Agenda 05/24/2011 Item #16D 75/24/2011 Item 16.D.7.
EXECUTIVE SUMMARY
Recommendation to approve and ratify Staffs extension of Contract No. 06 -3971
"General Contracting Services" with PBS Construction, Inc. and related Work
Order No. 45- 124175 "Goodland Boat Docks Installation of Ladders & Cleats" for
$14,620.00 in order to process the final invoice for work completed.
OBJECTIVE: To obtain Board approval for the extension of time for an expired work order
issued under a valid contract which subsequently expired.
CONSIDERATIONS: The General Contracting Services Contract #06 -3971 was initially
approved by the Board of County Commissioners on September 6, 2006, with an expiration date
of February 12, 2011. On November 17, 2010 staff executed a work order with PBS
Construction, Inc. under Contract #06 -3971 for construction related services to the Goodland
Boat Park Project with a completion date on December 17, 2010. The scope of work associated
with this work order included the installation of 22 galvanize ladders and 36 cleats to the newly
constructed boat docks at the Goodland Boat Park Marina. However, a change order request was
subsequently executed to add additional cleats, and labor to apply an anti - barnacle solution to 28
galvanize ladders. The anti - barnacle solution material was provided by the owner and was
placed on special order with the manufacturer. Unfortunately, there was an inadequate supply of
inventory available and the special order was substantially delayed causing a lapse in the
contractual duration and completion of work.
The work order essentially ratifies an arrangement under which the vendor had actually
performed services under contract #06 -3971, following the expiration of the underlying contract
on February 12, 2011. The complete scope of services was performed at the request of County
staff, the contractor has successfully completed all work related services to the County's benefit,
and Staff hereby recommends approval.
FISCAL IMPACT: There is no fiscal impact associated with this item.
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated
with this Executive Summary.
LEGAL CONSIDERATIONS: It is within the Board's authority to ratify Staff's extension of
an expired Contract for services provided from a vendor from which the County has received
benefit. This item has been reviewed by the County Attorney's Office, requires majority vote,
and is legally sufficient for Board action. — CMG
RECOMMENDATION: That the Board approve time extensions for Contract No. 06 -3971
and authorize the County Manager or his designee to execute Change Order No. 1 to Purchase
Order No. 45- 124175.
PREPARED BY: Clint Perryman, Project Manager, CZM Department
Packet Page -1508-
5/24/2011 Item 16.D.7.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.D.7.
Item Summary: Recommendation to approve and ratify Staff's extension of Contract No.
06 -3971 "General Contracting Services" with PBS Construction, Inc. and related Work Order No.
45- 124175 "Goodland Boat Docks Installation of Ladders & Cleats" for $14,620.00 in order to
process the final invoice for work completed.
Meeting Date: 5/24/2011
Prepared By
Name: PerrymanClinton
Title: Project Manager,Coastal Zone Management
4/29/2011 10:58:31 AM
Submitted by
Title: Project Manager,Coastal Zone Management
Name: PerrymanClinton
4/29/2011 10:58:33 AM
Approved By
Name: McAlpinGary
Title: Director - Coastal Management Programs,Coastal Zone Management
Date: 4/29/2011 1:51:20 PM
Name: AlonsoHailey
Title: Administrative Assistant,Domestic Animal Services
Date: 5/2/2011 2:16:28 PM
Name: WardKelsey
Title: Manager - Contracts Administration,Purchasing & Ge
Date: 5/10/2011 5:17:30 PM
Name: CarnellSteve
Title: Director - Purchasing/General Services,Purchasing
Date: 5/11/20114:56:27 PM
Packet Page -1509-
5/24/2011 Item 16.D.7.
Name: GreeneColleen
Title: Assistant County Attorney,County Attorney
Date: 5/11/20115:06:26 PM
Name: RamseyMarla
Title: Administrator, Public Services
Date: 5/12/20113:11:21 PM
Name: KlatzkowJeff
Title: County Attorney,
Date: 5/12/20113:54:48 PM
Name: IsacksonMark
Title: Director -Corp Financial and Mgmt Svs,CMO
Date: 5/17/20116:08:17 PM
Name: IsacksonMark
Title: Director -Corp Financial and Mgmt Svs,CMO
Date: 5/17/2011 6:12:07 PM
Packet Page -1510-
5/24/2011 Item 16.D.7
05/1112011 16:31 2396431080 P$5
C M-4—# 1
TO: FROM:
PBS (Professional Building Systems) Board of County Commissioners
4896 Corporate square Collier County coastal Zone Mgm "t
Naples. Fl. 34104 3299 Tamismi Trail Suite 103
Naples, Fl, 34112
Project Name: Goodland Boat Park Cleats B !,.adders proiect No. 811611.1
Contract Dated: September 12, 2006 Contract # 06 -3971
Change Order No; 1 (P.O. # 45- 124175)
Change Order Description:
This change order er is required and necessary to provide the appropriate
extension of contractual duration to complete the scope or work as outlined in the
original work order, and to add additional rrmeterial (24 cleats), and to provide the
necessary labor to spply an anti - barnacle solution material to 28 galvanize
ladders. The necessity of this change order is primarily due to the accumulated
tepee in time associated with the delinquent deliveries of specific materials and to
add materlats not previously covered under the Original srxOpe of work. This
change order will have a net increase of 180 calendar days to the original
contractual duration as indicated above.
