Agenda 01/08/2019 Item #16C 801/08/2019
EXECUTIVE SUMMARY
Recommendation to authorize the necessary budget amendments to reallocate Public Utilities
Department wastewater capital project funds pending Hurricane Irma reimbursements from
FEMA and the State of Florida.
OBJECTIVE: To remain in compliance and meet the demand throughout the wastewater collections and
treatment systems.
CONSIDERATIONS: In FY2018, the Solid Waste Fund 474 borrowed $40.7 million from the Collier
County Water-Sewer District (CCWSD) Water User Fee Fund 412 and Wastewater User Fee Fund 414 to
finance the Hurricane Irma debris mission. Fund 412 provided $4 million, and Fund 414 provided $36.7
million. To date, the CCWSD has been reimbursed for $2.8 million. The CCWSD anticipates receiving
the balance of $37.9 million in 2019 pending FEMA and State of Florida reimbursement. Until that time,
the existing Fund 414 funds need to be reallocated to execute priority projects.
Projects to benefit from the reallocated wastewater funding are:
70144 Force Main Transmission System Technical Support: The reallocated funds will be used
to procure air release valves (ARVs) to replace failing ARVs in the Wastewater Collections
system. Improperly functioning ARVs can lead to air accumulation in the pipeline, thereby
reducing the capacity to transport wastewater. ($150,000 budget amendment)
70116 Goodlette IQ Water Main: The reallocated funds will provide materials needed to
complete the 24” IQ water main along Goodlette-Frank Road. ($125,000 budget amendment)
70148 Water Reclamation Facilities Technical Support: The reallocated funds will provide
updated variable frequency drives at various locations in the South County Water Reclamation
Facility. ($111,000 budget amendment)
70206 MPS 321 Bypass: The reallocated funds will allow this project to progress to bidding and
construction. With the installation of the bypass system, Wastewater Collections will be able to
bypass wastewater flow around the wet well for cleaning and maintenance. ($160,000 budget
amendment)
70227 Twin Eagles Community Pump Station and Force Main: The reallocated funds will
provide materials needed to complete the 14” force main along 8th Street NW. ($50,000 budget
amendment)
The above projects will be procured separately in accordance with the County’s Procurement Ordinance.
FISCAL IMPACT: A wastewater budget amendment in the total amount of $596,000 is required to
reallocate funds within the Sewer Capital Projects Fund 414.
LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote
for Board approval. -SRT
GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan
standards to ensure the adequacy and availability of viable public facilities and to remain in compliance
with all regulatory programs.
16.C.8
Packet Pg. 1294
01/08/2019
RECOMMENDATION: To authorize the necessary budget amendments as set forth in the above Fiscal
Impact section.
Prepared By: Tom S. Chmelik, Public Utilities Engineering and Project Management Director
16.C.8
Packet Pg. 1295
01/08/2019
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.8
Doc ID: 7599
Item Summary: Recommendation to authorize the necessary budget amendments to reallocate
Public Utilities Department wastewater capital project funds pending Hurricane Irma reimbursements
from FEMA and the State of Florida.
Meeting Date: 01/08/2019
Prepared by:
Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management
Name: Tom Chmelik
12/19/2018 11:30 AM
Submitted by:
Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management
Name: Tom Chmelik
12/19/2018 11:30 AM
Approved By:
Review:
Public Utilities Operations Support Tara Castillo Additional Reviewer Completed 12/19/2018 11:37 AM
Public Utilities Planning and Project Management Michael Stevens Additional Reviewer Completed 12/19/2018 11:52 AM
Public Utilities Operations Support AmiaMarie Curry Additional Reviewer Completed 12/19/2018 2:10 PM
Public Utilities Department Sarah Hamilton Level 1 Division Reviewer Completed 12/19/2018 2:34 PM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 12/20/2018 2:26 PM
Public Utilities Department Dan Rodriguez Level 2 Division Administrator Review Completed 12/21/2018 11:04 AM
Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 12/21/2018 11:22 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 12/21/2018 2:34 PM
County Attorney's Office Emily Pepin CAO Preview Completed 12/21/2018 4:00 PM
Budget and Management Office Ed Finn Additional Reviewer Completed 12/26/2018 1:02 PM
Office of Management and Budget Susan Usher Additional Reviewer Completed 12/27/2018 2:48 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 12/27/2018 3:13 PM
Board of County Commissioners MaryJo Brock Meeting Pending 01/08/2019 9:00 AM