Agenda 03/09/2010 Item #16B 2
Agenda Item No. 1682
March 9, 2010
Page 1 of 17
-_-..
EXECUTIVE SUMMARY
Recommendation to provide authority to make payment in the amount of $135,625.00 to
CH2MHill for Professional Services for Design Services for the Immokalee Road, Collier
Blvd. to 43rd Ave. Project (No. 60018).
OBJECTIVE: To provide final payment to CH2MHill for post design services performed
during the life of the road construction and to provide payment for future services to be
performed in order to certify to South Florida Water Management District (SFWMD) that the
project has been constructed in accordance with its permits.
CONSIDERATIONS: On May 16,2000, Purchase Order 005281 was issued in the amount of
$2,352,928.00 for Professional Engineering Services for the Design and Permitting of the
lmmokalee Road Project (PSA 99-3020). The professional services agreement was expanded
during the life of the design as shown in the following table:
-
Document Date Amount P~se
99-3020 May 16, 2000 $ 2,352,928.00 Ori inal Contract Amount
SA#I January 9,2002 $ 230,444.00 36" Water Main & 16" Force Main added by
PUED
SA#2 June 11,2002 $ 213,490.20 Shift Alignment, add Wildlife Crossing,
Change Profile, add Box Culvert, Revise
Ponds, SHPO required and Development
Coordination
SA#3 July 29, 2003 $ 418,979.00 Revise design from 4-lane to 6-lane
$ 3,215,841.20 Revised Contract Amount
On September 15,2003, a notice to proceed was issued for construction. On October 12,2005,
Supplemental Agreement #4 was issued extending time on the design contract to provide for post
design services throughout the remaining life of the construction project. The Project Manager at
the time noted in the justification "There may be additional costs incurred due to the limited
post-design fees included in the original contract. They are constantly being contacted for
construction clarifications and field unknowns, and their services are needed." These fees were
never increased during the life of construction and the project was finalized on April II, 2008.
When following up on certification of the project to SFWMD, CH2MHill presented staff with
what was to be Change Order #5. It was intended to recover the cost for services performed
during construction and to complete the process of certification to SFWMD. We have researched
the tasks shown in their submittal and have verified that they were in fact performed and that
they are reasonable charges. However, a change order cannot be processed at this time because
Purchase Order 005281 has been closed. We therefore need to seek board approval for the
authority to make payment.
-
Agenda Item No. 1682
March 9, 2010
Page 2 of 17
In performing a comparison check of this contract, if this $35.5 million dollar project were to be
programmed, $3.55 million (IO%) would be set up for design and $355,000 (1 %) would be set
up for post design services for a total of $3.9 million. With board approval for payment of
$135,625.00 the total fee for this project becomes $3,351,466.20, which is well within reason
and certainly not excessive for a project of this size.
FISCAL IMPACT: The fiscal impact of item is $135,625.00. Source of Funds are Gas Taxes
and Impact Fees.
LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County
Attorney's Office and is legally sufficient for Board action--SRT.
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated
with this Executive Summary.
RECOMMENDATION: That the Board of County Commissioners:
1. Provide Authority to make payment in the amount of $135,625.00.
Prepared by: Gary R. Putaansuu, P.E., Principal Project Manager. Transportation Engineering &
Construction Management Department
Attachments: I) Change Order #5
2) Scope of Services
.",.,.
-
Agenda Item No. 1682
March 9, 2010
Page 3 of 17
COLLIER COUNTY
BOARD OF COUNTY COMMISSIONERS
--
Item Number:
Item Summary:
1682
Recommendation to provide authority to make payment in the amount of $135,625.00 to
CH2MHill for Professional Services for Design Services for the Immokalee Road, Collier
Blvd. to 43rd Ave. Project (No. 60018).
3/9/20109:00:00 AM
Meeting Date:
Prepared By
Gary Putaansuu Project Manager, Principal Date
Transportation Engineering &
Transportation Division Construction Management 2/22/20101:05:18 PM
Approved By
Lisa Taylor ManagemenUBudget Analyst Date
Transportation Division Transportation Administration 2/23/20108:19 AM
Approved By
Norm E. Feder, Alep Administrator ~ Transportation Date
Transportation Division Transportation Administration 2/23/2010 11 :45 AM
Approved By
,~-,
Scott R. Teach Deputy County Attorney Date
County Attorney County Attorney 2/24/2010 8:35 AM
Approved By
Rhonda Cummings Contracts Specialist Date
Administrative Services
Division Purchasing & General Services 2/24/20104:35 PM
Approved By
Pat Lehnhard Executive Secretary Date
Transportation Division Transportation Administration 2/28/2010 10:42 AM
Approved By
Steve Carnell Director - Purchasing/General Services Date
Administrative Services
Division Purchasing & General Services 2/27/20108:17 AM
Approved By
Leo E. Ochs, Jr. County Manager Date
County Managers Office County Managers Office 3/1/20108:44 PM
-~~-
~1_.11r;.\ A ___~...1_'T"__4-\r~u~_____\1r:f'I .K_.._1_ f'I "'^1f'1\1r. "^lI.TC'lT"':'lI.PT' Ar-orll.TT'!.A\1r.Tlo 'T'n AlI.Tc<nA
",)f"')f"'^1 ^
---.-",,-,,--------"
.
