Recommendation to approve Change Order No.1 to purchase order 4500113459
under Contract Number 09-5121 with Aztek Communications for Oil Well Road
fiber Construction in the amount of $104,306
OBJECTIVE: To increase the scope of PO 4500113459 under contract number 09-
5121 with Aztek Communications for the Oil Well Road Fiber Construction project.
CONSIDERATIONS: On November 3, 2009 the Information Technology Department
issued a work order under PO 4500113459 to Aztek Communications to relocate fiber
on Oil Well Road under contract number 09-5121. This relocation is necessary
because Oil Well Road is being widened and the fiber path needs to be moved into the
new right of way. This segment of the County's fiber network is the only fiber path to
provide internal network services in Immokalee. There are three changes being
requested in Change Order #1.
1. After approval of the initial purchase order to relocate the fiber, staff determined that
the segment of fiber associated with the intersection (turn lane) with Everglades Blvd
was omitted from the original quote. This resulted in an increase to the initial PO of
$71,400.74.
2. After approval of the intial purchase order, the Collier County School Board and US
Metro Telecom joined the project. All three parties will relocate their respective fiber
segments at the same time and share the cost of doing so. This resulted in a cost
reduction of $52,237.50.
3. As part of the partnership with the School Board and US Metro Telecom, all parties
agreed to relocate an adjacent network segment that will be part of the next phase of
the road widening project. Doing so in partnership yields a cost savings of
approximately 25 percent to the County. The cost of this change is $85,142.83.
These changes are reflected in Change Order NO.1.
FISCAL IMPACT: The fiscal impact of Change Order NO.1 is $104,306.07 and funding
is available in Project No. 50028 - Installation of Conduit; general fund 301 Capital
Improvements.
GROWTH MANAGEMENT IMPACT: There is no growth management impact
associated with this Executive Summary.
LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney's
Office and is legally sufficient for Board action. - CMG
RECOMMENDATION: That the Board of County Commissioners approves Change
Order NO.1 to PO 450013459 with Aztek Communications and authorizes the County
Manager or his designee to execute the Change Order.
Prepared by: E. Michael Berrios, Network Operations Manager, Information Technology
Department
Item Number:
Item Summary:
Meeting Date:
Agenda Item No. 16E9
April 27, 2010
Page 2 of 14
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
16E9
Recommendation to approve Change Order NO.1 to purchase order 4500113459 under
Contract Number 09-5121 with Aztek Communications for Oil Well Road fiber Construction in
the amount of $1 04,306.
4/27/20109:00:00 AM
Approved By
Lyn Wood
Administrative Services
Division
Contracts Specialist
Date
Purchasing & General Services
41151201011:05 AM
Approved By
Colleen Greene
County Attorney
Assistant County Attorney
Date
County Attorney
411512010 11 :25 AM
Approved By
Steve Carnell
Administrative Services
Division
Director - Purchasing/General Services
Date
Purchasing & General Services
4/151201011:54 AM
Approved By
Len Golden Price
Administrative Services
Division
Administrator - Administrative Services
Date
Administrative Services Division
4/15120105:28 PM
Approved By
OMB Coordinator
County Manager's Office
Date
Office of Management & Budget
4116/201010:45 AM
Approved By
Jeff Klatzkow
County Attorney
Date
Approved By
4/16120104:35 PM
Therese Stanley
Office of Management &
Budget
Manager - Operations Support - Trans
Date
Office of Management & Budget
4120/20108:35 AM
Approved By
Leo E. Ochs, Jr.
