COLLIER COUNTY LAND DEVELOPMENT CODE
CONSTRUCTION AND MAINTENANCE AGREEMENT
FOR SUBDIVISION IMPROVEMENTS
THIS CONSTRUCTION AND MAINTENANCE AGREEMENT FOR SUBDIVISION
IMPROVEMENTS entered into this 22neA day of JjA?.C,4 2011 between DiVosta Homes, LP
hereinafter referred to as "Developer", and the Board of County Commissioners of Collier County, Florida,
hereinafter referred to as the "Board ".
RECITALS:
A. The Developer has, simultaneously, with the delivery of this Agreement, applied for the approval by
the Board of a certain plat of a subdivision to be known as VeronaWalk Phase 4D.
B. Section 10.02.04 of the Collier County Land Development Code requires the Developer to post
appropriate guarantees for the construction of the improvements required by said subdivision
regulations, said guarantees to be incorporated in a bonded agreement for the construction of the
required improvements.
NOW, THEREFORE, in consideration of the foregoing premises and the mutual covenants
hereinafter set forth, the Developer and the Board do hereby covenant and agree as follows:
1. Developer will cause to be constructed: The paving, drainage, potable water system, sanitary
sewer system, irrigation, landscaping, and street lighting improvements within eighteen (18)
months from the date of approval said subdivision plat, said improvements hereinafter referred
to as the required improvements.
2. Developer herewith tenders its subdivision performance security (attached hereto as Exhibit
"A" and by reference made a part hereof) in the amount of $310,238.04, which represents 10%
of the total contract cost to complete construction of potable water, sanitary sewer, and storm
water, plus 110% of the probable cost for paving, drainage, lighting, landscaping, and irrigation
to complete the required improvements at the date of this Agreement.
3. In the event of default by the Developer or failure of the Developer to complete such
improvements within the time required by the Land Development Code, Collier County, may
call upon the subdivision performance security to insure satisfactory completion of the required
improvements.
4. The required improvements shall not be considered complete until a statement of substantial
completion by the Developers engineer along with the final project records have been furnished
to be reviewed and approved by the Development Services Director for compliance with the
Collier County Land Development Code.
5. The Development Services Director shall, within sixty (60) days of receipt of the statement of
substantial completion either: a) notify the Developer in writing of his preliminary approval of
OdDcuments and settingslpabutlerVocal settings \temporary internet
files tcontent.outlook\btjs7t4e\esbm_ app_ construction _and_maintenance_agreement_ for veronawalk _phase 4d.doc
16A 7
the improvements; or b) notify the Developer in writing of his refusal to approve
improvements, therewith specifying those conditions which the Developer must fulfill in order
to obtain the Director's approval of the improvements. However, in no event shall the
Development Services Director refuse preliminary approval of the improvements if they are in
fact constructed and submitted for approval in accordance with the requirements of this
Agreement.
6. The Developer shall maintain all required improvements for a minimum period of one year
after preliminary approval by the Development Services Director. After the one -year
maintenance period by the Developer has terminated, the Developer shall petition the
Development Services Director to inspect the required improvements. The Development
Services Director or his designee shall inspect the improvements and, if found to be still in
compliance with the Collier County Land Development Code as reflected by final approval by
the Board, the Board shall release the remaining 10% of the subdivision performance security.
The Developers' responsibility for maintenance of the required improvements shall continue
unless or until the Board accepts maintenance responsibility for and by the County.
7. Six months after the execution of this Agreement and once within every six months thereafter
the Developer may request the Development Services Director to reduce the dollar amount of
the subdivision performance security on the basis of work complete. Each request for a
reduction in the dollar amount of the subdivision performance security shall be accompanied by
a statement of substantial completion by the Developer's engineer together with the project
records necessary for review by the Development Services Director. The Development
Services Director may grant the request for a reduction in the amount of the subdivision
performance security for the improvements completed as of the date of the request.
8. In the event the Developer shall fail or neglect to fulfill their obligations under this Agreement,
upon certification of such failure, the County Administrator may call upon the subdivision
performance security to secure satisfactory completion, repair and maintenance of the required
improvements. The Board shall have the right to construct and maintain, or cause to be
constructed or maintained, pursuant to public advertisement and receipt and acceptance of bids,
the improvements required herein. The Developer, as principal under the subdivision
performance security, shall be liable to pay and to indemnify the Board upon completion of
such construction, the final total cost to the Board thereof, including, but not limited to,
engineering, legal and contingent costs, together with any damages, either direct or
consequential, which the Board may sustain on account of the failure of the Developer to fulfill
all of the provisions of this Agreement.
9. All of the terms, covenants and conditions herein contained are and shall be binding upon the
Developer and the respective successors and assigns of the Developer.
c:\documents and settings\pabutlerVocal settings \temporary internet
files \content.outiook\btjs7t4e \esbm_ app_ construction _and_maintenance_agreement for veronawalk_phase 4d.doc
16A
IN WITNESS WHEREOF, the Board an the Developer have caused this Agreement to be executed by
their duly authorized representatives this i2 day of t4gW 12011.
SIGNED
IN THE PRESENCE OF:
Witness
Printed or typed naltle
Witness]
A"�RicK 13"Cre -E2
Printed or typed name
ATTEST:
D IGHT )✓. BROC CLE
F
By:
Attist as to CM1
410iture oa,t 141
Approved as to form and Legal Sufficiency:
�. `
Assistant County Attorney
DiVosta Homes, LP
By:
Prin ame
fie}- -infirm Vice 1.4nej
BOARD OF COUNTY COMMISSIONERS
OF COLLIER C UNTY, FLORIDA
By: W .
Fred W. Coyle, Chairman