Loading...
Agenda 06/26/2018 Item #16A 906/26/2018 EXECUTIVE SUMMARY Recommendation to award Contract No. 18-7307, Livingston Road Sidewalk Improvements Project 60118, to Infinite Construction, Inc., in the amount of $222,490.57. OBJECTIVE: To construct a new sidewalk along the western right of way of Livingston Road from Progress Avenue to the Golden Gate Canal, by awarding Contract No. 18-7307, Livingston Road Sidewalk Project, to Infinite Construction, Inc. CONSIDERATIONS: The County posted ITB No. 18-7307 for the “Livingston Road Sidewalk Improvements” on March 23, 2018. Staff mailed out seven thousand eight hundred -seventy-one (7,871) notices, ninety-six (96) potential proposers viewed the bid packages and the County received six (6) bids by the April 27, 2018, closing date as shown in the below table. Staff recommends award to Infinite Construction, LLC, as the lowest, responsive and responsible bidder. FIRM NAME PRICE Infinite Construction, Inc. $222,490.57 O-A-K / Florida, Inc. dba Owen-Ames-Kimball Company $235,897.74 Pavement Maintenance, LLC $257,000.00 Bonness, Inc. $259,166.99 Coastal Concrete Products, LLC dba Coastal Site Development $268,513.00 Haskins, Inc. $312,692.43 Infinite Construction’s low bid is approximately 17% higher than the Engineer of Record’s (EOR) estimate but the EOR found the bid to be reasonable and, along with staff, recommends award to Infinite Construction, Inc. FISCAL IMPACT: A budget amendment is necessary to transfer $74,674.10 from the District 2 Sidewalk Project 69333 to the County wide Pathways Project 60118 within the Transportation Capital Fund 310. The sidewalk and all replacement features to be installed during execution of the project will be new. The estimated useful life of sidewalks is 30 years with minimal to no repair cost during that duration of time. GROWTH MANAGEMENT IMPACT: The project is in accordance with the goals and objectives of the Transportation Element of the Growth Management Plan. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and legality, and requires majority vote for Board approval-SRT RECOMMENDATION: To award Contract No.18-7307, Livingston Road Sidewalk Improvements Project, to Infinite Construction, Inc. in the amount of $222,490.57, and authorize the Chairman to sign the attached contract and authorize the necessary budget amendment. Prepared by: Andrew A. Miller, PE, Senior Project Manager, Transportation Engineering Division, Growth Management Department 16.A.9 Packet Pg. 661 06/26/2018 ATTACHMENT(S) 1. 18-7307_Bid_Tab (PDF) 2. 18-7307 Engineers Recommendation to Award Letter_CC Project 69081.18 (PDF) 3. 18-7307 NORA_Executed (PDF) 4. [Linked] 18-7307 Infinite_Contract_VendSign (PDF) 16.A.9 Packet Pg. 662 06/26/2018 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.9 Doc ID: 5749 Item Summary: Recommendation to award Contract No. 18-7307, Livingston Road Sidewalk Improvements Project 60118, to Infinite Construction, Inc., in the amount of $222,490.57. Meeting Date: 06/26/2018 Prepared by: Title: Project Manager, Senior – Transportation Engineering Name: Andrew Miller 05/22/2018 1:50 PM Submitted by: Title: Division Director - Transportation Eng – Transportation Engineering Name: Jay Ahmad 05/22/2018 1:50 PM Approved By: Review: Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 05/22/2018 2:13 PM Capital Project Planning, Impact Fees, and Program Management Laurie Beard Additional Reviewer Completed 05/23/2018 10:29 AM Transportation Engineering Jay Ahmad Additional Reviewer Completed 05/25/2018 9:20 AM Procurement Services Adam Northrup Additional Reviewer Completed 05/29/2018 10:21 AM Procurement Services Ted Coyman Additional Reviewer Completed 05/29/2018 6:37 PM Growth Management Department Gene Shue Additional Reviewer Completed 05/30/2018 10:19 AM Growth Management Department Diane Lynch Level 1 Reviewer Completed 05/30/2018 2:37 PM Procurement Services Barbara Lance Additional Reviewer Completed 05/31/2018 8:15 AM Procurement Services Sandra Herrera Additional Reviewer Completed 06/04/2018 9:01 AM Capital Project Planning, Impact Fees, and Program Management Rookmin Nauth Additional Reviewer Completed 06/04/2018 2:21 PM Growth Management Department Marlene Messam Additional Reviewer Completed 06/05/2018 1:21 PM Procurement Services Swainson Hall Additional Reviewer Completed 06/05/2018 2:16 PM Growth Management Department Andrew Miller Deputy Department Head Review Skipped 06/05/2018 12:38 PM Growth Management Department Thaddeus Cohen Department Head Review Completed 06/07/2018 8:44 AM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 06/11/2018 2:26 PM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 06/11/2018 2:57 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 06/13/2018 1:29 PM 16.A.9 Packet Pg. 663 06/26/2018 Office of Management and Budget Susan Usher Additional Reviewer Completed 06/13/2018 4:11 PM County Manager's Office Leo E. Ochs Level 4 County Manager Review Completed 06/14/2018 2:47 PM Board of County Commissioners MaryJo Brock Meeting Pending 06/26/2018 9:00 AM 16.A.9 Packet Pg. 664 Project Manager: Andrew Miller Attachment A-1 - Bid Schedule 18-7307 - Livingston Road Sidewalk Project Project # 69081.18 Notices Sent: 7,871 Bid Packages Downloaded: 96 Submittals: 6 Line #Pay Item #Section Description Unit Qty Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost 1 101 -1 1. Sidewalk Mobilization LS 1 41,865.00$ 41,865.00$ 41,495.03$ 41,495.03$ 14,522.40$ 14,522.40$ 14,587.83$ 14,587.83$ 26,500.00$ 26,500.00$ 30,000.00$ 30,000.00$ 2 102 -1 1. Sidewalk Maintenance of Traffic LS 1 8,942.00$ 8,942.00$ 8,874.09$ 8,874.09$ 45,000.00$ 45,000.00$ 21,095.22$ 21,095.22$ 12,500.00$ 12,500.00$ 25,750.00$ 25,750.00$ 3 104-10-3 1. Sidewalk Sediment Barrier LF 560 1.50$ 840.00$ 1.81$ 1,013.60$ 3.00$ 1,680.00$ 2.72$ 1,523.20$ 2.25$ 1,260.00$ 7.50$ 4,200.00$ 4 107-1 1. Sidewalk Litter Removal and Disposal LS 1 220.00$ 220.00$ 120.95$ 120.95$ 2,500.00$ 2,500.00$ 4,917.75$ 4,917.75$ 1,500.00$ 1,500.00$ 4,000.00$ 4,000.00$ 5 107-2 1. Sidewalk Mowing LS 1 110.00$ 110.00$ 241.90$ 241.90$ 4,000.00$ 4,000.00$ 3,340.93$ 3,340.93$ 2,500.00$ 2,500.00$ 3,000.00$ 3,000.00$ 6 110-1-1 1. Sidewalk Clearing and Grubbing LS 1 735.00$ 735.00$ 14,262.25$ 14,262.25$ 17,000.00$ 17,000.00$ 