Agenda 07/27/2010 Item #16C 7Agenda Item No. 16C7 July 27, 2010 Page 1 of 14 EXECUTIVE SUMMARY Recommendation to award Bid No. 08- 5011 -20, Repair of Four Sludge Presses at the South County Water Reclamation Facility, to Mitchell & Stark Construction Co., in the base bid amount of $281,550.00 for Project No. 73969, South County Water Reclamation Facility Technical Support. OBJECTIVE: The public purpose of this project is to maintain compliance with Florida Department of Environmental Protection- issued permit conditions at the South County Water Reclamation Facility ( SCWRF). CONSIDERATIONS: The SCWRF is a 16- million gallon per day water reclamation facility that treats wastewater from the South County service area. The SCWRF utilizes four sludge presses in the treatment process. The purpose of Project No. 73969 is to repair the presses that are critical components in the production of reclaimed water, and are essential for maintaining compliance. The four presses, manufactured by Komline Sanderson, have an average life expectancy of 7 to 10 years before repairs are necessary. Through a consistent and extensive preventive maintenance program, presses number l through 3 have been in operation since 1991 without requiring major repairs. Press number 4 has been in operation since 2004 and requires some repairs, though not as extensive as those for presses number I through 3. The cost of replacing the presses is approximately $275,000 each, or $1,100,000 for all four presses. Therefore, repairing the presses is the best -value solution. Request for Quote No. 08- 5011 -20 was posted on April 28, 2010, notices sent to all five (5) contractors under this fixed tern contract. Three contractors downloaded the specifications; only one quote was received. The qualified quote received is summarized in the table below Responder Quote amount Mitchell & Stark Construction Co. 5281,550.00 County staff determined the quote to be fair and reasonable and recommends awarding the contract to Mitchell & Stark Construction Co., as the only responsive and qualified local bidder. Mitchell & Stark Construction Co., did the installation of press number 4 in 2004 and, thus, has the extensive knowledge required for these repairs. FISCAL IMPACT: This project is consistent with the 2008 Wastewater Master Plan Update as adopted by the Board on June 24, 2008, as Agenda Item l OG. Project No. 73969 is on page 3 of 5, line 101. Funding for this obligation is available in the FY 10 Capital Budget adopted by the Board at a special meeting on September 24, 2009. The source of these funds is the Wastewater User Fee Fund 414. LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County Attorney's Office and is legally sufficient for Board action —JAK. Agenda Item No. 16C7 July 27, 2010 Page 2 of 14 GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATIONS: That the Board of County Commissioners, as the Ex- officio Governing Board of the Collier County Water -Sewer District • Award Bid No. 08- 5011 -20, Repair of Four Sludge Presses at the South County Water Reclamation Facility, to Mitchell & Stark Construction Co., in the base bid amount of $281,550.00 for Project No. 73969, SCWRF Technical Support. Prepared By: Oscar P. Martinez, P.E., Sr. Project Manager, Public Utilities Planning and Project Management Department. Agenda Item No. 16C7 July 27, 2010 Page 3 of 14 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS Item Number: 16C7 Item Summary: Recommendation to award Bid No. 08- 5011 -20, Repair of Four Sludge Presses at the South County Water Reclamation Facility, to Mitchell & Stark Construction Co., in the base bid amount of $281,550 for Project No. 73969, South County Water Reclamation Facility Technical Support. Meeting Date: 7/27/2010 9:00:00 AM Prepared By Oscar Martinez, P.E. Project Manager, Senior Date Public Utilities Division Public Utilities Engineering 7/7/2010 2:49:21 PM Approved By Margie Hapke Operations Analyst Date Public Utilities Division Public Utilities Division 717/2010 3:23 PM Approved By Thomas Wides Director - Operations Support - PUD Date Public Utilities Division Utilities Finance Operations 7/8/2010 9:26 AM -- Approved By Dale R. Waller Plant Manager Date Public Utilities Division Wastewater 7161201011:07 AM Approved By Tom Chmelik Project Manager, Senior Date Public Utilities Division Public Utilities Engineering 7/8/2010 11:09 AM Approved By Beth Johnssen IQ Water Manager Date Public Utilities