BCBE Construction Co.. Inc. presentation on Goodland Boat Park Project.
12/15/2009 9:00:00 AM
Agenda Item No. 5D
December 15, 2009
Page 1 of 2
Approved By
Kathy Carpenter Executive Secretary Date
Public Services Public Services Admin. 912512009 9:00 AM
Approved By
Marla Ramsey Administrator - Public Services Date
Public Services Division Public Services Division 91281200911:25 AM
Approved By
Lyn Wood Contracts Specialist Date
Administrative Services
Division Purchasing & General Services 9128/2009 11 :32 AM
Approved By
Gary McAlpin Director. Coastal Management
Programs Date
Public Services Division Coastal Zone Management 12171200910:24 AM
Approved By
OMS Coordinator Date
County Manager's Office Office of Management & Budget 1217120093:40 PM
Approved By
John A. Yonkosky Director - Management and Budget Date
Office of Management & Office of Management & Budget
Budget 1217120094:28 PM
Approved By
Winona W. Stone Assistant to the County Manager Date
County Managers Office County Managers Office 12/8/20098:50 AM
Agenda Item No. 5D
December 15, 2009
Page 2 of 2
CONTRACTOR PRESENT A nON FORM
Board Presentation Date: December 15, 2009
Contract Number. Proiect Title. Proiect Number: 09-5169, Goodland Boat Park,
80611.1.
Firm Name: BCBE Construction Co., Inc.
Proiect Manal!er: Angel Napoles
Proiect Description: Site clearing and excavation of existing 5.22 acre site for the
construction of a new 75 trailer parking lot boat park with a two lane hoat ramp,
dock master station with bait tanks, restroom facilities, picnic pavilion, boat dock
with 28 wet slips, fishing pier, fish cleaning station, landscape buffering, retention
areas, signage and fencing.
Oril!inal Start Date: 3.16.09
Notice to Proceed Issuance Date: 3.16.09
Oril!inal Completion Date: 11.11.09
Revised Comoletion Date: 03.06.10
Reason(s) for Variance: Due to
unforeseen site conditions, additional
scope of work was required to
accommodate reflected changcs, and
added value.
Actions Planned/Taken to Minimize
Variance: Consistcnt ongoing project
monitoring and assessment evaluation
of progress to minimize and avoid
foresecable problems.
Oril!inal Budl!et: $1,690,020.28
Revised Budl!et: $1,791,780.36
Reason(s) for Variance: Additional
funding was required to accommodate
reflected changes due to unforeseen site
conditions, and value enhancements.
Actions Planned/Taken to Minimize
Variance: Close monitoring of budgetary
restraints and effective value engineering
to offset cost deficiencies.
Current Proiect Status: The project is currently @ 60% complete, installation of
storm water drainage, placement of all retention areas, berm installations, and
installation of piling foundations.