Loading...
Agenda 10/12/2010 Item #16A 8 Agenda Item No, 16A8 October 12, 2010 p,'ge 1 of 58 EXECUTIVE SUMMARY Recommendation to approve Change Order No, 4 to Professional Service Agreement No. 03-3553 in the amount of $950,330.35 with CH2MHILL, Inc., for the design of Collier Boulevard Road Improvements from Davis Boulevard to Golden Gate Main Canal, combining this project with FDOT Davis Boulevard Improvements and Post Design Services, Projects No. 60001 and 60092. OBJECTIVE: To receive Board approval of the negotiated Change Order No.4 f()r Engineering and Permitting Services to be provided by CH2MHill, Inc., for capacity improvements to Coli ier Boulevard, Project No. 60001, CONSIDERATION: Change Order 4 provides for additional services to complete the design, peI1TIitting and carry the project into construction and to extcnd contract time from October 17, 20]0 to September 30. 2013 to allow for certification following completion of construction. Following is a history of the events that have led up to this change order: . On March 13, 2007 the BCC approved Change Order#2 to project 60001 for the design and permitting of Collier Blvd. from Davis Blvd, to the Golden Gate Main Canal. This change order was an addendum to the original agreement 03-3553. The approved amount was $995.500 of which $745.500.00 was lump sum for the design and pennitting and $250.000,00 in Time and Materials for Post Design Services. The notice to proceed (NTP) lor the commencement of design was April 2,2007 with a construction completion date of October 17,2010. . Change Orders Number 1 and 3 were no-cost change orders, Number 1 extended contract time and Number 3 reapportioncd the fees. . During the County's annual budget adjustments the Project was given a new Work Break Structure (WBS) and assigned a new project number of 60092 (aka Collier Blvd. Extension), The design contract is still carried under project 60001, . In December of 2008 it was Icamed that the developer for the "Abercia Development" that is adjacent to the west side of the project would not provide the commitments that were pat1 of an approved DCA (July 25,2(08), As pmi of the DCA the Developer had agreed to accept the stOITnwater runoff for 6.1 acres of the expanded roadway, It was fully expected that the developer's improvements would be ahead of the roadway construction. . As a result of the delay in the Developer's improvements: the roadway designs had to incorporate the design and pelmitting of the Developers Pond and outfall system. This change also affected the design completion schedule for the project. ~- /\genc;a Hem ND. 16A8 Octob'lr 12, 2010 Page :2 01 53 . On October IS, 2009 NTP was given to Agnoli Barher and Brundage (ABB) who was previously the developer's design consultant to provide the required design changes for the developer's Pond and to apply for a modification to the developer's pcnnit. Thc original design fee was S29,270.00 and a suhsequent contract modification of$] 8.705,00 was approved to allow ABB to apply for an FDOT drainage connection permit. . Two thirds of the project limits lie within the Florida Department of Transportation (FOOT) limited access right-of-way and as a result the design required several FOOT coordination and approvals, A major change in the design was needed as a result of not heing ahle to get a vertical height variance for the 1- 75 overpass, The redesign of the roadway cross section and drainage features as well as through the County's negotiations with the FDOT the variance was eventually granted. The variance was also needed to avoid relocating a major 48" Water main under 1-75, . Another major change in the design was the relocation of four (4) major utilities owned hy the Collicr County PUEO. These utilities included a 36" Water main, 3()" Raw water main, 20" Water main and a 12" Force main, These utilities had to he relocated to avoid conflict with the revised design and to meet the FDOT policy which does not allow utilities to remain in the pavement. . As part of the intersection improvements righl-ofway was needed from the BP Service station at the NW comer of SR84 and Collier Blvd owned by A L SUBS, Inc., ET AL. In an eminent domain proceeding held on July 31. 20()9 the Court ruled that the County needed to reanalyze the safety of the southbound trucks and cars simultaneously making the right-hand tUI11 at the NW comer of the intersection. The Court also ruled that the FDOT had to cC11ify that the rcvised improvements were safe. As a rcsult, the southbound right-turn lanes had to be lengthened and additional signing and marking were added to the design. As a result, additional coordination and pennitting was needed from the FOOT. . On Tuesday, July 27, 2010 the BCC approved a JPA amendment and Resolution (Agenda Item #16A20) with the FOOT and the County for the roadway construction and inspection services on SR 84 (Davis Blvd.) and CR951 (Collier Blvd.). The amended JPA extended the limits of the SR 84 project to include the intersection improvements at SR 84 [md CR 95] and continuing north to Magnolia Pond Drive, In the original JPA, the County is to fund constlUction and CEI services Illr SR84 (Radio Road to Collier Blvd), The FOOT agreed to reimhurse the County with scheduled payments up to a limit ofS20M dollars, Negotiations hegan on March 22, 20 I 0 and stalemated at the project level, so in order for the project to move forward into construction it was nccessary lilr a settlement to take place at the administrative level hy Nick Casalanguida, Deputy Administrator of Growth Management. The final scttlemcnt was rcached on Septemhcr 9,20 I O. item !\)c "h3PB O:tcber : 2 2010 P2ge :3 of 58 This Change Order provides for shop drawings review during construction for a lump sum amount of$25,269,80, 11 does not provide the timc and materials pOltion needed to address the needs of the construction project. The procedures for administering these services are currcntly being studied by a committee which will result in changes, These changes will be implemcnted in a future Change Order in the approximate amount of $125,000 to provide for the time and materials aspect of services during construction. FISCAL IMPACT: Funds in the amount of $950.330.35 are available within the Transportation Supported Gas Tax Fund and Road Impact Fee Funds. Source offunds are in gas tax and impact fees. GROWTH MANAGEMENT IMPACT: The project is currently identified on the Capital Improvement Plan as CIE 61 is consistent with the Gro'Nth Management Plan, RECOMMENDATION: That the Board of County Commissioners approve Change Order No.4 to Professional Services Agrecment No, 03-3553 with CH2MHill, Inc" in the amount of $950,330.35 for design and engineering services for roadway and capacity improvements to Collier Boulevard from US 41 to Main Golden Gate Canal, and authorize the Chainnan to execute the agreement on behalf ofthe County. Prepared by: Gary R. Putaansuu, Principal Project Manager, TEeM Attachments: (1) Change Order No, 4; (2) Change Order Checklist; (3) Backup Document - Fees; (4) Scope Item Number: Item Summary: Meeting Date: Aqenda Item No. 16A8 . October 12,2010 Page 4 of 58 COLLIER COUNTY BOARD OF:::OUNTY COMM!SS!ONERS 16AB Recommendation tG apPiQ'Je C,2.nge Oraer hJo. 4 to Professional Service ,~greement No 03~3553 III 1~~; <"moun! of s;nSO,::';30.35 with C~:2r,,'1HILL, Inc., for the deSign ot 80llier Bouiev('nd =<08(; Improvements from :)Bvis Bo~!evard to Golcen '33:e rv'I811l Canal, combining thiS projeC1 with FOOT Davis Boulevard Improvements and Post Design Services Projects I'Jo 60001 and 60092. 10/12/20109:00:00 AM Prepared By Gary PutaanSllU Transportation Division Project Manager, Principal Date Transportation Engineering & Construction Management 9{20J201D 12:54:01 Dr.' Approved By Norm E. Feder. AICP TransportAtion Division Administrator. Transportation Date Transj)onation Administration 9,/2012010 1 :07 PM Approved By Nick :':asaianguida Transportation ::Jivision Director. Transportation Planning Date Transportation Planninf:l 9i2CJ:201 (j 4 04 PM A pproved By :...isa T ay ior Transoortation :>ivisi'Jn Managemem/8udge"; h.nalyst Date Trwspart8t1op ~,dmif;is:rati:)n 9/29:20': 0 "i :::2 OM Approved By Stevc::':arneJ! AdministrativE. E;€'rvIC~,S Division Di~ec:tor, ::;'ur:ha~',ingiC"'0ner('l; Sf:rvic;e~' D2te D;;rc:,asnf & G:;:t;C;';i: Sr,;" :::(~S 9,,'30,'::)1[' [;:4L t,fi~ Approved By RhonoE' :umminrlS t\.dministrativE :;:,e~vi~es ::1I'iiSlc-n Contra::!;:: Sne::laiist Dale ::;'vrch2Sin[ &. Ci011'2ra; Servi~:es S:30,':'~'iO ~:1(1 t,M Approved By '~a:aii 8ctan:::w 1-ranSDo~ation :Yiviston Ic,am:nrsr,ati'/J;; ;'_55E~;t2r~~ D218 Trar!sportatlon F;.c,ac! f\/;,:iints:na!1~e- ::::2Ci201(:~: 10 Pflt Approved By :>MS C:oordrnatcF :::;Olinty !\!;anape.' s Office :Jate Office of lVia:12geme:.t & 5u~ige: '1 O!i/2~"j C f- Ar{ Approved By item r..j'J. ;:'i\p '.-1'-,,,, :'=Jc::cher ~2. 2JH) 5 of 58 Susan Usher f'Jianagem(':,-.jj8CJdge; A.naiyst. Senior :,c:t~ Jffl;:~; of Men2,gement & DfLse 0;' r\'ia;la~ls'::iC7:'. ~~; ~,UC~~let ," D/::;;'201 C! ': .~: PM ::,uciget Approved By f,';c;ri: ;sa::I'5~)I~ r.'iZ;:,2'~:;:;:;;':.'r.l;2u:j;'c: ~:"~\'cc:. ~;~'lli,y ..:",t;: 8m;:e 0; Nia.,2gemsn: g OfficE' of Man8gement &. Budget 10/5:20103:06 PM Budget Approved By Jeff I'~ iatzi;ow COUr1ty Attorney D&te 10/6/20104:26 PM /:\qenda ltem !\lo. '16A8 '.- OCtUb0H" i 2. 2010 6 of 58 Change Order 4, Contract 03.3553. Project 60001 Description of Changes: The scope of this project has been influenced greatly by outside factors, The developer that was suppose to provide stonnwater treatment and did not move forward as was intended added to the desilo'll and pennitting services of the project. The FDOT decided to move forward with an interim 1-75 ramp modification project which required design changes that could not have been anticipated at the time the original scope was developed. Right of way acquisition and signal desilo'll at the Collier Boulevard/Davis Boulevard Intersection hecame much more involved than was originally expected requiting several iterations of design modifications. Following is a history of the events leading up to this change order: . On March 13,2007 the BCC approved Change Order#2 to project 60001 for the desif,'ll and pennitting of Collier Blvd, from Davis Blvd, to the Golden Gate Main Canal. This change order was an addendum to the original agreement 03-3553,The approved amount was $995,500 of which $745,500,00 was lump sum for the desilo'll and pennitting and $250,000,00 in Time and Materials for Post Desilo'll Services, The notice to proceed (NTP) for the commencement of desif,'ll was April 2. 2007 with a construction completion date of October 17, 2010. . During the County's annual budget adjustments the Project was given a new Work Break Structure (WBS) and assilo'lled a new project number of 60092(aka Collier Blvd, Extension). . In December of 2008 it was learned that the developer for the "Abercia Development'. that is adjacent to the west side of the project would not provide the commitments that were part of an approved DCA (July 25, 2008), As part of the DCA the Developer had agreed to accept the stormwater runoff for 6.1 acres of the expanded roadway. It was fully expected that the developer's improvements would be ahead of the roadway construction, . As a result of the delay in the Developer's improvements; the roadway designs had to incorporate the desif,'ll and pennitting of the Developers Pond and outfall system. This change also affected the desib'll completion schedule for the project. . On October 15,2009 NTP was given to Agnoli Barber and Brundage (ABB) who was previously the developer's design consullant to provide the required design changes for the developer's Pond and to apply for a modification to the developer's permit. The original design fee was $29.270,00 and a subsequent contract moditication of$lR,705,OO was approved to allow ABB to. apply for an FDOT drainage connection permit. . Two thirds of the pro.ject limits lie within the Florida Department of Transportation (FDOT) limited access right-of-way and as a result the desib'TI required several rDOT coordination and approvals. A major change in the design was needed as a result of not being able to get a vertical height variance for the 1-75 overpass. The rcdesibTf1 of the roadway cross section and drainage features as well as through Mr. Feder's negotiations with the FDOT the variance was eventually b"'anted, The variance was also. needed to avoid relocating a major 4R" Watermain under I- 75, . Another major change in the desiblTl was thc relocation of four (4) major utilities owned by the Collier County PUED, These utilities included a 36" Watermain. 30" Raw watermain. 2()" 'A-.'atermain and a 12"' Forcemain. These utilities had to be relocated to avoid conflict with the revised desib:rn and to meet the FDOT policy \vhich does not allow utilities to remain in the pavement. !t.;)rr: t\b. ';Sl\e :_~;::;LbGr i 2, :20; (1 "( of ~)8 . As part of the intersection improvements right-ofv.'ay was needed from the BP Service station at the NW comer of SR84 and Collier B]vd owned hy A L SUBS, Ine.. ET At. In an eminent domain proceeding held on Ju]y 3],2009 the Court ruled that the County needed to reanalyze the safety of the southbound trucks and cars simultaneousl)' making the right-hand turn at the N\\l comer of the intersection, The Court also ruled that the FOOT had to certify that the revised improvements were safe. As a result the southhound right-turn lanes had to be lengthened and additional signing and marking were added to the dcsib.l11. As a result additional coordination and pemlitting was necded from the FOOT. . After several months of requesting a fee proposal ti'om CH2MHill to capture and address the various scope creep items \A!ith no response; the consultant was asked to cease all work on the project until a fee proposal for all out of scope work can he negotiated, On March 22. 2010 a change order proposal was received, The amount requested was $693,946,24: however, after the numbers were checked an error was discovered and the actual amount was found to be $736,532,62, . This change order #4 was reviewed and a response was prepared to address the items and charges that were being requested hy the Consultant and to schedule <l negotiations conference (see attached for staff comparative response report), . On May 19, 20] 0 at 9:00 a,m, staff (Rhonda Cummings- contract specialist: Gary Putaansuu- Principal Prnject Manager: and Mar]ene Messam - Sr. Project Manager) met with CH2MHill stafJ(Bill Gramer, Frank Scerhn and Tim Sharp) to begin negotiations, . The County's initial counter otTer for all changes was $164,345,73 and was hased on a lump sum contracting method as the original agreement. The Consultant's proposal \vas based on a time and materials method; and. the meeting: terminated with only three of the tasks reaching resolution. They were tasks 4a, Sa. and 6 ror a combined total of S;] l)].3 73.3 I. . It was explained hy the Consultant that some of the tasks resulting in a change of scope were requested by the Transportation Planning Department c<lrly in the design phase oftlle project. Subsequently the Consultant requested a postponement of the negotiation proceedings to have discussions with Transportation Planning to confirm the charges met \vith their approval. . On Tuesday, July 27,2010 the BeC approved a JPA mnendment and Resolution (Agenda lIem #] flA20) \vith the FDOT and the Count:y.' for the roadv.'3)' construction and inspection services on SR g4 (Davis B]vd,) and CR95] (Collier B]vd.). The amended .IrA extended the limits of the SR k4 project to include the intersection improvements at SR k4 and CR 951 and continuing north to Magnolia Pond Drive. In the original JP^. the County is to fund construction zl11d eEl services j(lr SRS4 (Radio Road to Collier Blvd), The [-"DOT a~"'eed to reimhurse the County with scheduled payments up to. a ]imil or S20\1 dollars. . At a meeting on Thursday, Septembcr 2. 20] 0, Mr, Nnrman feder, Nick Casalanguida and Gary Putaansuu and I discussed the resolution of Change Order #4. It vv'as decided that to move the project forward Nick would spear head the next negotiation proceedings with CH2MHil1. Also discussed \vas the need to maintain separate accounting: for the Jr A reimhursements. It was decided thaI the construction documents 1'01' Collier Blnt would he split \vithin the limits covered hy the JPA. As a consequence this additional \\'ork was added to Change Order #4. Aoenda item !'>Jo. 161\8 , October ~12, 2010 Page 8 of 58 . On September 9,2010 at 9:04a,m, CH2MHill emailed a revised Cbange Order # 4 proposal requesting a total fee of $1.239,940.41. Additional tasks were added to tbe proposal for consideration, Tbese tasks included tbe construction plans separation and the desib'll of a sib'llal at Noah's Way which was anticipated but not included in the original agreement. Also included were additional services required to address FOOT's comments on permits, and plan revisions to coordinate with Developers Project at City Gate North and at the Ahcrcia Development. . On September 9,2010 staff met with CH2MHilL In attendance were Nick Casalanguida, Gary Putaansuu and Marlene Messam from the County and Bill Gramer aud Alan Bolinger of CH2MHill, At the end of the negotiations the final fee agreed to was $1,051,897.72 ($791,726.48 in lump sum and $260, I 7J.24 as time and material), CH2MlIill was also directed to cease all work on the project until the change order is approved by the BCe. . Subsequent to this above meeting on September 15, 2010 staff received the revised Change Order scope and fee from CH2MHill and there were concems about the structure of the change order and the amount that was set up in time and materials. Staff wanted to have more control over the expenditures and requested that lump sum amounts be given to all tasks and sub tasks except Test 17a - Expert Witness - Deposition, It was a6'feed by stan' and C1I2MlIill that Task 16a is composed of several subtasks resulting from the review comments from FOOT, It is slaffs intent to request FDOT allow that some of these tasks be eliminated, . As a result on final scope and fee was a6'feed to on September 20, 20 I 0 resulting in the Change Order amount of $950,330,35 of which $12,250,24 is time and materials and $938,080. 11 is lump sum. . This Change Order provides for shop drawings review during construction for a lump sum amount of $25.269,80, It does not provide the time and materials portion needed to address the needs of the construction project. The procedures for administcring these services are cUITcntly being studied by a committec which will result in changes. These changes will be implemented in a future Change Order in the approximate amount of $125,000 to provide for the time and materials aspect of services during construction. The probable cost of this project is $18,5 million, The total cost of desi6'll for Collier Boulevard irom Davis Boulevard to East Golden Gate Canal with approval of this change order will be $1,945,830,35 which is 1 O.52(~';) of the cost of cc.mstruction. 