-
.
,",h_"' ,_
,
Agenda Item No. 1682
March 9, 2010
Page 4 of 17
Scope of Services - Change Order No.4
Collier County Transportation Division
Immokalee Road, CR 951 to 43'd Ave NE
Consulting Engineering Services Agreement
Additional Design Services
Project No. 60018
The CONSULTANT has been requested and retained to provide additional engineering services
associated with final completion of construction and certification of the project from South
Florida Water Management District. These additional services are based on various design
revisions requested by the County Transportation Division during construction to address the
needs of the project through construction and project close-out in order to certify the project.
Typically, these services are compensated for as a component of Post Design Services and not
specifically itemized in this fashion, however in this particular case the funding for Post Design
Services was not periodically increased while under construction to compensate the requested
work. This was due for the most part to the fact that the Project Manager assigned to the
project passed away and the newly assigned Project Manager concentrated on the need to
manage the CEI, Contractor and Construction. The specific details of the Design Contract
(services during construction budget amount remaining and contract schedule) were
overlooked at the time.
While these services were performed without immediate reimbursement, the services were
necessary to support construction activity and expedite the project. The direction to perform
these activities came from various sources within Transportation, rather than directly from a
Design Project Manager which is the usual protocol. The designer continued to provide services
and respond to the needs requests independent of specific project manager oversight and pro-
actively responded to the change requests in an effort to respond to public inquiries, avoid
project delays and expedite construction.
Prior to construction completion (during the project close-out phase), it was determined that
the existing design contract had been closed out and the remaining monies reallocated. That
determination prompted the need to request additional funding by different means to
compensate the Design Engineer for the Additional Services provided.
The following CONSULTANT Services are an addition to the original contract:
1. Traffic Safety and Access Management: The following changes were necessary to make the
project compatible with future roadway expansions at Wilson Baulevard and Oil Well Road
Page 1
Agenda Item No. 1682
March 9, 2010
Page 5 of 17
r
as well as address changes in access management that occurred due to the project being
converted from a 4-/ane typical section to 6-/ane typical sect/on post construction bid.
Add/tiona/Services provided by the Engineer included the following:
('"
a. Wilson Boulevard Design and Signal Modifications - $8,293
1. Coordinated design modifications with Collier County Construction and
Traffic Operations staff to address issues raised during construction
ii. Extend lanes and provide turn lanes to improve capacity and operations
iii. Revise signal layout to conform to new lane configurations
iv. Change signal timing to improve Immokalee Road green time (operations)
v. Revised Roadway Plan & Profile sheets, Cross Section sheets, Signing &
Marking sheets, Signalization sheets and applicable quantities
vi. Efforts included Project Management, roadway design and plans
modifications, and traffic engineering design and plans modifications (87
total hours charged)
b. Oil Well Road Signalization Changes - $6,635
i. Coordinated design modifications with Collier County In-house Design and
Traffic Operations staff to incorporate intersection improvements not
anticipated during original design at Oil Well Road
II, Revise Signalization to accommodate future Oil Well Road Improvements
i1i. Identify utility relocations needed with Orange Tree Utilities
IV. Revised Signalization sheets and applicable quantities
v. Efforts included Project Management, utility coordination and traffic
engineering design and plans modifications (67 total hours charged)
c. Orange Tree Homes Median Opening(s) Modifications - $4,285
i. Coordinated with Collier County Construction staff to address an access
management policy change for median openings that occurred after the
design was complete
ii. Closed full opening on Immokalee Road at Sta. 536+50 due to six-lane
configuration
iii. Replaced median opening with a restrictive direction opening
IV. Eliminated proposed SB left on Immokalee Road at Sta. 509+00 due spacing
distance with median at Randall Boulevard (full opening was too close to
Randall Boulevard)
v. Revised Roadway Plan & Profile sheets, Cross Section sheets, Signing &
Marking sheets and applicable quantities
r
Page 2
Agenda Item No. 1682
March 9, 2010
Page 6 of 17
e
vi. Effort included Project Management, roadway design and plans modification,
and traffic engineering design and plans modifications (50 total hours
charged)
d. Turn Lane Extensions at Oil Well Road and 35th - $3,387
I. Coordinated with Collier County Project Management, Construction and
Traffic Operations staff to address citizen concerns/complaints regarding
queue lengths at the intersections of Immokalee Road/Oil Well Road and
Immokalee Road/35th Avenue.
ii. Changes are the result of increased traffic needing to make u-turns due to
median becoming restricted.
