Loading...
Agenda 12/14/2010 Item #16A 6 Agenda Item No. 16A6 December 14, 2010 Page 1 of 12 EXECUTIVE SUMMARY Recommendation to grant final approval of the roadway and drainage improvements for the final plat of City Gate Commerce Center, Phase One with the roadway and drainage improvements within "Tract R-2" being privately maintained, and "Tract R-1" being maintained by Collier County and authorizing the release of the maintenance security. OBJECTIVE: To grant final approval of the infrastructure improvements associated with that subdivision known as City Gate Commerce Center, Phase One, CONSIDERATIONS: 1. On September 14, 2006, the Land Development Services Department granted preliminary acceptance of the roadway and drainage improvements in City Gate Commerce Center, Phase One. 2. The roadway and drainage improvements will be maintained by the project's master property owners' association. 3. The required improvements have been constructed in accordance with the Land Development Code. The Land Development Services Department has inspected the improvements and is recommending final acceptance of the improvements. 4. A resolution for final acceptance has been prepared and approved by the County Attorney's Office. A copy of the document is attached. 5. This PUD has been found to be in substantial compliance. FISCAL IMPACT: The roadway and drainage improvements will be maintained by the project's homeowners association, The existing security in the amountpf $23,087.86 will be released upon Board approval. The original security ih the amount of $1,880,796.17 has been reduced to the current amount of $23,087.86 based on the previous work performed and completed. Maintenance for the County portion of City Gate Commerce Center, Phase One will come from the Transportation Services Operations and Maintenance budget. GROWTH MANAGEMENT IMPACT: There is no growth management impact. Agenda Item No. 16A6 December 14. 2010 Page 2 of 12 LEGAL CONSIDERATIONS: The County Attorney's Office has reviewed and approved the Resolution for legal sufficiency. This item is ready for Board consideration and approval. STW RECOMMENDATION: Grant final acceptance of the roadway and drainage improvements in City Gate Commerce Center, Phase One and release the maintenance security. 1. Authorize the Chairman to execute the attached resolution authorizing final acceptance. 2. Authorize the release of the maintenance security. PREPARED BY: John Houldsworth, Senior Site Plans Reviewer, Land Development Services/Engineering Review, Growth Management Division, Planning and Regulation ~ Attachments: 1 ) Location Map, 2) Bond Basis, 3) Resolution c_ Item Number: Item Summary: Meeting Date: Agenda Item No. 16A6 December 14, 2010 Page 3 of 12 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 16A6 Recommendation to grant final approval of the roadway and drainage improvements for the final plat of City Gate Commerce Center, Phase One with the roadway and drainage improvements within Tract R-2 being privately maintained, and Tract R-1 being maintained by Collier County and authorizing the release of the maintenance security. 