Loading...
Agenda 09/13/2011 Item #16E169/13/2011 Item 16.E.16. EXECUTIVE SUMMARY Recommendation to accept reports, ratify staff- approved change orders and changes to work orders. 0SJ� IVE: To enable the Board to oversee the execution of administrative change orders and changes to work orders and promote accountability in the use of staff authority. C0NSQERAT10NS On April 22, 2003, the Board approved a recommendation to implement a plan to enable changes to BCC- approved contracts (Section XV.C, Collier County Purchasing Policy) of not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff. Also included in the report are changes to Work Orders. These include work orders issued under CCNA Contracts that are less than or equal to $200,000 (Section VII.C,,Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XV.G, Collier County Purchasing Policy) that are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater). - The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above. The plan calls for staff to submit a monthly report listing these change orders from the previous reporting period. Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders. These reports cover the period of July 8, 2011 through August 19, 2011. FISCAL. IMPACT: The total change to contracts is a deduction of $869.797.30. The total change to work orders is $52,500.00. LEGAL CONSIQERATIONS: This item raises no legal issues and requires majority vote for approval. -JAK GROWTH MANAGMENT>IMPACT: There is no Growth Management Impact associated with this action: RECgMMI DATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders ;Report and Administrative Changes to Work Orders Report, ratifies the listed change orders and changes to work orders, and _extend Contract . Number 08- 5124 until October 31', 2012 to coincide with the work order extension. PREPARED BY: Diana De Leon, Contracts Technician, Purchasing; Department 9/13/2011 Item 16.E.16. n COLLIER COUNTY l Board of County, Commissioners Item Number: - . 16.E.16: Item Summary: Recommendation to accept reports and ratify staff- approved change orders and changes to.work orders. Meeting Date: 9/13/2011 Prepared By Name: DeLeonDiana Title: VALUE MISSING 8/30/2011 1 :37:21 PM Submitted by Title: VALUE MISSING Name: DeLeonDiana 8/30/2011 1:37:22 PM Approved By Name: CarnellSteve . Title: Director.- Purchasing/General Services,Purchasing Date: 8/31/20116:58:26 AM Name: SmithKristen Title: Administrative Secretary,Risk Management Date: 8/31/20118:10:28 AM Name: PriceLen Title: Administrator - Administrative Services, Date: 8/31/2011 1 :35:30 PM Name: KlatzkowJet"f Title: County Attorney, Dater 9/1/2011 11 :41 :05 AM Name: StanleyTheres Packet Page -2758- 9/13/2011 Item 16.E.16. Title: Management/Budget Analyst, Senior,Office of Management & Budget Date: 9/2/20114:17:21 PM Name: OchsLeo Title: CountyUanager Date: 9/6/20113:46:33 PM Packet Page -2759- 140"N O C v O o m (a w 0 0 s d � 7 m W � p w O Z G op ov�9' W O a O a aCO� S _a S OD Cn Z7 -� ° p' D a � N m 3 x' Z m 0 C � D m CL d z 0 v N O N T r m A O O' N O W °w a a 0 m 0 3 C CL 3 CD CD(R O O. 3 N fU CD 'O d �U) En N V V O Z D O 0 Efl V 0 0 O 0 0 0 r. O CD A m f o O S d W O m V o D cn 7 v °o wat o0 d N - CD O A a a T d D A a) m o (a N R CD o z CL a d m CL T m r A O O a m 0 x � C �N F, E CA O 00 F. RE ffl O 00 (A 0 00 01 e z D Packe O C v O m Z m (a m' F CD f G 0 O S O W d 7 W W O m p O O p ? 7 O -� ° p' D a d j N O m 0 C � D > > m N CD CD m C c a s d 3 m J c 3 o � o ? m K z d m N D m N � C 3 Z 'D z D I z `n Z D z CD 'D 0 CD m n v � o N 00 o 0 °o 0 :Page-2760- co 0 a m a 0 w v 3 CD a 3 CD CD7 N O S c. 3 7 41 N CD 7 � G Z D Fn V V O z D O 0 4 N O 0 00 0 Z D /13/2011 Iterr C v O W Z m N Z CD f G 0 o d O m � W O m O N p O U d A a CT CL a N j 3 A A 7 CA co L S oV m. .< G d m o > > m N z d � m o N O O T s r m (a O O 7 � co 0 a m a 0 w v 3 CD a 3 CD CD7 N O S c. 3 7 41 N CD 7 � G Z D Fn V V O z D O 0 4 N O 0 00 0 Z D /13/2011 Iterr O - W Z CD f G W O cngoz CO C 0 Cn a — d a W Cr j N d N A 3 O m A W ` o :3 m D rn w o m w o CD Cn O C Z ° c2i N O r CD H O T � r CD O O K w CA z D 0, (b O U1 0 z D O 00 co 0 o tn 0 0 00 0 16.E.16. Z m o g v CD m 0 0a < S O W A 7 K A a 2W C"ZZ v OGi0 d 3 a 3 9 W W oZ O 'v O N � v W d n d C T m 3 m .mm 0 D O Dn W O Z 3 0m• F O ID d y m in 0 n x D 3 3 c m C d 7 0 w Oi r m m x x m m W O x wnn � D c 3� O v m co c 4A D O S 3 a d O W 0 c m 3 W D O m o < O y C d W T o a Se 0,0 a S S d d CD m f° W W 0 0 O Dd3n 3 n n S < O 'O c d D p < W CO O -n 50 Item O y z 0 W M. C7� o Z W f o fD O V o * 0 V O 4 O 5 N O N p� 7 fC N z 0 � O m o A t0 (D O CL N V O CA N CWO O � # ba CD CD M y � 0 3 R. N N m (p v O fD C O (7 N O c ' O N N t0 O O O~ N 7 � a N N V 0 p� O 7 N W A O En N W A O 4A Co O w O O 0 N O Oc A 0 0 O 0 O Item O < 0 W M. C7� o Z W f F O V 0 M 0 V 0 V 0 N O N 7 m A z 0 � m W OK�zC� U O N w W ool O y o 3 , rn O N M — A D CD S 0 3 R. N O O Co a ' O c ' O .i N QO f07 N - Cn tU a 7 =r CD O O N 'NO CD N O A O O N 0 O T_ O N =r N T D� i 0 a L ' n N O O x z D z D z D O O D O 0 0 Item O m 2 0 W M. C7� m f W f o O V A S Ot 0 V N \ 7 N N O V N -i O z 0 m Co w m W V N U O N w W a N W V CD CD O z 3 `° Co N m C m N N d O c O N O N m m O N 7 7 tU a 7 �_ N N N C (7 CD A Co A O b9 M A A O <n A C, A O is J v En rn O Oo N m O b o I o c 0 0 °0 0 0 0 Packet Page -2761- O Item O < CD 0 W M. C7� V Z W f F 0 0 0 V 0 � S N O V N 7 � m W D 0O O O o? N N CL CL C CL w V w w d c ti c w d a CD N m � N N > 7 � O � N x O N O � Q c O C C O � T 0 r N' fn N A O O 00 Cp w w O) A w N V A E» ca A J O w en w v O 0 Co N C m 9/13/2011 Item O z 0 W M. C7� O m m W f D > 0 0 V n � N O 7 N c d 7 -i O ID 0) 0 ID w o D 0O < = a 0 N Yk O .c-•.. o C U A Cn O v CD << C 3 0 O a N c O 7 N N N N O � 3 0 ? X CD .9 m d C CD N < O CD 169 N O en N N Ln rQ O O V N N O O En O O en Ut N 0 0 O O O 0 C. 0 16.E.16. z� O g O L 00'O< 3. N 7 6 7 ' 0. Y m 0 O. O Z O C 0 m 3 a0' 3 O z O V O CA M r O N d n d m c fD M .fir 3 o 7 < C d N T o a 3 c O n C-) W � d m m N A 400 O ° ` 3 a C) o 0 0 d 3 m ^� Co N T a '� D D> a O z 0 W M. C7� O m m w a D > M Oo 0 c 3 m c d 7 M m Co O 400 X Df)o 3 a O a N c O .3i CD CL 3 0 ? O 7 c 0 so 3 o 7 < C d N T o a 3 c O n C-) W � d m m N A 400 O ° ` 3 a C) o 0 0 d 3 m ^� Co N T a '� �, no Cy', C<D p N_ o :E 7 o 0 o °' 3 d o 3 3 N O CD c Z D CID d d O. 6 D x a m N 7 a w t y 7 o S N Z N 7 O ? 3 d a d N L] a a 3 d ID CD a CD o ° 7 (D <? m .< o y G O cx W o N 3 a (D d o N ° r o ° Er a so r� CD o � 7 G O Cn 41 (D n < ° y O E o V y CP = v ci rn 7 Ul 3 m o 'Go a oD C V Q m o a w N A c w y O 7 d � 7 a (b < V CD 7 A O O w N w CD y d Q o o0 CD (D CD N � oo d a CD w A m w m w CS CD m = O (D °o N e N fD O a 'm o 7 O � o 0 9/13/2011 Item 16.E.16. O _ (D 5 O ° _ < O — Z3 `' m Cr ° CD CD m 0 o c o a o 0 n OD S O C O CD S N W CD A x S O v d 3 7 CD CD (O N < O NO CO Cn- O 7 0 _ Sy _ O OHO CD (� O �� pZ� DSO �N fD w -y a N 30 3 3 d m 30 d o y o a A O C o m S r °- C°(11 -O D 5. ° A 7 a CD G. ANCo 7 JN -:, 9CD CD - d TO Co W O CD S W C p7j fD 'O ? ti N a 7 CD 9. d 0 O d R N n 7 ? O� 7 CD O O A W d a C 7 CD 0 N a S d N O 7 w d CD r CD Z d Cn j y y y CD 3 O < K 2, o CS y d 3' C� O 7 M CL d � (° O w o S o CD CD CD 7 CD D 7 y CD Q 'O y CD S < 0 a CD N N O N 0 ° y 3 CD 0 7 an 3 ZCD Q O CD O N. CD ° 0 CD C3 3 d Cnvv 3 CD r 2 a Q y (� v v o C 0'(Q N CD ^' (D d d Co c = N CD a �. Z �. T N O 3 N j r C� = G fC, N CD 7 O N 7 N 7 CD 7 O a CD N C N N. N 3 a fA N' 'r ° (o m Cl 0 7 o O v O a O 00 Sp l Sa O D= -. Z_ C7 (e C O_ (Tl (D .C.. S 7 CD O O O V y O y S U, O O a fn O< n 7 CD d O C d ;. O O C d y O w a DDD 7 '-Y 5 d -p (0 n. CD < M N C' n y 7 x U y N 69 O (D D (D O O N m C) 0 O a N d c a N CJ X 0 0 0 m C) m o O 3 d OD F o CV° d N 7 O O C n 7 A p O O. o CD m o .7. - m m m M o x O y d° o O 7 mn T CL O CD W 0 7J m CD N CD y O V d 7 O n 0 D C Cu CD Z D CD o a 7 (O c d m Z D 3 a m CD o ,`V° O O C o 7 < 3 CD s (D a Co CD Q O S 33 S N Cp CO � fA n D w -Co 3 Om C) m a C,0 O w A _o ° C p CD Cc N CL C�J CD 7 o Co m a b9 d C Q. O N y -Cl EA p ZI D o m CD w W 3 < w 7 Co m X n °O C d N =r A CD O O 7 - S o w°? N y w O n o O c O oN O o 00 a 3 3 W= d 7 ? CD V c m 7 O CD CD N CD 3 ao o ? N o Dy30 c` °o ° o 3-o C)> m O O O C d D T CL Packet Page -2762- 0 S O 7 O N O n O O N N Cn to is 0 a 00 N N N N D) O O O (3 `p (D n 3 S m N d 7 o r .- to N o R. 0M: rn D CD CD O 2 C�maf° F CD 3 7. O a S w N 7 0. OCn DOf7oO \ o 3 o s ° (SD 7 A 7 Co D � ° 7 W ,. C a (� m m o 0) m n .CL * m 0 °' N `O G7 g 3 0 N n a � w m o m CD w R Co o o Co < (n 9. M eo A O 0 ss N A Co C) O N A 0. UI 0 0 Cl eo A Co Cn O O 0 0 °O 0 Z V O O O S � 7 W K o o� C o m CL x. a O_ (7i ND N � O IM A v 0 Q l< m w m m n v w CD 0= a a ^ m m `O C N CD 0 n. �y o c a 3 m 0 D c v CL 0 c � W � o CL { D ro D C rfl c0 O O c N 6s w O Ut O O i O 0 N al O O N 0 c en 0 0 N i.J N w N 0 Packet Page -2763- O D O CD CD O 2 (n F CD rn O o O n d D I 7 N \ O �o oCD O A S 00. O � (D 7 W ,. o M o 0 o y m CL 0a(n� > N T X 0 CD * m ° CD DJ N `O 0_ m 0 N O N a � 7 o N m o C N Zi m E_ m w o a v CD (0 a CD 0 (D 0 _� C O v j m m 0 3 Q, lA A A O e� A Ot A °o W A W O O w 0 0 0 6B T 0 A °o PO (D w 0 po w 0 9/13/2011 Item 16.E.16. s O D O CD CD O 2 (n F CD O o O n d D I 7 N \ o �o oCD m 00.ai 00. ° N Aft ,. CD o'c a w a w m 0 M 0. N T X 0 CD o °' C 0 O 0 0 O C v im In 3 Q, Eo O O O 69 Co O CD O O 69 Co O O O 0 °O O O °o O 0 0 CD °o 0 O 3 T\ O 1)00'o< S O (D >2�3� it0 i O C o m a0' O Z O_ 'O O (nvv �o m � d 3 m CD D O m D O Dv z W 3 n(o °c < o a �. N D I a S m M 3 (O W A 3 c m Aft ,. m n0 O O C 7 M W m v O 0 A D00 fl/ 010 N CL O 3 m O m E_ m D O m 3 0 < O `i N C d W T 0 a � e fl O 0 n a S m 3 (O W A C M Aft 0 > n0 O O C 7 O m ^' N N T M K COT rier C ow'It AdrinistraM Senriom Oi<vision /�N Purchasi Contract Change Request i _t1/ ) C4� T — 9/13/2011 Item 16. E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: oA - Mod # :x f PO/Work Order M Project Name: 45A44a68W 5Zt3 Last BCC Approval Date; Agenda Item # 4500126898 528324 th Ave SW, Naples, FL 34116 Project #: 11 -06 Project Manager: Department: Housing, Contractor/Firm Name: William J. 0.00% Frank Ramsey Human & Veteran Services Varian Construction Original Contract/Work Order Amount $ 80,118.50 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount #N /A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 80,118.50 Explain why additional days are needed (detailed /specific): Dollar Amount of this Change $0.00 , insurance certificate(s) from; AP 0.00% Total Change from Original Amount Revised Contract/Work Order Total Add new task(s) $80,118.50 ❑ Delete task(s) #N /A Change from Current BCC Approved Amount Cumulative Changes $0.00 Provide a detailed and specific explanation of the requested change(s) to the task(s): Revise completion date for 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 3/25/2011 7/11/2011 change): 10/10/2011 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current Project was stopped by Housing, Human & Veteran Services due to administrative insurance certificate(s) from; AP plan delays. or obtain from vendor Add new task(s) ❑ Change task(s) ❑ Delete task(s) Other (specify): Additional Time Provide a detailed and specific explanation of the requested change(s) to the task(s): Revise completion date for additional time to complete project. 