Wastewater 7/81201012:36 PM Approved By Phil E. Gramatges, P.E. Project Manager, Principal Date Public Utilities Division Public Utilities Engineering 7/8/2010 1:05 PM Approved By Dianna Perryman Contracts Specialist Date Administrative Services Division Purchasing & General Services 7/8/2010 1:29 PM Approved By G. George Yilmaz Director - Wastewater Date Public Utilities Division Wastewater 7/8/2010 4:31 PM Agenda Item No. 16C7 July 27, 2010 Page 4 of 14 Approved By Jeff Klatzkow County Attorney Date 7/9/2010 3:53 PM Approved By Steve Carnell Director - Purchasing /General Services Date Administrative Services Division Purchasing & General Services 7/12/2010 11:37 AM Approved By James W. DeLony Public Utilities Division Administrator Date Public Utilities Division Public Utilities Division 7/1212010 12:54 PM Approved By OMB Coordinator Date County Manager's Office Office of Management & Budget 7112/2010 1:59 PM Approved By Susan Usher Management/Budget Analyst, Senior Date Office of Management & Budget Office of Management & Budget 7115/2010 5:19 PM Approved By Mark Isackson ManagementlBudget Analyst, Senior Date Office of Management & Budget Office of Management & Budget 7/15/2010 5:27 PM Agenda Item No. 16C7 July 27, 2010 Page 5 of 14 �Q 1CY C,_0141'TtY +r„v c REQUEST FOR QUOTATIONS UNDER CONTRACT # 08- 5011 -20 "Underground Utilities Construction Services" Date: April 27, 2010 From: Dianna Perryman, Contract Specialist 239 - 252- 4270(Telephone) 239 - 252 -6691 (FAX) diannaperryman @colliergov.net (Email) To: Prospective Vendors Subject: Quote: 08- 5011 -20 Repair of 4 sludge presses at SCWRF As provided in the referenced contract, the Collier County Purchasing Department is soliciting quotes for the referenced project. _ Your response must be received in the Purchasing Department, 3301 E. Tamiami Trail, Building G, Naples, Florida 34112 or via the On -line bidding system at www collieroov net /bid no later than 4 pm on May 14, 2010. Any response received after that time shall not be considered. All quotations shall be in accordance with the terms, conditions, and specifications stated herein and in accordance with the terms and conditions of Contract # 08 -5011 of which your firm was an awardee. NO OTHER FIRMS ARE ELIGIBLE TO SUBMIT OR RECEIVE AN AWARD FOR THIS PROJECT. If you have any questions regarding the specifications or intended scope of work, you must make those inquiries on the Collier County Purchasing Department On -Line Bidding website: wvvw.ccllier ov.net' bid by 4 PM on May 7, 2010. For general questions, you may contact the Purchasing staff member noted above. Your quotation response is due online at t .z.v. collier. ov nec' id no later than the date and time specified in the Public Notice on page three (3). The website will not accept any quotation responses later than the noted time and date. If your firm is unable to respond electronically, your quotation must be received in the office of the Purchasing Department at the above referenced address no later than the time and date specified. No late quotation responses will be accepted. We look forward to your participation in this request for information /quotation process cc: Oscar P. Martinez, P.E., Public Utilities, PPMD RFQ ContractDriven 04152010 1 General Information Agenda Item No, 16C7 July 27, 2010 Page 6 of 14 The SCWRF has 4 sludge presses that are in need of repair. Komlin- Sanderson, the manufacturer of the presses recently conducted an inspection of the 4 presses and generated a list of the parts that would be required to repair these. The job entails the following tasks: Task 1: Supply and install parts specified in the attached quote for the four presses at the South County Water Reclamation Facility; please refer to attached parts quote from Komline- Sanderson. Presses 1 -3 are under job # S2984 (see pages 1 & 2 of parts breakdown) and press 4 is under job S3803 (see page 2 of parts breakdown). Order of parts installation will start with press 1, then 2, the 3 and finally 4. Each press shall be completed and fully functional before work is begun on the next press. Only one press is allowed to be down for repair at any given time. Please provide a quote for labor and material costs for each of the presses. The County reserves the right to directly purchase the parts in the attached quote and award any or all the press repairs as budget permits. Task 2: Owner's allowance of $5,000 T & M. The County may elect, at