12/14/20109:00:00 AM Prepared By John Houldsworth Community Development & Environmental Services Site Plans Reviewer, Senior Date Engineering & Environmental Services 11/9/20108:10:14AM Approved By Judy Puig Community Development & Environmental Services Operations Analyst Community Development & Environmental Services Date 11/9/201010:03 AM Approved By Nick Casalanguida Transportation Division Director - Transportation Planning Date Transportation Planning 11/10/26,108:34 AM Approved By Lauren Beard Transportation Planner Date Transportation Planning 11/10/20108:38 AM Approved By Steven Williams County Attorney Assistant County Attorney Date County Attorney 11/10/201010:23 AM Approved By William D. Lorenz, Jr., P.E. Community Development & Environmental Services Director - COES Engineering Services Date Engineering & Environmental Services 11/17/20109:59 AM Approved By Norm E. Feder, AICP Transportation Division Administrator - Transportation Date Transportation Administration 11/22/201010:00 AM Approved By Travis D. Gossard Transportation Division Superintedent. Roads & Bridges Date Transportation Road Maintenance 11/22/2010 4:11 PM Approved By John Vliet Director - Road Maintenance Date Agenda Item No. 16A6 December 14. 2010 Page 4 of 12 Transportation Division Transportation Road Maintenance 11/22/20104:30 PM Approved By OMS Coordinator Date County Manager's Office Office of M",nagernent & Budget 11/23/2010 1 :03 PM Appro\'ed By Jeff Kla!zkow County Attorney Date 12/1/20108:50 AM Approved By Therese Stanley Office of Management & Budget Manager - Operations Support ~ Trans Date Office of Management & Budget 12/'1/20103:59 PM Approved By Mark Isackson Management/Budget AnatY5t, Senior Date Office of Management & Budget Office of Management & Budget 12/2/20109:35 AM <DO'" <(~~ (O..Q........ . 0 I " . z Q) < ~ ~OJ Z 0 ~ E Q) '" .. wQ . Q).DCL !( ==E ... t:!< '" Q) .. , ",0 DO ; 0 c(]) .... -' ",0 ...'" c:> OJ " $ <( z .. , . " i , ~ 0 - " 0- N . <( i ~ i I.LJ (l.e '~':J) llllV~:Jll1OlI dTl::XJ t- - CJ) , . ~ ~ ; , W C C i;i . ~~ . iI ~ 2 .~ ~ ~ ~~ . ,~ . . . '~ . ~ ~ i l~ ! 5i~ . < 0 ~ ~ ! ~ ~ ~ III ~ I ~ ~ rn:n;Q11011 / I- a ! e ! I i. 5! 5! . " , ~l ~~~ ~ ~i . ~ ~ ~ ~ ~ e ~ 5. 5. . IJz ~ i... 031 . ~ . I~ ~ wQ .!;( " 0 00 [9 ! I ! ! 0- i. i, i. . <( " " ;! o i~ i ii:! ~ ii . lii ~ ~ d ~ II " u -""""'~ ~h z I....::. 0 ! ! . .. ........ - i i. II ~ . ~ ~ , nil- l . ~I I ~ ~3 '" - ~ ,3. I~ I I I Ir 3 II' u ~ 0 ! -I i!.~ . ;~ ...3;;1;.1; ~ " UI '~illl - ~ii I I N r ~ I lllfi......... -""""'~ -.- 1- " .; i&- Oni " .. ~. ( ) CllY GATE PHASE ONE COMMERCIAl ENGINEER'S COST ESTIMATE HM FILE NO. 1998147 ORIGINAL COST ESTIMATE JANUARY 2004 Agenda Item No. 16A6 December 14, 2010 Page 6 of 12 r:-~ :~~~ ~.::t~1:,;:,711-~- ---~~-_ ,__ -,- ~ ~ Descri lion Quanlit Units Unit Cost Total Paved Shoulder 279 SY $4.00 $1,116.00 3" As hall Paving - Ty e S III 19,407 SY $8.00 $155,256.00 8" Umerock Base 19,686 SY $6.20 $122,053.20 12" Slab~ized Subgrade 22,519 SY $2.00 $45,038.00 Ty e "A" Curb 2,772 LF $11.00 $30,492.00 T pe"F" Curb 5,710 LF $12.00 $68,520.00 6' Sidewalk (concrete) 5,175 LF $11.00 -? $56,925.00 