Loading...
Agenda 06/22/2010 Item #16D 7 Agenda Item' No. 16D7 June 22, 2010 Page 1 of 36 EXECUTIVE SUMMARY Recommendation to authorize the County Manager, or his designee, to approve Change Order #6 in the amount of $108,488.53 to BCBE Construction Co., Inc. Contractor for the Goodland Boat Park Project #80611.1 under Contract #09-5169 to provide additional scope of work due to unforeseen site conditions. OBJECTIVE: Request that the County Manager, or his designee, approve Change Order #f3 in the amount of $108,488.53 to BCBE Construction Co" Inc. contractor for the Goodland Boat Park Project #80611.1. CONSIDERATIONS: On May 13, 2009, the Board of County Commissioners awarded Contract #09-5169 to BCBE Construction Co., Inc. for the construction related services in connection with the development of the Goodland Boat Park Project. Since the commencement of the boat ramp construction phase of the project the contractor (BCBE) encountered unforeseen site conditions with unsuitable soil material. As the result of these unforeseen site conditions the specific design concept and construction method for the boat ramp required modifications and additional scope of work to complete the related task. The additional scope of work included the installation of large rip rap aggregates, installation of vinyl sheet piles as substitution for the concrete seawall panels, installation of filter fabric materials, and extended dock pilings. The total cost associated with this changed condition is $108,488,53, which represents an increase of 12.44% over the original Board approved contract amount. Staff has thoroughly evaluated and reviewed the cost associated with this change order and have determined that the cost is consistent with the prevailing industry rates for the intended scope of work, FISCAL IMPACT: There is adequate funding available in the Goodland Boat Park Project 80611 Impact Fee Fund 346-110418, LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County Attorney's Office and is legally sufficient for Board action. - CMG GROWTH MANAGEMENT IMPACT: This project is consistent with the Growth Management Plan Objective 1.3, Policy 1,3,2, to ensure that access to waterways remains available to the general public. RECOMMENDATION: Recommendation to authorize the County Manager, or his designee, to approve Change Order #f3 in the amount of $108,488,53 to BCBE Construction Co" Inc, Contractor for the Goodland Boat Park Project #80611.1 under Contract #09-5169 to provide additional scope of work due to unforeseen site conditions. PREPARED BY: Clint Perryman, CGC, PMP, Project Manager, Coastal Zone Management Department. Item Number: Item Summary: Meeting Date: Agenda Item No. 1607 June 22, 2010 Page 2 of 36 COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 1607 Recommendation to authorize the County Manager, or his designee, to approve Change Order #6 in the amount of $1 08,488.53 to BCBE Construction Co., Inc. Contractor for the Goodland Boat Park Project #80611.1 under Contract #09-5169 to provide additional scope of work due to unforeseen site conditions. 6/22/20109:0000 AM Approved By Clinton Perryman Public Services Division Project Manager Date Coastal Zone Management 6/3/20108:08 AM Approved By Gary McAlpin Public Services Division Director ~ Coastal Management Programs Date Coastal Zone Management 6/4/2010 10:20 AM Approved By Marla Ramsey Public Services Division Administrator - Public Services Date Public Services Division 6/8/20101:55 PM Approved By Kathy Carpenter Public Services Executive Secretary Date Public Services Admin. 6/9/20108:41 AM Approved By Jeff Klatzkow County Attorney Date Approved By 6/10/20109:39 AM Lyn Wood Administrative Services Division Contracts Specialist Date Purchasing & General Services 6/15/20104:20 PM Approved By Colleen Greene County Attorney Assistant County Attorney Date County Attorney 6/15/2010 4:44 PM Approved By Steve Carnell Administrative Services Division Director - Purchasing/General Services Date Purchasing & General Services 6/16/2010 5:53 AM Approved By OMS Coordinator Date County Manager's Office Agenda Item No 1607 June 22, 2010 Page 3 of 36 Office of Management & Budget 6/16/20108:23 AM Approved By Susan Usher Office of Management & Budget ManagemenUBudget Analyst, Senior Date Office of Management & Budget 6/16/20108:34 AM Approved By Leo E. Ochs, Jr. County Managers Office County Manager Date County Managers Office 6/16/20108:46 AM CONTRACT/WORK ORDER MODIFICATION CHECKLIST FORM PROJECT NAME: <9 ooCLAi-JD. 'BoA=1~OJECT #: M~ " . r PROJECT MANAGERCl.=5I &-J'pYMM ',)NTRACT#;~OD#: c", PO#~5-loS55owORKORDER#:~ DEPARTMENT: CONTRACTOR/FIRM NAME: ~~ CT'-O:>..J Agenda Item No. 1607 June 22, 2010 Page 4 of 36 Current BCC Approved Amount: $ 1, (o9'eJ. 02-0. 2--8 (StartIng Point) , I rr, q 0 . 02-0. "2-& (Last ~OUl't Approved by the BCC) $ 1."7QI. 7[30,0-4 (Including All Ctulnges Prior To This Modification) 106, ~86.S3 . Original Contract Amount: $ Current Contract Amount Change Amount: $ $ \, q (")0, Z a:>q. (-:r- (Including This Change Order) Revised ContractIWork Order Amount: Cumulative Dollar Value of Changes to this ContractIWork Order: $ Z.W, V1~,e:q Date of Last BCC Approval z.. 10. 0 '1- Agenda Item # I Q. E. Percentage of the change over/under current contract amount I 2.-44 Formula: (Revised Amount 1 Last BCC approved amount)-1 CURRENT COMPLETION DATE is): ORIGINAL:.JI. II. <D1_CURRENT: B. z.cI . /0 % -This change order will: C1 Add a new Task for $ o Increase Task Number by $ Other Describe the change(s): M. o~ "'" F-'l1+oD of C-o>>Sj12.Jc::;rt:c::>...J A-J..