Agenda 09/11/2018 Item #16A1709/11/2018 EXECUTIVE SUMMARY Recommendation to approve a Temporary Construction Easement Agreement (Parcel 127TCE) necessary for the construction of the stormwater improvements in the Northwest Quadrant of Golden Gate City, Project No. 51029 (Fiscal Impact: Approximately $3,000) OBJECTIVE: To acquire a Temporary Construction Easement (TCE) needed for the stormwater improvements in the northwest quadrant of Golden Gate City (Project No. 51029) (the ”Project”). CONSIDERATIONS: Collier County wants to repair and replace existing underground drainage pipes and related drainage facilities in the northwest quadrant of Golden Gate City. The property owners, Mr. Jose A. Elizondo and Martha Elizondo, have executed a five-foot wide temporary construction easement which will provide the County’s contractor additional space to replace the existing drainage pipe located in a platted drainage and utility easement. The property owners are not seeking compensation for the conveyance of the easement; however, they do wish to be compensated for the loss of a mature Bismarckia Palm tree located within the area of the temporary construction easement. The property owners requested a guarantee from the County that the tree could be successfully relocated. Staff has been advised that no such guarantee can be given and that it would be preferable to compensate the property owners for the cost of transplanting the tree with the understanding that they will hire their own contractor to do so. The accompanying memo dated July 30, 2018 by Harry Henderson, Review Appraiser, estimates the cost of removing and replanting the tree elsewhere on the property to be $3,000. Accordingly, staff is recommending that the Board of County Commissioners (the “Board”) approve the accompanying Temporary Construction Easement Agreement that provides for compensation of $3,000 to the property owners and stipulates that the TCE will not be recorded in the public records. FISCAL IMPACT: Funds in the amount of $3,000 are available in the Golden Gate City Stormwater Improvement Project No. 51029, within the stormwater capital improvement fund 325. Source of funds is transfers from the General Fund (001) and Unincorporated Area General Fund (111). The stormwater system has previously been on the Road Maintenance Division’s maintenance schedule. Therefore, maintenance costs are unchanged. GROWTH MANAGEMENT IMPACT: The proposed construction projects are in accordance with the goals, objectives, and policies of all applicable sections of the Stormwater Management and the Conservation and Coastal Management elements of the Growth Management Plan. LEGAL CONSIDERATIONS: This item has been approved as to form and legality and requires a majority vote for Board approval . - ERP RECOMMENDATION: That the Board of County Commissioners performs the following: . Approves the Temporary Construction Easement Agreement and authorize the Chairman to execute same on behalf of the Board; . Accepts the conveyance of Parcel 127TCE; . Authorizes the payment of all costs and expenses that Collier County is required to pay under the terms of the Temporary Construction Easement Agreement at the time of closing; . Authorizes the County Manager, or his designee, to take the necessary measures to ensure the County’s performance in accordance with the terms and conditions of the Temporary Construction Easement Agreement; and . Authorizes any, and all, budget amendments that may be required to carry out the collective will of the Board. 16.A.17 Packet Pg. 448 09/11/2018 Prepared by: Sonja Stephenson, Property Acquisition Specialis t, Transportation Engineering Division, Growth Management Department ATTACHMENT(S) 1. Temporary Construction Easement Agreement (PDF) 2. 