Original Contract Amount ... . ...... ....................$ 9,20$.00
This Change Order #1 Amour► t . .......................5,415.D0
Contract Amount..... ...................
...... ...... .....................$14.620.00
Original Contract Calendar Days.......... ..... ............................... ..30 gays
Adjusted Calendar Days this Change Order......
Revised Contractual Calendar Days ..... ............................... .... 190 Days
210 Days
NTPDate.................... , .. , .... ...............
. .............. .......... November 17, 2010
Original Completion Date.,.............. .....December 17, 2010
Revised ComplsSon Dom ... ..
................................
.............. .............lone 15, 2017
Your acceptance of this Change Order shall constitute a modification tc our
Original Agreement and will be performed in accordance to ail orfglna, terms and
conditions stipulated in the Original Agreement of record to include this
acceptance and modification. The adjustment to this Agrerement shat! constitute
a full and final settlement of any and all claims arising out of. or related to the
changes set forth herein, including claims for impact and delay costs.
Prepared by; "'4',�".r� � 4.. -. Date: �./o l
Clint L. Perryman, GCG, Project Manager
Cosstaf,ZerqManagement Department
Accepted
systems
Date: !/ % 1
Approved by: Date:
- Gary MrAlorn, P.E., director
Coastal Zone Manggement Department
Packet Page -1511-
PAGE 01!01
i
Prime Contract Change Order
Goodiand Boat Docks Installation mf
Ladders and Cleats
To: Clint Perryman
Collier County Coastal Zone
Management Dept.
3301 EamtTenm}arni Trail Bldg F. Suite
103
Naples, FL34112
011 Item 16_D_7_
4305 Corpwate Sqmarm
Maples, FL 3410"*764
4239)643-6527 - (239)643-4293
Proeo #5D01102
Date: May 6, 2011
Change Order: 001
From: Stephen Jordan
PBS Construction, Inc.
4DS5 Corporate Square
Naples, FL341O4-4754
Description
Amt Req.
Days
1. Prime and paint twenty two (22) new ladders and six (6) existing ladders
utilizing a County specified contractor. Includes removing and reinstalling the
6 existing ladders and transporting the 22 new ladders tolfrom paint shop.
$5,115.00
2. Furnish and install additional dock cleats
$300.00
Total
$5,415.00
The original Contract Value: $9.205-00
Sum of changes bv prior Prime Contract Change Orders: 00.00
The Contract Value prior to this Prime Contract Change Order was: $9.305,00
The Contract Value will be changed by this Prime Contract Change Order in the amount of: $6.416.00
The new Contract Value including this Prime Contract Change Order will ba� $14.620.00
The Contract duration will be changed by: 180 Days
The revised Substantial Completion date of this Prime Contract Change Order is:
By:
Signature: Date: May 5, 2011
By: Clint Perryman
Printed on: May 5, 2011
Packet Page -1512-
Page 1 of 2
Goodland Boat Park
PBS Construction, Inc.
Change Order Request #
Ladder Finishing & Cleats
Self Performed Work
5/24/2011 Item 16.D.7.
Subtotal Self Performed I $ 900.00
Qverhead & Profit @ 10% $ 90.00
Total Self Performed $ 990.00
Packet Page -1513-
Unit
Rate
Total
General Conditions
Partial General Conditions
0
$ -
$ -
Assistant PM
0
$ 75.00
$ -
Project Manager
0
$ 100.00
$ -
Superintendent
12
$ 75.00
$ 900.00
Total General Conditions
1 $ 900.00
Subtotal Self Performed I $ 900.00
Qverhead & Profit @ 10% $ 90.00
Total Self Performed $ 990.00
Packet Page -1513-
Hours
Rate
Total
Labor
<E ui ment>
0$
-
$ -
0$
-
$ -
Total Material
I
$ -
Total Labor
I
$ -
Subtotal Self Performed I $ 900.00
Qverhead & Profit @ 10% $ 90.00
Total Self Performed $ 990.00
Packet Page -1513-
Quantity
Cost
Total
Material
<E ui ment>
0
$ -
$ -
Total Material
I
$ -
Subtotal Self Performed I $ 900.00
Qverhead & Profit @ 10% $ 90.00
Total Self Performed $ 990.00
Packet Page -1513-
Quantity
Cost
Total
Equipment
<E ui ment>
0
$ -
$ -
Total Equipment
$ -
Subtotal Self Performed I $ 900.00
Qverhead & Profit @ 10% $ 90.00
Total Self Performed $ 990.00
Packet Page -1513-
Page 2 of 2
Goodland Boat Park
PBS Construction, Inc.
Change Carder Request #
Ladder Finishing & Cleats
Subcontracted Work
5/24/2011 Item 16.D.7.
Packet Page -1514-
Quantity
Cost
Total
Subcontract
Prime and paint 22 Ladders
0
$ -
$ 1.050.00
Clean, prime, paint 6 existing ladders
0
$ -
$ 2,860.00
Added Cleats
0
$ -
$ 285.67
< Subcontractor>
0
$ -
$ -
<Subcontractor>
0
$ -
$ -
Subtotal Subcontractor
$ 4,195.67
Subcontractor Mark Up
$ 391.00
Subtotal
$ 4,586.67
PBS Overhead & Profit @ 5%
$ 229.33
Total Subcontractor
$ 4,425.00
Total Self Performed From Page 1
$ 990.00
TOTAL CHANGE GIRDER REQUEST
$ 5,415.00