-lp. R.t==--ces~ f?Om-f<.AM.f> C-<o,J~~rJ D'-ll2- -ro (JJJH)~SF~.-...J 'S~ ~..;....DEj=w..Js.. Specify the reasons for the change(s) r 1. Planned or Elective ~nforeseen Cgnditions r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Work) ~ Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project if this chan order were not processed: o Cc::> s~ H,.e.c. SS~ This ~ge was requested by: ~tor/consultant ~er rJ Using Department r CDES !l:.o;;sign Professional rlRegulatory Agency (Specify) r Other (Specify) ~ u.L.:: CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: r Yes APPROVED BY: This form is to be signed and dated. ~ .ft'~____ - " . roject Manager Date: b. 2-. /0 REVIEWED BY: Date: , Contract Specialist Revised 4.10 Agenda Item No. 16D7 June 22, 2010 Page 5 of 36 TO: Chanae Order # 6 FROM: BCBE Construction Co., Inc, 3630 Enterprise Ave. Naples, FI. 34104 Board of County Commissioners Coastal Zone Mgm't Department 3301 Tamiami Trail East Bldg, "F" Naples, FI. 34112 Project Name: Goodland Boat Park Contract Dated: May 13, 2009 Change Order No: 6 Project No. 80611.1 Contract # 09-5169 (P,O, #45-105550) Change Order Description: This change order is necessary and required to address unforeseen site conditions and modifications to the scope of work as per the following considerations: The initial plans and specifications for the construction of the boat dock and boat ramp included the installation of concrete seawall panels, piling system, concrete ramp and the docking system, However, during the construction installation process unforeseen site conditions were encountered and required changes to the method of constructing the boat ramp, The unforeseen site conditions that were encountered included unsuitable soils below the water surface, preventing the minimum bearing penetration and resistance required for the installation of the concrete seawall panels, and pile driving system. Therefore, in order to proceed forward with the construction of the boat ramp objective. the process required the installation of large rip rap aggregates, installation of filter fabric, and placement of gravel bedding for the proper installation of the concrete ramp panels, In addition to the revised design plans, the concrete seawall panels were also replaced with vinyl sheet piles for the seawall, and the lengths to the piles were extended in the specific troubled areas, Additional value enhancements were also considered to include the installation of access ladders at the boat docks for safety measures, and the decks on each side of the ramp were extended at the ramp exchange. The revised design considerations were carefully engineered and evaluated by the design consultant to determine the least financial impact to the project. This change order will have a net increase in the contractual time duration by 30 calendar days. Original Contract Amount"...,....,...., ....".,.. .".."..,....,'..,......., ,$1,690,020.28 Previous Contract Balance.....,......... ..,.., ..".. ,.. ,....,..,.., ,.. .,. ..,..$1,791,780.64 This Change Order Amount...."..,..., ,..."...."................".., ,..., ..,$108,488,53 Revised Contract Amount ....................................................$1,900,269.17 Agenda Item No. 1607 June 22, 2010 Page 6 of 36 Original Contract Time in calendar days ....,.......................................240 days Previous change order adjusted time ..............,......................' ..... ....261 days This change order adjusted time in calendar days...... .........., ............ ...30 days Revised Contract nme in worlting da}'5....................................... 531 days Original Notice to Proceed date .............................................March 16,2009 Completion date based on original contracttime..................November 11, 2009 Previous Completion date......... ............ ...................................July 30. 2010 Revised complete date this change order...........................Auguat 29. 2010 Your acceptance of this change order shall constitute a modiflClltion to our Agreement and will be performed subject to all the same terms and conditions as conteined in said Agreement indicated above, as fully as if the same were repeated in this acceptance. Prepared by: .~- ~?~ Cllnt L. Perryman, CGC, Project Manager Coastal Zone Mall8~ent Department Date::$i";.~iY. .....0 Recommended by: -,\Chris , . Johnson Engineeri" C~~ Accepted by: 0 Barry Conner, Executive Vice President BCSE, Construction Co" Inc. Date 6f/zyho Date: 1? ./'?')IO / I Date: ,:j. /'~//i '/ f, ./, j./ u' .(1 2 Agenda Item No. 1607 June 22, 2010 Page 7 of 36 Final Dock related Improvement and Changes -'-..---'.- r' '-tCOP#46) _"..___#___...:_.0::.__ 5.11,10 ~,jg' Superintendent (Chuck Anderst) Safety Inspector Project Manager (Angel Napoles) Scheduling (Oayle Cartwright) Quality Control General Superintendent Temporary Office Temporary Toilets (one porte toilet) Temporary Water Temporary Electric Communication Equipment Fuel for Vehicle Trucks and Vehicles l~~~__ k~m~~~fAW~~ o o o o o o o o o o o o o $280.00 $98.00 01001 000 $0.00 $0.00 010040.00 $320.00 $112.00 010080,00 $25.00 $8.75 01012000 $0.00 $0.00 010150.00 $33.00 $11.55 012050.00 $638 $0.00 01301 0.00 $4.00 $0.00 01303000 $20.00 $0.00 013040.00 $30.00 $000 013050.00 $5.00 $0.00 013560.00 $36.00 $0.00 013580.00 $42.40 $0.00 01362 0.00 General Conditions Subtotal 0 00 5% Markup 0.00 Florida Marine Construction COP #26 COP #28 COP #32 COP #37 COP #39 COP #45 ""J>r"'"""-"''If,~)i'''''''''' i~'1t~!I:~~'m~~$i'&~~f}.f"?,,,,, f~. ~ Subcontractors 0.00 '/ Notes: This change request represents the culmination of several dock related COP's atlahced for reference. The current contractually agreed to date for Substantial Completion IS TSD The schedule Contract Time will be increased by X (TSD) working days by this Change Order The date of Substantial Completion as of the date of this Change Order therefore is To Se Determined Owner SCSE - General Contractor CONTRACTIWORK ORDER MODIFICATION CHECKLIST FORM .