County Managers Office
County Manager
Date
County Managers Office
4120120104:03 PM
CONTRACTIWORK ORDER MODIFICATION
CHECKLIST FORM
Agenda Item No. 16E9
April 27, 2010
tI ~ Page3of14
PROJECT NAME: Oil Well Road Fiber Installation PROJECT MANAGER: Mike Berrios
BID/RFP #: 09-5121 MOD #: 1- PO#4500113459
DEPARTMENT: Information Technology CONTRACTOR/FIRM NAME: Aztek Communications Technology
Original Contract Amount:
$ _198,058.84
(Starting Point)
$ tllPc
(Last Total Amount Approved by the BCC)
Current BCC Approved Amount:
Current Contract Amount:
$_198,058.84
(Including All Changes Prior To This Modification)
Change Amount:
$_104,306.07
$_302,364.91
(Including This Change Order)
Cumulative Dollar Value of Changes to $ .//1 ,I 3' ~ /. O,,-r
this ContractlWork Order: __(,.'. ~ _ c.."~ "
Revised ContractIWork Order Amount:
Date of Last BCC Approval~ A.
Agenda Item # .
Percentage of the change over/under current contract amount .5 02 . 1 %
Formula: (Revised Amount / Last BCC approved amount)-1
CURRENT COMPLETION DATE (S): ORIGINAL: Mav 15. 2010
CURRENT:
June 30. 2010
Describe the change(s): We added phase 3 of the Oil Well Road widening project so we don't have to move
additional fiber on Oil Well when the construction in phase 3 takes place. We also added additional relocation
on Everglades Blvd which is required as part of the construction project associated with Phase 4; an additional
3,000ft we were not aware of.
Specify the reasons for the change(s) n 1. Planned or Elective X 2. Unforeseen Conditions C 3. Quantity
Adjustments C 4. Correction of Errors (Plans, Specifications or Scope of Work) C 5. Value Added
C 6. Schedule Adjustments Note: One or more may be checked, depending on the nature of the change(s).
Identify all negative impacts to the project if this change order were not processed: The additional 3,OOOft on
everglades must be relocated because it is in direct conflict with the new turn lanes installed on everglades blvd.
This change was requested by: rlcontractor/Consultant rl Owner X Using Department r CDES
r Design Professional rlRegulatory Agency (Specify)
rOther (Specify)
r Yes ~o
CONTRACT SPECIALIST PARTICIPATION IN NEGOTIATIONS:
This form is to be signed and dated.
APPROVED BY: ~
Project Manager
REVIEWED BY: ~ 21J t'..L!~
Contrci~peci~list '
Date:
/1 Ap.,/ 26/0
.
Date:
Lf -/'/-/0
Revised 11.19.2007
CHANGE ORDER
Agenda Item No. 16E9
April 27, 2010
Page 4 of 14
CHANGE ORDER NO.
CONTRACT NO. 09-5121
BeC Date: 1/27/2009
Agenda Item: 16B2
TO: Aztek Communications Technology
4730 Enterprise Ave
Naples, FL 34104
DATE: 4/12/10
PROJECT NAME: Oil Well Road Fiber Installation
Purchase Order NO.: 4500113459
Under our AGREEMENT dated February 28, 2010
You hereby are authorized and directed to make the following change(s) in accordance with
terms and conditions of the Agreement See attached Exhibit. A"
FOR THE Additive Sum of: One hundred and four thousand three hundred and six and seven
cents. ($104,306.07).
Original Agreement Amount
$198,058.84
Sum of Previous Changes
This Change Order Add $85,142.83-Phase 3
$71,400.74-Phase 4 Associated Changes
Subtract $52,237.50-deduct from original amount
$ 104,306.07
Present Agreement Amount
$302.364.91
The time for completion shall be increased by 60 calendar days due to this Change Order. The
substantial completion date is May 15, 2010 and the final completion date is June 30, 2010. Your
acceptance of this Change Order shall constitute a modification to our Agreement and will be
performed subject to all the same terms and conditions as contained in our Agreement indicated
above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to the
Agreement shall constitute a full and final setUement of any and all claims of the Contractor arising out
of or related to the change set forth herein, including claims for impact and delay costs.
