon, ConnecƟvity, & Walkability Projects Complete Streets (Major) A. Linwood Ave—Phase I B. Shadowlawn Ave C. Bayshore Dr—Us 41/Thomasson Dr D. Thomasson Dr/Hamilton Ave E. Commercial Dr F. Kirkwood Ave/Kirkwood Ave ConnecƟon G. Pine St ConnecƟon Complete Streets & Trails (Neighborhood) A. Bicycle/Pedestrian Trail B. Jeepers Dr C. Linwood Ave—Phase II D. Republic Dr E. Danford St F. Bay St G. Bayshore Dr—Thomasson Dr/Holly Ave Parking A. Surface/garage parking—Mini Triangle area B. Surface/garage parking—Bayshore area C. Car/boat parking—Bayview Park area General Road Engineering Standard Improvements A. Pine Tree Dr B. Andrews Ave C. Woodside Ave D. Holly Ave E. PalmeƩo Ct Infrastructure Projects Infrastructure A. Underground/Relocate Overhead UƟlity Lines—Linwood Ave and Commercial Dr B. Underground/Relocate Overhead UƟlity Lines—Bayshore Dr A. Development of MulƟ‐Purpose Facility/Structure 2
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐5
5.3
Project Type Project Name
Development A. Land AcquisiƟon for Community Land Trust
TransportaƟon, ConnecƟvity, &
Walkability
A. Sidewalk Gap Improvements
B. Bicycle Infrastructure
C. Street Sign/Wayfinding Improvements
D. General MulƟ‐Modal Improvements
Infrastructure A. Water Main and Fire Suppression Upgrades
B. Stormwater Improvements
C. Upgrade Sanitary Sewer Lines
Public Space, Parks, & Open Space
A. Pocket Park Land AcquisiƟon & Development
B. General Parks Improvements
C. Community Safety/Clean‐Up and Neighborhood IniƟaƟves General Improvements
Non-Location Specific Capital Projects
Non-Capital Projects
Projects and iniƟaƟves that are not capital
investments include a variety of plans, studies, and
grant programs in support of redevelopment or
capital project planning throughout the CRA area.
These non‐capital projects and iniƟaƟves include:
CRA operaƟng expenditures and administraƟve
updates
Land Development Code updates
Development support for catalyst development sites
Master planning for:
Stormwater improvements
Arts– and culture‐oriented development and
redevelopment efforts
ImplementaƟon of Complete Streets projects
Community safety and clean‐up
Branding
MarkeƟng and communicaƟons
Water and fire infrastructure improvements
Feasibility studies, including:
General market study/economic profile
Bayshore Drive Complete Street technical
feasibility
Bayshore Drive Complete Streets pilot project
Triangle retenƟon pond improvements
Micro‐enterprise and arts incubator
CRA boundary expansion
Grants and funding programs, including:
ResidenƟal improvements grants/loans
Commercial façade improvements
Wall and fence funding for areas with
incompaƟble uses
Public art funding
Economic development incenƟves
Mobile home replacements
Community Land Trust housing construcƟon
Other affordable/workforce housing investments
Other non‐capital expenditures that may arise in the
future and are not yet idenƟfied
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐6
5.3
Future Land Use DensiƟes
Mixed Use AcƟvity Center
A. Mixed Use—Bayshore/Gateway Triangle Overlay
B. ResidenƟal—Bayshore/Gateway Triangle Overlay; 16 UPGA for area outside of
overlay
Redevelopment Overlay—
ProperƟes with access to US 41
East/Bayshore Dr/Davis Blvd (84)/
west side of Airport‐Pulling Rd1
12 UPA via density pool units (with cap of 97 density pool units per project); limits apply
for projects that do not comply with the requirements for this density increase. The Mini
Triangle Catalyst Site is an excepƟon with a maximum of 12 UPA and is not subject to the
density pool unit requirements. Within this site, there is a Mini‐Triangle Subdistrict that
was approved through Ordinance No. 2018‐23 which amended the Growth
Management Plan and Ordinance No. 2018‐25 which amended the Land Development
Code creaƟng the Mini‐Triangle MPUD to allow for construcƟon of up to, with a mix to
be determined by maximum allowable traffic generaƟon, the following development
plan:
377 mulƟ‐family dwelling units
228 hotel suites
150 assisted living units
200,000 square feet of commercial uses inclusive of 60,000 square feet of self‐
storage and 30,000 square feet of car dealership
Redevelopment Overlay—
ProperƟes having frontage on
one or more of Bayshore Drive,
Davis Boulevard, Airport‐ Pulling
Road (west side only) or US 41
East2
ResidenƟal only: 8 UPA via use of density bonus pool (with cap of 97 density pool units
per project). Eligibility requires that the project:
1. shall be a Planned Unit Development (PUD)
2. shall be a minimum of 3 acres
3. shall be redevelopment of a site
4. consist of all market‐rate units
Limits apply for projects that do not comply with the requirements for this density
increase.
Urban ResidenƟal Subdistrict
(outside Redevelopment Overlay)
Maximum residenƟal density determined through Collier County’s Density RaƟng
System, but shall not exceed 16 UPA except in accordance with Transfers of
Development Rights in the Land Development Code.
Urban Coastal Fringe Subdistrict
(outside of Redevelopment
Overlay)
To facilitate hurricane evacuaƟon and protect the adjacent environmentally sensiƟve
ConservaƟon designated area, residenƟal densiƟes within the Subdistrict shall not
exceed a maximum of 4 UPA, except as allowed in the Density RaƟng System to exceed 4
UPA through provision of Affordable Housing and Transfers of Development Rights, and
except as allowed by certain Future Land Use Element Policies under ObjecƟve 5 in the
Growth Management Plan. New rezones to permit mobile home development within
this Subdistrict are prohibited. Rezones are recommended to be in the form of a PUD.
Future Land Use Densities
The following table shows Future Land Use densiƟes corresponding to designaƟons on the Concept Map (Figure
5‐3‐1). Note that certain projects in the Redevelopment Overlay are eligible for addiƟonal units from a pool of
388; these units are referred to as “density pool units” below. Also note that the enƟre CRA area lies in the
Coastal High Hazard Area, which deducts one unit per gross acre (UPGA) from the eligible base density of four
units per acre (UPA) and does not permit rezones for mobile home development.
1This definiƟon is interpreted broadly to mean properƟes that can gain access to the road(s), whether directly (access point on the road) or via one or more
other roads; it is not viewed narrowly to mean have an access point onto the road(s). As a result, this definiƟon encompasses all properƟes in the Bayshore
Gateway Triangle Redevelopment Overlay except those on east side of Airport Road.
2According to Collier County Growth Management staff, such properƟes must literally have frontage on (abut) one or more of the specified roads.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐7
5.3
5.3.2 Land Use & Urban Design
The Growth Management Plan and Land Development
Code (LDC) provide tools to shape land use and urban
design, which have a direct impact on the built
environment of an area. This secƟon highlights exisƟng
condiƟons related to various land use types, as well as
ways to promote a defined, harmonious, and urban
visual and land use character tailored to the CRA area,
culƟvaƟng its unique arƟsƟc and cultural idenƟty.
Promote a defined, harmonious, and urban visual
and land use character tailored to the CRA area,
cultivating its unique artistic and cultural identity.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐8
5.3
Mobile home
Small single‐family near large new single‐family with guest house
Small mulƟ‐family housing
Single‐family housing
Gated community housing
MulƟ‐family housing
Existing Residential Land Use Characteristics
The CRA area has 3,814, dwelling units according to Florida Department of Revenue 2017 data. These units include a
range of housing types from mobile to larger single‐family to mulƟ‐family homes (see Map 5‐3‐2 and corresponding
images). This diversity of types, when coupled with a range of price points, can accommodate a diversity of residents
living in the community. Currently, streets such as Jeepers Drive (picture 3 below) show areas of transiƟon between
larger residenƟal and smaller residenƟal, as well as between smaller single‐family residenƟal and mulƟ‐family on
nearby streets. The vision set forth in the Redevelopment Area Plan aims to guide these transiƟons towards the desired
built environment character laid out for different sub‐areas (see SecƟon 5.3.8).
1 2
3 4
5 6
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐9
5.3
1
4
3
6
5
2
Map 5‐3‐2: ExisƟng ResidenƟal Land Use CharacterisƟcs; Data source: 2017 Florida Department of Revenue
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐10
5.3
Existing Commercial & Industrial Land Use Characteristics
As with housing types, there are a range of commercial types in the CRA area (see Map 5‐3‐3 and corresponding
images). Many commercial sites include on‐site, street‐facing surface parking. The area contains two major mall‐style
commercial spaces, Gulfgate Plaza and Courthouse Shadows. Uses range from restaurants and retail stores to heavier
uses such as auto services. Industrial uses are also present in the Triangle area and northwest of Sugden Park.
New neighborhood commercial on Bayshore Drive— Three60 Market
Mall commercial—Courthouse Shadows
MulƟ‐story strip commercial
Mall commercial—Gulfgate Plaza
Linwood Avenue commercial
VerƟcal mixed‐use
1 2
3 4
5 6
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐11
5.3
1
2
3
5
6
LINWOOD AVE BAYSHORE DR 4
Map 5‐3‐3: Commercial & Industrial Land Use CharacterisƟcs with Non‐ResidenƟal ExisƟng Land Use; Data source: 2017 Florida Department of Reve‐
nue
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐12
5.3
Existing Community-Oriented Uses
Community‐oriented uses support community‐building and provide services via government, faith‐based, non‐profit,
and other enƟƟes. The Redevelopment Area Plan aims to preserve and enhance these uses. Government
establishments in the area include the Bayshore Gateway Triangle CRA Area office, a Naples Fire Rescue staƟon, and
the County Center (see Map 5‐3‐4 and corresponding images). Schools in and near the area include Avalon Elementary,
Shadowlawn Elementary, and The Garden School of Naples (a Montessori school). There are also various arts‐oriented
spaces, places of worship, and non‐profit service providers. EvaluaƟng locaƟons for a library or other public meeƟng
space can also facilitate the addiƟon of community services and spaces.
Bayshore Gateway Triangle CRA Area Office
1
Avalon Elementary School
2
Opera Naples
3
East Naples BapƟst Church
4
Greater Naples Fire Rescue—StaƟon #22
5
Catholic ChariƟes
6
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐13
5.3
1
2
3
4
5
6
Map 5‐3‐4: Community Oriented Land Use CharacterisƟcs with Non‐ResidenƟal ExisƟng Land Use; Data source: 2017 Florida Department of Revenue
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐14
5.3
Objective 1: Promote urban-style
development.
Strategy 1: Coordinate with Collier County Growth
Management and Zoning Divisions to pilot
innovaƟve land use and zoning approaches to
promote more urban‐style development in the
LDC. These approaches might include:
Increasing mixed use designaƟons
Focus increased densiƟes/intensiƟes
along improved roadways (with
consideraƟon of Coastal High Hazard Area
restricƟons)
Roadway design standards to support
mulƟ‐modal transportaƟon (see SecƟon
5.3.5)
Reduced building setbacks
Zoning for live/work spaces
Zoning and incenƟves for accessory
dwelling units
Flexible parking regulaƟons
Strategy 2: In awarding density pool units,
establish eligibility requirements and/or
performance metrics that promote these urban
approaches.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐15
5.3
Local Mix Use
Promote use of guest houses (shown here in back of main house) as a
way to provide addiƟonal density and potenƟally address
affordability
Local mulƟ‐family housing styles
Character Images
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐16
5.3
Objective 2: Achieve consistent land uses in the CRA
area and sub-areas.
Strategy 1: Use sub‐area (“Character Area”) characterisƟcs
(see SecƟon 5.3.8) to guide land use vision in the CRA area.
Strategy 2: Amend the LDC to limit heavy commercial and
manufacturing/warehouse/storage uses throughout the CRA
area; evaluate incenƟves to encourage transiƟons away from
heavy commercial and manufacturing/warehouse/storage
uses.
Strategy 3: IdenƟfy elements in the LDC to create clear
transiƟonal areas and land use buffers between uses that are
incompaƟble (see Figure 5‐3‐2); coordinate buffers with
related improvements, such as landscaping improvements
via the Bayshore BeauƟficaƟon MSTU.
Strategy 4: Provide funding through CRA‐funded grant
programs for transiƟonal structures (e.g., walls and fences)
between incompaƟble uses. Provide guidance in the
program guidelines to coordinate with related elements,
such as design standards and Bayshore BeauƟficaƟon MSTU
improvements.
Strategy 5: Provide clear guidance in the LDC for new and
emerging uses to ensure consistency with the respecƟve
Character Areas.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐17
5.3
Land Use Transition Types
There are four main types of land use strategies to transiƟon between differing land use types (Figure 5‐3‐2).
Factors affecƟng use of any given type might include characterisƟcs of the parƟcular site or the general Character Area.
Figure 5‐3‐2: Land Use TransiƟon Types
Building
Parking Lot/Landscape
Intensity of Use
Green/Open Space
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐18
5.3
Focus: transiƟon from interior residenƟal area of Triangle to the major commercial corridors
surrounding it
Strategies:
Put in place land use transiƟon areas of lighter commercial or mulƟ‐family residenƟal near single‐
family residenƟal areas
Promote use of physical barriers/buffers between heavier commercial uses and residenƟal uses
Limit heavier industrial and commercial uses in the Triangle area
Focus: transiƟon from commercial to residenƟal and between different residenƟal densiƟes
Strategies:
Establish land use transiƟon areas to transiƟon from commercial and denser mulƟ‐family along
Bayshore Drive to moderately dense mulƟ‐family residenƟal to single‐family residenƟal
Focus: put in place transiƟon strategies to mesh new development coming online with exisƟng uses
Strategies:
Establish land use transiƟon areas
Needed Land Use Transitions: Uses
Elements to facilitate transiƟons can be helpful where there are dissimilar uses, built forms, or development styles.
Strategies range from land use buffers (e.g., gradual transiƟon in density/intensity, open space buffers; see Figure 5‐3‐2),
physical barriers (e.g, walls, fences, landscaping), or limitaƟons placed on uses incompaƟble with the area’s land use vision.
Map 5‐3‐5 shows the generalized base zoning districts, highlighƟng areas with use boundaries that might benefit from
transiƟon strategies. The highlighted areas are described further below.
1
2
3
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐19
5.3
1
2
3
Map 5‐3‐5: Needed Land Use TransiƟons with Base Zoning
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐20
5.3
Needed Land Use Transitions: Building Heights
IdenƟfying boundaries between different exisƟng zoned building heights can indicate areas where land use transiƟon
approaches may be helpful. Map 5‐3‐6 shows the applicable Mixed Use Overlay Districts that provide more detailed
design standards for the CRA area with highlighted transiƟon areas from Map 5‐3‐4 and maximum zoned heights of
buildings in the table below. Note that there are excepƟons for certain structures in the code (e.g., church spires,
antenna). PUD sites are governed by zoning in their respecƟve ordinances.
Maximum Zoned Height of Building in Feet
House Rowhouse Apartment Mixed‐Use Commercial Civic &
insƟtuƟonal
BMUD‐NC 42 42 42 56 56 42
BMUD‐W 42 42 42 56 56 42
BMUD‐R1 35 35 35 35
BMUD‐R2 35 35 35 35
BMUD‐R3 35 35 35 35
Mixed Use
Overlay
DesignaƟon Mobile
Home
30
BMUD‐R4 35 35
GTMUD‐MXD 42 42 42 56 56 42
GTMUD‐R 35 35 35 35
Needed TransiƟon Area
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐21
5.3
Map 5‐3‐6: Mixed Use Overlay Districts in the CRA Area
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐22
5.3
Strategy 6: Evaluate opportuniƟes for arts‐oriented
code flexibility that will incorporate exisƟng arts
acƟvity such as gallery space.
Objective 3: Achieve a consistent design
character in the CRA area and sub-areas
that cultivates the area’s unique artistic and
cultural identity.
Strategy 1: As part of a CRA‐specific Arts and
Culture Plan (see SecƟon 5.3.4, ObjecƟve 1,
Strategy 5), develop a comprehensive design
approach for the public realm with reference to
specific Character Areas. The approach might
consider:
Architectural styles, including resilient
designs that beƩer manage natural
hazards such as flooding
TransiƟonal elements between Character
Area designs, building mass types, etc.
(see SecƟon 5.3.8)
Design consideraƟons for gateway/focus
intersecƟons
Design consideraƟons for public art
IdenƟficaƟon of public art opportuniƟes
and incenƟves
Design consideraƟons for streetscape
improvements in coordinaƟon with the
Bayshore BeauƟficaƟon MSTU Master Plan
Design consideraƟons for CRA‐funded
grants for façade and other exterior
improvements
IncorporaƟon of urban‐style development
design standards (see SecƟon 5.3.2,
ObjecƟve 1)
Airport Zone height restricƟons
Strategy 2: Fund a commercial façade grant
program for exterior improvements to commercial
buildings not targeted for major redevelopment.
Character Images for Design Style
A number of buildings in the CRA establish a modern
architectural style that the CRA can promote in public
realm design; there are a number of residences with a
more tradiƟonal Florida style that the CRA can also
promote. Art that is incorporated into private
development, but visible in the public realm, can also
contribute to the community character conveyed in
the physical environment (see the character photos on
the facing page). In addiƟon to architectural style, sign
styles can be considered as part of public realm design.
Figure 5‐3‐3 provides potenƟal sign design opƟons for
the Bayshore neighborhood of the CRA area, reflecƟng
the style of exisƟng infrastructure. The CRA can
promote a more modern design for the Triangle area
in the commercial areas targeted for redevelopment.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐23
5.3
Local residence with modern design style
Opera Naples with modern design style
Modern design of Ankrolab Brewing Co. (Source: Hlevel
Architects, hƩp://hlevel.info/project/ankrolab_bre)
wing_co/)
Local residenƟal design
Local residenƟal design Local residenƟal design
Modern design of The Garden School (Source: Corban
Architecture/Planning/Sustainability, hƩp://
www.davidcorban.com/the‐garden‐school/)
Figure 5‐3‐3: Sign Design Examples
Local residenƟal design
Art in the public realm on Bayshore Dr
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐24
5.3
ExisƟng gateway design near US 41 and Bayshore Drive
Bayshore Drive/Thomasson Drive roundabout rendering
Bayshore Drive flag, lighƟng, bike lane, landscaping, pavement
treatments
Design Treatments & Attributes
Public realm design in the area is important given the emphasis on arts‐oriented development and input from public
outreach efforts indicaƟng architectural style as a way of building a sense of place and community. The Bayshore
BeauƟficaƟon MSTU has contributed significantly to the design of the southern porƟon of the CRA area with streetscape
improvements including lighƟng, flags, landscaping, and the design of the Bayshore/Thomasson roundabout. The CRA
should coordinate with the MSTU for further improvements, including the design of major gateway intersecƟons that can
include signs and public art (see Map 5‐3‐7 for opportuniƟes). Note that gateway intersecƟon opportuniƟes north of US 41
would not qualify for Bayshore BeauƟficaƟon MSTU funds, yet the northern Triangle area can explore the creaƟon of its own
MSTU to fund these and other types of improvements (see SecƟon 5.3.7, ObjecƟve 3, Strategy 2).