S {fraffic Signs 15 EA $100.00 $1,500.00 Street Signs name) 3 EA $160.00 $480.00 9 Bulton Barricade Sign 12 EA $160.00 $1,920.00 24" Slop Bar, White (thermoplastic) 130 LF $5.00 $650.00 12" Crosswalk Striping, While (Ihermo laslic) 635 LF $2.50 ~ $1,587.50 6" Solid White Striping 940 LF $0.20 $188.00 4" Skip Striping white 880 LF $0.25 $220.00 Direclional Arrows/Markers 39 EA $75.00 $2,925.00 6" Ski White 4,298 LF $0.25 $1,074.50 Cui 0 CY $3.00 $0.00 Fill 28,780 CY $1.50 $43,170.00 Sill Fence 16,800 LF $1.25 $21,000.00 Seed and Mulch 7AO AC $1,350.00 $9,990.00 Sod - 2' Strip 5,700 LF $0.60 $3,420.00 Fire H dranl Markers 8 EA $5.00 $40.00 6" PVC Utility Conduits w/ 3M Markers 2,200 I.F $4.50 $9,900.00 Clearing 4.7 AC $2,830.00 $13,301.00 6" Double Yellow 1,600 I.F $0.50 $800.00 Gore SIi ing 246 I.F $1.50 $369.00 Subtotal Paving and Grading $591,935.20 ~~~~-E.:_ 7~~~-~-- .~-~~=-=-~-_~_-~~ Descti tion Quantit Units Unit Cost Tolal 19"x30" RCP 1,960 LF $34.60 $67,816.00 24"x38" RCP 55 LF $44.50 $2,447.50 24" RCP 1,230 LF $33.90 $41,697.00 30" RCP 765 LF $41.80 $31,977.00 36" RCP 325 LF $51.60 $16,770.00 42" RCP 285 LF $69.80 $19,893,00 48" RCP 160 I.F $79.90 $12,784.00 Junction Box 5 EA $2,650.00 $13,250.00 Mitered End 19" X 30" 2 EA $1,20000 $2,400.00 Calch Basin T pe "A" 22 EA $2,000.00 $44,000.00 SB - Box 4 EA $2,000.00 $8,000.00 H:I 19981199814 71SSIBond Reduction Spreadshcetsl041130 Cost to Complete.xls ~ ,. C) Agenda Item No. 16A6 December 14, 2010 Page 7 of 12 CITY GATE PHASE ONE COMMERCIAl ENGINEER'S COST ESTIMATE HM FILE NO. 1998147 ORIGINAl COST ESTIMATE JANUARY 2004 Junction Box 8' X 8' win 19 X 30) 5 EA $2,999.00 Construct Perimeter Beon 4,440 LF $8.00 $14,995.00 $35,520.00 Subtotal Drainage $311,549.50 "~~'- .._~,~ "~,-, - -- ~~.:..~: ~ ~ '-~~~.~" _.::.... -- ..--- ._- - - ~-- Oeseri tion Units Unit Cost Total 8" PVC Gravit Sewer 0-6* 1,632 LF $17 .20 $28,070.40 8" PVC Gravny Sewer 6-6* 267 LF $22.20 $5,927.40 8" PVC Grav' Sewer 8-10' LF $30.70 $0.00 8" PVC Gravity Sewer 10-12* 30 LF $41.00 $1,230.00 . = From Natural Ground Manhole 0-6 3 EA $2,052.00 . $6,156.00 Manhole 6-8 3 EA $2,432.00 $7,296.00 Manhole 8-10 1 EA $3,064.00 $3,064.00 Manhole 10-12 EA $3,768.00 $0.00 4" Force Main 555 LF $7.50 $4,162.50 Video Gravi Sewer 1,900 LF $1.20 $2,280.00 Video Gravil Sewer (1 Year) 1,900 LF $1.50 $2.850.00 Pum Station 1 LS $75,000.00 $75,000.00 8" PVC Force Main 240 LF $18.00 $4,320.00 6" PVC Lateral 595 LF $12.50 $7,437.50 Sewer Cleanouls 13 EA $150.00 $1,950.00 Tie To Existing Force Main Stub 1 LS $2,000.00 $2,000.00 " Plu Valve 1 EA $1,300.00 $1,300.00 'r Release Valve 2 EA $1,100.00 $2,200.00 Jenecl Existing Force Main 4 LS $1,200.00 $4,800.00 H:\1998\1998147ISSIBond Reduction Spreadsheetsl041130 Cost to Complete.xls " " (') Agenda Item No. 16A6 December 14, 2010 Page 8 of 12 CITY GATE PHASE ONE COMMERCiAl ENGINEER'S COST ESTIMATE HM FilE NO. 1998147 ORIGINAl COST ESTIMATE JANUARY 2004 Pum Station - PS #2 South 1 lS $80,000.00 $80,000.00 Subtotal Sewer Items $240,043.80 Oescri lion Quantil Units Unit Cost Total 3" ABC 1,118 SY $9.00 $10,062.00 8" Umerock 1,118 SY $7.00 $7,826.00 12" Subgrade 1,252 SY $2.50 $3,130.00 "A" Curb 96 IF $12.00 $1,152.00 "F" Curb 182 IF $14.00 $2,548.00 5' Sidewalk 32 IF $11.00 $352.00 6' Sidewalk 128 IF $12.00 $1,536.00 6" While stri 600 IF $025 $150.00 24" Sto bar 137 IF $5.00 $685.00 Site Prep 1 lS $3,000.00 $3,000.00 Subtotal Southern Right Turn Items $30,441.00 ~~"'J'r~'~---~----:'T'1 ~:.'I~'i::'''''J "=....tiL~~:,.. _ , " ~ ~ _A_._......""'