111 comparison the cost of construction for Collier Boulevard from US-41 to Davis Boulevard was $24 million and the cost of design was $2,264,000 for 9.41 '1., of the cost of construction, Though the cost of desi6'll of this section has nearly doubled due to the complexities encountered during design, the overall cost is still within reason. ii~::.m t.~Oo CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM , -. /0,(, 1 Gl..8 12.2010 58 :::';:.tCJh~' PROJ=.CT NAME: Collier Boulevard. US41 to Main Golden Gate Canal PROJECT MANAGER; Gary PUlaansuu PROJECT #; 60001 CONTRACT #: 03-3653 MOD #; 4 PO#: 4500099957 WORK ORDER #; DEPARTW:EIH; TE&CM :::ONTRACTOR/t=IRM NAM::: CH2MHiII Original Contract Amount: S 2.264,000.00 (Starting Point) I Current sce Approved Amount: $ 3.269,500,00 (Last T ota[ Amount Approved by the BCC) Current Contract Amount: $ 3 25950000 (Including All Changes Prior To This Modification) Change Amount: $ 950,330,35 Revised ContractlWork Order Amount: $ 4.209,630.35 (Including This Change Order) Cumulative Dollar Value of Changes to this ContractfWork Order: $ 1,945,630.35 Date of Last BCe Approval ,- ..., . 1.-:. ,~ Jbl. .IT ;~~_. Agenda Item # 16B .~ Percentage of the change over/under current contract amount_~~% Formula: (Revised Amount.' Last BCe approved amount). 1 CURRENT COMPLETION DATE (5); ORIGINAL: February 24 2009 CURRENT; September 30 2013 This change order will: 0 Add new Tasks for $ 950.330.35 U increase Task Number by $ Other Describe the change(s); See Attached Chanae Order Descriotion Specify the re'2S0ns for the change(sl ~' 1. Planned or Elective (' 2. Unforeseen ConcHtions r 3. Quantity Adjustments ("' 4. Correction of Errors (Plans, Specifications or Scope of Work) I{ 5. Value Added (' G, Schedui6 Adjustments Note: One or more may be checl:ed, depending on the nature oflhe change(s). identify all negative impacts to the p;oje~t if this change order were not processed: sianed sealed set of contract olans for advertisement. This change \\'a5 requested by: rl:ontra:tor/Consu!~ant ir Owner x Using Department C CDES Vve would not receive a L.Design Professional riRegu~atory Agency (Spe:ity) r Other (S pecify) COIHRACT SPECIALIST PARTICIPATIOII! IN N"GOTlA TiONS; x Vce No This form is to be signed and date-d... j ,/ .// A~PKOV=D BY: _:>-.::::;;~/~ Pnnclpal Proje-:::t Manager Date: 9'-.1(;_/4 P.EVi:=VV:::D BY' , J3te Cor,ti""8ct Specia:lst Revised 4.1 () Agenda item ~~o. 16/\8 October 12, 2010 Page 10 of 58 CHANGE ORDER CHANGE ORDER NO, 4 CONTRACT NO. 03-1553 , ''-/ ."' ",..' ,.1 .,"", "", ,. . Bee Date, Sl,..'. 'v. _J,O --"-'. t Ag"nda Item _1.01( -;;. 71 2LE4 TO: CH2M Hill 5801 p.<;lican Bay. Suite 505 NavIes. FL 34108 DATE: 9-20-]010 PROJECT NAME: Collier Boulevard. US-41 to D"vis Blvd PROJECT NO.: 60DOJ Under our AGREEMENT ihted .J ())'I ;;"7, f 20rY-f You hereby are aULhoriL;t~J dud dilccted to make the foI1owing chan.gc.(s) in acc.ordal1cc with terms ilOd conditions of the Agreement: (See attached Attachment "A") . FOR THE Additive Sum of: _Nine hundred ~nd lifty th()u;ar..d, Tr,.ree, hundrc:d lhirt}' dolklrs 8Tld thirty five cents ($ 950.330,35 ), Original Agreement Amount s 2.~6J,OOOOO Sum of Previous Changes ~ 995.500.DO Tnis Change Order add s ('50._~30.j5 Present Agreement Amount s 4,209.~3{L35 The time for compktlOn sh,dl be increased hy _L979 calendar days due to lhis Change Order. Accordingly, the Contract Time is now _3.3].:.'; . calendar days. Th(: substantial completion date lS _5_m~~IJber :<'0.1013 and tbe ;:.na! completicm .rime l.~ ~entemner ~O.:2013 Y(~ur 2cce,pt,mce of this Change Order shall ccms;:itute a modiEc~ilion to OUi' Ab,.'Teement and will be perforrne.d subject to all the same terms and condltions as ~ontained :n our A.[S"eemenl mdi:':,i.ted abuve. DS LIllY d,', if the S<ll1l:"~ were I e,)catt:d in this acceptance. T11t: adjustment. if an}', to the Agreement sr.<.flll constitute a fuil and final settlcm;m of any and all ;lalITls of tbe Contractor sri sing {JUt of or rela:sJ to the chJ.nge sC. forth herein. including dair-D.s for impact and del.ay co~;ts, Accepted: .].()~ OWNER: CONTRACTOR, CH2MHill BOARD OF COUNTY COMMISSIONERS OF COLLJER COUNTY, FLORIDA By: "..-.--- By: Alan BoIlinser ~ \ ,p, OpcratioT.J:s Nl2:L- Cas<JlangUlda, Deputy AdJ11ini.str'dtDr C:fowth Miinage:Ytent Di'dsion By: Norn:anE. Fcdc~" AJCl;~~d;;~inistrato;. CirCl\vth lVlanage:11ent Division D~ll:;~: ATTEST: :}",'l~ht E. Broc:L C"!:o:-l: BY: f\rprovcd As 'j 1 1 nrrn :1:ld Lef.!3J SufJl;;;:.:ncy: Print N~Ul1e: ___________~_____'__._ Assistant Counry Attorney 1~0_rr1 i'.!C ~)' L._ .i:' (ij !~'T'j'.\.'T :;P~C'l\.Ll-,,;r ---~'---~-'~"---'___""c-___' LiH_:;I~b BOARD OF COU,,'TY COMMTSSIONFRS OF C(ll.UH( CUUNTY j''L(JRIDi\ :~Y: Fred '\A.,', Cnyle. Chairman p,oenda item 1".]0, 16A8 - October 12. 2010 12 of 58 Change Order 4, Contract 04-3553, Project 60001 Description of Changes: The sc.ope of this project nas been inllucnccd greatly by outside factors. The developer that was suppose to provide stormwutcr treatment and did not move forward as \vas intended added to the design and permitting services of tile project. The FDOT decided to.move forward with an interim ]-75 ramp modification project which required design changes that could not have been anticipated at the time the original scope was developed. Right of way acquisition and signal design at the Collier Boulevard/Davis Boulevard Intersecrion became much more involved than was originally expected requiring several iterations of design modifications. following is a history of the events leading up to thi::; change order: . On March 13, 2007 the BCC approved Change Order#2 to project 60001 for the design and permining of Collier Blvd. from Davis Blvd. 10 the Golden Gate f\1ain Canal. This change order \vas an addendum to the original agreement 04-3553.The approved aITlount ,vas $995.500 of which $745,500,00 was lump sum for the design and pennitting and $250,000,00 in Time and Materials for Post Desi.!:-l11 Services. The notice to proceed (NTP) for the comlm:ncement of design was April 2, 2007 \vith a construction completion date of October 17,2010. . During the County.s annual budget adjustments the Project was given a new \Vork Break Structure (WBS) and assigned a new project number of 60092(aka Collier Blvd, Extension). . In December of 200S it was learned that the developer for the "Abercia Development" that is adjacent to the west side aUhe project would not provide the commitments that \""ere part of an approved DCA (July 25. 200S), As part of the DCA the Developer had agreed to accept the storm\\'ater runoff for 6.] acres oftbe expanded roadv;ay. It was fully expected that the developer's ir::lprovements Ivvould be ahead of the roadw]:' construction. . As a r2~~u!1 of the delay in the Developer's improvements: the road\vay dC3igllS had TO incorporate the design and pennitting oflhe Developers Pond and outfall system. This change alse, affected the design completion schedule for the project. . On October!.5. 2UU9 ~TP w~~s given to Agnoli Barber and BruIldagE.~ (AB8) \\'ho was previl..iusly the d~veloper's design consultant to provide the required design changes for the de\'cloper's Pond ~~ild to apply Cor a modification tn the devtlop;:r's permit. Ti-le original Jesign i'::-,e \\'(1:'" $29.27U.uO and a suhsequent cOl1traC:lmodification tIC$lf;,70:S.00 \-vas approved to 21110\\ ABB to apply for an PDOT diainage connection pennil. . Two thirds, oftlle project limits lie within :i1c ~]orida Department nCf,anspOna1ioll (FDOT) limited access right-of-\vay and as <l result the- design required several rDOT coordination and approvals. A m~i(lr change in the design \\'a." needed as a n.:'sull of not being able to gel a venical height variance for the [-75 overpas:;. The re-design ofrhe road\vay CHl:i:; ;)CC1JO!l and drainage fC3tures as \vell a~, through Mr. Feuer's ;legotiations wit]l the FDOT the variance was eventually granted. The variance \vas aiso needed to avoid r(:loc.ming, 3 major 48" Viarermain under 1-75< II /\notber major <.:hange in tlll: design \Va::,; the rdocation of four (4) major utilities mvm:d by the Coliier County PLiED. Th~sc militie.s included J 36" V/arermain, 30'. R~l\'" w:.:m:~rmiliJL 20.' \Vakrrnain and 81:2'< Furcernain. These utiliri~s had to be relocated to 3V\lid conflict with the ievised design and to meet the rDOT policy which does not 21]]01,.\" utilities tel r~maill in tbe pavement. Item 1\10. :6A8 Oct:Jhe: 12, 2010 Page 13 of 58 . A~ part of the intersection imrro\'em~Jlts right-of\-\'ay was needed from the BP Service station at the N\V corn::r of SRS4 and Collier Blvd OVl'llt.'U hy A L St~BS, Inc., ET :\.L. in an eminent domain proceeding held on July 3 L 2000 the Court ruled tl1m the County needed to reanalyze the s:.n'cty or the southbound trucks and cars ;;imu]taneously making the righr~hand turn a: the N\V corner of1he intersection. The Court 31."0 ruled that the FDOl had 10 cenify that the revised improvements v..'E're safe. As 3 result, the southhound righI-turn lanes had 10 be lengthened and additional signing and marking were added to the design. As (\ result additional coordination and pcrmining 'vas needed from tbt FUOT. . After severa] months of requesting a fee proposal from Cll::i'v1Hill to capture and address the variou:; scope creep items 'with no ft'sponse: the consultant was asked to cease all vlOrk on the project until a fee proposal for all out of scope work can be negotiated. On March 22. 2010 a change order proposal ViliS received. The amount requested was $693,946.24: hO\veveL after the numbers were checked an error W33 discovered and the actual amount was found to be $736.532.62. . This change order #5 was revie\\'ed and .J re-spome 'vas prepared to address the items and charges that were heing requested hy the Consultant and to schedule;) negotiations conference (see attached for staff comparative response report), . Un May j 9.201 0 a~ tl:OO a.m. 5t3tf (Rho;lda Cummings- contracl specialist: CJary PutaanSllU- Prin~'ipal Pro.icct :-vhmager: and !v1arlene lIvIessam -- Sr. Pro.iecl I'v1anagcrJ met with CH2rvlHill staff (Bill Gramer, Frank Scerho J.nd Tim Shar;l) to h~'gin negotiations. . rhe C()unt~'.s initial counter offer for <111 changes was };1()4.345.73 and \\'a5 based on (j lump sum contracting rnethod as lht, original agr(:,~1llel1t. The Consultant's proposJ~ was lnsec O:l 2time and J112.terizlIs mcth0d: ~l11d. the: rnccrin;' lcnTlinatcd w1:11:\11]: lhrec of the ta~ks n:achinf:! rcsuluTioTl. They were tasks .:.J-a. Sa. and 6 for a combined tural nf S: Q].3 73 .31. . It ''''3S e::flhiiiled by the Consul:am that ;-",)!11t' o(lh~' L~sb r('sult111~ ill <J change ofscop:: were r;::,::w~sted b~ the T;-'J1EpOnmion Pl:":Jilli:lf' D(';~ml!ii~'n: ~'J.:'l: i11111;:; d::si~n phas~> ofth:: project. Sub:)cqucn:l;' th:.: Consultant requested;; P('S1POf]1'11jC111 {i1th::.' negotiation proceedings 10 hav:: di.'i2'Jssinns \\'iIh Tr:mspo,-Uli.icn PI<~l1njn~' IiI L:D,l[~:-!n tl1;.' ;:.'iur~~s m~'t ''>'IIh ti1('ir :l~l~rO\:I!. . (Ill Tuesday, Jui:' :::7. =(I~ U U:l" F)CC J.lJprovcd u .J[J/; amcr,dm'~11l and R~soiUlion (Agenda 1t<.'Tn :-! ~ 6/\201 \',i~.i; th~' FlY," ::\11(: :h'~' Cd11Il;.\ i('I'I;l:'" (c::::ttU'.-::iOL and ins;.K'cizl)l ."::'.:T\'lce,s 011 SR g..+ (Davi:~ Blvd. j z:nc: CR951 (((dlie,' B!\cl.l. TJ-.~' amen,kd JPA (;x1t'llded the lill]il" oflhe SR ,'-)...'. DFJ.i::.:ct L', jnc.1ujL:'lh,~' jm(.'r~;'~';:.'tinn innrClVC;ll(.'m:; ~]: ~R i,oj :tIlJ cr\ 0) I arid c()ntlnui:~~', nDnh In ~vhl~noliJ 1\1llC: urivL'. in 1il~ i.lr:gilui ,JP/". lhv ("uun,) is To fUlld cUlblruc,iun ~l1iJ CTj ~';:'rvic::s fur SRR4 (Radio Road tp C(llji~r DJ\.d I. The FD(Yl :L,:rc.?.,:i 1(' :'~'irnbur"c :h',: ('(Iimr)' with SCll,;,'dul.::d p~l:TnCJl!" ur h' :1 limiT 0: ~:20\i doiiur::. . ,\1 ;__: l1l:.:cling ern Tntlr.~jay. :~cpTcmh.~'r'::::, :::();U. \'lr. l<o:T1l~m Ft~j'-:r. '\ick CasiJklilgujd~l and Cia:-) !)ut::<ansuv and I db,-:Ll~:,ed tile r;:-su!uI!U!l o~ .'kmgc (l~<.L.T ;!S. 11 \v:.~:-. cic:.:id~d th;-:l 1(1 move the p;'oicct !-()I.\\~mj!\icL wiJu]d 3j1c<..ir h;:ac Ull' 11;:\1 pi'll:::~t'(iings with CH2;vlHil!. A!so ci~"cus::;~:cl v,::~ lh~ need !(' mUlrna:r: 'i:;;'~l;Y:-Jl~' "ccount for th:' .!Pi'. n.;,jr;ihur'icJl1~lll:;'. 11 \\:--!S (J..;'cidcj ~I;J~ ~:k' CUIl'ir:--U~',;!lli d:-)Clll1l(T~" i'or ~_-();ji'.':' Bkd. WOUld bi." .. .' " ' . \\'l,T1IIi U}: l!l,nt;; (:(wcrcu \1:> :i1:..' .IP/L /'.> ,1 C~Hh:':'\lll(:Tl'~'::: 1;11'-, :lCLL':nna: horii '\,1' :jjcl:..'d ie' Ch,Jl;L:~ C)rd::,y A.;;enda l1em No. ! 6t\8 October 12. 2010 F)age '14 of 53 . On September 9, 20]0 at 9:04a,m, CH2MHill emailed a revised Change Order # 5 proposal requesting a total fee of $1.239,940.4], Addi\ionaltasks were added to the proposal for consideration. These tasks included the construction plans separation and the design of a signal at Noab's v..;ay v..'hich '\va: anticipated but not inciuded in the original agreement. Also included were additional services required to address FDOT's comments on permits, and plan revision.'> to coordinate with Developers Project at City Gate North and at the Abercia Development. . On September 9,20]0 staff met with CH2MHill. In attendance were Nick Casalanguida, Gary Putaansuu and Marlene Messam from the County and Bill Gramer and Alan Bolinger of CH2MHi]1. Althe end of the negotiations the final fee agreed to was $1.051.897,72 ($791.726.48 in lump sum and $260,171.24 as time and materia]), CH2MHil1 was also directed to cease all work on the project umilthe change order is approved by the BCC, . Subsequent to this above meeting on September 15,20 I 0 staff received the revised Change Order scope and fee from CH2MHill and there were concerns about the structure of the change order and the amount that was set Lip in time and materials. Staffyvantcd to have more control over the expenditures and requested that lump sum amounts be given to all ta<.;ks and sub tasks except Test 17a - Expert Witness - Deposition, It was agreed hy staff and CH2MHill that 'I ask ] 6a is composed of several subtasks resulting from the review comments from FDOT. It is staff's intent to reguest FDOT allow that some of these tasks be eliminated. . As a result on final scope and fee \vas agreed to on September 20,2010 resulting in the Change Order amount of$950,330.35 of which $12.250.24 is time and materials and $938,080.11 is lump sum. . This Change Order provides for shop drawings revie\v during construcTion for a Jump sum amount of$25.269.80. It docs not provide the time and materials portion needed to address thl: needs of the construction project. The procedures 1l:l[ administering these s.ervices are cUrTcnt]y being studied by a committee which will result in changes. These changes will be implemented in a future Change Order in the apprOXil11~lte amoLlnt ofS125,000 to provide for the time and materials aspect of services during construction. The probable cost ofthis project is $] 8.5 million. The total cost of design for Collier Boulevard from Davis Boulevard to East Golden Gate Canal \vith approval of this change order \\'ill be $1,945.830.35 which is 10.520;';) of the cost of constructioli. In comparison the cust of c::Instruction for Coliier Boulevard from US-41 TO Davis Boulevard was $24 million and the :051 of dcsit=n v.as S2.26-i.OOO fOT 4,41 t>;) of the cost of construction. Though the cost of design of this section has nearly doubled due to the complexities encoumered during design, li1e Clverall C()SI is sUI \\ithin reason. i\y::md? :tem ~Jo. G.L\8 CJ::180ei' 12 201 0 15 of 58 ATTACHMENT A SCOI 'E OF StI\VICES FOR CHANGE ORDER NO, 4 TO CONSULTING ENGlJ-";EERING SERVICES AGREEMENT FOR COLLIER BOULEVARD (C.R 951) SOUTH EXTENSION (Davis Boulevard to Main GDlden Gate Canal) PROfFeT NO, 6000l October 6, 20111 The CONSULTANT has been requested and retained to provide additional engineering services associated ",vith final design and cOlllpletion of construction of the Collier f)oulevard South Extension Project (Davis Boulevard to I\'1ain Golden Cate Canal). These additional services are based on various design revisions and SCl1pC: of ..vork additions requested by the Collier County Grcrvvth r\Ianagenlent Division Transportation Engineering Department to address the changing needs and conditions along the project corridor cmd tp conform to adjacent de\'t~l<lrment a~;rpenlents. In addition, S011le of the additional services arc required to malch "r\s-Huil,'. conditions of surrounding projects and resolve surrounding lJropcrh' i~:;lH-'S. j"hese services aft:' nc'ccssary to resnlvc projC"=t stai<ehold'2f is.'-aJ(-"S r,Col]j(T C:nunty'rranspm"tation Dcparh:n.C'nt Collier County Solid ''Vastv f1q:l'-lrLllv-:-nt Collier =:~)llntv Uhlir\, D('pclrtlTicnt, fDCYf, 1'1-1\\'/\, 2~\\'J\:'n-"'-B(-:~B, .i\bcrcia Dev:::]u;.-lment, (:i~\' Cd:.t' Dcvclnpm'~'llt), iJnd fini:dize Ul(' pn1jecf permiU..ing clnd cL.'sinl. c, Ch,l.'lgt~ Dl'der :\Jc~. 4 pn/\'idl.'s for the C\)\;SL:I,'1 .'\f'~'!U~; scn:ict.,;-, tn hf' ll1lldifi",d tn cHId l11.';: .JILw-.'ing Dc::,:ipl. s<'u}"c' ::)f ':';:>l'\'ic';~:, :l:' Collier C(~l.lr:::\ :\0. bOUT!. Th',' f('llowing CONS1)TT AT\J'T S,~-'rv]ces dE' int iJ<.idition to th~' llriginal contract: 8. FDOT Design and Permitting Requiremen~s: The' fonCJwing tasks are required as a resuft of FOOT comments mode and requirements stated during the FDOT review of the Coilier Boulevard Project Plans. The Additiona! ScrviC2S that arc required and i'l/iil be provided by the Engineer to obtain approvals and permits included the fol/owing: a.. T:rpicaI S(':ctior~ R~~visillns a.nd Compld'2 Project Plans Redesi~n - Pos~ hOIl/;, Plans due loFDOT Comm>2nt and Approvals - SlYt-;.254.4-4 Agenda Itern No. 16.L\8 October 12.. 2010 Page 16 of 58 Attachment A Change Order No.4 Collier Boulevard (SR/CR 9511 Davis Blvd (SR 84) to Main Golden Gate Canal Project No. 6000 I . Prior to 30% submittal, a coordination meeting vvith FDOT District 1 District Interstate Review Committee (DIRC) was held in Bartow tD review the proposed design for this project. As part of tl1C discussion at this Ineeting, the design exceptions for vertical clearance and longitudinal grade along the curb and gutter were addressed. Initial comment from the FDOT indicated tl1at although a design variance would need to be submitted for both, due to the excessivE' cost of revising tll.(.