MSTU Improvements
Gateway Design OpportuniƟes
1
2
3
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐25
5.3
3
1 BAYSHORE DR HAMILTON AVE THOMASSON DR
2
Map 5‐3‐7: Design Treatments & AƩributes
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐26
5.3
5.3.3 Public Space, Parks,
& Open Space
Public space, parks, and open space types of land use
that serve an important community‐building purpose
with parƟcular design consideraƟons given the variety
of acƟvity they can support. This secƟon focuses on
how to ensure accessible, acƟvated, and well‐
maintained public spaces, parks, and open space.
Ensure accessible, activated, and well-maintained
public spaces, parks, and open space.
Objective 1: Increase access to parks and
public gathering places in the CRA area.
Strategy 1: Coordinate with Collier County Road
Maintenance Division and Parks & RecreaƟon
Division to increase the number and quality of
bicycle and pedestrian connecƟons 1) between
the Bayshore Dr area and neighboring County
parks, including Bayview Park, East Naples
Community Park, and Sugden Regional Park and 2)
running north/south from neighboring County
parks to increase accessibility to the Triangle area
(see SecƟon 5.3.5, ObjecƟve 1, Strategy 6).
Strategy 2: Coordinate with Collier County Road
Maintenance Division and Parks & RecreaƟon
Division in conjuncƟon with Thomasson Ave and
Hamilton Ave MSTU improvements to evaluate
opportuniƟes for 1) maintaining car and boat
parking at Bayview Park and 2) operaƟonal
maintenance at Bayview Park.
Strategy 3: Coordinate with Collier County Public
Services Department to evaluate opportuniƟes for
a park and/or public meeƟng space (e.g., library)
in the CRA area.
Strategy 4: Create a site‐specific park plan for the
exisƟng retenƟon pond in the Triangle area.
Strategy 5: Evaluate opportuniƟes for “pocket
parks” (very small neighborhood park spaces).
Strategy 6: Coordinate with Collier County Parks &
RecreaƟon Division on any general parks
improvements related to CRA development/
redevelopment sites and efforts, including the 17‐
Acre Site (see SecƟon 5.3.4).
Objective 2: Support events in park spaces
geared towards the CRA community.
Strategy 1: Coordinate with Collier County Parks &
RecreaƟon Division to promote park spaces as
venues for CRA community events.
Pedestrian connecƟon between Bayshore neighborhood and Sugden
Regional Park that can serve as an example for addiƟonal connecƟons
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐27
5.3
Park and Connectivity Design
Concepts
The potenƟal park design concept
shown in Figure 5‐3‐4 for the Triangle
stormwater retenƟon pond is based on
previous planning and design efforts for
the pond, with more consideraƟon
given to increasing visibility to enhance
safety in the pond area (a concern
menƟoned during public outreach).
The rendering includes a consideraƟon
for idenƟfying sites for consolidated
public parking, which may take the form
of a garage.
Figure 5‐3‐4: PotenƟal Triangle Stormwater Pond Design Concept
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐28
5.3
Sugden Regional Park: County park that provides inland water access
and water recreaƟon programming. Image source: Collier County
Parks & RecreaƟon Division
Bayview Park: County park that provides access to Haldeman Creek,
the local canals, and the Gulf of Mexico.
Park Opportunity at Stormwater Pond: potenƟal for design, traffic
flow, safety, and flood management improvements.
East Naples Community Park: County park that houses 38 pickleball courts for
sports tourism and local recreaƟonal use; hosts the annual US Open Pickleball
Championship and other pickleball tournaments. Image source: Collier
County Parks & RecreaƟon Division
Naples Botanical Garden: a non‐profit 170‐acre botanical garden with
over 220,000 visitors per year. Also includes meeƟng spaces.
Parks & Open Space
The Redevelopment Area Plan update process idenƟfied parks and open spaces as important community assets,
providing event spaces and opportuniƟes to build a sense of place and community. Park access can be improved by
providing beƩer connecƟons to parks and capitalizing on opportuniƟes for new parks (such as at the Triangle retenƟon
pond and small pocket parks). Expansion of the CRA area to include the parks to the east should also be evaluated since
it may facilitate making connecƟons and other improvements. See Map 5‐3‐8 for exisƟng parks and opportuniƟes.
1 2
3 4
6
Haldeman Creek and Canals: provide access to the Bayshore Drive
commercial area and the Gulf of Mexico. The Haldeman Creek MSTU
funds periodic dredging and maintenance.
5
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐29
5.3
1
2
3
4
6
5
Map 5‐3‐8: Parks & Open Space
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐30
5.3
Objective 3: Ensure a clean and well maintained public realm.
Strategy 1: Coordinate with the Collier County Sheriff’s Office, Collier County Code Enforcement Division,
service providers in the CRA area, and residents and business owners in the CRA area to develop a proacƟve
community safety and clean‐up strategy (inclusive of private property along the canal network) with an aim
at reducing reliance on case‐by‐case enforcement. This effort should focus on residenƟal properƟes and
coordinate with the Community Standards Liaison pilot program of the Collier County Community & Human
Services Division.
Strategy 2: IdenƟfy and document a strategy for canal maintenance in the right‐of way, including seawalls
and mangroves, in coordinaƟon with the Haldeman Creek MSTU Advisory Board.
Table 5‐3‐1 indicates the amount of parks and open space that are in and bordering the CRA area.
DesignaƟon LocaƟon Acreage EsƟmate
Total publicly‐owned
open space within CRA
area
RetenƟon pond site
(northern Triangle area)
6.48
(includes pond)
AddiƟonal open space or
green space in the CRA
area
Botanical Garden
(non‐profit owned) 168
Total open space/green
space in CRA area 174.48
Park space adjacent to
CRA area
Bayview Park
East Naples Community Park
Sugden Regional Park
6.27
120
173.27
Total park, open, or
green space within or
adjacent to CRA area
347.75
Table 5‐3‐1: Amount of Parks and Open Space.
Source: 2017 Florida Department of Revenue and Google Earth calculaƟon
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐31
5.3
5.3.4 Development
Development and redevelopment can improve the
quality and aestheƟcs of the built environment, as well
as generate tax revenue and benefits to property
owners through increased property values. This
development and redevelopment acƟvity also needs to
include protecƟons for exisƟng community members
who may face burdens from the increase in property
values, such as increased costs for renters. This secƟon
provides an approach to foster and guide private
development to enhance community character and
provide increased stability and prosperity for community
members. Also documented are more specific planning
and visioning efforts for two key development
opportuniƟes, at the Mini Triangle and 17‐Acre sites.
Foster and guide private development to enhance
community character and provide increased
stability and prosperity for community members.
Mini Triangle site rendering excerpt; Source: Zyscovich Architects
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐32
5.3
Objective 1: Improve the marketing,
branding, and communication approach for
the CRA area.
Strategy 1: Create a branding strategy for the CRA
area to establish a community vision and
character. This strategy should coordinate with
the Arts and Culture Plan and the Market Study
for the CRA (see SecƟon 5.3.4, ObjecƟve 1,
Strategy 5 and SecƟon 5.3.4, ObjecƟve 3, Strategy
1).
Strategy 2: Create a markeƟng and
communicaƟon strategy for the CRA area to
communicate vision and character with effecƟve
tools (e.g., website, social media, branding
materials). This strategy should coordinate with
the comprehensive design approach developed
for the CRA area (see SecƟon 5.3.2, ObjecƟve 3,
Strategy 1), as well as improved communicaƟon
efforts between the CRA and the community (see
SecƟon 5.3.7, ObjecƟve 1).
Strategy 3: Provide CRA administraƟve materials
(e.g., Advisory Board agendas, budgets, annual
reports) in an accessible and easy‐to‐understand
way.
Strategy 4: Coordinate with the Collier County
Tourist Development Council, Collier County Parks
& RecreaƟon Division, and other jurisdicƟons to
promote the CRA area and its local business and
commercial establishments as part of tourism
development efforts in the area. This should
include coordinaƟon with Collier County Parks &
RecreaƟon related to East Naples Community Park
master planning and pickleball sports tourism.
Strategy 5: Create an Arts and Culture Plan for the
CRA area to incorporate into the overall CRA area
vision. This effort should:
Consider prior arts and culture planning efforts,
such as those related to the Bayshore Cultural
District (ResoluƟon No 2008‐60).
Incorporate an inventory of exisƟng arƟsƟc and
cultural features of the community to elevate.
Include a comprehensive public realm design
approach for the CRA area and sub‐areas (see
SecƟon 5.3.2, ObjecƟve 3, Strategy 1).
Consider housing needs and economic incenƟves
related to arts and culture‐oriented development
(see SecƟon 5.3.4, ObjecƟves 3 and 5).
Include administraƟve needs of implemenƟng the
plan (e.g., an arts commiƩee, addiƟonal staff).
Coordinate with countywide arts and culture
strategic planning efforts.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐33
5.3
Objective 2: Streamline and clarify the
development process
Strategy 1: Coordinate with Collier County Zoning
Division to clarify LDC requirements related to
development in the CRA area, parƟcularly related
to:
RelaƟonship of overlay zoning to base
zoning
RelaƟonship of various applicable codes to
each other (e.g., LDC, fire code, building
code)
Allowable uses
Strategy 2: Coordinate with Collier County Zoning
Division to evaluate approaches to streamline and
shorten the development review process.
Approaches might include:
DedicaƟng County staff to review projects
within the CRA area and expedite them
through the development process.
Improving coordinaƟon and communicaƟon
between enƟƟes overseeing applicable
codes (e.g., Zoning, Fire Marshall).
IdenƟfying opportuniƟes to increase
reliance on defined criteria for development
approval (as opposed to discreƟonary
approval)
Encouraging design‐build approaches.
Strategy 3: Establish a formal role for the CRA in the
development review process to facilitate
development of projects in the CRA area.
Clearer LDC guidance would help new uses such as microbreweries
US Open Pickleball Championships at East Naples Community Park.
Source: Collier County Parks & RecreaƟon Division, hƩps://
www.facebook.com/CollierParks/photos/
a.852037184807466.1073741827.118036328207559/19606389606
13944/?type=3&theater
ExisƟng arƟsƟc features, such as murals, should be considered in the
Arts and Culture Plan
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐34
5.3
Objective 3: Incentivize desired types of
development.
Strategy 1: Conduct a market study, including
informaƟon on owners of second homes, which is
not captured in typical data sets, to determine
what development will be supported in the CRA
area.
Strategy 2: IdenƟfy incenƟves and targeted
assistance (see Development Assistance and
IncenƟves Examples) for a range of development
and redevelopment, including consideraƟon of
the following types of development and addiƟonal
desirable development supported by the market
study:
Local neighborhood commercial
establishments
Social enterprises and business
opportuniƟes for those with tenuous
livelihoods
Larger catalyst development projects
Arts‐oriented development
Strategy 3: Evaluate and amend as needed current
grant program offerings to reflect new incenƟves
and assistance approaches from SecƟon 5.3.4,
ObjecƟve 3, Strategy 2.
Objective 4: Capitalize on current and
potential real estate and development
opportunities.
Strategy 1: Facilitate tenancy, development, and
redevelopment, parƟcularly for opportuniƟes
along US 41, Linwood Ave and neighboring non‐
residenƟal areas, and Bayshore Dr, through
incenƟves and communicaƟon efforts (see
Development Assistance and IncenƟves
Examples).
Strategy 2: ConƟnue to facilitate exisƟng catalyst
project opportuniƟes on the Mini Triangle and 17‐
Acre sites (see Map 5‐3‐10) to strengthen and
solidify development interest in the CRA area.
Efforts might include assisƟng with coordinaƟon
of property owners in target areas, negoƟaƟng
desired ameniƟes to be incorporated into
proposed development, and providing incenƟves
(see Development Assistance and IncenƟves
Examples).
Strategy 3: Evaluate alternaƟve funding
opportuniƟes, such as private funding and
donaƟons, for capital projects.
Strategy 4: Assess development opportuniƟes for
the AcƟvity Center area, including the Courthouse
Shadows site.
Strategy 5: Evaluate concepts to expand the CRA
boundaries . ConsideraƟons might include the
incorporaƟon of new development opportuniƟes,
such as areas along Thomasson Drive, and the
incorporaƟon of County parks.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐35
5.3
Development Assistance and Incentives Examples
Density/intensity increases
Impact fee offsets or payment over Ɵme
TIF rebates and TIF money for infrastructure
Land acquisiƟon through CRA for targeted needs,
such as parking and stormwater infrastructure, and
to facilitate redevelopment
Tenant aƩracƟon and relocaƟon support
Micro‐enterprise incubator and technical assistance
support in partnership with other local enƟƟes
PotenƟal Partnership OpportuniƟes for
Micro‐Enterprise Incubator
Incubators can provide workspace and assistance to
micro‐enterprises, parƟcularly small businesses, looking
to get their start in the CRA area. The CRA could
potenƟally partner with exisƟng efforts or collaborate
on new efforts to support the work of incubators. For
example, the Naples Accelerator
(hƩps://naplesaccelerator.com/) provides office space
and ameniƟes and connecƟons to local economic
resources to assist its member businesses. There may
also be interest from other local enƟƟes, such as St.
MaƩhew’s House, in partnering to start a new
incubator. Such partnerships can bring together
organizaƟons to pool capacity and funding to carry out
incubator efforts and can also be used to support arƟsts
and arts‐oriented development, a key aspect of the
CRA’s vision.
Other Partnership OpportuniƟes: Business AssociaƟons
The CRA encourages businesses operaƟng in the area to
form associaƟons and business districts to coordinate
development efforts and potenƟal funding tools such as
MSTUs. Such associaƟons can also serve as important
partners to the CRA in its implementaƟon of
development assistance and incenƟves. Areas where
these associaƟons might be parƟcularly beneficial are
among the Bayshore Drive businesses, the Mini
Triangle are property owners, and the property
owners along Linwood Avenue and Kirkwood
Avenue.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐36
5.3
Development and Redevelopment Potential
Figure 5‐3‐5 provides a general indicaƟon of the development opportuniƟes in the CRA area, showing vacant land
acreage and the corresponding number of vacant parcels by land use type that could potenƟally be developed
and indicaƟng that most of the vacant acreage is residenƟal. Map 5‐3‐9 indicates where these parcels are located.
As the map indicates, the parcel sizes can run fairly small, so assembly may be a consideraƟon for developers. The
background analysis for the Redevelopment Area Plan also indicates a sizable number of parcels with structures,
parƟcularly single‐family and mobile homes, that might benefit from upgrades to improve their structural
condiƟon. These efforts should take into account any potenƟal increases in prices and costs when units are
upgraded to avoid pricing out residents who find the new price and cost points unaffordable.
Total Vacant Acreage: 186
Figure 5‐3‐5: Vacant Land Acreage DistribuƟon by Land Use Type .
*Note: A 32.5‐acre parcel northwest of the Bayshore/Thomasson intersecƟon is coded as Vacant InsƟtuƟonal but is owned by MaƩamy Naples LLC. (Source:
2017 Florida Department of Revenue)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐37
5.3
Map 5‐3‐9: Vacant Land Parcels in CRA Area . Note: Vacant insƟtuƟonal land northwest of Bayshore Dr/Thomasson Dr intersecƟon is coded as Va-
cant InsƟtuƟonal but it owned by MaƩamy Naples LLC. (Source: 2017 Florida Department of Revenue)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐38
5.3
Development & Real Estate Opportunities
The CRA can facilitate development, redevelopment, and tenancy of vacant spaces through incenƟves and
improvements to the surrounding areas. Map 5‐3‐10 and corresponding images show some of the key
opportuniƟes in the CRA area; note that the Mini Triangle site and the 17‐Acre Site contain parcels currently
owned by the CRA.
Linwood Avenue commercial corridor redevelopment
Gulfgate Plaza office tenant opportunity
Del’s 24 redevelopment opportunity
Bayshore Drive commercial corridor redevelopment (including Halde‐
man Creek Entertainment District near Creek)
Courthouse Shadows redevelopment
1
4 3
2
5
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐39
5.3
3
2
Map 5‐3‐10: Development & Real Estate OpportuniƟes with Non‐ResidenƟal ExisƟng Land Use; Data source: 2017 Florida Department of Revenue
LINWOOD AVE BAYSHORE DR 4
5
1
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐40
5.3
Collier County Mobile Home Upgrade Program
Collier County Community & Human Services Division
currently oversees a program that uses State Housing
IniƟaƟves Partnership (SHIP) program funds to replace
mobile homes with more sturdy single‐family modular
homes in response to hurricane damage. In Everglades
City, these homes are elevated on sƟlts. The Bayshore
Gateway Triangle CRA may be able to refine this pro‐
gram to meet the needs of the community to encour‐
age replacement with a more suitable building type for
the area.
Residential Renovation & the FEMA 50% Rule
The FEMA 50% Rule requires that any exisƟng building
within an idenƟfied FEMA Flood Zone will have to be
upgraded to meet current flood standards if improve‐
ments are made that are in excess of 50% of the struc‐
ture value. When determining structure value, only the
value of the improvement itself (exclusive of land value)
is considered. During the building permit review pro‐
cess, the County will require anyone located within a
flood zone to go through a review process to ensure
that proposed improvements are not worth in excess of
50% of the building value. The CRA may consider devel‐
oping partnerships/grants to assist in replacing struc‐
tures to encourage bringing exisƟng buildings up to
code and maintain affordability.
Impact Fee Deferral for Income-Restricted Units
Several ciƟes and counƟes in Florida, including Collier
County, offer impact fee incenƟves for affordable and/
or workforce housing. In Collier County, for‐purchase
and rental units for households with incomes less than
120% of median income in the county qualify for impact
fee deferrals. Deferrals are equivalent to up to 3% of
the prior year’s total impact fee collecƟons, a cap insƟ‐
tuted to minimize revenue lost through the program.
Objective 5: Incorporate protections in de-
velopment efforts to enhance existing
community character and support existing
CRA area residents.
Strategy 1: Establish assistance programs and
incenƟves to protect and enhance exisƟng com‐
munity‐oriented uses and local neighborhood
commercial and single‐family neighborhoods off
the main corridors. Assistance and incenƟve dis‐
tribuƟon might account for building age, struc‐
tural quality, and means of property owners.
Strategy 2: In coordinaƟon with the Collier Coun‐
ty Affordable Housing Advisory CommiƩee, pro‐
mote strategies to maintain current affordable
housing availability in the CRA while improving
baseline quality condiƟons. Strategies to consider
include:
Community land trust
CoordinaƟng with Collier County Com‐
munity & Human Services Division for
mobile home upgrades and replace‐
ments with alternaƟve unit types (see
Housing Assistance and IncenƟves Exam‐
ples)
ResidenƟal renovaƟon loan/grant pro‐
gram
Encouraging use of Collier County’s im‐
pact fee deferral program for income‐
restricted units (see Housing Assistance
and IncenƟves Examples)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐41
5.3
The County also limits to 225 the number of rental units
receiving deferrals. Impact fees are deferred for owner‐
occupied units unƟl the owner sells, refinances, or
moves out of the home, at which Ɵme fees are due with
interest. Rental unit fees are deferred for a 10‐year pe‐
riod. Historically, this level of deferral has allowed the
program to defer impact fees on approximately 100
homes per year. A pilot program for payment of impact
fees by installments collected through property tax bills
(as an alternaƟve to making the enƟre payment up‐
front) was also planned for the Immokalee CRA area.