2. Provide detailed rationale for the requested change: Vendor was asked to delay work start date in order to allow for administrative plan amendments so that payment would not be delayed. 3. Provide explanation why change was not anticipated in original scope of work: Payments were stopped due to administrative plan. 4. Describe the impact if this change is not processed: Project will not be completed and will need to be rebid. I Type of Change / Modification ❑ 1. Planned / Elective ® 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4. Correction of errors ) I ❑ Regulatory Agency (specify): I ❑ 6. Schedule adjustment Change Requested By Contractor /Consultant —Design ® Owner I ® Using Department Professional I ❑ Regulatory Agency (specify): ❑ Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes ❑ No Approved by: Date: 1 Name and Title: Trait NHS eviewed by: Date: -Jurchasing Professional's Name: Packet Page -2764- Revised: 4/6111 1 Goer COW-* AdriniwaM SeMom Division Pu as' g Contract Change Request 9/13/2011 Item 16.E.16. b6':W 7Iltllt V--t� Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: OQ— Mod #: t PO/Work Order #: Project Name: 4a8A4�6S8C- SZYB 7/11/2011 4500126886 1924 46th Terrace SW, Naples, FL 34116 Project #: 11 -07 Project Manager: Department: Housing, Contractor /Firm Name: William J. plan delays. Frank Ramsey Human & Veteran Services Varian Construction Original ContractlWork Order Amount $ 72;447.10 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount #N /A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 72;447.10 Dollar Amount of this Change 1 $0.00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $72,447.10 #N /A Change from Current BCC Approved Amount Cumulative Changes $0.00 1 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 3125/2011 7/11/2011 change): 10/10/2011 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current Project was stopped by Housing, Human & Veteran Services due to administrative insurance certificate(s) from SAP plan delays. or obtain from vendor): `1 I Add new task(s) ❑ Change task(s) ❑ Delete task(s) Other specify): l Additional Time 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Revise completion date for additional time to complete project. 2. Provide detailed rationale for the requested change: Vendor was asked to delay work start date in order to allow for administrative plan amendments so that payment would not be delayed. 3. Provide explanation why change was not anticipated in original scope of work: Payments were stopped due to administrative plan. 4. Describe the impact if this change is not processed: Project will not be completed and will need to be rebid. Type of Change / Modification ❑ 1. Planned / Elective ® 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4. Correction of errors ❑ 5. Value added ❑ 6. Schedule adjustment Change Requested By ❑ Contractor /Consultant Owner ® Using IDepairtment Desi n Professional ❑ Re ulato A enc s eci Other Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes ❑ No Approved by: Date: I Name and Title: - fin K k Vvut t A, Reviewed by: n Date: Purchasing Professional's a Packet Page -2765- r Revised: 4/6111 1 zr cowdy Adm�-Setvioes, Uvisbn Parchasit 5a Contract Chanae Reauest 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form 7 Work Order Modification Contract #: 10 -5551 Mod #: 1, Amend 1 PO/Work Order #: N/A Project Name: 2011 Tourism 4. Correction of errors 5. Value added -Quantity I L 6. Schedule adjustment Agreement Project #: N/A Project Manager: Jack Department: Tourism Contractor /Firm Name: Children's Wert Musaam of Naples Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change Revised ContracttWork Order Total Cumulative Changes Original BCC Approval Date; Agenda Item # Last BCC Approval Date; Agenda Item # #tOa ' #N /A Total Change from Original Amount #NIA #N /A Change from Current BCC Approved Amount #N /A #N /A Change from Current Amount Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 9130/11 1 9/30/11 change): 9130/11 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current N/A insurance certificate(s) from SAP or obtain from vendor : 0 ❑ Add new task(s) Change task(s) Delete task(s) Z Other (specify): Name Chanae 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): To change the name of the sub - recipient from Children's Museum to Golisano Children's Museum 2. Provide detailed rationale for the requested change: To properly reflect the correct grantee. 3. Provide explanation why change was not anticipated in original scope of work: The department was notified of the name change after contract award. 4. Describe the impact if this change is not processed: Invoices cannot be processed. Type of Change. /; Modification' ❑ 1. Planned / Elective ® 2. Unforeseen conditions /circumstance ❑ 3. or price adjustment 4. Correction of errors 5. Value added -Quantity I L 6. Schedule adjustment —'� Approved by: _ ..4., `,.4 !r, �"- Change Requested`By ❑ Contractor /Consultant I ❑ Owner Using Department ❑ Design Professional 1 ❑ Regulatory Agency (specify): ❑ Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: L3 Yes ® No —'� Approved by: _ ..4., `,.4 !r, �"- Date:7/13/11 Name and Title: Jack Wert, Tourism Director .viewed by: �. Date: -7 1-3 i Purchasing Profession l's Name: i)�cc�.o� Revised: 4/6/11 1 Packet Page -2766- 9/13/2011 Item 16.E.16. EXHIBIT A -1 Contract Amendment 91 10 -5551 "2011 Tourism Agreement between Collier County and the '^ Children's Museum of Naples, Inc." This amendment, dated ( ( , 2011 to the referenced agreement shall be by and between the parties to the original agreement, Children's Museum of Naples, Inc. (to be referred to as "Grantee ") and Collier County, Florida, (to be referred to as "County"). Statement of Understanding RE: Contract #10 -5551 "2011 Tourism Agreement between Collier County and the Children's Museum of Naples, Inc." In order to continue the services provided for in the original Contract document referenced above, the Grantee agrees to amend the above referenced Contract as per the Supplemental Authorization Exhibit "A1 -A" attached to this Amendment and incorporated herein by reference. The following change to the above referenced Contract has been mutually agreed to by the Grantee and the County: Each and every place where the name Children's Museum of Naples, Inc. is used is to be replaced with Golisano Children's Museum of Naples, Inc. All other terms and conditions of the agreement shall remain in force. IN WITNESS WHEREOF, the Grantee and the County have each, respectively, by an authorized person or agent, hereunder set their hands and seals on the date(s) indicated below. GRANTEE: Children's Museum of Naples, Inc. By: Edward J. Jone$ President of Golisano Children's Museum Type Name of Signatory Accepted: . 1 « [ Sa i i , 2011 T OWNER: BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY,, FLORIDA By: —66 I `�W Stephen Y. Carnell Purchasing/General Services Director PURCHASING By r� Diana De Leon, Contract Technician Approved as to form and Legal sufficiency: ulo?q — Assistant County Attorney By: Jack Wert, Director 6f Tourism Packet Page -2767- Contract #: N /A Change Request Chris Townsend 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification PO/Work Order #: Project Name: 4500127456 4471 32nd Ave SW, Naples, FL 3411 Department: Housing, Contractor[Firm Name: Sun Coast Human & Veteran Services Roofino, Inc. Original Contract/Work Order Amount Original notice to proceed Last approved completion date: Original BCC Approval Date; Agenda Item # Current BCC Approved Amount 08/30/2011 change): 8/30/2011 Last BCC Approval Date, Agenda Item # Current Contract/Work Order Amount extension, must attach current insurance certificate(s) from SAP Dollar Amount of this Change ti" &51% Total Change from Original Amount Revised Contract/Work Order Total $6,700.00 #N/A Change from Current BCC Approved Amount Cumulative Changes $350.00 5.51% Change from Current Amount Completion.Date„Qescriptian ofthe Task(p) Ctian..gej. and ?Rafaoraaie forthe Cizange Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 6/1/2011 08/30/2011 change): 8/30/2011 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SAP or obtain from vendor): 0 Add new task(s) Ll Change task(s) L3 Delete task(s) Z Other (specify): Additional Time 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Repair damaged wood on roof and re -nail roof deck. 2. Provide detailed rationale for the requested change; Damaged wood is rotten and roof deck needs to be secured. 3. Provide explanation why change was not anticipated in original scope of work: Not aware of roof deck condition until current roofing system was removed. 4. Describe the impact if this change is not processed: Hol)le 1z)e (LLD, A-)di be 67+Fi5 , Tyype:q of Change / Modification ❑ 1. Planned / Elective 2. Unforeseen conditions /circumstance 3. Ouantity or price adjustment ❑ 4. Correction of error(s) I ❑ 5. Value added I LJ 6. Schedule adjustment Revised: 4/6111 1 Packet Page -2768- Change Requested By - ; ED Contractor /Consultant 1 ® Owner Using Department ❑ Design Professional 1 ❑ Regulatory Agency (specify): Others i : Purchasing Professional Participated in Ne obabon of Change / Modification: L1 Yes Ll No Revised: 4/6111 1 Packet Page -2768- Ar.