~ existing condition, approval "\vould be recommended. . Design Variance 1 dealt with the fact tllat the existing vertical clearance under the 1-75 Bridge is currently substandard (16'-3" vs. 16' -6") and the propDsed clearance would be at 16' -1" . Variances for vertical clearances under 1-75 were previously granted by FDOT to Collier County for other projects, so hased on the excessive costs to raned)' the situation, approval for this project should not have been delayed or denied especially since resulting clearance was greater than the 16'-0" minimum. . HOV\Tever, based on discussions with FDOT after submittal of the design variation, the potential for approval of the design variances did not appear to he forthcoming. . After discussions with TECM it was agreed that CH2M HILL should redesign the plans to len-ver the profile at the 1-75 Bridge to provide 16' _Sf{ of under-clearance in urder to obtain FDOT concurrence \viU1 the desit,'T1 in a tirrlely IIlanner and preserve the project schedule. . Design Variance 2 was to due to the fact that the exi,c;bng profile of roadway, would not provide the required minimum longitudinal grade when the typical section \vas modified from a rural section to an urban section. Curb and gutter was considered in the initial design for consislen-:-y since ~xdtlsion in U-:i~ project ''''mIld have resulLed in a 0.75 mile gap in the curb through the 14 (nilt' corridor. In addition, it contained the Clramagc runpH and provided a mean;,: for rdi;,::~d sidewalk along- tho;:: corridor. . To modify tllE' longitudirial slope in areas that did not meet staJ:ldards ,\-'QuId require complete!v nee-profiling the roadvvay during cpnstruction at a cost in excess of 521\1 (> 10% of tllt~ overall estinlated project construction cost). .' Hc)"\'vever, based on discussions with FDOT after submittal of the design ~,'ariabon! the poh::ntial for approval 0: tlle design 'variances did no{ app'2ar to be forthcOlning. . After discussions V\lith TECl\i1 Des!b'l:, it was decided that CH.2.1\1 }-IlLL should revise the road\^.'ilY typical section from urban to t,cencJa itern !"~o. -j 6,i\8 '::J:lObsl ~12. 2010 Page 17 of 58 :'\ttachmcnt A Change Order No.4 Collier Boulevard (SRlCR 95 i) Davis Blvd (SR S41 to .\1oin Gulden Gate Canol Project ~,;O. 60001 suhurban and to redesisrn the plans in. order to obtain FDOT concurrence vv"ith the design in a timely manner and preserve the projeC"t schedule. . The change in typical section tron1 urban to suburban \\Till require CI-I2h,1 HILL to modify the Drclinage Design along Collier Buulevard and to revise and expand the Basins to aCCOffilTIoda te the revised roadway design. Drainagt' areas will change, drainage modeling \",ill change, calculatiDIls \\rill change and Permit~ will need to be revised. . The project's original scope of work and 60 % Design assu111ed that due to tl1l' excessive costs of making the required modifications to the existing condition, the FDOT \,vould appro,,'!::' the Design Variances requested since similar variances were approved on previous projects. ,l\ Iso during the initial coordination meeting with the FTKyr, they indicated that approval would not be an issue. CH2M HiLL proceeded \,"ith design based on that understanding. Therefore this task is considered Additional Services . S~-~r\'ic:cs requirEc'd to finalizf~ the plans, specifications and estimates include: NUIlwrous Conceptual Design Alternatives, Complete ROi:1ch...'ay l\l~-l )esii.;n - Post 60',\, Plans (Typical St,"ction Package, Typical Sections, Plan and Profile, Cross Sections, Sjr;njng and I\1arking, \'10T, T.Jtility Plans, Quantibcs); Drainage Design; Drainage Calculations, and /\bercia Development and Collier Boulevard Pcnnit modifications. b. Preparation of a FDoT Interchange Analysis and Operations Report (IAoR) and I'vlethodology Letter of Understanding (MLoU) - 523,735.54 . /\.t tlH.~ coordination meeting withFDOT ;::nu ITTV\" A at tht' 30S;, dr~sigll submittal, HK)'J' indicated that <l I\lLUL: dnd l/\OE would rlP'2d in be prt'pan'd a.nd aprr(1\'f'cl h\' hoth FDOT and FH\V:\ 'TillS would be' !'L'quin'J 1(' ',-"Ilsun-> ~h(jt U-It~ planned irnprC1v'~':-Tl('nb in tllt' FDOT Li1nitcd .,'\cccs_s I\O\V ''''(ltdd confc-rm to tlw existing r;-':lllhg,t:-ati:1li u~ tlH.:.' lnt~~n::hd~1~),( '-:s vvdl ,-l~ Lht:, ::nOT //{ut'.ue" planned !!npro\-'cmcnt:-; to tIll' hltcrch;-mgc. The FDCY[" "\,vantt':d th:::' County':,; Consultant to prcpart' both docunlt:::lts. The County a.greed tc, have' CH2~\1 HILL F'l"'c"PJ.l"C th.;- dll'~'tllYl'~~:"itS. . The FrCli,::,;.::'~'s urifrml1 scopr:-- uf \'\'()rk could nCl1 hd\'Ej ..mlicipaled this J:r~OT r~'qu~5t for :,'_'fviccs o::.n::; thu~ did not include tllC above tdsks. Tlwrdnrc thi~ t2.sk is C(l1lSilh~~'(o(! _.:\dditi(1na] S,-::':rvice~ . ~:';'.;'n.'L,.~.,> rcquin:'d (( flECllize' illli..i, (lbteJIlI Ull' FDc.__rr I'cnnit lnclucl'2: i\l'.:-:'f.'tings. D3""L<! C2Ul'~T]llg. C~ol3(l]jl,:.ti{m v,-jth F'I<n ConsuJtrJnts \\'-or!:ing en InL::'fc)1<:1nge Plannint:: Tasks. Interchan;;~' PerrOrmdllc!..' Aaenda item ~io. 16A8 ~ October 12,2010 Page 18 of 58 Attachment A Change Order No, 4 Collier Boulevard (SRlCR 951) Davis Blvd (SR 84) to Main Golden Gate Canal Project No, 6000 I Analysis, Traffic Modeling, 5ynchro .I,nalysis and Report (2) Preparation, c. Additional FDOT Permitting Requirements (Permits) - $31,858.31 . The design and permitting of the Collier Boulevard Project requires extensive effort with respect to coordination with FDOT and FHWA, For Approval, the FDOT has required that, in addition to the Drainage Connection Permit required for discharging stormvvater into the FDOT ROW, CH2M HILL will be required to submit the following three (3) separate Permits: o Driveway Connection Permit with Plans o Utilities Permlt with Plans o Signalization/Signing and Marking/Lighting Permit with Plans . The project's original scope of "\vork did not anticipate having to prepare and submit three (0) additional (Drainage Connection Permit was assumed) Permits for the above mentioned portions of work Based on previous experience working on projects within PDOT ROW, it was assumed that cupies of the applicable plans would be submitt,'d to FDOT for therr files upon completion of design. Therefore this task is considered Additional Services . ServIces required to finalize and ohtain the FDOT Permits include Coordination, l\leetings, Project Pliln Changes, and Preparation of thn~p (~) Additional FCffilH Pdcka~~l's. 9. Match to "As-Built" Conditions of Existing and Concurrent Projects: The project plans are developed on information availoble at the stort of the design process. Due to continued growth and development many site conditions on surrounding County ,=DOT ond/or developer projects change during the design per iod which reouires redesign e/forts. These changes generally require additional coordination, design survey.. design analysis and revisions to the construction pian documents. Additional Services that are required and will be provided by the Engineer include the following: a. Conceptual Alternatives and Revisions to N\r\T Corner of l,eck/CoIlier Intersection - 533,30656 .. I)ue to ROV\/' Acquisition cunccrns from the adja:ent property CHvner, Coll1f'r County requested that CH2I\1 HILL prepare various alternatives for th1:.':' NVV corner of thf' Davis Boulevard - Collier ,il,cwnda Hem 1\10, '16,1\8 - OClOber' 12 2010 F>ar-J8 1 q of 58 Attachment A Change Order >;>0, 4 Collier Boulev:J.rd iSR/CR (51) Davis Blvd (SR 8~) to Main Golden Gate Canal Project No, WOO I Boulevard Intersection and evaluate the RO\V requirem.cnt'i of each a.lternativL' . Numerous concepts will be prepared and from them, three (3) Dual Right Turn Lanes alternatives ,,,,'ill be designed using various size desir;n vd,icles (WB-50, WB .62 l'tC.), The ROW impacts of each of the alternatives will be c\'aluated. . The alternatives will also need to consider the FDOT - Davis Boulevard Widening Project (being designed by TY Lin) Lo evaluate and provide sufficient ROVv' for the Intersection Signalization, . The changes being lllaJe by TY-Lin to this int~rscction and how it will be constructed require numerous changes to the plans to account for design changesl sig'nallocation changes and maintenancp of traffic (MOT) phasll1g revisions. . The project's original scope of work could not have anticipated the property' l1wner contesting the nlinimal RO'V Acquisition at the ('unler and thl' latc' changes to the TY Lin Roachvay, Signal and 'r-\'1ajntl~nanC(' of Traffic (2 tinles) Desit,'TJl dnd thus did. not include the above tdsks. Therefore this task is cnnsidercd Additional Services . Services required to finalize the plans, specifications and estimates inclucte: Slte visits, Conceptual Alternatives (3); Roadv\~ay Design rL.''\'isions (Plan and Prufilc); Urilinagc- Design revisions, Sketch iJ.~Hj Descriptio:::s and ROIV !\,Iap Revisions; Coordinalion 'A/lth T'l' Linl Si'!l1a{ I'ldIlRe\'jc\\' J'vIUT PblL revIsions u b. Utility Drive/J\;1~lgnulia Fond Drive Intersection Inlprovernents- S22,716.23 . rht' ori[.;inaI .c.,~ '.1Fl-' l-'( ,...'()rk Wi):': f':'vist2d dUI'ing oP';,', Design to d;...:'sigl": the lTtibh' nrj~,'l'/ i\L:q.';Ilolicl Pond Jlri\'e Int:erscc:-ion ?s a Signaliz~~d lnterst'ction. v\'lth C()lli(~r BouleYdrd as opposed lo directional lefts. Collier Cuunty I--'L.,lnning rL'questcd this dut> to tht' COU:lty being CkL-l.\,:,,'d irl securing LHi. i,1srccmcnt with aI', dcijJc.'C'iYt dC\ct.::lop:..'f (City C;at'e) kn ,: portilm l1f "Vndc' lklllJl''\-,Hd (prih1h' rn~1d) to be t,<1nsfern-'d to the' CO'Jnr:' in Jddihon, cL:-lngl's dssncl<Jted "vith the- (I~jd~'ed cC1n<;trucrion ('I r--~()ah',s \Vav !"y the :\bcrcia Dev121crper ;,:!sCl c,mtribut'..d tC' ~h(' ll\.'('d l.ur d Signal r\'~Sih11 an~i intcrsectinn revisions aL the Ublit}, Drivc/lvIa.:.-:nolid I\lnJ Dri\';~} Jnlerscctiun, \lultiple cmc'~'pts f(lJ' L__--:.ne ('oniii;'ura:ioc" nn Collier 13h'd. ,-1S 'oV,dl JS on Udlit\, Dr. \','<c'TC dc\'clc1p,:'d. . /\tl':T Jj,"-,cussicwt.; v,iU.. TEC~d r)('sih'T:, Phr'.llint; ~;:1d TrZlHi,.::, it was d(;t~~Tnin'2d thai thts v::.ltdd 1,,,- incl'..lded in ~_h(' p~'ol~cL bid plans as a Aaenda Item No. 16A8 ~ October 12, 20'10 Page 20 of 58 Attachment A Change Order No.4 Collier Boulevard (SRlCR 951) Da\'is Blvd (SR 84) to Main Golden Gate Canal Project No, 60001 signalized intersection \-\lith Collier Boulevard with minimum lane assignments to economically accommodate the interim condition of having a signal (temporary) at this intersection as opposed to where the permanent "future" Signal will be at the City Gate Dl;ve/Noah's VVay Intersection. . The medians of Collier Boulevard will be designed to accommodate the signalized intersection in the interim condition while providing for the future reconfiguration of the intersections to Collier Boulevard directional lefts ""7ith minimum throw 3vvay costs. . The project's original scope of work could not have anticipated the various alternatives and conditions that needed to be prepared and accommodated due to the changing developer agreements and plans (caused mostly be economic conditions), Thus the scope did not include tile above tasks, Therefore, this task is considered Additional Services . Services required to finalize the plans, specifications and estimates include preparation of multiple Conceptual Design Alternatives and c\ialuatlon of tTaffic operations, Once an alternative is approved: RDadway Desis'1l (Typical Section, Plan and Profile, Cross Sections, Signing and Marking, Signalization, Quantities). c. Design Changes resulting from Abercia Development - $37,386.89 The Abercia Devt'Iopment Agn~enlent ,-\'ith the County has had a 111d.jUf in1pact on the desiST1) of the Collier Boule-vard pro}ect dUE~ to site development changes, changes to rv:1a~olia Pond Drive and Noah's lVay t~vpical section, alignn1ent and lane configurations, as well as U1C fact that a S16rnificant portiun of tht, W(;~st side RO\;\' and Drain.:lge Treatment and Att~~nuation requircrnents of this project arc directh~ tied to the .Abcrcia d(;'velopment. There \vere rrtanv changes to th.E' agreement including postrlonemenl of developm,,-~nt ((JTlstruction V\'hich occurred latE: in design (post 60',:,(, Phase) that ."vill rcquin.. significunt design changes. These iterIlS include: . Drainage conveyance system redesign for implE~rnplltation of a Joint Lise Pond \\'it.~ the Abercia development. The original design that ,vas at~recd to by tlw :'\.bercia Developer and Collier County shc)\\'cd. the C,-)llierBoulevard Drainage System tying into their parking area catch basins, This slorn\'vvater would then be transferred tel the pond via their inknla] conveyance svstem. Due tel internal site conveyance cClnsn-aints, thE' Developer reguested that tIle-" County install t..~eir own >2,400 LF "trunk line" pipe to convey the stormwater to tht~ agreed to Joint 'Use Pond. The County agreed h! this lTIodificahon and CII2J\.1 il:'";:, f';]. ~:6/\8 C::-.<'(:~'.i;'":: 2D10 r)~ c: 5::; Attaclnnenl A Chc:mgc Order i\o. 4 Coilier Boulevard {SR/CR (!511 Davis Blvd ~ SR :;';4) to .\Lin G:,)ldcn Catc Cm:::] Pr()jc~'l ~o. 6000 J HILI", 'iYllT be rt'i..HlircJ to rcdeslzn t:h:~ (1nsjt~ drair,dre s\'sl~m dnd . ~, ~, COI1VC'\'JIlCC'. . !\ludifications to the J\.lasnulia Pond 1)r1v(:' and ~Joah's 'Yay lntcrscchon:.; will he required due to :\bercia. Site Plan shifting locations in the coordinate svstcm. CH2I\J I-lILL noted the l:~rr()r in the Abcrcia Sltt' nan <lTh_J buth Dt,''\'ciDjl('r o.nd C~}I2rvr HILL will be required to nlOdify their design plans. . County Planning Dq)artmenl requested tl1at C:U2M HILL prepare conceptual design tlltf.'rnalivl's (a 3-Iane ,md 4-Jane rOdd\.vay) to realign l\1agno!in I'ond Drive ttl accoTI1:.nodate initial roachva,r/ site planning as wl'll as future T()(l(h\'ay/ site rlanning to minimize unnecessarv initial costs and fuhlrE' tbnn''''-,l\\'<--lY costs when UlL' signalized int(';"s('ction ''''"IS l'v~"ntua]Jy moved t() the City Cate \Jorth/,\]oah's \V,TV jl1ters~'cti()n, . PrC'paration of dOCUI1H'ntatil\ll uf df'lin;~gl:' ,--:alcul3,tions for inclusion intn the /\lJl'n..~ia Permit submittal h) SF\VTvTD and revisions to Collier Blvd Pennit dUl' h~ the changc'd .^~bcrcia Pern,it submittal, . I\e\:lsioll.'- in the pdclwav <1J1\:.1 berm lrCdhll'.:.'nt hetween i\Iagnoiicj P\lnd Ih'ivc and Ntldh's \'\'(1\ I(l dG,-\IUUlodatl' th(;' Abefcia UC\"l.'l(\}'cl-'s f.,"qucst in tJrdt~r ie' m,1\:i1l~jzL' tl1L'ir sil'~' parkin~~ 'i\i-tllout a H'-(I:.'sign un Ult.\lI' pM! \\,jll(:h l~(J'...ljd hd\,t~' J.iI'~'ct(..:d th~::ir l",isting ,1~~Tt'i..'r;lcnt \.yith tllc~r cumml.'l\~i,~l dicl':,t. .. l)rr'ri;1rd~i\ln (ll ((In("~'p:~uai Ci,Tl\'('Ydncc' S~\'~;ti.-'l1ll Trea,nH'nl Pond ['J',::.'SigT:, ~\l<liti C(ddt'n (.-.~,lt~' Calla] LJitch i~Tl;..rc)\.--',:'nH:'nts for 1\1:; ~'t:ngs ~lnd C (lcm..il;'h,;,i::mv,lth ~:'\\[\,;~) ~ hT'!,a:".;;tiori ,}] i:liticll" ',(1]1\;1,',',]11('\' ~\ ')h_~m Clnd pond lksign JLH,' hJ :J I~ .. ',; ).~, t',- i,', . J'. \ '_'j, '1 ,_':- p' ((\'"i.,<rLl,;'UC:-1 {j ;h,~> ('. \~ )::E'!^ '-. ,".1:1;\ !( 1; :::::;i.I" ~<'J:.::;tnictinn (\f tit'" /\hc'rci,' p:"'}jhl :::1h_; (IU::;,;, 1T\ Ull'I:- . i ::~-' ...! ';','.' ( \\\,)"1 ,'\''-lL liul ]-:;:1\", dJicicir1dh-'J ::~;c cll:::nl~\'S l"l,Ij" ,::hangl'-" tn U:.'~~ !\berc:a D,~\\,'C'lcpme;-Lt gF-". ;T\'5j~ \'\';tl: 1- D:11'.'r Ceu:-.'" (lLd ~J-:l1S di(~ riot include' the dlll1',re t::Sl<~:; :1\.';-' l1:~. :,~sL ::. ',1;i. ~:l::~L'F :..:'-\\..:~:ir;~1J1<l] S~T..ii.:"'s. )'j,,-c,-,"':' '~',)L"- .\1: j;,! l~'/'S F.lllH'skd i::H1:::,d~ir.. benci'itL_,-! Cul1j'_'f (\llJn!y <~,c, i.',ut of L:l':' '\.l"~'rcI.1 '\gn:"'.;.'!11ent. .. S"'f,,:j.,","e :i' ;:n;1.::7!.' f;'". \"i, ;i'-Cllionc; alll! ",>timil:- '::' ,.... ['-:,J;::j :.\ 1~: c. \\' ,l \. ".!t\_'lTlclt:l",:.'" ;,y' \ "1l::':;::(;;, ',: ~, 'L. "_ u: \.\::)\ : ~y ~~ ~i :)Ii., ; ):ll' ;:::;-1-1 " :;, 'I:';\-".'';l' ':1.<" f\98nda Item ~,jo. 1 CAS October 12. 2010 P298 22 0' 58 Attachment A Change Order No, 4 Collier Boulevard (SR/CR 951) Davis l3Ivd (SR g4) to Main Golden Gate Canal Pro.ject No., 60001 Drainage Design and Conveyance Systenl Changes; Signalizution Design" Permit modifications; Surve~v, ROVv' Sketch and Descriptions and I\lap revisions, d. City Gate Blvd. NfNoah's Way Intersection Improvements - 519,826.66 . The original scope of work \\'as re~,isl'd during 60% Design to design the City Gate Blvd, North/Noah's Way Intersection as a Directional Left lntcrsl~ction \vith Collier Boulevard as opposed to a signalized intersection, Collier County Planning requested this due to the County being delayed in securing an agreement vvith an adjacent devdoper (City Gatc) for a portion of \\11ite Boulevard (private road) to be transferred tn the County. In additionl ch,mges associated V\rith the delayed construction of .\Joah's vVay by the Aberda Developer also contributed to the need for directional lefts from Collier Boulevard NB and SB,I\1ultiple concepts for lane configurations on City Gate Boulevard North ;:lnd Noah's IVay were developed. . After discussions \vith TEC.rv1 Design, Plarming and Traffic, it was determined tha [ tl tis vv'QuId be included ill the project bid plans as a directional left inLersecticll\vith Collier Boulevard with ula,jmunl typical sections built (but initially striped out) to cconCJmically aCCOffilTIodate the interim condition of hzrving directional lefts (f.::'lnpUl"dry) at this intcrst'ction as opposed to the pennant-:nl "futun:" 5i;11d1. . The mcdidm; of Collier BOUlevard wil! be designed fur initial dircctiona1lcfts tlal v,'ouId acconlInodatf' a si~;nali2l'(1 int~rst'ction ,,\'tWIt I: is l\:~('(mfi~~,ured in tile fU1ure with n1inl:nl:D1 thn1\^'" a\VJV ce,sts, The foundtltlcms Jor the futurcsisnalizcd int'.::-rsC'chcms \,\'ill be' dcsif-:,'TH.'d and h\,-~dtcd to ,:;vuid constn1Ctiur: i:,;sucs and utilihr conflicts in UK ;,Jtur,' \'\'l'~'r:, tlH j;)un-:l<;-;:-i:J:l::; ,,_,-,d ,,:^C in::;tilIL'..:l. . nl~' <.; O)";f)lli::l SC\:.l} )(, ',l[ ",:u1'1, cuu:d nut hJ.\'t' ;::ntitjp~ltt.G. Lilt, vc:riDus a]tcrnaLi\\~~ and conditions that \\'il1net'd to be prcpGred and <:Kcommod;-li:C:'d alE: tu ~h[' c1-janging de\'~~Iup[:'r ugE)'2m('nts and plans (causel': I11{.stiy h.:- CCOTlOn1\C' c()nJitio:1S)_ 'r:~l!S thE': sn1p~' did not ~llcludt' the aOC'\"E:: tasks. nj(~rcfore, this LEiSk is cCIlsidcred :\dditi()na] :;crVI~:["S. . SC'fvices requin:'C; te finalizl' tJl';: pLil1S, spccifi:?:tic-'Tls dnd cstimat'~s incIude pn'pan1b()1' of m:l1tip]'._' Cunc'~)Ftual D;;sign .'\1t\:;rni1tlV(~2i und ~'\'dluation ')1 traffic ()l'(:r(-~bons. Onc,,-~ an alr'-.:;IT,~lti\,".' is imFnlv~d: K;)dd\\"<:l',' . - ~~!