The Bayshore Gateway Triangle CRA could support or
replicate the County’s program to defer fees in the
Bayshore Gateway Triangle CRA area; this approach
could also be used to incenƟvize other types of desired
development, as well.
Case InformaƟon Source: Tindale Oliver (August 2017), Impact Fee Incen‐
Ɵves for Affordable/Workforce Housing.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐42
5.3
5.3.5 Transportation,
Connectivity, & Walkability
Having a variety of transportaƟon opƟons that are
easy and desirable to use are important for all who
live and work in the CRA area. TransportaƟon systems
not only cater to local needs between the CRA area
and places such as Downtown Naples and local work‐
places, but also to more regional traffic moving
through the CRA area on major roadways. In light of
the various needs, this secƟon aims to ensure safety,
comfort, and convenience for various modes within
and connecƟng with the CRA area.
Ensure safety, comfort, and convenience for various
modes within and connecting with the CRA area.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐43
5.3
Objective 1: Increase safety, comfort, and
connectivity for active transportation modes
(e.g., walking and biking).
Strategy 1: Create a strategy to implement discrete
transportaƟon improvements and more
comprehensive Complete Streets corridor
improvements.
Strategy 2: The effort undertaken for Strategy 1
should include development of a sidewalk master
plan with inclusion of the following:
Visibility assessment related to landscaping
ConsideraƟon of connecƟons to
neighboring parks (see SecƟon 5.3.3,
ObjecƟve 1, Strategy 1 and Strategy 6 in
this secƟon)
CoordinaƟon with roadway and
infrastructure improvements planned and/
or approved for implementaƟon, including
those that may stem from this
Redevelopment Area Planning process or
other agency planning and implementaƟon
efforts (e.g., County and CRA stormwater
master planning).
Strategy 3: IdenƟfy opportuniƟes to coordinate
transportaƟon capital improvements with County/
MPO improvements along major arterials.
Strategy 4: Pilot transportaƟon improvements, such
as elements of Complete Streets corridor
improvements, elements of Bayshore Dr road diet
(traffic lane consolidaƟon), reduced turning radii at
intersecƟons to slow traffic, and addiƟonal
pedestrian crossings, with temporary installaƟons.
These efforts should incorporate community input
and feedback to gauge response to more urban‐
style development and any parƟcular concerns to
address or opportuniƟes on which to capitalize.
These installaƟons can be incorporated into
community events that include educaƟonal
elements on, for example, Complete Streets, the
Vision Zero effort to eliminate bicycle and
pedestrian fataliƟes, and roundabouts.
Strategy 5: Based on input from temporary
installaƟons from Strategy 4, move forward with
veƫng of Bayshore Dr road diet concept scenarios
and traffic analysis.
Strategy 6: Evaluate opportuniƟes for a north/
south bicycle and pedestrian connector in the
eastern Bayshore area with connecƟons to Sugden
Park and East Naples Community Park (see SecƟon
5.3.3, ObjecƟve 1, Strategy 1).
What are Complete Streets?
Streets that “serve the transportaƟon needs of
transportaƟon system users of all ages and abiliƟes,
including pedestrians, bicyclists, transit riders,
motorists, and freight handlers. A transportaƟon
system based on Complete Streets principles can help
to promote safety, quality of life, and economic
development.” ‐ FDOT, CompleƟng Florida’s Streets,
hƩp://www.flcompletestreets.com/files/FDOT‐
CompleteStreets‐Brochure.pdf.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐44
5.3
Existing Transportation Conditions
Map 5‐3‐11 highlights exisƟng transportaƟon condiƟons idenƟfied by fieldwork. Roadways in the CRA area range from large
arterials carrying regional traffic to small neighborhood streets, many of which dead‐end throughout the CRA area. During
fieldwork, cyclists were noted on the sidewalks of larger arterials such as Davis Boulevard and Airport Pulling Road, and
many bikes were parked at Gulfgate Plaza off of US 41. The MPO and FDOT also idenƟfied Airport Pulling Road and US 41 as
high bike/pedestrian crash corridors. RelaƟve to other streets, Bayshore Drive has a number of improvements, including
bike lanes, sidewalks, and transit shelters, yet it sƟll experiences a lack of parking. There are limited pedestrian connecƟons
to parks from streets off Bayshore Drive; one connecƟon is at Republic Drive. Note that these exisƟng condiƟons are a
general, preliminary assessment, with more detailed measures of exisƟng condiƟons such as trip counts and traffic
modeling anƟcipated as part of follow‐up strategy– and project‐specific evaluaƟon prior to a decision to implement.
Divided arterial with street‐fronƟng parking
Bayshore Drive with sidewalks and bike lanes
Dead‐end neighborhood street
Cyclist on sidewalk of arterial
Bus shelter at Bayshore Drive and Thomasson Drive
Pedestrian bridge to East Naples Community Park
1
3
2
4
5 6
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐45
5.3
1
2
3
4
5
6
Map 5‐3‐11: ExisƟng TransportaƟon CondiƟons with Roadway ClassificaƟons
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐46
5.3
Bicycle & Pedestrian
Curb extensions
General bike accessibility
Pedestrian crossing(s)
Bike lanes
General connecƟvity, walkability
North/south connecƟvity
East/west connecƟvity
Sidewalk(s)
Wayfinding
LighƟng
Road diet (lane reducƟon)
Traffic
Traffic circulaƟon along corridor, including
intersecƟons
Traffic calming
Connect street
Parking
Commercial parking
Parking including boat parking
Specific Transportation Needs & Considerations
Fieldwork, discussions with CRA staff, public outreach, and specific project recommendaƟons from the 2018 Blue
Zones Project/Dan Burden East Naples Discovery Report informed locaƟon‐specific, discrete transportaƟon needs and
consideraƟons in the CRA area (Map 5‐3‐12). Many of these needs and consideraƟons will be addressed through
Complete Streets projects recommended in this Redevelopment Area Plan. Other transportaƟon improvements such as
addressing sidewalk and bike infrastructure gaps, providing parking infrastructure, and providing wayfinding signs will
be addressed through separate project recommendaƟons. Note that “Major Corridors” are designated based on
highways, minor arterials, and major arterials in the area. “Needs Corridors” are designated where needs idenƟfied are
generalized along the length of a roadway segment (related needs are those where labels intersect the corridor on
Map 5‐3‐12).
1
2
3
1
2
Major Corridor Needs Corridor
1
2
3
4
5
6
7
8
9
10
11
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐47
5.3
4 8
3
2
2
8
DAVIS BLVD BAYSHORE DR 7
THOMASSON DR HAMILTON AVE 2
1
1
1
1
1
3
1
3
1
2
1
2
1 10
2
7
7
7
6
7
6
9
5
2
1
11
10 AIRPORT RD S Map 5‐3‐12: TransportaƟon Needs & ConsideraƟons
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐48
5.3
Regional & County Transportation Projects
The projects shown in Map 5‐3‐13 are those idenƟfied in the Collier Metropolitan Planning OrganizaƟon’s Fiscal Year
2017/18 to 2021/22 TransportaƟon Improvement Program (which also features the Collier County five‐year program)
and the trail recommendaƟons from the Comprehensive Pathways Plan update process. These projects will thus be
overseen by regional and county transportaƟon agencies. The full set of recommendaƟons from the Comprehensive
Pathways Plan, once finalized, should also be considered in conjuncƟon with transportaƟon planning and
improvements led by the CRA.
Major Corridor
FDOT TIP Projects
US 41 resurfacing
US 41 signal Ɵming improvements
Davis Boulevard resurfacing
1
3 MPO Pathways Plan Proposed Trail Improvements
Naples Bay Greenway (Sun Trail)
2 County TIP Projects
Davis Boulevard/Airport Pulling Road
intersecƟon improvement
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐49
5.3
DAVIS BLVD BAYSHORE DR THOMASSON DR NAPLES BAY GREENWAY (SUN TRAIL) 3
1 2 AIRPORT PULLING RD Map 5‐3‐13: Regional & County TransportaƟon Projects
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐50
5.3
Potential CRA Complete Streets Projects & Trails
Complete Streets is an approach to comprehensive corridor improvements tailored to the size and land use context of the
corridor. This approach can address many of the major needs and consideraƟons idenƟfied in Map 5‐3‐13, including traffic
calming, sidewalks, bike lanes, lighƟng, wayfinding, on‐street parking, and landscaping. Complete streets improvements can
also be coordinated with other infrastructure improvements, such as water main, fire suppression, and drainage upgrades.
The CRA can take the lead on Complete Streets projects, focusing on the streets listed below categorized. Fieldwork, staff
discussions, public outreach, and prior planning efforts informed which streets were targeted for these improvements.
Map 5‐3‐14 shows recommended projects for neighborhood streets and busier corridors (“Major Complete Streets”).
Suggested improvements for Major Complete Streets corridors may include changes to the roadway for vehicles (such as
the addiƟon of on‐street parking). Neighborhood Complete Streets & Trails recommendaƟons focus primarily on
improvements for pedestrians, cyclists, and other acƟve transportaƟon (see the remainder of SecƟon 5.3.5 for examples of
suggested improvements). ConnecƟvity in terms of desƟnaƟons and network connecƟons was a key consideraƟon in
selecƟon and prioriƟzaƟon of these projects. Note that the length of the bicycle and pedestrian trail will depend on
consideraƟons such as available right‐of‐way; the SecƟon 5.4 capital planning provides an esƟmate for a secƟon between
East Naples Community Park and Sugden Regional park. Also note that the Kirkwood Avenue “connecƟon” between Pine
Street and Shadowlawn and the Pine Street “connecƟon” between Davis and Linwood refer to proposed roadway
extensions that that do not have exisƟng right‐of‐way.
Major Corridor
Major Complete Streets
Linwood Avenue—Phase I
Shadowlawn Drive
Bayshore Drive (north of Thomasson Drive)
Thomasson Drive
Commercial Drive
Kirkwood Ave/Kirkwood Ave ConnecƟon to
Shadowlawn Drive
Pine Street ConnecƟon
2 Neighborhood Complete Streets & Trails
Bay Street
Linwood—Phase II
Danford Street
Hamilton Avenue
Jeepers Drive
Republic Drive
Bayshore Drive (south of Thomasson Drive)
Bicycle/Pedestrian Trail
1
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐51
5.3 HAMILTON BAY ST
JEEPERS
LINWOOD AVE SHADOWLAWN DR 1
DAVIS BLVD
2 BAYSHORE DR THOMASSON DR
2 COMMERCIAL DR 2 BICYCLE & PEDESTRIAN 1 AIRPORT PULLING RD DANFORD
REPUBLIC DR
KIRKWOOD AVE PINE ST 2
Map 5‐3‐14: PotenƟal Complete Streets Projects
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐52
5.3
Character Images for Complete Streets Improvements and Connections
The following images illustrate Complete Streets elements from prior planning efforts for Bayshore Dr and Complete Streets
improvements elsewhere.
These efforts and examples inspired the renderings of possible transformaƟons for Linwood Ave, Bayshore Dr, and Jeepers
Dr (shown in Figures 5‐3‐6 through 5‐3‐9) suggested as part of this Redevelopment Area Plan update effort. As corridors for
potenƟal commercial redevelopment, the Linwood Ave and Bayshore Dr renderings highlight an emphasis on ample
sidewalk space along the landscaping and storefronts. Linwood Ave might promote a more modern design style for lighƟng
and streetscape features as shown in Figure 5‐3‐6 and potenƟally further inspired by the modern style images on page 5‐3‐
22. Bayshore Dr might retain the exisƟng style of streetscape elements in the lighƟng and signs. These renderings can
provide a starƟng point for Complete Streets designs of other busier corridors (see “Major Complete Streets” on Map 5‐3‐
49), with the Linwood Ave design parƟcularly suited as a basis for the suggested re‐designs of Commercial Dr and Kirkwood
Ave.
As a less traveled residenƟal street type, Jeepers Dr shows how people biking, walking, and playing can share the street
space with cars accessing residences. Given that many streets dead‐end and do not allow for through traffic, more
simplified pedestrian infrastructure may be promoted over formal sidewalks. For example, the pedestrian space in the
PotenƟal cross secƟon for Bayshore Dr road diet, as proposed in Trebilcock’s 2017 Parking Needs Analysis. ExisƟng cross secƟon is four‐lane
road with bike lanes and sidewalks
Complete Streets improvement
examples (LeŌ image source:
Wikimedia Commons)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐53
5.3
Figure 5‐3‐6: PotenƟal Cross SecƟon of Linwood Ave
rendering might be indicated with road paint. The swales have also been retained for water quality consideraƟons, but
incorporate vegetaƟon to improve the visual appearance of swales. Porous pavement may also be an opƟon for the areas
where swales are represented, which might require different maintenance costs (an aspect that would be addressed with a
more detailed follow‐up design evaluaƟon as noted below). LighƟng in provided on one side given the limited road space,
similar to improvements made on Lunar St in the CRA area. This type of design might serve as a starƟng point for the re‐
design of other neighborhood Complete Streets projects (see Map 5‐3‐49).
Note that these proposed cross secƟons are only intended for general, iniƟal illustraƟve purposes; final designs would need
to account for a more detailed study and analysis of factors including engineering consideraƟons, impacts, miƟgaƟon
needs, and potenƟally the increase of alternaƟve transportaƟon methods (see ObjecƟve 2, Strategy 1 of this secƟon for
examples). For example, a follow‐up analysis of a lane reducƟon proposal on Bayshore Drive would need to account for
impacts to Level of Service standards on the roadway and on connecƟng roadways such as US 41, air quality, freight and
evacuaƟon routes, and a variety of other factors. It would also study whether addiƟonal easements would be needed or
desired for a re‐design. PiloƟng temporary versions of these improvements also provides a way to vet the design. This plan
accounts for this follow‐up analysis need and piloƟng with budgeted items for a Bayshore Drive technical feasibility study, a
Complete Streets ImplementaƟon Plan that would provide a next‐level feasibility analysis for these projects, and a Bayshore
Drive pilot project with opportuniƟes for addiƟonal pilots as part of the “other” non‐capital projects budget item (see
SecƟon 5.4 for more informaƟon).
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐54
5.3
Figure 5‐3‐8: PotenƟal Cross SecƟon for Jeepers Dr
Figure 5‐3‐7: PotenƟal Cross SecƟon for Bayshore Dr
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐55
5.3
Figure 5‐3‐9: PotenƟal Aerial Rendering for Jeepers Dr
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐56
5.3
Objective 2: Increase and enhance
alternative vehicle mode options within and
connecting with the CRA area.
Strategy 1: Evaluate opportuniƟes for alternaƟve
transportaƟon methods (e.g., golf carts, electric
shuƩles, other neighborhood/electric vehicles,
shared and/or autonomous vehicles, bikeshare,
water‐borne transportaƟon), including
consideraƟons for partnerships with neighboring
communiƟes.
Strategy 2: Coordinate with Collier County Public
Transit & Neighborhood Enhancement
Department for transit service and faciliƟes
improvements (e.g., more frequent service and
transit stop shelters).
Strategy 3: Evaluate opƟon to expand
TransportaƟon Concurrency ExcepƟon Area
(TCEA) to include enƟre CRA area.
Objective 3: Improve parking options in
commercial areas.
Strategy 1: Evaluate parking concepts for the
Bayshore Dr and Mini Triangle/Linwood Ave
commercial areas, which may include:
Shared parking with shuƩle service,
parƟcularly to meet peak‐season demand
Reduced design requirements for parking
On‐street parking as part of the Bayshore
Dr road diet
Parking garages
Parking miƟgaƟon fee (development pays
for construcƟon of public parking in lieu
of providing parking spaces)
ConsideraƟons for changes in alternaƟve
transportaƟon methods such as those
noted in ObjecƟve 2, Strategy 1 of this
secƟon.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐57
5.3
Transportation Concurrency Exception Area (TCEA)
Policy 5.4 of the TransportaƟon Element in the Growth Management Plan created the South US 41 TCEA. This
designaƟon allows commercial and residenƟal developments an excepƟon to meeƟng transportaƟon
concurrency standards, which relate to the Ɵming and programming of necessary transportaƟon faciliƟes to
ensure they are generally provided in a Ɵmeframe comparable to the development. (see Policy 5.3 of the Capital
Improvement Element for more details). The strategies developers can use to obtain the excepƟon are intended
to reduce trips or miles traveled in single‐occupancy vehicles, such as incenƟves and ameniƟes to promote
transit, carpooling, telecommuƟng, walking, and biking. This Redevelopment Area Plan reinforces these strategies
by promoƟng mixed‐used and urban land use types that support alternaƟve transportaƟon (see SecƟon 5.3.2).
ObjecƟves 1 and 2 of this secƟon also promote improved faciliƟes for walking, bilking, and transit use. A potenƟal
opƟon to further align the redevelopment efforts of the CRA and the goals of the TCEA is to expand the TCEA to
include all of the CRA area, expanding the excepƟon applicability to further encourage alternaƟve transportaƟon.
South US 41 TCEA (Source: Collier County Growth Management Plan, TransportaƟon Element, Map TR-4)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐58
5.3
Downtown Naples Mobility and Connectivity Study
This study, completed in 2017, included a recommendaƟon for an improved bicycle and pedestrian pathway on the Gordon
River Bridge (5th Avenue/US 41) that connects Downtown Naples and the Triangle area. The proposed design calls for
narrower travel lanes and removal of the road shoulder to increase the bicycle and pedestrian pathway to 14 feet on either
side of the bridge. If implemented, the responsibility for carrying out the project would be FDOT.
Proposed typical secƟon for Gordon River Bridge bicycle and pedestrian improvement from 2017 Downtown Naples Mobility and ConnecƟvity Study
(Source: City of Naples, hƩps://www.naplesgov.com/sites/default/files/fileaƩachments/streets_amp_stormwater/project/3351
city_council_presentaƟon_201710_final_revisions.pdf)
Objective 4: Improve transportation connections with Downtown Naples.
Strategy 1: Coordinate with the City of Naples to explore and partner on transportaƟon improvements and
approaches serving both Downtown Naples and the CRA area noted in ObjecƟve 2, Strategy 1 of this secƟon.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐59
5.3
5.3.6 Infrastructure
Infrastructure can be key to facilitaƟng development,
providing the services communiƟes need to funcƟon.
Certain infrastructure, such as for stormwater
management, is parƟcularly important in the CRA
area, which grapples with natural environmental
factors including storms and flooding but also
benefits from a healthy natural environment due to
quality of life factors and tourism. As a result, the
framework for this secƟon aims to provide effecƟve
infrastructure that preserves environmental and
neighborhood design quality through coordinated
improvement planning and funding.