4,706.93$ 4,706.93$ 4,500.00$ 4,500.00$ 17,000.00$ 17,000.00$ 7 110-4 1. Sidewalk Removal of Exisiting Concrete SY 14 18.90$ 264.60$ 26.88$ 376.32$ 125.00$ 1,750.00$ 116.78$ 1,634.92$ 45.00$ 630.00$ 75.00$ 1,050.00$ 8 120-1 1. Sidewalk Regular Excavation CY 235 15.00$ 3,525.00$ 40.66$ 9,555.10$ 32.00$ 7,520.00$ 17.84$ 4,192.40$ 40.00$ 9,400.00$ 23.00$ 5,405.00$ 9 425-1-455 1. Sidewalk Inlet Top - Type 5 (S-2 and S-5)EA 2 1,784.00$ 3,568.00$ 3,447.13$ 6,894.26$ 6,500.00$ 13,000.00$ 2,885.32$ 5,770.64$ 3,500.00$ 7,000.00$ 9,500.00$ 19,000.00$ 10 425-1-465 1. Sidewalk Inlet Top - Type 6 (S-1, S-4 and S-6)EA 3 2,058.00$ 6,174.00$ 4,172.84$ 12,518.52$ 6,500.00$ 19,500.00$ 2,395.73$ 7,187.19$ 3,500.00$ 10,500.00$ 10,000.00$ 30,000.00$ 11 515-2-311 1. Sidewalk Pipe Handrail, - Guiderail, Aluminum (42" high, type 1)LF 28 125.00$ 3,500.00$ 99.18$ 2,777.04$ 120.00$ 3,360.00$ 167.05$ 4,677.40$ 120.00$ 3,360.00$ 265.00$ 7,420.00$ 12 520-1-10 1. Sidewalk Concrete Curb and Gutter, Type F LF 42 20.60$ 865.20$ 29.12$ 1,223.04$ 46.50$ 1,953.00$ 36.77$ 1,544.34$ 28.00$ 1,176.00$ 58.00$ 2,436.00$ 13 522-2 1. Sidewalk Concrete Sidewalk, 6" Thick (3,000 psi)SY 980 30.00$ 29,400.00$ 55.34$ 54,233.20$ 44.75$ 43,855.00$ 73.73$ 72,255.40$ 65.00$ 63,700.00$ 65.00$ 63,700.00$ 14 527-2 1. Sidewalk Detectable Warning Truncated Domes SF 20 25.00$ 500.00$ 30.24$ 604.80$ 25.00$ 500.00$ 66.58$ 1,331.60$ 45.00$ 900.00$ 48.00$ 960.00$ 15 570-1-2 1. Sidewalk Performance Turf, Sod SY 498 2.70$ 1,344.60$ 8.13$ 4,048.74$ 4.00$ 1,992.00$ 17.23$ 8,580.54$ 12.00$ 5,976.00$ 5.00$ 2,490.00$ 16 102 -1 2. Signal Maintenance of Traffic LS 1 2,700.00$ 2,700.00$ 3,265.70$ 3,265.70$ 3,105.00$ 3,105.00$ 2,672.75$ 2,672.75$ 6,500.00$ 6,500.00$ 2,500.00$ 2,500.00$ 17 630-2-11 2. Signal Conduit (Furnnish & Install) (Open Trench)LF 70 13.60$ 952.00$ 16.45$ 1,151.50$ 15.65$ 1,095.50$ 20.05$ 1,403.50$ 75.00$ 5,250.00$ 16.50$ 1,155.00$ 18 632-7-1 2. Signal Single Cable - Reconstructed Inersection Furninsh & Install)PI 1 5,660.00$ 5,660.00$ 6,845.87$ 6,845.87$ 6,510.00$ 6,510.00$ 4,677.31$ 4,677.31$ 9,500.00$ 9,500.00$ 3,850.00$ 3,850.00$ 19 635-2-11 2. Signal Pull & Splice Boxes (Furnish & Install)EA 4 640.00$ 2,560.00$ 774.09$ 3,096.36$ 737.15$ 2,948.60$ 534.55$ 2,138.20$ 850.00$ 3,400.00$ 440.00$ 1,760.00$ 20 646-1-12 2. Signal Aluminum Signal Pole(Furnish & Install) Ped Detector Post EA 2 1,580.00$ 3,160.00$ 1,911.04$ 3,822.08$ 1,820.00$ 3,640.00$ 1,202.74$ 2,405.48$ 3,500.00$ 7,000.00$ 990.00$ 1,980.00$ 21 650-2-102 2. Signal Vehicular Signal Auxilliaries, Retrofit Backplate -Black w/Reflective Border EA 8 370.00$ 2,960.00$ 447.52$ 3,580.16$ 425.50$ 3,404.00$ 567.96$ 4,543.68$ 450.00$ 3,600.00$ 467.50$ 3,740.00$ 22 653-1-11 2. Signal Pedestrian Signal (Furnish & Install) LED Countdown 1 Way AS 2 940.00$ 1,880.00$ 1,136.95$ 2,273.90$ 1,081.00$ 2,162.00$ 1,069.10$ 2,138.20$ 750.00$ 1,500.00$ 880.00$ 1,760.00$ 23 665-1-11 2. Signal Pedestrian Detector (furnish & Install) Standard EA 2 250.00$ 500.00$ 302.38$ 604.76$ 287.50$ 575.00$ 400.91$ 801.82$ 500.00$ 1,000.00$ 330.00$ 660.00$ 24 670-5-400 2. Signal Traffic Controller Modify AS 1 3,400.00$ 