- PROJECTNAME:~OOC1.A1-Jt> 1X>A:1'R4IROJECT#:~~ fl., PROJECTMANAGERC1..:t:t.JI ~~ CONTRACT '~OD II: (p PO#~ s.. loL.>55o WORK ORDER .:--M-- DEPARTMENT: r."7 ~ CONTRACTOR/FIRM NAME: a.....- ~= C ~ \s::-re.....;lc:r=.J ~~.~ -p~~ ~vJ Original Contract Amount: $ !' (09'0.02--0. z-8 (Starting Point) , . $ (last ~o~nt ~~b~ :;1'CC) $--.J. '7Q I. 780.04 (IncluClng All Chdnges Pnor To This Modification) lOB, ~$.~3 , f-=1- $ $ l,'1t)O za:-q. (Including This Chanbe Order) Current BCC Approved Amount: Current Contract Amount: Change Amount: Revised Contract/Wor1< Order Amount: Cumulative Dollar Value of Changes to this ContrscllWor1< Order: $ ~IO, ~e>,eq . Date of last BCC Approval 2.. 10. o'l_ Agenda Item # 10. E- Percentage of the chsnge over/under current contract amount I 2. _ -94 Fonnula: (Revised Amount 1 Last BCC approved amount)-l CURRENT COMPLETION OATE (S): ORIGINAL: ~CURRENT: ~. ZLl ' 10 % This change order will: ' C1 hdd s new Task for $ Other o Incresse Task Number by $ Descrlbethechange(s): MO~ ~~ of c.o~~~ ~ ~-o~~~ f?Om-RA....t.f> c...c:>,J~;; ~ D '-lf2. r.uJ - ~<;F "":. r. oJ S. Specify the reasons for the challge(s) r 1. Planned or Elective ~nfOreSfl!ln C~ons r 3. Quantity Adjustments r 4. Correction of Errors (Plans, Specifications or Scope of Wor1<) ~ Value Added r 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s). Identify all negative impacts to the project If this chan order were not processed: 'T(Z..J M~ SS~ This ~ge wa.s requested by: ~or/Consultant ~er n Using Department r CDES ~19n Professional rlRegulatory Agency (Specify) r Other (Specify) rYes ~ CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS: APPROVED BY: Date: b .2-. /D REVIEWED BY: Date: & liS/It} I ' Revised 4.tO Agenda Item No. 1607' June 22, 2010 Page 9 of 36 TO: Chanae Order # 6 FROM: BCBE Construction Co., Inc. 3630 Enterprise Ave, Naples. FI. 34104 Board of County Commissioners Coastal Zone Mgm't Department 3301 Tamiami Trail East Bldg, uFo Naples, FI. 34112 Project Name: Goodland Boat Park Contract Dated: May 13, 2009 Change Order No: 6 Project No. 80611.1 Contract # 09-5169 (P,O. # 45-105550) Change Order Description: This change order is necessary and required to address unforeseen site conditions and modifications to the scope of work as per the following considerations: The initial plans and specifications for the construction of the boat dock and boat ramp included the installation of concrete seawall panels, piling system, concrete ramp and the docking system, However, during the construction installation process unforeseen site conditions were encountered and required changes to the method of constructing the boat ramp. The unforeseen site conditions that were encountered included unsuitable soils below the water surface, preventing the minimum bearing penetration and resistance required for the installation of the concrete seawall panels, and pile driving system. Therefore, in order to proceed forward with the construction of the boat ramp objective, the process required the installation of large rip rap aggregates, installation of filter fabric, and placement of gravel bedding for the proper installation of the concrete ramp panels. In addition to the revised design plans, the concrete seawall panels were also replaced with vinyl sheet piles for the seawall, and the lengths to the piles were extended in the specific troubled areas, Additional value enhancements were also considered to include the installation of access ladders at the boat docks for safety measures, and the decks on each side of the ramp were extended at the ramp exchange. The revised design considerations were carefully engineered and evaluated by the design consultant to determine the least financial impact to the project. This change order will have a net increase in the contractual time duration by 30 calendar days. Original Contract Amount ." ",.." ". .....,.. ...... ................ ""..., ....$1,690,020.28 Previous Contract Balance..,.....,............ ...... ...."....., .........' ....$1,791,780,64 This Change Order Amount........,..,..........,.........,... .........."... ...$108,488.53 Revised Contract Amount ....................................................$1,900,269.17 Agenda Item No. 1607 June 22, 2010 Page 10 of 36 .. Original Contract TI/TlB In calendar clays ........,.......... ""....... .............240 dllYll PreviOUll change order adjusted time .....""..."....".................. ......".261 days This change order acljUlted time in calendar days. " ,............................30 days Rwlaed Contract T/fMlrr wortlnQ daya............. .. ... ........ ... ......... 531 days Original Notice to Proceed date ............."..............................March 16, 2009 Completion cIate baaed on original contract time..................November 11,2009 Previous Completion date..................... .................."" ...... ......,Juty 30, 2010 Revlfid cornpletll dlIte thhl t:hMIge order............ ...............Auglmt B. 2010 Your acceptance of this change order shall constitute a modification to OIJr Agreement and will be performed subjecllO all the same terms and conditions as contained in said Agreement Indicated above. IIlI fully as if' the same weill repeated In this acoeptance. . ';:~.