Provide effective infrastructure that preserves
environmental and neighborhood design quality
through coordinated improvement planning and
funding.
Objective 1: Ensure that infrastructure
provided will effectively achieve its primary
purpose without significantly compromising
environmental and neighborhood design
quality.
Strategy 1: Develop a stormwater master plan for
comprehensive infrastructure improvements that
incorporates consideraƟon for the following:
Flood plain designaƟons, including FEMA
flood designaƟons and Coastal High
Hazard requirements
Building and site plan design to respond
to flooding
Primary, secondary, and terƟary
infrastructure improvements (both short‐
and long‐term)
PotenƟal for a bicycle and pedestrian
pathway in easement of north/south
drainage ditch along Sugden Regional Park
Shared maintenance and maintenance
funding between County and CRA
Water quality
Use/design of right‐of‐way areas on local
streets, including an evaluaƟon of turf
block (see page 5‐3‐58)
InnovaƟve techniques to pilot in CRA area,
including green infrastructure
Strategy 2: Coordinate stormwater infrastructure
planning with design of new parks (see SecƟon
5.3.3, ObjecƟve 1).
Strategy 3: Integrate green infrastructure
improvements into landscaping and drainage
improvements, including those funded by the
Bayshore BeauƟficaƟon MSTU.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐60
5.3
Green Infrastructure Examples
Green infrastructure aims to reduce stormwater runoff and
treat it closer to its source while providing environmental,
social, and economic benefits. The following examples create
surfaces or collecƟon structures that allow stormwater to
infiltrate the underlying or surrounding ground. They also can
help manage stormwater flows and improve water quality of
runoff and oŌen can be combined with vegetaƟon and
landscaping.
InfiltraƟon basin/retenƟon pond – shallow basins or
ponds that collect stormwater and can allow it to
infiltrate the underlying ground
Permeable pavement – pavement that allows water to
flow through and infiltrate the underlying ground
Rain garden – shallow planted basins that allow water to
infiltrate the ground
Bioswales – vegetated or soŌ‐lined channels that collect
and convey, slow, and clean water and let it infiltrate into
the ground
Vegetated planter boxes and bulb‐outs– infiltraƟon areas
with raised edges that can be incorporated into roadway
design features
Tree planƟngs
Vegetated infiltraƟon area in roadway bulb-out in PalmeƩo, FL at
10th Ave W and 5th St W (Source: Google Maps, hƩps://
www.google.com/maps/@27.5151522,-
82.575633,3a,60y,118.29h,75.57t/data=!3m6!1e1!3m4!
1slahgGjvzSzLDetQ43h5HQg!2e0!7i13312!8i6656)
Kissimmee Lakefront Park rain gardens (Source: City of Kissimmee,
hƩps://www.kissimmee.org/Home/Components/News/
News/2208/263?backlist=%2F)
RetenƟon pond ameniƟes in Tampa at E Dr MarƟn Luther King Jr. Blvd and N 19th St (Source: Google Maps, hƩps://www.google.com/maps/@27.9815571,
-82.4391844,3a,60y,90t/data=!3m6!1e1!3m4!1sQJ3uI3LDTatc2Vr7pkfflg!2e0!7i13312!8i6656)
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐61
5.3
Objective 2: Coordinate with other
jurisdictions and government entities for
infrastructure planning and funding.
Strategy 1: IdenƟfy addiƟonal funding
opportuniƟes to supplement capital
improvements funds (e.g., grants).
Strategy 2: Document the project prioriƟzaƟon
strategy to upgrade water lines and fire
suppression systems in coordinaƟon with the City
of Naples.
Strategy 3: As part of the stormwater master plan
(ObjecƟve 1, Strategy 1 of this secƟon),
coordinate with Collier County Stormwater
Management to integrate CRA stormwater
infrastructure planning with County stormwater
planning efforts.
Strategy 4: As part of the stormwater master plan
effort (ObjecƟve 1, Strategy 1 of this secƟon),
coordinate with Collier County Zoning Division to
create right‐of‐way design guidelines for
development that coordinate with Complete
Streets concepts for neighborhood streets.
Strategy 5: Coordinate with Collier County
agencies and uƟlity providers to idenƟfy and
improve other infrastructure including sanitary
sewer lines, roadways that fail to meet minimum
standards, and electrical uƟliƟes idenƟfied to be
placed underground or relocated.
Turf block, shown in the right-of-way area immediately bordering the
street in the photo above, has been used in certain developments in the
Bayshore neighborhood to allow for use of right-of-way space for park-
ing. This opƟon should be evaluated as part of the right-of-way design
consideraƟons in the stormwater master plan update.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐62
5.3
Need for culverts for flooding,
RetenƟon pond area improvements needed—lighƟng, security, barriers/gates to direct car traffic,
pump improvements for flooding issues
Flooding issues and need for drainage
Flooding issues and need for drainage on side streets off of Bayshore Drive. Note that Pine Tree
Drive, Andrews Avenue, and Woodside Avenue have been idenƟfied as below County standards
(involving for example sufficient right‐of‐way, drainage, paving, or similar elements) in ResoluƟon
2011‐097. These streets should be a focus in stormwater and infrastructure planning to bring
them up to standards.
Flooding issues and need for drainage on Holly Avenue. Holly Avenue also idenƟfied as below
County standards and in need of road engineering improvements (see Item 4 above).
PalmeƩo Court idenƟfied as below County standards and in need of road engineering
improvements (see item 4 above).
Upgrades needed to sanitary sewer capacity in the Triangle area to support new development.
OpportuniƟes to place overhead electric uƟliƟes on Linwood Avenue and Commercial Drive
underground or relocate them.
Infrastructure—Stormwater, Roadway Engineering, Sanitary Sewer, Electric
Stormwater and flooding are major challenges in the CRA area, requiring special aƩenƟon be paid to stormwater
management projects. The CRA has already overseen a successful drainage improvement project on Karen Drive, and
moving forward, will coordinate with the County Stormwater Management SecƟon. Map 5‐3‐15 shows where further
stormwater management improvements are needed based on public outreach. AddiƟonal needs should be idenƟfied
through an updated stormwater master plan for the area. Other idenƟfied infrastructure needs on the map include
upgrading certain roads to meet County standards, upgrading capacity of sanitary sewer infrastructure in certain areas,
and placing underground or relocaƟng overhead electric uƟliƟes in certain areas.
1
2
3
4
5
6
7
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐63
5.3
6
7
9
1
2
3
4
5
6
7
Map 5‐3‐15: Infrastructure Needs—Stormwater, Roadway Engineering, Sanitary Sewer, Electric
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐64
5.3
Water Infrastructure
The City of Naples provides water and water infrastructure for the CRA area, which also supports fire suppression
systems such as fire hydrants. The fire suppression infrastructure can influence the insurance raƟngs for an area. On a
scale of 1 to 10 (with 1 being the best), the CRA area currently has an Insurance Service Office (ISO) raƟng of 4.
according to the Greater Naples Fire Rescue District. In pracƟce, the District typically assigns raƟngs of 4, 9, or 10.
The City is currently in the process of upgrading neighborhood water lines to support hydrants for fire suppression.
Areas highlighted in red on Map 5‐3‐16 indicate water mains that do not meet the standard fire flow requirements
determined by the City of Naples’ potable water model. These mains have potenƟal for replacement to upgrade for fire
flow improvements. However, note that other secƟons of the water mains in the CRA area are older and will need to be
replaced eventually.
There is conƟnued interest on the part of the CRA to idenƟfy and obtain grants to complete this work in partnership
with the City of Naples.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐65
5.3
Map 5‐3‐16: Water Infrastructure
Areas highlighted in red
indicate water mains that
do not meet the standard
fire flow requirements
determined by the City of
Naples’ potable water
model. These mains have
potenƟal for replacement
to upgrade for fire flow
improvements. However,
note that other secƟons of
the water mains in the CRA
area are older and will
need to be replaced even‐
tually.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐66
5.3
5.3.7 Process
The substance of the CRA’s planning and
implementaƟon is important, as is the way it carries
out this planning and implementaƟon. In view of the
diversity of communiƟes living and working in the CRA
area, this secƟon lays out a framework to carry out
CRA area planning and implementaƟon efforts to
engage and serve the various communiƟes within the
CRA area.
Carry out CRA area planning and implementation
efforts to engage and serve the various
communities within the CRA area.
Objective 1: Improve approaches and tools
for communicating with communities in the
CRA area and the general public.
Strategy 1: As part of the markeƟng and
communicaƟon strategy (see SecƟon 5.3.4,
ObjecƟve 1, Strategy 2), evaluate communicaƟon
mechanisms and tools that will most effecƟvely
communicate with the various communiƟes in
the CRA area.
Strategy 2: Coordinate with schools and other
community partners to improve outreach and
communicaƟon between the CRA and harder‐to‐
reach populaƟons.
Strategy 3: Provide mulƟ‐lingual communicaƟons
and materials.
Strategy 4: Create a CRA‐specific Capital
Improvement Plan to idenƟfy, prioriƟze, and
effecƟvely communicaƟon near‐term capital
improvements . Coordinate with MSTUs
operaƟng in the CRA area for relevant capital
improvement projects.
Objective 2: Ensure a targeted and
balanced distribution of CRA planning and
implementation efforts.
Strategy 1: Account for both need‐based and
geographic consideraƟons in the distribuƟon of
planning and implementaƟon efforts.
Strategy 2: IdenƟfy street blocks for targeted
comprehensive improvements, with a focus on
blocks that have already received some
improvements and consideraƟon for balanced
distribuƟon of these targeted blocks throughout
the enƟre CRA area.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐67
5.3
Strategy 3: Update rules and procedures for the CRA
Advisory Board for legal consistency and with
consideraƟon given to a balanced distribuƟon of
planning/implementaƟon efforts and diverse
representaƟon.
Objective 3: Coordinate with MSTUs in the
area and explore opportunities for new
MSTUs.
Strategy 1: Incorporate Haldeman Creek and
Bayshore BeauƟficaƟon MSTU Advisory Boards into
planning and implementaƟon processes for CRA
improvements.
Strategy 2: Explore the opƟon of creaƟng an MSTU
for capital improvements in the Triangle area north
of US 41.
5.3.8 Character Areas
In addiƟon to a diversity of communiƟes in the CRA
area, there is also a diversity of built character.
This secƟon tailors the themaƟc goals, objecƟves, and
strategies of the previous secƟons to specific character
areas within the CRA area as a whole.
The character areas numbered on the Map 5‐3‐17 are
defined by the land use characterisƟcs discussed in the
preceding maps. Key focus nodes, intersecƟons, and
corridors within the character areas that have potenƟal
for redevelopment are noted on the map with the
asterisks and doƩed lines.
For each Character Area, a brief descripƟon is provided
as well as a focus for redevelopment efforts to prioriƟze
framework elements for each area.
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐68
5.3
1 2
3 4
5 6
7
Focus Corridor
Focus Development Node/IntersecƟon
Mini Triangle/Davis
The Mini Triangle, including CRA‐owned
parcel, is a major commercial redevelopment
opportunity and Focus Development Node
Corridor commercial along Davis
Linwood Avenue another potenƟal area for
redevelopment.
Shadowlawn
Primarily a residenƟal neighborhood with mix
of apartments/duplexes and single‐family
homes around Shadowlawn Elementary
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Airport Pulling
Mix of corridor commercial, larger big‐box
style retail, and County Center
Part of area currently designated as an
AcƟvity Center in Future Land Use Map
Tamiami
Corridor commercial and residences,
including two major malls, Gulfgate Plaza and
Courthouse Shadows)
Borders US 41/Bayshore Drive Focus
IntersecƟon (asterisk), a gateway between
north and south secƟons of CRA area
Windstar
ResidenƟal is primarily condos and single‐
family homes in gated communiƟes
Includes golf course designated as a
commercial use
North Bayshore
Focus Corridor along Bayshore Drive with
neighborhood commercial (including
Haldeman Creek Entertainment District near
Creek)
Mix of mulƟ‐ and single‐family residenƟal
Focus IntersecƟon at Bayshore/Thomasson
with planned roundabout
CRA‐owned Focus Development Node (17‐
Acre Site)
South Bayshore
Primarily single‐family residenƟal
neighborhood with Naples Botanical Garden
Wetland consideraƟons for development
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐69
5.3
2
3
4
5
6
7 BAYSHORE DR LINWOOD AVE 1
Map 5‐3‐17: Character Areas
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐70
5.3
Focus of Redevelopment
The following provides a focus of redevelopment for
each Character Area based on the specific characteris‐
Ɵcs described for Map 5‐3‐17 and the most relevant
strategies.
1. Mini Triangle/Davis
Urban‐style mixed use commercial redevelop‐
ment, including capitalizaƟon on the Mini Triangle
as a catalyst development site and urban‐style
parking soluƟons
Park development at retenƟon pond site
Complete Streets design and commercial redevel‐
opment along Linwood Ave and other nearby
commercial roadways; pedestrian scale street de‐
sign between Mini Triangle, Linwood Ave, and the
proposed retenƟon pond park
Improved access to Mini Triangle development
from US 41, Davis Blvd, and Linwood Ave
MulƟ‐modal connecƟvity:
Across Davis Blvd
Between Mini Triangle, Linwood Ave, pro‐
posed retenƟon pond park, and eastern
Triangle neighborhood
To Downtown Naples potenƟally via Davis
Blvd, US 41, and Gordon River Bridge im‐
provements
AddiƟonal infrastructure improvements: sanitary
sewers, electrical, stormwater
2. Shadowlawn
ResidenƟal structural enhancement and upgrades
Avoidance of incompaƟble uses
TransiƟonal elements between different uses
Infill development on vacant residenƟal lots
Flooding and drainage on neighborhood streets
Complete Street improvements along Shadow‐
lawn Drive
3. Airport Pulling
TransiƟons between residenƟal neighborhoods
and commercial development
Eventual street enhancements, parƟcularly con‐
necƟvity across Airport Pulling Rd
Commercial façade improvements
4. Tamiami
ConnecƟvity to Downtown Naples via US 41
Redevelopment of Courthouse Shadows
Tenant opportunity at Gulfgate Plaza
5. Windstar
Complete Streets and MSTU improvements along
major community roadways, including Bayshore
Drive, Thomasson Drive, and Hamilton Avenue
Access to Bayview Park
6. North Bayshore
Corridor commercial development along Bayshore
Drive, including Haldeman Creek Entertainment
District near Creek and creaƟve parking soluƟons
Larger redevelopment opportuniƟes of 17‐Acre
Site and Del’s 24 property
Arts and culture‐oriented development
TransiƟonal elements between corridor commer‐
cial and residenƟal areas in along Bayshore Drive
and Thomasson Drive
Development of vacant residenƟal lots
Complete Street design along Bayshore Drive and
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐71
5.3
Thomasson Drive, including Bayshore Drive/
Thomasson Drive roundabout
Neighborhood Complete Streets and trails
ConnecƟons between Sugden Regional Park and
CRA area
Water main and fire suppression upgrades
Flooding and drainage on neighborhood streets
7. South Bayshore
Mobile home and single‐family home residenƟal
improvements, upgrades, affordability
Development of vacant residenƟal lots
Access to Bayview Park
ConnecƟons between CRA and uses to the east,
including East Naples Community Park
Wetland, flooding, and site preparaƟon considera‐
Ɵons for development
Roadway improvements to meet County engineer‐
ing standards
Neighborhood Complete Streets
PLANNING FRAMEWORK & ELEMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐3‐72
5.3
This page is intenƟonally leŌ blank.
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐1
5.4
5.4.1 Prioritization of Projects
& Initiatives
The CRA will need to evaluate and implement or
coordinate on a number of capital improvement
projects and planning, administraƟve, and regulatory
iniƟaƟves to carry out the framework of goals,
objecƟves, and strategies presented in SecƟon 5.3.
Since these projects and iniƟaƟves cannot be
evaluated and carried out all at once, this secƟon
presents a prioriƟzaƟon plan in terms of amount of
funds programmed and project/iniƟaƟve Ɵming. A key
consideraƟon for prioriƟzaƟon is the amount of
funding available for these projects and iniƟaƟves,
discussed more in SecƟon 5.4.2. Other prioriƟzaƟon
criteria to consider that were primarily highlighted in
the public outreach process include:
Funding availability from dedicated or outside
sources (aside from CRA funds)
Magnitude of anƟcipated impact and mulƟplier
effects
Whether planning has already been undertaken or
completed
Other consideraƟons that received sizable posiƟve
responses during the public outreach process
included:
Project Ɵming consideraƟons independent of
prioriƟzaƟon (e.g., Haldeman Creek dredging
should account for Ɵmeframe of sediment build‐
up, a stormwater master plan should be
completed before stormwater improvement
projects)
Ability to address health/safety concerns
AddiƟonal consideraƟons recommended by the
project team based on the Redevelopment Area Plan
update process include:
Degree of need
Geographic distribuƟon of projects in the CRA
area
PrioriƟes idenƟfied during public outreach for the
Redevelopment Area Plan
5.4.2 Financing Plan
The primary funding source for the CRA is Tax
Increment Financing (TIF) revenue generated by the
property within the CRA area. The Bayshore Gateway
Triangle CRA area is able to use County ad valorem tax
revenues generated above the base‐year amount (the
increment) to apply to projects and iniƟaƟves
idenƟfied in this Redevelopment Area Plan.
Figure 5‐4‐1 shows the historic revenue trends and
projected revenues through 2048 based on a low
growth scenario that follows the County’s historic
growth trends with a 4.8% assumed growth rate, a
medium growth scenario that assumes a 5.2% growth
rate, and a high growth scenario that assumes a 5.7%
growth rate. For more informaƟon on the
development of growth scenarios, methods of
revenue calculaƟon, and detailed revenue tables, see
SecƟon 5.6.
Certain parts of the CRA area are also designated as
Municipal Service Taxing Units (MSTUs), which uƟlize
an addiƟonal ad valorem tax for specific purposes.
The CRA can evaluate the opportunity to coordinate
with the MSTUs to provide eligible projects proposed
in this CRA plan.
The Bayshore BeauƟficaƟon MSTU, created in 1997,
applies to most of the CRA area south of US 41 (see
Map 5‐4‐1); revenues from this tax are focused on
streetscape and right‐of‐way improvements (including
right‐of‐way maintenance), with some addiƟonal
provisions for use of funds on other public realm
improvements in the MSTU area. Figure 5‐4‐2 shows
projected revenues through 2048 using the same
growth scenarios developed for the TIF revenue
calculaƟons (see SecƟon 5.6 for more informaƟon and
detailed revenue tables).
A Haldeman Creek MSTU (see Map 5‐4‐2) was created
in 2006 for maintenance dredging and navigaƟonal
marker maintenance within the MSTU boundary.
Figure 5‐4‐3 shows projected revenues through 2048
using the same growth scenarios developed for the TIF
revenue calculaƟons (see SecƟon 5.6 for more
informaƟon and detailed revenue tables).
