Loading...
Agenda 05/24/2011 Item #16E 95/24/2011 Item 16.E.9. EXECUTIVE SUMMARY Recommendation to approve and ratify staff's Zero - Dollar Time Extension of Contract #09 -5195 with Boran Craig Barber Engel Construction Co. (BCBE) in order to process the Contractor's Final Invoice for work completed on the Marco Island Library Rose Hall Addition; and authorize the County Manager or his designee to sign the necessary documents. OBJECTIVE: To obtain Board approval for a Zero - Dollar Time Extension to expired Contract #09 -5195 - Marco Island Library Rose Hall Addition, in order to process the final Invoice for a late evolving, owner requested, change order issued 9/29/2010, but only completed on 4/6/2011, in the previously committed amount of $2,254.84. Also, to authorize the County Manager or his designee to sign the necessary documents. CONSIDERATIONS: Contract #09 -5195 with Boran Craig Barber Engel Construction Co. (BCBE) is for the construction of the Rose Hall Addition to the Marco Island Library. The Contractor achieved substantial completion of the Rose Hall Addition (as scheduled) on 6/21/2010. On 9/24/2010, after the Hall had been in use for about three (3) months, the Library staff requested that the project change a floor- mounted audio /video /power box, located on the stage of the auditorium, from the type and model originally specified, supplied and installed; to a different model that presented less of a tripping point, and was reportedly easier to use. Change Order #5 in the amount of $2,254.84 was issued to the Contractor on 9/29/2010, but the Contract completion date of 11/10/2010 was not extended since it was believed that the item could be completed before that date. Unfortunately, there was a delay in the material delivery and in addition due to the heavy schedule of events for the auditorium, the Library staff requested that the installation be postponed until after high, seasonal utilization of the facility subsided. In late March the Library staff requested that the Contractor complete the installation, and BCBE completed the work on April 6, 2011. The Contractor's final invoice was submitted on 4/7/2011, but was rejected by the Finance Department due to the contract having expired. In order to process the Contractor's final invoice for this project covering the last Change Order for the work performed, it is necessary to process a Zero Dollar Time Extension to the Contract. This change order essentially ratifies an arrangement under which the vendor has actually performed under the Contract, following the expiration of the Contract on 11/11/2010. The services were performed at County Staff's request, and in accordance with the project requirements. The Contractor has successfully completed the work authorized by Change Order #5 issued before the Contract expired, and staff recommends approval. FISCAL IMPACT: There is no fiscal impact associated with this item. All work and costs were covered by previously authorized Change Orders. GROWTH MANAGEMENT IMPACT: this Executive Summary. There is no growth management impact associated with LEGAL CONSIDERATIONS: It is within the Board's authority to ratify staff's extension of an expired contract to include vendor services provided from which the County has received Packet Page -1765- 5/24/2011 Item 16.E.9. benefit. This item has been reviewed by the County Attorney's Office, requires a majority vote, and is legally sufficient for Board action. - CMG RECOMMENDATION: That the Board approves and ratifies the Zero Dollar Time Extension for contract #09 -5195 and authorizes the County Manager or his designee to execute the related documents. Prepared by: Hank Jones, Principal Project Manager, Facilities Management Packet Page -1766- COLLIER COUNTY Board of County Commissioners Item Number: 16.E.9. 5/24/2011 Item 16.E.9. Item Summary: Recommendation to approve and ratify staff's Zero - Dollar Time Extension of Contract #09 -5195 with Boran Craig Barber Engel Construction Co. (BCBE) in order to process the Contractor's Final Invoice for work completed on the Marco Island Library Rose Hall Addition; and authorize the County Manager or his designee to sign the necessary documents. Meeting Date: 5/24/2011 Prepared By Name: JonesHank Title: Project Manager, Principal,Facilities Management 5/6/2011 5:40:00 PM Submitted by Title: Project Manager, Principal,Facilities Management Name: JonesHank 5/6/2011 5:40:02 PM Approved By Name: CampSkip Title: Director - Facilities Management,Facilities Manage Date: 5/9/2011 9:10:29 AM Name: SmithKristen Title: Administrative Secretary,Risk Management Date: 5/9/2011 10:47:49 AM Name: WoodLyn Title: Contracts Specialist,Purchasing & General Services Date: 5/10/2011 8:19:22 AM Name: CarnellSteve Title: Director - Purchasing /General Services,Purchasing Date: 5/10/2011 2:04:30 PM Packet Page -1767- Name: GreeneColleen Title: Assistant County Attorney,County Attorney Date: 5/10/20114:36:14 PM Name: PriceLen Title: Administrator - Administrative Services, Date: 5/10/2011 5:22:11 PM Name: KlatzkowJeff Title: County Attorney, Date: 5/12/20113:19:56 PM Name: StanleyTherese Title: Management/Budget Analyst, Senior,Office of Management & Budget Date: 5/13/20114:46:50 PM Name: OchsLeo Title: County Manager Date: 5/15/2011 9:36:36 PM Packet Page -1768- 5/24/2011 Item 16.E.9. From: CHANGE ORDER NO. 6 TO: Boren Craig Barber Engel Construction Co, In 3606 Enterprise Ave Naples, Florida 3410 DATE: May 4, 2011 PROJECT NAME: Marco Island LihM Rose Hall Addition PROJECT NO.: 54004 Under our AGREEMENT dated March 10, 2011. 05/06,2011 0-. 5/24/2011 Item 16.E.9. CONTRACT NO.09-5195 BCC Date; 3/24/09 Agenda Item: I &D- I I You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: Extend time 156 days. FOR THE (Additive) (Deductive) Sum of. —Zero write Out in words ($ 0.00 Original Agreement Amount $832,170.00 Sum of Previous Changes $63,499.94 This Change Order add or deduct $0.00 Present Agreement Amount $895,669.94 The time for completion shall be increased) by 156 calendar days due to this Change Order, Accordingly, the Contract Time is now _,April 15, 2011_ (619) calendar days. The substantial completion date is and the final completion date is April 15, 2011. Your acceptance of this Change Order shall Agreement W ciinsoiis as -- contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted: PW 4 _, 20 It CONTRACTOR, BCBE By: OWNER: BOARD OF COUNTY COMMISSIONERS OF COLLIER CdVNTY, FLORIDA By: flank jcnes, Project Manager DEP,A,RTME,N7 DJ` FCTOR By: Skip'Camp Packet Page -1769- From: 05/06/2011 0: 5/24/2011 Item 16.E.9. DIVISION ADMINISTRATOR By: Len Golden Price By: Packet Page -1770- CONTRACT SPECIALIST