~:: ,'j ;~f-.,-.::~-,.~_ Prepared by: .~ ~~ ~ Clint L. Perryman. CGC. project Manager Coastal Zone ~oa~ent Department Date: ~..Z;IJ!I.o Dale 6#~11 Recommended by: /"Ehris '.. ~son Engin Aooeptedby: ' Barry Conner, Executive Vice President BCBE, Construction Co" Inc. Date: ~ .!"3>lo I I Approved by: t~ /11(;- r!!J:: J, ry n, P.E., 01 or Coastal Zone Management Department Date: b!z-/UJ 10 , 2 'i Agenda Item No. 1607 June 22, 2010 Page 11 of 36 I ~, . l:::. '::., ,: ~ I I,' II I i~ I ':, j' , -: " , Superintendent (Chuck Anderst) Safety Inspector Project Manllller (Angel Napoles) Scheduling (Dayle Cartwright) Quality Control General Superintendent Temporary Office Temporary Toilets (one porte toilet) Temporary Water Temporary Electric CO!nmunication Equipment Fuel for Vehicle Trucks and Vehicles Florida Marine Construction o o o o o o o o o o o o o Additional Pile Lengths at Dock COP #26 Date:12,02,09 $280.00 $98.00 01001 $0,00 $0,00 01004 $320,00 $112.00 01008 $25,00 $8.75 01012 $0.00 $0,00 01015 $33,00 $11,55 01205 $6,38 $0,00 01301 $4.00 $0.00 01303 $20.00 $0.00 01304 $30,00 $0.00 01305 $5.00 $0.00 01356 $36.00 $0,00 01358 $42.40 $0,00 01362 General Condition6 Subtotal 5% Markup 0,00 0.00 0,00 0,00 0.00 0,00 0,00 0.00 0,00 0,00 0.00 0.00 0,00 0,00 000 Stlbcontractol'8 0,00 3,472.26 Notes: Additional Pile length required on 33 piles for dock. Please refernce RFI #10, Discussed at OAG meeting 12,02,09, This CO!' is associated ONLY with the ADDED length for each pile The current contractually agreed to date f?r Substantial Completion is TBD The schedule Conlract Time will be increased by X (TBD) working days by this Change Order The date of Substanlial Completion as of the date of this Change Order therefore is To Be Detennined Owner \'2.. n. 6"\ BCBe ralContractor Agenda Item No. 1607 June 22, 20) 0 Page 12 of 36 Proposed Chanse Order Job: Goodland Boat Park SlJbcontractor: Flortda Marine Construction Description of Change: Increase piling length due to poor soil condltlon$ Unit Total Total Resource DesCription Unit Cost Cost Resource labor Incre.ase Longer ?iIfngs .. 32 hours 21.00 672,00 0.00 0.00 Subtotal Labor 672.00 !lurden 201.60 toto !labor 873.60 873,60 Mat'l (add) 10. Dia Marine Pilings 30 Fool 33 each 180,50 5,956,50 each 0.00 each 0.00 each 0.00 .ach 0.00 each 0,00 . Mat'llcreditl 10. Dia, Marine Piilngs 25 Foot 33 each .158,00 .5,214.00 each 0.00 each 0,0{) (See attached proposal(s}) Subtotal Material 742.50 Total material 742.50 742.50 Equipment IBarge and Cran. I l/day 11.500,0{) 1.500.00 Total equipment 1,500,00 1,500.00 Submittals Insurance Permits . Subtotal this PCO 3,116.10 3.116.10 Overhead and Profit 10% 311,61 311,61 . 6% Tax 44,55 44.55 Total this Proposed Change 3.472.26 ;..."1~~_~C.:..~:'"'=~~~,--~~"",'~"'-'~'r.:---'--I~-. .,... ~-~,..; _~_~"'t~"~~ ~~""'~ -"fJ."':~---;=~,,-_-,!-,-~- Supenntendent (Chuck Anderst) Safety Inspector Project Manager (Angel Napoles) Scheduling (Dayle Cartwright) Quality Control General Superintendent Temporary Office Temporary Toilets (one porte toilet) Temporary Water Temporary Electric Communication Equipment Fuel for Vehicle Trucks and Vehicles o o o o o o o o o o o o o Agenda Item No. 1607 June 22, 2010 Page 13 of 36 Boat Ramp Redesign COP #28 2,9,10 $280.00 $98,00 01001 $0,00 $0.00 01004 $320,00 $112.00 01008 $25.00 $8.75 01012 $0.00 $0,00 01015 $33,00 $11.55 01205 $6.38 $0.00 01301 $4.00 $000 01303 $20,00 $0.00 01304 $30.00 $0.00 01305 $5.00 $0.00 01356 S36,OO $0,00 01358 $42.40 SO.OO 01362 General Conditions Subtotal 5% Markup 0.00 0,00 0,00 0,00 0.00 0,00 0,00 0,00 0,00 0,00 0.00 0,00 0,00 0.00 0.00 Florida Marine Construction Subcontractors 0,00 61,998.94 Notes: Per drawings and proposal shown on 2.10.10 OAC mtg, FMC Proposal dated and em ailed 2.9.10 The schedule Contract Time will be increased by MIN.25 working days by this Change Order The date of Substantial Completion as of the date of this Change Order is TSD Owner SCSE - General Contractor Agenda Item No. 1607 June 22, 2010 Page 14 of 36 (i) Coastal Zone Management DeDartment WORK DlREcrIVE CHANGE PROJECT NAME: Goodland Boat Park CHANGE II COP 26 '" COP for Boat Ramp Modifications DATE OF ISSUANCE: 2.12 .10 EFFECTIVE DATE: 2.12.10 PROJECTI#: 80611.1 OWNER: CoUier Couoty Board of Commissioners CONTRACTOR: BCBE Coostructioo Co., 10"- ENGINEER: Joboson Engineering You are directed to proceed promptly with tbe following change(s): Descriptioo: Install the additional pile lengths required for (33 pilings) to achieve the minimum penetration resistance per engineering specifications and pile driving standards. Also, provide the necessary engineering and permitting modifications in association with the boat ramp scope of work to include all material. labor. and contract credits for the boat 1'8Il'lp redesign as per the (Reuben Clarson Consulting) design drawings dated USfIO. to include the narrative of the cost break down dated 2,9/10 by FMC, All imported and eltCftvated material quantities shall be field verified and documented with proper documentation for final invoicing, No other work. shall be approved beyond this work directive without written approval. Purpose of Work Directive Cballge: To conunence with continual on-site work production of site improvements in connection with the installation of the boat ramp. Attachmems: COP 26. Cost BMlk down Narrative, and Design Rcndcrinl\5 [f u claim is lI1llde that the above change(s) have affected Contract Price or Contract Times any claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract Price: IZI Unit Prices o Lump Sum o Other (Error tn E.