Accepted:
.2010
CONTRACTOR:
Aztek Communications
Br.lM/-~-4-
Mike Leed
OWNER:
BOARD OF COUNTY COMMISSIONERS
OF COLLIER COUNTY, FLORIDA
BY:~
Mike Berrios, Project Manager
By:
Bar
Change Order # 1
Oil Well Road Fiber Installation
Work OrderlPurchase Order 4500113459
April 27, 2010
Page 5 of 14
I
A'ITEST:
Dwight E. Brock, Clerk of Courts
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
By:
Dated:
(SEAL)
By:
Pred W. Coyle; Chairman
Approved 8S to form and
legal sufficiency:
@;,t~tCounty AI"""'"
Print Name
Change Order #1
Oil Well Road Fiber Installation 2
Work Order/Purchase Order 4500113459
Agenda Item No. 16E9
April 27, 2010
Page 6 of 14
.
Collier County IT Department
PROPOSED PROJECT:
Oil Well Road
Conduit and Fiber for Phase 4
Reduced Pricing
Presented by
Tim Beckman, RCDD
tbeckman@aztek-naples.com
4730 Enterprise Ave. · Suite 308 · Naples, FL · 34104
Phone: 239-659-0017 · Fax: 239-659-0018
FEBRUARY2B,2010
~~-.
Agenda Item No. 16E9
April 27, 2010
Page 7 of 14
CCIT
011 Well ReI. - Phase 4
SCOPE OF SERVICES
OIL WELL RD. - CONDUIT AND FIBER (pHASE 4)
REDUCED PRICING
We are pleased to submit the following quotation for the project requirements to install conduit
and fiber cabling along the south side of Oil Well Road from Oil Well Grade Rd. to Camp Keais
in conjunction with Phase 4 of the road widening project. This pricing reflects the cost savings of
installing the conduit along with CCPS and US Metro. Aztek Communication Technologies shall
furnish Labor and Material for this project. The Scope of Work will consist of the following:
PRICING:
Conduit Installation (F &:1 viti Directional Bore)
SDR-13.5 Conduit (2") -550 ft. @$6.13/ft.
Conduit Installation (Fell via Trenching - >5,OOOft)
SDR-13.5 Conduit (2") - 22,200 ft. @ $3.27/ft.
Fiber Installation (one cable In conduit)
48-strand Fiber Cable - 24,200 ft. @ $1. 13/ft.
Materials
48-strand Fiber Cable - 24,200 ft. @ $0.49/ft.
Hand-holes - 28 @ $680,53/ea.
Fiber Optk Mllrker Posts - 28 @ $24.50
TrllCer Line - 24,200 @ $0. 1 O/ft.
Fiber SDlicine
Fiber Spiking - 96-strands (48 x 2) @ $211ea.
Fiber Spike CflSes - 2 @ $420.00/ea.
OTDR Testine (48-strands ellCh direction)
OTDR Testing-96-strands @$10/ea.
Hourlv Senrices
Permit tIIId DrtlWings - 40 hours @ $85/hr.
As-buUt drllwings ad docrunentlltion - 15 hours @ $85/hr.
$3,371.50
$72,594.00
$27,346.00
$11,858.00
$19,054.84
$686.00
$2,420.00
$2,016.00
$840.00
$960.00
$3,400.00
$1.275.00
(ToW) $145,821.34
Aztek Communication Technologies will perform the prescribed work as outlined in this
document for a fixed price of $145,821.34 (One Hundred Forty-five Thousand, Eight Hundred
Twenty-one dollars and lbirty-four cents).
Confidential
Page 2
4/1312010
~a
Agenda Item No. 16E9
April 27, 2010
Page 8 of 14
CCIT
011 Well Rd. - Phase 4
Again, thank you for the opportunity to service Collier Count IT on this project. Please let me
know if you have any additional questions and/or requirements.