..~_---.:..~>-_....... Descriplion Quanlit Units Unit Cost Total 3" ABC 1,261 SY $9.00 $11,349.00 8" limerock 1,261 SY $7.00 $8,827.00 12" Subgrade 1,412 SY $2.50 $3,530.00 "N Curb 113 IF $12.00 $1,356.00 "F" Curb 215 IF $14.00 $3,010.00 5' Sidewalk 34 IF $11.00 $374.00 6' Sidewalk 160 IF $12.00 $1,920.00 24" RCP 147 IF $35.00 $5,145.00 24" Mitered End 2 Ea $1,400.00 $2,800.00 6" White strip 518 IF $025 $129.50 24" St bar 122 IF $5.00 $610.00 Site Pre 1 lS $3,000.00 $3,000.00 Subtotal Northern Right Turn Items $42,050.50 "'-"-'1'-""~"."..T=------"- ~--.... .., l.Siill.r~:."'...[:..::-~~_._;,,~.!i.'l.{__ '__ ,___~ _ ~~ ~_ _~ _,.,: Descri lion Quantit Units Unit Cosl Tolal 3" ABC 720 SY $9.00 $6,480.00 8" limerock 720 SY $7.00 $5,040.00 12" Subgrade 800 SY $250 $2,000.00 "F" Curb 635 IF $14.00 $8,890.00 Turn Arrows 6 EA $75.00 $450.00 Site Pre 1 LS $3,000.00 $3,000.00 H:\ 1998\ 1998147\SS\Bond Reduction Spreadsheelsl041130 Cosllo Complete.xts () (') Agenda Item No. 16A6 December 14, 2010 Page 9 of 12 CITY GATE PHASE ONE COMMERCIAL ENGINEER'S COST ESTIMATE HM FILE NO. 1998147 ORIGiNAl COST ESTIMATE JANUARY 2004 Subtotal Northern left Turn Items $25,860.00 SlreelLighting 17 EA $3,500.00 $59.500.00 Selling PCP 1 LS $3,000.00 $3,000.00 Subtotal Infrastructure Items $160,851.50 ~}~~~2:_ ~ ~~_,-~-- ~-~~_-=-~~~~~~_==-_~~'~ Descriolioll Quantitv Units Unit Cost Total 535 LF $11.00 $5,885.00 310 LF $16.50 $5,115.00 1,390 LF $22.00 $30,580.00 16 EA $720.00 $11,520.00 2 EA $1.110.00 $2,220.00 2 EA $1,500.00 $3,000.00 8 EA $370.00 $2,960.00 4 EA $850.00 $3,400.00 1 EA $1,000.00 $1,000.00 1 LS $1,350.00 $1,350.00 11 EA $2,200.00 $24,200.00 2 EA $1,100.00 $2.200.00 $93,430.00 $1,554,377.00 $155,437.70 6" PVC C.900 Class 200 8" pve C.900 Class 200 16" PVC C.905 Class 200 6" Gale Valve 8" Gale Valve 16" Gale Valve Temp Bac-T Sample Point asp (Permanent) Blow-Otl Assembly Chlorinate & Test Fire Hydranl Assembly Air Release Valve Subtotal Water Items Total 10% H:\1998\1998147\SS\Bond Reduction Sprcadsheels\041130 Cosllo Complete.xls Agenda Item No. 16A6 December 14, 2010 Page 10 of 12 RESOLUTION NO. 10-_ A RESOLlITlON OF nm HOAIUJ OF COUNTY COMMISSIONERS OF COLLIER COUNTY, I'LORII)A AIJTIIORIZING FINAL ACCEPTANCE OF CERTAIN ROADWAY AND J)RAINAGE IMPHOVEMENTS IN CITY GATE COMMERCF: CENTEI~, PHASE ONE, ACCOIUJING TO Tim PLAT THEREOF RECORDED IN PLAT BOOK 41, PAGES 6 THROUGH 7; RELI~ASE OF TH~: MAIN'n;NANCE SECURITY; AND ACCI~PTANCE OF THE MAlNTENANCI~ RESPONSIBILITY FOR THE IWADW A Y AND DRAINAGE IMPIWVEMENTS THAT ARE NOT REQUIRED TO BE MAINTAINED Ill' TilE CITY GATE COMl\lERCE CENTER MASTER PROPERTYOWNERS' ASSOCIATION OR CITYGATE DEVELOPMENT, LLC. WHEREAS, the Bo"rd of Coullty Commissioners of Collier County, Florida, on