III. The addition of a u-turn at Immokalee Road/Oil Well Road intersection was a
result the median restriction associated with item 1.c. above
iv. The increased traffic directed to the median openings at Oil Well Road and
35th Avenue required additional queue lengths to accommodate the
movements not anticipated in the original design
v. Revised Roadway plan & profile sheets, cross section sheets, Signing &
Marking sheets and applicable quantities
VI. Effort included Project Management, roadway design and plans modification,
and traffic engineering design and plans modifications (30 total hours
charged)
.
e
e. Randall Blvd Signal Pole Dampening Evaluation - $1.298
I. Evaluate the existing signal pole and mast arm to determine if something
could be done to reduce the wind induced vibration of one of the signal
poles.
ii. Structural Analysis to determine if a dampening device could be installed.
III. Provide the specifications and details for the improvement.
iv. Effort included Project Management, structural analysis, detail preparation
(13.2 total hours charged)
f. EMS Signal Pole Evaluation - $1,401
I. Evaluate the existing signal pole and mast arm to determine if additional
signal heads could be installed.
Ii. Performed a structural analysis on EMS signal pole to confirm it could be
done.
III. Effort included Project Management, structural analysis (14 total hours charged)
g. Immokalee Road Speed Study and Technical Memo - $3,202
I. Evaluate the proposed 45 MPH Speed Limit
ii. Determine available options for higher speeds.
Page 3
Agenda Item No. 1682
March 9, 2010
Page 7 of 17
r
Hi. Prepare Technical Memo identifying the cost impacts of various options.
iv. Effort included Project Management, traffic engineering, plans and geometric
analysis, cost evaluation, preparation of tech memo and power point
presentation material (32 total hours charged)
h. Final Certification of Oilwell and Randall Signals - $3,202
I. Coordinated with Collier County Project Management, Construction and
Traffic Operations staff as well as Contractor
II. Analyze contractor field modifications to Signal Design Plans
iii. Evaluate field conditions compared to FDOT Standards
iv. Attend office and on-site field certification meetings
v. Effort included Project Management, traffic engineering, field analysis (32
total hours charged)
~
2. Match to "As-Built" conditions of surrounding projects: The project plans are developed
on information ovailable during the design process. Due to continued growth and
development, many site conditions on surrounding County and/or developer projects
change after the design period ends which requires design modifications during
construction. This is required in order to make the projects compatible and avoid future
throw-away construction by incorporating the changes at a later date. These changes
generally require odditional coordination, design survey, design analysis and revisions to
the construction plan documents. Additional Services provided by the Engineer included the
fallowing:
,.
a. Drainage Basin DA-1 and Pond 1 Design - $12,850
i. Coordinated with Collier County Planning and Project Management staff to
address a developer commitment change that occurred post design
completion.
ii. By DCA requirement, Outdoor Resorts Development was required to accept
drainage from the Immokalee Road drainage basin DA-1. Post design
completion, the development failed to construct their internal pond system
which impacted the roadway projects ability to provide treatment and
attenuation volumes for basin DA-l
III. Post design and construction bid, an agreement was reached to have the
County's engineer design and contractor build pond 1 on the Outdoor
Resorts Development in lieu of the original DCA agreement
iv. The Designer revised and/or added Roadway plan & profile sheets, drainage
pond plan sheets, drainage pond cross section sheets, drainage structure
sheets, and applicable quantities
Page 4
, n"""__~__, ,~_ _ ",,,. ._,_
Agenda Item No. 1682
March 9, 2010
Page 8 of 17
. v, Effort included Project Management, coordination with developer's
-.."....
engineer, roadway design and plan modifications, drainage design
calculations and plans modifications, and permit documentation preparation
(129 total hours charged)
b. ERP for Oil Well Road Improvements - $20,754
I, Coordinated with Collier County In-house Design to provide permitting
services associated with the modifications being prepared by Collier County
Transportation staff for the eastern leg of the intersection of Immokalee
Road and Oil Well Road
It, Collier County indicated a desire complete the work in a timely manner in
order to add the intersection improvement modifications to the original
construction contract
III. The proposed improvements along Oil Well Road resulted in an increase in
impervious area of approximately 3,2 acres
IV. Waterways Development and HOA was required to accept the drainage from
Immokalee and Oil Well Roads within their development limits
v, The addition of the 3,2 acres of impervious area required modifications to
Ponds lOA and 10C to treat this area and to discharge into Waterway
. development
~
VI, In addition to the design changes, a permit application (No. 050909-29) was ,
prepared & submitted to SFWMD
VII. Effort included Project Management, permit coordination, roadway design
and plans modifications, drainage calculations and plans modifications, and
permit documentation preparation (206 total hours charged)
c. Utility Evaluation at Wildlife Crossing - $12,235
. Coordinated with Collier County Construction and Utilities staff to evaluate a
I.
change associated with a construction deviation from plans.
II. The proposed utility lines shown in the construction plans were not
constructed according to plan by the contractor
III. The revised utility configuration resulted in clearance issues with other
construction elements and created difficulties with passing pressure tests
required by Collier County Utilities and the permit agencies
, Designer was asked to evaluate the situation and provide recommendations
IV,
to address the field conditions in a manner which avoided or minimized
relocation or reconstruction of the utilities and if possible avoided a
Construction Schedule delay
. -.