Kind regards,
.~
----
-
Tim Beckman, RCDD
Confidential
Page 3
4/1312010
~~
Agenda Item No. 16E9
April 27, 2010
Page 9 of 14
CCIT
011 Well Rd. - Phase 4
SIGNATURE PAGE
The undersigned authorized representative of Client agrees that the services described in this
proposal accurately describe the scope of the work required and authorizes AZTEK to begin
work under the terms and conditions described in this document.
Please return signed acknowledgment copy promptly.
Collier County IT
Aztek Communication Technologies
Authorized Client Representative
Tim Beckman, RCDD
President
Title
Title
Date
February 28. 2010
Date
The services and pricing outlined in this proposal will expire sixty (60) days from the date of this
proposal unless extended in writing by Aztek Communication Technologies.
Any applicable Federal, state, and local taxes have been excluded from the charges quoted in this
proposal.
Please contact me if you have any questions.
Thank: you,
Tim Beckman, RCDD
Aztek Communication Technologies
4730 Enterprise Ave.
Suite #308
Naples, FL 34104
239-659-0017 OFFICE
239-659-0018 FAX
239-494-7411 CELL
tbeckman@aztek-naples.com
www.aztek-naples.com
Confidential
Page 4
4/1312010
~a
Agenda Item No. 16E9
April 27, 2010
Page 10 of 14
CCIT
011 Well Rd. - Phase 4
SCOPE OF SERVICES
OIL WELL RD. - CONDUIT AND FIBER (pHASE 4) - CHANGE ORDER #1
REDUCED PRICING
We are pleased to submit the following quotation for the Change Order requirements to extend
the conduit and fiber cabling 3,000 ft. south on Everglades Blvd. from Oil Well Road, 3,000 ft.
east on Oil Well Road from Everglades Blvd. and 3,000 ft. west on Everglades Blvd. from Oil
Well Grade Rd. This pricing reflects a cost savings of installing the conduit along with CCPS
and US Metro. Aztek Communication Technologies shall furnish Labor and Material for this
project. The Scope of Work will consist of the following:
PRICING:
Conduit Insta1lation (F &1 via Directional Bore)
SDR-1J.5 Conduit (2") -1,200 ft. @$6.13/ft.
Conduit Installation (F&1 via Trenching - >5,000ft)
SDR-13.5 Conduit (2") - 9,550 ft. @$3.27/ft.
Fiber Installation (one cable in conduit)
'IB-strand Fiber Cable-15,800 ft. @$1.13/ft.
Materials
48-strand Fiber Cable -15,800 ft. @ $0.49/ft.
Hand-holes - 8 @ $680.53/ea.
Fiber Optic Marker Posts - 8 @ $24.50
Tracer Line-15,8oo @ $0.10/ft.
$7,356.00
$31,228.50
$17,854.00
$7,742.00
$5,444.24
$196.00
$1,580.00
(ToW) $71,400.74
Aztek Communication Technologies will perform the prescribed work as outlined in this
docwnent for a fixed price of $71,400.74 (Seventy-one Thousand, Four Hundred dollars and
Seventy-four cents).
Again, thank you for the opportunity to service Collier Count IT on this project. Please let me
know if you have any additional questions and/or requirements.
Kind regards,
.--.--.
~-
--
Tim Beckman, RCDD
Confidential
Page 2
31212010
~~a
Agenda Item No. 16E9
April 27, 2010
Page 11 of 14
CCIT
0/1 Well Ref. - Phase 4
SIGNATURE PAGE
The undersigned authorized representative of Client agrees that the services described in this
proposal accurately describe the scope of the work required and authorizes AZTEK to begin
work under the terms and conditions described in this document.
Please return signed acknowledgment copy promptly.
Collier County IT
Aztek Communication Technologies
Authorized Client Representative
Tim Beckman, RCDD
President
Title
Title
..
February 28. 2010
Date
Date
The services and pricing outlined in this proposal will expire sixty (60) days from the date of this
proposal unless extended in writing by Aztek Communication Technologies.
Any applicable Federal, state, and local taxes have been excluded from the charges quoted in this
proposal.