~i._ine Coleulotlon,) Method of determining change in Contract Times: o Con1nlctor's records o Engineer's record IZI Other (cqNTRACTOR'S COSn A mounl of increas<: in Contract Price: S 68,744.76 Estimated change in Contract Time: Increase or decrease by 45 calendar days. ~ect er r (Johnson neering) AUTHORIZED: B~~. Project Manager Owner's Representative By: 02112110 10:05 AM Agenda Item No. 1607 June 22, 2010 Page 15 of 36 . Narrative for P.C.O. February 9, 2010 BOAT RAMP STABILIZATION Labor Install 383 cubic yards of rock 384 hours at $21,00 per hour $ 8,064,00 Material Addition 460 tons of rip-rap 460 tons at $16,00 per ton $ 7,360,O(f- ; ,"', Remove excess spoil material 23 trucks at $150,00 per load $ 3,450,00 I i I J .pI ...., .'based on 15-16 cubic yards ; EQuipment Supply barge & excavator to place rip-rap 8 days at $1,500 per day $ 12,000,00 Provide front end loader 9 days at $500 per day $ 4,500.00 Transport rip-rap to Goodland 20 loads at $300 per load $ 6,000,00 $41,374.00 ./ Total soil stabilization cost for boat ramp Does not include labor burden or sales tax MODIFICATION OF SEAWALUDOCK DESIGN Remove 40 foot of proposed concrete seawall and install wood piling to sustain dock structure. Labor Install 8 dock piling 32 hours at $21,00 per hour $ 672,00 . , Material Addition Provide 10 inch marine piling - dock 8 each at $158,00 EauiDment Barge and crane/excavator 1 day at $1,500,00 Total cost to install dock piling Does not include labor burden or ss/estax SEAWALURETAINING WALL MODIFICATION Install vinyl seawall panels instead of concrete seawall panels Labor Install 1 0 - 35 foot piling to sustain vinyl seawall 58 hours at $21.00 per hour Install vinyl panels and form wood timber cap 120 hours at $21,00 per hour Drill holes to mount wood seawall cap to piling, vinyl and timbers 32 hours at $21.00 per hour Materials Addition 10" marine piling 35 foot - seawall 10 each $235.00 Vinyl seawall panels - 660 square foot 660 square foot at $6,00 per foot 12 foot 3 inch X 10 inch - seawall cap timbers 36 each at $38.00 12 foot 2 inch X 10 inch - seawall cap timbers 6 each at $27,00 Agenda Item No. 1607 June 22, 2010 Page 16 of 36 $ 1,264.00 $ 1,500,00 $ 3,436.00 V $1,218,00 $ 2,520.00 $ 672.00 $2,350.00 $3,960,00 $1,368,00 $162,00 Agenda Item No. 1607 June 22, 2010 Page 17 of 36 ," 24" HDG bolts - seawall 76 each at $12.00 $912.00 Eauioment Vlbro excavator to install vinyl sheet piling 2 days at $SOO.DOper day Total cost for seawall/retaining wall modification $1,600,00 $14,762.00 V Does not include labor burden or sales tax Credit materials Remove center wood dock 1 each ($4,800,00) Remove labor & material to instaD seawall slabs and not install concrete seawall cap 1 each ($7,375.00) Total credit ($12,1 T5.00) V PLANS/PERMITS/ENGINEERI NG Revised sign and sealed plans for revised seawall, dock and boat ramp 1 each $3,000,00 Revised/new plans conceptional and revision 1 each $1.200,00 $350.00 $4,550.00 ,/ Permit reVisions - Collier County Total forplanslpermitslengineering Subtotal for pce February 9, 2010 Labor burden 10% overhead and profit Sales tax $ 51,947.00 V $ 3,943.80 $ 5,589.08 ~ 519.06 TOTAL p.c.e FEBRUARY 9, 2010 $ 61,998.94 oD,Jii" "i. - ~1" (" ,? ( ~ f;;x)r 0 9$ ,e1 Ploric;la Tool and Fasteucr Joe. 12831 MEfRO PKWY FT MYERS. FL 33966 USA 239.768.2658 Agenda Item No. 1607 June 22, 2010 ..-. . Page 18 f 36 Orm Number 1049448 _.- Old;'" Date-! ... Pa~.." 4/5/2010 00:00:00 1 of I Bill To: FL MARINE CONSTRUCTION PO BOX 248 MATLACHA, FL33993 USA Ship To: FLORIDA MARINE CONSTRUCTION 5300 DOUG TAYLOR CR ST lAMES CITY, FL 33956 USA ~ 239.283-1728 " ~ Requested By: CHAJUJ.E GARCIA Customer f1): 10 1408 PO Number Ship RoufI Taktr BRUCEF ~r u.",m fJ/fI? UIII.l Er#....d Ord<r<dl J llt-.mgIUO~ It u.... Dorcrlplio1l Unit/ii<t PrItt 1'rlct ]6.00 0,00 16.00 SA ooSONOO4OOLBG 1.0 112 X 4 LAG BOLT HEX 2 GR GALV Ordered As: SON400I.BO PERC 100.0 500.0000 80.00 . _.,- ,_. -- - -_'_"..0 TC1UlILin(!s: 1 SUB-TOTAL: TAX: AMOUNT DUE.. 80,00 4,80 84.80 ",._-. ;1~ .. ':1j tll ", ..\;1 Agenda Item No. 1607 June 22, 2010 Page 19 of 36 CHUCK NEWMAN ARCHITECT AIAiNCARB 2407 Sycamore Street, St. James City, Florida 33956 Tel (239) 282-9297 INVOICE FOR ARCHITECTURAL SERVICES Date: 05-01-10 Invoice Number: 10 Florida Marine Construction PO Box 248 Matlacha, FL 33993-0248 Project: Goodland Boat Docks Collier County, Florida Invoice for work completed to date on above noted project. April 26, 2010 - Review and revise seawall and dock drawings. Cost includes signed and sealed permit drawings to reflecting project revisions and modifications. Cost for engineering services $3,000,00 Total Amount Due Now $ 3,000.00 Thank you for the opportunity to be of service. Chuck Newman AIA/NCARB Store: NAP .' st DECKS,:;'DoCKS 3750 Exchange Ave. Naples, FL 34104 239-403-9663 _.dllCkt-docke.com OCl~~n~!\1~~ ~11~7 ~~J~o Page 20 of 36 Bill To: Florida Marine. Constructi P.O. ~ox248 Matiacha, FL 33993 239.283-1728 I Terms Description Pile 10"bult x 25ft I Shipped VIa Pile 10"butl x SOft 10825 2.5CCA 10830 2.5CCA I DfIlvery Date Ordered Shipped 8 0 ! Delivery TIme I Price Ext Price $158.00 $1,264.00 33 0 $180.50 $5,956.50 Subtotal: $7,220.50 6 % Tax: + $433.23 TOTAL: $7,653.73 Balance Due; $7,653,73 Collier County Received By: Date: Thank you for your order! .' , Agenda Item No 1607 June 22, 2010 I P~!l.e 2~ of 36 nvOlce [t....... ~': Bonita Grande Mining LLC d/b/a Bonita .