PBSD MSTBU Minutes 01/07/2019PELICAN BAY SERVICES DIVISION BOARD REGULAR SESSION
JANUARY 7, 2019
The Pelican Bay Services Division Board met on Monday, January 7, 2019, at 1:00 p.m. at the
Community Center at Pelican Bay, 8960 Hammock Oak Drive, Naples, Florida 34108.
In attendance were:
Pelican Bay Services Division Board
Scott Streckenbein, Chairman (absent)
Tom Cravens, Vice -Chairman (Acting Chair)
Joe Chicurel
Jacob Damouni
Ken Dawson
Nick Fabregas
Pete Griffith (absent)
Bohdan Hirniak
Susan O'Brien (absent)
Mike Shepherd
Rick Swider
Pelican Bay Services Division Staff Mary McCaughtry, Operations Analyst (absent,
Neil Dorrill, Administrator Lisa Jacob, Associate Project Manager
Marion Bolick, Operations Manager (absent) Barbara Shea, Recording Secretary
Also Present John Gandolfo, Pelican Bay Foundation
Charles Bodo, Pelican Bay Foundation Jim Hoppensteadt, Pelican Bay Foundation
Sean Callahan, County Manager's Office Mark Isackson, County Budget Office
Tim Corcoran, Pelican Bay Foundation Trent Waterhouse, Pelican Bay Foundation
APPROVED AGENDA (AS PRESENTED
1. Pledge of Allegiance
2. Roll Call
3. Agenda approval
4. Approval of 12/05/18 Regular Session meeting minutes
5. Audience Comments
6. Overview of long-term financing alternatives (Mark Isackson)
7. Administrator's report
a. Update on streetlight project and sign bid award
b. US 41 berm clean-up and restoration bid schedule
c. NTP for planning new field operations facility & admin. building
d. Inspection of selected WM pipes from pond to pond and under berm
e. Status of WM easements in Oakmont neighborhood
f Clam Pass aerials/annual reports
8. Committee reports
a. Clam Bay
b. Landscape & Safety
c. Water Management
d. Budget
Pelican Bay Services Division Board Regular Session
January 7, 2019
i. Proposal for revising PBSD revenue methodology
9. Chairman's report
10. Old business
11. New business
12. Adjournment
ROLL CALL
Mr. Griffith, Ms. O'Brien and Mr. Streckenbein were absent and a quorum was established
Mr. Dawson motioned, Mr. Damouni seconded to approve the agenda as
nresented. The motion carried unanimously.
Mr. Dawson motioned, Mr. Damouni seconded to approve the 12/05/18 regular
session meetiniz minutes as amended. The motion carried unanimously.
AUDIENCE COMMENTS
None
OVERVIEW OF LONG-TERM FINANCING ALTERNATIVES
Mr. Mark Isackson, Director of Corporate Finance & Management Services, County Office of
Management & Budget, and Chair of the County Finance Committee, provided a presentation on the
issuance of debt and "the County's process." He provided a spreadsheet, distributed to board members
and added to the record, which provided a detailed analysis of a 7 -year scenario and a 10 -year scenario
for loan amounts of $10, $15, and $20 million. For each of these scenarios, the spreadsheet provided
data on (1) total annual PBSD debt service, (2) annual debt service per ERU if the repayment is through
an assessment pledge, and (3) examples of the increases to homeowner taxes at various home values,
if repayment is through a property tax pledge.
Mr. Isackson's discussion included the following highlights:
• A bank loan, obtained through an RFP, minimizes issuance fees.
• A loan structure which includes a balloon payment is not recommended.
• The PBSD would choose the length of time for the loan repayment.
• The PBSD would determine whether repayment is through a property tax pledge (which will
generally result in a lower interest rate, but requires approval by PB residents through a
referendum) or an assessment pledge.
• If the PBSD chooses to proceed with the County's process of issuing debt, the next steps would
include (1) a discussion and approval by the County's Finance Committee, (2) a
recommendation from the Finance Committee to the Board of County Commissioners (BCC),
(3) approval by the BCC, and (4) a 90 -day process to obtain competitive bids.
