Agenda 02/22/2011 Item #16D8 2/22/2011 Item 16.0.8. EXECUTIVE SUMMARY Recommendation to approve a change order to contract #10-5561 ARRA Green Lighting for Parks - Eagle Lakes to Electrical Contracting Services, Inc. for $303,000 to add two additional community park sites. OBJECTIVE: To allow a modification to existing Contract #10-5561 ARRA Green Lighting for Parks - Eagle Lakes to Electrical Contracting Services, Inc., to retrofit existing light fixtures at the East Naples Community Park and Vineyards Community Park sport fields. CONSIDERATION: The Parks and Recreation Department's green lighting system retrofit projects have received a portion of the grant award from the Energy Efficiency and Conservation Block Grant (EECBG) from the United States Department of Energy for American Recovery and Reinvestment Act of 2009. On April 13, 2010 (Item 16D8), the aboard approved ITB 10-5417 for ARRA Green Lighting for Parks in the amount of $485,809 to Electrical Contracting Services Inc. At the conclusion of the retrofit of lights for Immokalee Community Park and Gulf Coast Community Park, additional ARRA funding became available. The provision to add additional sites was not included in the original solicitation, and therefore, the Purchasing Department conducted a new solicitation. On September 14,2010 (Item 1602), the board approved 10-5561 and executed a contract with Electrical Contracting Services Inc for $276,096 for the retrofitting oflights at Eagle Lakes Community Park. The agreement allows for: "The County reserves the right, should additional funding be identified, to quote out future energy saving lighting projects that are of a similar nature to this project to the successful firm." (Page 4 of the solicitation document, and incorporated by reference in page 5, paragraph 17 of the contract and page 8, paragraph 28) On February 8, 2011, (Item # 16E4), the Board of County Commissioners accepted and approved the reallocation of EECBG funding to existing EECBG projects. Parks and Recreation was allocated additional funding of $286,676.12 to expand the project to East Naples Community Park and Vineyards Community Park sp0l1 fields. The scope of work for East Naples and Vineyards Community Parks include the same specifications as in solicitation and contract 10-5561 for Musco Lights and ARRA grant requirements that apply for Eagle Lakes Community Parks, as well as contract 10-5417 for Immokalee and Gulf Coast Community Center. Parks and Recreation received two quotes from Electrical Contracting Services Inc for: · Vineyards Community Park: $175,310 · East Naples Community Park: $127,690 Packet Page -946- 2/22/2011 Item 16.0.8. Parks and Recreation staff negotiated the quotes with the contractor and prepared a cost comparison per pole and per fixture for each park sites; the cost comparison is closely in line with 2 previous bids. Staff recommends the Board approve the change order in the amount of $303,000. FISCAL IMP ACT: The project cost for Immokalee Community Park, Gulf Coast Community Park and Eagle Lakes Community Park is $763,580.12. With the addition of East Naples Community Park for $127,690 and Vineyards Community Park for $175,310 the total project cost is $1,066,580.12. Funds are available in ARRA Grant Fund 725 in the Energy Efficiency and Conservation Grant number 33062.2. LEGAL CONSIDERATION: This item has been reviewed by the County Attorney's Office, requires simple majority vote, and is legally sufficient for Board action. - CMG GROWTH MANAGEMENT IMPACT: The value of the improved facility will be inventoried in the Growth Management Plan. RECOMMENDATION: Recommendation that the Board of County Commissioners approves the change order to Contract 10-5561 with Electrical Contracting Services, Inc for $303,000 to include East Naples Community Park and Vineyards Community Park sport fields. Prepared by: Vicky Ahmad, Project Manager, Parks and Recreation Department Packet Page -947- 2/22/2011 Item 16.0.8. COLLIER COUNTY Board of County Commissioners Item Number: 16.D.8. Item Summary: Recommendation to approve a change order to Contract #10-5561 ARRA Green lighting for Parks - Eagle Lakes to Electrical Contracting Services, Inc. for $303,000 to add two additional sites. Meeting Date: 2/22/2011 Prepared By Name: AhmadVicky Title: Project Manager,Parks & Recreation 2/3/2011 1 :54:49 PM Submitted by Title: Project Manager,Parks & Recreation Name: AhmadVicky 2/3/2011 1 :54:50 PM Approved By Name: WiIliamsBany Title: Director - Parks & Recreation,Parks & Recreation Date: 2/4/2011 8:34:48 AM Name: AlonsoHailey Title: Administrative Assistant,Domestic Animal Services Date: 2/4/2011 12:42:54 PM Name: RubertoTony Date: 2/7/2011 10:01 :26 AM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & General Services Date: 2/10/2011 2:33:52 PM Name: NelsonTona Packet Page -948- 2/22/2011 Item 16.D.8. Title: Administrative Assistant, Senior,Parks & Recreation Date: 2/10/2011 3:05:18 PM Name: Carnell Steve Title: Director - Purchasing/General Services,Purchasing Date: 2/10/20113:43:50 PM Name: CummingsRhonda Title: Contracts Specialist,Purchasing & General Services Date: 2/10/2011 3:53:37 PM Name: WiIliamsBan)' Title: Director - Parks & Recreation,Parks & Recreation Date: 2/10/2011 4:06:31 PM Name: FoordMarlene Title: Grant Development & Mgmt Coordinator, Grants Date: 2/10/2011 4: 14:03 PM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 2/10/2011 4:39:02 PM Name: KlatzkowJeff Title: County Attorney, Date: 2/11/2011 8:53:40 AM Name: UsherSusan Title: Management/Budget Analyst, Senior,Office of Manage Date: 2/14/2011 2:38:57 PM Name: IsacksonMark Title: Director-Corp Financial and Mgmt Svs,CMO Date: 2/14/2011 3:38:14 PM Packet Page -949- 2/22/2011 Item 16.0.8. Charles Floyd Electrical Contracting Services, Inc. 2375 West 7th Street Hialeah, FL 33016 CHANGE ORDER TO A CONTRACT Parks & Recreation 15000 Livingston Road Naples, FL 34109 Tel. (239)252-4000 Fax: (239)514-3646 ARRA Green Lighting for East Naples and Vineyards Community Parks Cont:ractNo.10-5561 Change Order No.2 Change Order Description: This change order is to add East Naples and Vineyards Community Parks to the contract and update the Davis Bacon Wage Determination schedule. Original agreen1ent BDlOunt .............................................................. 5276,096.00 Sum of Previous Changes............. n". . ... .. .. . ... ... ... .. .... . .. . .. ...$ 1,500.00 This Change Order No.2 Amount (add)...............:........................... $127,690.00 EastNaples $175.310.00 Vineyards Revised Agreement Amount ................. ............................. .... ........... $580,596.00 PO Number - 4500123229 February 4, 2011 Original contract time in calendar days ................ n .. . .. .. .... .... ....... .. 180 days . Adjusted number of calendar days due to previous change orders ............ 60 days This change order adjusted time is. ... .. .. . .,.. .. .. . .. . .. . .... ... .. ....... .... ... .... 240 days Revised. Contract Time ill working days.......................................- 110 days Original Notice to Proceed date ................................................. October 21,2010 Completion date based on original contract time........................ April 19, 2011 Revised completion date due to change orders........................... June 19, 2011 Your acceptance of 1his change order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as COJItained in said Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, to this Agreement sbaI1 constitute a full and final settlement of any and all claims arising out of, or re set fa . including claims for impact and delay ~by: Date: . ~/&/.~I Vicky ~ectManager ~ ~d ~ 'on Department. Accepted by: \ _ ~~ ~~ Date: J....- ~ - LC \ \ Charles Floyd E1~ Contracting Services, Inc. Approved by: I~$L-. Barry Wi1Iiams, Director Parks and Recreation Department Date: c?~.h~/~ Packet Page -950- . c1!r County Admnistrative Services Division Purchasing 2/22/2011 Item 16.0.8. Purchasing Department Change Modification Form . Contract Change Request o Work Order Modification Contract #: Mod#: 2 POlWork Order #: Project Name: 10-5561 4500123229 ARRA Green Lights for Parks Project #: Project Manager: Vicky Department: Parks & Rec. Contractor/Firm Name: 33062.2.3 Ahmad Electrical Contracting Services, Inc. Original ContractIWork Order Amount Current BCC Approved Amount Current ContractIWork Order Amount Dollar Amount of this Change Revised New ContractIWork Order Total Cumulative Chan es $ 276,096.00 $ 276,096.00 $ 277,596.00 $303,000.00 $ 580,596.00 $304,500.00 9-14-10, 16D2 Original BCC Approval Date; Agenda Item # Last BCC Approval Date; Agenda Item # 110.29%1 Change from Current BCC Approved Amount 109.15% Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed date: Last approved date: I Revised date (includes this change): 10/21/10 11/17/10 6/19/11 Number of days added (if Explain why additional days are needed (detailed/specific): extension, must attach current We need additional days to conduct light test, punch list and final close out. insurance certificate(s) from SAP or obtain from vendor): 60 CD DAdd new task(s) D Change task(s) o Delete task( s) Other (specify): Add East Naples & Vineyards light retrofit projects to existing contract. 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): It was anticipated during the last bid process that additional parks might be added to this contract; a provision for additional park site was added if additional ARRA grant funding is available in the future. On October 2010, Parks was notified on the available reallocation of ARRA grant funds. Parks and Recreation has submitted 9 park sites to DOE for light retrofits. Three park sites were approved, funded and completed under the ARRA grant funds. East Naples Community Park was the next highest ranked project on the list that was also submitted to DOE. Parks also recommended to retrofit the lights at Vineyards Community Park because of high enegy bills on the soccer fields. Both park projects does not require significant work, are shovel ready and both were approved by DOE. This change order also includes update to the DBA wage detemination schedule. 2. Provide detailed rationale for the requested change: Electrical Contracting Services, was the low bidder on the last two projects that went out for bidding of a similar nature to this project; they completed all the work on time, meet all ARRA grant requirements and Park staff is please with their work. 3. Provide explanation why change was not anticipated in original scope of work: As noted in item #1, this change order was anticipated earlier. Funding for another parks was limited at that time. 4. Describe the impact if this change is not processed: The park sport fields will continue to use old light fixtures with high energy consumption. 