+re � Drtilisiott. com county Purd1 Contract Change Request Contract #: #: 09 -35 1 Project Manager: Frank Original Contract/Work Order Amount Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change Revised Contract/Work Order Total Cumulative Changes .71 9/13/2011 Item 16.E.16. i Purchasing Department 1 Change Modification Form ❑ Work Order Modification PO/Work Order #: 4500123601 Department: Housing, Human & Veteran Sen Name: Contractor /Firm Name: Rnvmer. G.C. FL 341 1 t w Q 41S;1bq ;1&03 Original BCC Approval Date; Agenda Item # -�- A:: Last BCC Approval Date; Agenda Item # $g 00 = 0.00% - Total Change from Original Amount 117.00 #N/A Change from Current BCC Approved Amount $0.00 0.00% Chan a from Current Amount Ccrtnpletion. Date, Descr>tption:of,the Task4s3 Change, and RatiartNate far the Ghange Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 11/0112011 06/0412011 change): 07/10/2011 Number of days added (if Explain why additional days are needed (detailed/specific): extension, must attach current Project was stopped by Housing, Human & Veteran Services due to administrative insurance certificate(s) from SAP plan delays. or obtain from vendor): 36 Add new task(s) LJ Change task(s) Delete task(s) Z Other (specify): A.• 4;+;n n1 - ima 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Revise completion date for additional time to complete project. 2. Provide detailed rationale for the requested change: Vendor was asked to delay work start date in order to allow for administrative plan amendments so that payment would not be delayed. 3. Provide explanation why change was not anticipated in original scope of work: Payments were stopped due to administrative plan. 4. Describe the impact if this change is not processed: Project will not be completed and will need to be rebid. Type of Change /IModification 1. Planned / Elective I Z 2. Unforeseen conditions /circumsta��& . Quantity or rice adjustment 4. Correction of error(s) _ 5. Value added Schedule ad ustment n 2 Charge Requested By 0 Other 0 ' Approved by: �- ----r' - Date. 06/0312011 i Name and Title: Frank Raahs4' Housing Manager Reviewed by: ZI Date: 7 Purchasing Professional's Name: Revised: 416/11 1 Packet Page -2769- crier Coway ,� � ServiaPS Dnnsion Pur�asing ® Contract Change Request 9/13/2011 Item 16.E.16. V Purchasing Department Change Modification Form ❑ Work Order Modification Contract M Mod #: 1 POIWork Order M. Project Name: Master Developer for 09 -5184 ❑ 5. Value added 4500107949 Mixed Use Development Project #: N/A Project Manager. Department: Contractor /Firm Name: N/A Jean Jourdan Bayshore/Gateway CRA Pizzuti Solutions, Inc. Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change Revised Contract/Work Order Total 00 16G3 Original BCC Approval Date; Agenda Item 00 06/09/09 Last BCC Approval Date; Agenda item # Total Change from Original Amount Change from Current BCC Approved Amount Chanae from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date:N /A TRevised completion date (includes this completion date: ❑ 5. Value added I change): N/A Number of days added (if Explain why additional days are needed (detailed/specific): extension, must attach current insurance certificate(s) from SAP N/A or obtain from vendor): Add new task(s) -T Change task(s) Delete task(s) Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Active Wading Bird nests are located on the site. The addition of this task is for attendance, coordiantion and provision of a management plan to the Environmental Advisory Committee and Florida Fish and Wildlife Conservation Commission required by County staff in relation to the rezone application PUDZ- PL2010 -592, Cultural Arts Village at Bayshore. 2. Provide detailed rationale for the requested change: To comply with Collier County's direction in order to complete the MPUD rezoning process. 3. Provide explanation why change was not anticipated in original scope of worts: Unaware that Wading Bird nests were active. 4. Describe the impact If this change is not processed: Noncompliance with County staffs request for coordination with the appropriate agencies and provision of a management plan would not permit rezoning approval of the site. Type of Change / Modification 1. Planned/ Elective 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4. Correction of errors ❑ 5. Value added 6. Schedule adjustment Change Requested By ❑ Contractor /Consultant ❑ Owner I ❑ Using Department =Design Professional 10 Regulatory en cy (specify): County ❑ Others c' Packet Page -2770- Revised: 4W 1 1 Purchasing Professional Participated in Negotiation of Change / Modification: Yes 9/13/2011 Item 16.E.16. Revised: 416(11 2 Packet Page -2771- .1'\ 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 04- Mod #: 43 PO/Work Order #: Project Name: Courthouse Annex 3576 completion date: Various dates for 4500100674 various phases Project #: 52533 Project Manager. Hank Department: Contractor /Firm Jones Facilities Name:Manhattan/Kraft Construction Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change Revised Contract/Work Order Total Cumulative Changes e7;j,o, f Last BCC Approval Date; Agenda Item # 12.45% Total Change from Original Amount 4.61 % Change from Current BCC Approved Am •2.20% Change from Current Amount ni a ionJ?ateespr�j3ti In ate eTask(s�O ota eflf;,, v Using Department �y�, Last approved completion date: Revised completion date (includes this Original notice to proceed completion date: Various dates for 8/112011 change): 6/1/2011 various phases Purchasing Professional PaVpafkd Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SAP N/O or obtain from vendor): /V I lar Add new task(s) Change task(s) Delete task(s) Other (specify): Deduct Change 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): To reduce cost of contract to reflect approved amount to close out contract and make final payment to Manahattan Kraft Construction. 2. Provide detailed rationale for the requested change: To make final payment and close out contract. 3. Provide explanation why change was not anticipated in original scope of work: N/A 4. Describe the impact if this change is not processed: can not make final payment and close out contract. 'x�z6�Tf GFiari ica'o a�'��,�� _. [ p pm 5 ip ®- M . ,s rh,a Srso-° s ° tir rcMiY:S�:' a a£i�# . xF k 1, Planned / Elective LJ 2. Unforeseen conditions /circumstance L 3. Quantity or price adjustment Ef 4. Correction of error(s) I L1 5. Value added I U 6. Schedule adjustment iii��a Approved by: Chang`e..(ZeglJes Lipwner v Using Department ❑ Contractor /Consultant ❑ Design Professional I ❑ Regulatory Agency (specify): ❑ Other s eci : Purchasing Professional PaVpafkd in Negotiation of Change / Modification: LJ Yes LJ No iii��a Approved by: Date: Z Name and Title: �� Y v 4 Packet Page -2772- Revised: 416111 1 Packet Page -2773- A Revised: 4/6/11 2 cm- qty Admirisb* a SWAMSDOSIM PUMh=V ® Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract M. 11- Mod #: a POtWork Order #: 45- Project Name: Napier Berm Restoration 5637 5.7.11 125857 Number of days added (if Project #: 88030.1 Project Manager: Clint Department: CZM Contractor /Firm Name: Eastman Perryman. Aggregate Enterprises, LLC Current BCC .Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change Revised ContractlWork Order Total Original BCC Approval Date; Agenda [ter Last BCC Approval Date; Agenda Item # -0.83% Total Change from Original Amount 44L -! Change from Current BCC Approved Amount - 0.83% Change from. Current Amount a 3mpletios Date, Desnrptxon oe 7as(� {sya�ae� aid Fzatiare arigrs Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: May 7, 2011 5.7.11 change): 5.7.11 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SAP or obtain from vendor): Add new task(s) Ll Change task(s) Delete task(s) Other (specify): Reduction in labor burden due to reduced material placement 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): The original bid estimate and contract included a specific amount of material to be installed on site including the required labor burden associated with this amount. However, during the course of construction the amount of material installed was reduced and subsequently reduced the amount of labor burden required to complete the intended scope of work. 2. Provide detailed rationale for the requested change: The required amount of sand material to be installed on site was governed and regulated by the DEP permit restrictions and the engineer's template outlining the boundary areas of the scope of work. During the course of construction the boundary areas were properly surveyed and staked out and upon the completion of work it was determined that less sand material was required in contrast to what was originally anticipated. 3. Provide explanation why change was not anticipated in original scope of work: The original bid calculations and estimate of sand material to be installed was determined according to the engineer's template outlining the boundary areas of the intended scope of work, however, after the official boundary areas were properly surveyed and staked out the margin of material is either increased or decreased depending on the prevailing site conditions. This condition is largely created by the unrestricted erosion control factors. I 4. :Describe the impact if this change is not processed: The contract value will be diminished by the consideration of what was received. Type of Ciratlged: Modff ca#ton ;'. _. 1. Planned / Elective Z 2. Unforeseen conditions /circumstance 3. Quantity or pnce adjustment ❑ 4. Correction of ergo s ❑ 5. Value added I ❑ 6. Schedule adjustment Packet Page -2774- Revised: 4/6/11 1 Contractor /Consultant Owner Using Department LJ Design Professional I LJ Regulatory Agency (specify): Other (specify): Packet Page -2774- Revised: 4/6/11 1 n 9/13/2011 Item 16.E.16 Purchasing Professional Participated in Negotiation of Change / Modification: Yes V-V — , Approved by: Date: Name and Titie. Clint Perryman, Project Manager Reviewed by: Date: _ Purchasing Professional's Name: Lyn Wo Revised: 4/6/11 2 Packet Page - 2775 - "'' /1 cr County A&*i9rAft.SeNtm Dvisim t*o� Phasing n Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 11- Mod #: 1 PO/Work Order #: N/A Project Name: On -Call Roofing Repair 5644 5. Value added I Ll 6. Schedule adjustment & Inspection Services Project #: N/A Project Manager: Robert Department: Facilities Contractor /Firm Name: Crowther Fuentes Roofin & Sheet Metal of Florida, Inc. Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change Revised Contract/Work OrdeF Total Cumulative Changes Original BCC Approval Date; Agenda Item Last BCC Approval Date; Agenda Item # #N /A Total Change from Original Amount #N /A #N /A Change from Current BCC Approved Amount #N /A #N /A Change from Current Amount Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: N/A N/A change): N/A Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SAP N/A or obtain from vendor): Add new task(s) Change task(s) Delete task(s) Other (specify): Provide a detailed and specific explanation of the requested change(s) to the task(s): To delete the words "work order" and replace with "purchase order" 2. Provide detailed rationale for the requested change: 3. Provide explanation why change was not anticipated in original scope of work: 4. Describe the impact if this change is not processed: TYpe of Change f Modification El 1. Planned / Elective 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ® 4. Correction of errors 5. Value added I Ll 6. Schedule adjustment Change Requested By= ❑ Contractor /Consultant H Owner ® -Using Department ❑ Design Professional Re ulato enc (specify): Other(specify): Purchasing Profess' nal Parjkipated in Ne i ion of Change / Modification: Ll Yes L No i i i , > c_v Approved by: Date / Name and Ti fie: eviewed by: Date .irchasing Professional's Name: V -- Packet Page -2776- Revised: 4 /6111 1 9/13/2011 Item 16.E.16. EDIT A -1 Contract Amendment 11 -5644 "On -Call Roofing Repair & Inspection Services" This amendment, dated July 19, 2011 to the referenced agreement shall be by and between the parties to the original Agreement, Crowther Roofing and Sheet Metal of Florida, Inc. (to be referred to as "Crowther Roofing and Sheet Metal of Florida, Inc." and Collier County, Florida, (to be referred to as "County") Statement of Understanding RE: Contract # 11 -5644 "On -Call Roofing Repair & Inspection Services" Statement of Understanding The following change to the above referenced Agreement has been mutually agreed to by the Contractor and the County. The additions to the existing language in the Agreement are shown herein by underlining; deletions from the Agreement are shown by s#iledeeughs- SECTION 2. STATEMENT OF WORK: Prior to issuance of a (delete) -T �,.-oi (replace) Purchase Order the Owner shall provide a summary of Work to be performed which will afford the Contractor the opportunity to submit a quotation for the work All other terms and conditions of the agreement shall remain in force. IN WITNESS WHEREOF, the Contractor and the County have each, respectively, by an authorized person or agent, hereunder set their hands and seals on the date(s) indicated below. Accepted: a , 2011 CONTRACTOR: Crowther Roofing and Sheet Metal of Florida, Inc. Thomas S. Callans Type Name of Signatory roved as to al orm and sufficiency bQf)uty ty Attorney NQ Robert DEPARTMENTPMECTOR By: / Step - n Y. Carnell Packet Page -2777- ack STRATEGIST rAQ Z Contract Change Request - 9/13/2011 Item 16. E.16. Purchasing .Department Change Modification Form ❑ Work Order Modification Contract #: 14.239 Mod#: 2 PO/Work Order M Project Name: Main Street Village Upgrades #M- 10 -UC-12 -0017 El 4. Correction of errors 4500125224 Last BCC Approval Date; Agenda Item # Project #: HM10 -01 Project Manager. Rosa Munoz Department HHVS Contractor /Finn Name: Big Cypress Dollar Amount of this Change 4, ��rllr, "' �� 1 0.00% Change from Current BCC Approved Amount Housing Co oration Original Contract/Work Order Amount T.ype.of Change/ Modification 1. Planned / Elective Original BCC Approval Date; Agenda Item # Current BCC Approved Amount El 4. Correction of errors Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount 19 Dollar Amount of this Change 4, ��rllr, "' �� 1 0.00% Change from Current BCC Approved Amount Revised New Contract/Work Order Total' $ . 220,834.00 0 Cumulative Changes $0.00 1 0.00% Change from Original Amount 0 Co plaon Ems, Description of the Task(a)- Change, and.Rad6 a lo. Eorthe.Change Original notice to proceed date: GffellM Last annroved date: Revised date (includes this change): 1 Number of days added ('d extension, Explain why additional day's are needed (detaiied/speafic): The developer recently learned that must attach current insurance their buildings did not have the needed outside electrical box per building. The water heaters oertificate(s) from SAP or obtain from they will install will remain "energy efficient", however, not ` tankless" ones. vendor :-Nfff O Add new tasks Chan a tasks Delete tasks Others • 2 D/ GNRivG c' 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): r The goal of this modification is to replace all references to " tankless" water heaters with "energy efficient° water heaters in the original project scopetagreement 2. Provide detailed rationale for the requested change: The language change will allow Big Cypress Housing Corporation to proceed with the installation of 'energy efficient" water heaters. 3. Provide explanation why change was not anticipated in original scope of work: This was an unforeseen circumstance because this subrecipient did not know that their buildings would not be compatible for the installation of tankless water heaters. 4. Describe the impact if this change is not processed: If this is not processed, the project will not be able to be completed, and we will not be able to provide the grant funds towards the project This will result in the cancellation of the project, thus resulting in Big Cypress Housing Corporation not completing the energy efficienty upgrades at Main Street Villaae for Collier Countv elialbe residents. Change Requested Ry T.ype.of Change/ Modification 1. Planned / Elective 2. Unforeseen conditions/circumstance I El 3. Quantity or price adjustment El 4. Correction of errors 5. Value added 1 0 6. Schedule adjustment Change Requested Ry ❑ Contractor /Consultant 113 Owner ® Usinq Department ❑ Design Professional Regulatory Agency sea ❑Other s Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes ® No Mn Approved by (Name and Title): Rosa Munoz, Grants Coordinate Date:7127/11 Reviewed by (Purchasing Professional): Date: f -v Packet Page -2778- Revised: 1 /1 212 01 1 1 X Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 10 -. Mod #: 1 PO/Work Order #: Project Name: On Line Video Learning 5530 Nhk- /O/S, //1 io/30 12 Jp /3o f Z Number of days added (if Project #: N/A Project Manager: Karen Department: Human I Contractor /Finn Name: Milner Fenwick, Eastman Resources Inc. Original Contract/Work Order Amount § '9 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount f 0MVIR �" ,r' Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount _ ° _ g Dollar Amount of this Change , _ _ #VALUE! Change from Current BCC Approved Amount Revised New Contract/Work Order Total $ 30,938.00 Cumulative Changes 1 $ 5.888 nn 23.50/9, Change from Original Amount 9 �f iOd►ia�Eioot�t�e Eronaof�th -` j�C�fsang Rio `ae Change .�. y Reviewed by (Purchasing Profe iona ): ' Last approved date: NtA Revised date (includes this change): WA Original notice to proceed date: Nhk- /O/S, //1 io/30 12 Jp /3o f Z Number of days added (if Explain why additional days are needed (detailed /specific): N/A extension, must attach current insurance certificate(s) from SAP or obtain from vendor : N/A X Add new task(s) I M Change task(s) El Delete task(s) Ll Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): To add funds for on -line health videos for the contract renewal period of 10/31111 through 10/30/12. 2. Provide detailed rationale for the requested change: The contract was originally for 3 years with pricing established for each year. The contract is being renewed for one additional year and videos were selected and priced for the renewal year. 3. Provide explanation why change was not anticipated in original scope of work: The contract contemplated a one year renewal; however, with the original contract term of 3 years, pricing could not be established for the renewal year when the contract began in 2008. 4. Describe the impact if this change is not processed: Staff and out -of -county members (incl. retirees on medical plan) would no longer have 24/7 remote access to required Diabetes education nor HRA - Healthy Bucks. Project an additional 1 FTE to provide the mandated education at additional facilities, telephonic service or Go -To Meeting education format during selected daytime hours. 9 �f iOd►ia�Eioot�t�e X 1. Planned / Elective Reviewed by (Purchasing Profe iona ): ' F1 2. Unforeseen conditions /circumstance X 3. Quantity or price adjustment 4. Correction of errors 5. Value added I EJ 6. Schedule adjustment 4 r. NO Contractor /Consultant ❑ Owner X Using De artment ❑ Design Professional ❑ Regulatory Agency (specify): Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: Lj Yes X No Approved by (Name and Title : 7, Date: l� Reviewed by (Purchasing Profe iona ): ' Date: Revised: 1/1212011 1 Packet Page -2779- rdown 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form M Work Order Modification Contract Mod#: PO Project Name: Isles of Capri Water Main 10-5441 1 4500117689 Replacement Phase I Project #: Project Manager Department: Planning and Contractor/Firm Name: Douglas N. 71010.7 Diana C. Dueri Project Management Higgins, Inc. F Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Change �Revised New Contract/Work Order Total Cumulative Changes 2. Original BCC Approval Date; Agenda Item Last BCC Approval Date; Agenda Item # Change from Current BCC Approved Amount Amount ................ "VIRP on" nale th" "'Ch'"" ; 17-1. Planned Elective Original notice to proceed date: Last approved date: Revised date (includes this change): May 17, 2010 February 17, 2011 February 17, 2011 Number of days added (if Explain why additional days are needed (detailed/specific): N/A extension, must attach current Purchasing Professional Participated in Negotiation of Change I Modification'. LQ Yes LJ No insurance certificate(s) from SAP or obtain from vendor): 0 Add new task(s) L Change task(s) Delete task(s) Other (specify): Provide a detailed and specific explanation of the requested change(s) to the task(s): Provide for removal and dispose of Asbestos Cement (AC) pipe, in lieu of grouting it in place. A work directive was issued on October 28, 2010 to proceed with the process of the removal. 2. Provide detailed rationale for the requested change: During construction, it was found that portions of the existing AC pipe was in conflict with the new main or was within 8' horizontal of the new main and must be removed to comply with Collier County Standards 3. Provide explanation why change was not anticipated in original scope of work: This work was not anticipated during design because the original plan was to abandon it in place. 4. Describe the impact if this change is not processed: In case of future new main maintenance, the abandoned AC pipe could be damaged. This would risk the health and safety of workers and the general public. If proper procedure were not employed in remediating the AC pipe disturbance, there would also be the risk of regulatory non-compliance. Both of these risks have monetary impacts. h -,V d 1 10 .. .... ....... 'Y .1 9. o fi H A -p 17-1. Planned Elective 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment -[1-4. Correction of error(s) I LJ 5. Value added I U 6. Schedule adjustment Revised: 1/12/2011 1 Packet Page -2780- ......... . ...... .... ... a, ...... ........ . . Change;Requesteds $ y .. . . .. ... . ............ v Z Contractor/Consultant I ❑ owner I ❑ Using Department Design Professional 1 0 Regulatory Agency (specify): I E) Other (speci!y): Purchasing Professional Participated in Negotiation of Change I Modification'. LQ Yes LJ No Revised: 1/12/2011 1 Packet Page -2780- Cj& czwlty Atutistive Dn+isiora Putt 7contract Change Request )L M 9/13/2011 Item 16.E.16. 1 � Purchasing Department Change Modification Form ❑ Work Order Modification i Contract #e? I Mod #: PO/Work Order #: Project Name: 4699426838 r 4500126898 5283 24"' Ave SW, Naples, FL-34116 Project #: 11 -06 Project Manager: Department: Housing, Contractor /Firm Name: William J. Dollar Amount of this Change Frank Ramsey Human & Veteran Services Varian Construction Original Contract/Work Order Amount gym, 11& -. n , v . u Original BCC Approval Date; Agenda Item # Current BCC Approved Amount` r a. Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount' extension, must attach current New tasks are being added. insurance certificate(s) from SAP Dollar Amount of this Change or obtain from vendor): 10 2.38% Total Change from Original Amount Revised ContractlWork Order Total $82,027.83 #N /A Change from Current BCC Approved Amount Cumulative Changes $1,909.33 1 2.381X. Change from Current Amount _. Coeaptetion Data: [escriptioit nt!< the T:ask(ajiCharag area ;Rateonaie ftar the Change Original notice to proceed Last approved completion date. Revised completion date (includes this completion date: 3125/2011 10/1012011 change).: 10/20/2011 Number of days added (if i Explain why additional days are needed (detailed /specific): extension, must attach current New tasks are being added. insurance certificate(s) from SAP or obtain from vendor): 10 I ff-A-dd new task(s) LJ Change task(s) Delete task(s) Other (speci 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Remove damaged dywall and framing due to termites, replace damage framing, replace removed insulation, replace drywall, patch any damaged stucco removed to access work areas, re- install outlet boxes and re- secure wiring attached to damaged wall areas, and provide additional termite treatment at affected areas. 2. Provide detailed rationale for the requested change: Areas have been damaged by termites and must be repaired and treated to protect the integrity of the structure. 3. Provide explanation why change was not anticipated in original scope of work: Termite damage was not discovered until cabinetry and interior doors were removed. 4. Describe the impact if this change is not processed: Contractor will not be able to continue project.ef the integrity of the structure would remain at risk. Type of.Change.!-;Madification I F-1 1. Planned i Elective ® 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment 4. Correction of errors 5. Value added 6. Schedule adjustment Approved by: f _ - ChangE:: l ## equested y Contractor /Consultant Owner Using Department Desion Professional 10 Regulatory Agency s eci : I Other s ci : Purchasing Professional Participated in Negotiation of Change / Modification: Yes No Approved by: f _ - Date: Date: Name and Title: ;j�;,yt�ay� I Reviewed by: ' Date: g �� Purchasing Professional's Name: Packet Page -2781- Revised: 4/6/11 1 y .t r XContract Change Request J— 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract M 08- Mod #: 4 PO/Work Order M Project Name: Watershed Management 5122 5. Value added X 4500106318 Plans Project M Project Manager: Mac Department: Land Contractor /Firm Name: PBSJ now A Hatcher Development Services Atkins Original Contract/Work Order Amount <$ a?5;736 95., 311010916A.10' Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 1 7J,134:33 ,',,10/131D9`-1'1,0B Last BCC Approval Date; Agenda Item # Current ContractNllork Order Amount $ 't;879,134.31 Dollar Amount of this Change ° 0.00% Change from Current BCC Approved Amount Revised New Contract/Work Order Total $ 1,879,134.33 Cumulative Changes $ 1,303,397.38 1 0.00% Change from Original Amount Original notice to proceed date: Last approved date: October -43, Revised date (includes this change): March 25, 2009 2002 (Re=-14-8+ ?I 3i I t 1 December 31, 2011 Number of days added (if Explain why additional days are needed (detailed /specific): ): The time extension is to extension, must attach current allow a more through public discussion and vetting of issues and completion of final insurance certificate(s) from SAP deliverables. The fertilizer ordinance component delayed workshops on the other or obtain from vendor): 122 Days I issues and extended the project completion date. _ Add new task(s) I LJ Change task(s) I LJ Delete task(s) I XOther (specify): Time Extension 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): NA 2. Provide detailed rationale for the requested change:The time extension is to allow a more thorough public discussion and vetting of issues and completion of final deliverables. The fertilizer ordinance discussions took much longer than anticipated and delayed completion of the project. 3. Provide explanation why change was not anticipated in original scope of work: An overly ambitious attempt to meet planning deadlines did not allow sufficient time for public discussion. 4. Describe the impact if this change is not processed: Failure to complete the Watershed Management Plans would result in a Growth Management Plan deficiency. Type of Change / .Modification 1. Planned / Elective X X 2. Unforeseen conditions /circumstance 3 3. Quantity or price adjustment 4. Correction of errors 5 5. Value added X X 6. Schedule adjustment Change Requested By - ❑ Contractor /Consultant I ❑ Owner X Using Department Design Professional I ❑ Regulatory Agency (specify): Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: Yes X No proved by (Name and Title): Reviewed by (Purchasing Professional): i" Packet Page -2782- Date:8/5/2011 Date: 9/- / /// proved by (Name and Title): Reviewed by (Purchasing Professional): i" Packet Page -2782- Date:8/5/2011 Date: 9/- / /// cf 6176TCOUXty Admini a Sens as DNL,�on Purchasing ® Contract Change Request ❑ Work Order Modification 9/13/2011 Item 16. E.16. T Purchasing Department Change Modification Form Contract #10 -5596 Mod #: 1 POIWork Order M Project Name: SRO Wellfiled Pipeline completion date: July 1.1, 2011 August 17, 2011 4500125162 Repair Project Project #: 70030 Project Manager: Alicia Department: PUPPMD Contractor /Firm Name: Mitchell & Stark from relocation of fittings to accommodate unknown field conditions, removal of Abbott existing fittings identified during the course of the work and associated repair of the Construction Co. Original Contract/Work Order Amount $ . "1.,8.12D00.00 -4_ 12,44 - 201A_10E Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 11„- T2DODMD Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount Dollar Amount of this Change $0 :00' 0.00% Total Change from Original Amount Revised Contract/Work Order Total $1,812,000.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and - Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: July 1.1, 2011 August 17, 2011 change): September 18,2011 Number of days added (if Explain why additional days are needed (detailed /specific): Additional Time related to extension, must attach current Pay Item 10.00 Contract Allowance work directives. These work directives resulted insurance certificate(s) from SIRE from relocation of fittings to accommodate unknown field conditions, removal of or obtain from vendor): M days existing fittings identified during the course of the work and associated repair of the pipeline, removal of rock to obtain proper clearance to the pipe, and investigation and repair of fittings in order to eliminate leakage in the pipeline. ❑ Add new task(s) ❑ Change task(s) ❑ Delete task(s) Z Other (specify): Time Extension 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): The requested change is to add an additional 33 days to the contract time. Staff previously approved by letter change 36 additional days. 2. Provide detailed rationale for the requested change: This additional time will allow the contractor to adequately complete the repair of the pipeline.The work resulting from these work directives will reduce the risk of a failure occurring during a future peak flow period. This will minimize risk and maintain quality of service. 