Page 5
--"-.--- ---"
Agenda Item No. 1682
March 9, 2010
Page 9 of 17
r
v. Effort included Project Management, roadway design and plans
modifications, structural design and plans modifications/additions and utility
coordination (117 total hours charged)
d. ERP for Sanctuary Road Improvements - $10,056
i. Coordinated with Collier County Construction and In-house Design staff to
assist with the design of a compensatory treatment system within the
Immokalee Road project for improvements along Immokalee Road at
Sanctuary Road
II. The Sanctuary Road improvements required treatment which was not
obtainable within the Sanctuary Road intersection improvement limits but
could be obtained by providing compensatory treatment within the
Immokalee Road Pond 11 limits.
iii. In addition to the design changes, a permit application (No. OS0413-7) was
prepared & submitted to SFWMD
iv. Effort included Project Management, roadway design and plans
modifications, drainage design calculations and plans modifications and
permit documentation preparation (103 total hours charged)
e. 36 Inch Water Main - Pipers Road Design of "Physical Break" - $3,313
I. Coordinated with Collier County Construction and Utilities staff to resolve
issues associated with activating only a portion of the newly completed
utility.
ii. Design a "physical break" in the water main which will allow just the first 2-
miles to be activated while keeping the remaining 6-miles dry.
III. Prepare plan drawings for restraining system, valves, plugs and blow-off
assemblies associated with the separation of lines.
iv. Effort included Project Management, utility design and coordination, plans
modifications and DEP permit documentation preparation (35 total hours
charged)
f. 5FWMD-BCB Handrail and Access at Box Culvert - $1,550
I. Coordinated with Collier County Construction and SFWMD-BCB Maintenance
staffto resolve issues associated with the access to and operation of Box
Culvert Control Gates
II. Develop non-standard configuration for handrail to improve access and
better accommodate SFWMD-BCB needs to operate control gates.
III. Effort included Project Management, field meetings and coordination and
design revisions. (17 total hours charged)
r'
,..
Page 6
",. .".~,-,-
-, - - . -" '._'.,"~'P"-
Agenda Item No. 1682
March 9, 2010
Page 10 of 17
e
g. DEP "Dry" vs. "Wet" Permit- $3,711
I. Coordinated with Collier County Construction and Utility staff as well as DEP
staff to resolve issues associated with the delayed timing of placing the 16
inch Force main and 36 inch Water main in service
II. Construction of the planned North East Water Plant project has been
delayed; therefore, segments of the two utilities will remain "dry" until the
plant is constructed.
iii. Engineer was requested to modify the DEP permit to reflect a "dry" utility.
IV. Effort included Project Management, numerous meetings and DEP
coordination, plan modifications and permit certification revisions. (41 total
hours charged)
~
.
3. Resolve Surrounding Property Issues: During construction, issues arise due ta changing
site conditions or stakeholder concerns that need to be addressed in a timely manner to
expedite construction and/or convey a positive public image associated with the project.
The Immokalee Raad Project was an 8-Mile, 2-lane to 6-Lane widening project whose
project footprint was approximately 155 Acres. Concerns and requests from adjacent
property owners, developments, projects and facilities are received and reviewed by project
staff for resolution if possible during canstruction. Additional Services provided by the
Engineer included the fallawing:
-.
",
.
a. Guard Rail & Grading Modifications for Well Field Ingress/Egress - $5,703
I. Coordinated with Collier County Construction Management and Utilities staff
to address safety and access issues associated with providing openings in the
guardrail along Immokalee Road for six (6) well locations
II. All changes requested by PUED Maintenance occurred post bid and required
modifications to the ingress/egress locations, guardrail and slopes of the
access roadway
iii. Revised Roadway plan & profile sheets and cross section sheet
IV. Effort included Project Management, field meetings and site visits, roadway
design and plans (cross sections, guardrail, grading) modifications (57 total
hours charged)
b. Foggs Nursery - $2,701
I. Respond to property owner's request to modify second entrance to match a
proposed future elevation of their site.
ii. Revise plans to accommodate the owner's request.
III. Modifications included revisions to grading, lateral ditch and cross drain.
.--
,
.
Page 7
Agenda Item No. 1682
March 9, 2010
Page 11 of 17
r
IV. Effort included Project Management, field meeting and site visit, roadway
design and plans (cross sections, lateral ditch grading, cross drain)
modifications (27 total hours charged)
c. Pond 1- Summit Lakes Permit Coordination - $2,801
I. Pond 1 was to be built by the developer of an RV Park in accordance with a
Developer Contribution Agreement, but their project did not move forward.
ii. Pond 1 was built under the road contract (see Item 2a. above) at a different
location on the property, but as provided for in the Developer Contribution
Agreement.