- Grande Aggregates 2550] Bonita Grande Drive '. ."" Bonita Springs, FL 34135 Date Invoice # 4,1i2010 1012963 6ill To Ship To . Florida \.1arine ConSt. ir,c P.O. Bo:c 24~ ! Ma::ach<.: FL ::"'93 , P,O, Number Tenns Oue Date Job or Project ~et 30 Day~ , 1 '2010 - Guantity Units Description Price Each Amount ~ ---- Order #001 Goodland Boar Park - FILL IN(EA\ 20,00 140,00 Sales Tax 0,00% 0,00 Total $140,00 , 2 Yo discount If payment 15 receIved WIthIn 10 days of the Invoice date Phone # Fax# 239-947-6411 239-947-1340 ltore: . NAP :111I To: Florida. MarinEl Constructi P.O. Box 248 Matlacha, FL 33993 239-283-1728 ,at DECKS&.DoCKS 3760 Exchange Ave. NIpie$, FL 34104 239-403-9663 _decks-<locks,ccm -"'Agenii~ t>J~:1SD7 une~~mo Page 22 of 36 Terms I Shipped Via >ascription )lJe 1 O"butt x 35 !l 10835 2.5CCA 310PP12RC60 210PP12RC60 lx10x12 #2 .60 CCA RGH 1x10x12 #2 .60 CCA RGH I Delivery Date I Delivery Time Ordered Shipped Price Ext Price 10 0 $235.00 $2,350.00 36 0 $38.00 $1,368.00 6 0 $27.00 $162.00 Subtotal: $3,880.00 Collier County 6 % Tax: + $232.80 TOTAL: $4, 112.80 Balance Due: $4,112.80 Received By: Date: Thank you fur your order! ,/ Bonita Grande \1inmg LLC d/b/a Bonita Grande Aggregates 25501 Bonita Grande Drive Bonita Springs. FL 34135 Agenda Item No. 1607 June 22, 2010 Page 23 of 36 Invoice ".c. -' , Date Invoice # 4/1012010 1012904 Bill To Ship To Florida ~iarir,e Coost. Inc. P.O. Box: 24$ \t,,:2cil.a FL ::9"?: [ J I P,Q. Number Tenms Due Date Job or Project :\et 30 Days 51 I 0/20 I 0 Date -Quantity Units Descnption Price Each Amount Order #000 General ! FILL IN(EA) 20.00 20,00 Order #00 I Goodland Boat Park 9 FILL IN(EA) 20,00 180.00 Sales Tax 0.00% 0,00 Total $200,00 2% discount if payment is received within 10 days of the invoice date Phone # Fax # 239-947-6411 239-947-1340 ~~~ "~=nl"~~ ~-,_"'" "':--" :~~>,'~:~~ ~~ ===-:~ " ~:~'7i'l~~I::' -:~-~:f;-~-:;::: Superintendent (Chuck Anderst) Safety Inspector Project Manager (Angel Napoles) Scheduling (Dayle Cartwright) Quality Control General Superintendent Temporary Office Temporary Toilets (one porte toilet) Temporary Water Temporary Electric Communication Equipment Fuel for Vehicle Trucks and Vehicles Agenda Item No, 1607 June 22, 2010 Page 24 of 36 Four (4) Dock Ladders COP #32 4,20,10 o o o o o o o o o o o o o $280.00 $98,OO 01001 0,00 $0,00 $0,00 01004 0.00 $320.00 $112.00 01008 0.00 $25,00 $8.75 010120,00 $0,00 $0.00 010150.00 $33,00 $11.55 012050.00 $6,38 $0.00. 01301 0,00 $4,00 $0.00 01303 0.00 $20.00 $0.00 01304 0.00 $30.00 $0.00 013050.00 $5,00 $0,00 013560,00 $36,00 $0,00 01358 0,00 $42,40 $0,00 01362 0,00 General Conditions Subtotal 0.00 5% Markup 0.00 Florida Marine Construction backup dated 4,8,10 Subcontractors 0.00 1,010.24. Notes: This change order adds four (4) aiuminum safety ladders to the dock area. The current contractually agreed to date for Substantial Completion is TBD The schedule Contract Time will be increased by X (TBD) working days by this Change Order The date of Substantial Completion as of the date of this Change Order therefore is To Be Determined Owner seSE. General Contractor Job: Subcontractor: PROPOSED CHANGE ORDEr Goodland Boat Park DaTe: Florida Marine Construction PCO # Agenda Item No. 1607 June 22, 2010 Page 25 of 36 April 8, 201 0 Description of Change: Safety ladders ~:;'~~~~'7JJV,~'~l-~""TT-:'?1~"'- '~ - ~:. l"' - 'r' ". . 'L. ~:~ I j I sp \ii f '}:" t rn ,t. t _ "T .~~ (r I::: . ";i.-,' ."'; - 4j fY, J ~ t~tl'(' '~B "';- >'. f '~~i":1.. ,; , c: " 1:, t ,I , ,.... I '~~<-, '_, '~.~ _b__ '... _><>-'"' ..o:J..i..:_-=> ~.... _c..:..~__ ......~~"____~. iii ~ '= ~ .:.l",-_ l~ '-' "~_,... .....t. '-""~., -,,_.1 _~....idll.:>t;tl- nsa sa e a ers our! Subtotal Labor 168,00 Burden 50.40 lotallabor 218.40 218.40 Aluminumm safety ladders 4 each 155,00 620,00 14" lac bolts 16 each 5.00 80,00 (See attached proposal(s)) Subtotal Material 700.00 Total material 700.00 700,00 Total equipment 0,00 0,00 Subtotal this PCO 918.40 918.40 Overhead and Profit 10% 91.84 91.84 Tax 6% 42,00 42.00 Total thiS Proposed Change 1,052,24 I t II f ty I dd 8 h 2100 16800 Submitted By: Approved By: Subcontractor BeBE BeBE Subcontractor SHORELINE LUMBER 1 0871 KELLY RD FORT MyeRS, FL 33908 PHONE: (239) 267-6857 Agend;frt@~o. 1607 June 22, 2010 Page 26 of 36 MATlACHA 239-860.6707 Fl. 33993 COST NO: 1036 ,....., NET 10TH flI:UAI..!.NO: ......YrO, SAFTEV LADDeRS ""IRENC", PO # SAFTEY LADDE JOB NO; 000 .,.,Ql.TE: 6115/10 DATI: 6/15/10 Tel 9:14 CLiRK: 4 TeRMINAl.: 551 IAUSPiR!lDN; TAX, S LEE;COL.l.IER SO\.O Fl.ORIDA MARINE CONSTRUCTION TO: P.O. BOX 248 s~ ~b1; rfWli ~ f4y om oueOATt:. 7/10110 INVOICE: 4151 iJN! QTY UM SKU DESCRIPTION UNITS SUGG PRICEI I'E EXTENSION 1 4 EA 1905 DOCK LADDER 5 STEP LIFT 4 165.00 lEA 620,00 I I I , ! TAXABLE NON-TAXABLE 620,00 000 SUSTOT AL 620,00 SUBTOTAL 620.00 .. AMOUNT CHARGED TO STORE ACCOUNT" 657.20 illllllllllllll~~~IIIII~IIIIIII"III~1111 TAX AMOUNT I TOTAL 37,20 657.20 I TOT WT: 0,00 xDelivery Kec;elV8d ~y Florida Tool and Fastener Ioc. 12831 METRO PKWY PI' MYERS, FL 33966 USA 239-768-2658 Agenda Item No. 1607 June..22, 2010 P~f36 Order NUlXIber , 1049447 Order Date Page 3/81201000:00:00 1 of! ... Bill To, FL MARINE CONSTRUCfJON PO BOX 248 MA TLACHA, FL 33993 USA Ship To: FLORIDA MARINE CONSTRUCTION 5300 DOUG TAYLOR CR Sf JAMES CITY, FL 33956 USA 239-283-\728 ~ Requestll(! By: CHARLIE GARCIA CustomerlD: J 0 J 408 PO NIlmlHi, S~lp R.Ilte Tau' BRUCEF (iwI-' l_lD =' III1it -- o..t.Ndl ~Iug:....lf 1wIolH..ripIioft UIIit Silo ?rift ?rift 76,00 0,00 76.00 )SA ooSOCOl400HO 1.0 1/2.13 X 14 HEX CIS 2 OR GALV O,dffl!d As: .IOC 1400HO PERC 100.0 1,200.0000 912,00 -uti - TuIU[ Lines; J SUB-TOTAL: TAX: AMOUNT DUE: 912.00 54.72 966.72 ,ill Agenda Item No. 1607 June 22, 2010 Page 28 of 36 