Mr. Tim Corcoran asked whether a simple majority approval of the PB residents casting ballots
would be sufficient to approve a referendum vote required for PBSD issuance of debt backed by ad
valorem taxes. Mr. Isackson confirmed this.
Pelican Bay Services Division Board Regular Session
January 7, 2019
Mr. Charles Bodo commented on the PBSD's possible move towards ad valorem funding and
suggested the need for discussion forums and community input.
Mr. Trent Waterhouse commented on the possibility of pension fund private placement
financing. Mr. Isackson commented that the County prefers public placement.
Mr. George Russell asked whether the credit of the County would be behind the PBSD's debt.
Mr. Isackson responded that the debt would be issued based on the stand-alone credit of the PBSD,
and not the credit of the County.
Mr. John Gandolfo requested a description of the four infrastructure projects which would be
funded by the proposed long-term financing. Mr. Shepherd commented that the proceeds of the bank
loan ($17 - $25 million) would be used for (1) replacement of PB sidewalks (approx. $7 million), (2)
lake bank renovations for ten lakes which are in immediate need of remediation (approx. $10 million),
(3) replacement of our operations/maintenance facility, and (4) repairs of our failing storrawater
conveyance structures.
ADMINISTRATOR'S REPORT
UPDATE ON STREETLIGHT PROJECT AND SIGN BID AWARD
Mr. Dorrill commented that our streetlight pole repairs project has been completed, except for
the installation of the pathway bollard lights which are on order. The contract for the repair and
replacement sign project has been awarded. A pre -construction meeting is scheduled for this week,
which will be followed by the commencement of the project.
OTHER WATER MANAGEMENT PROJECT UPDATES
Mr. Dorrill reported that staff is pursuing a permit modification to do the lake bank erosion
project for the facility (St. Maarten/St. Thomas) which is adjacent to the Commons. This lake bank
remediation project includes a hybrid solution consisting of seawall, rip rap, and geotube.
Mr. Dorrill reported on a recent meeting to evaluate the permitability of the beach dune swale
(Bay Colony drainage system) reconstruction. The PBSD will need a permit modification in order for
us to reconstruct/re-dig the Swale which conveys the water from the south to the north and upper
reaches of Clam Bay.
OAK LAKE SANCTUARY WEIR MODIFICATION
Mr. Dorrill commented that he hopes to have a start date for the Oak Lake Sanctuary weir
modification project (to effectuate the enlargement of the orifice at the weir adjacent to the Oak Lake
Sanctuary community) by the end of the month. The contractor had delayed work until the dry season,
waiting for the water levels to decline.
NTP FOR PLANNING NEW FIELD OPS. FACILITY & ADMIN. BUILDING
Two alternate site plans for the PBSD maintenance site, located on land owned by the County
Public Utilities Dept., were provided in the agenda packet. Mr. Dorrill commented that the new site
would include replacement of the existing 40 -year old structure as well as offices for administrative
staff. Mr. Dorrill summarized the two alternatives: (1) replacement of the existing facility "in place"
with a larger facility, or (2) construction of a new larger facility at the south end of the site adjacent to
the old decommissioned sewage treatment plant. The site plan would also include the construction of
(1) a separate out -building which would be used as a storage facility for fertilizers, chemicals, and
hazardous materials, and (2) a fueling facility for our vehicles and equipment. Mr. Dorrill commented
3
Pelican Bay Services Division Board Regular Session
January 7, 2019
that he has conveyed to County senior management that the PBSD Board would like our property
interest in the site to be hardened and that he will continue to pursue a long-term lease on the property.
INSPECTION OF SELECTED WM PIPES FROM POND TO POND AND UNDER
THE BERM
Mr. Dorrill updated the board on our on-going work on PB stormwater conveyance pipes. The
original contractor was terminated for non-performance. A second contractor has been hired to do
further cleaning, minor repairs, and video inspections with a robotic camera, with work scheduled to
begin on Jan. 14. Our civil engineer ABB will perform a post -inspection evaluation and provide
information as to the nature of the deficiencies. This data will enable us to provide a better estimate
of the total funding required for pipe repairs and possible pipe replacements, if the PBSD were to take
on this responsibility.