111. Pond 1 was later viewed by ACOE as being constructed without a permit
when the new owner of the property owner tried developing the property.
iv. Prepared a technical memo which documented the timing of the events on
Pond 1 construction, thereby satisfying ACOE concerns.
v. Effort included Project Management, field meeting and site visit, technical
memorandum and permit coordination with new developer and ACOE. (28
total hours charged)
d. Rock Road Residential Drainage Concern - $3,138
i. A resident of Rock Road expressed concern that the road improvements
were causing flooding to occur on their property.
ii. Consultant performed a field investigation and gathered wetland, soils and
contour data reflecting the condition prior to the road construction and
studied the drainage, concluding that the flooding was attributable to
development on neighboring property and not the road project.
111. Consultant then met with the property owner and explained their findings.
IV. Effort included Project Management, field meeting and site visit, data
gathering and evaluation, minor survey. (31 total hours charged)
e. Richards Road Residential Drainage Concern - $1,601
I. Resident on Richards Road complained to the board of water ponding they
attributed to the road construction,
ii. The board directed Transportation to look into the matter and come back
with recommendations.
Iii. Consultant performed a field investigation and gathered wetland, soils and
contour data reflecting the condition prior to the road construction and
studied the drainage, concluding that the flooding existed before and was
not attributable to the road construction.
iv. Transportation appeased the property owner by having Road & Bridge make
modifications to improve the driveway.
f"
",..
Page a
.
-
.
.
.
Agenda Item No. 1682
March 9, 2010
Page 12 of 17
v. Effort included Project Management, field meeting and site visit, data
gathering and evaluation. (16 total hours charged)
f. Krape Road Residential Drainage Concern. $3,526
i. Resident on Krape Road (Equestrian Center) was concerned about flooding
and ponding or water on their property.
II. Consultant performed a field investigation and gathered wetland, soils and
contour data reflecting the condition prior to the road construction and
studied the drainage, concluding that the flooding existed before and was
not attributable to the road construction.
iii. Consultant designed a lateral ditch to help store water and help reduce the
flooding along the owner's property.
iv. Effort included Project Management, field meeting and site visit, data
gathering and evaluation, minor survey, roadway design and plans (cross
sections, lateral ditch grading) modifications. (36 total hours charged)
~~c
.
4. Expedite Construction Activities and Schedule: The construction of 8 miles of G-Iane
improvements to Immokalee Road required a significant amount of coordination and
oversight from the Design Engineer. In addition to meetings with County and Permitting
Agency staff, the Designer spent a significant amount of time coordinating design and
construction elements with the Contractor including making minor modifications to design
to reflect changing conditions along the corridor. This coordination helped reduce
construction costs and expedite the schedule by resolving issues in a timely manner.
Additional Services provided by the Engineer included the following:
-.
,
a. Miscellaneous Design and Construction Oversight Services for coordination and
resolution of issues - $9,618
I. Attendance at weekly CEI - Contractor Meetings
II. Responses to Contractor Requests for Information (RFI's)
III. Review of proposed deviations from Contract Plans
IV. Review of Contractor Change Requests (Scope and Budget)
v. Periodic Field Review of Project Construction Elements
vi. Minor Design Modifications
VII. Attendance at Field Meetings
VIII. Effort included Project Management, office meetings, field meetings and site
visits, data gathering and evaluation, minor design modifications. (94 total
hours charged)
-,\
Page 9
r
,...
,...
.
Agenda Item No. 1682
March 9, 2010
Page 13 of 17
5. SFWMD Project Certification: The construction of 8 miles of 6-lane improvements to
Immokalee Road utilized 12 ponds (2 "wet" and 10 "dry") to treat and attenuate the storm
water run-off from the project. CH2M HILL was required to field review the constructed
facilities, review as-built drawings, prepare documents submit and obtain SFWMD
Certificotion of the project based on current criteria. Coordination with the Contractor was
also required to set survey monumentotion for the control structures, Additional Services
provided by the Engineer included the following:
a. SFWMD Project Certification - $10,365
I. Engineer Certification of constructed Storm Water Management System
ii. Perform field/site visits
ili. Coordinate Survey, As-Built data and Survey Monumentation with Contractor
IV, Coordination with SFWMD and Preparation of Project Certification
Documents
v, Effort included Project Management, office meetings, field meetings and site
visits, data gathering and evaluation, preparation of project certification
documents. (100 total hours charged)
Summary of Costs
1- Traffic Safety & Access Management $ 31,702.00
2. Match to "As-Built" Conditions $ 64,469.00
3. Resolve Surrounding Property Issues $ 19,471.00
4. Expedite Construction Activities and Schedule $9,618.00
5. SFWMD Project Certification $10,365.00
TOTAL (lump Sum) $ 135,625.00
.
Page 10
,...---...-.--.
ImmokakH> ROBd lColl1e
Brdio-.i.d$lreel)
Agenda &No. 1682
MarCh 2010
PagE! 1 of 17
Ch.n~OrtlttrNo,4
CH2MH1LL
,~,
SENIOR
R.EVlEW
PROJECT
-
'-EAllENGI
~-,
'"''
"""
srENO
TCT,IJ.