>crion, fidn i\nd ("~r()~,'~ SeCQ{);lS, Signing and Ivlc:rjdng. CO[h:'~'pt: Sig'"1iaE:ta'cion. L\C1811da item No, 16AS ~ Oct:mer 12, 2010 Page 23 of 58 Attachment A Change Order No, 4 Collier Boulcsard (SR/CR 051) Davl, Blvd (SR 841 to Main Golden Gatc Canal Pmject No. (,OO()] e. Evaluation of Existing 48" Water Main under I-i5 - $5,993.56 . The proposed widening design of Collier Boulevard under the 1-75 structure ,,,,,'ill result in a portion of the existing 48" \'Vater }"Iain being located under the proposed left turn lane from Collier Blvd 5B to 1-75 5B. SUE was perf0n11CU to verify the depth of the line, . Upon investigation of the existing utility It was found that the depth of the 48" water mam along Collier Blvd 5B under the 1-75 Bridge was shallower than shown on the As-Built plans obtained at the County Utilities offices, Instead of 48" of cover shown on the As-Built plans, U1CfC 'vas only 36" of ({lVCr (per SUE Investigation) in some locations, This meant that the proposed widenin[; would result in a 100 ft section of the pipe having a lllini111Um depth of cover of less than 36". . After meetings with Collier County staff, a revised design (Design Change No.1) was prepan'd which showed that the 48" pipe could fClTIZlin in place with lOll' of the pipe locJted under the left turn lane trom Collier Blvd SB to 1-75 5B. This lO(] ft section of pipe had a minimulll depth of lUVi;:'r of ,':14.5" to 36". County rUED initially agr('(~d to the sulutiun and it \VdS prc-senteLl to the FDOT. . As a stipulation oj their approvaL lhe FDOT required profile and cn~ss slope cha.ngt>s i{) thE-' cnllcppt (Dt'sign Change No.2) to eHrrdnate tJl~' existing !clW point from bctlVPf'n the 1-75 NB dnd 513 structures, .. The rcJ!;~~jgn was curnplcteJ drill appn)\'ed h\' FDOI', hm.vever, Cd1icf Count\.' peED indicz:ted that the cover and loca.tion ('If the 100' of i-lip\' \vas not .1Cl.'~'l't<1hlc and would requ;rc it 10 ht~ relcK.'ated. . Due to th'o:.' '2~,:ccssi\;Ct. cost nf n::lPcal1ng the existing .J8" \Vatcrline, the lTKJT agT"'l>l~ tCI ,; r('du..::h(~:l ()f i-}E' pnlPd"vd len,e;tll of hlfn lane (so th::' c):tsbng .:Job" \\dt'cr main \vcndd not bl::' under the turn lane and also a~;T::>vd to dcccpt d lIt_'sign \ arianCE' f~1r Ule Colli'~r Dlvd SB lTJ;:;dv"',,n'. This required a third r.~-'desi~~n of the roach-va)' under 1-75 (DesiSl1 Ch.-:.ngc >..'0, 3). . 'I'he ?r::)i~'ci.' s original scope of v.:ork could not hav~~ dnticipated the iSSllt'~: ,~ssociated v,'ith v:~t,'nding the k,lt turn lane an(1 the rC';'.llting sub-standar(~ Cllvef on the l~xlsbng .Jt," \\:'dt'~)r :main since Il() utility inv:::sbgaliul1,,, v,'er::' done bernI".-' th,,:~ .'--,\ opt' \\',1S develurwc; ;:lnd thus did not include thl' a.lxn.'l.' :;::sks Th::retofc, this tasl..;, is considered \~Llitional S'.:';'vi<.cs ti S:~'rvic~'s r'.:.'Cluin,J to rin3lizc and obL:dn the FDCiT Pcrnlit.s include Cil()j'jmd::-iC);l, J\ll't:hngs. F'il'Jd !n\'(~stigations, lHillty ?1-LJ rVlodeling ,'l,;lenja lien. r~o, -ICil\'3 CJc:::Jber" i ~~ :2Cl0 2~1 Of 58 Attachment A Change Order No, 4 Co!iicr Boulevard (SRlCR 951) Davi, Blvd (SR 84; to Main Golden Gate Canal Proie.ct No, 6000 I Cost Estiutates. and Roadway GC'ometr~y Changes (Typical Sc'ction, Profile, Cross Slope) and Eoadway Plan Changes (Design I, IJcsign 2r Design 3) 10. Collier County Requested Improvements for Future Development: Due to continued growth and development, many site conditions on surrounding County FOOT and/or developer projects change during the design period which requires redesign efforts. This is required in order to make the projects compatible ond avoid future throw-away construction by incorporating the changes at a later date, These changes generally require additional coordination, design survey, design analysis and revisions to the construction plan documents. Additional Services that are required and will be provided by the Engineer include the foilowing: a. Beck Blvd Realignment and Addition of Right Turn Lane - 530,440.33 . Rased on tl1e ROW restrictions of Davis Boulevard, the Davis Boulevard lane geometry was revised by the FDOT Consultant TY Lin to renlalll within the existing RO'y\.' and an eastbound !Tee-11m\' "nnnp" ""vas designeJ behind the cOlnmerciaJ COTI1cr parcel. /\s a result, Collier County requested that the alignment of Beck Boulevard be redesigned to better align 1vith the fi"vised configuration of Davis Boulevard. . Collier County' Planning also rC'quest~xl tha~ a separate right turn lane fo-; Beck Boulevard be designed at this time tn accOll1modatc the .tul:ur(l traffic demands of Beck Boulevard . T)-:is additional right turn lane v,rill rc(}ujre <Jccess man;igcmcnt cnange~, a.nAainlng \\-all tu reduce rj~_;hl of \\.ay irnpacts to the dd'iaCt'llt: COinnl{-T~.ia] dev':l::pnlent, eli'lC; the !":-'quin'TnCllr fnr an:j11isi-j(11l ill =- n~'w FO'iV In:hJ';lnn of th~'.'v' clwnges \\'iLh this prujectwuuld reducc' "Lhro\v dW:dY" costs and tdi:ninat.~ llnpacts 1n the' COni'~T-neck inkrs',~c:tion in ~hl' fUi'UTt'. . 'The' projt~cf s original scope of V\"ork could nt1[ ha\/'~: nnticipated thE' late chz.:ngc.:-; tCl Dc:vi~ BouJ.:'vard chie to RO\,\r l<;SU(~S :ac'ed by the' I:nClT dIld ;1"1c nHldifi,-~db~ms liJ 01-:cL [)(\llk'vard r~',-]ll',~s[ed bv C:ullicr Countv Planning to accommodate th~_. i:uture n";('~cb of Becl( B()'u]e\C;1rd. TltJ~n:{or('r this tJ.sk is c(1r.sid'.~red l~dd.iljOL~l~ S('r\'i~~'2s . Sl'rvi.~~'c:~: r~:quir~"d lu finelLzc tll'2 pLUb, sp'.x:ifictiLion~: eme: I2stimdtes in::ludc RCiil(hvav S(';~bcc;, TJlan ;],2-.d ~,'n,fil(;', Cr('s~, 5~'ctjur:s, ~;igni;lg ;mu J\larLrni:',. i~:.lanbb,:'s); r~,,-,Lai:".ing \\:all ./\, C'c'S" \,'L::,1i':1~t.'nH'nt r('\'i'~L)'ns Draina~:t TJcsi,71. F'criT'.it ,n,genda item No. 1DAB Octoheri2, 2010 Page 25 of 58 AttachmclltA Change Order No.4 Collier Boulevard (SRfCR 9.51 ) Davi:; Blvd (SR H4) to tv1ain GiJlden (~atc Canal PWlect No, WOO I modifications; ROW Sketch and Descriptions and ROW Map revisions. b. Future Beck Boulevard Extension Drainage Revisions - $9,616.98 . During design of the Phase II Plans (60%) CH2M HILL was requested by Collier County Planning to revise the size of the drainage trun.k line and proposed dry detention arCJ to provide ildditional capacity in the storm water drainage system to accommodate the fu ture expansion of Reck Boulevard to the ear.:;t. . These revisions \vould elin1inate the need in tile future to n10dify the drainage conveyancE> systcln. . The project's original scope of \vork could not have anticipated the request made by Collier County to accommodate the future needs of Beck Boulevard, Therefore, this task is considered Additional St.:rvict's . Services required tn finalize the plans, specifications, estimates and permits include DrainagE' Design, Drv Pond revisions and Permit 111odificatlons. 11. Resolve Surrounding Property Issues; During construction, issues arise due to stakeholder concerns that need to De addressed in a timely manner to expedite design and construction on(j/or convey a positive public image ossociated with the projf!ct. Concerns and requests from adjacent property owners are received and reviewed by County and project staiffor resolution. Additional Services that are required and will be provided by the Engineer include the joliowing, d. Addressing Eminent DOlnain Issues with Property Owner ~ $21,37331 . During Pcsign of thE' FDOT Din-is Bnuk'\'ard Project and Collier C 'DunL"\' Collic'r Bnuif.'\'ard Projc\ct d:': ddji:l:.:c:'nt pro?'.:.'rty owner un the north\\',--',,! CO:Tl'..:.\}" ut C~1111'~'r gl)uh.'\'z~rd and Davis Boulc\yard contvstcd ilh'111in:n1d.) RO\Y /\cquisitinll {'~:(lnli.'l' dtFl ,.1l HL'~\ir prop<:~:-t"\'. The C()~ll1ty n'qtl~'~;kd th<:lt C;-I~!\: j iILL r,.:.'\'j;~"\y FCJ\Y w~t'ds, prVpi:Ht' e'<hibirs, d(,\'.~..lor alil'rndtivc. con.:..~''-.'pLs, ,1110 generat.C' plans ior g",ometTV, sl,<;nin<; dId marLin>". drilindi'" and slgnalization that ,"jrlriii{'<:; (-jH~ Iwt,d {nf ~hl-' 1'n]1111'n:1111 RC1,Y dccp:isit-ioTl. The servio:. to he prClvidt.'cI b~' C}-l~l\tf 1 In~L in.:iude: !vic',.~~i!l;' .\n'.J:hial1c',' \"it]; C ()....~nt"\ dnd FIX;"], \illlbvh. Cn1L(T'hs'j '.:>'c':':;lli:h::n ,(\,genda Item No. 16A8 Clctobe'-12,2CJ"10 Pa';J8 26 of 58 Attachment A Change Order No.4 Collier Boulevard (SRJCR 951) Davis Blvd (SR S4) to ~1ain Golden Gate Canal Project No, 60001 o Three (3) Deposition ?\.1eetings ,.vith laV\l'er~. () Prcparatic;m and Attendance at hVQ (2) Court llearings o Changes to Design Plans to address Judge concen1S o Reviews with FDOT to review revised signing plans and turn lane geometry . The project's original ~cope of work could not have anticipated the prDperty cnvner contesting the minin1al ROvV' Acquisition at the corner and the request of Collier County to assist them with defenuing the Eminent DmIlain case. Therefore this task is considered Additional Services . Services required to address eminent domain issues and finaLize the plans, specifications and estimates include Field Reviews, rvleeiings with County CJld FDOT, Evaluation of Site Plans and Gpometric Design Alternatives, Preparation for and A tlendance at Depositions, Preparation and /\tlendance at Courtl-learings, Olanges to Design Plans, Eeviews with FDOT. 12, SFWMD Additional Permitting Requirements: During the Permitting Phase of the project, the SFWMD requested that the project survey limits be extended to include ~he entire FOOT interchange infieid area as well as the outfall ditches up to the box culvert crossing locations. Additional Services that are required and will be p.rovided by the Engineer include the following: a. Additional Survey Required for Extension of Project Drainage Limits - $28,322.64 . As part of the Origini,:l Scupe, the ar:bc:ipatt:'d sun'(~y boundary \vas li1l1:i:ed t,:") the (,~xL'nl c( the propost'd pll}!sical conslruction improvenlents utilizing tJ1C' existing FDOT drainage {aciIitit~s. . As a r,;:~suH- of our initial d~~;ign 'Irork, it bc::camc apparent that the field conditiuns along 1-75 wilhb FDOT RO\\ had been modified uVer U1e years and the FDOT ditch L:Jciliti~s ""'ere cl-wnged from their original (:oncept. . in addition, Sf'\Vi',lD lS requiring prcpa::(ltion EiJ1d subm.ittal uf a signed dnd s'~:..11ed lopugraphic survey for thE' linllts cf permitted a"'~'3 nI' to and including E:U extsting and proposed oL'l::Idlllucations. It has be.::C'711l' !l'.;~Cl,'ssilr.\' to L'xic!\d the Iimit~~ Cll the iniLiill S!..:fVC:\'" te, includ~' U-t'.' lirnil's Cli' the c,,:isbng fLl(}T Jr,::una!;~~ to the potential outfall, -whi~:h is IClcatcc ,lppF~xinl(:tel\ 40UC fc;x}~ rrOIri tll,:' Prc'j','ct: area, tD r~',Cl~:rlcJa !tern hio. 1 ~i.6.,8 , CJ:::te;ber ~2. 2010 Pc"\;1e 27 of 58 Attachment A Change Order No.4 Collier Bouie\'"rd (SRJCR 95 J I Duvis Blvd (SR 84-' to Main Cinlden Gale Clna] hoject No. WOO] verify flo,^,' direction and set thE' n10dified f're-design conditions ror this project. . This is required to provide CH2M HILL enough information to complete design to SFWMO and F[JOT requirement' so they would review and approve tJ1{~ Permits. . The project's original scope of \vork could not have anticipated and did not include all the survey that was being required bv SFWMD and FOOT. It would have been unrealistic to foresee that the SFWMD would insert the requirenlent for a full topographic survey to the outfalls during the initial project scoring. Therefore tilis task is considered Additional Services . Services requin~d to gather survey data, finalize the plans, specifications and t'stin1ates and obtain SFWrv1D Pennits include site visits; extensive field topography surve?; coordination and incorporation ot new survey data into the original project terrain model. Drainage D~'sign changes, drainage calculatinns and Pernlit mc\u.ifications, b. SF\VMO Dewatering Permit - 59,994.91 . During the Permitting Phase of the I)esign Contract, Cullier County reqll(~stf'd that cr12~T lTTLL prppJff' a D?\vatering Pennit for the Pr,'jecL. Typically' this is a req uiremcnt of tile construction cunlracto1', hut the County requested that due tn the SF\Vr'vID changing permit r,_,'quin-'menl-s, f.~:'l-l2r\.IIIILL. pn.:pan.:' the pcnnit to expeditL' the prucetis. CH2Ivl HILL v;il! pf'::'piUt' d I k\.-vdtering P'..:~rmit which \,vill be subn1iUcd \vi1..h Ull' Cullier Boulevard Enp (Pennit) [or the project. This T~!;lrr:1it will h'_: L1\'dilable for the C"onb"ador to us'.: (0':' mcdify) when the proj'_"ct g('CS 1,1 consb-l1ctiOD . The pn>j;._'cC::; orizinal score of \I\'u1']( could not have anticipated these ~crvices v,:hich \vere r'2quesled 1'1:1 Cullier County during the Permitting PLilSC. fhis decision \\'<.1.'-; !lli:ldc to helr -L]w Contrador during cunsh-1Ktior; and aVi:1id pc:tC'nti.:ll proje.ct constructioii delays, Therefor'~o th15 task is cC"1!1s1dep.d :\ddi tional Sl'n.'jc,~s '" Sc:'rviCt",: to prvpan' and. nht~:in the lv,Tmij include De\\'dtering Plans Prep21rdtion: D;ainag~~ CalcuiahclT1s and Preparation of f)':,:v\>atering J'ermiL, :3. Utilitv Design and Relocation Services: During the S:::Opi:ig of th:: desiQn of this Droject it WG5 aqreed to bv Co/l;'2," Cou.'-:t\' o,'ld C/-i2fvi ,I-lfLL to cxdude cel'to;n design Agenda Item No. 16A8 October 12.2010 Page 28 of 58 Attachment A Change Order No.4 Collier Boulevard (SR/CR 951) Davis Blvd (SR 84) to Main Golden Gate Canal Project No. 60001 elements due to the uncertainty of what would be required. It was agreed that the Utility Design and Relocation Services would be added to the contract once the actual footprint of the project was determined and impacts to existing utilities cau/d be evaluated. Only utility coordination, research and minimal SUE services were included in the initial scope. The Additiona/Services that are required and will be provided by the Engineer include the fol/owing. a. Utility Design and Relocation - $160,001.30 . Once the project typical section, geometry and drainage facility design was agreed to and conceptually approved by the County, FDOT and SFWMD, the actual impacts to the existing facilities were determined. To construct the project in a limited ROW with existing and planned development adjacent to both sides of the roadway, relocation and! or modification of the following utilities will be required: CASING EXTENSIONS (ON EXISTING PIPE) I ITEM STATION RANGE LENGTH I UNITS i COMMENTS 24" CASING 800+02 62 LF , ! , ! I 30" CASING 838+52 31 LF ! ! , I I , 60" CASING 801+02 25 LF r i NEW PIP:;: CmiSTRUCTION I ITEM I STATION RANGE LENGTH UNITS COMMENTS - ;:~- 10" FM 837 +81 TO 838+05 38 I 30 I I - -l 799+97 TO 799... 98 LF 812+75 TO 818+73 618 LF I 321 LF OF 24" CP,SING REOUIRED 12" F'M 836+61 TO 638+24 186 LF 152 L.F OF 24" CASING REOUIRED -------- I .'--'-"-'~-'~-- 838+ 19 TO 838+23 39 LF , I i TOTAL 878 LF I i I -.- ---, 837+08 TO 838+57 209 LF 91 LF OF 3D" CASlhlG REQUIRED i I , 16"WM 838"48 9 LF i I TOTAL I 218 LF .. c c c c " - . - -~-IiTSI-- ! 20 V,M ~""V\I~ 1791+69 TO 823+041 i 838+35 ~O 849"37 I ~_L_.._..____.___.._._~_. 3079 i LF 116G i LF 43::;1 L, OF 30 CASING R!:::QUIR:::D 85 LF OF 42" CASING P.:=QU1RED :{~:;:ri r':ClE-~:'\8 :~:~):Yj: :~ 20'1 J ?'~> J! S8 A.ttachment A Chant:"c Order No. :1 Col]icr Boulevard !SR/CR 9511 !);l';j:-, Blvd (SR S,~l J to Y\/Iain C;nldt'il c;a~~~ C;.;.n:d p;-('iC,Cl ;'\:(1. (,OOO I S2ci+ ~ 9 TO B38,53 i ~_L~ 52 ~F i P 7 I " OF 48" CASING REQUiRED 3C"Wh.'1 845+42 ro 85G- 70 551 LF TOTAL I I 602j LF "._,.~~--_._,- . Tht' pn)j'.."d's original scope n{ work specifically excluded these services. Therefore this task is considert'd Additional Services. . Services feyuin:d tll gather aJditional SUE data, finaliz.c' the plal1s, specifications and estirnates and obtain DIP Permits include meetings, planning, evaluation of n:1ocatiol1 limitations, additional SUE Investigation, preparation t)f T\plocation Design; Plan/Profile 1'lan revisions tu nlinin1izt' impacts; Ctility Adjustment Slleet revisions; Cross Section revisions and DFP Permitting. 14. Reconfigure Plans, Specifications, Bid Tabs, and Estimates into Two (2) Bid Packages: The County has requested that CH2M HILL break the Bid Plans for Davis Boulevard Project (FOOT) ond Collier Boulevard Project (Collier) into 2 separate projects. Project I Lirrlfts consist of the entire FOOT DaVIS Boul'2vard Project and a portion of the Coflier Boulevard Project from Davis tu f/fagnolic. Project!/ consists of the CoJ/ier Boulevard Project from f/iognofia to AIJain Gofden Gate Canal. The /J,dditionai Services tha~ ore r::'yuired ana' ~'Ji/! be provided by the Engineer include [fIe foflowmg: c1. r\econfigur~ P]ans, Specifications, Hid Tabf;, and Estim.ales into '1\\'0 (2) Did P ad('J.ges: 522..002.44 . Sc;'vic~s L'quin'd tll iindlizl Llli.:\ plans, Spt'ci;icahons ~I:-ld estimates ,:-:h1 l);lcain i j),. )Ci !','rnl-:ts JTl,'h!cII' me, -"~';)(,:':ri()I'. (If PL'..i'!..' I :;,'ll;"l,'.',d:;"n ,)~- nnri~y: :imit'-) \\-;:hin th._' 1 Pr:-1j,_,:,: P;,::n:j, '""_'Tla:_",::tinn nf '-;cpcU',--: il ~)n d: L,:, tjn,ci k:,. r)r'~TI:Lj"<lb( '11 oj SCpdl"J.tr "',_'~ ,:r;(! ljjd~,;bs. :'\tL:lC!1m\ ~lt r; in:_j-ud,--'.:;; J .' ~i'c'tcl!;,,-';J hrdb1(\\'.n !"<'cjuir".d ~d~,Ls dnd d:;s(<i<.:L:l; J.,)\"_'I I)f c_,f{(1:-'t. :5. Fir.al Signalization P~al1s for CoBier Boulevard-City Gate North intersection: The :':-our;t}! tI:<s r:?qu9stcc that Ci~i2t\/J HiLL rrcpa,~c Final Signaii:!otion Plans for the Future Signafjzed Inr'3tsectiCIn Co/!>::>r Boulevord end Cit)' Gate Drive North/t\i:Joh'_'1 V~:'()\f. Tho:: Aridlti:Jrim S0.'!Vi::C.', tnc}~ arc and wiii {]';:' provider.:' by :h'!. Engulf._'er jndudf..~ the? fof/owinp' ~L }:iI:ai .sip1aliz~tion Pi'-ii"':< 1m Culli~:i" Bml1::,",,:rc;-Cit\, l.~a:.t !....:o,th 1::1 ter." ectio I"'.: S2:;:, 1 til..:;-,~ !-\oenda Item No" 1 GAS '-.J:tober I 20';:] p(;~ja :Jf 58 Atkchment A Change Order No.4 Collier Boulevard (SRfCR Y51) Davl~ Blvd (SR 64) to I\1ain Golden Gate Canal Project No. 6()()()] ~ Services n~quired to finalize the plans, specifications and estimates include rneetings, analysis! and prep~1ration of Signal Plans, Details, Quantities and Estimates. Attadunent B includes a detailed breakdown of required tasks and associated level of effort. 16. BCB Permits (Requirement of SFWMD): During review of the Project with SFWMD- BCB, BCB indicated that even though the project was not constructing anything within their ROW limits, a Permit would be required since we will be discharging storm water into the Henderson Conal. CH2M HILL will be required to prepare and submit a BCB ROW Permit. The Additional Services that are required and will be provided by the Engineer include the following: a. BCB Permits (Requirement of SFWMD): $7,003.89 . Services required to obtain Bes ROW Permits include meetings, coordination, preparation of ROvV Permit and Plans Submittal. Responses tn conlffients. Attachment. B includes a detailpd breakdown of required tasks and associated level of effort. 