Other potenƟal funding sources that may be idenƟfied
to supplement the funds above include grants and
funding from partnerships (other agencies and private
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐2
5.4
Map 5‐4‐1: Bayshore BeauƟficaƟon MSTU Area
Note: includes a boundary extension on Thomasson east of the CRA boundary that was pending approval during the development of this Redevelop‐
ment Area Plan.
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐3
5.4
Figure 5‐4‐1: CRA TIF Revenue Scenarios
Figure 5‐4‐2: Bayshore Beau. f caƟon MSTU Revenue Scenarios
Figure 5‐4‐3: Haldeman Creek MSTU Revenue Scenarios
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐4
5.4
Map 5‐4‐2: Haldeman Creek MSTU Area
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐5
5.4
funders). There may also be opportuniƟes in the
future to take on addiƟonal debt to pay for capital
projects with a plan for repayment. More informaƟon
on coordinaƟon and partnerships, including those for
funding opportuniƟes, is discussed in SecƟon 5.4.4.
5.4.3 Projects & Initiatives
Prioritization
Based on available funding and prioriƟzaƟon
consideraƟons, the following sets out the phasing for
recommended projects and iniƟaƟves with
descripƟons. Note that the sunset date for the TIF
Trust Fund is in 2060 (42 years), while the funding
Ɵmeframe for this plan is for 30 years through 2048 .
AddiƟonally, this plan should be re‐evaluated regularly
(e.g., every five years) to keep it relevant and updated
if redevelopment circumstances evolve.
This Plan does not obligate any funding to any projects
listed. This Plan provides a guide and list of both
capital and non‐capital projects that tax increment
revenues can fund if approved by the CRA and
allocated through the standard operaƟng and
procurement guidelines adopted by the Collier County
Board of Commissioners. Projects may require
addiƟonal veƫng and piloƟng to beƩer understand
technical feasibility, impacts, and broader County
implementaƟon prioriƟes prior to approval for
implementaƟon. To this end, planned projects include
technical feasibility studies and pilot projects. As a
result, this capital and non‐capital funding plan is
subject to change as it is re‐evaluated. AddiƟonally,
the Plan sets a framework based on current condiƟons
but also allows for flexibility in the phasing of projects
based on funding opportuniƟes and community
prioriƟes idenƟfied in annual work plans and capital
improvement project lists.
Table 5‐4‐1 summarizes projected revenues for the
30‐year plan period for various funds operaƟng in the
CRA area (including MSTUs). Note that following the
successful sale of the Mini Triangle property
anƟcipated in the first five years, it is expected that
the CRA will have addiƟonal funds of $350,000
available that are currently being held in reserve due
to loan requirements.
Figures 5‐4‐4 through 5‐4‐6 summarize capital and
non‐capital project costs for different increments of
the 30‐year plan period, followed by Tables 5‐4‐2
through 5‐4‐4 which provide a detailed list of projects
and iniƟaƟves. Table 5‐4‐5 compares projected
revenues to esƟmated costs to show deficits and
surpluses. Note that the capital planning includes a
built‐in deficit to indicate where other agencies would
likely help fund projects or other revenue sources
might be sought. Regarding maintenance costs,
maintenance of standard capital improvements is
anƟcipated to be provided and funded by relevant
County agencies, while maintenance for capital
improvements above and beyond County standards
are anƟcipated to be funded by the CRA.
Short Term (1-5 years)
Capital Projects
Linwood Ave Complete Street Phase I – major
Complete Street improvement between
Commercial Dr and Wild Pines Ln including on‐
street parking, lighƟng, sidewalk widening, and
any addiƟonal needed infrastructure
improvements
Thomasson Dr and Hamilton Ave Improvements –
Bayshore BeauƟficaƟon MSTU anƟcipated to fund
project, but any shorƞall could trigger partnership
with CRA funding porƟon
Republic Dr Complete Streets Improvements –
neighborhood‐level Complete Streets
improvements between Bayshore Dr and East
Naples Community Park, including lighƟng,
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐6
5.4
possible sidewalk expansion, any necessary
drainage improvements, and an improved
pedestrian bridge connecƟon to East Naples
Community Park
Danford St Complete Streets Improvements –
neighborhood‐level Complete Streets
improvements between the end of the roadway
and Hamilton Ave
General Parks Improvements in Bayshore Area—
general item to address connecƟons to parks and
ameniƟes, including any associated with the 17‐
Acre Site and Sugden Regional Park
Community Safety/Clean‐Up and Neighborhood
IniƟaƟves General Improvements—general item to
address capital improvements from Community
Safety & Clean‐Up Strategy and Neighborhood
Focus IniƟaƟves; may include projects idenƟfied
based on neighborhood interest to coordinate with
the Sheriff’s Department and Code Enforcement to
educate and provide small capital improvements
Land AcquisiƟon for a Community Land Trust—may
support maintenance of current affordable housing
availability in the CRA area while improving
baseline quality condiƟons; may also support
housing for arƟsts
Bay St Complete Street Improvements –
neighborhood‐level Complete Streets
improvements between Hamilton Ave and the end
of the roadway
Surface Parking Lot in Bayshore Area – to increase
available commercial parking
General Road Engineering Improvements on Pine
Tree Dr and Andrews Dr – to bring these roadways
up to minimum County standards
Jeepers Dr Complete Street Improvements –
neighborhood Complete Streets improvements
between Bayshore Dr and Sugden Regional Park,
including walk lane striping, upgraded bioswales,
lighƟng, and a pedestrian connecƟon to Sugden
Regional Park
Gateway IntersecƟon Design Improvements at US
41/Shadowlawn Dr/Bayshore Dr – sign
improvements in the right‐of‐way and median
areas with an opportunity to showcase public art
Street Sign/Wayfinding Improvements in CRA area
– signs to address branding and bicycle/pedestrian
movement
Sidewalk/Bicycle Infrastructure Program – program
to address gaps in the pedestrian and bicycle
infrastructure networks that are not addressed
through Complete Streets improvements
Other General MulƟ‐Modal Improvements—for
addiƟonal mulƟ‐modal ameniƟes (e.g., bus
shelters)
Stormwater Infrastructure Upgrades/
Improvements
Sanitary Sewer Line Upgrades in Triangle Area – to
increase capacity
Water Line and Fire Suppression Upgrades—to
address infrastructure age and flow requirements
Non-Capital Expenditures
Ongoing OperaƟng Expenses for CRA, including
staff and administraƟon costs
Process Improvements – updated bylaws for CRA
Advisory Board
Land Development Code Updates‐ based on
recommendaƟons from CRA Plan Update
Mini Triangle Development – funding for incenƟves
and other needed support for the development of
the Mini Triangle
17‐Are Development—funding for incenƟves and
other needed support for the development of the
17‐Acre Site.
Gateway Property Development – funding for
potenƟal incenƟve in support of the project at the
apex of Davis Boulevard and Us 41.
Stormwater Master Plan Update – idenƟfy primary,
secondary, and terƟary improvements needed in
the CRA area with a prioriƟzaƟon plan
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐7
5.4
Arts and Culture Plan for CRA Area
Complete Streets ImplementaƟon Plan
Bayview Parking Study – concepts and outreach in
coordinaƟon with Parks & RecreaƟon Division
Community Safety & Cleanup Strategy – strategy to
address code enforcement issues and community
safety
Branding Strategy
MarkeƟng and CommunicaƟon Strategy –
strategies to communicate outcomes from the
branding effort and connect with the various
communiƟes in the CRA area (including hard‐to‐
reach groups) with updated tools including the
website, e‐blast templates, markeƟng materials,
etc.
Market Study/Economic Profile
Bayshore Dr Pilot project – for Complete Street
implementaƟon
Water & Fire Update Strategy – documentaƟon of
what mains and hydrants will be updated and
phasing
Triangle RetenƟon Pond Feasibility Study – finalized
design and engineering for passive park
improvements
Other Non‐Capital OperaƟons and Study
Expenditures—may include a study to expand the
CRA boundary, non‐capital costs associated with
Community Safety & Clean‐Up Plan, non‐capital
costs from Neighborhood Focus IniƟaƟves, or other
expenditures that may arise in the future and are
not yet idenƟfied.
Grants and Programs
ResidenƟal Grant/Loan Programs – for
structural improvements to single‐family
homes
Commercial Façade Program – for areas
that are not a major focus for commercial
redevelopment but that can be enhanced
with exterior façade and structural
improvements
Wall & Fence Funding – for transiƟonal
structures between incompaƟble uses
Public Art Funding –for public art pieces and events
Economic Development IncenƟves Program – for
economic development incenƟves related to
SecƟon 5.3.4 of the Redevelopment Area Plan
Bayshore Bicycle/Pedestrian Feasibility Study
Mobile Home Replacement Fund ‐ for transiƟon of
mobile homes to modular homes or other
appropriate structures
Community Land Trust Housing ConstrucƟon
Other Affordable/Workforce Housing Investments
Mid Term (6-15 years)
Capital Projects
Triangle RetenƟon Pond Improvements ‐
implementaƟon of passive park improvements at
the pond site with any necessary drainage and
connecƟvity improvements
Land AcquisiƟon for Two Pocket Parks (small
neighborhood parks)
Community Safety/Clean‐Up and Neighborhood
IniƟaƟves General Improvements
Land AcquisiƟon for a Community Land Trust
Surface Parking Lot in the Mini Triangle area to
support commercial uses
Development of MulƟ‐Purpose Facility/Structure—
may occur on currently CRA‐owned 17‐Acre Site;
potenƟal uses of the facility/structure may include
a CRA office and/or arts/incubator space
Bicycle and Pedestrian Trail ‐ along Sugden
Regional Park Drainage Ditch to provide north/
south connecƟvity
Commercial Parking Garage on Bayshore Dr ‐
possibly on surface lot included in short‐term
capital projects for commercial parking
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐8
5.4
Bayshore Dr Complete Street – major Complete
Street improvement between US 41 and
Thomasson Dr, including possible lane reducƟon,
on‐street parking, and any addiƟonal needed
infrastructure improvements
Kirkwood Ave Complete Street—Complete Street
improvement potenƟally similar to Linwood Ave
Phase I with potenƟal Shadowlawn Dr connecƟon
Commercial Dr Complete Street—Complete Street
improvement potenƟally similar to Linwood Ave
Phase I
Linwood Ave Complete Street Phase II—
neighborhood Complete Street improvements
between Wild Pines Ln and Airport‐Pulling Rd
Shadowlawn Dr Complete Street – major roadway
Complete Street improvement between Davis Blvd
and US 41, including lighƟng and any addiƟonal
needed infrastructure improvements
Gateway IntersecƟon Design Improvements –
signage and potenƟal public art opportuniƟes for:
Davis Blvd/Airport‐Pulling Rd
Davis Blvd/Shadowlawn Dr
Davis Blvd/US 41
Thomasson Dr/Dominion Dr
US 41/Osceola Ave
General Road Engineering Improvements – to bring
the following roads up to minimum County
standards:
Woodside Ave
Holly Ave
Sidewalk/Bicycle Infrastructure Program
Other General MulƟ‐Modal Improvements
Water Line and Fire Suppression Upgrades—to
address age and flow requirements
Stormwater Infrastructure Upgrades/
Improvements
Undergrounding UƟliƟes along Bayshore Dr—
between US 41 and Thomasson Dr , coordinated
with the Complete Streets project and Bayshore
BeauƟficaƟon MSTU
Non-Capital Expenditures
Ongoing OperaƟng Expenses for CRA
Land Development Code Updates
Bayshore Dr Technical Feasibility Study – for
Complete Street implementaƟon
Microenterprise and Arts Incubator Study—for
concepts and implementaƟon, which could include
an arts focus and/or arts space
Other Non‐Capital OperaƟons and Study
Expenditures—other expenditures that may arise
in the future and are not yet idenƟfied
Grants and Programs
ResidenƟal Grant/Loan Programs – for
structural improvements to single‐family
homes
Commercial Façade Program – for areas
that are not a major focus for commercial
redevelopment but that can be enhanced
with exterior façade and structural
improvements
Wall & Fence Funding – for transiƟonal
structures between incompaƟble uses
Public Art Funding –for public art pieces
and events
Economic Development IncenƟves
Program –for economic development
incenƟves related to SecƟon 5.3.4 of the
Redevelopment Area Plan
Mobile Home Replacement Fund ‐ for
transiƟon of mobile homes to modular
homes or other appropriate structures
Community Land Trust Housing
ConstrucƟon
Other Affordable/Workforce Housing
Investments
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐9
5.4
Long Term (16-30 years)
Capital Projects
Bayshore Dr Complete Street Improvement
between Thomasson Dr and Holly Ave –
neighborhood‐level Complete Street, including any
drainage improvements and connecƟons to
potenƟal Naples Bay Greenway Sun Trail
improvements
Commercial Parking Garage in Mini Triangle Area
possibly on Surface Lot included in Mid‐Term
Capital Projects– to address commercial parking
needs
Pine Street ConnecƟon—between Davis Blvd and
Linwood Ave
Sidewalk/Bicycle Infrastructure Program
Other General MulƟ‐Modal Improvements
Land AcquisiƟon and Development of 4 Pocket
Parks (small neighborhood parks)
Community Safety/Clean‐Up and Neighborhood
IniƟaƟves General Improvements
Water Line and Fire Suppression Upgrades—to
address infrastructure age and flow requirements
Stormwater Infrastructure Upgrades/
Improvements
Underground/Relocate Overhead UƟlity Lines—
Linwood Ave and Commercial Dr
General Road Engineering Improvements – to bring
the following roads up to minimum County
standards:
PalmeƩo Ct
Undergrounding UƟliƟes along Bayshore Dr—
between Thomasson Dr and Holly Ave, coordinated
with Complete Streets project and Bayshore
BeauƟficaƟon MSTU
Non-Capital Expenditures
Ongoing OperaƟng Expenses for CRA
Land Development Code Updates
Other Non‐Capital OperaƟons and Study
Expenditures—other expenditures that may arise
in the future and are not yet idenƟfied
Grants and Programs
ResidenƟal Grant/Loan Programs – for structural
improvements to single‐family homes
Commercial Façade Program – for areas that are
not a major focus for commercial redevelopment
but that can be enhanced with exterior façade and
structural improvements
Wall & Fence Funding – for transiƟonal structures
between incompaƟble uses
Public Art Funding –for public art pieces and events
Economic Development IncenƟves Program –for
economic development incenƟves related to
SecƟon 5.3.4 of the Redevelopment Area Plan
Other Affordable/Workforce Housing Investments
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐10
5.4
Figure 5‐4‐4: Short‐term costs by project type
Total Short‐Term Costs
(1‐5 Years):
$25.0 million
Figure 5‐4‐5: Mid‐term project costs by type
Total Mid‐Term Costs
(6‐15 Years):
$57.9 million
Figure 5‐4‐6: Long‐term costs by project type
Total Long‐Term Costs
(16‐30 Years):
$74.5 million
Short Term Total Mid Term Total Long Term Total
(1‐5 Yrs)(6‐15 Yrs)(16‐30 Yrs)
Tax Increment Financing (TIF)$10,831,197 $39,256,457 $104,330,124 $154,417,778
Bayshore Beautification MSTU $7,403,290 $20,956,845 $48,857,829 $77,217,964
Haldeman Creek MSTU $644,865 $1,831,442 $4,277,648 $6,753,955
TotalFund Revenue
Table 5‐4‐1: Summary of Projected Revenue Estimates
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐11
5.4
Land Use & Urban Design Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Gateway Intersection Design Improvements
Gateway Sign ‐ Davis Blvd/Airport Pulling Rd $17,250 $17,250
Gateway Sign ‐ Davis Blvd/ Shadowlawn Dr $17,250 $17,250
Gateway Sign ‐ Davis Blvd/US 41 $17,250 $17,250
Street Sign/Wayfinding Improvements
Wayfinding Sign Improvements $52,500 $52,500
$104,250 $52,500 $51,750 $0
Public Space, Parks, & Open Space Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Park Improvements
Triangle Retention Pond Improvements $752,605 $752,605
Land Acquisition for Pocket Parks (2 parks)$918,750 $431,250 $487,500
Development of Pocket Parks (2 parks)$169,705 $169,705
Public Space Improvements
Community Safety/Clean‐Up and Neighborhood
Initiatives General Improvements $75,000 $25,000 $25,000 $25,000
$2,916,060 $25,000 $1,208,855 $682,205
Transportation, Connectivity, & Walkability Projects Total Short Term (1‐5 Years)Mid‐Term (6‐15 Years)1 Long Term (16‐30 Years)2
Complete Streets ‐ Major
Linwood Ave. (Phase I)$1,925,186 $1,925,186
Shadowlawn Drive ‐ Installation of Streetlights $379,500 $379,500
Commercial Drive $1,750,961 $1,750,961
Kirkwood Ave./Kirkwood Ave Connection $2,003,588 $2,003,588
Pine Street Connection $2,299,326 $2,299,326
Complete Streets & Trails ‐ Neighborhood
Linwood Ave. (Phase II)$2,046,448 $2,046,448
Parking
Surface Parking Lot ‐ Land Acquisition $862,500 $862,500
Surface Parking Lot – Mini Triangle Area ‐ excludes land
acquisition cost $351,290 $351,290
Commercial Parking Garage (possibly on surface lot) –
Triangle ‐ excludes land acquisition cost $12,374,050 $12,374,050
General Mutli‐Modal Improvements
General Sidewalk/Bicycle Infrastructure Improvements $2,747,555 $430,622 $932,931 $1,384,002
Other General Multi‐Modal Improvements $862,500 $250,000 $287,500 $325,000
$27,602,904 $2,605,808 $8,614,718 $16,382,379
North of US 41 (Triangle)
Sub‐Total
Sub‐Total
Sub‐Total
Table 5‐4‐2: Capital Improvements Project Matrix—North of US 41 (Triangle)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐12
5.4
Infrastructure Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Other Infrastructure Improvements
Upgrade Sanitary Sewer Lines $1,000,000 $1,000,000
Stormwater Infrastructure Upgrades/Improvements $5,825,000 $250,000 $575,000 $5,000,000
Underground Utility Lines ‐ Linwood Avenue $931,913 $931,913
Underground Utility Lines ‐ Commercial Drive $247,443 $247,443
Water Line and Fire Suppression Upgrades $4,038,023 $482,801 $555,222 $3,000,000
$12,042,379 $1,732,801 $1,130,222 $9,179,356
Total North $43,665,594 $4,916,110 $11,505,545 $26,243,939
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Sub‐Total
Table 5‐4‐2 (continued): Capital Improvements Project Matrix—North of US 41 (Triangle)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐13
5.4
Table 5‐4‐3: Capital Improvements South of US 41 (Bayshore)
Land Use & Urban Design Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Gateway Intersection Design Improvements
Gateway Sign Improvements at US 41 and Bayshore3 $15,000 $15,000
Gateway ‐ Thomasson Dr/Dominion Dr3 $17,250 $17,250
Gateway US 41/Osceola3 $17,250 $17,250
Street Sign/Wayfinding Improvements
Wayfinding Sign Improvements3 $52,500 $52,500
$102,000 $67,500 $34,500 $0
Public Space, Parks, & Open Space Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Park Improvements
Land Acquisition for Pocket Parks (2 parks)$975,000 $975,000
Development of Pocket Parks (2 parks)$169,705 $169,705
General Parks Development/Improvements $1,000,000 $1,000,000
Public Space Improvements
Community Safety/Clean‐Up and Neighborhood
Initiatives General Improvements $75,000 $25,000 $25,000 $25,000
$2,219,705 $1,025,000 $25,000 $1,169,705
Development Projects Total Short Term (1‐5 Years)Mid‐Term (6‐15 Years)1 Long Term (16‐30 Years)2
Land Acquisition for Community Land Trust $1,000,000 $500,000 $500,000
Development of Multi‐Purpose Facility/Structure $2,250,000 $2,250,000
$3,250,000 $500,000 $2,750,000 $0
South of US 41 (Bayshore)
Sub‐Total
Sub‐Total
Sub‐Total
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐14
5.4
Transportation, Connectivity, & Walkability Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Complete Streets ‐ Major
Bayshore Drive Complete Street – between US 41 and
Thomasson3 $2,875,000 $2,875,000
Thomason Drive and Hamilton Improvements3 $500,000 $500,000
Complete Streets & Trails ‐ Neighborhood
Bicycle and pedestrian trail along Sugden drainage ditch3 $394,073 $394,073
Jeepers Drive Complete Street Improvements3 $491,849 $491,849
Republic Drive Complete Streets improvements3 $506,849 $506,849
Danford Street Complete Streets3 $689,329 $689,329
Bay Street Complete Street Improvements3 $491,849 $491,849
Bayshore Drive Complete Street ‐ Thomasson Dr/Holly
Ave3 $2,600,000 $2,600,000
Parking
Surface Parking Lot at Bayshore and Coco $351,290 $351,290
Commercial Parking Garage (possibly on surface lot) –
Bayshore Drive $11,377,525 $11,377,525
General Road Engineering Standard Improvements
General Road Engineering Improvements – Pine Tree
Drive3 $346,649 $346,649
General Road Engineering Improvements ‐ Andrews
Drive3 $346,649 $346,649
General Road Engineering Improvements ‐ Woodside
Avenue3 $398,647 $398,647
General Road Engineering Improvements ‐ Holly Avenue3 $398,647 $398,647
General Road Engineering Improvements ‐ Palmetto
Court3 $221,905 $221,905
General Multi‐Modal Improvements
General Sidewalk/Bicycle Infrastructure Improvements3 $2,747,555 $430,622 $932,931 $1,384,002
Other General Multi‐Modal Improvements3 $862,500 $250,000 $287,500 $325,000
$25,600,317 $4,405,088 $16,664,322 $4,530,908Sub‐Total
Table 5‐4‐3 (continued): Capital Improvements South of US 41 (Bayshore)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐15
5.4
Infrastructure Projects Total Short Term (1‐5 Years)Mid‐Term
(6‐15 Years)1 Long Term (16‐30 Years)2
Other Infrastructure Improvements
Stormwater Infrastructure Upgrades/Improvements3 $5,150,000 $250,000 $2,300,000 $2,600,000
Water Line and Fire Suppression Upgrades $6,317,221 $1,542,894 $1,774,328 $3,000,000