STATUS OF WM EASEMENTS IN OAKMONT NEIGHBORHOOD
Mr. Dorrill reported that staff has received the inventory of County or public drainage
easements (completed by the County Transportation Division) which identifies all public drainage
easements or important easements for us to acquire in order to facilitate roadway drainage and the
conveyance of water between our lakes. In the event that the PBSD were to assume responsibility for
the roadway drainage facilities, we would expect annual compensation from the County.
DISCUSSIONS WITH COUNTY SENIOR MANAGEMENT
Mr. Dorrill commented on recent discussions with Mr. Nick Casalanguida, Deputy County
Manager, regarding what a reasonable County contribution would be in exchange for the PBSD
assuming responsibility of PB sidewalks. Mr. Dorrill stated that an annual amount of $250,000 for
the capital portion and $50,000 for maintenance could be considered reasonable.
THREE-MONTH GOALS
Mr. Dorrill commented that within the next three months he expects (1) to receive the final
engineering sidewalk analysis, (2) to receive a better estimate of the linear feet of roadway drainage
pipes if the PBSD were to assume responsibility, and (3) to receive a draft of a memorandum of
understanding between the County Manager's Office and the PBSD which would spell out the annual
reimbursement appropriation that the PBSD would receive.
CLAM PASS AERIALS/ANNUAL REPORTS
Mr. Dorrill provided an aerial photo of Clam Pass taken Dec. 27/28 for review by the board,
and commented that the Pass looks very good, as we approach the one-year anniversary of the last
maintenance dredging. He commented that Mr. Casalanguida has obligated the PBSD to do a five-
year evaluation of the Clam Bay Management Plan and provide any alternative designs which would
be appropriate for hydraulic dredging purposes. At the January Clam Bay Committee meeting, a
related scope of services proposal submitted by Humiston & Moore was reviewed.
Mr. Dorrill commented that the Earth Tech and Humiston & Moore annual reports were
received in December and some information from these reports was included in the agenda packet.
COMMITTEE REPORTS
CLAM BAY REPORT
Ms. O'Brien's January 2019 Clam Bay update was included in the agenda packet.
11
Pelican Bay Services Division Board Regular Session
January 7, 2019
LANDSCAPE &SAFETY REPORT
Dr. Chicurel reported that the Landscape & Safety Committee met on Dec. 20, and the
following items were discussed.
1. Mr. Tom Barber of Agnoli, Barber & Brundage presented an engineering analysis and cost
estimate for the construction of new sidewalks within Pelican Bay and along Vanderbilt Beach Rd.
He was asked to prepare a similar estimate for the sidewalk along Seagate Drive. The Seagate section
will be added to the approximate project cost of $5,666,866. The next engineering report will include
the exact location of the sidewalks, reflect property lines, and any easements necessary for construction
and maintenance. March 2019 is the target time for the PBSD Board to vote on approving the sidewalk
project and related issues.
2. Due to County school security manpower needs, extra CCSO patrols within Pelican Bay
may be difficult to obtain. Our Sheriff's Office community policing liaison, Cpl. Tania Wrobleski,
will try to help secure the after -hour patrols.
3. Ms. Jacob reported that (1) streetlight pole repairs have been completed, (2) a contract has
been awarded for street sign replacement and a pre -construction meeting is planned for Jan. 8, and (3)
the County plans to install additional crosswalk signs on Myra Janco Daniels Blvd. near St. Williams
Catholic Church.
4. Staff was asked to prepare an inventory of "line of sight" conflicts within Pelican Bay
utilizing a sedan for gauging any conflicts. Plant heights and multiple tree trunks at corners and
median bull noses will be specifically evaluated.
5. The committee consensus was to approve the concept of widening the median along Gulf
Park Dr. to finalize the newly constructed "right turn only" lane onto US 41. ABB will provide the
committee with a plan.