17. Plan Revisions due to Delay in Abercia Site Construction: Due to the current economic situation the Aberica Development will not be moving forward with their planned development. The Coilier Boulevard Project was utilizing portions of the Abercia site for drainage storm water treatment and attenuation. CH2M HILL wil! be required to modify the Project Plans to construct portions of the latera! ditch svstem ~vith the Cother Bouievard Project to treat and con vel' oroject run-oft. The Additional Services that are required ana will be provided by the Engineer include the foliowing: a. Pian Revisions due to Delay in Aberda Site Construction: $19,928.90 . Services required to finalize tlu: plans! specifications and estimates and obtain FDCyr and SF\,\'l\1D rr::nTlits incIudt' 111'2t:'hngs, Luo::dinauof\! revisiDns topn*'_d Plans Cross Sections, Quantiti~~s end Eshrnfltes and 5F\/'/:,'11) J-'errrtil Flans. Attachment B jncludes J detailed bn:akdown Df r'~qllired tasks and associated level ~)f effort. 18. SFWMD Dewatering (Water Use) Permit Modifications: During the Coordination and Revievv oftne Prcsi~ct Dewatering pf:'rmit s;=V~/rvlD (lli/mer Use Dept) requested modifications to the approach a.id configuration of tht, u:?::nriE"nt end co!:tafnrnent 5/'stems. A Te::hni::ai Reoort i.vifi a/50 bE rC'quired. Cf--f2f'-v'11-!!U I/Jiti be reauired to conform to the reGuests in order to obtain a De~"\/at'::ri:7D Permit fo,~ the Project. ::::;;-; i'oj:;,. 1 :';':\C, ':):; ;;~'(;! ;:~ ;2C110 :11 c162, Atts.ctJ:a:el,t :\ CL~:lr<:.:.(~ Orlkr :\n Collier Boulevard (SR/CR 051 ) D:J\'j.., Bh'u {SR g4) to l\!i~lifl Goldc!1 C;:(tc C~;)];JI Pn';~(~l ~<u. HI;)OI Additional Services that :He required and lvil! be provided Of! the Engineer include the jollowinq: a. SFWMD Dewatering (Water Use) Permit Modifi:ations: $1Z,3!!9.14 . Services required t(l (lbt~lin ~ll(, Dcwilh:ring I-\'fmits includes l"?vlsiuns tu PC'nr,it, I\'nnit Plans dnd Calculations, Preparation of Tcchnical Rt-'f)(lrt. :\ttachrrlt'nt B includes a d('taih:~d breilkdown of required tasks and associated level of effort 19. Retaining Wall Design- Lateral Pond Reconfiguration: During the Coordination and Review oj the Project Permit, SFWMD requested modijicotions to the conjiguration oj the treatment and containment systems- lateral ponds to provide additional (50% based on juture Permitting Reguiations) treatment and storage. This required the reconfiguration of the swales as IIvell as the addition of retaining wails on one side of the treatment swales to eliminate the need for additional ROVV (since it was not available). Ch'2M HILL will be required to conform to the requests in order to obtain an EliP Permit for the Pr:Jicct. Additiona! Services that arc r-:!quired and will be provided by the Engineer includE th~ fo/towing: a. Retaining Wall Design- Lateral Pond Reconfiguration: $2.3,152.86 S'--'r\"ic~':> n'q,rirecl te, nL'tdin till' SF\\'i\,lT) [rzp I\'fnlits in('1ude n"'-viSlOllS to L:te:::aJ I )itch ) >c'SJp;, Cross Sectiolls, dnd QUdntiti('s, Pn'!1dfi'1tinIl 'll' T\d:iinill;~ \\:,di PLp1<.;, C)l;,m1"ii'i~}" ~Ilid E<;timaL's. .'\tr.:h::1!I11('nt B incilldt.'.<; ,1 6ctaiJc.d bn:_';~L,I(i\';n uf n-:qujr(~d ti.1Sl:S dJld ,1,<::sc1c;,d-ed Jc\cl ,:j ,~,tt(,:.t 20, Typ::ai 5e::tion ~)zve:nen: Moc;;j::c:::io:1s Unde~ [-70S: ::;'~':-i.'~'q t:::? Coo.'"ci,-;cti:;,"': cr;c' Review of the Project Permit ;:DOT (HDF?) requested c:ddiUonoJ dl''Oinage modeling Efforts assoclcted with tne Fie::overy Anaivsis, Based on the requirernents, tf7e /:;t[:o/ punds reloined run-o/r Jonp::::- than previous!)' ..iiode/::d and thercfu:-e c/earan::e to pavr;,"Tierit b:::SE bel::,vv occ:?mOD1'! ci~Joths. To accommodate the new modeli.r";Q, the .ncvem::~r:1 typico'!'1;:-'c:ion wc.c: ,'('\'i'.,,:'d co j,'Ic/ude ('hiaeh D:JSr.;" in Cf:'rtci.'7 arees ~vhich cr~)Video' tht" required c!::":-;rn"lcP C'---f)f'.,f', ,-{ilL (','iff h~-" r~'auir::,d:,o confo;"n! ~"O th::-.' r':!q:_F!5fs in ordc_.";' ~o clt<:::in 0 ,~JO-:- P~:r'; iit for- :-h::' PIDj::,'c~,,!J,c'ci"U:x;c'd 5!:?n,icss t/;at arE re:JUlred une iiiil! b:-' t,l,'ovi:i'.:.'c/ iJ\1 the ~n(:ineer inciudo::. rhe /o/Iotvir:;;: item f\Jo, -1 tlA8 ,]:::Cb9! 12.2010 3:2 of 58 Attachment A Change Order No.4 Collier Boulevard (SRJCR 951 j Davi, Blvd (SR X41 to Main Golden Cate Canal Project No. 60001 a. Typical Section Pavement Modifications Under 1-75: $7,912.32 . St'rvices required to obtain the FDOT Pemlits include I\-1odeling of new Recovery Analysis, Changes to Typical Section and Cross Sections, Revisions to Quantities and Estimates, Attachment B includes a detailed breakdown of required tasks and associated level of effOli 21. Services During Construction - Shop Drawing Review: The County has requested that CH2M HILL provide Shop Drawing Review assistance to the County, on a Lump Sum Basis, During Construction of the Project. Additional Services that are required and will be provided by the Engineer include the following: a. Services During Construction- Shop Drawing Review: $25,269.80 . Services reyuired include coordination \-vith Project eEl Firm, Reviev,' of Contractor Shop Drawing Submittal(s), Response to Submittal(s) (Acceptance/Comment/Rejection), Coordination witn Contractor, Ivlceting Attendance. AttachlTIE'nt B includes a detailed breakdown of required task(s) and associated IevE-l of funding 2:2. FOOT 100% Comments - Design Change Requests: During the FDOT review of the 100% Project Plans, the FDOT requested changes to the Plans that would help accommodate a future planned FOOT Project. These changes ore related to clear zone issues andfuture /-75 ramp improvements and inc!uded Bridge tvlfounted Sign Panel Modifications, UghUng Relocations and Signal Redesign (1 location). The Additional Services that are required and will be provided bV the Engineer incfude the folio wing: a. [DOT 10011,/(1 Comments - Design Chang'e Requests - $62,115.36 . Services n~yuir'.':d to findlizt:' the plansl ~pt':cification~ and estimates and obtain FDOT ?ermits include ~n',~('tings, an2.lysis, ('valuation of relocation ]jn1itation~, additional SuE Investigatiorl. prqJaration of Lizhting Plans, Signali~':crli()n Plans, Bndge J\lnunted Sign Pian::.;, resubmittal of fI10T Permit {or Approval. :-'\lta(~hn1t'nL D includes a detailc.d bH~akdO\vn of required tasks and associated (evel of funding 23. Expert Witness-Deposition: The County nos r~que5ted that the Ch'2{v! HILL EOR (Fronr Scerbo) be made available to assist the Cour;ty (ora vide expert witness services) with any issues or ciaims tnot rnoy oris::' during the ROVI! Process. !L-~:T i'h. : '3i\~:, ::::):-::T'_-;!:~'~;;rI2 2C:1(\ of :3B Attachment A C'hange Order .\0. ..:+ Cu~lier Boulevard (SKieR l)5J) D:li'j" Blvd (SIZ h4J 10 !\/Iain C:;clld::'1l CialC C,-mal Pnl_iccl.:"-JO, ()(}()(}J Additionai Services that are required and wili be provIded by the Engineer include Ule followrng: a. Expert Witness-Deposition: $12,250.24 . Services rpLJuin~d indudt"~ !\1eehngs, Preparation for Depositions and;"';- Court AppedfclTICes. Attachment B includes a dt'tailt'd breakdc)V\,,'n of requIred tasks and associated h~\.!el of funding 24. Services During Construction - Miscellaneous Services: The County has requested that the CH2M HILL provide assistance to the County on a Time and Materials Basis, During Construction of the Project. Additional Serviccs that arc required and will be provided by the Enginecr inciude the following: a. Services During Construction - Miscellaneous Services: $100,295.94 . SC1T1CC'S rcquirt:.'d include I\JC'ctings, r:('spc1nsc to RFI's, Field CDordin.1ti(m, and rcquestC'd I )~'sjgn Ch2.ngcs During Conshuction. /\tt<_J(_:hmt'n~ H inchldes it deLli>_"d bn.:.'dl.;,duwn of n:~quin'd tasks unci assocIated level elf funding PART 2. - Prolect Schedule: Changes to FrnjE-~('l: Schedul,,,-, - [0 he IJt'ter'mincd r,~BT_.::._- Exclusions: :::"::;r\'!ces oth,.:.'J' thdn th(>.~,c j,.,1' thi..;; ChiJ.ll~l' (irdc:'. nealh ji,;j~_'l~ ~lb()',,"_\ ',Of' J1C<- :n~:1ud,-=,d in the ~'c!p'.:~ of \\.'crk PART'; - COrvfPET"'\~SATI(_;~ Summan' of Costs i _________,.....J r'p"'-70' 17 I ...O..i, 0... I , l~~i~~ and- Ma~'~~-j~~ TaSk(S-)-;';~-~4------'-' Lump S~uTl1ask(s) 8~22 --.--.-------.--..-...-----..,-- ! L S112.54€,i8 i 70T AL Cost Change Ord8~ Ne.';' I , , 2950.3~--=.35 J ~\~dcJ:.nlu1t r; 1:!"IC1Ud\'::-,.: ;lU1\: d'~<,l:L '.1 [)] ~'dL~L )\<'-1: \'j th,," ;_\;_'~-ll:;L:~'s and C\l~jLS ,\.'.,,',o:.:i,::kll \';iiJ~ th,,,: c.bc\'\, ~ ); {~, Aoenda ITem No. 16/\8 , October 12. 2010 - '-'~1-' ~'1 ,)f 58 Collier Boulevard (Davis Boulevard to Main Golden Gate Canal) Change Order No.4 CK2M HILL Attachment B -----,-----. I I i !. LEAD SENIOR i PROJECT ENGI REVIEW I MGR PE:,,~IT LEAD DRAFT~ERK TECH 'STENO TOTAL HRS LABOR COSTS 'ES TECH DES. TECH la~k# I TASI( DESCRIPTIO'"' CONTRACT RATES I ~ 147.S~' !, \32.42 i $ H)~d14 r 90,25 I ~ 72.50 S 53.21'1 $ 5i,JU Task 8 ~ FOOT Design and Permitting Flequiremenls (Lump Sum) 19<:,254,49 1 ask lla -1 YPH;al Section Revisions and Hoadway Recteslg-n Due Iv FOOT CommenlandApproVllls i) ConcuDI"al tJOSlonAllamativec 2 T IcHiS~CI,,,,' f'acKac;wF1evlSiOm; 3,I,caISncl,,,ns 4; Sumnlarvof [Jramaoe StruClure~ 51 Plan and P"'limS",wt~ cj[)ra,naocStruclUreSi1eels 'ilCrossSect,ons e.\lSIQnH" anrli-'uwmomMafk'n [<)Ulil'lvPI""S '0) MOT ptans anll (Jelulls 11' CJuanliliesar:dCostl:st,maies 1~) P'()'ecl Ma,,~oar"en1 13:,Sanallza\<on 1411Waler Ma'l<lQaman: [je~,qn and ERP P~"n'tllnq 1:.d[),a,n3(lc['"s,qn -~~=~; :52 " '12 " Ta-skflb.Prep.lflllionolan FOOT Inlerthang.e Analvsisand Operalion s ~epor1 snd MethOdology LeUero/Understanding plMLOU ~) Tral'le An~lyS's 3\ SvncroMDdel'naaf1oi':val~allon 411keortllOARi ~ ho'e~t Marl" arrla"t 610A/QC Ta"k8e,AtltllliO"sIFDOTParmltlingRaoUlfem<;>nls l)IUflvewav(;onneCTicni-'arnlllanr)Pla"S ~\lUlili'V Permllwi!tl Plans J,ISI<l"aILzalloll'S'~lIlllq ~,,(j l,jw~""jJc,()I\I,no ""..,nlll CUlc! Pi",,, 4', ProPec'Manatl~mem I "~I UA'QC '" :C:l I;' , , I~ , , - " i " , " m ! " , . BCo , " " ~4 '" -t- o 0 J:, , 8h " '" 526 , , " 12 , " . 10(1 <0 " ~2 " , " " , , - '1~ "' " 11104 $ ...- , ! '" i i 1[, 2<' Jli ~I' H' 1~ !'4 , , 1110 " ;'4 ]2 " :10 , ~ -- '" " :<:~ " '"' 1M H' " 0 . 20 21' , 17 _. '"' 23,735.54 11~~-O 3?-+te+-4irl- 30 12 24 30 It,' 31 1:; I 1_, ! , i 0 I " 317 " 31.85G.31 1h I " iC I , 1[.:(;0;'[,1 ::'Qiil'" Ci...." ~Iy,: C', ."co t'.I!eI I,,.~,,n ,~,(.IcJ," :':0,11;1,_ '-Ilit.!_ IE (~_ I JoJ(;1[, "~ ,:.i( ..~--~-~- 191 1$ :'1.37331 I CalHer Boulevard (Davis Boulevard to Main G::>lden Gate Canal) Change Order No, 4 CH2M HILL Attachment B U I Tasl;1: I TASI:OE'SSRIP'fI('JN c::mTRAcTRr,YEs I I ,LIoAO LEAD I r'.-----.----..,.,-".-~-I.. ! SENIOR I PROJECT I lONG' DES DRAFT, CLERK i REVIE\~, MGR ) f',;pRIC~T ~EE:~H TECH i TECH I STEND TOTAL HRS 1$ 1~'(.9~!; 132012;1, '05_0~1~. 9(1,251~ 72_5011 5Z.2&1! 51.n 1ask 10" Collier County Requested Improvements lor Future Developmenl{Lurnp Sum) I 36 ! S8 T:lskl0a_BeckBcul"v"rdA....,ipnmenland....dd;\;onoIRigh!T,,'"Lan e "'I :i--~ ::F' j- '(; "' m 1\:ConccPtJolt,lte,na',v<,'; ~'I 1 Pleal Secllon :~I ~umm"r 01 Uml<,a e SlrLJct.He< ",If'w" a~o Pro:u" Sheel~ -'-'~'"'naOeSlruc;ureSnew f,\Ic..'o%S~CIIOns -. 7: S,(m'nc ~nd P'lVcmont Mml""G GIWlll.l:zahonf'lansC"ordln8[10c,IUM'';:b'c,., uuant,t,esiCosl Ec~l<milt€S -,- 101 f--m'GctMunaaorncnt IT dHsta,mnll Walls 121 Waler ManBoampnt [Je,;IO" ,,,..d c:tlPf''''''''I'I'''j---' 13,L'mlflaoau,,",an 14., QA'QC , --'-1-' I i , ..:t:= , 20 p- --'-'"1 :' I . ..=f. --l '; -',,'0 , , 1~ '_..L " +- j- '" lasr, 10~, Future BeCIl !Jout..varlll:'.~l"nslon Dr~i"~Qe R{'VISHlr15 r J: -, -4 I r-- I'; : 1 IIf~Qnr; Details ___,,_~ll["alna()e StrutTLJl6(JeIaH" . ..- :,."wale, M'JOao"m~nt lleslq;' anti Ff'W r'W'~ "Inc. 31p,Olectl~a"SqernG!1I .---- 0" QA.'QC J~o I t' I I 1:, ; rr,___~:_-_- I 12 I IT35k l1a - Address.ng tm1nenl Dommn 15StJC5wlm f'rooer!~ OW"", I t=== I nll'laelJnQ, V.'IHl COLJtllv G'ln f-~l(_'~l ,),'f--rap;"~llon ollvl'-'LtrDtu CQnGr'DI~ 3';.ITh'~" GI D"~"",II"'-,lvI{!"i;"q" 4' Cil8nQee te' ue,,'Q[] PI~c~: 'Pe, JI.'aQ~ rem" ~1 toV"ll:alA rAVt%C ~IUI'''''(II(,~omo~r,1 ""\" Fll:JT Tasi-; 11 - ResDlve Surrounding Propr:tt\'ls$ucs (Lump Sum) ------~--~~.,- , T I ----1 _h--+_~ .......t~~--d sn 1~~ _... -.. .:i:.J _J , _L' L_ " (j'! , ,. Task 12 - SFWMO Permillin9 Requirement,> (Lump Sum) , Ir~sk .,20 lLimll~ ! ,Aoclllional Survey ReQulrea tor EX;HnStr)[l 01 P'Oje:;' [lr~;T1~Qe i ~Dg -, ~U{) .; 1~"~:",~,, '""'1[1 !1'~:':iTi !':G 10:1,(; :_:i.J:',)2i :2 2010 3:) of 58 lACORCOSTS <10.440.33 I, ~,616,!I~ !, iU.Jn,6~ , il. I,'",~",:: "~--..J-~-I-----" !__~i 1-- --,~~'------<.;:;------ ~ _:---~~-"~-" --r---- ,...: ~ 16~.OC1.3c' , ! I I . -'--T::--:===:::=~:;"---i~- - - -. ""--- ----~=I~----=---=-i'---"-'"-~i. : "'.; ',",' "e.. ------:-.-~--~-.-- -: I II"n ~--'~:;EjE......'..~.:J---f-,;~~=~=:::=! I ! .. .--_::::j-' ---- .=.=--.::::::1=-:....-=-=..::1 I' _____-'----____L__ __~___L:._--'~_="'2_2-'-j -I ~'2.'JO".~.1 I I I I I , .'-"----~__ ,I , --:5;:-~--;-~.,(';:;j ---------- 1 i ! i i:I"',LP,%:;,"V"" ~, ~(_f~.... , 1- r--.-.- [Tc''''1n._.sFl'.'r.ml".watArin';F'crrr''i .. , r:=--~~i~;;~~~-;::',:: ~: ~~;';,~~~;~~::::=:-----~==--=~-=-j=~-~:=_L~'~--~-=l. I.__.____~__"_._"....'__._m_____.__~~_.__.__..m___."m _._.._ , , _----.ll' I 0(1 i 0.1, u,[== ;- --=:-_=--=' "I! l'.O ,(I:" ,:::51::3 - UliIit_y D~si(]n and Re!ocallor: ;:krvj(;es (Lump Sum) rl ,.~~ 1:1" . 1I1itily f,eincalion De';'pt ,1P1:,,',;,wf'm:."" Snn[': ^;';V"_.,,;"i;';:-;:icIIO;.." ---,--- [.--J)II:':..':~t"'I()C~.."'" i ''''~''', __.____~_..~,. L____~~,q"".I~".':'::!.~_~c~:"_____ I I ','I'jUon;il"',,"'::'u'!c'iIr'li't'- L :',i"f'''C!I''JJ.~(JC'l'crl__- j -----8B~J?~~"~~~~ :_~~I~;l:" S;:li'-I:;::-~~~ ~;lc.L.'~0::.!!L:..C~:...~_____ , L.-.._.,,__,_____ TasK 1': - Reconll[]ure Plan<., Spe:::lljcallons. f;i::.: Tabs am: ~stimates into Two (2) Bi::J Packag<'s (lump Sum) 1.1"51, 14'_ "He~nnTtQ"'c Plnn,. Inln IW(j :;') G", :,~:,.' j(i bG ".j 22<1 ,--~c(o.",,:.,;": ');"". .,18"1 -----------:-7ifwv",' ,~"(J~,~n~~"-;;; I;;~", ,-,,-:- , ,-.Ik;'-;;:S(-L:;;';;;;;,;'-I:>::--~';:--- ------- '" ;,'Ho'."'c'" (.:."~,,,,7,,-, ""0 l' (J; ,",1' ;:'. i',."" 'j:!_'~~!..'.'..',!::?,?c'-'_:""'" ,,;-;, "~~~WJ 1'~~'2.'L~': I ;-,:ir''''Dote I",;: '~: :,e:" r..~ 10" ,<,,,' 1___.' .,.----'-j;"'VIS~ t:'I_y:;"~""t",,. __~_.__ _t.:~!Z': 1,.18nW"l'"'1tt:l. ~""""'2."2-':c.....__ .... ..,- , , .--..---- -~ _._--~---~------+----- -em! , , -------.-..-- ,,- -_.;----~.--I ,.. . . .....--1 ---'-',--,.__._-_._._._-~ -----.--1-_-.- ....._.___.________~__~__._ '-1 <, , : ~ i". ';; . l':tsl.!::; - lOin,,1 ';'[In;o,liZilliOl' Pi~ll$ for- ::::Dlli,,, Blllll(>\!fmi-CI1~' Gale tJGnh inlersec:jion fLwnr, Sum) 1'i~.o.I; 15, -rill," S",n~Ii~",il'" for","", .,," ~,("IIC.'-.:it..' ci,." 1',,,,1 IlnIH'~ctlcn "I :"C'-',!,Z~"- "I'" -.----- '-;"'~I'a:,Z,::;~" c:,,'"' L~.=-':'~=! i"!"",..:;n"~,,C;."-,i1,,( ---,G:::-':;I,'" _.'.'::'~,=-,-~ 'j~ !$ () ~<.,4.9 i ----I 1$ t\29nda t2m r~o, 1Gf\S " C)C ober '12 2010 Psge 36 of SS Collier Boulevard (Davis Boulevard to Main Golden Gate Canal) Change Order No. 4 CH2M HILL Attachment B SENIOR I PROJECT I ~~~~ I LEAD OES DI~AFT CLERK I REVIEW I MGR I P;:~~T ~:gH TECH TECH S'TENO TOTALHRS I lA80RCOSTS I Task/4- TASK DESCRIPTION CONTRACT RATES " 147.951 , 1n,421$ 105_041$ 90_251 , 1"2.50 , 53.26 , 51.78 '.' " Task 16 - BCB Permils (Requirement of SFWMD) (Lump Sum) Task 16&- aC8Pllrmil~ , , T " " , , . " , 7,003.89 1 I f'ermi~ Plan Preparation 2 " " ?IPermiTPreparalion , . e 8 , I ":HeSpDmlIOR!l.l's , , , Task 17. Plan Revisions Due to Delay in Aben;ia Site Construction (Lump Sum) la",k17a Plan Revl5lon~ DUll 10 Delay in Abercia Slle CDn"lru~lio" , " ! " " i " I , " 210 , 19.928,90 '1 Uralnaae !l.naIVf,I~ ., . " " , ~I Plan -Shlffit ReVISions , , I I 12 8 I 31 CrO.S;;'IICIIOnf1fWlSLOrl, , , . 12 , ".OUAnllr..."..ndEsllmRlflB , 12 1;' HI 51 :::RP Pl1rmll'lrt(l MadillGat,on, , , 12 , , , , FtJOT Perm:llInqMcOIiLcal,on, 0 , , , 7"1 ROWfle\%lons , , , , , Task 18. SFWMD Dewatering Permit Modifications (Lump Sum) lnsk1!la - SFWMD Dewelering Permit ModlfiCR1ions ~~ ~~----r-:~:T , , , '" , 12.389.14 ',:"e,"S'011'; '0 "",proael' ilno C"'clllal,o"~ c , , Hi 1C , 21Iif1(;lnlonoI175inlleloAreas{4 Pon(l~.,in f-'om,,' , 2~ J,IPreparallolloll>ewaler'1qrwporl .- - . , " Task 19. Retaining Wall Design. Lateral Pond Aeconfiguralion (Lump Suml l.ask Hla - Flela;ninn Wall Oeslpn,Lalaml POlld Recontlgumlloo ! , ! 30 ! " ! eo " , , T ,,, !' 2:1,152.86 l\'Or~'''il"e Analv,;," , , , , 21 LaleralUltr.t>ReoeGiQn I ! , ,~ 1 ~ " I I " R~lwnin W"IIUeslon , I 'i , , I " I I : j 4\ Pia" HeV1Sl0ns , " " , 2" I " I i ~I Cm% SeCllon Madillc..tlon~ i -+-'- - I " 1 :~ , - I 611C1u..nMIBS and i:.Sllmaler 'r; I ~' 1 12 , I I ~ Tilsk20 - Typical Section Pavement Modifications under 1-75 (Lump Sum) 1 I , , I' T"51<2U3 TypjcaISeclionP~vcmenIModificalion5underi-75 " " " '" 1 , " 0 i " 7.!l12_32 ___~,!L'I h~~y.,,~~'~!y~____ - ,.--,--.---- -~...~.. C__ ' J. 1 I~ : 1:- 1 1 ; , 1 2i1Cnmm' TVl1i~a' Seell"" 0r.rl Crn,' Sf' "O~ u , --~,--=----- . r-~-F=.l .~ T~~ ..---=--r---~=--+ --r ~ "liOuontl\.csandfoSI"nete,' I u.,____ - -- ~.._-_. --_..~...._---_._---~-_..._---- -.., --.,.--..----.-------.- Task 21 - Services During Construction ; Shop Drawing Fleview (Lump Sum} --- -..--- ------~ --~"'--- ITm;t ;1.. - SmVlCe,. During Construct"", - Shop DmwJng Rev,ew ~--!..Ut1~,ew 01 3"or.,,,awlnos.S',,bml1lals ~r I '_', 6U fill i~ 1..2'__i~ '"T :'38 I I" ! I ,.",,,,", I ~~-- '" !r' L- Task 2.2. FDOT 1()U% 8onJment!'o - De5!~J!1 Change ReCluest~ (Lump Sum) h~!<k22~_FDOT100%CDPnnlenIS"[)e"i~nCh"n,'eR"qut!'.>ls 36 '1 '~~52 -'P-;;:l-~~-' i liI1..'OI1:1P1C<HHQes'qn"rl"Dr,'_ln~f"lmpEct" _.~-1 4-~ =t~ 4[, ~ ~ ~:I~~:~,~~:~~r;:,_R~~~~~" V"jllw; LL'ffilr'oW, H"llif" I ~: t---H I I ^ dS'ona!!Z3Hon hede"'<l', ICollle.' :Ao""""~' ------=~"___ .. -+- r.:.' 'i'i..L_ iH' I 5118",jQel",olln'eCS1!Q.2'~I,:~tl~-'--!ioG!J:1~_____m___i___~_,-t..___!1 1~'.~ 1_:-+ ~- 3a 61" 52,'10.56 10 1( I I I , i$- IX " I 15.1'4_2B 5.173.80 4.2~39'; ':1.21'/.5B G_3!iS::'!'1 TaSK 23 - Expert Witness.,Depasiljon (Time and Materials) -~---------:----"-I-~''-'---~T~'''-- ITasl:23a ,EXllel1 Wltness,l)"o,,~illon Il)avlsi:;olllCr f'~rccl) ~__.,i_~_L-~_,! ~J I 'IH,Ae"~lnq..l)..pos"I"". _____.__ I ~if ._....i_. .C.__I ~Cu"'r1l,t}nea'''rlce.~",,pa,p.I''J' ,L~~_.__-------1______~ I -~T I"' I, I . -J==l='-___I ,-0",1 ~.- ,,~ ' I Tasic 24 - Ser\!ice~ Durinn ConSTruction - Miscellaneous Servir;es (Time nod Ml1terial~;) i ITask 24" - S"rvj~es D"rjn~ COPlstruCtiOfl - M.~~"iI"np.()lI" Services 7()' ~jU,~ ! 2~.~.;""[. '," :" r '" 1 "J_ ',',..', --l:;: - loa.?g'ig, 1, ',I/,IL~'L' ?'Q'eZII'~iG" af' ,In.; ~rocm~c :AO'.,lI'.'C ~_, ,'- I ~::~,:~:~nQ'~~i~~;, .,"~u~~~__ ;2 .L :(;0 : ~~~ .L_l~_~~~~:",__L_J,~ ~~; I I !CHANGE ORDER NO. 4: TASI~S 8-22 (LUMP SUM) , ! ~ 837.784.171 CHANG:: ORDER NO.4: TASKS 23-24 (TIM!::. AND MATERIAl-5) I, 112S1~.:[ TOTAL ::05T CHANCE ORDER ND_ 4: n,SKS [;-24 Is r~C,33D.3c' :o.c.;" Pi/ -;:)~ l;~.,' "c,r'.;0!()<-';C'C,:01n,--'_'-."" lttl" irem I\jo. -16.i'I,8 CJCTob.::;r 12. 20 -I 0 37 of S8 ATTACHMENT A SCOPE OF SERV1CES FOR CHANGE ORDER NO. .. TO CONSULT1NG ENGINEERING SERVICES AGREEMENT FOR COLLIER BOULEVARD (C.R. 95]) SOUTH EXTENSION (Davis Boulevard to Main Golden Gate Canal) PROJECT NO. 60001 October 6. 