Spoil Disposal COP #37 4.20,10 Superintendent (Chuck Anderst) 0 $280.00 $98.00 01001 0.00 Safety Inspector 0 $0,00 $0.00 01004 0,00 Project Manager (Angel Napoles) 0 $320. DO $112,00 010080,00 Scheduling (Dayle Cartwright) 0 $25,00 $8,75 01012 0,00 Quality Control 0 $0,00 $0.00 010150,00 General Superintendent 0 $33.00 $11.55 01205 0.00 Temporary Office 0 $6.38 $0.00 01301 0,00 Temporary Toilets (one porte toilet) 0 $4.00 $0,00 01303 0.00 Temporary Water 0 $20.00 $0.00 01304 0,00 Temporary Electric 0 $30.00 $0.00 01305 0.00 Communication Equipment 0 $5.00 $000 013560.00 Fuel for Vehicle 0 $36,00 $0.00 01358 0.00 Trucks and Vehicles 0 $42.40 $0,00 013820,00 General Conditions Subtotal 0.00 5% Markup 0.00 Subcontractors 0,00 Florida Marine Construction 935,00 backup dated 4.8,10 ~ The change represents the cost of disposal of 17 loads of contaminated fill. The current contractually agreed to date for Substantial Complation is TBD The schedule Contract Time will be increased by X (TBD) working days by this Change Order The dale of Substantial Completion as of the date of this Change Order therefore is To Be Determined Owner BCBE - General Contractor Agenda Item No. 1607 June 22, 2010 Page 29 of 36 Job: Subcontractor: PROPOSED CHANGE ORDE}... Goodland Boat Park Date: Florida Marine Construction PCO # April 8,2010 Description of Change: Disposal of Fill E";~"'~-;_""'fii~_,--"".,~,,-_.,,--~r;~':"i"'r~~"1...,,~-r.::.r'~-)/~l-;""l::'W"~~"';~~~~",., . --e--T ~",~;.~'1 .""lli: '" ,~~,q.: cff 'r " ~. f' ~ <, 1,' . ,~' ~~rl"~ ;r. ',. 'n ,I f "" ";,':"ij .of' -' ~c' . ,. t .~ oJ.J;\ ""';' L." ~ ' ;! ~ l. "'" .". . ~ tr ,!! Zi -<;-.." _"-' < l1... ~__....~ t'=.....:I. Jll!.j._~)1.'-4__~ _ '.!....~~''''''' ~- ~\i,-' .:.. h,,-=~I.i:.~ ~,,',; ~ ~ ~ - "-,~ Labor 0.00 0.00 0.00 0.00 0.00 Subtotal Labor 0.00 Burden total labor 0,00 0.00 Mat'l (add) Disposal Fee 17 each 50.00 850,00 0.00 0,00 0.00 000 0.00 0.00 0,00 Mat'l (credit) 0,00 0.00 0.00 (See attached proposal(s) Subtotal Material 850,00 Total material 850,00 850.00 Equipment 000 0.00 0.00 0.00 Total equipment 0.00 0.00 Subtotal this peo 850.00 850,00 Overhead and Profit 10% 85.00 85.00 Tax 6% Total this Proposed Change 935.00 Submitted By: Approved By: BeBE Subcontractor __BeBE Subcontractor Agenda Item No. 1607 June 22, 2010 Page 30 of 36 Additional Rock and Placement from unit prices in COP#28 cop #39 4,26.2010 ~ '"1', ~t - ...".",.." - -"(t" ~",.., '"r~. - ~':;l -: ~-~-:;~'t . ,~ "".1" "--;-: ~,~.-~~: :--;""" Superintendent (Chuck Andersl) Safety Inspector Project Manager (Angel Napoles) Scheduling (Dayle Cartwright) Quality Control General Superintendent Temporal)' Office Temporal)' Toilets (one porte toilet) Temporary Water Temporary Electric Communication Equipment Fuel for Vehicle Trucks and Vehicles o o o o o o o o o o o o o $280,00 $98.00 01001 0,00 $0,00 $0.00 010040.00 $320,00 $112,00 01008 0,00 $25.00 $6,75 010120,00 $0,00 $0.00 010150.00 $33,00 $11.55 012050.00 $6,38 $0,00 01301 0,00 $4.00 $0.00 013030,00 $20.00 $0,00 01304 0,00 $30,00 $0.00 013050,00 $5,00 $0,00 01356 0.00 $36.00 $0.00 013580,00 $42.40 $0,00 01362 0.00 General Conditions Subtotal 0,00 5% Markup 0.00 Florida Marine Construction Back-up dated 4.23,10 Subcontractors 0,00 32,046,74 ~ This add constitutes the additional material, labor and equipment to place an additional 322 tons of rip-rap as part of the modifications of the seawall design. See comparison of COP#28 and the current cost figures attached, The current contractually agreed to date for Substantial Completion is TBD The schedule Contract Time will be increased by X (TBD) working days by this Change Order The date of Substantial Completion as of the date of this Change Order therefore is To Be Determined Owner scse - General Contractor Agenda Item No. 1607 June 22, 2010 Page 31 of 36 Goodland Boat Park Florida Marine Construction, Inc, Reconciliation of Rock for COP #46 ~ QIt! Rock (tonl 1m! 280833 3/812010 15,76 Rip Rap 1 280873 3/812010 15,75 Boulders 2 280945 3/8/2010 15,76 Boulders 3 260913 31812010 1371 Boulders 4 281054 3/912010 15.21 Boulders 5 281073 31912010 13.89 Boulders 6 281030 3/912010 15.36 Boulders 7 280957 3/912010 15.58 Boulders 8 280993 3/912010 15.54 Boulders 9 281469 3/1512010 14,21 Boulders 10 281496 3/15/2010 '4.26 Boulders 11 281563 311512010 15.74 Boulders 12 281594 3/1512010 15,76 Rip Rap 13 281529 311512010 13,59 Boulders 14 281609 311512010 14,06 Boulders 15 281657 3/1812010 14.32 Boulders 16 281717 3/1612010 15.65 Boulders 17 281747 3/16/2010 15.69 Rip Rap 18 282005 3/19/2010 13.52 Boulders 19 282076 3/1912010 15,12 Boulders 20 282151 3/19/2010 15.48 Boulders 21 282324 3122/2010 15.15 Rip Rap 22 2B234O 3122/2010 15.19 Rip Rap 23 282290 3122/2010 15.19 Rip Rap 24 282216 3/22/2010 14,68 Boulders 25 282253 312212010 15,06 Rip Rap 26 282594 3/24/2010 14,85 Boulders 27 282658 3/24/2010 14,33 Boulders 28 282793 3/24/2010 14.5 Rip Rap 29 282728 3/24/2010 14.74 Rip Rap 30 282644 3/251201 0 14.59 Rip Rap 31 282901 3/25/2010 14,25 Rip Rap 32 282952 3/2512010 14.51 Rip Rap 33 283093 3/2512010 14,64 #57 Slone 34 283029 3/25/2010 15,14 #57 Stone 35 283363 3/2912010 20,89 #57 Stone 36 283383 3/2912010 20,91 #57 Stone 37 283337 3129/2010 20.91 #57 Stone 38 583.49 Agenda Item No. 1607 June 22,2010 Page 32 of 36 Job: Subcontractor: *** REVISED*** PROPOSED CHANGE ORDER Goodland Boat Park Date: Florida Marine Construction peo # April 23, 2010 Description of Chanl!e: REVISED COST APRIL 23, 20] 0 Modification of seawall design 1. 