6. Mr. Bolick reported (1) the US 41 berm restoration project should begin in the Spring, (2)
a new tree maintenance RFP was issued, and (3) pine straw, mulching, and re -sodding work is on-
going.
WATER MANAGEMENT COMMITTEE
The Water Management Committee did not meet.
BUDGET REPORT
Mr. Shepherd provided a presentation on PBSD revenue analysis and a proposed funding
modification plan. Highlights included the following:
• The creation of a funding modification plan was precipitated by comments from commercial
and institutional members during the Spring 2018 budget process.
• The PBSD has traditionally collected revenue through an ad valorem revenue stream and a
non -ad valorem revenue stream based on ERU's (equivalent residential units).
• Since 1993, non-residential properties have been assigned ERU's based on acreage; improved
land has been assigned 5.75 ERU's per acre and unimproved land has been assigned 1 ERU
per acre.
• The goals of the proposed plan are to (1) improve the equity between the non-residential
members, (2) lower the cost of the commercial/institutional members, and (3) reduce the
regressivity on the residential members.
• Changes in the ERU formula in the proposal would include (1) changing the assigned ERU's
for commercial improved property from 5.75 to 5.50, (2) changing the assigned ERU's for
5
Pelican Bay Services Division Board Regular Session
January 7, 2019
"The Club" from 1.0 to 1.75, and (3) maintaining the assigned ERU's for unimproved property
at 1.0.
• The proposed plan is revenue neutral, maintains the existing methodology, and provides some
relief to commercial members.
• If the new modification plan was applied to last year's budget cycle, then the Club would have
paid an additional $53,738, or approximately $10/month for each of the 450 golf members.
Mr. John Gandolfo questioned whether this modification plan is the first step in a series of
modifications. Mr. Shepherd commented that there are no plans for future modifications.
Mr. Charles Bodo commented on whether PB residents have a progressive or traditional view
of life.
Mr. Tim Corcoran commented positively on the presentation and that the current inequity of
ERU allocation to the Club is being addressed/corrected appropriately.
CHAIRMAN'S REPORT
None.
OLD BUSINESS
UPDATE ON CHATEAUMERE'S VIEW OF THE OPERATIONS CENTER
Mr. Dorrill commented on continued concerns expressed by Chateaumere residents on their
visual impact from the PBSD Operations Center property. He suggested follow up work on this issue
and asked the bond for the authority to revisit this issue and identify budget for possible remediation
work.
Mr. Trent Waterhouse (a Chateaumere resident) commented that (1) a mulch pile has been
visible since Hurricane Irma, (2) Ms. Ellin Goetz provided a tree screen drawing for remediation
purposes with an estimated cost of approximately $10,000, and (3) suggested that the Goetz tree screen
proposal be combined with the US41 berm restoration project.
Ms. Diane Lustig commented that Hyde Park residents experience the same poor view of the
Operations Center property as Chateaumere residents.
Mr. Dawson motioned that Mr. Dorrill look further into a possible barrier to not
obstruct the Chateaumere's view or have them be able to see into where the tank
used to be (where the replacement operations facility is planned). After
discussion by the board, Mr. Dawson withdrew his motion. Mr. Shepherd
motioned, Mr. Dawson seconded to authorize Mr. Dorrill to proceed with the
Goetz recommendations in the Hyde Park and Chateaumere areas not to exceed
The motion carried
NEW BUSINESS
PBSD ELECTION
Ms. Denise McLaughlin commented that she is interested in joining the PBSD Board and has
had trouble obtaining information on the PBSD election. Mr. Shepherd commented that the County
determines the election dates. Mr. Dorrill commented that the PBSD ordinance obligates the Clerk of
the Circuit Court to conduct the PBSD election and he will work with Mr. Hoppensteadt to include
Pelican Bay Services Division Board Regular Session
January 7, 2019
the PBSD Board candidates' biographies in a future edition of the PB Post. Dr. Chicurel commented
that the PBPOA typically facilitates a PBSD Board candidates forum.
The meetine was adiourned at 2:36