20] 0 111e CONSULTANT has been requested and retained to provide additional engineering services associated with final design and completion of construction of the Collier Boulevard South Extension Project (Davis Boulevard to Main Golden Gate Canal). TI1ese additional services are based on various design revisions and scope of work additions requested by the Collier County Growth Management Division Transportation Engineering Department to address the changing needs and conditions along the project corridor and to confom1 to adjacent development agreements. In addition, some of the additional services are required to match" As-Built" conditions of surrounding projects and resolve surrounding property issues. These services are necessary' to resolve project stakeholder issues (Collier County Transportation Department, Collier County Solid Waste Department, Collier County Utilitv Department, FDOT, FHW A, SFWMD-BCB, Abercia Development, City Gate Development), and finalize the project permitting and design. Change Order No... provides for the CONSULTANTS services to be modified to add the following Design scope of services to Collier County Project No. 60001. 111e following CONSULTANT Services are an addition to the original conh'act: 8. FOOT Design and Permitting Requirements: The following tasks are required as a result of FOOT comments made and requirements stated during the FOOT review of the Collier Boulevard Project Plans. The Additional Services that are required and will be provided by the Engineer to obtain appravals and permits included the following: a. Typical Section Revisions and Complete Project Plans Redesign - Post 60'\1" Plans due to FDOT Comment and Approvals - $198,254.49 itsm No. 16A8 ':.Jc1;)be: 12. 2010 32, of 58 Attachment A Change Order No.4 Collier Boulevard (SR/CR 951) Davis Blvd (SR 84) to Main Golden Gate Canal Project No. 6000 I . Prior to 30% submittal. a coordination meeting with FDOT Disb'ict 1 District Interstate Review Committee (DIRC) was held in Bartow to review the proposed design for this project. As part of the discussion at this meeting, the design exceptions for vertical clearance and longitudinal grade along the curb and gutter were addressed. Initial comment from the FDOT indicated that although a design variance would need to be submitted for both, due to the excessive cost of revising the existing condition, approval would be recommended. . Desi~ Variance 1 dealt with the fact that the existing vertical clearance under the 1-75 Bridge is currently substandard (16'-3" vs. 16' _6") and the proposed clearance would be at 16' -1". Variances for vertical clearances under 1-75 were previously granted by FDOT to Collier County for other projects, so based on the excessive costs to remedy the situation, approval for this project should not have been delayed or denied especially since resulting clearance was greater than the 16'_0" minimum. . However, based on discussions witll FDOT after submittal of the design variation, the potential for approval of the design variances did not appear to be forthcoming. . After discussions witll TECM it was agreed tllat CH2M HILL should redesign the plans to lower the profile at tlle 1-75 Bridge to provide 16' _5" of under-clearance in order to obtain FDOT concurrence with the design in a timely manner and preserve the project schedule. . Design Vafiance 2 was to due to the fact that the existing profile of roadway, would not provide the required minimum longitudinal grade when the typical section was modified from a rural section to an urban section. Curb and gutter was considered in the initial design for consistency since exclusion in this project v\'ould have resulted in a 0.75 mile gap in the curb through the 14 mile corridor. In addition, it contained the drainage runoff and provided a means for raised sidewalk along the corridor. . To modify the longitudinal slope in areas tllat did not meet standards would require completely re-profiling the roadway during construction at a cost in excess of $2M (>10% of the overall estimated project construction C<lst). . However, based on discussions Witll FDOT after submittal of the design variation, the potential for approval of tlle design variances did not appear to be forthcoming. . After discussions with TECM Design, it was decided that CH2M HILL should revise the roadway typical section from urban to iIe:Ti l\j~J '3/,8 :::?C :J Attachment A Change Order No.4 Collier Boulevard (SIVCR 95 I) Davis Blvd (SR X4) to Main Golden Gate Canal Proj eet No. 6000 I ,.'l_"" ~) f",", suburban and to redesign the plans in order to obtain FDOT concurrence with the design in a timely Inanner and preserve the project schedule. . The change in typical section from urban to suhurban \-vill require CH2M HILL to modify the Drainage Design along Collier Boulevard and to revise and expand the Basins to acconlmodate the revised roadway design. Drainage areas V\,ilI change, drainage modeling "vill change, calculations will change and Pennits will need tel be revised. . TIw project's original scope of work and 60 % Design assumed that due to the excessive costs of 111aking the required 111odifications to the existing condition, the FDOT would approve the Design Variances requested since silnilar variances were approved on previous projects. Also during the initial coordination meeting with the FDOT, they indicated that approval would not be an issue. CH2M HILL proCt-'t'ded \-vith design based on that understanding. Therefore this task is cOllsiderf'd j\dditional Services . Services required to finalize the plans, specifications and estimates include: Numerous Conceptual Design Alternatives, Complete Roadway Re-Design - rost hOC~" Plans (Tyrical Section Package, Typical Sections, Plan and Profile, Cross Sections, Signing and Marking. MOT. Utility Plans. Quantities); Drainage Design; Drainage Calculations, and Ahercia Developnlent and ColI1er Boulevard Pernlit modifications. b. Preparation of a FDOT Interchange Analysis and Operations Report (IAOR) and Methodology Letter of Understanding (MLOU) - $23,73554 . At the coordination meeting with FOOT and FHWA at the ~O'\, design submittal, FDClT indicated that a Ml.OU and IAOR would need h' he prepared and appmved by both FDOT and FHV\! A. This would be required to ensure that the planned in1prnvenlcnts in the FDOT Limited Access l\OV/ w()uld cnnform to thE' existing configuration of the interchange as \vell as the rOOT "future" planned improvenlents to the interchange. 111E' FDOT \vanted the County's Consultant tn prl'piWE' both documents. The Count}' agreed to have CH~M HILL prepare the doculllents. . T11C project's original scope of work could not have anticipated this FDOT request for services and thus did not include the above tasks. Therefore this task is considered Additional Sen'ices . Services required to finalize and obtain the FDOT Permit include: I\1eetings, Data Gathering, Coordinahon with FDOT Consultants working on Inil'rchange Planning Tasks, Interchange Perfonnance Attachment A Change Order No.4 Collier Boulevard (SRJCR 951) Davis Blvd (SR R4) to Main Golden Gate Canal Project No. 60001 i\g8nda ! tern No, '16/\8 October 12, 2010 Page 40 of 58 Analysis, Traffic Modeling, Synchro Analysis and Report (2) Preparation. c. Additional FDOT Permitting Requirements (Permits) - $31,858.31 . The design and pennitting of the Collier Boulevard Project requires extensive effort with respect to coordination with FDOT and FHW A. For Approval, the FDOT has required that, in addition to the Drainage COlUlection Permit required for discharging stormwater into the FDOT ROW, CH2M HILL will be required to submit the following three (3) separate Permits: o Driveway Connection Permit with Plans o Utilities Pern1it with Plans o Signalization/Signing and Marking/Lighting Pennit with Plans . TI1e project's original scope of work did not anticipate having to prepare and submit three (3) additional (Drainage Connection Permit was assumed) Permits for the above mentioned portions of work. Based on previous experience working on projects within FDOT ROW, it was assumed that copies of the applicable plans would be submitted to FDOT for their files upon completion of design. Therefore this task is considered Additional Services . Services required to finalize and obtain the FDOT Permits include Coordination, Meetings, Project Plan Changes, and Preparation of three (1) Additional Permit Packages. 9. Match to "As-Built" Conditions of Existing and Concurrent Projects: The project plans are developed on information available at the start of the design process. Due to continued growth and development, many site conditions on surrounding County FOOT and/or developer projects change during the design period which requires redesign efforts. These changes generally require additional coordination, design survey, design analysis and revisions to the construction plan documents. Additional Services that are required and will be provided by the Engineer include the following: a. Conceptual Alternatives and Revisions to NW Corner of Beck/Collier Intersection - $33,306.56 . Due to ROW Acquisition concerns from the adjacent property owner, Collier County requested that CH2M HILL prepare various alternatives for the NVV corner of the Davis Boulevard - Collier """', :';:' G;\S Attachment A .,. ')8 Change Order No.4 Collier Boulevard (SR/CR 95 I) Davis Blvd (SR S4) to Main Golden Gate Canal Project No. 60001 >c., v~-:-s:- :J Boulevard Intersection and evaluate the ROW rt'guirements of each alternative. . Numerous concepts will be prepared and from them, three (3) Dual Right Turn Lanes alternatives will he designed using various size design vehicles (WR-50, WB -62 etc.). The ROW impacts of each of the alternatives will be evaluated. . The altel1latives will also need to consider the FDOT - Davis Boulevard \Videning Project (being designed by TY Lin) to evaluate and provide sufficient ROW for the Intersection Signalization. . TIle changes being made by T'r'-Lin to this intersection and hovv it v\'ill be constructed require lllnnerous changes to the plans to account for desigrl changes, signal location cllanges and maintenance of traffic (MOT) phasing revisions. . 1l1E' project's original scope of work could not have anticipated the property owner contesting the minimal ROW Acquisition at the corner and the late changes to the TY Lin Roadway, Signal and ivlaintenance of Traffic (2 tinles) Design and thus did not include the above tasks. Therefore this task is considered Additional Services . Services required to finalize the plans, specifications and estimates include: Site visits, Conceptual Alternatives (3); Roadway Design revisions (Plan and Profi10); Drainage Design revisions, Sketch and Descriptions and RO\V t\1ap Revisions; Coordination with nl Lin, Signa] Plan Revievv !\iIOT PIan revisions. b. Utility Drivejl\1agnolia Pond Drive Intersection Improvements - 522,716.23 . 'nlf' original scope of vyork VVdS revised during hO'?;-1 Design to design the Utility Drive/ivlagnolia Pond Tlrive Intersection as a Signalized lntersection with Collier Boulevard as opposed to directional lefts. Collier County Planning H'ljuested this due to the County being delayed in securing an agreen1t'nt ,vith an adjacent developer (Cit}1 Gate) for a portion l)[ \Vhite Boulevard (private road) to be transferred t(l the County. In addition, changt's associated ,vith the delayed construction of Noah's \Vay by the /\hefcia Developer also contributed to the need for d Signal Design and intersection revisions at the Cti1ity Drivcj\'lagJ101ia Pond Drive Intersection. Multiple concerts for li.lJ1e configurations (m CnIller Blvd. as v"lell as on Utility 1)r. were developed. . .~fter discussions ,vitJl TEei\1 Dl:sign, Planning and Traffic, it vvas determined that this v\'ould be included in the project bid plans as a itern No. '16A8 Q:::tc'ber 12, 20'iO Page "'12 of 58 Attachment A Change Order No.4 Collier Boulevard (SR/CR 95 I) Davis Blvd (SR R4) 10 Main Golden Gate Canal Project No. 6000 I signalized intersection with Collier Boulevard with minimum lane assignments to economical1y accommodate the interim condition of having a signal (temporary) at this intersection as opposed to where the permanent "future" Signal will be at the City Gate Drive/Noah's VVay Intersection. . The medians of Collier Boulevard will be designed to accommodate the signalized intersection in the interim condition while providing for the future reconfiguration of the intersections to Collier Boulevard directional lefts with minimum throwaway costs. . TIle project's original scope of work could not have anticipated the various alternatives and conditions that needed to be prepared and accommodated due to the changing developer agreements and plans (caused mostly be economic conditions). Thus the scope did not include the above tasks. TIlerefore, this task is considered Additional Services . Services required to finalize the plans, specifications and estimates include preparation of multiple Conceptual Design Alternatives and evaluation of b'affic operations. Once an alternative is approved: Roadway Design (Typical Section, Plan and Profile, Cross Sections, Signing and Marking, Signalization, Quantities). c, Design Changes resulting from Abercia Development - $37,386,89 The Abercia Development Agreement with the County has had a major inlpact on tlle design of the Collier Boulevard project due to site development changes, changes to Magnolia Pond Drive and Noah's VVay typical section, aliglUTIent and lane configurations, as "veIl as the fact that a significant portion of the west side ROWand Drainage Treatinent and Attenuation re'luirements of this project arc directly tied to the Abercia development. There were many changes to the agreement including postponement of development construction which occurred late in design (post 60% Phase) that will require significant design changes. Tllese items include: . Drainage conveyance system redesign for implementation of a Joint Use Pond with the Abercia development. TIle original design that was agreed to by the Abercia Developer and Collier County showed the Collier Boulevard Drainage System tying into tlleir parking area catch basins. TIlis stOlIDwater would then he h'ansferred to the pond via their internal conveyance system. Due to inten1al site conveyance constraints, the Developer requested that the County install their own >2,400 LF "h'unk line" pipe to convev the stonnwater to the agreed to Joint Use Pond. The County agreed to this modification and CH2M i:'?;n1 i~'J. 1'3;;3 J:-_t:J!:ie~ 2. _~C' ~ 0 ~j,' elf ~,E: Attachment A Change Order NO.4 Collier Boulevard (SR/CR 95 I) Davis Blvd (SR X4) to Main Golden Gate Canal Project No. (,000 I HILL will be required to redesign the onsite drainage svstem and convevance. . Modifications to the Magnolia Pond Drive and Noah's Way Intersections wi]] be required due to Abercia Site Plan shifting locations in the coordinate system. CH2M HILL noted the error in the Abercia Site Plan and both Developer and CH2M HILL will be required to modify their design plans. . County Planning Deparhllent requested that CH2M HILL prepare conceptual design alternatives (a :,-lane and 4-lane roadway) to realign J\.lagnolia Pond Drive to accomlllodate initial roadvvay / site planning as \\Tell as future road\,vayjsite planning to minin1ize unnecessaY~y initial costs and future throw-away costs ''v hen the signalized intersection was evenhlaIly moved to the City Gate North/Noah's Way Intersection. . Preparation of documentation of drainage calculations for inclusion into the Abercia Permit submittal to SFV\'MD and revisions to Collier Blvd Permit due to the changed Abcrcia Permit submittal. . l~evisions to the pdthway andhern1 treahllent behveen l'v1agnolia Pond Drive and Noah's 'Vav to acconl111odate the Abercia Developer's request in order to maxin1ize their site parkil1g without a re-desihT]1 on their part \\'hieh could have affected their existing agreement \-vith tlwir con1111ercial client. . Preparation of Conceptual Conveyance System, Treabnent Pond Design. J\lain Golden Gate Canal Ditch Improvements for Meetings and Coordination with SFWMD. . Preparation of "initial" conveyance system and pond design due to the .Abercia Developer postponing Cl1J1stnlCtion of the deveJoplnent, requiring CollIer Cnunty to indude cOl1sh'uctlnn of tIll' /\bercia pcmd and outfall in the'ir project. . rlH' project's original scope of \"'ork could not have anticipated the requested design chi1nges nor changes tn the A.bercia Df'velopTI1ent Agreenlcnt \yith Collier County and thus did 110t include the ahove tasks. Therefort' this task IS considered Additional Services. Please Note: All changes requested dnd 111ade benefitted Collier County as part of the Abercia Developer Agreelnent. . Services required tn finalize the plans, specifications and estilllates include preparation of Conceptual Design Alternatives for J\1agnolia Pond Drive; ~oah's \-'\'a)', Roadway Design (Typical Section, Plan and Profile, Cross Sections, Signing and \1ar"king, Quantities); Significant Attachment A Change Order No.4 Collier Boulevard (SR/CR 95 I) Davis Blvd (SR g4) to Main Golden Gate Canal Project No. 6000] item NCJ.16A8 Octobe:"12,2010 4:.1 of 58 Drainage Design and Conveyance System Changes; Signalization Design, Permit modifications; Survey, ROW Sketch and Descriptions and Map revisions. d. City Gate Blvd, NjNoah's Way Intersection Improvements - $19,826.66 . The original scope of work was revised during 60% Design to design the City Gate Blvd. North/Noah's Way Intersection as a Directional Left Intersection with Collier Boulevard as opposed to a signalized intersection. Collier County Planning requested this due to the County being delayed in securing an agreement with an adjacent developer (City Gate) for a portion of White Boulevard (private road) to be transferred to the County. In addition, changes associated with the delayed construction of Noah's Way by the Abercia Developer also contributed to the need for directional lefts from Collier Boulevard NB and SB. Multiple concepts for lane configurations on City Gate Boulevard North and Noah's Way were developed. . After discussions with TECM Design, Planning and Traffic, it was determined that this would be included in the project bid plans as a directional left intersection with Collier Boulevard with maximum typical sections built (but initially sb'iped out) to economically accommodate the interim condition of having directional lefts (temporary) at this intersection as opposed to the permanent "future" Signal. . The medians of Collier Boulevard will be designed for initial directional lefts that would acconmlodate a signalized intersection when it is reconfigured in the future with minimum throwaway costs. The foundations for the future signalized intersections will be designed and located to avoid construction issues and utility conflicts in the future when the signal foundations and poles are installed. . The project's original scope of work could not have anticipated the various alternatives and conditions that will need to be prepared and accommodated due to the changing developer agreements and plans (caused mostly be economic conditions). Thus the scope did not include the above tasks. TIlerefore, this task is considered Additional Services. . Services required to finalize the plans, specifications and estimates include preparation of multiple Conceptual Desipl Alternatives and evaluation of bAfic operations. Once an alternative is approved: Roadway Design (Typical Section, Plan and Profile, Cross Sections, Signing and Marking, Concept Signalization, Quantities). Attachment A Change Order No.4 Collicr BoulevarJ (SR/CR 951) Davis Blvd (SR X4) tn Main GolJen Gatc Canal Project No. 6000 I :';!