3,400.00$ 4,112.36$ 4,112.36$ 3,910.00$ 3,910.00$ 2,672.75$ 2,672.75$ 3,500.00$ 3,500.00$ 2,200.00$ 2,200.00$ 25 700-1-11 3. Sidewalk Single Post Sign(Furnish & Install) Ground Mounted up to 12 SF AS 1 183.65$ 183.65$ 362.86$ 362.86$ 1,000.00$ 1,000.00$ 374.22$ 374.22$ 550.00$ 550.00$ 550.00$ 550.00$ 26 700-1-60 3. Sidewalk Single Post Sign, Remove EA 1 115.50$ 115.50$ 12.10$ 12.10$ 1,000.00$ 1,000.00$ 98.45$ 98.45$ 350.00$ 350.00$ 330.00$ 330.00$ 27 711-11-123 3. Sidewalk Thermoplastic, Standard, White, Solid, 12"LF 188 9.42$ 1,770.96$ 4.84$ 909.92$ 4.60$ 864.80$ 5.35$ 1,005.80$ 12.00$ 2,256.00$ 4.40$ 827.20$ 28 711-11-125 3. Sidewalk Thermoplastic, Standard, White, Solid, 24"LF 16 18.83$ 301.28$ 9.68$ 154.88$ 9.20$ 147.20$ 10.69$ 171.04$ 25.00$ 400.00$ 8.80$ 140.80$ 29 999-999 3. Sidewalk Signed and Sealed AS-BUILT Record Drawings LS 1 2,500.00$ 2,500.00$ 2,177.13$ 2,177.13$ 4,600.00$ 4,600.00$ 2,405.47$ 2,405.47$ 3,500.00$ 3,500.00$ 11,000.00$ 11,000.00$ 30 LS-0101 4. Landscape Remove (6) Sabal Palm Trees EA 6 250.00$ 1,500.00$ 241.90$ 1,451.40$ 230.00$ 1,380.00$ 523.86$ 3,143.16$ 400.00$ 2,400.00$ 431.20$ 2,587.20$ 31 LS-0102 4. Landscape Furnish & Install: 20 L.F. Per Location Of 18" Depth Rigid Plaster Interlocking Root Barrier Along Outside Edge Of Proposed Sidewalk EA 6 240.00$ 1,440.00$ 241.90$ 1,451.40$ 230.00$ 1,380.00$ 501.14$ 3,006.84$ 350.00$ 2,100.00$ 412.50$ 2,475.00$ 32 LS-0103 4. Landscape Furnish & Install: Performance Turf ( Bahia Grass), To Include Watering To Establishment SY 167 2.70$ 450.90$ 6.05$ 1,010.35$ 6.00$ 1,002.00$ 20.05$ 3,348.35$ 5.00$ 835.00$ 16.50$ 2,755.50$ 33 LS-0104 4. Landscape Furnish & Install: 3" Depth Of Wood Mulch Per Collier County Specifications In 2 Cu. Ft. Bags BAGS 75 7.50$ 562.50$ 6.05$ 453.75$ 5.75$ 431.25$ 6.48$ 486.00$ 25.00$ 1,875.00$ 5.34$ 400.50$ 34 LS-0105 4. Landscape Field Locate Existing Sleeves And Extend Two Feet Beyond Edge Of Proposed Sidewalk. (Approx. 5 Feet)LS 1 672.00$ 672.00$ 272.14$ 272.14$ 260.00$ 260.00$ 3,781.94$ 3,781.94$ 2,500.00$ 2,500.00$ 3,113.00$ 3,113.00$ 35 LS-0106 4. Landscape Remove Components And Abandon Existing Main Line, Bubbler Line And Valve Wiring.LS 1 1,008.00$ 1,008.00$ 254.00$ 254.00$ 242.00$ 242.00$ 2,940.02$ 2,940.02$ 1,500.00$ 1,500.00$ 2,420.00$ 2,420.00$ 36 LS-0107 4. Landscape Furnish & Provide: Air Spade Services To Expose Root Systems Of Existing Live Oak Trees Prior To Irrigation Main Line Installation.EA 0 -$ -$ -$ 5,000.00$ -$ -$ 5,000.00$ -$ -$ 37 LS-0108 4. Landscape Connect Valve Wiring And Check Operation Of All Valves From Existing Controller To New & Existing Valves.LS 1 1,680.00$ 1,680.00$ 338.66$ 338.66$ 325.00$ 325.00$ 1,603.65$ 1,603.65$ 3,500.00$ 3,500.00$ 1,320.00$ 1,320.00$ 38 LS-0109 4. Landscape Furnish & Install Bubbler Line By Mechcanicaltrenching: 1.25" Pvc Pantone Purple 522C, 1120-1220 Class 200 Solvent Weld Irrigation Lateral Piping With Bubbler Connections. 12" Depth, See Notes, Specifications And Details For Installation Requirements And Required Components. LF 305 3.76$ 1,146.80$ 3.63$ 1,107.15$ 3.50$ 1,067.50$ 7.28$ 2,220.40$ 17.00$ 5,185.00$ 6.00$ 1,830.00$ 39 LS-0110 4. Landscape Furnish & Install Bubbler Line By Hand Trenching: 1.25" Pvc Pantone Purple 522C, 1120-1220 Class 200 Solvent Weld Irrigation Lateral Piping With Bubbler Connections. 