...
~~
COSTS
" WU",,_ , " ~ "
....Fe ,-, , ,
l:l-loIoy.05DELR1O.GERAAOOL'- ,
2O.....Y:-lI5oELR1O,GERARDI:l"L ,
2O......r-05FE!'lWlND.I'Z,AATI-iRn.i" "
B'JuI.ll5FEF!JII\NOU,KATHR~ .
1$..i".05 OElRlO, GEAARDOL "
22.Jul.OliOODaoi.ii:ilfflJsHANA .
22.,JuI-ll$l.JI.lWl8EAA,ADAM '"
1&-Oel.Q5fER!W<IDEZ.KATHR'rii "
2,M.Y-IlIIOELRm,GERAROOL ,
, . . . ,
.~. 011 {JODBOlE,BI-lUSHAl<lA ,
.. Im__.mWe!l_ " " " , $li,~:J5
:H'_KHAN,,o,sHFAO .
,().j'e.,.OO"ENOIl,SACIlIN "
l~f_DEi.R16GEIV.J-lpOL ,
m.f.I>.OOFERIl/l.h/OEZ,AAlIlFlYN ,
Hl_F.0-06 Kw.Il,ASH~A6 .
~._rERN:o.ND-Et_AATIlRYN '"
J........-OGf'ERNANDELAATHFlYN ,
10_""".QfIFERN":1l0EZ,AATH!iVN ~t
., lJrlIIIOOT....l-Iom.',-.O IncMDOolo<:lll_ , , o- W ~.:I$!I
Z7-101~DEJ.F1jO.GERAl.'l_lJO.l ,
2T_May-05FEFlNANllEZ,ILATI-!RYN .
:!--Jl.O\-05DELRIO.GERARDOl
:;.J\.o>.OSFERNANDF.z.KATI-lRYN .
1~J.....05'SCER80,FRAA'KE ,
HI_JLJ:l<lSDELRJO.GERARDOl ,
IT_Jun.05DELRJO.GERARDOl ,
II_J....05FEIlHANO€Z,MTHRYN "
29-JuHT5FERNANOEZ,AATH"YN "
" 'm~R",,~ ~'" l..... ~ll\e'1'I"""", 011 We' "",,~...;3 A...lfI\<l<O....""'" " " W "~
l,b"l'"Ofl.MIONON '" ,
8~09MENON,lIM:HIN ,
11._* MENON. SACHIN .
1C__Deo_OflGRAMlCR v.1lllMlJ "
.. "'''',,''''1:11''''1; nntp."'lIlIr"""'" cO"""'''''' " " ,.., S1,llll'
,~_EMc-{l7 S~l~. B lllAN~ ^ "
2Il-Doo-OTOI:LRIO.GERAROOl .
'_J.n-lI!IOElRIOGERAROOl ;
" E'M~ b"'"",~""E',"""""'''' s.""'-".-.'E''''U,"'''" " " li' ~<l'
\I-~"Y-OU L.J\lI"'fl~"RA....tJAM ;
ll1-MolMl80ElRIO.GERJlROOl ,
2J-MrH181-AllARBEAA.AD"'" ,
2J_.......08fiEtJER,JAMIEP ,
".,__l<ooO~"",,"Ii'cOl.E""'""''''''d"01''''''''O.''''''''no "' " SO_W
"'.Mar-llllOEL!llU,Cl:FlAflO.o,. .
21_Mat--DBOELRIO,GERNlDOI "
78,..,....06-0E1RIO.GFRAIlOOL ,
" ,...1"0", (..."'",."""01U_~_~""".'_~n""mo"'''' kOBo "' " $3,:m
"AIl'.UlIHEUER,JMIIEP "
11.......oe.OE\RICl,GEl'IAAOO, "
~.0<'-68-0Ei.R'OGERAROOl ,
ImmOUlH_C....."'.1
$'"'-"
I1ZT,e~
I1OG.~
.
.u N&lCtI10 "Ao-eul ~. --
" U"""..,elloo",(JA-l ~ol1dD<><'o" ,. . . ~ .~ 5\2.6~O
T~.<.b.lM WI\lLA{;~. STEVENl '"
l7-FfIl>.04CURllli,-ANOREWE "
27.~~b,04 WALLACE, SlEVl:N l "
2;.f_lUQO.QI>lE6,NYDIAM ,
1!>-1\lI<.I)OWIIl.i.ACE.STEVl:~l .