~b ':,:~~.: !-k" ';j. ,> ,'- 'l' ~:);'J -';fj or :';,3 e. Evaluation of Existing 48" Water Main under 1-75 - $5,993.56 . TIle proposed widening design of Collier Boulevard under the 1-75 structure \\'ill result in a portion of the existing 48" \Vater :l\,lain being located under the proposed left turn lane from Collier Blvd SB to 1-75 SB. SUF was performed to verify the depth of the line. . Upon investigation of the existing utility it was found that the depth of the 48" water main along CoIIier Blvd SB w1der the 1-75 Bridge was shallower than shown on the As-Built plans obtained at the County Utilities offices. Instead of -18" of C(1ver shown on the As-Built plans, there was only %" of C(1ver (per SUF Investigation) in some locations. This meant that the proposed widening would result in a 1110 ft section of the pipe having a 111ininluln depth of cover of less than 36". . After l1H::,etings ,-vith Collier County staff, a revised design (Design Change No.1) was prepared which showed that the 48" pipe could remain in place with 100' of the pipe located under the left turn lane from CoIIier Blvd SB to 1-75 SB. This 100 ft section of pipe had a minimum depth of cover of ~-l.5" to %". County PUFD initially agreed to the solution and it \-vas presented to the FDOT. . As a stipulation of their approval, the FDOT required profile and cross slope changes to the concept (Design Change No.2) to eliminate the existing 1m;\' point frenn heh,\'pen the 1-75 NB and 5B shuctures. . The redesign \vas cOlnpleted and approved by FDOT, hov.'ever, Collier County PUFD indicated that the cover and location of the I ()(Y of pipe V.'dS not acceptable and V\T()uld require it to he relocated. . Due to the excessive cost of relocating the existing 48" \\'aterline. t]le FDOT agreed to a reduction of the proposed length of turn lane (so the existing 4H" \\'all'r 1113i11 would nol be under the turn lane and also agreed to accept a design \'ariance for the Collier Blvd 58 roadwa\'. 111is required a third redesign of thE-' road-vva:y under 1-75 (Design Change No.1). . llw project's original scope of \vork could not have anticipated the issues assoclated \,vith extending the left turn lane and the resulting sub-standard cover on the existing 48" \'Vatcr n1ain since no utility investigations -vvere done before the scope was developed and thus did not include the above tasks. Therefore, this task is considered Additional Services . Services required tn finalize and obtain tht::, FDOT Pennits i.nclude Coordination, ~i1pptings, Field InVl!stigaool1s, Uti.lity :;-D i\1odeling 112m i'~o 16A8 '::Jctobel' i 2. 2010 Page 46 of 58 Attachment A Change Order No.4 Collier Boulevard (SRJCR 95 I) Davis Blvd (SR S4) to Main Golden Gate Canal Project No. 6000 I Cost Estimates, and Roadway Geomeh-y 01anges (Typical Section, Profile, Cross Slope) and Roadway Plan Changes (Design I, Design 2, Design 3) 10. Collier County Requested Improvements for Future Development: Due to continued growth and development, many site conditions on surrounding County FOOT and/or developer projects change during the design period which requires redesign efforts. This is required in order to make the projects compatible and avoid future throw-away construction by incorporating the changes at a later date. These changes generally require additional coordination, design survey, design analysis and revisions to the construction plan documents. Additional Services that are required and will be provided by the Engineer include the following: a. Beck Blvd Realignment and Addition of Right Turn Lane - $30,440.33 . Based on the RO\V restrictions of Davis Boulevard, the Davis Boulevard lane geometry was revised by the FOOT Consultant TY l.in to remain within the existing ROWand an eastbound free-flow "ramp" was designed behind the commercial corner parcel. As a result, Collier County requested that the alignment of Beck Boulevard be redesigned to better align with the revised configuration of Davis Boulevard. . Collier County Planning also requested that a separate right turn lane for Beck Boulevard be designed at this time to acconunodate the future traffic demands of Beck Boulevard. . This additional right turn lane will require access management changes. a retaining wall to reduce right of way impacts to the adjacent connnercial development, and the requirement for acquisition of 2 new ROW parcels. Inclusion of these changes with this project would reduce" throwaway" costs and eliminate impacts to the Collier-Beck intersection in the future. . The project's original scop" of work could not have anticipated the late changes to Davis Boulevard due to ROW issues faced by the FDOT and the modifications to Beck Boulevard requested by Collier County Planning to accommodate the future needs of Beck Boulevard. Therefore, this task is considered Additional Services . Services required to finalize the plans, specifications and estimates include Roadway Design (Typical Section, Plan and Profile, Cross Sections, Signing and Marking, Quantities); Retaining Wall Design; Access JvIanagement revisions; Drainage Design; Permit Attachment A Change Order No.4 Collier Boulevard ISR/CR 951) Davis Blvd (SR X41 tu Main c;"lden Calc Canal Pmject !\Io. 60001 . !Ci. '!C:,':\B ')~~Lji>R' 1:~, :~(i 0 ..:17 c/ :-<:_: modifications; ROW Sketch Jnd Descriptions and ROW Map re\'1SlOns. b. Future Beck Boulevard Extension Drainage Revisions - $9,616.98 . During design of the Phase II Plans (60%) CH2M HILL was requested by Collier County Planning to revise the size of the drainage trunk line and proposed dry detention area to provide additional capacity in the storm water drainage system to aCC01111TIodate the future expansion of Reck Boulevard to the east. . TI1ese revisions would eliminate the need in the future to modify the drainage conveyance systen1. . 1l1e project's original scope of \'\'ork could not have anticipated the request madc by Collier Countv to accommodate the future needs of Reck Boulevard. Therefore, this task is considered Additional Sen1lces . Services required to finalize the plans, specifications, estinlates and penl1its include Drainage Design, Dry Pond revisions and Pernlit lnodifications. 11. Resolve Surrounding Property Issues: During construction, issues arise due to stakeholder concerns that need to be addressed in a timely manner to expedite design and construction and/or convey a positive public image associated with the project. Concerns and requests from adjacent property owners are received and reviewed by County and project staff for resolution. Additional Services that are required and will be provided by the Engineer include the following. a. Addressing Eminent Domain Issues with Property Owner - $21,373.31 . During Design of the FOOT Da,'i, Boulevard Project and Collier Count,\-.' Collier Boulevard Project an adjacent property o\\'ne1' on the northwest COll1er of Collier T10ulevard and Davis Boulevard contested the minimal POW Acquisition (comer clip) of their property. TIle County requested that CH21\1 HILL review ROW needs, prepare exhibits, develop alternative concepts, and generate plans for geOlnetry, signing and 111arking, drainage and signalization that clarifies the need for the 111ininlum RO\V acquisition. TIle service to 'he provided by CH2)vl H I 1.1. include: f\/lt"t'ting Attendance \vith County and FDOT l\1ultiple Concept(s) cvaluJtion Attachment A Change Order No.4 Collier Boulevard (SRJCR 951) Davis Blvd (SR 84) to Main Golden Gate Canal Project No. 60001 Aaenda Item No. '16A8 .. October ',2. 2010 Page 48 of 58 o Three (3) Deposition Meetings with la",)'ers. o Preparation and Attendance at two (2) Court Hearings o 'Changes to Design Plans to address Judge concems o Reviews with FOOT to review revised signing plans and turn lane geometry . The project's original scope of work could not have anticipated the property owner contesting the minimal ROW Acquisition at the comer and the request of Collier County to assist them with defending the Eminent Domain case. Therefore this task is considered Additional Services . Services required to address eminent domain issues and finalize the plans, specifications and estimates include Field Reviews, Meetings with County and FOOT, Evaluation of Site Plans and Geometric Design Alternatives, Preparation for and Attendance at Depositions, Preparation and Attendance at Court Hearings, Changes to Design Plans, Reviews with FOOT. 12. SFWMD Additional Permitting Requirements: During the Permitting Phase of the project, the SFWMo requested that the project survey limits be extended to include the entire FOOT Interchange infield area as well as the outfall ditches up to the box culvert crossing locations. Additional Services that are required and will be provided by the Engineer include the following: a. Additional Survey Required for Extension of Project Drainage Limits - $28,322.64 . As part of the Original Scope, the anticipated survey boundary was limited to the extent of the proposed physical construction improvements utilizing the existing FOOT drainage facilities. . As a result of our initial design work, it became apparent that the field conditions along 1-75 within FOOT ROW had been modified over the years and the FOOT ditch facilities were changed from their original concept. . ln addition, SFWMD is requiring preparation and submittal of a signed and sealed topographic survey for the limits of permitted area up to and including all existing and proposed outfall locations. 1t has become necessary to extend the limits of the initial survey to include the limits of the existing FOOT drainage to the potential outfall, which is located approximately 4000 feet from the Project area, to :,:'-:fV I'Hl. 1 '~:':\2, Attachment A Change Order No.4 Collier Boulevard (SR/CR 051) Davis Blvd ISR X41 to Maio Golden Gate Canal Project :'-10. bOOO I ; --:l,)i:'~:O:' ,,:. 2~:l:J :1C: DC 53 verify flow direction and set the modified pre-design conditions for this project. . This is required to provide CH2M HILL enough information to complete design to 5FWI'vID and FOOT requirements so they would review and approve the Pennits. . TIle project's original scope of work could not have anticipated and did not include all the survey that was being required by SFWMD and FOOT. It would have been unrealistic to foresee that the SFWMD would insert the requirement for a full tnpographic survey to the outfalls during the initial project scoping. TI1erefore this task is considered Additional Services . Services required to gather survey data, finalize the plans, specifications and estimates and obtain 5FWMD Permits include site visits; extensive field topography survey; coordination and incorporation of new survey data into the original project terrain model. Drainage Design changes, drainage calculations and Pernlit lTIodifications. b, SFWMD Dewatering rem1;t - $9,994.91 . During the Permitting Phase of the Design Contract, Collier Cnunty requested that CH21'vl HII J, prepare a Dewatering Permit for the Project. TypicaIl~/ this is a requirelnent of the construction contractor, but the County requested that due to tlw SFWMD changing permit requirements, CH2M HII.I. prepare the permit to expedite the process. CII2M 1-1lI.1. will prepan' a Dewatering Permit which will be submitted with the Collier Boulevard FRP (Permit) for the project. This Permit will he available for the Conh'actor to use (or modify) when the project got's tel construction. . cnlt' project's original scope of work could not have anticipated these services vvhich "vere H.'quested by Collier County during the Pernlitting Phase. 'Ihis decision \-vas made to help the Conh-actor during consb"uction Clnd avoid potential project construction delays. -[11erefore this task is considered Additional Services . Services to prepan.:> and obtain the pt'rnlit include Dewatering Plans Preparation; Drainage Calrulations and Preparation of De\vatering Pern1it. 13. Utility Design and Relocation Services: During the scoping of the design of this project, it was agreed to by Collier County and CH2M HILL to exclude certain design Attachment A Change Order No.4 Collier Boulevard (SR/CR 95 I) Davis Blvd (SR 84) to Main Golden Gate Canal Project No. 6000 J !rsrn [\Jo. 16A8 :JcT'Ji)e~ ~i2 2010 ~E1gS ~C of 5d elements due to the uncertainty of what would be required. It was agreed that the Utility Design and Relocation Services would be added to the contract once the actual footprint of the project was determined and impacts to existing utilities could be evaluated. Only utility coordination, research and minimal SUE services were incfuded in the initial scope. The Additional Services that are required and will be provided by the Engineer incfude the following. a. Utility Design and Relocation - $160,001.30 . Once the project typical section, geometry and drainage facility design was agreed to and conceptually approved by the County, FDOT and SFWMD, the actual impacts to the existing facilities were determined. To construct the project in a limited ROW with existing and planned development adjacent to both sides of the roadway, relocation and/ or modification of the following utilities will be required: CASING EXTENSIONS (ON EXISTING PIPE) 24" ~:~~NG 8::~;ION RANGE : LENGT6~~ ' ~:lfTS I 30" CASING 838+52 i 31 L~ . 60" CASING I 801 +02 J 25 L~ COMMENTS -. NEW PIPE CONSTRUCTION ITEM STATION RANGE LENGTH UNITS ! 10" FM ' 837+81 TO 838+05 38 LF ._,- ._,-- f------ 799+97 TO 799+98 30 LF 812+75 TO 818+73 I 618 i LF 3 -- .~...-._- 12" FM 836+61 TO 838+24 I 186C 1 ---- - ~_:OMMENTS I j:~ , 838+ 19 TO 838+23 =r TOTAL -.j 837 +08 TO 838+57 39 f LF 873 LF 209 I CF ~1 LF_~24" CASING REQUIRED 52 LF OF 24" CASING REQUIRED --,-- - I --- ! I , 20"WM , 30" RWM , 838+48 9 I LF I TOTAL-- - T 21~ -~;--r' - ----- 791+69 TO 823+24 __ . 3,079 LF 435 LF OF 30" CASING REQUIRED 838+36 TO 849+87 1160 , LF ' 85 LF OF 42" CASING REQUIRED L,,_. , 91 LF OF 30" CASING REQUIRED Attachment A Change Order No.4 Collier Boulevard (SR/CR 95 I) Davis Fllvd (SR S4) to Main Golden Gate Canal ProJcct No. 60001 :i:::rn ,.lD ijl\e, Cr~::..:J)e: ~'j :.:U':J ~) 1 c' f ~i ~:: 36"WM 838+ 19 TO 838+63 845+42 TO 850+ 70 52 I LF I ~ -~-T 117 LF OF~8" CASING~~QUIR~D . I 603 I LF ___J TOTAL . 'n1f' project's original scope of \'\'ork specifically excluded these services. 1l1erefore this task is considercd Additional Services, . Services required to gather additional SUE data, finalize the plans, specifications and estimates and obtain DEI' Permits include meetings, planning, evaluation of relocation liInitations, additional SUE Investigation, preparation of Relocation Design; Plan/Profile Plan revisions to minimize impacts; Utility Adjustment Sheet revisions; Cross Section revisions and DEP Pennithng. 14. Reconfigure Plans, Specifications, Bid Tabs, and Estimates into Two (2) Bid Packages: The County has requested that CH2M HILL break the Bid Plans for Davis Boulevard Project (FOOT) and Collier Boulevard Project (Collier) into 2 separate projects. Project I Limits consist of the entire FOOT Davis Boulevard Project and a portion of the Collier Boulevard Project from Davis to Magnolia. Project 1/ consists of the Col/ier Boulevard Project from Magnalia to Main Golden Gate Conal. The Additianal Services that are required and will be provided by the Engineer include the following: a. Reconfigure Plans, Specifications, Bid Tabs, and Estimates into Two (2) Bid Packages: $22,002.44 . Services required to finalize the plans. specifications and estul1ates and obtain FDOT Permits include lneetings, separation of Plans l delinea tion of rrnkct Iinlits) \vithin the 2 Project Plans, separation of Quantities, separation of Estilnates. Preparation of separate Specification packages dnd Bid Tabs. Attachnlent B includes a detailed breakdov\'n of Tf'quired tasks and associated level of effort. 15. Final Signalization Plans for Collier Boulevard-City Gate North Intersection: The County has requested that CH2M HILL prepare Final Signalization Plans for the Future Signalized Intersection of Collier Boulevard and City Gate Drive North/Noah's Way. The Additional Services that are required and will be provided by the Engineer include the following.' a. Final Signalization Plans for Collier Boulevard-City Gate North Intersection: $25,181.55 Item hio. 'iG,6,8 Oc:tobe:- 12_ 2010 Pa;j~; 52 of 58 Attachment A Change Order No.4 Collier Boulevard (SRJCR 951) Davis Blvd (SR 84) to Main Golden Gate Canal Project No. 6000 I . Services required to finalize the plans, specifications and estimates include meetings, analysis, and preparation of Signal Plans, Details, Quantities and Estimates. Attaclunent B includes a detailed breakdown of required tasks and associated level of effort. 16. BCB Permits (Requirement of SFWMD): During review of the Project with SFWMD- BCB, BCB indicated that even though the project was not constructing anything within their ROW limits, a Permit would be required since we will be discharging storm water into the Henderson Canal. CH2M HILL will be required to prepare and submit a BCB ROW Permit. The Additional Services that are required and will be provided by the Engineer include the following: a. BCB Permits (Requirement of SFWMD): $7,003.89 . Services required to obtain BeB ROW Permits include meetings, coordination, preparation of ROW Permit and Plans Submittal. Responses to comments. Attachment B includes a detailed breakdown of required tasks and associated level of effort. 17. Plan Revisions due to Delay in Abercia Site Construction: Due to the current ecanomic situation, the Aberica Development will not be moving forword with their planned development. The Collier Boulevard Project was utilizing portions of the Abercia site for droinoge stormwater treatment and attenuation. CH2M HILL will be required to modify the Project Plans to canstruct portions of the lateral ditch system with the Collier Boulevard Project to treat and convey project run-off. The Additional Services that ore required and will be provided by the Engineer include the following: a. Plan Revisions due to Delay in Abercia Site Construction: $19,928.90 . Services required to finalize the plans, specifications and estimates and obtain FOOT and SFWMD Permits include meetings, coordination, revisions to project Plans Cross Sections, Quantities and Estimates and SFWMD Permit Plans. Altaclunent B includes a detailed breakdown of required tasks and associated level of effort. 