12" Depth, See Notes, Specifications And Details For Installation Requirements And Required Components. LF 100 6.58$ 658.00$ 4.84$ 484.00$ 4.60$ 460.00$ 20.05$ 2,005.00$ 22.00$ 2,200.00$ 16.50$ 1,650.00$ 40 LS-0111 4. Landscape Option 1: Furnish & Install Main Line By Mechcanicaltrenching: 3" Pvc Pantone Purple 522C, 1120-1220 Class 200 Gasketed Or Solvent Weld Irrigation Piping With Ductle Iron Pipe Fittings & Thrust Blocking. See Notes, Specifications And Details For Installation Requirements And Required Components. LF 213 6.67$ 1,420.71$ 9.68$ 2,061.84$ 9.25$ 1,970.25$ 37.82$ 8,055.66$ 22.00$ 4,686.00$ 31.13$ 6,630.69$ 41 LS-0112 4. Landscape Option 1: Furnish & Install Main Line By Hand Trenching: 3" Pvc Pantone Purple 522C, 1120-1220 Class 200 Gasketed Or Solvent Weld Irrigation Piping With Ductle Iron Pipe Fittings & Thrust Blocking. See Notes, Specifications And Details For Installation Requirements And Required Components. LF 100 11.39$ 1,139.00$ 11.49$ 1,149.00$ 10.95$ 1,095.00$ 52.12$ 5,212.00$ 26.00$ 2,600.00$ 42.90$ 4,290.00$ 42 LS-0113 4. Landscape Option 2: Furnish & Install By Directinal Bore: (1) 2" Sch. 40 Pvc & (1) 3" Pvc Pantone Purple 522C, 1120-1220 Class 200 Gasketed Or Solvent Weld Irrigation Piping With Ductle Iron Pipe Fittings & Thrust Blocking. See Notes, Specifications And Details For Installation Requirements And Required Components. LF 313 170.56$ 53,385.28$ 42.33$ 13,249.29$ 40.25$ 12,598.25$ 31.81$ 9,956.53$ 23.00$ 7,199.00$ 26.18$ 8,194.34$ 43 LS-0114 4. Landscape Option 2: Furnish & Install: 3" Hdpe To Pvc Mechcanial Joints EA 2 937.56$ 1,875.12$ 332.62$ 665.24$ 316.00$ 632.00$ 435.66$ 871.32$ 250.00$ 500.00$ 358.60$ 717.20$ Haskins , Inc.O-A-K Pavement MaintenanceInfinite Construction Bonness, Inc. Coastal Concrete Products 1 of 2 5/7/2018 16.A.9.a Packet Pg. 665 Attachment: 18-7307_Bid_Tab (5749 : Livingston Road Sidewalk Construction Award) Project Manager: Andrew Miller Attachment A-1 - Bid Schedule 18-7307 - Livingston Road Sidewalk Project Project # 69081.18 Notices Sent: 7,871 Bid Packages Downloaded: 96 Submittals: 6 Line #Pay Item #Section Description Unit Qty Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Haskins , Inc.O-A-K Pavement MaintenanceInfinite Construction Bonness, Inc. Coastal Concrete Products 44 LS-0115 4. Landscape Furnish & Install: Toro 220-227-X-5, 1.25" 220 Series Brass Electric Ac Solenoid Valve With Pressure Regulator, 2.5" Red White 206 Series Isolation Valve. Install Assembly In (Jumbo Size) Rainbird Valve Boxes Vb-Max-Pl, Nominal Size To Be 35" X 22" X 18". Lid Label To Read "Irrigation". To Include 6" Extensions As Needed. EA 1 1,456.44$ 1,456.44$ 1,451.42$ 1,451.42$ 1,380.00$ 1,380.00$ 1,629.04$ 1,629.04$ 1,500.00$ 1,500.00$ 1,342.00$ 1,342.00$ 45 LS-0116 4. Landscape Furnish & Install Splice / Pull / Junction Boxes: Polymer Concrete / Fiberglass, Tier 8, Nominal Size To Be 10" X 15" X 18". Lid Label To Read "Irrigation". EA 2 