February 24, 2004. approved ti,e pi", of City Gate Commerce Center, Phase One for recording; and ; WHEREAS, the Developer has constructed and maintained' the roadway and drainage improvements in accordance with the approved plans and specifications as required by the Land Development Code (Collier County Ordinance No, 04-41, as amcnded); and WHEREAS. the Developer is requesting linal acceptancc of the roadway and drainage improvcments and release of his maintenance security; and WHEREAS, the Land Devclopmcnt Scrvices Department has inspected the roadway and drainage irnpro\'elllcllls, and is recommending acceptance of said facilities, NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY COMMJSSIONERS OF COLLIER COUNTY, FLORIDA, that final acceptance is hereby granted ror those roadway and drainage improvements in City Gate Commerce Center, Phase One. pursuant to the plat thereof recorded in Plat Book 41, pages 6 througl, 7, and the Clerk is hereby authorizcd to rei case the maintenance security. Agenda Item No. 16A6 December 14, 2010 Page 11 of 12 1312 IT FURTHER RESOLVED AND ORDERED that the roadway and drainage improvements within Tract "R-2" (City Gate Boulevard North & portion of White Lake Boulevard as indieated on the recorded plat) will be maintained privately, and will not be the responsibility of Collier County, The roadway and drainage improvements within Tract "R-]" (portion of Whitc Lake Boulevard as indicated on the recorded plat) will be maintained by Collier COllnty as Public road right-of-way. This Resolution adopted after motion, seeond and majority vote favoring same, this day of ___,2010. DATE: ATTEST: DWIGHT E. BROCK, CLERK BOARD OF COUNTY COMMISSIONERS COLUER COUNTY, FLORIDA By: , Deputy Clerk f'RED W. COYLE, CHAIRMAN Approved as to form and legal sufficiency: Steven T. Williams Assistant Collier County Attorney ~:.::t,\b W N l~," ~ 3h;;'~ "J ~ "' ;f ~f:'~ ~ '" N :il ~ I;; j W ~ " n ~ , -, '" ~ ~ 0 z ;:... '" 0 ~i 9 ~ lLJ t' zs 08 " w~ V)O <('-J :c~ a..~ N '" ~I) ~~ lLJ'" 1-5 Zo "' lLJ~ u~ "' w~ us> cr>-i w~ ~g :ri "' 00 uiS w~ 1-2 <(i \..:)0 >-15 J-9 -z UQ II "' ;;: 6 OJ ::> "' '" ~I i~r , ~ 1 ~: oJ: F-<~ ,;,; g: f:L'i ' _J:;i"'::";{'~:;;'" , {OJ :'l~' ~~ : ~1 : ,;i'!i: ," ~."-~~_:'" " f ~ . c II , ;:~ . . :~; " _.' ,;' ;;, ~~ m k:.:'/,:;: ,'.',' ,;; , ':' N n ~ < rr?io ." pJ .. z " ir ~ " ::!;! " ~...:.~--~::~'~' ! '" ~ --:H~u ,..,......"'... ~ t_u ,j :t~ ~"V .'>t..".. ~ .J u cQ ~ -::> < (J... c C> " 1'1 0: -_.-')' · iff ;,"~''''M~': ,~~ ~~ '.i"tL-:r ._ ~~: i- .JL't\" - . "i~ .' CJpp,~\~N-n"~ - l~ jIo;Z",u~li') l..iH ;: "_ J _:.~_'r~I~~~ " -1---- ) II ~, u '" , " .., I,' \ : ."~ ~( "J)o' .~~ t"":'''' "' i"" ~," III l- 4 :> .~ d I:l- ",,,,-; "'" o , , , , : , -- ..",,-j.. ...;;r.~i<.1tii"T"+ '" ;., ~ " 7 ,-".' (r'~h-r l il .' ! l m)< ;,'! I .L~.aJll " , , !,,'" ,j" ..,"' .;. ';,r Agenda Item N o. 1GA6 Pa ,10 l;., flil~, 12 e~l.j t ~~llfd i ~v! .. ~ - '"~ I !S~ j:111 i -iZill ~~ I ., ~ , ,~ 'Ul :m I~ ;2.- i '0 ,x ,:; :~ ,0 Ig ~~ ~ ,~ " ,u ! " if , " '/:,1;; :,e ,. ~ . I.. ; :~~ ;;! ~ ~iM'.'t,' .'a..... ~ '..... 1 " ,"'-- , ' 0.. ,,( n..~; ~ -,,-,,- L> l'eSSI