0 21,00 21,00 21,00 ~~r:l':'I'rl'r--.rr;m~ -- -~- Subtotal Labor Burden total labor Mat'l (add) 10" marine piling - dock 1 0" marine illn 35' - seawall 10" marine i1in - 30 foot - Ion er Vin I seawall anels - 660 s It 12 foot 3" X 10" seawall timbers 12 foot 2" X 10" seawall timbers 24" HDG bolts- 8 each 10 each 33 each 660 s It 36 each 6 each 158,00 235,00 180.50 6.00 38,00 27,00 20,496.00 6,148.80 26,644,80 26,644,80 1,264,00 2,350.00 5,956,50 3,960.00 1,368.00 162,00 912.00 emove access spoil material Mat'l (credit) Remove center dock Credit seawall labor & material 10" 25 foot marine ilin s 2, -4,800,00 -7,375,00 -5,214.00 Equipment Total equipment (See attached proposal(s) 13,645,50 1 13,645,50 I Subtotal this PCO Overhead and Profit Tax T alai this Proposed Chan e 10% 6% 43,300,00 3,000,00 1,200,00 350.00 88,140.30 8,814.03 818,73 43,300,00 3,000,00 1,200,00 350.00 88,14030 8,814.03 563,61 97,517.94 Engineering I Seawall & docks Conceptual Plans I Revised plans Permit Revisions Submitted By: Approved By: Subcontractor BeBE BCBE Subcontractor .' ~~,. '. - ^ ~~-....--.".--"-.- Job: Subcontractor: PROPOSED CHANGE ORDER Goodland Boat Park Date: Florida Marine Construction PCO # Descriotion of Change: Modification of seawall design sla 8 doc p ng Install 1 0 seawall i1in Form wood ca Drill - instell bolts seawall Increase Ion er j/in s ,00 21,00 21,00 21,00 8 each 1 0 each 33 each 660 s ft 36 each 6 each 76 each 158.00 235,00 180.50 6.00 36,00 27.00 12,00 (See attached proposal(S) Subtotal Material Total material Seawall & docks 'Ians I Revised plans ons Subtotal this pea Overhead and Profit Tax Total this Proposed Change 10% 6% Submitted By: Approved By: Subcontractor BeBE BCBE Agenda Item No, 1607 June 22, 2010 Page 33 of 36 February 9,20]0 672.00 1,216.00 2,520,00 672.00 13.616,00 4,145.40 17,963,40 17,963.40 1,264,00 2 350.00 5,956.50 3,960.00 1,368,00 162,00 912,00 9,393.50 9,393,50 3,000,00 1,200 00 350,00 59,006,90 5,900.69 563.61 ,100,00 3,000,00 1,200,00 350,00 59,006,90 5,900,69 563.61 65,471,20 Subcontractor Agenda Item No 1607 June 22, 2010 Page 34 of 36 Dock Extensions to paver walkway COP #45 5:11,10 ~ ~~~ -:,' --; - ~ ")""<- ~ ~~" ~"T"~. ;~-;~ - -=- '~ j;-7rI~~- ,.,..-:~"~,~ ".., ~ --, , ?''''.;~ {:';",' ~ -: -.:: I' Superintendent (Chuck Anderst) Safety Inspector Project Manager (Angel Napoles) Scheduling (Dayle Cartwright) Quality Control General Superintendent Temporary Office Temporary Toilets (one porte toilet) Temporary Water Temporary Electric Communication Equipment Fuel for Vehicle Trucks and Vehicles o o o o o o o o o o o o o $280.00 $98.00 01001 0.00 $0.00 $0.00 01004 0.00 $320.00 $112,00 01008 0.00 $25,00 $8,75 01012 0.00 $0,00 $0.00 01015 0.00 $33.00 $11,55 012050.00 $6,38 $0,00 01301 0,00 $4,00 $0,00 013030,00 $20.00 $0,00 01304 0,00 $30,00 $0,00 01305 0,00 $5,00 $0,00 01356 0,00 $36.00 $0.00 01358 0.00 $42.40 $0,00 013620.00 General Conditions Subtotal 0.00 5% Markup 0,00 Florida Marine Construction 5.4.10 Credit Pavers 1 00 sq ft Credrt Curb 20 I.f Subcontractors 0,00 4,610.18 450.00 340.00 Notes: This change represents revisions to the dock approach ramp to tie into the paver area. The current contractually agreed to date for Substantial Completion is TSD The scheduie Contract Time will be increased by X (TBD) working days by this Change Order The date of Substantial Completion as of the date of this Change Order therefore is To Be Determined Owner seBE - General Contractor III ENGINEERING ]CJHNS May 5, 2010 Mr. Clint Perryman, cac, Project Manager Collier County Coastal Zone Management 330] E, Tamiami Trail W. Harmon Turner Bldg" Suite 103 Naples, FL 34] 12 Re: Good]and Boating Park COP #39 - Additional Rock and Placement at Boat Ramp Dear Mr, Perryman: Agenda Item No 1607 June 22, 2010 Page 35 of 36 SINCE 19116 As you know we have been intimately involved with this and have closely reviewed the field work provided by F]orida Marine Construction. This additional supplement should be approved as submitted and processed, Should you have any comments or questions regarding this, please contact me, Sincerely, GINEERING, INC. H:/200662/61Conslruc/Jon Documen/s/Oj-05~/O. CDH to Pe.rryman re Pay App No. 39.doc 2350 Stanford Court. Naples, Florida 34112 (239) 434-0333 . Fax (239) 434-9320 Agenda Item No, 1607 June 22, 2010 Page 36 of 36 Final Dock related Improvement and Changes ;, _ '~f- jj"', ~.~ ""~~;,-"""'" .- --I '(" -;-- 1 ",;r' -~ ......,~-,-~ - ~ . Superintendent (Chuck Anderst) Safety Inspector Project Manager (Angel Napoles) Scheduling (Dayle Cartwright) Quality Control General Superintendent Temporary Office Temporary Toilets (one porte toilet) Temporary Water Temporary Electric Communication Equipment Fuel for Vehicle Trucks and Vehicles COP #46 5.11.10 o o o o o o o o o o o o o $280,00 $98.00 01001 0,00 $0.00 $0.00 01004 0.00 $320,00 $112.00 010080.00 $25,00 $8.75 010120,00 $0,00 $0.00 010150.00 $33,00 $11.55 01205 0,00 $6,38 $0,00 01301 0,00 $4.00 $0.00 013030,00 $20,00 $0.00 01304 0,00 $30.00 $0,00 01305 0.00 $5,00 $0.00 013560,00 $36,00 $0.00 013580,00 $42.40 $0.00 01362 0.00 General Conditions Subtotal 0,00 5% Markup 0,00 Florida Marine Construction COP #26 V- COP #28 - COP #3:;- COP #37- COP #39- COP #45 - Subcontractors 0,00 3,472,26 V 61,998.94 1,010,24 935,00 32,046,74 3,820,18 v ,..,/ V y ~ This change request represents the culmination of several dock related COP's attahced for reference. The current contractually agreed to date for Substantial Completion is TBD The schedule Contract Time will be increased by X (TBO) working days by this Change Order The date of Substantial Completion as of the date of this Change Order therefore is To Be Oetennined Owner BCBE. General Contractor