1. Planned / Elective 4. Correction of error s Type of Change / Modification 2. Unforeseen conditions/circumstance 5. Value added Packet Page -951- Change Requested By 2/22/2011 Item 16.0.8. Approved by (Name and Title): Vicky Ahmad, Project Manager Reviewed by (Purchasing Professional): Date: /- -1/ Date: Revised: 1/1212011 2 Packet Page -952- III .Vi ~ CO c:: <( .... III o U III -c .... CO >- Q) c:: :> -c c:: CO III Q) c. $: .-j CO Q) .-j Z 'S: 0 .... N .... Q) - III > <:t t1lo~ 2/22/2011 Item 16.0.8. 0 N 0 0 q .-t 0 0 .... Cl"l ,...j c:i c:i III 0 0 ,.... 1.0 00 U 00 ,.... N 1.0 ra Lt')' ,....' Lt')' ,....' 00 ,.... ,.... N .... <:t N .-j .-j 0 I- 0(/). 0(/). 0(/). 0(/). ... o "CI c:: Ql > "CI Ql .... u Ql Qj \I) tkO c:: :;:; u co ... .... c:: o u rc u OJ .i:: u tJ .~ ~ OJ UJ l/'l o .-j III ... Ql "CI "CI iii - o # >- Cl .J:l 1.0 "CI "CI .-j Ql .... 6' ~~.-j ii. a:I -;:0 C. .-j <( ~ "CI iii ,.... .-j <:t Lt') I o .-j .... U Ql .0 .... e. cu .Q,! Cll .:x: o Et .s~ I ..... ~ ~ '- 0 CllU 11._ 0"3 -<.9 g>-c ._ c:: :c Cll 0) .:x: :.:J ro c::l1. cu :>. ~:g <.9 ::l <( E e::: E e::: 0 <(u tkO c:: ..;:; u rc .... .... c:: o u tkO c:: ..;:; u rc ... .... c:: o u tkO c:: :;:; u rc ... ..... c:: o u rc rc rc UOJ UcuuOJ .~ u .~ u 'i: u tJ ':; tJ.s: tJ .:; ~"-~""OJ"- UJ~ UJ~i:i:i~ "- .2 0) c:: :c 0) :.:J c:: cu cu C5 <( e::: e::: <( Lt') Cl 1.0 .-j 6' .-j - <:t .-j - Cl"l .-j 1.0 Lt') Lt') I o .-j en cu .:x: Cll ....J .Q,! 0) Cll UJ en .:x: "- Cll 11. OJ > o ..0 rc OJ OJ l/'l OJ > o ..0 rc OJ OJ V'l .-j 1.0 Lt') Lt') 1 o .-j OJ III :::> .-j 1.0 Lt') Lt') I o .-j OJ III :::> "- OJ C. III OJ "- ::l ..... X <.;: N - .:x: ... rc c.. >- ;!:: c:: ::l E E o U III -c "- rc >- OJ c:: :> .:x: "- rc c.. >- ;!:: c:: ::l E E o U III ~ C. rc Z ..... OJ III rc 0 L.U C. Packet Page -953- ~ OJ C. '^ ..., .s:: ~ N >- C J!I 0 c .s .. E OJ ::I E -c 8 -c ~ .5 0- ~ 0 .0 .!!! '" cU ~ "0 UJ c. 0 0 0 0 '"" 0 0 '"" "CI N <ci <ci <Vi c 0 .... '"" .... .. <II co .... N '"" 6 :m '" ....- '" ....- ..CI ~ co .... .... N ~ '<:t N .... .... .. iii :!E ~ ;n. ;n. ;n. ;n. 0 0 0 0 '"" 0 0 '"" c::i <ci <ci ...; 6 Lrl M Lrl co co '" '" 0 ..CI m <is Lrl- M- .. -' co M N M ;n. ;n. ;n. ;n. Lrl .... .... M <II .. .,. ..,.; ~ N :; :; co .... ,..: 0 cO .... :t: )( 6 i:i: ..CI Cii .. Q. -' .. 0 0 0 0 0 0 0 0 <II N c::i c::i N 0 U Lrl '<:t .... '" ~ '" co M Lrl ....- 0 en .,.- 0 .,. .,. '" 2J '<:t N .... .. :!E ;n. ;n. ;n. ;n. .. 0 0 0 0 <II 0 0 Lrl 0 0 -.i c::i cO <ci u .,. M co Lrl l'! Lrl N .,. '" .a N- N- N- N- )( i:i: ... .. "'" ;n. ;n. ;n. ;n. on co 00 0 N Lrl 0 '"" M ~ ~ .... .... .a )( .. u: "'" ... iii .. .. Q. 0 .... 0 N 0 0 - 0 .... 0 0 0 ai ...; c::i c::i .. 2J 0 .... '"" 00 on 0 00 .... N '"" U 0 Lrl- ..... '" ..... iii ::I co .... .... N Cf .,. N .... .... 15 ;n. ;n. ;n. ;n. .... Q) :5 Cl '" " UJ -c '" e '" c::'. -'" <tI -'" m-'" m ~ ~ 0.. m 0.. '" 00.. .Q '" c.. tl c.. ?: -.?;- ~ .. C).- C) .c "e e e e e ::I E E :E ::I E "'" .g> E g> E E OJ -' 0 -' E 0 "0 eLl e 0 U C. ~~~ OJ U '^ ~ Q) '^ ~ OJ 0-<tI 0 -c c. 0. <tIo.. ~ '" '^ ~~u; ~ gj ~z OJ (l) ..., E 0: E '" 0:-'" e '^ <{E8 <{~ >~ x <.:: 2/22/2011 Item 16.D.8. ~ U ::I -c 0 ..., 5- u (l) ~ .0' .0; -'-.s:: 5- '^ ..., ~o .s:: u '" (l) B (l) ..., ."' ::I .E -c .0 (l) E ~ ::: '^ ::I (l) :c 0 5- .s:: (l) Oi x :: ~ ::I 0. '^ 0 0 ~ '^ '"" ::I (l) ;n. 0 ~ "" .s:: e 0 (l) .~ .0 .s '" .!!! .!!! .s:: - u 0 0 '^ Oi ~ 0 .0 ::I E ~ -c c ::I v; (l) e (l) > ."' ~ ..., u '^ .w (l) (l) B u .!!! 5- e ~ (l) ~ ~ '" c.. ~ :c ~ (l) .c -c "" :B to .9P S: Vi =e "" .8 '" ~ -c .;;; -c c ~ ;; > (l) ::I 5- .0 ~ ~ '" <{ '^ cr: '" ..., cr: (l) .s:: <{ u ~ e e ~ 0 '" ~ ~ '^ v; ::I '^ (l) Ci ~ :c 0 .... z ...; N <Vi Packet Page -954-