3. Provide explanation why change was not anticipated in original scope of work: This change was not anticipated as the additional work to be performed was not discovered until the pipe was uncovered, new as -built data surveys were performed, and an internal video inspection was completed as part of this contract. 4. Describe the impact if this change is not processed: If this change is not processed the contract will be closed and the contractor will not be able to complete the work. This would leave the raw water pipeline in an incomplete state and may result in the inability of the County to provide adequate utility service to its customers. Utilizing a different contractor to complete the work is a possibility. However, this would significantly delay the work and result in unnecessary additional cost and risk. Type of Change I Modification ❑ 1. Planned / Elective ® 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4. Correction of errors ❑ 5. Value added ® 6. Schedule adjustment Change Requested By ® Contractor /Consultant I ❑ owner [] Using Department ❑ Design Professional I ❑ Regulatory Agency s eci ❑ Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes ❑ No Approved by: -�1 Date: zi 1 Name and Title: — v �-,'I Reviewed by: Date: Purchasing Professional's Name:, t Revised: 7127 Packet Page -2783- I /0"\ CO r Comity AdminWave Services Division Purchasing ® Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #10 -5599 Mod #: 1 PO/Work Order #: Project Name: SRO Wellfrled Pipeline completion date: January 24, 2012 ❑ 5. Value added 4500125398 Re air Project Project M 70030 Project Manager: Alicia Department: PUPPMD Contractor /Firm Name: Stantec Abbott Consulting Services Original Contract/Work Order Amount $ 341 „534:00 1-11-2011, 1 OF Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ .'si .. 341; 534:A0 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 341:;534 DO: Dollar Amount of this Change $30.5001J11 8.93% Total Change from Original Amount Revised Contract/Work Order Total $372,034.00 8.93% Change from Current BCC Approved Amount Cumulative Changes $30,500.00 8.93% Change from Current Amount Completion Date, :Description of the Taskts) Change,'and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: January 24, 2012 ❑ 5. Value added change): Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SIRE or obtain from vendor): ❑ Add new task(s) ❑ Change task(s) ❑ Delete task(s) ❑ Other (specify): Provide a detailed and specific explanation of the requested change(s) to the task(s): The requested change is to add additional construction engineering inspections services. Work includes ongoing field inspection, project administration, and report generation. Additional inspection is required as the contract time for the contractor (Mitchell & Stark) was extended to allow for work done under an allowance item for unknown field conditions. 2. Provide detailed rationale for the requested change: The additional funds requested will allow for inspection of the work performed by the contractor to adequately complete the repair of the pipeline. The additional work by the contractor will reduce the risk of a future failure occurring. 3. Provide explanation why change was not anticipated in original scope of work: This change was not anticipated as the additional work to be performed was not discovered until the pipe was uncovered, new as -built data surveys were I performed, and an internal video inspection was completed as part of this contract. Continued discovery by the contractor and Staff of deficiencies and errors in the original construction and associated record drawings has extended the duration of the work, but will result in a safer, more reliable well system upon completion. 4. Describe the impact if this change is not processed: If this change is not processed the contract will be closed and there will be only be limited inspection performed by Staff. Detailed inspections are also required to assist with the pending litigation. Type of'Change /Modification ❑ 1. Planned / Elective ® 2. Unforeseen conditions /circumstance ®3. Quantity or price adjustment ❑ 4. Correction of errors ❑ 5. Value added I ❑ 6. Schedule adjustment Change Requested By ® Contractor /Consultant I ❑ Owner ❑ Using Department ❑ Design Professional 1 ❑ Regulatory Agency (specify): ❑ Others eci : Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes EJ No &Qproved by: Date: r nre and Title: — 2 A.-, .- viewed by: Date: Purchasing Professional's Name: 8 Packet Page -2784- Revised: 7127111 1 C-2 r3e�r CORYMV Adrr `� Savices Wsian purchu ng ® Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification I Contract #: 10 -5498 tT,e)edie Mod #: 1. PO/Work Order #:.N4— Project Name: MKYTaxiway Construct Project #: 33127 Proect Manager: Robert Department: Airport Authority Contractor /Firm Name: DeAngelis I ( Diamond Original Contract/Work Order Amount $' _5,959,00C. 02 10112110= 1`441':. Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ . 5,959,fi3tD:02, Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $:, ° x,:959 OOD:D2 Dollar Amount of this Change _. 9 ($78,44&1OLi) -1.32%1 Total Change from Original Amount Revised Contract /Work Order Total $5,880,560.02 - 1.32% Change from Current BCC Approved Amount Cumulative Changes ($78,440.00) -1.32% Change from Current Amount Completion Date, Description of the Task(s) Change; and: Rationale for the Change Original notice to proceed Last approved completion date: - - -...._ .. Revised completion date (includes this i completion date: 2/2/12 2/2/12 change): N/A Number of days added (if I Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SIRE N/A or obtain from vendor): N/A ❑ Add new task(s) Change task(s) Delete task(s) Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Delete electrical components for direct material purchaseas specified on the attached quotation from World Electric Supply. 2. Provide detailed rationale for the requested change: Airport Authority saves $4,440 in sales tax by purchasing these items directly from the supplier instead of through the contractor. 3. Provide explanation why change was not anticipated in original scope of work: Electrical work and components ' included in overall contract /bid. 4. Describe the impact if this change is not processed: Collier County will not realize the savings by purchasing the electrical components needed for this project directly from the supplier rather than through the contractor. Type of Change / Modification ❑ 1.. Planned / Elective ❑ . Unforeseen conditions /circumstance ® 3. Quanto or price adjustment 4. Correction of error(s) 5. Value added I L 6. Schedule adjustment Approved by: Date: J / Name and Title: Chris Curry, Exec ve Director Reviewed by, /' Date: Purchasing Professional's Na e: Wood Revised: 7127/11 1 Packet Page -2785- 10"1\ X r Goumy = dun ,.- Sery '— ,*,n= ® Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 11 -5690 Mod#: 1 1 PO/Work Order #: N/A Project Name:CEI for SR84 Radio Rd Current BCC Approved Amount $ 2,964,487.50 change): N/A to Collier Blvd Project #: 60073 Project Manager: Kevin Department: TECM Contractor /Firm Name: Atkins and 60092 Dugan 0.00% Total Change from Original Amount Original Contract/Work Order Amount $ 2,964,487.50 6028/11: 10B Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 2,964,487.50 change): N/A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 2,964,487.50' NIA insurance certificate(s) from SIRE Dollar Amount of this Change $0::00` 0.00% Total Change from Original Amount Revised Contract/Work Order Total $2,964,487.50 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: N/A Revised completion date (includes this completion date: NIA Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes Z No change): N/A Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current NIA insurance certificate(s) from SIRE or obtain from vendor.: N/A ❑ Add new task(s) LJ Change task(s) I ❑ Delete task(s) ® Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): To amend the contract language: correct project description, delete constructability review section and delete mention of geotechnical services. 2. Provide detailed rationale for the requested change: Project description was not complete and constructabiiity review and geotechnical services were already complete. 3. Provide expl anation why change was not anticipated in original scope of work: It was added to the contract in error. 4. Describe the impact if this change is not processed: Contract would include unnecessary services. Type of Change I Modification ❑ 1. Planned / Elective I ❑ 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ® 4. Correction of error(s) ❑ 5. value added I ❑ 6. Schedule adjustment Change Requested By EJ Contractor /Consultant Owner I Z Using Department ❑ Design Professional I ❑ Regulatory Agency s eci ): I ❑ Others eci ): Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes Z No Approved by: - I Date: . Name and Title. in DugVVrojeJ Manaaer Reviewed !� ` Date: Purchasing Wo signal's ame: � Packet Page -2786- r Revised: 7/27/11 1 9/13/2011 Item 16.E.16. EXHIBIT A -1 Contract Amendment 11 -5690 "CEI and Related Services for SR84 (Davis Blvd) Radio Road to Collier Blvd; Collier Blvd (SR/CR 951) North to Magnolia Pond Drive; and CR 951 (Collier Blvd) North to Main Golden Gate Canal" This amendment, dated ($. 