its own expense, to have a factory certified rep present at start-up to commission the equipment. Please note that lead time for equipment shipment is 6 -8 weeks. H. Specifications Please refer to the attached Komline- Sanderson parts quote. Order of parts installation will start with press 1, then 2, the 3 and finally 4. Each press shall be completed and fully functional before work is begun on the next press. Only one press is allowed to be down for repair at any given time. Please provide a quote for labor and material costs for each of the presses. The County reserves the right to directly purchase the parts in the attached quote and award any or all the press repairs as budget permits. Substantial completion October 8, 2010 and Final Completion dates is October 22, 1010 respectively; however, these dates could be changed to later dates depending on parts delivery and County budgets constraints. III. Instructions 1. Complete Vendor's name, sign and date on all pages where so indicated. This will constitute your acceptance of the specifications, terms and conditions as listed. If taking exception to any part or section of this request for information /quotation, please indicate such exceptions on a separate sheet entitled "Exceptions." 2. Your quote may not be accepted unless all requested information is furnished. 3. The Collier County Purchasing Department reserves the right to reject any and all quotes. 4. All quotations must be made on the quotation form furnished by the County. No quote will be considered unless the quotation form is properly signed. UCI— ContractDri ven_04152010 2 Agenda Item No. 16C7 July 27, 2010 5. All work completed shall be under the terms and conditions of the above referenceCPage 7 of 14 contract. 6. Liquidated damages? None. 7. Performance and payment bonds shall be required if the lowest responsive quote exceeds $200,000. 8. Payments will be made for articles and /or services furnished, delivered, and accepted, upon receipt and approval of invoices submitted on the date of services or within six (6) months after completion of contract. Any untimely submission of invoices beyond the specified deadline period is subject to non - payment under the legal doctrine of "laches" as untimely submitted. Time shall be deemed of the essence with respect to the timely submission of invoices under this agreement. RFQ_ContractDri ven_04152010 3 Agenda Item No. 16C7 July 27, 2010 Page 801`14 �...(3LL7P_Y ��O�F2Cy COLLIER COUNTY FLORIDA REQUEST FOR QUOTATION Quote # and Title 08- 5011 -20 Repair of Four Sludge press at SCWRF Due Date: May 14, 2010 NON- QUOTER'S RESPONSE Non- ouoter's Response: In the event that you are unable to submit a response for this quote, please return this form to: Dianna Perryman, Contract Specialist, dianraoerrvmarna- -coliiereov. net, 3301 Tamiami Trail East, Naples, FL 34112. We are not responding to this Request for Information /Quotation for the following reason(s): Name of Firm: Representative Signature: RFQ_ContractDriven 04152010 4 Agenda Item No. 16C7 July 27, 2010 Page 9 of 14 vOLileY County COLLIER COUNTY FLORIDA REQUEST QUOTATION # and Project 08- 5011.20 Repair of Four sludge presses at SCWRF PROPOSALPAGE DUE DATE: May 14, 2010 The undersigned, as quoter, hereby declares that the firm has examined the specifications and is informed fully in regard to all terms and conditions pertaining to the project and, if this Proposal is accepted, to furnish same in full, according to the following: Item # Press # Parts 1 1 2 2 - 3 3 4 4 Labor Total 5 Owner's allowance: $5,000 6 Alternate 1: Payment & Performance Bond Total of items 1 -5 above: Alternate 1- Payment & Performance Bonds: Total of items 1 -6 above: IN WITNESS WHEREOF, WE have hereunto subscribed our names on this day of 20 in the County of , in the state of Firm's Complete RFQ_ContractD riven_04152010 5 Telephone Number FAX Number Email Address Address City State Zip Agenda Item No. 16C7 July 27, 2010 Page 10 of 14 Florida Certificate of Authority Document Number (www.sunhizor %sParoh,'html) Federal Tax Identification Title Print Name Date RFQ_ContractDri ven_04152010 6 Agenda Item No. 16C7 July 27, 2010 Page 11 of 14 Bid schedule for 4 sludge presses at SCWRF Item # Press # 1 1 2 2 3 3 4 4 Parts Labor Total 5 owner's allowance: $5,000 6 Alternate 1: Payment & Performance Bond Total of items 1 -5 above: Alternate 1: Total of items 1 -6 above: Agenda Item No. 16C7 July 27, 2010 Page 12 