18. SFWMD Dewatering (Water Use) Permit Modifications: During the Coordination and Review of the Project Dewatering Permit, SFWMD (Water Use Dept) requested modifications to the approach and configurotion of the treatment and containment systems. A Technical Report will also be required. CH2M HILL will be required to conform to the requests in order to obtain 0 Dewatering Permit for the Project. Attachment A Change Order No.4 Collier Boulevard (SR/CR Y5 I I Davis Blvd (SR X4) to Main Golden Gate Canal Project No. 6000 I ..:'.;"'::' 'jD. ! '~j '\.o "0> -(,..r, I':-._:,)I\..' ::~.) ~)~ :';,s .-\:'E>i:J;:;; ~iem Additional Services that are required and will be provided by the Engineer include the following: a. SFWMD Dewatering (Water Use) Permit Modifications: $12,389.14 . Services required to obtain the IJt'\yatering Pl'rn1its includes revisions to Pern1it, Penl1it Plans and Calculations, Preparation of Technical Report. Attachment R includes a detailed breakdown of required tasks and associated level of effort 19. Retaining Wall Design- Lateral Pond Reconfiguration: During the Coordination and Review of the Project Permit, SFWMD requested modifications to the configuration of the treatment and containment systems- lateral ponds to provide additional (SO% based on future Permitting Regulations) treatment and storage. This required the reconfiguration of the swales as well as the addition of retaining walls on one side of the treatment swales to eliminate the need for additional ROW (since it was not available). CH2M HILL will be required to conform to the requests in order to obtain on ERP Permit for the Project. Additional Services that ore required and will be provided by the Engineer include the following: a. Retaining Wall Design- Lateral Pond Reconfiguration: $23,152.86 . Services required to obtain the SFWMfl FRP Permits include revisions to Lateral Ditch Design, Cross Sections, and Quantities, Preparation of Retaining VVall Plans, Quantities and Estinlates, Attachment B includes a detailed breakdown of required tasks and associated level of effort 20. Typical Section Pavement Modifications Under 1-75: During the Coordination and Review of the Project Permit, FOOT (HDR) requested additional drainage modeling efforts assaciated with the Recovery Analysis. Based on the requirements, the lateral ponds retained run-off longer than previously modeled and therefore clearance to pavement base fell below acceptable depths. To accommodate the new modeling, the pavement typical section was revised to include "black base" in certain areas which provided the required clearance. CH2M HILL will be required to conform to the requests in order to obtain 0 FOOT Permit for the Project. Additional Services that are required and will be provided by the Engineer include the fallawing: Attachment A Change Order No.4 Collier Boulevard (SRJCR 951) Davis Blvd (SR 84) to Main Golden Gate Canal Project No. nOOO] a. Typical Section Pavement Modifications Under 1-75: $7,912.32 Item ~~o. 16.L\8 20'iO 'Jf 53 . Services required to obtain the FOOT Permits include Modeling of new Recovery Analysis, Changes to Typical Section and Cross Sections, Revisions to Quantities and Estimates. Attachment B includes a detailed breakdown of required tasks and associated level of effort 21. Services During Construction - Shop Drawing Review: The County has requested that CH2M HILL provide Shop Drawing Review assistance to the County, on a Lump Sum Basis, Owing Construction of the Project. Additional Services that are required and will be provided by the Engineer include the following: a. Services During Construction- Shop Drawing Review: $25,269.80 . Services required include coordination with Project CEI Firm, Review of Contractor Shop Drawing Submittal(s), Response to Submittal(s) (Acceptance/Comment/Rejection), Coordination with Conb"actor, Meeting Attendance. Attachment B includes a detailed breakdown of required task(s) and associated level of funding 22. FOOT 100% Comments - Design Change Requests: During the FOOT review of the 100% Project Plans, the FOOT requested changes to the Plans that would help aceommodate 0 future planned FOOT Project. These changes ore related to clear zone issues and future 1-75 ramp improvements and included Bridge Mounted Sign Panel Modifications, Lighting Reloeotions and Signal Redesign (110eotion). The Additional Services that ore required and will be provided by the Engineer include the following: a. FOOT 100% Comments - Design Change Requests - $62,115.56 . Services required to finalize the plans, specifications and estimates and obtain FOOT Permits include meetings, analysis, evaluation of relocation linutations, additional SUE Investigation, preparation of Lighting Plans, Signalization Plans, Bridge Mounted Sign Plans. resubmittal of FOOT Permit for Approval. Attachment B includes a detailed breakdown of required tasks and associated level of fW1ding 23. Expert Witness-Deposition: The County has requested that the CH2M HILL EOR (Fronk Scerbo) be mode available to assist the County (provide expert witness services) with any issues or claims that may arise during the ROW Process. !t-:::rr! i~C. fjL'Ji Attachment A Change Order No.4 Collier Boulevard (SR/CR 95 I) Davis Blvd 15R X4) 10 Main Golden C,alc Canal Project No. 6000 I ~:GIJS: I ~. ~~C; 'j ':J ;c:,-' Additional Services that are required and will be provided by the Engineer include the following: a. Expert Witness-Deposition: $12,250.24 . Services required include T\ileetings, Preparation for Depositions and/ or Court Appearances. Attachment B includes a detailed bredkdo\\Tl of required tasks and associated level of funding 24. Services During Construction - Miscellaneous Services: The County has requested that the CH2M HILL provide assistance to the County on a Time and Materials 8asis, During Construction of the Project. Additional Services that are required and will be provided by the Engineer include the following: a. Services During Construction - Miscellaneous Services: $100,295.94 . Services required include Meetings, Response to RFI's, Field Coordination, and requested Design Changes During Construction. Attachment B includes a detailed breakdown of required tasks and associated level of funding PART 2. - Project Schedule: Changes to Project Schedule - To Be Detenl1ined PART 3. - Exclusions: Services other than those specifically listed above are not included in the Scope of Work for this Change Order. PART 4 - COMPENSATION I [-..21..... Lump Sum Task(s) 8-22 I Time and M;;;rials TaSk(~) 23.24------- . U ---!-$;12.546.18 _..___._...._._._._____~.__. ._.._._._______.__ 1__.___ ..___ ____!?~AL Cost~~ange Order NO.~ ~~,330'~1 Attachnlent B includes a 11101'1.:' detailt'd hrcakdc)\vn of tht-' labor hours and. costs associated -with the alxl\'t' Sun1111 '-11"\ , ()( Costs. u S[jmmary of C;Es~s $837,784.17 A:Jenda Ilem i\lo. 16/\8 '10 ~tb8 0"l>.)0:..; ,t... Page :,(1 Collier Boulevard (Davis Boulevard to Main Golden Gate Canal) Change Order No.4 CH2M HILL Attachment B 1-----.---- ----'-11 SENIOR -'l PROJEc~l- i~~~ ~EEi~---r DES ! DRAFT CLERK i REVIEW 'I MGR I P!~~T TECH i TECH I TECH STENO i TOTAL HRS IS 147.95 S 132.42 $105.04 $ 90.25 $ 72.50 $ 53,26!$ 51,78 Task B - FOOT Design and Permitting Requirements (Lump Sum) T8Sk 8a-Typical Section AeVi&iOnS8nd. R08dwayAedef;ignOuetoFD OT[~ 417J 634 I 526 I 0 I~r- 46 Comment and Approvals .' \ _'~ I - __ ' -,_ ~ 11ConcetualDeslnAIlernahves ~7 1!\4: 24 I 21 T icalSeclionPackaoeRevisions 12 12 12 B 3\T IcalSections 4 ,B If; 4 Summarvol DrainaqeSlruc\ures I 2 4 _.4 4..... 5)PlanandProlileSl1eelS t2 80 100 tOil 5) Oraina eStruclufeSheets 8 ?4 24 20 ~ ~;o~i~s:~~o~:vemenIMarkin .-.-+-~~: i----%-+-li-----^ 9 Util,l Plans B 16 24 18 10\ MOT Plans and OBlalls I 12 II 30 8 11 OuantltlBsandCoslEstlmates 12 8' 8 40 12 Proioct Mana ement 32 32 32 32 13181 nallzalion 16 8 B B 14 Water Manapamenl Oesil<n and ERP Pe'miltlnq 12 I 88 100 11? 15 Dra,na eOBsl n "------------"j- . 1-4'-------!--.-86 164 88 Task II TASK DESCRIPTION CONTRACT RATES LABOR COSTS '''' 198,254,49 " e " Task 8b _ Preparation ot an FOOT Interchange Analysis and Operallons 3 J '" 1 , I " , , , 3" . 23.735,54 Reporlllnd Melhodology Leller of Understanding 1'IMLOU -I-- " , i - -~.- 2iTrallicAna's;s , " 20 3\ SyncroModelin and fvalu~lIon 3C '" 1--. 4) Re 0>1 r10AR) - .- , 30 " , -~ 5\ Pro'ecIManaQeme~1 '" --, I> OAfOC " , Task8c, Addllional FDOT Permllling Ae<;uiremenls ~_ ~g;ji;fwpa:r~~r;:~~~::SF.rmil and Plans :l., S'onal,zallon."S,ql1lnQ and Mar~lna/Lll<hj'n 4lPr(ljecIManaqemenl 510AiOC - -, , , '" " ---+- + " '" 30 " PermrlandPI<lflS 3C '" + 12 8""-- '~--~-I _ ~.~ ~J--+-."~- " 5" 317 $ -~ 31.858.31 " " " , " -- Task 9 _ Match to As-Built Conditions of Existing and Concurrent Projects (Lump Sum) ----r " ' ~;;. ~:~~:"~::";::,:':"~:':~::m,:~::': """pm,"' I::. ~I ~ ': - 2.1 Modi'LCal'Qns to Maonolia Pond OrlvelColI'ar 1n18rSBC1'On 8 f, 25 E.O 3.IConce tual Oesi n All for a 3-Lane and 4-Lane MAqnoll<l 8. 12 i -30 ' I 4,Pre aral'ono!Rev,sedDraln~ ~CalculahonstorAtJe'cl~Pe'r:l't; 5 ,~e' ~~ _~'onstoPathwavIBe'm,AdlaCenl\OOeVelopment . _"..,,1~4_ 8,,20 r-,. j f--.. -. ;'~~.o~n~c~Eeg~~~'eO~~i~:a;..~~~e;..;r~~~~~."e.'.;~.;d~iMG.GDi."._hO~.',..;.+ __ --~.~. .'.0 - ~ 4...' ,,.-. _~ _---mt~foler;tManaqeme':'-I_ _.__"._ - '10.. ,: .~ _L.. -- _'_L==I-- 9 QAQe ~ ~t ,', t9' ~~',- I, ' , ~" Task 9d ' City Gate Blvd. NorlhlNoah's Way IntersectIon Improvements y < 49 21 0 $ , 1) Concep1ual Allernallves ? ~?4 I ~ =1 2',TvoicaLSectlons ~ 3 _4 j 4 ___ ~~:~~~~:~~~~~~i~8sneels -^.....~r--;, .. ',".- ;,~ _' 14.2" i,~-~l; ~ -----l 5JSlqn"'gandPavBtT'entMarklfl<;) <" ===t ==1 ;:~Z:~~~~:;:,~;~c""m"," _ ,; I >f:' 1=- ",=3= I I : i ; Ii ' "~":"1 "fl' 4 I I" ! i . TaSk9a_concePluaIAlternalives.'ndAeViSjOnstoNWcornero~'" . " BfK:klCollierlntertlectlons l\Conce tualAllernahves 4 ~" 21 Road,:"av DeSign Revls'ons u-----; _"_:' 8 3 Dra,naqeDeSlonRev'smn$ I 8 4'1 Slqnal Plan Rcvlcwsand Rev,s,onslTYLtNI 0 B 5'1 MOT Plan ReviSIons I?T,mesj 2 A ~1 :~:c~~"a~~:II~~~c~~d Rev,sions I 4 II' : B' OAI,'QC I" " 9 , , -, r- I -, , , , , , , '--"'- Task 9b - Utility Drive/Magnolia Pond Dtive Intersection Improvements 1'1 ConceplllaiAltematlves 2iTyp,calSectlOns 3'IPlanaf1dPmfllcSheals 4', C'oss Secllons S)Slgn,n and PavemenlM3rkln 6',Ouant'tie~andCoslESllmat"" -"-~7; Pro;ecl'Mana<lement---'----- 8 QAiGe Taskge 48"WalerMainUnderl'75 . , ;- - , I , ~~'"_ l)ICoorn'n'ltlonandMeelin.gs ~'eldlnves1,qallons 3 IUulllv3-DModel'n 4jlOuantllieS f--'-~~-ESlimatDs ..~. 6',Geolnell ReviSlons(T l1icaI.P,olile,X.$lo el 7) RQ~~~ilY Plan ChJnqes IDeslon 1.? 31 10160'2010 " , - " , Be '" , " " " " m " 9 " " " " 9 , '" , I .-.- '" 33,30tLS6 1[; " .-- L -oTo" I 22 -.- -- ~ I ,-1 i$ 22.716,23 '" " " I 1 1 -- 0 '" . 37.366.89 , -3 -"- , + J o 1 19.826.66 5,993.56 ColI,cr B,vd CO#4 - DiNlS Blvd - Ma,n Golder' Gal<, C~na'_ ~INAL REVc,_._100,,10.XLSX !~,e:'Y": i\:or{j.!:',E! ~)CtJi:'9;' ';1. 2C:1 (] :;:"Ir'r_c <58 Collier Boulevard (Davis Boulevard to Main Golden Gate Canal) Change Order NO.4 CH2M Hill Attachment B :'.' : 'I LEAD I LEAD SENIOR i PROJECT ENG,' i OES i REVIEW j. MGR ,PERMIT 1 . TECH 1 __ _ ; !'iPEC, L I CQNTRACTRATES '$ 147_951 $ 132,42 I $ 105_04' $ 90.251 $ '7250 1$ 53.26' $ 51.'78 Task 10 - Collier County Requested Improvements for Future Development (Lump Sum) Task10a-BeCk;O~I:~;r~-;;i1l1gnmentandAddl!i:~--O~RlghtTUmL~~;----- 36 98: 111 ~-[~- -- · "_J ',"~=-:::l=:::t= H I _,~ --"-i.2~-- I ~ 8 I _ ~ ,_~ 1-5 ~ 12 D DES. TECH DRAFT TECH CLERK STENO TOTAL HRS LABOR COSTS Task # TASK DESCRIPTION '" -,------- 1$ 30.440,33 -1 '1 Conccr>lualAltNnallve, 2',T\'plcaISect<on 3;, Summaly o~ [Jra,naQo StrUClures . 4,JPl3nand Profile Sheels b\IDralnaoeStructurcSlleels G\iCrossSeotlons '7'ISir>ntnoand Pavcm!'nt Markin 8 S,qnallzallOnPlansCoord'natloniDavls,8cckl 8'i Q'-'ilnt>lI1'lSiCostEshma!es 10' PrOlectManaoemenl ",ReW'"rnaWalls 1?\ Water M3naqemcnt [,es1qnandERPPprnlllllr' __ ~.~llE?ralnaCle Uf$lgn ;41IQA/Q8 I -, I :~p: , ' g I I , e .e e , " t:'; ~__~ t2,~t:~ " " I t- II Pond Details ~, Dra'''a(jCl StrlloH"" D"t~lr5 3'IWalm ManaqllmP:~~ DeRlqn and FRP P!'rmitlln~ A I Prf}I"~1 M~na~ement -- 5)QAiqC ~I . , " " o , .------j r:-T r , I i I 9,616_98 TaGk 10b-Fllture Beck Boulevard Extension Drainage l'Ievislons " , " , , " " " " -'. Task 11- Resolve Surrounding Property Issues (Lump Sum) '_i'MeetlllQS wrlh Counlv amI FDCl."!:_ -2IPreparatlf}nOIMultlpleCO"ccDts 3 Threei3', DeposrtlonMeehnqs ~ C~_~~ges to Deslqn PI~ns_i~~r_J_U(Jg_ll-'equ~Sl! ...5 'I Evaluale revised S'(jnlnq..'Genmplrv w,t~ FOOT " , -iJ--I----64 --.- "'---- -----'-~~~_5S'~~.- ., , r--- L_ ' L '" i. 21,3'73.31 Task lla - AddreSSing Iminen\ Domain Issues with Properly OWller 59 124 .,~ ., I I T----- --j 3 . u,_-----L--___" 1.IISI,,~(Fleldi , -~.. . 2 ~'Pfocess Survey Da;a-- Create rfi\i Moae' 31QAiQC Task 12 - SFWMD Permilling Requirements (Lump Sum) "'!_;I-; _ --------r------- , t ~:. 40 ----~---- ., I I Task 12a ' AddiHonal Sl1rvey l'Iequired fOf EXlension olPtoiecl Drainane Limits 23,0 0_0 n.O .~:~J 0,0 --~~ 1 --------=::1<) 1-=--:: L '"t-.'~''''' , 100_0 !S 9.994.91 Task 12b. SFWMD Dewalerinl1 Petmil , "!"'reoarJIIGr' nl pprm",-P'~ns and Ca;culatlc~!; "I,Prcparatl[)n ot Dewale"nll Perm~~_, 00 0.0 I i --"--~ 1', Pla'l ~nd Profile Shell! ?"\ICrOS5Sectlors--- 3:,;JIIIQ,ReIOcaIIM[leS'Gno .t'IUlilllyAdluslm"n: S~pe's S,I(Juantltlcs,CostE:stlmatp'"^ 6'I!Prol(>cIManaoe~1f'f11 7dOEP Perm'ttln~ ~&F-~:jJCES "NCWDEDII;-~~~A'C C~;STI Task 13 - Utility Design and Relocation Services (Lump Sum) - -c;;-_ ---"-~---; : .-r.;-r.u~,;;-;; --------,- ---'~--;;--'--,,; MJ ~, I ---+-lils^~oel t, '_f> [1 "I - I lor.lldp lilbor --.------,--------_80 ;\ :__f _-=-- ~ ~',LJLltprr'~}q ~-.--.6r' . , _=-- ~ ~~-~: ___=~- - -- _-_~ _; - I ~ ~ =~. ?C '4 _~_.!l.__ __ _~ i 2( ~51 IIf Task13a, Utility Aelocation Design Task 14 - Reconfigure Plans, Spectfications. Bid Tabs and Estimates into Two (2) Bid Packages (Lump Sum) 1,' ReVise Roaawa PI~n SI,ccts 2', Revl~"SlgninoandMarklna '-'Ian Shp('IS 3', '1ev'Sp.lIq~llno P;an Sheels- -- ~ :.1Rcv;se GLJan"lres Ann 8'Cilk 'nld 121-P~-O~C;C1S S',tRevlsef::s:lmates and Break ''''O(~\ Proerts ~f:~~~~:;es::,i,~~!~~: o! Bij Tao~ 8'1 Pro'ect Manaaerren~, CaorGlr1at'~n q,CiA,'OC ____ " " -:l 06 " "~ 22.002.44 ~-=-- '5 31 - ..-- 31J 1;' ,:', " ._--;~ ; ---I ..----------j :l Task 14a-AeconfigurePians in10Two (2) Bid Sets Task 15, Final Signalization Pians for Collier Boulevard-City Gate North Intersection (Lump Sum) Task15a-Final Sigl1al'zatlon Plal1s lor Coliier-Cily Gale Nol1h II1!ersection l:,SI~~at'~",PlanS ----'--i:" SI~nalrZfltro-n Dct;",s ---- 3\ SI~nJ"zaltet1 Ou~n"!le~ a~o I::str"'J1CS 4 PrO'Bcl Manaq"m~nl OA'QC " m " " I '''J' 25,181.55 r;- c,fI ---}- . q---c:==, '5 ,.'.j __1- p , , O/G,'20~ G '~'I'('I Ei,vc :'J";~,' [Ji;"JI<i B;vr' ',1"Ir' C;olucn Ciat(- Ca"" f'11"Ai f-IfV" '0061:-' XLS\ item 1\)0. 16/\8 'Jctobei 12,2010 PaQ8 ~18 of 58 Collier Boulevard (Davis Boulevard to Main Golden Gate Canal) Change Order NO.4 CH2M HILL Attachment B I I r "AD I I i I : SENIOR PROJECT, ENGI ~EEAD DES, DRAFT CLERK h REVIEW, MGR I PERMIT TE~H; TECH TECH STENO I TOTAL HAS LABOR COSTS -;p~;::- , ' Task# TASK DESCRIPTION CONTRACT RATES $ 147.951$ 132.42 $105.041$ 90.251S 72.50 S 53,261$ 51.18 Task 16. BCB Permits (Requirement of SFWMD) (L!Jmp Sum) Tas.k1&.a, BCBPermils. , I , " I " , , , " , 7,003,89 1\ Permll Pian Pre a'alton 2 '" " 2 Perm<IPreoaration , I , , , 2 3 Res ondloRAI's I 2 , 6 2 Task 17. Plan Revisions Due to Delay in Abercia Site Construction (Lump Sum) Task17a-Plan Revislon$ Oue to Delay In AberclaSlleConslruclion 6 I 20 " " " , , '" , 19.928.90 l' Draina eAnal sis , , >0 B 8 2) Plan Sheel Revisions , , ? 6 " 8 I , f--- 3) CrossSecllOnRev<sions __-0 -!-+ , " , I - , QuantiliesandEsllmaleS " " '" , 51ERPPerm'l11 Mod,flcallons , , , " , , 5'1 FDOT Permi1HnQ MOd,f,calirms - , , , 2 -+ , u._. 71 ROW Revisions , , , 2 Task 18. SFWMD Dewatering Permit Modifications (Lump Sum) Task 18a - SFWMO Dewalering Permit Modifications , i "m" , 1 , I , I He 12.389.14 ~- I , , RevisionSloA roachandCalclJla1lons -... -.2 4 16: 16 ---,- 2 Inclus,on 01 1-75 Infield Areas (4 Ponds) In Permit 4 28: 16 "-.- 3 Pre arat,on01 Oewatenn Report , __4 i6 _ 8 ~-- -- Task 19 - Retaining Wall Design. Lateral Pond Reconfiguralion (Lump Sum) Task 19a-Retaining Wall Design,Lateral Pond Reconilgllration , I 30 " " 60 , 0 i 0 I '" . 23.152.86 i 1 -- 1--, DrainaqeAna'ysls L , I- - " "" I B - I 2 Lateral Ditch Redesi n 2 " " - " 31 Relalnlno Wall Desl n , ; , " , Plan Revls'ons , " , " " 5'1 CrossSeel,onModillcallons " " -- 61 Quanlilles aEd Estimales , ;6 20 " Task 20. Typical Section Pavement Modifications under 1.75 (Lump Sum) Task 20a ' Typical Section Pavement ModilicatlonsllnderJ.75 0 I , i " " 0 0 i 0 eo , 7.912.32 I 1\IMorIclRecover Anals<s J , fl ' P 1~ I 2\Chan aT Ic"ISeclionandCrossSec,;ons .~ " ~ouantJllesanrJE_stlmales _ 6 _L T2 I ..----- Task 21 - Services During Construction - Shop Drawing Review (Lump Sum) --2~~ --~5.2~~ I , ~-l 0 Task21a' Services During Construction ShOp Drawing Revll!w , " " w i 11 Revi..wolSho Drawm a-Submittals - " 60 _1- " "0 , .~O -- Task 22 - FOOT 100% Comments. Design Change Requests (Lump Sum) ~ -~ , 1 ! Task 223 - FOOT 100% Comments Design Change Requests '" we " " , 36 1 .>0 , 62,115_56 , 1 , Llahlln Redesl nandOramaqelrn aels " -~~ I " , , " , 15.144.28 : 8 2f! : 4 18' 2' PhofomelricR I<UseVeilmq Lllrnlnance Rallo' >0 " , , 5.113.80 3 Voltaqe Dron Reporl , :~ " " . 4.223.% ____~;;~iZ~~~~I:~S~~~O~~~I~~~~~(~C:~~~1 ==1- 10 " G6 " T . 31.217_58 W " " . 6.355.94 ~~ m Task 23 - Expert Witness-Deposition (Time and Materials) I o~o I Task23a-ExpertWltness- Deposlllon (Davis/ColIIl!r Parcell , . 0 0 I 0 i , " , 12.250,24 1 11 Meetin s_DeoosiiJons - 36 - -, , 2 CO<1:1Apoearance, Preparat,on " I , Task 24. Services Durina Construction - Miscellaneous Services (Time and Materiais Task 241t, Services During Construction-Miscellaneous Services " : 300 I '" I >oe " i eo " i ", , 100.295.94 1jlAllencl Pro-eel K,ck-oli and PfooressMeelinQs 26 -he , 3? .- Ie 14? 2-, RespondfoRFI's 22 132 100 60 " " 6 420 3' FlelclCoorolnalionandConillcIResO'lJt'O'l 22 - ~ 00 I '" n " '" e '"0 CHANGE ORDER NO.4: TASKS 8.22 (LUMP SUM) I' 837.784,17 CHANGE ORDER NO.4: TASKS 23-24 (TIME AND MATERIALS) I' 112.546.18 TOTAL COST CHANGE ORDER NO.4: TASKS 8-24 i. 950,330.35 10/6/2010 Co,I,,,r Blvd COii4 - DaVIS Blvd. Main (ioldAIl Gate Can;,: ~-INAI REVS_100G10_X,--SX