Underground Utility Lines ‐ Bayshore Drive3 $2,220,000 $1,430,000 $790,000
$13,687,221 $1,792,894 $5,504,328 $6,390,000
$44,859,243 $7,790,481 $24,978,149 $12,090,612
$88,524,836 $12,706,591 $36,483,694 $38,334,552
$69,915,363 $12,315,280 $21,449,912 $36,150,171
$158,440,199 $25,021,871 $57,933,606 $74,484,723
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
3 Potentially MSTU‐eligible project; requires coordination and approval of Bayshore Beautification MSTU Advisory Board.
Sub‐Total
Total South
Overall Capital Costs Total
Non‐Capital Costs Total
Total Costs
Table 5‐4‐3 (conƟnued): Capital Improvements South of US 41 (Bayshore)
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐16
5.4
Project Total Short Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Process Improvements – updated bylaws for CRA Advisory Board $25,000 $25,000
Staff and Operating (salaries, benefits, rent, etc.)$53,625,363 $7,110,280 $14,714,912 $31,800,171
Land Development Code Updates‐ based on recommendations from CRA Plan Update $100,000 $25,000 $25,000 $50,000
Mini Triangle Development Support $500,000 $500,000
17‐Acre Development Support $500,000 $500,000
Gateway Property Support $100,000 $100,000
Stormwater Master Plan Update $200,000 $200,000
Arts and Culture Plan for CRA $75,000 $75,000
Complete Streets Implementation Plan $50,000 $50,000
Bayview Parking Study – concepts and outreach in coordination with Parks & Recreation
Division $25,000 $25,000
Community Safety & Cleanup Strategy to address code enforcement issues and community
safety. $15,000 $15,000
Marketing, Branding and communication strategy – website update, e‐blast templates,
marketing materials, etc. $50,000 $50,000
Market Study/Economic Profile $50,000 $50,000
Bayshore Drive Technical Feasibility Study $40,000 $40,000
Bayshore Drive Pilot project $15,000 $15,000
Water & Fire Update Strategy – document what mains and hydrants will be updated and
phasing $50,000 $50,000
Triangle Retention Pond Feasibility Study $25,000 $25,000
Microenterprise and arts incubator Study for concepts and implementation $20,000 $20,000
Other non‐capital operations and study expenditures $750,000 $250,000 $250,000 $250,000
Project Total Short Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Residential Grant/Loan Programs – for structural improvements to single‐family homes $750,000 $125,000 $250,000 $375,000
Commercial Façade Program $1,500,000 $250,000 $500,000 $750,000
Wall & Fence Funding – for funding transitional structures between incompatible uses $750,000 $125,000 $250,000 $375,000
Public Art – funding for public art pieces and events $450,000 $75,000 $150,000 $225,000
Economic Development – funding for economic development incentives listed in
Development Section $750,000 $125,000 $250,000 $375,000
Mobile Home Replacement Fund $1,500,000 $500,000 $1,000,000
Community Land Trust Housing Construction $4,800,000 $1,800,000 $3,000,000
Other Affordable/Workforce Housing Investments $3,200,000 $250,000 $1,000,000 $1,950,000
Totals $69,915,363 $12,315,280 $21,449,912 $36,150,171
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Non‐Capital Expenditures (Studies, Plans, Other)
Grants and Programs
Operations and Studies
Table 5‐4‐4: Non Capital Expenditures
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐17
5.4
5.4.4 Coordination & Partnerships
Many of the items listed in the SecƟon 5.3 framework and capital and non‐capital projects listed in this secƟon
require the CRA to seek approval from and coordinate with other agencies and enƟƟes, which may include
planning and process approval and/or coordinaƟon and idenƟfying opportuniƟes for shared funding.
CoordinaƟon also includes instances in which another agency or enƟty oversees a project or iniƟaƟve directly
with the CRA assisƟng.
As menƟoned in SecƟon 5.4.3, the framework and projects idenƟfied in this plan are suggesƟons to be further
veƩed prior to approval for implementaƟon. This includes review and approval from relevant County staff and
elected officials. Planning and implementaƟon may also include broader coordinaƟon with agencies. Examples
include coordinaƟon with the Collier MPO to share local needs that might inform a state roadway improvement,
as well as coordinaƟng with other Collier County agencies on topics such as Land Development Code changes,
park access, community safety, transit and transportaƟon, and stormwater. The CRA also has opportuniƟes to
coordinate with the City of Naples on transportaƟon planning and water main upgrades. This type of
coordinaƟon might involve design review for projects led by the CRA and seƫng up meeƟngs coinciding with
regular planning and project cycles prior to finalized design phases. Key planning cycles for coordinaƟon include
the TransportaƟon Improvement Program planning by the MPO and capital improvement planning for Collier
County. When working with agencies to idenƟfy shared funding opportuniƟes as a part of these planning and
implementaƟon processes, it is important to recognize exisƟng funding commitments, as well as limitaƟons on
the use of funds. For example, road impact fees in Collier County must be used for capacity expansion, such as
adding a new road or new lanes to an exisƟng road.
Aside from government agencies, the CRA may also have opportuniƟes to partner with local enƟƟes such as
private firms and non‐profits to realize some of its strategies and projects, as well as seek private sponsorships
Examples include potenƟally partnering with the Naples Accelerator , St. MaƩhew’s House, and/or the United
Arts Council on a business/art incubator idea. There may also be opportuniƟes to partner with companies such
as Slidr for alternaƟve vehicle transportaƟon in the area. CoordinaƟon and funding opportuniƟes may also be
idenƟfied as part of private development projects.
TIF Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ North of US 41 (Triangle)$42,665,594 $4,916,110 $11,505,545 $26,243,939
Total Capital Costs ‐ South of US 41 (Bayshore)$44,859,243 $7,790,481 $24,978,149 $12,090,612
Total Capital Costs $87,524,836 $12,706,591 $36,483,694 $38,334,552
Total Non‐Capital Costs $69,915,363 $12,315,280 $21,449,912 $36,150,171
Total TIF Revenue $154,417,778 $10,831,197 $39,256,457 $104,330,124
Difference ‐$3,022,421 ‐$14,190,674 ‐$18,677,149 $29,845,401
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Table 5‐4‐5: Summary of CRA Project Costs and Projected TIF Revenues
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐18
5.4
Lastly, as menƟoned at the beginning of this secƟon, the CRA should look for opportuniƟes to
coordinate with the MSTUs operaƟng in the area to implement capital improvements. Table 5‐4‐6
shows the costs for projects in the CRA prioriƟzaƟon plan that may qualify for Bayshore BeauƟficaƟon
MSTU funds and compares them to the projected revenues for the MSTU. The comparison shows that
the money available would cover these project costs with a sizable amount of funds remaining for other
MSTU projects. Note that the MSTU Advisory Board would need to approve any process or funding
coordinaƟon.
MSTU Funding Summary Total Overall Short‐Term
(1‐5 Years)
Mid‐Term
(6‐15 Years)1
Long Term
(16‐30 Years)2
Total Capital Costs ‐ MSTU‐Eligible Projects $13,973,502 $4,121,297 $5,321,297 $4,530,908
Total Right‐of‐Way MSTU Revenue $77,217,964 $7,403,290 $20,956,845 $48,857,829
Difference $63,244,462 $3,281,993 $15,635,548 $44,326,921
1 Overall period costs increased by 15% to account for annual increases
2 Overall period costs increased by 30% to account for annual increases
Note: Projects are considered MSTU‐eligible based on those that align with accepted uses of Bayshore Beautification MSTU funds according to Ordinance No. 2013‐68
Table 5‐4‐6: Summary of MSTU‐Eligible Costs and Projected MSTU Revenues
PRIORITIZATION PLAN
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐4‐19
5.4
This page is intenƟonally leŌ blank.
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐1
5.5
5.5.1 Overview of Relevant
Statutes
Community redevelopment areas are created on the
basis of a finding of blight or slum condiƟons, as noted
in SecƟon 163.355 of Florida Statute. Table 5‐2‐1
provided detailed blight condiƟons for the Bayshore
Gateway Triangle CRA area, summarizing informaƟon
from the 2000 Plan. Table 5‐5‐1 shows how the
framework in this Redevelopment Area Plan addresses
the main blight factors idenƟfied. Related capital and
non‐capital projects can also be found in SecƟon 5.4.
In addiƟon, secƟons 163.360 and 163.362 of Florida
Statutes contain specific requirements for community
redevelopment plans. Tables 5‐5‐2 and 5‐5‐3 provide
an overview of the requirements from these statutes
and the locaƟon in this Redevelopment Area Plan
where the relevant informaƟon can be found to saƟsfy
these requirements.
5.5.2 Consistency with the
County’s Comprehensive Plan
This Redevelopment Area Plan sets forth a vision for
the CRA area centered on fostering more urban‐style
development, including mulƟ‐modal corridors, mixed
use projects, and building out to allowable densiƟes.
The Collier County Growth Management Plan largely
supports this vision with the Bayshore Gateway
Triangle Redevelopment Overlay provisions and the
AcƟvity Center designaƟon. The Mixed Use overlays
provided in the Land Development Code further
support these efforts. Development and
redevelopment are thus largely intended to be
completed within the provisions of the Growth
Management Plan as they exist now or indicate where
future amendments may be needed in order to carry
out implementaƟon of acƟon items.
5.5.3 Acquisition, Demolition/
Clearance, & Improvement
In the future, the Redevelopment Agency may choose
to pursue a program of property acquisiƟon and/or
consolidaƟon to realize the redevelopment objecƟves.
These objecƟves might relate to facilitaƟng private
development and providing idenƟfied needed public
uses. If a property is designated for acquisiƟon, the
process must comply with County requirements and/
or State statutes.
The Redevelopment Agency is authorized to demolish,
clear, or move buildings, structures, and other
improvements from any real property acquired in the
redevelopment project area, subject to obtaining
necessary permits.
The CRA may also engage in or assist in site
preparaƟon improvements on properƟes it already
owns or properƟes it acquires in the future to
facilitate development. Other improvements include
general infrastructure and streetscape improvements
that indirectly support development. See SecƟon 5.4.3
for those improvements that are planned for the CRA
to fund. All of these improvements are subject to
obtaining necessary permits.
SecƟon 1.5 further outlines the Agency’s authoriƟes
that governs this area.
5.5.4 Zoning & Comprehensive
Plan Changes
No Growth Management Plan or Land Development
Code changes were brought through an approval
process as part of this planning effort, and no Land
Development Code or Comprehensive Plan changes
are being adopted with the adopƟon of this
Redevelopment Area Plan. However, recommended
changes will be brought for iniƟal consistency review
by Collier County staff and the Collier County Planning
Commission following adopƟon of this plan.
5.5.5 Land Use, Densities, &
Building Requirements
As noted in SecƟon 5.5.4, no Land Development Code
or Comprehensive Plan changes are being adopted
with the adopƟon of this Redevelopment Area Plan.
Consequently, the Redevelopment Area Plan will
follow the land uses, densiƟes, and building
requirements provided in the Growth Management
Plan and the Land Development Code for the Ɵme
being. However, recommended changes will be
brought forth for iniƟal consistency review by Collier
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐2
5.5
Main Issue Relevant Plan SecƟon(s)
Predominance of
defecƟve or inadequate
street layout
SecƟon 5.3.5 addresses street design primarily with Complete Streets iniƟaƟves;
there are addiƟonal improvements for addressing bicycle and pedestrian gaps,
commercial parking need, and addiƟonal bicycle and pedestrian connecƟons.
Faulty lot layout in
relaƟon to size,
adequacy, accessibility,
or usefulness
SecƟon 5.3.4 focuses on specifically on facilitaƟng private development. As part of
these efforts, the CRA can acquire property to merge lots and make them more
easily developed. AddiƟonally, SecƟon 5.3.2 lays out examples of mulƟ‐family
residenƟal that provide examples to achieve higher residenƟal densiƟes where
approved densiƟes are not realized.
Unsanitary or unsafe
condiƟons
SecƟons 5.3.3 and 5.3.4 contain strategies to address structural upgrades and public
realm clean‐up and improvements. SecƟons 5.3.2 and 5.3.4 also address residenƟal
types and approaches to affordability that can address overcrowding. SecƟon 5.3.5
highlights lighƟng and other transportaƟon safety improvements, parƟcularly for
cyclists and pedestrians.
DeterioraƟon of site or
other improvements
(drainage and surface
water management)
SecƟon 5.3.6 focuses on infrastructure improvements, including those for
stormwater.
Other problems: Lack of
right‐of‐way for
Shadowlawn Drive
improvements
SecƟon 5.3.5 includes improvements for Shadowlawn Drive.
Other problems: Lack of
public transportaƟon SecƟon 5.3.5 includes a coordinaƟon strategy for public transit in the CRA area.
Other problems: housing
affordability SecƟon 5.3.4 includes example strategies to address housing affordability issues.
Table 5‐5‐1: SecƟons of Redevelopment Area Plan that address blight condiƟons
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐3
5.5
SecƟon 163.360, F.S. Requirements Relevant Redevelopment Area
Plan SecƟon
Conformity to the Growth Management Plan SecƟon 5.5.2
Zoning and planning changes SecƟon 5.5.4
Land uses, maximum densiƟes, and building requirements
SecƟon 5.3.1, Maps 5‐3‐5 and 5‐
3‐6, SecƟon 5.5.5; for general
consideraƟons to guide these
requirements, see SecƟon 5.3.2
Land acquisiƟon, demoliƟon, clearance and site preparaƟon,
redevelopment, improvements, and rehabilitaƟon proposed to carry out
the Redevelopment Area Plan
SecƟons 5.4.3 and 5.5.3
Affordable housing provision SecƟon 5.3.4‐ ObjecƟve 5
Table 5‐5‐2: SecƟon 163.360, F.S. Requirements for Redevelopment Area Plan
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐4
5.5
SecƟon 163.362, F.S. Requirements Relevant Redevelopment Area
Plan SecƟon
Legal descripƟon of CRA area boundaries and reason behind establishing
such boundaries
ResoluƟon 2000‐82, Exhibit A at
end of this document and
ResoluƟon 2000‐83
Approximate amount of open space to be provided shown by diagram and
in general terms
SecƟon 5.3.3‐Table 5‐3‐1 and
Map 5‐3‐8
Property intended for parks and recreaƟon space shown by diagram and in
general terms SecƟon 5.3.3‐Map 5‐3‐8
Street layout and property intended for streets shown by diagram and in
general terms SecƟon 5.3.5‐Map 5‐3‐14
LimitaƟons on the type, size, height, number, and proposed use of
buildings shown by diagram and in general terms
SecƟon 5.3.1, Maps 5‐3‐5 and 5‐
3‐6, SecƟon 5.5.5; for general
consideraƟons to guide these
requirements, see SecƟon 5.3.2
The approximate number of dwelling units shown by diagram and in
general terms SecƟon 5.3.2‐Map 5‐3‐2
Replacement housing and relocaƟon SecƟon 5.3.4, SecƟon 6
Property intended for public uƟliƟes shown by diagram and in general
terms
SecƟon 5.3.6‐Maps 5‐3‐15 and 5
‐3‐16
Property for public improvements of any nature shown by diagram and in
general terms
SecƟon 5.3.1‐Map 5‐3‐1 ,
SecƟon 5.4.2; addiƟonal details
in SecƟon 5.3.2‐Map 5‐3‐7,
SecƟon 5.3.3‐Map 5‐3‐8, SecƟon
5.3.4‐Map 5‐3‐10, SecƟon 5.3.5‐
Maps 5‐3‐12 and 5‐3‐14, SecƟon
5.3.6‐Maps 5‐3‐15 and 5‐3‐16
Neighborhood impact element describing impacts on residents of CRA area
and surrounding areas in terms of relocaƟon, traffic circulaƟon,
environmental quality, availability of community faciliƟes and services,
effect on school populaƟon, and other maƩers affecƟng the physical and
social quality of the neighborhood
SecƟon 5.5.6
Publicly funded capital improvements to be undertaken in the CRA area SecƟon 5.4.2
Safeguards, controls, restricƟons/covenants SecƟon 5.5.7
Replacement housing for relocaƟon of displaced persons from housing
faciliƟes SecƟon 6
ResidenƟal use element SecƟon 5.3.2, SecƟon 5.3.4‐
ObjecƟve 5
Projected costs of redevelopment SecƟon 5.4.3
Redevelopment Area Plan duraƟon and Ɵme certain for redevelopment
financed by increment revenues SecƟon 1.6
Table 5‐5‐3: SecƟon163.362, F.S. Requirements for Redevelopment Area Plan
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐5
5.5
County staff and the Collier County Planning
Commission.