If'-AjlI',OO_W.o.L\.ACE.STtvtN\ ,
10-/>fII-04M.I.RINESCU,GRISTIAN' .
lb''''',.lMlORENZO,WlI-llAMG ,
l:l-Apr.l)OWAlUICE,STElJEN, ,
Z~-Aj>r-I)O CUTRONE_GREGORY j ,
)Q.~.llOCumONt.Gf!EGORYJ ,
H.I"Y.oaW/lJ.lACE,STEI'lON, ,
'~.May:O. W/l.lll\CE SfEVf.I, l ,
lq,'*,_04WAllACE STEV~NL ,
21''''*1'.04 CUTRONE,GREGORYJ ,
2B.May.04MCKINNEYSANORA.. ,
l8''''''YO<GRAMER_WII1.IAMJ ,
"8.May04WillLACIO.srEVE'Nl ,
._J""O-< W<.LLACE SlEII~t;t .
'_J"",OoI CUT'l'ONE, G~~GO~Y;
"-J"".O~, NIl 1'1 I'l'f-NE 0
I7_J"".O~ SCEReO "RA'JY [ "
" ".""o.._Il,,,,~ _Oi'_" R",,~ Peml;\ " "" " 11, ,$ 5207,.
B_,J,JI.{)':>N..1t(IRHlt ,
I ~,_Ju>O'J HU'f1 llL>UlRl' "
1,.jU'05101\IH,'PfrNE ,
:rI.Ju"O~ HUNT, R06E'l'11 '"
Z,_JU',O&>w\OUll.l5ANToN'S "
n.Jul,lY.'W,HI,IRENL ,
~2_J">-OO WlNl.10M, M<Y 1- ,
~"'.hM)&HUNLROaUlll ,
2g_.,",O~' IlELRIO GE'l'AIlDO, "
2\1-J\~,O~ WINDOM, AIM L ,
~""".o~ 'IUNT, ROBf.:F\T' .
!>-AIJ9.md,lCCDRD,SUlANNfr ,
'~_"~OSHUNT,ROBERTl '"
'~.A<I\I.Q5 WlNDOM_AM\-'l ,
1!\-A",,<I~ HRw.NtlEl,KATHR1'i "
2r,.huQ.n5WlNOOM,.M<\-'l .
17_1-.b--00IiUNl flOBFRTT ,-
24.\-eb--OliHUNT RO[JfR1T "
11.M.y-OCiHUNT.JlOaI:RTT .
11~.1..00 OESTREICH. JcJrn~Y A ,
. utili &..,~."o".'Wl'd'H.C"",. ~; . 1<" "1 $'2Z1~
1."ol>-080~1.RIO.GERAlWOl "
U.Col>-OaS'MPSON.SCOTll ,
n_"""'D8010~OANO,r.;ARYt.' , ~
2~_C.o_0!I C1n~Io. GERARDO. "
29-C.D-OflDElR'O_GfRAROOl "
zg_..o.D8GODDOLE.BIiUSIlANA .
T-M..-_D80I";,LRIO,GERARDOl "
1-M<iI_OII~OIlBOLE BHUS'1N'A ,
'.ApI.{I!OHRIO.GERIIROO\ "
:\.Apr-UIIlAMROfRA,ilOM' ,
18.Ap,.08 LA!lhR6f:RA....DhM "
In.'''..-llIl DElRIO. GE,...~IJCJ l "
U ,,,,,,,"""..RO"..$o"""'" ~-" . " " .00 $100
Copyor'''''''o'_C''""g.O''l,,,_N,,_~o'"p''''''''mm,,"",'' PiI!l<'l Pt1n16ClTOIllll2OOe2'.ol-OPM
CH2MHlLl
: Agenda No
March 9
- p.age 1
1682
2010i
of 17
ChanlleOrclerNc..4
" ".....
'^~
CLERK TOTAl
STENO HRS
lAllO~
COST6
~-,
'4-Q<:l.05'WINOOIoI,AMYl
u_0<:I-05' GRl\MER.WILLIAM i
21.o.'.05'HUHl,'FlOBERTT
2'..Qct.4Ii WRIO, GF.RMOO~
iii:Oci.o!lIfJifr,RoIlERlY"
2&-O<:l,clfoeL,RJO,GEIWIPPl
..-.c5'HUNl,-ROBERTI
4-Nov-O!lDELRIO.GEFlAROOl
18.-.o!iE5CAl.o\NrE,'Il~I!!_
'2.lill<:05-6El~IO,OEFiAAOOL
l&tJK.05-'WtNnoM.N.ffl"
--....,,','
h
~W_""iII.
'/.Met.c5'''' ,6ACHIt<'
1'J.Miii.OO:OELAio.GERNfDbk
21-Mar.(lll HELDOIIf'e~. KEVIN.
24-l,lIHlllOELRIO.GERAROOl
3\-Mar-OOOELRIO.GERAIlOOL
3i.:Miii;QqoemEid{jEFrnEYA
~ "
'" --...
.
.
. _u__....._
.
.
. .
.
.
~ ..
"
"
'"
..
"
$3,~13
"
"
$1.MO
i OIiPW.t-"'....ndforeft'l..........'l_i.ob"""
'N." LRIO. ElVoROOl
--\~....oiI'DE'LtijD:GERAROOL.
u.p.--Oll:OElll;iO,GElWIDOl
3-.'Il>r..(lllllIAOTH..EUZf<II.ETHJ
3--Ap,:Q&.'STVART.Ml<Il;lANl
d_b 4\
$3J11
..