210.80$ 421.60$ 393.10$ 786.20$ 375.00$ 750.00$ 523.86$ 1,047.72$ 550.00$ 1,100.00$ 431.20$ 862.40$ 46 LS-0117 4. Landscape Furnish & Install On-Site: Irritrol 533 Adjustable Flood Bubblers. Includes Pvc Pantone Purple 522C 1120-1220 Class 200 Solvent Weld Lateral Piping From Zone Valves To Bubblers And Flex Piping At Tree Locations. Size Pipe For Proper Flows As Recommended In The Pipe Sizing Schedule. Pipe Size Shall Be 1.25" To 3/4" Dia. Per Plan Notes & Details. EA 11 84.15$ 925.65$ 30.24$ 332.64$ 28.75$ 316.25$ 196.45$ 2,160.95$ 150.00$ 1,650.00$ 161.70$ 1,778.70$ 47 LS-0118 4. Landscape Furnish & Install: Green (Rpm) Reflective Pavement Markers On Top Of Curbing Or On Pavement Edge At Each Valve Or Groups Of Valves. One On Each Side Of Median Curbing. Expoxy Set Per Fdot Specifications. EA 1 45.26$ 45.26$ 60.48$ 60.48$ 30.00$ 30.00$ 56.13$ 56.13$ 75.00$ 75.00$ 46.20$ 46.20$ 48 LS-0119 4. Landscape Furnish & Install: Valve Control Wire, Awg 12 Ga. Wire (2 Common White) Solid Copper Insulated Suitable For Direct Burial LF 700 1.77$ 1,239.00$ 0.79$ 553.00$ 0.75$ 525.00$ 3.13$ 2,191.00$ 4.00$ 2,800.00$ 2.57$ 1,799.00$ 49 LS-0120 4. Landscape Furnish & Install: Valve Control Wire, Awg 14 Ga. Wire (12 Activation Red & 1 Spare Green) Solid Copper Insulated Suitable For Direct Burial LF 4550 1.30$ 5,915.00$ 0.67$ 3,048.50$ 0.65$ 2,957.50$ 1.20$ 5,460.00$ 2.00$ 9,100.00$ 0.99$ 4,504.50$ 50 LS-0121 4. Landscape Furnish & Install: Omni Markers Model 168 (Purple) See Notes, Specifications And Details For Installation Requirements EA 2 26.26$ 52.52$ 54.43$ 108.86$ 51.75$ 103.50$ 68.16$ 136.32$ 250.00$ 500.00$ 56.10$ 112.20$ 51 CC-999-001 5. Allowance Project Allowance LS 1 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 52 $222,490.57 $235,897.74 $257,000.00 $259,166.99 $268,513.00 $312,692.43 Responsive Check: Bid Opened By: Adam Northrup Witness: Barbara Lance Project Total Insurance and Bonding Requirements (Form 8) Conflict of Interest Affidavit (Form 9) Bid Response Form (Form 1) Exhibit N - Contractors Key Personnel Assigned to the Proj - (Form 2) Material Manufacturers (Form 3) List of Major Subcontractors (Form 4) Yes Yes Yes Yes Grant Forms Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes N/A Vendor Declaration Statement (Form 10) Immigration Affidavit Certification (Form 11) Vendor Substitute W-9 (Form 12) Bidders Checklist (Form 13) Addendum Statement of Experience of Bidder (Form 5) Trench Safety Act Acknowledgement (Form 6) Bid Bond (Form 7) Yes Yes Yes Yes Yes Yes YesYes Yes Yes Yes N/A Yes Yes Yes Yes N/A Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes N/A Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes N/A Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes N/A Yes Yes Yes Yes Yes 2 of 2 5/7/2018 16.A.9.a Packet Pg. 666 Attachment: 18-7307_Bid_Tab (5749 : Livingston Road Sidewalk Construction Award) 16.A.9.b Packet Pg. 667 Attachment: 18-7307 Engineers Recommendation to Award Letter_CC Project 69081.18 (5749 : Livingston Road Sidewalk Construction 16.A.9.cPacket Pg. 668Attachment: 18-7307 NORA_Executed (5749 : Livingston Road Sidewalk Construction Award)