5.5.6 Neighborhood Impact
The Redevelopment Area Plan focuses on improving
structural quality of buildings, compaƟbility of uses,
and urban design, as well as promoƟng more urban‐
style development and mulƟ‐modal transportaƟon. As
of right now, there is housing available at lower income
levels, yet this may be due to lower structural quality
based on findings from the background analysis for the
Redevelopment Area Plan. As improvements are made
in the area, there is a potenƟal risk of property values
rising to make housing substanƟally less affordable.
Consequently, protecƟve measures are being
considered to maintain the affordability of these units
while improving their quality (see SecƟon 5.3.4,
ObjecƟve 5). Temporary relocaƟon of residents in
lower quality units may be required to make building
improvements.
An addiƟonal consideraƟon for lower income
households with improvements to the CRA area is the
availability of community faciliƟes and services. These
uses may also risk displacement if property values
increase rapidly or dramaƟcally. This Redevelopment
Area Plan includes provisions to support community‐
oriented uses that include these faciliƟes and services
so that they can remain a part of the community (see
SecƟon 5.3.4, ObjecƟve 3, Strategy 2).
With more urban‐style development and mulƟ‐modal
improvements, traffic circulaƟon may change. There
may be increased congesƟon on roadways and at major
state road intersecƟons in making them safer for non‐
automobile modes and pursuing catalyst development
opportuniƟes. Any development would need to go
through the exisƟng Collier County process to assess
and miƟgate for Level of Service changes on roadways.
Ensuring low‐cost transportaƟon alternaƟves may also
support affordable mobility for lower income
households and community members.
Regarding impacts on other faciliƟes, such as schools,
any new development would need to go through the
exisƟng Collier County process to assess and miƟgate
for Level of Service changes.
Regarding environmental quality, water quality is a key
consideraƟon for stormwater management
improvements. Water quality impacts can be evaluated
through exisƟng Collier County processes. AddiƟonally,
this Redevelopment Area Plan encourages green
infrastructure techniques that may help provide certain
levels of localized water treatment and ground
infiltraƟon prior to arriving at major collector sites.
5.5.7 Safeguards, Controls,
Restrictions, & Assurances
Redevelopment acƟviƟes idenƟfied in this
Redevelopment Area Plan will not be iniƟated unƟl
they are found to be consistent with the Collier County
Growth Management Plan and applicable land
development regulaƟons. The Community
Redevelopment Agency, working collaboraƟvely with
County agencies, may propose amendments to the
Growth Management Plan and the Land Use
Development Code, including design criteria, building
heights, land coverage, setback requirements, special
excepƟons, traffic circulaƟon, traffic access, and other
development and design controls necessary for proper
development of public and private projects.
To leverage the increment revenues, Collier County
may consider non‐ad valorem assessments. For
example, during the Redevelopment Area Plan update
process, the County was working on a stormwater
uƟlity fee that, if adopted, would apply to the CRA area.
The imposiƟon of special assessments for capital
improvements and essenƟal services is covered by well
seƩled case law and specific statutory provisions
authorizing collecƟon of non‐ad valorem assessments
on the same bill as ad valorem taxes. Such provisions
require extraordinary noƟce to all affected property
owners.
Issues concerning restricƟons on any property acquired
for community redevelopment purposes and then
returned to use by the private sector will be addressed
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐6
5.5
on a case‐by‐case basis to ensure all acƟviƟes
necessary to perpetuate the redevelopment iniƟaƟve
are advanced in a manner consistent with this
Redevelopment Area Plan and any amendment to it.
Such restricƟons or controls would be expected in the
form of covenants on any land sold or leased for
private use as provided for in the Community
Redevelopment Act, SecƟon 163.380, F.S.
To assure that redevelopment will take place in
conformance with the projects, objecƟves and
strategies expressed in this Redevelopment Area Plan,
the Redevelopment Agency will uƟlize the regulatory
mechanisms used by the County to permit
development and redevelopment within its
jurisdicƟon. These mechanisms include but are not
limited to the Growth Management Plan; the Land
Development Code; adopted design guidelines;
performance standards; and County‐authorized
development review, permiƫng, and approval
processes and any other adopted codes, standards,
and policies.
GENERAL REQUIREMENTS
Bayshore Gateway Triangle CRA Area Plan—DraŌ March 2019 5‐5‐7
5.5
This page is intenƟonally leŌ blank.
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-1
5.6
5.6.1 Tax Increment Financing
The Redevelopment Area is dependent upon the use of
increment revenue financing for funding. Using this
method, the County froze all taxable values within the
Redevelopment Area at the 2000 rate to establish a base
collection amount. Millages are applied through the General
Fund (001) and the Unincorporated Area General Fund
(111). The future taxes collected (associated with tax base
and property value increases) are placed into a separate
account and designated for specific uses. The funds can be
dedicated to transportation or general improvements, or
placed in the general fund with the base ad valorem
revenues.
The analysis is based on the historical tax roll data obtained
from the Florida Department of Revenue (FDOR) and
population projections for Collier County obtained from the
Bureau of Economic and Business Research (BEBR). Specific
increases in the tax base are shown in terms of expected
development and its value. This expected development is
based exclusively on past patterns of activity adjusted for
anticipated community redevelopment activities within the
Redevelopment Area. These programmatic assumptions
offer a baseline for comparison with future potential
development.
For this analysis, the Bayshore CRA’s current millage rates
have been used, and were held constant over the planning
horizon.
As for the structure of the revenues which may accrue, only
the taxable value(s) net of the base year taxable value is
considered in calculating current or future increment
revenues.
The general procedures used to calculate available
revenues are shown in the following calculations:
• Assessed values, including new construction –
Exemptions or exclusions = Current taxable values.
• Current taxable values – Established base year taxable
values = Net valuations subject to applicable
jurisdictional millages.
• Net valuations × by applicable millages = increment
revenues. Pursuant to the Community Redevelopment
Act, Section 163.387, F.S., the maximum revenue
available to the Redevelopment Trust Fund will be 95
percent of the calculated increment revenues.
Note that the first five years of projected values are
obtained from Florida’s Office of Economic & Demographic
Research (EDR) Revenue Estimating Conference. The
conference produces detailed projections of the “County
Taxable Value” for each county in Florida. The values
projected by EDR were used for each CRA tax increment
scenario with the low, medium, high growth scenarios
starting in 2025. For projection purposes past 2025, three
different scenarios were developed that reflect different
future growth rates for taxable values in the
Redevelopment Area. Additional details for each scenario
are presented below and in Tables 5-6-1 through 5-6-3.
Scenario #1
Ad valorem revenues associated with the increment
revenue financing for the Redevelopment Area were
estimated using the projected growth of the taxable values
for residential and non-residential developments. The
average taxable values were indexed annually based on the
positive correlation between population growth and taxable
value increases discussed previously, along with the
historical growth trends of taxable values in the
Redevelopment Area, by land use. Based on these
projections, if the current millage is held constant (3.5645
mils for fund 001 and 0.8069 mils for fund 111), the ad
valorem taxes used for the Redevelopment Area fund are
estimated to generate approximately $154.4 million
between through 2048.
Additional growth scenarios are presented in this report
that reflects more aggressive growth rates in taxable values
and potential revenues. Although more aggressive than the
growth rates in Scenario #1, these scenarios still present
revenue projections that can reasonably be obtained. Since
1976, the taxable value for residential property in Collier
County has averaged a 10 percent annual increase, and
commercial property has averaged a 9 percent annual
increase. Within the CRA, taxable values (all property) have
averaged a 5 percent annual increase.
Scenario #2
Scenario #2 reflects increased growth rates that are
consistent with the historical growth rates in taxable values
for the entire CRA area. This scenario estimates slightly
higher taxable value growth than Scenario #1, with a
projected average annual taxable value growth rate of 5.2
percent (as opposed to Scenario #1 at 4.8 percent). As CRA
properties are redeveloped, it is reasonable to assume that
taxable values will increase at or above historical growth
rates. Using these higher annual growth rates, the Scenario
#2 increment revenue financing option would generate
approximately $165.4 million through 2048.
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-2
5.6
Scenario #3
Additionally, an optimistic growth rate scenario was
developed. Scenario #3 has increased growth rates that are
more than Scenarios #1 and #2, bringing the average
growth rate for all land uses more in line with the
recent growth rates of the entire county seen over the
last few years. This scenario projects the growth in
taxable values for all property to average
approximately 5.7 percent, annually. Using these rates,
the increment revenue financing option generated
approximately $183.7 million through 2048.
For each of the following scenarios, the following
apply:
• Projected total taxable value of all properties
within Redevelopment Area. Projected growth
rates by land use are consistent with historical
growth rates observed between 2000 and 2017
within Redevelopment Area. All figures rounded to
nearest thousand.
• Difference between total taxable value (Item 1) for
each year and base year (2000).
• For projection purposes, millage rates are assumed
to remain the same through 2048.
• Increment revenue by year (Item 2), divided by
1,000, multiplied by total millage rate, and reduced
by 5 percent for budgeting purposes.
5.6.2 Municipal Service Taxing
Units (MSTUs)
There are two MSTUs that overlap with the CRA area –
the Bayshore Beautification MSTU and the Haldeman
Creek MSTU. The Bayshore Beautification MSTU was
created to provide certain streetscape and right-of-way
improvements in the CRA area generally south of US
41. The Haldeman Creek MSTU was created for
maintenance dredging and navigational marker
maintenance. Projected revenues for these two MSTUs
are based on the same scenarios described for the TIF
calculations above (see Tables 5-6-4 through 5-6-6 for
Bayshore Beautification MSTU and 5-6-7 through 5-6-9
for Haldeman Creek MSTU). Note that revenues stem
directly from millages (as opposed to an increment
difference with a base year as in the case of the TIF
revenues).
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-3
5.6
Table 5-6-1: Scenario #1 Projected TIF Revenues
Notes:
1. Source: Scenario #1 projected taxable values for the Bayshore CRA. Average annual growth at 4.8%. Note that the first five years of projected values
are obtained from Florida’s Office of Economic & Demographic Research (EDR) Revenue Estimating Conference. http://edr.state.fl.us/Content/
conferences/advalorem/index.cfm
2. Taxable value for each year (Item 1) less the base year taxable value of $288,081,106
3. For each fund, the tax increment for the previous year multiplied by the millage, divided by 1,000 and reduced by 5%. Note that the revenues for each
year are offset against the tax increment changes due to timing of collections (i.e., the revenue for 2019 is based on the ta x increment change from
2017 to 2018
Fund 001 Fund 111 Fund 001 Fund 111 Total
2019 $761,806,000 $473,724,894 3.5645 0.8069 $1,398,514 $316,583 $1,715,097
2020 $810,239,000 $522,157,894 3.5645 0.8069 $1,604,162 $363,136 $1,967,298
2021 $861,111,000 $573,029,894 3.5645 0.8069 $1,768,171 $400,263 $2,168,434
2022 $914,322,000 $626,240,894 3.5645 0.8069 $1,940,438 $439,259 $2,379,697
2023 $970,752,000 $682,670,894 3.5645 0.8069 $2,120,623 $480,048 $2,600,671
2024 $1,062,117,000 $774,035,894 3.5645 0.8069 $2,311,712 $523,305 $2,835,017
2025 $1,109,715,000 $821,633,894 3.5645 0.8069 $2,621,100 $593,341 $3,214,441
2026 $1,158,389,000 $870,307,894 3.5645 0.8069 $2,782,277 $629,827 $3,412,104
2027 $1,208,139,000 $920,057,894 3.5645 0.8069 $2,947,101 $667,139 $3,614,240
2028 $1,258,967,000 $970,885,894 3.5645 0.8069 $3,115,570 $705,275 $3,820,845
2029 $1,310,871,000 $1,022,789,894 3.5645 0.8069 $3,287,685 $744,237 $4,031,922
2030 $1,363,851,000 $1,075,769,894 3.5645 0.8069 $3,463,447 $784,024 $4,247,471
2031 $1,417,909,000 $1,129,827,894 3.5645 0.8069 $3,642,854 $824,637 $4,467,491
2032 $1,473,043,000 $1,184,961,894 3.5645 0.8069 $3,825,907 $866,075 $4,691,982
2033 $1,529,253,000 $1,241,171,894 3.5645 0.8069 $4,012,606 $908,338 $4,920,944
2034 $1,586,541,000 $1,298,459,894 3.5645 0.8069 $4,202,951 $951,427 $5,154,378
2035 $1,644,905,000 $1,356,823,894 3.5645 0.8069 $4,396,942 $995,341 $5,392,283
2036 $1,704,346,000 $1,416,264,894 3.5645 0.8069 $4,594,579 $1,040,080 $5,634,659
2037 $1,764,863,000 $1,476,781,894 3.5645 0.8069 $4,795,862 $1,085,645 $5,881,507
2038 $1,826,457,000 $1,538,375,894 3.5645 0.8069 $5,000,791 $1,132,035 $6,132,826
2039 $1,889,128,000 $1,601,046,894 3.5645 0.8069 $5,209,365 $1,179,250 $6,388,615
2040 $1,952,876,000 $1,664,794,894 3.5645 0.8069 $5,421,586 $1,227,291 $6,648,877
2041 $2,017,700,000 $1,729,618,894 3.5645 0.8069 $5,637,453 $1,276,157 $6,913,610
2042 $2,083,601,000 $1,795,519,894 3.5645 0.8069 $5,856,965 $1,325,848 $7,182,813
2043 $2,150,579,000 $1,862,497,894 3.5645 0.8069 $6,080,124 $1,376,365 $7,456,489
2044 $2,218,633,000 $1,930,551,894 3.5645 0.8069 $6,306,928 $1,427,707 $7,734,635
2045 $2,287,764,000 $1,999,682,894 3.5645 0.8069 $6,537,379 $1,479,874 $8,017,253
2046 $2,357,971,000 $2,069,889,894 3.5645 0.8069 $6,771,475 $1,532,867 $8,304,342
2047 $2,429,256,000 $2,141,174,894 3.5645 0.8069 $7,009,218 $1,586,685 $8,595,903
2048 $2,501,617,000 $2,213,535,894 3.5645 0.8069 $7,250,606 $1,641,328 $8,891,934
$125,914,391 $28,503,387 $154,417,778
Revenue (3)Millage
Year Tax Increment(2)
Total
Taxable Value(1)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-4
5.6
Table 5-6-2: Scenario #2 Projected TIF Revenues
Notes:
1. Source: Scenario #2 projected taxable values for the Bayshore CRA. Average annual growth at 5.2%. Note that the first five years of projected val-
ues are obtained from Florida’s Office of Economic & Demographic Research (EDR) Revenue Estimating Conference. http://edr.state.fl.us/Content/
conferences/advalorem/index.cfm
2. Taxable value for each year (Item 1) less the base year taxable value of $288,081,106
3. For each fund, the tax increment for the previous year multiplied by the millage, divided by 1,000 and reduced by 5%. Note that the revenues for
each year are offset against the tax increment changes due to timing of collections (i.e., the revenue for 2019 is based on the tax increment change
from 2017 to 2018
Fund 001 Fund 111 Fund 001 Fund 111 Total
2019 $761,806,000 $473,724,894 3.5645 0.8069 $1,398,514 $316,583 $1,715,097
2020 $810,239,000 $522,157,894 3.5645 0.8069 $1,604,162 $363,136 $1,967,298
2021 $861,111,000 $573,029,894 3.5645 0.8069 $1,768,171 $400,263 $2,168,434
2022 $914,322,000 $626,240,894 3.5645 0.8069 $1,940,438 $439,259 $2,379,697
2023 $970,752,000 $682,670,894 3.5645 0.8069 $2,120,623 $480,048 $2,600,671
2024 $1,028,659,000 $740,577,894 3.5645 0.8069 $2,311,712 $523,305 $2,835,017