2t i Ito the below Agreement shall be by and between the parties to the original Agreement Atkins North America, Inc. (to be referred to as "CONSULTANT") and Collier County, Florida, (to be referred to as "COUNTY "). Statement of Understanding RE: Contract #11 -5690. "CEI and Related Services for SR84 (Davis Blvd) Radio Road to Collier Blvd; Collier Blvd (SR/CR 951) North to Magnolia Pond Drive; and CR 951 (Collier Blvd) North to Main Golden Gate Canal" The following changes to the above referenced Agreement have been mutually agreed to by the Consultant and the County. The additions to the existing language in the Agreement are shown herein by underlining, deletions from the Agreement are shown by st- FikethMeugh SCOPE OF SERVICES CONSTRUCTION ENGINEERING AND INSPECTION 2.0 SCOPE: COUNTY Project Nos.: 60073 and 60092 Description: SR 84 from Radio Road to CR 951 -North to Magnolia Pond Drive, and CR 951 (Collier Blvd) from Davis Blvd. North to Main Golden Gate Canal. Section 8.7 CONSTRUCTABILITY REVIEW: Remove in its entirety. Section 10.0 SUBCONSULTANT SERVICES: The CONSULTANT may subcontract for engineering, specialized professional services with prior written approval o All other terms and conditions of the agreement shall remain in force. Packet Page -2787- finspection, materials testing, or the County. if eed; —t#e 9/13/2011 Item 16.E.16. IN WITNESS WHEREOF, the Contractor and the County have each, respectively, by an authorized person or agent, hereunder set their hands and seals on the date(s) indicated below. Accepted: 5+ f i� , 2011 CONSULTANT: OWNER: ATKINS NORTH AMERICA, INC. BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA PURCHASING /GS DIRECTOR By: AA By: ,. Stephen Y. Carrell Steven W. Martin, PE PROJECT MANAASER Vice President By. Kevin H. rVgifn Appr ed as to form and L aI�sufficiency- Deputy Coui ty Attorney Packet Page -2788- .. Cummings, FCCN, CPPB 9/13/2011 Item 16.E.16. Purchairav DepacEmeM: Chance Modification Forts Work order Modification con.t1ract M. MGM 1 P4Mlork Order k P ojeat Name: NCWRF 1. ydmulic 4500119433 Analysis Projects: 70082.1 Pcop>Gt.lti.MaW. Peter Deparineart PP!b!D t:orrtraetaefl=ierre Name: lioie tiiicxrrtes Sdtali.`frAilP Original Conbactltllfork :Order Amount: �W' ' Original BCC Approval Dates Agenda ftem tk Current BOO Approved_ Amount; mast BCC Approval Date; Agenda aeon #i Current ContractlWbirk der Amount Dollar O;�O'�6 change from Origirml Amowmt t;ontrar�JVlfoolcc:ttVifooic Revised Order Total Sa6.,700cO1 1/A Fs1El Charge frflm .Curmnt 13CO.Approved Amount : t trnitlsdtive Glaa 3Q:00 D.W% from Current Aniocrnl vnpiatloti�e,'ilaipti+ott. i� Tasit(sj Ctzattpa, ■red :fatloneie fafiife9e Original notice to proceed Last.approved completion date:. Revised completion date (mdudes this completianidaW.12W010 $2fflft 4$ 12 3 2 el 10 change): 8 IM11 Number of tars added (if n why add"dionak: are needed detailed+! c wdension, must attacitrurnu t This change order is to add: tine. It wRt add A7 days to the original hwi ance.cer2fficate(s) frttrn. SAP completion date. As a result. of time hydraulic analysis phase and subsequent . or obtain from vendor?:W2�- 1 i 0 desip rV&W meetings, Hoje Montes identified "bottlenecks" within the plant Fig and valve: "stem that required finther investigatumn via ground penetrating: radar and "soft dig" locates. TMs was ,not originally anticipated nor could- it.ha:v6 been imovin prior to performin8 the hydraulic analysis. Li Add new °#ask(s) `'Chengetesk(s) pelete1ask(s) Wither (specdfy): TWm Extension 1'. Provide a detained # specific expianatiort of the requested change(s) to the task( *) - This change order into add time Ftwilt add days to the original completion date. As a result of frAmuiic analysis phase and Hole Montes Identified "'bottlenecks' witW the plant piping and .valve::system subsequent design review;mestirigs. tW regairad-ftuther.'investipallon via ground penetrating radar and 'soft clip' locates. This was root originally anticipated nor could 8 have been known prior to performing the hydraulic analysis. 2. Provide detained rationale forthe.requested` change;. As a result of the hydraulic analysis phase and subsequent design review meetings, HOW Montes :jeierrtfied'botilenecks' within the plant piping and valve system that required further investigation via•ground penetrating radar and 'soft dW locates. 3. Provide explination vft change was not anticipated lot odginatscope cf work: It manifested itself during design. review imeetinps and as a final: Msutt Of the hydraulic analysts. 4. [describe the itt pact. if this change.1s; not processed The bottleneck that currently exists in the piping and values of he 0iint would not be corrected and thus the plaht could not be operated at its designed lit . Name and Tale: paterzcnar i-mp Senior Project manager Reviewed by. Dads: Purchasing Pr lessionars Name: Rwia.x'.2t271!t7 Packet Page -2789- 2 t 3 c:Lca y `"bOVIL- neck 'it#rm the piarrt paPznt� aid vale syst m aad ttr ft u�tk�er iav 4Qa on via: ro�md Pent~ u radar snd lomft r> tr►eds i"aalecl to fazici aiid 1tleratiftr tie faulty waives and pang that`are h nclerri the h dr�ulics at tj►e_ p mj- it was tl fore' reewunende ci the ez� er t[iat..an tnlde -roan coutrac or be b red m order t physic C dig:. doves ii�xo the ground m.thret.s�3spected_ loc= k ns tzl.iind.t#te.non %ctiotiing, r ''es,. to evaluate tbeir, disrepair; and to f them so- that they cease'tt . bl . the proper hydraulic: func -don of tine � , ormi* : contact basis sti fiat the plattt tit cynce m operate meiiatsly atx ': -teinalzly at toll capacity. l IitcheU Stark was.comveuuvelk pr rest te..dn this work end tiaev %,j carilp3ete August 21, ?fl:.I I:. This etetsinn ;fn'tbe. adcliiicartal. 2 T3 days is aecessarzf because as a . � pi�ed resW, f o f the underground contractor's e ender has � sh {lS� pe CPSS adequoic.t1me -to: evaltWe tie w mlh condiI �7 and/or re(3lacerneiM, and to produce sagned and sealed plans and specifications W perfitrr the repi eplaeeruerti work This'is an cxnfAescen conditi icli W not ougum y_ anbmpate . aor rs there eLi ? Way... it could 18z�e he�ri loiCi�tx or to zn the- 'ftwdraaaJ c analysis and. resultant im*,irgro und pn perfoan g ': ea�xax�atsoia. Add new task(sj a ange tasks Delete task( ) . Tmae .Extension a re'mltof the.-b ic ana vsrs p ucpL Fiol� Mon rMed th. nit � Packet Page -2791- Ar�rsatra5ve Selvioes DiMision Purcheeinp ❑ Contract Change Request 9/13/2011 Item 16.E.16. Purchasing Department Change Modification Form ® Work Order Modification Contract #: 07- Mod #: 3 PO/Work Ord pr #: ; Project Name: On call Project Mngt. For 4135 4690004498 �/.�OV 1,6f1'19 GMD IT Project M N/A Project Manager: Natali Department GMD C &M - Contractor /Firm Name: Executive Betancur Administration Alliance Group Original Contract/Work Order Amount $54,000:Efprw' .,•: Original BCC Approval Date; Agenda Item # Current BCC Approved Amount *N/A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount 137,325.w. Explain why additional days are needed (detailed /specific): This additional time is Dollar Amount of this Change $52 500.W.-t insurance certificate(s) from SAP 251.53% Total Change from Original Amount Revised Contract/Work Order Total $189,825.00 I El Change task(s) #N /A Change from Current BCC Approved Amount Cumulative Changes $135,825.00 division's core functions. Projects such as the migration of files from shared drives to SIRE GMD cabinets, Cartegraph 38.23% Change from Current Amount Completion Date, Description of the Tasl�(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 03/26/2010 04/01/2011 change): 02/14/2012 Number of days added (if Explain why additional days are needed (detailed /specific): This additional time is extension, must attach current needed to achieve current initiatives required for the division's core functions. insurance certificate(s) from SAP or obtain from vendor : 319 days Add new task(s) I El Change task(s) Delete task(s) ❑ Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): 2. Provide detailed rationale for the requested change: This modification is needed to support projects required for the division's core functions. Projects such as the migration of files from shared drives to SIRE GMD cabinets, Cartegraph upgrade (8.3 version), ESRI (GIS) 10.0 upgrade and association to Cartegraph 8.3, implementation of Cartegraph field equipment solutions and other IT related tasks including maintenance of current application and implementation of future applications. 3. Provide explanation why change was not anticipated in original scope of work: The original scope was restricted in time due to funding limitations. As funding becomes available and projects become critical for core functions; the work order is extended to provide support to the division. 4. Describe the impact if this change is not processed: If this change is not processed, projects will not be successfully completed causing a major impact in the division's core functions including Traffic and Road Maintenance daily operations. Type of Chan g / Modification 1. Planned / Elective ❑ 2. Unforeseen conditions /circumstance 3. Quantity or price adjustment ❑ 4. Correction of errors 5. Value added 6. Schedule adjustment Change Requested By Contractor /Consultant Owner Using Department =Design Professional Regulatory Agency s eci ): Others eci : Purchasing Professio al Participated in Negotiation of Change / Modification: Yes No Approved by: v Date: Name and Title: cs� Coputocicr Reviewed by: -� Date: Purchasing Professional's Revised: 4/6111 1 Packet Page -2792- CuterCouxty Adrniristl*s Serubes DivWm Pt+n0 ❑ Contract Change Request 9/13/2011 Item 16.E.16. - n -7 K� c a�- Purchasing Department Change Modification Form ® Work Order Modification Contract #. Mod #: 1 PO/Work Order M Project Name: Interim Renourishment- 09- 5262 -CZ 5/18/11 45- 119725 Marco South Beaches Project #: 80123 Project Manager. Department: Contractor/Firm Name: Gary McAI in Coastal Zane Management CEC - &15,. Original Contract/Work Order Amount Current BCC Approved Amount (Current Contract/work Order Amount Dollar Amount of this Change (Revised New Contract/Work Order Total Last BCC Approval Date; Agenda Item # ?SQ't1, 1 0.00%1 Total Change from Original Amount 000.00 0.00% Change from Current BCC Approved Amount $0.00 0.00% Change from Current Amount Completion Date, Description of the.Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 51(-6 it 5/18/11 1 change): November 18, 2011 Number of days added (if Explain why additional days are needed (detailed /specific): Additional time is needed extension, must attach current to allow for completion of the modeling and alternatives analysis. insurance certificate(s) from SAP or obtain from vendor): 184 days El Add new task(s) Change task(s) TT7 Delete task(s) 72r� her (specify): Provide a detailed and specific explanation of the requested change(s) to the task(s): The final completion date was for may 18, 2011 and additional time is requested for completion of the modeling alternatives analysis. Provide detailed rationale for the requested change: A key task within the model study was to deploy wave, tide and current gauges to measure these parameters to serve as input to the model program for calibration and validation of the model predictions. During field deployment of the gauges, one of the gauges was stolen. This resulted in having to obtain and reinstall a new gauge and repeat the field work. This resulted in several months of unanticipated delay. Provide explanation why change was not anticipated in original scope of work: Theft of equipment was not contemplated in development of the original schedule. Describe the impact if this change is not processed: The goal of the work effort and model study is to evaluate alternatives for enhancing the performance and perhaps reduce long term costs of the South Marco Beach Renourishment Project scheduled for construction in 2012 -2013. Without the requested additional time, the model study can not be completed. This will preclude selection and implementation of a recommended alternative to enhance Project performance. Type of Change, / Modification . . 1. Planned / Elective 2. Unforeseen conditions /circumstance 3. Quantity or price adjustment El 4. Correction of errors ❑ 5. Value added I LJ 6. Schedule adjustment Change Requested By Contractor /Consultant Owner I L Using Department LJ Design Professional I LJ Regulatory Agency (specify): Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: LJ Yes LJ No Approved by: ; 1 / Date: ? C C Name and Title:; )Gary M Alpin, CZM Director Reviewed by: Date: Purchasing Professional' e: Lyn Wood, Contract Specialist Revised: 4/6/11 1 Packet Page -2793- co Fier county Adr1iros6rahe Services Division /"N, Purchasing Contract Change Request 9/13/2011 Item 16.E.16. ' Purchasing Department Change Modification Form (Work Order Modification Contract M Mod #: PO/Work Order Project Name: Pine Ridge at Naples 09- 5262 July 21, 2011 #4500126858 Blvd Traffic Signal Upgrade to Mast Arm Project #: N/A Project Manager: Department: Contractor /Firm Name: proposed steel mast arm location and adjustments to design requested by County. John W. Miller Traffic Operations Tindale Oliver & Associates Original Contract/Work Order Amount $ 28,000.00 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $&�A 28- ,QW-e0 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 28,000.00 Dollar Amount of this Change $0.00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $28,000.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change fro m Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed J;ktj q, Last approved completion date: Revised completion date (includes this completion date: A�i�1 u(( July 21, 2011 change): September 5, 2011 Number of days added: .W 44 Explain why additional days are needed (detailed /specific): (if extension, must attach current Additional Days are needed due to extensive underground utilities in proximity of insurance certificate(s) from SAP proposed steel mast arm location and adjustments to design requested by County. or obtain from vendor): Add new task(s) El Change task(s) El Delete task(s) Z Other (specify): Add Days to Contract Time. 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): No Change to Task. Time Extension Only. Type of Change / Modification ❑ 1. Planned /Elective ® 2. Unforeseen conditions /circumstance I ❑ 3. Quantity or price adjustment ❑ 4. Correction of errors ❑ 5. Value added I ® 6. Schedule adjustment Change Requested By ® Contractor /Consultant Owner Z Usin De artment El Design Professional I ❑ Regulatory Agency s eci : ❑ Other(specify): Purchasing Professional Participated in Negotiation of Change / Modification: El Yes 0 No Approved Date: 7 _ 13- :1-ell Name Title- Nv Reviewed by: Date: r Purchasing Professional's Name: 0 r, dl Revised: 4/6/11 1 Packet Page -2794- 9/13/2011 Item 16.E.16. t� ,tIer commy Purchasing Department Adlrir Selvioes DaRSiorl Change Modification Form Pumhasing ❑ Contract Change Request Work Order Modification Original Contract/Work Order Amount Contract #: Mod #: 1 POIWork Order M Project Name: IJ/�l , - Last BCC Approval Date; Agenda Item # 08 -5124 $. 183,367:501 45- 128299 Annual Monitonn Dollar Amount of this Change $0 -0D 0.00% Project M 90536.1 Project Manager. Department: Contractor /Firm Name: Change from Current BCC Approved - Amount Cumulative Changes $0.00 0.00% Gary McAi in Coastal Zone Management Humiston & Moore Engineers 5. Value added Original Contract/Work Order Amount $ 11831367 W n4 - �D� r Original BCC Approval Date; Agenda Item # Current BCC Approved Amount IJ/�l , - Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $. 183,367:501 or obtain from vendor): 359 days Add new task(s) F1 Change task(s) Delete task(s) ®Other (specify): WO completion date extended. Dollar Amount of this Change $0 -0D 0.00% Total Change from Original Amount Revised ContractlWork Order Total $183,367.50 #DIWDI Change from Current BCC Approved - Amount Cumulative Changes $0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale. for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 7f Y l U/-7 I-7 11/7/11 change): 10/31/12 Number of days added (if Explain why additional days are needed (detailed /specific): Extend the completion date extension, must attach current to October 31, 2012. insurance certificate(s) from SAP or obtain from vendor): 359 days Add new task(s) F1 Change task(s) Delete task(s) ®Other (specify): WO completion date extended. 1. Provide a detailed and speck explanation of the requested change(s) to the task(s): Extend the completion date to October 31, 2012. 2. Provide detailed rationale for the requested change: The monitoring requirements of the DEP permits dictate the timing of the monitoring surveys. The monitoring surveys for Doctors and Wiggins Pass must be conducted in the spring, and the South Marco survey was scheduled for the summer of 2012. The monitoring report is due within 90 days of the survey completion. 3. Provide explanation why change was not anticipated in original scope of work: Orriginally FDEP indicated that they would be willing to change the timing of the monitoring to accommodate our schedule. After further consideration, the schedule will continue to be on the anniversary date of the renourishment. 4. Describe the impact if this change is not processed: DEP will not change the timing of the monitoring schedule for the Doctors or Wiggins Pass project, and consequently if the completion date is not extended we will be in violation of the permit compliance conditions. Type of Change / Modification 1. Planned / Elective 2. Unforeseen conditions /circumstance 1 1 Quantity or rice adjustment S. Schedule adU ent 4. Correction of error(s)_ 5. Value added Change Requested By Contract or /Consultant Owner Usina Department Design Professional Regulatory Agency s eci : Oth r soeci : Purchasing Professional Participated in Ne otiation of Change / Modification: Yes No Approved by: c Date: Name and Title. Gary MdAlpifi, CZM Director Reviewed by: Date: Purchasing Professional's Name: Lyn 1 Revised: 41011 1 Packet Page -2795- /-11. 0 F O S d CO W 9/13/2011 Item 16.E.16. Packet Page -2796- O W 3 O A v0-0< s W V C 9 3 W O. y 1C a O L O 0 CL D ('D W Z 0 09 O p x O w z O � Z O a Cn v o .W. n y CD 2 W 7 a M C C7 G a D° 0 x o O U Cn C a y 0 » � 0 0 O �+ D O 3 ° n ° o c CD n » a m 0 A D O 0 x � O O N r a» » ID D Oo S � (U O O (O C a W »moo � O � ;r < 7 o OID Boa 0 0 3 n COs W 0 0.� o a =• !D 3 � d O O 3 �. 0 c 9 W W D { ° y0 A OO W 0O N o0 -' C C<D Er W CD N W W 2 a 0 CL f f w A S M A Op.. N 7- N O N < W O to p -{ (O O to W Cr CD O u v>v�z� CD O o D 7 5. --1 ° (n�KCo O 0 0 0 3- --1 -. O �O c0 O O z x � S° Zg-4 O° O a� W O z�Vx 0 o 7 W a 21 a W 0 �a � _�. °- N N W d C 3 n °' D n W �. C < a� W � (ll � G�� Cd W W # N N.9 00 ;N W ... < D a N iTI T NN K -� O -, a it -n #N� � O 'O O O W O < W° ' O N W W '� Iu W C) 7 M O O O 'O < V N. O W D 7 \ Z ° x O N y S N p N N tit W S ° S O N r W 'O � O O (D O - d fD S -O C y N W W W p <x 0. y y W Z p D d a N 0 W N A G 0 W 0 M. N C. ° a CD C n (D N N N CD 7 (a N N �O 3 °. j 7 S =i M v n W 7 (7 ^ .W.. O`Z N C aN Gi o N y N N a N --I W O A 0. O 'T- 7 0 W N 0 CL W W S CA f0 C) N O 'CD A a (O O N O CL C C W< Cn O d '� CO CAn O O 0 W -b. �O Cn O O N N O� .WN.. N ? y O N p y. O W CTt O m N O S °. W pC pNj N Co W Cn CD V N C? 00 S CD A W S N CD N S CL W _n 7 C CO O O Cn O C S CWn F - W x n W O 3 C O W O W O a O c=i is a ° ° � y o N N O CD N a W :0 1 C7N o o r n p c a n� < Z -0 C m e CD W Z_0 V �p C n 30 CACN < N CD (° C W N 7° d 'N D I N 0 = S (p W ? j W N N 2 C W a D N W y W CD N C _ 0 C) 00 a 64 S n ^ C W N 64 N CD 0 69 a 6 6s Cb = o ° 0 �. A a CAO C 7 (AD ° LU O A F O V y a V CD CD O Q CD W O O O O 7 N O O O O O ° N N O p0 .�. U N �p O CL W O N 7 < N O N N N fA N N n < 3 .p 3 7 m O o N . 7 W � Z y o o 0 Q° ? W �. Z M a Z D ti ° o an d D W o CD _ CL p ° � o ° m °- o cn 6' W n 3 ° O c N u� p N W W to cn N o<i a <n OD O N t0 p W O T W N V O O O O N N O ° to 7 N N d O p N N CD 'OO C) a a oo W o °0 0 0 o 3 0 N O W Vi O'a 00 Cn N Cn O W < N N V3 0 O W O O O O W ° CD C). CL °O o c 0 ° m CD C 0 o N a n a N CD O ~ m o 64 W Co S N O N a O (O D O A w 7 < 69 A (O ° m ° a N CD O o o °o o ° N CL p ? W � CD N � o. ° 0 p < O ° O a 0 ' a N N a N O d Co O C O ° m N C O o W W W (n w o N CD m a w n O 0. o 'p CD W 0 O o O N r N N 7 a a C> 2: oo a ° o e N N ° 00 0 m = a 0 0 o Packet Page -2796- O W 3 O A v0-0< s W V C 9 3 W O. y 1C a O L O 0 CL D ('D W Z 0 09 O p x O w z O � Z O a Cn v o .W. n y CD 2 W 7 a M C C7 G a D° 0 x o O U Cn C a y 0 » � 0 0 O �+ D O 3 ° n ° o c CD n » a m 0 A D O 0 x � O O N r a» » ID D Oo S � (U O O (O C a W »moo � O � ;r < 7 o OID Boa 0 0 3 n COs W 0 0.� o a =• !D 3 � d O O 3 �. 0 c 9 W W D { 9/13/2011 I m 16.E.16. 2 \ ) § \ \ Packet Page -2797- 3 ° � 71 ■ \( `} § ) \ZE \i « \ § ° \ | 2 } § 7 )% ju m Cn )\ k 0 `} § ) \ZE \i « \ § \ | \ ( } § 7 2E m Cn )\ k n$ pr [\ OD 0 of - = )ƒ 7 \/ CD [g ��o 2 / 0 t� k§K (n 2 E} }o E §2 j M CD g _ ; �3 r >= \ \ \�_ \ / \ CD \ CL $ -» n o CD ( i 0 o § §\ 3 [ \ j\ 41 n 0. 2 - \\ _ |} ■o CD _ o 0} �- \) ° nom i(g CD CL q� {� a/( 2o& }\ � � CD CD (.\ CD CD 0 0' ^ ° �3�= C §\ ®� CD 0 70 (� \ \ } \&