... --- "Q.471
h Ii""'" Rail.nd O..d'n Madlllcail"",,~""'W.llf~' " " .~, ro
v"JJ2fJ(J7.0EU!:IO.GEI'W'lDOl- .
~:DHR10.GEf:i.i.ili:iOT ,
2I1012007DELRIO.GERAROOL "
m312007'OHRIO,GERAROOl- .
3C,l12OO7 PELRi6:0ERAAOOT- "
3rnli2cKs-;'oELRib:GERAAtiol .
4i612iiilfDEiil'iO,GER.t.Rlioi. .
4113r:zoo10ELRlO.GERAFlOOL .
" .. .1'1.... ~- 0 0 " 0 0 0 " $;I,7m
'1131;U1(17 llll(),GERAROOuL .
1I11lr.l00l"OElRIO,ecRARDOL .
8/17120010F.LRIQ,GF.RARDOl "
~12"1N070HRIQ.aEI\AROQL .
" P....d'.s.u"""jIU....P.m>lICootd'n.''''nw''''AC;O~ 0 " '" 0 " " 0 " "',801
2()"G~.09.0El.RIO,G~RARDOl "
21.F_DEt.RIO,GF.AAROOl '"
OCMOf.OIlDEH1IO,mi'RARDOl ,
" RookR...u._I_'.'OnI'n. ~- , '" " 53,1,J,l1
\.Sep-OOHUIlJ,..R.OBE"-TT ,
'!;.f;<tp-OO..OES1REICH.,JEF~EYA
i2.SaF'-f?6 !"k,lNT, R9BERTJ - ,
,--, 19.5Gp..Uln,ur<<, ROBERT 1 "
l!l--Sop..OO,SCERIIO,m""IKE ,
Za_5<I!>-OOWINDOM.AMYl ,
" R'tII0td._G-R..'Mn'IoID..,n .C......." '" , 51,001
ll--J.l-llIP#,rH.'REI1lE ,
ii.~5-OIilfl[O.GERAROOt. "
, '" Ra.G._IG.nti.IO.. ,~~ . . " 53.~211
14",,,.00 m. EIlAAOOl "
l.J..ll~ OlElRID_GERARDOl ~
il.J....CS,ER.I1lANDrz,.j(ATHRI"'I .
2N.....OSDl!lRIO.GERAADOl ,
..
~
."
~
An..IIJ.n....6alHul...CIlI1''''''''''.CElOI>II
Olt...."df'.Id"'..,..
,
.
~
~
n5'~
"
_0
.
"
00
"
,-,
I1n.l:t6
,-~~
Copyollmmal_CI>an~Dnlc'_N""_B.ckupJ<l>:Xllmm,*,-
'-'
PMled11lrnlJ2OO92;"4PM
,....,..._,--
. .."--_.-.---
~_.._._.._.._-,-,_._---
Agenda Item No. 1682
March 9, 2010
Page 16 of 17
CHANGE ORDER
CHANGE ORDER NO.
5
CONTRACT NO. 60018
BCC Date:
Agenda Item:
TO: CH2M Hill
4350 W. Cypress Street
Tampa, FL 33607
DATE: 11-23-09
PROJECT NAME:
Immokalee Road, Collier Blvd. to 43'" Ave
PROJECT NO.:
60018
Under our AGREEMENT dated
May2
,2000.
You hereby are authorized and directed to make the following changers) in accordance with terms and
conditions of the Agreement: Add 719 daysto the agreement extending the completion date to March 31,
2010.
FOR THE (Additive) Sum of:
($ $135,625 ).
One hundred thirty-five thousand, six hundred twentv-five dollars
Original Agreement Amount
$
$2.352,928.00
Sum of Previous Changes
$
$ 862,913.20
This Change Order (add)
$_-L135,625.00
Present Agreement Amount
$
$3,351,466.20
The time for completion shall be increased by _719 calendar days due to this Change Order. Accordingly,
the Contract Time is now 3,606_ calendar days. The final completion date is March 31, 2010
Your acceptance of this Change Order shall constitute a modification to our Agreement and will be performed
subject to all the same terms and conditions as contained in our Agreement indicated above, as fully as if the
same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a full and final
settlement of any and all claims of the Contractor arising out of or related to the change set forth herein,
including claims for impact and delay costs.
Accepted:
,20
CONTRACTOR:
CH2MHill, Inc.
OWNER:
BOARD OF COUNTY COMMISSIONERS
OF COLLIER COUNTY, FLORIDA
By:
Gary R. Putaansuu, P.E.,
Principal Project Manager
By:
Alan Bollinger
Vice President
Agenda Item No. 1682
March 9, 2010
Page 17 of 17
DIVISION ADMINISTRATOR
"br_
By:
Norman E. Feder, AICP,
Administrator Transportation
CONTRACT SPECIALIST
By:
Rhonda Cummings
-
,-