2025 $1,086,938,000 $798,856,894 3.5645 0.8069 $2,507,799 $567,693 $3,075,492
2026 $1,146,540,000 $858,458,894 3.5645 0.8069 $2,705,150 $612,368 $3,317,518
2027 $1,207,463,000 $919,381,894 3.5645 0.8069 $2,906,977 $658,056 $3,565,033
2028 $1,269,707,000 $981,625,894 3.5645 0.8069 $3,113,279 $704,757 $3,818,036
2029 $1,333,274,000 $1,045,192,894 3.5645 0.8069 $3,324,057 $752,471 $4,076,528
2030 $1,398,162,000 $1,110,080,894 3.5645 0.8069 $3,539,310 $801,198 $4,340,508
2031 $1,464,372,000 $1,176,290,894 3.5645 0.8069 $3,759,040 $850,938 $4,609,978
2032 $1,531,904,000 $1,243,822,894 3.5645 0.8069 $3,983,245 $901,692 $4,884,937
2033 $1,600,757,000 $1,312,675,894 3.5645 0.8069 $4,211,925 $953,458 $5,165,383
2034 $1,670,932,000 $1,382,850,894 3.5645 0.8069 $4,445,081 $1,006,238 $5,451,319
2035 $1,742,429,000 $1,454,347,894 3.5645 0.8069 $4,682,713 $1,060,031 $5,742,744
2036 $1,815,247,000 $1,527,165,894 3.5645 0.8069 $4,924,821 $1,114,837 $6,039,658
2037 $1,889,387,000 $1,601,305,894 3.5645 0.8069 $5,171,404 $1,170,657 $6,342,061
2038 $1,964,849,000 $1,676,767,894 3.5645 0.8069 $5,422,463 $1,227,489 $6,649,952
2039 $2,041,632,000 $1,753,550,894 3.5645 0.8069 $5,677,997 $1,285,335 $6,963,332
2040 $2,119,738,000 $1,831,656,894 3.5645 0.8069 $5,938,007 $1,344,194 $7,282,201
2041 $2,199,165,000 $1,911,083,894 3.5645 0.8069 $6,202,493 $1,404,065 $7,606,558
2042 $2,279,913,000 $1,991,831,894 3.5645 0.8069 $6,471,454 $1,464,951 $7,936,405
2043 $2,361,983,000 $2,073,901,894 3.5645 0.8069 $6,744,891 $1,526,849 $8,271,740
2044 $2,445,375,000 $2,157,293,894 3.5645 0.8069 $7,022,804 $1,589,760 $8,612,564
2045 $2,530,089,000 $2,242,007,894 3.5645 0.8069 $7,305,192 $1,653,685 $8,958,877
2046 $2,616,125,000 $2,328,043,894 3.5645 0.8069 $7,592,056 $1,718,623 $9,310,679
2047 $2,703,482,000 $2,415,400,894 3.5645 0.8069 $7,883,396 $1,784,573 $9,667,969
2048 $2,792,161,000 $2,504,079,894 3.5645 0.8069 $8,179,211 $1,851,537 $10,030,748
$134,858,385 $30,528,049 $165,386,434
Revenue (3)
Tax Increment(2)
Millage
Year
Total
Taxable Value(1)
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-5
5.6
Table 5-6-3: Scenario #3 Projected TIF Revenues
Notes:
1. Source: Scenario #3 projected taxable values for the Bayshore CRA. Average annual growth at 5.70%. Note that the first five years of projected values
are obtained from Florida’s Office of Economic & Demographic Research (EDR) Revenue Estimating Conference. http://edr.state.fl .us/Content/
conferences/advalorem/index.cfm
2. Taxable value for each year (Item 1) less the base year taxable value of $288,081,106
3. For each fund, the tax increment for the previous year multiplied by the millage, divided by 1,000 and reduced by 5%. Note t hat the revenues for each
year are offset against the tax increment changes due to timing of collections (i.e., the revenue for 2019 is based on the tax increment change from
2017 to 2018
Fund 001 Fund 111 Fund 001 Fund 111 Total
2019 $761,806,000 $473,724,894 3.5645 0.8069 $1,398,514 $316,583 $1,715,097
2020 $810,239,000 $522,157,894 3.5645 0.8069 $1,604,162 $363,136 $1,967,298
2021 $861,111,000 $573,029,894 3.5645 0.8069 $1,768,171 $400,263 $2,168,434
2022 $914,322,000 $626,240,894 3.5645 0.8069 $1,940,438 $439,259 $2,379,697
2023 $970,752,000 $682,670,894 3.5645 0.8069 $2,120,623 $480,048 $2,600,671
2024 $1,054,119,000 $766,037,894 3.5645 0.8069 $2,311,712 $523,305 $2,835,017
2025 $1,119,750,000 $831,668,894 3.5645 0.8069 $2,594,015 $587,210 $3,181,225
2026 $1,187,573,000 $899,491,894 3.5645 0.8069 $2,816,259 $637,520 $3,453,779
2027 $1,257,587,000 $969,505,894 3.5645 0.8069 $3,045,925 $689,510 $3,735,435
2028 $1,329,792,000 $1,041,710,894 3.5645 0.8069 $3,283,012 $743,179 $4,026,191
2029 $1,404,190,000 $1,116,108,894 3.5645 0.8069 $3,527,521 $798,529 $4,326,050
2030 $1,480,778,000 $1,192,696,894 3.5645 0.8069 $3,779,450 $855,559 $4,635,009
2031 $1,559,559,000 $1,271,477,894 3.5645 0.8069 $4,038,801 $914,268 $4,953,069
2032 $1,640,531,000 $1,352,449,894 3.5645 0.8069 $4,305,573 $974,658 $5,280,231
2033 $1,723,694,000 $1,435,612,894 3.5645 0.8069 $4,579,766 $1,036,727 $5,616,493
2034 $1,809,049,000 $1,520,967,894 3.5645 0.8069 $4,861,381 $1,100,476 $5,961,857
2035 $1,896,596,000 $1,608,514,894 3.5645 0.8069 $5,150,416 $1,165,906 $6,316,322
2036 $1,986,334,000 $1,698,252,894 3.5645 0.8069 $5,446,873 $1,233,015 $6,679,888
2037 $2,078,264,000 $1,790,182,894 3.5645 0.8069 $5,750,751 $1,301,804 $7,052,555
2038 $2,172,385,000 $1,884,303,894 3.5645 0.8069 $6,062,051 $1,372,273 $7,434,324
2039 $2,268,698,000 $1,980,616,894 3.5645 0.8069 $6,380,771 $1,444,423 $7,825,194
2040 $2,367,202,000 $2,079,120,894 3.5645 0.8069 $6,706,913 $1,518,252 $8,225,165
2041 $2,467,898,000 $2,179,816,894 3.5645 0.8069 $7,040,476 $1,593,761 $8,634,237
2042 $2,570,786,000 $2,282,704,894 3.5645 0.8069 $7,381,460 $1,670,950 $9,052,410
2043 $2,675,865,000 $2,387,783,894 3.5645 0.8069 $7,729,865 $1,749,819 $9,479,684
2044 $2,783,135,000 $2,495,053,894 3.5645 0.8069 $8,085,692 $1,830,367 $9,916,059
2045 $2,892,598,000 $2,604,516,894 3.5645 0.8069 $8,448,940 $1,912,596 $10,361,536
2046 $3,004,251,000 $2,716,169,894 3.5645 0.8069 $8,819,609 $1,996,505 $10,816,114
2047 $3,118,097,000 $2,830,015,894 3.5645 0.8069 $9,197,699 $2,082,094 $11,279,793
2048 $3,234,133,000 $2,946,051,894 3.5645 0.8069 $9,583,211 $2,169,362 $11,752,573
$149,760,050 $33,901,357 $183,661,407
Revenue (3)
Taxable Value (1)Tax Increment(2)
Millage
Year
Total
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-6
5.6
Table 5-6-4: Bayshore Beautification MSTU Scenario #1 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $591,115,003 95%2.3604 $1,325,504
2020 $625,527,320 95%2.3604 $1,402,670
2021 $660,034,619 95%2.3604 $1,480,048
2022 $694,831,419 95%2.3604 $1,558,076
2023 $730,024,175 95%2.3604 $1,636,992
2024 $765,674,832 95%2.3604 $1,716,934
2025 $801,819,577 95%2.3604 $1,797,984
2026 $838,478,945 95%2.3604 $1,880,188
2027 $875,663,295 95%2.3604 $1,963,570
2028 $913,375,780 95%2.3604 $2,048,136
2029 $951,615,129 95%2.3604 $2,133,883
2030 $990,376,372 95%2.3604 $2,220,800
2031 $1,029,652,374 95%2.3604 $2,308,872
2032 $1,069,434,646 95%2.3604 $2,398,079
2033 $1,109,713,336 95%2.3604 $2,488,399
2034 $1,150,478,225 95%2.3604 $2,579,809
2035 $1,191,719,137 95%2.3604 $2,672,287
2036 $1,233,425,692 95%2.3604 $2,765,809
2037 $1,275,588,082 95%2.3604 $2,860,353
2038 $1,318,196,940 95%2.3604 $2,955,898
2039 $1,361,243,853 95%2.3604 $3,052,426
2040 $1,404,721,160 95%2.3604 $3,149,919
2041 $1,448,622,279 95%2.3604 $3,248,362
2042 $1,492,941,782 95%2.3604 $3,347,743
2043 $1,537,675,538 95%2.3604 $3,448,053
2044 $1,582,820,738 95%2.3604 $3,549,286
2045 $1,628,375,926 95%2.3604 $3,651,438
2046 $1,674,341,360 95%2.3604 $3,754,510
2047 $1,720,718,577 95%2.3604 $3,858,505
2048 $1,767,510,764 95%2.3604 $3,963,431
Total -FY 2019-48:$77,217,964
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-7
5.6
Table 5-6-5: Bayshore Beautification MSTU Scenario #2 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $606,549,761 95%2.3604 $1,360,115
2020 $647,828,592 95%2.3604 $1,452,678
2021 $688,973,702 95%2.3604 $1,544,941
2022 $730,242,846 95%2.3604 $1,637,482
2023 $771,769,450 95%2.3604 $1,730,600
2024 $813,623,294 95%2.3604 $1,824,453
2025 $855,837,738 95%2.3604 $1,919,113
2026 $898,423,883 95%2.3604 $2,014,608
2027 $941,377,891 95%2.3604 $2,110,927
2028 $984,686,255 95%2.3604 $2,208,041
2029 $1,028,328,725 95%2.3604 $2,305,904
2030 $1,072,280,092 95%2.3604 $2,404,459
2031 $1,116,512,185 95%2.3604 $2,503,645
2032 $1,160,994,826 95%2.3604 $2,603,392
2033 $1,205,696,625 95%2.3604 $2,703,630
2034 $1,250,585,657 95%2.3604 $2,804,288
2035 $1,295,630,050 95%2.3604 $2,905,295
2036 $1,340,798,359 95%2.3604 $3,006,579
2037 $1,386,060,036 95%2.3604 $3,108,073
2038 $1,431,385,662 95%2.3604 $3,209,711
2039 $1,476,747,194 95%2.3604 $3,311,428
2040 $1,522,118,310 95%2.3604 $3,413,168
2041 $1,567,474,241 95%2.3604 $3,514,873
2042 $1,612,792,344 95%2.3604 $3,616,493
2043 $1,658,052,037 95%2.3604 $3,717,983
2044 $1,703,234,847 95%2.3604 $3,819,300
2045 $1,748,324,458 95%2.3604 $3,920,408
2046 $1,793,306,734 95%2.3604 $4,021,275
2047 $1,838,170,219 95%2.3604 $4,121,876
2048 $1,882,905,417 95%2.3604 $4,222,189
Total -FY 2019-48:$83,036,927
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-8
5.6
Table 5-6-6: Bayshore Beautification MSTU Scenario #3 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $618,846,476 95%2.3604 $1,387,689
2020 $666,424,041 95%2.3604 $1,494,376
2021 $714,013,673 95%2.3604 $1,601,090
2022 $761,898,751 95%2.3604 $1,708,467
2023 $810,218,308 95%2.3604 $1,816,817
2024 $859,037,223 95%2.3604 $1,926,288
2025 $908,377,891 95%2.3604 $2,036,928
2026 $958,236,209 95%2.3604 $2,148,730
2027 $1,008,590,342 95%2.3604 $2,261,643
2028 $1,059,406,499 95%2.3604 $2,375,592
2029 $1,110,642,628 95%2.3604 $2,490,483
2030 $1,162,251,104 95%2.3604 $2,606,209
2031 $1,214,180,327 95%2.3604 $2,722,654
2032 $1,266,376,232 95%2.3604 $2,839,697
2033 $1,318,783,498 95%2.3604 $2,957,214
2034 $1,371,346,270 95%2.3604 $3,075,079
2035 $1,424,008,878 95%2.3604 $3,193,169
2036 $1,476,716,929 95%2.3604 $3,311,361
2037 $1,529,416,999 95%2.3604 $3,429,534
2038 $1,582,057,896 95%2.3604 $3,547,575
2039 $1,634,590,626 95%2.3604 $3,665,373
2040 $1,686,968,643 95%2.3604 $3,782,825
2041 $1,739,148,306 95%2.3604 $3,899,831
2042 $1,791,089,012 95%2.3604 $4,016,302
2043 $1,842,753,405 95%2.3604 $4,132,153
2044 $1,894,107,627 95%2.3604 $4,247,309
2045 $1,945,121,181 95%2.3604 $4,361,701
2046 $1,995,767,160 95%2.3604 $4,475,268
2047 $2,046,022,279 95%2.3604 $4,587,959
2048 $2,095,866,709 95%2.3604 $4,699,730
Total -FY 2019-48:$90,799,046
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-9
5.6
Table 5-6-7: Haldeman Creek MSTU Scenario #1 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $121,367,536 95%1.0000 $115,299
2020 $128,526,521 95%1.0000 $122,100
2021 $135,704,827 95%1.0000 $128,920
2022 $142,942,896 95%1.0000 $135,796
2023 $150,262,704 95%1.0000 $142,750
2024 $157,677,032 95%1.0000 $149,793
2025 $165,193,225 95%1.0000 $156,934
2026 $172,815,346 95%1.0000 $164,175
2027 $180,545,373 95%1.0000 $171,518
2028 $188,383,756 95%1.0000 $178,965
2029 $196,329,988 95%1.0000 $186,513
2030 $204,382,850 95%1.0000 $194,164
2031 $212,540,650 95%1.0000 $201,914
2032 $220,801,394 95%1.0000 $209,761
2033 $229,162,805 95%1.0000 $217,705
2034 $237,622,632 95%1.0000 $225,742
2035 $246,178,462 95%1.0000 $233,870
2036 $254,827,995 95%1.0000 $242,087
2037 $263,568,960 95%1.0000 $250,391
2038 $272,399,253 95%1.0000 $258,779
2039 $281,316,833 95%1.0000 $267,251
2040 $290,320,002 95%1.0000 $275,804
2041 $299,407,206 95%1.0000 $284,437
2042 $308,577,110 95%1.0000 $293,148
2043 $317,828,658 95%1.0000 $301,937
2044 $327,161,143 95%1.0000 $310,803
2045 $336,574,094 95%1.0000 $319,745
2046 $346,067,305 95%1.0000 $328,764
2047 $355,641,019 95%1.0000 $337,859
2048 $365,295,793 95%1.0000 $347,031
Total -FY 2019-48:$6,753,955
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-10
5.6
Table 5-6-8: Haldeman Creek MSTU Scenario #2 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $124,558,218 95%1.0000 $118,330
2020 $133,140,017 95%1.0000 $126,483
2021 $141,695,436 95%1.0000 $134,611
2022 $150,277,871 95%1.0000 $142,764
2023 $158,914,679 95%1.0000 $150,969
2024 $167,620,097 95%1.0000 $159,239
2025 $176,400,756 95%1.0000 $167,581
2026 $185,258,652 95%1.0000 $175,996
2027 $194,192,721 95%1.0000 $184,483
2028 $203,199,877 95%1.0000 $193,040
2029 $212,275,571 95%1.0000 $201,662
2030 $221,414,344 95%1.0000 $210,344
2031 $230,610,047 95%1.0000 $219,080
2032 $239,856,126 95%1.0000 $227,863
2033 $249,145,751 95%1.0000 $236,688
2034 $258,472,054 95%1.0000 $245,548
2035 $267,828,164 95%1.0000 $254,437
2036 $277,207,234 95%1.0000 $263,347
2037 $286,602,686 95%1.0000 $272,273
2038 $296,008,161 95%1.0000 $281,208
2039 $305,417,647 95%1.0000 $290,147
2040 $314,825,418 95%1.0000 $299,084
2041 $324,226,118 95%1.0000 $308,015
2042 $333,614,832 95%1.0000 $316,934
2043 $342,987,111 95%1.0000 $325,838
2044 $352,338,908 95%1.0000 $334,722
2045 $361,666,688 95%1.0000 $343,583
2046 $370,967,365 95%1.0000 $352,419
2047 $380,238,358 95%1.0000 $361,226
2048 $389,477,595 95%1.0000 $370,004
Total -FY 2019-48:$7,267,918
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-11
5.6
Table 5-6-9: Haldeman Creek MSTU Scenario #3 Projected Revenues
Notes: there is a 5% statutory reduction requirement for counties when projecting for budget
Tax Year (FY)MSTU Valuation Budgeting
Adjustment Millage Projected
Revenue
2019 $127,106,206 95%1.0000 $120,751
2020 $136,994,758 95%1.0000 $130,145
2021 $146,888,010 95%1.0000 $139,544
2022 $156,844,298 95%1.0000 $149,002
2023 $166,892,038 95%1.0000 $158,547
2024 $177,044,257 95%1.0000 $168,192
2025 $187,305,175 95%1.0000 $177,940
2026 $197,673,490 95%1.0000 $187,790
2027 $208,144,221 95%1.0000 $197,737
2028 $218,709,954 95%1.0000 $207,774
2029 $229,361,500 95%1.0000 $217,893
2030 $240,088,574 95%1.0000 $228,084
2031 $250,880,014 95%1.0000 $238,336
2032 $261,724,194 95%1.0000 $248,638
2033 $272,609,257 95%1.0000 $258,979
2034 $283,523,220 95%1.0000 $269,347
2035 $294,454,148 95%1.0000 $279,731
2036 $305,390,372 95%1.0000 $290,121
2037 $316,320,528 95%1.0000 $300,505
2038 $327,233,622 95%1.0000 $310,872
2039 $338,119,195 95%1.0000 $321,213
2040 $348,967,293 95%1.0000 $331,519
2041 $359,768,601 95%1.0000 $341,780
2042 $370,514,490 95%1.0000 $351,989
2043 $381,196,966 95%1.0000 $362,137
2044 $391,808,847 95%1.0000 $372,218
2045 $402,343,563 95%1.0000 $382,226
2046 $412,795,427 95%1.0000 $392,156
2047 $423,159,430 95%1.0000 $402,001
2048 $433,431,416 95%1.0000 $411,760
Total -FY 2019-48:$7,948,927
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-12
5.6
5.6.3 Underlying Assumptions
The following charts show underlying population and tax value trends that inform and contextualize the revenue
projections calculations presented in this section. Figure 5-6-1 shows that the rate of population growth for
Collier County has decreased sizably since 2002/2003, with a more gradual decrease projected out from
2017/2018 for the next few decades.
In terms of historic tax value growth rates since 2000, Figure 5-6-2 shows that there was an increase during the
lead up to the recession, followed by a drop during the recession itself. In recent years, the rate has gradually
risen.
Given the sizable changes during the lead-up to the recession and the recession itself, the model used to
generate TIF projections was matched to longer historical trends in County taxable values, from the 1970s
through 2003/2004 historical taxable value for Collier County. Figure 5-6-3 shows the historical trend used for
guidance in blue; this trend is continued for comparison to projection calculations (in this case, for the low
revenue projections, shown by the grey line through 2048). The orange line indicates historic data that was
excluded from the historic trend basis since it was considered an anomaly.
Figure 5-6-1: Population Growth Rate Trends and Projections (2000-2045)
Source: BEBR, Volume 51, Bulletin 180, January 2018
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-13
5.6
Figure 5-6-2: Trends in Tax Value Growth Rates (2000-2017)
Source: Florida Property Valuations and Tax Databook & EDR Ad Valorem Revenue Estimating Conference
Figure 5-6-3: Historic and Projected TIF Revenue Trend Comparison for Low Revenue Projection
Source: Florida Property Valuations and Tax Databook & EDR Ad Valorem Revenue Estimating Conference
y = 67,809,839.76x2 -717,793,067.39x + 6,145,364,420.48
R² = 0.95
$0
$50,000,000,000
$100,000,000,000
$150,000,000,000
$200,000,000,000
$250,000,000,000
$300,000,000,000
$350,000,000,000
TAX INCREMENT & MSTU ESTIMATES
Bayshore Gateway Triangle CRA Area Plan—Draft March 2019 5-6-14
5.6
Conclusion
With the recovery from the recession of 2008, the CRA
area is poised for revitalization via investment,
development, and redevelopment. With this update,
the CRA will be able to continue the general mission of
redevelopment that it set out when the Bayshore
Gateway Triangle redevelopment area was first created
in 2000.
The CRA can move forward with the more detailed
planning and evaluation for the suggested
implementation items of this Redevelopment Area Plan
with the guidance of the overall vision, allowing for
change and also protecting and enhancing what
defines the area and makes it unique.