127TCE Memo (PDF) 3. Location Map (PDF) 16.A.17 Packet Pg. 449 09/11/2018 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.17 Doc ID: 6369 Item Summary: Recommendation to approve a Temporary Construction Easement Agreement (Parcel 127TCE) necessary for the construction of the stormwater improvements in the Northwest Quadrant of Golden Gate City, Project No. 51029 (Fiscal Impact: Approximately $3,000) Meeting Date: 09/11/2018 Prepared by: Title: Property Acquisition Specialist – Transportation Engineering Name: Sonja Stephenson 08/06/2018 1:44 PM Submitted by: Title: Division Director - Transportation Eng – Transportation Engineering Name: Jay Ahmad 08/06/2018 1:44 PM Approved By: Review: Capital Project Planning, Impact Fees, and Program Management Gary Putaansuu Additional Reviewer Completed 08/06/2018 1:50 PM Transportation Engineering Robert Bosch Additional Reviewer Completed 08/06/2018 3:06 PM Transportation Engineering Jay Ahmad Additional Reviewer Completed 08/07/2018 7:41 AM Growth Management Department Lisa Taylor Additional Reviewer Completed 08/07/2018 9:15 AM Growth Management Operations Support Christopher Johnson Additional Reviewer Completed 08/07/2018 11:16 AM Growth Management Department Gene Shue Additional Reviewer Completed 08/07/2018 5:08 PM Road Maintenance Travis Gossard Additional Reviewer Completed 08/09/2018 1:04 PM Growth Management Department Diane Lynch Level 1 Reviewer Completed 08/10/2018 12:39 PM Capital Project Planning, Impact Fees, and Program Management Amy Patterson Additional Reviewer Completed 08/10/2018 2:11 PM Growth Management Department Thaddeus Cohen Department Head Review Completed 08/13/2018 3:54 PM County Attorney's Office Emily Pepin Level 2 Attorney Review Completed 08/14/2018 9:58 AM Growth Management Department James C French Deputy Department Head Review Skipped 08/21/2018 9:58 AM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 08/21/2018 1:53 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 08/22/2018 1:08 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 08/24/2018 4:30 PM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 09/01/2018 9:08 AM 16.A.17 Packet Pg. 450 09/11/2018 Board of County Commissioners MaryJo Brock Meeting Pending 09/11/2018 9:00 AM 16.A.17 Packet Pg. 451 16.A.17.a Packet Pg. 452 Attachment: Temporary Construction Easement Agreement (6369 : 51029 - Parcel 127TCE) 16.A.17.a Packet Pg. 453 Attachment: Temporary Construction Easement Agreement (6369 : 51029 - Parcel 127TCE) 16.A.17.a Packet Pg. 454 Attachment: Temporary Construction Easement Agreement (6369 : 51029 - Parcel 127TCE) 16.A.17.a Packet Pg. 455 Attachment: Temporary Construction Easement Agreement (6369 : 51029 - Parcel 127TCE) 16.A.17.a Packet Pg. 456 Attachment: Temporary Construction Easement Agreement (6369 : 51029 - Parcel 127TCE) 16.A.17.a Packet Pg. 457 Attachment: Temporary Construction Easement Agreement (6369 : 51029 - Parcel 127TCE) TE/CM, Right-of-Way Office Phone: 239.213-5847 Fax: 213-5885 Memorandum To: Sonja Stephenson, Property Acquisition Specialist From: Harry Henderson, TE/CM Review Appraiser Date: July 30, 2018 Subject: Compensation Estimate; Parcel 127TCE Golden Gate City Stormwater Proj. A Temporary Construction Easement is being acquired across a section of the residential lot located at 2200 54th Street SW, Naples, FL 34116 (tax folio #36372640007). This is an improved lot (single-family home with residential site improvements/landscaping) owned by Jose and Martha Elizondo. The parent tract lot has an area of approximately 13,500sf; Parcel 127TCE is a 5ft wide strip located along the parent tract’s northerly boundary platted drainage easement. The TCE is for a period of 1 year. The TCE area will be graded and sodded after its use by our contractor and will be left in a state similar/equivalent to its current condition. The compensatory value for use of this TCE area is nominal. However, a large specimen Bismarckia Palm Tree (mature) is located within the TCE area which would be destroyed by our construction work within the TCE if not moved. Independent landscape specialists have estimated the value of this type specimen tree from $1,000-$5000 depending on size and age. The median cost estimate to remove and replant this tree elsewhere on this lot comes in at $3,000+-. As such, compensation in the amount of $3,000 has been offered to and accepted by the property owner for the transplant of this tree (to be undertaken by the property owner at his own risk, without warranty from Collier County that this transplant may fail). This compensation is judged to be justified and fair given the special circumstance outlined above. Harry Henderson, SRA Review Appraiser RD3475-FL 16.A.17.b Packet Pg. 458 Attachment: 127TCE Memo (6369 : 51029 - Parcel 127TCE) LOCATION MAP Golden Gate Stormwater Improvement Project 51029 Parcel 127TCE (Not to scale)          PLATTED 6’ EASEMENT PROPOSED 5’ TCE BISMARCKIA PALM TREE /  16.A.17.c Packet Pg. 459 Attachment: Location Map (6369 : 51029 - Parcel 127TCE)