of 14 COLLIER COUNTY FLORIDA REQUEST QUOTATION # and Project 08- 5011 -20 Repair of Four sludge presses at SCWRF PROPOSALPAGE DUE DATE: May 14, 2010 The undersigned, as quoter, hereby declares that the firm has examined the specifications and is informed fully in regard to all terms and conditions pertaining to the project and, if this Proposal is accepted, to furnish same in full, according to the following: Item # Press # Parts Labor Total 1 1 $421472 $32,878 $75,350 2 2 $42,472 $32,878 $75,350 3 3 $42,472 $32,878 $75,350 4 4 $25,985 $22,015 $48,000 5 Owner's allowance: $5,000 6 Alternate 1: Payment & Performance Bond _$2,500 Total of items 1 -5 above: _$279,050 Alternate 1- Payment & Performance Bonds:—$2,,;00 Total of items 1 -6 above:_$281,550 IN WITNESS WHEREOF, WE have hereunto subscribed our names on this 14th day of May, 2010 in the County of Collier, in the state of Florida. Mitchell & Stark Construction Company, Inc. Firm's Complete Legal Name __239- 597 -21 Telephone -Number--- Contract!)6ven 04152010 1 ;olliefCounty Online Bidding System - Active Solicitations Active Solicitations . -.ri, ent 3cr: mtcns oPJe MY '.?1r..n4di}ny Agenda Item No. 11 1 of ] July 27, 20 Page 13 of 14 Solicitation Title: Repair of 4 Sludge Presses at SCWRF - Mandatory Pre -Quote Mtg.,S(4 at 10:30 a.m Press Bldg. SCWRF Solicitation Number: 0$- 5011 -20 ri •y I SpeclUCatjons,_Teemmnll ConSlltSgr1S 4 &A PlanhhQlde I Tabulation Agency: yl e Contact tc idn N qo- ... l Solicitation Si ri ay, May , 20 0 2110 ,00 PM0'00 nth Eastern Q&A taboo Ends: Friday, May 14, 104 4:00:00 PM fasterp S.b ,cs,cn e: Friday, May OJ, 2010 4:OOe0U PM Eastern Submission Method: EleRmnlc Commodity Subcommotlity 85011 - nwardii Only of 08-5011 (Expires 3/10/12) (otller) Tabulation Vendors Who Subscribe to Solicitation Commodities: Vendors Who Downloaded Specs:4 Vendors Who Submitted Solicitation: 1 Item Description: Sludge Press 1 - Supply and install parts for press one (1) specified in the attached quote at the South County Water Reclamation Facility; please refef to attached parts quote from Komline- Sanderson. Preis 1 is andef job 4 52984 (see Pages 1 & 2 of parts breakdown) Please provide Labor and material .. for each of the presses. Item Number: 1 vvvv =ndgr Compa_y Quantity Unit Price unit of Measure Subtotal Notes MitChell Stark Company, inc. 1 $75,350.00 LS $75,350.00 Item Descried., Sludge Press 2 - Supply and install parts for press two (2) specified in the attached quote at the South County Water Reclamation Facility; please refer to attached parts quote from Komline- Sanderson. Press 2 is under job P 52984 (see Pages 1 & 2 of parts breakdown) Please provide Labor and material cast far each of the presses. Item Number:2 vender Company pusntity Umt Price Unit of Muasurd Subtotal Notes Mitchell Stzik Carnparty, Inc. 1 'x100 LS $75,350.00 Item Description: Sludge Press 3 - Supply and install parts for press three (3) specified in the attached quote at the South County Water R throve fon Facility; Please refer to attached parts quote from Komline- Sanderson. Press 3 is under job V 52994 (see pages 1 & 2 of parts breakdown) Please provide Labor and material cost for each of the presses. Item Number: 3 Vendor Comsany Quantity Unit price Unit .1 Measure Subtotal Nate$ Mitchell Stark Company, Inc. 1 $75,350.00 S $]5,350.00 Item Description: Sludge Press 4 - Supply and install parts for press four (4) specified in the attached quote at the South County Water Reclamation Facility: please refer to attached parts quote from Komline- Sanderson. Press 4 is under job 53803 (see page 2 of parts breakdown). Please provide Labor and material cost for each of the Presses. Item Number: 4 Vch0o SP_ .paox M Achell Sled, Company, Inc. Vendor Grand Totals Vendor Commarry Mi Ini Stark Company, Inc. This solicitation has no adrnln fizlds I « Go m 5ollotabon Mist _ nre _ -", r, . enrcd b, vw - ._carne, Quantity Unit Price unit or Measure 1 €4[,000.00 S It eos Bid On 4 n.�1ut tptal $48,00000 Grand-Tptgl 5274,050.00 Notes ittp: / /www.colliergov. net / bid /default.asp9id= 6lB8E565 -603D- 4177 - BASE- 2918CI86EDE1 &show =tab 5117/201( Z rn O O LL 75 O Ul CL CL U) 0 6 E W z 11 CY CY ....... . . .... . .... .. . . CY .. . .. . . ................ . .. ....... . . . .... . . . . CY . . . . ... .. . ..... . cr CY iS . ..... . ....... ------------ Olt IE a . . ..... . . ......... . ... .. ........ . ........ . .. . ..... ....... -R o U m z 0 w '4 > FO 0 U IL