Please contact me if you have any questions.
Thank you,
Tim Beckman, RCDD
Aztek Communication Technologies
4730 Enterprise Ave.
Suite #308
Naples, FL 34104
239-659-0017 OFFICE
239-659-0018 FAX
239-494-7411 CELL
tbeckman@aztek-naples.com
www.aztek-naples.com
Confidential
Page 3
31212010
Agenda Item No. 16E9
April 27, 2010
Page 12 of 14
REQUEST FOR PROPOSAL RESPONSE TO
Collier County IT Department
PROPOSED PROJECT:
Oil Well Road
Conduit and Fiber for Phase 3
(Joint Installation wI CCPS and US Metro)
Presented by
Tim Beckman, ReDD
tbeckman@aztek-naples.com
4730 Enterprise Ave. · Suite 308 · Naples, FL · 34104
Phone: 239-659-0017 · Fax: 239-659-0018
FEBRUARY 28, 2010
~~
Agenda Item No. 16E9
April 27, 2010
Page 13 of 14
CCIT
011 Well Rd. - Phase 3
SCOPE OF SERVICES
On. WELL RD. - CONDUIT AND FIBER - PHASE 3
We are pleased to submit Optional Pricing to install conduit and fiber cabling along the entire
south side of Oil Well Road from Everglades Blvd. to Oil Well Grade Rd. for the portion that
was originally to remain on the north side. This pricing reflects the cost savings of installing the
conduit along with CCPSand US Metro. Aztek Communication TechD.ologies shall furnish
Labor and Material for this project. The Scope of Work will consist of the following:
PRICING: (This reflects a reduced price to be installed wi CCPS and US Metro)
Conduit InstaUation (F &1 via Trenching - >5,OOOft)
SDR-13.5 Conduit (2") -15,250 ft. @ 53.27/ft. $49,867.50
Fiber Installation (one cllble in conduit)
48-strand Fiber Cable-16,000 ft. @ $1. 13/ft.
518,080.00
Materials
48-strand Fiber Cable-16,000 ft. @ $0.49/ft.
Hand-holes - 11 @ 5680.53/ea.
Fiber Optic Marker Posts - 11 @ 524.50
Tracer Line - 16,000 @ 50.1 o/ft.
57,840.00
$7,485.83
5269.50
$1.600.00
(Total) $85,142.83
Aztek Communication Technologies will perform the prescribed work as outlined in this
document for a fixed price of $85,142.83 (Eighty-five Thousand, One Hundred Forty-two dollars
and Eighty-three cents).
Again, thank you for the opportunity to service Collier Count IT on this project. Please let me
know if you have any additional questions and/or requirements.
Kind regards,
~
w--
Tim Beckman, RCDD
Confidential
Page 2
3/212010
~~a
Agenda Item No. 16E9
April 27, 2010
Page 14 of 14
celT
Oil Well Rd. - Phase 3
SIGNATURE PAGE
The undersigned authorized representative of Client agrees that the services described in this
proposal accurately describe the scope of the work required and authorizes AZTEK to begin
work under the terms and conditions described in this document.
Please return signed acknowledgment copy promptly.
Collier County IT
Aztek Communication Technologies
Authorized Client Representative
Tim Beckman, RCDD
President
Title
Title
February 28.2010
Date
Date
The services and pricing outlined in this proposal will expire sixty (60) days from the date of this
proposal unless extended in writing by Aztek Communication Technologies.
Any applicable Federal, state, and local taxes have been excluded from the charges quoted in this
proposal.
Please contact me if you have any questions.
ThankY014
Tim Beckman, RCDD
Aztek Communication Technologies
4730 Enterprise Ave.
Suite #308
Naples, FL 34104
239-659-0017 OFFICE
239-659-0018 FAX
239-494-7411 CELL
tbeckman@aztek-naples.com
www.aztek-naples.com
Confidential
Page 3
3/2/2010