#13-6164CZ WO (Humiston & Moore Engineering) WORK ORDER/PURCHASE ODER
Contract 13-6164CZ"
Contract Expiration Date:March 8,2019
This Work Order is for professional Architect and Engineering services for work known as:
Project Name: Ann Olesky Park Erosion Control Project
Project No: 195-80268 ✓
The work is specified in the proposal dated April 23,201(which is attached hereto and made a part of
this Work Order. In accordance with Terms and Conditions of the Agreement referenced above, this
Work Order/Purchase Order is assigned to: Humiston& Moore Engineers/
Scope of Work: As detailed in the attached proposal and the following:
* Task I Peer Review Lake Trafford Shore Erosion
Schedule of Work: Complete work within 90 days from the date of the Notice to Proceed which is
accompanying this Work Order. The Consultant agrees that any Work Order that extends beyond the
expiration date of Agreement No. 13-6164CZ will survive and remain subject to the terms and
conditions of that Agreement until the completion or termination of this Work Order.
Compensation: In accordance with the Agreement referenced above,the County will compensate the
Firm in accordance with following method(s): QNegotiated Lump Sum (NLS) OLump Sum Plus
Reimbursable Costs(LS+RC) Time& Material (T&M) (established hourly rate—Schedule B)0
Cost Plus Fixed Fee (CPFF), (define which method will be used for which tasks) as provided in the
attached proposal.
Task I $13,931.00(T&M),f
TOTAL FEE $13,931.00(T&M),Y
PREPARED BY: el ii
Gary M Al in,CZM anger Date
APPROVED BY: 01/4/10 5/( 1 i g
Am Pa 0 e n.Department Direct,r Date
i t �rj f
�� ''? APPROVED BY: 'v 7 ;I i ,y/L5
{ i `������—'y �.
Thaddeus L.Cohen, Department Head GMD Date f
By the signature below, the Firm (including employees, officers and/or agents) certifies, and hereby
discloses,that,to the best of their knowledge and belief,all relevant facts concerning past,present,or
Page 1 of 3
S
1
i I
currently planned interest or activity(financial,contractual,organizational,or otherwise)which relates
to the proposed work;and bear on whether the Firm has a potential conflict have been fully disclosed.
Additionally,the Firm agrees to notify the Procurement Director,in writing within 48 hours of learning
of any actual or potential conflict of interest that arises during the Work Order and/or project duration.
ACCEPTED BY: Humiston& ,oore • ineers
. illp
067/8
jj
Brett D. Moore,P.E.,President
Date
Page 2 of 3
ATTEST: BOARD 0 O ►'- Y COM RS
Dwight E.Brock Clerk Collier C• ty, r onda
•
Attestas to airman's By A
DR1140 i1eijc 'v. An.y Solis,Chairman
ATTEST:
B .
(Print Name/Title
Approved as to Form and
gality:
_ /#
A I#!! County Attorney
Page 3 of 3 ff
`c`�O
CAC May 10,2018
VIII-4 New Business
1 of 2
HUMISTONF3MOORE
ENGINEERS
COASTAL 5679 STRAND COURT
' ENGINEERING DESIGN NAPLES,FLORIDA 34110
AND PERMITTING PHONE 239594590 5
PHONE 239 594 2021
April 23,2018
Gary McAlpin,Manager
Coastal Zone Management
Collier County Government
2685 South Horseshoe Drive Unit 103
Naples,FL 34104
Re: Collier County Contract 13-6164CZ
HM File No 23-065.2018-60%plan review
Peer Review Lake Trafford
Dear Gary:
As requested,we are providing a proposal to review the 60%plans for Anne Olesky Park Erosion Control
Project.Scope of Work will involve the following:
• Conduct site visit and review historic changes along area of study.
• Review potential wave conditions relative to design criteria and objectives for shoreline
stabilization.
• Meet with design professional at RWA, Inc. regarding project design, assumption, design goals
and wave criteria.
• Meet with subconsultant biologist on design.
• Contact provider of shoreline stabilization matt for design criteria for matt.
• Provide written summary with recommendations.
• Provide a preliminary cost estimate of recommendations.
Task I—Peer Review Lake Trafford
RATE/UNIT HOURS/OT AMOUNT
PRN2 Principle Engineer 206/ 16 3,296.00
SEN Senior Engineer 157✓ 10 1,570.00
SDS Engineer 123✓ 15 1,845.00
GIS Senior Scientist 118/ 10 1,180.00
SIN Environmental Specia 109 / 20 2,180.00
SRT Senior Technician 851% 28 2,380.00
Environmental Sub 185 / 8 1,480.00
TOTAL 13.931.00
CAC May 10,2018
VIII-4 New Business
2 of 2
This task will be billed on a time and materials basis.A draft copy of the report will be provided prior to
the final. Draft report will be provided within 60 days and final product within 90 days of Notice to
Proceed.
The budget may therefore be considered a not-to-exceed amount with the understanding that in the
event requests from County staff result in Additional Services exceeding the estimated budget amounts,
a budget amendment will be requested.
Please call if you have any questions.
Sincerely yours,
HUMISTON&MOORE ENGINEERS
Brett D.Moore,P.E.
President
TURRELL, HALL & ASSOCIATES, INC.
MARINE& ENVIRONMENTAL CONSULTING
3584 Exchange Avenue•Naples,Florida 34104-3732•239-643-0166•Fax(239)643-6632•Tuna®THAnaples.com
May 3,2018
Rxhihit"A"
Mr.Brett Moore
Humiston&Moore Engineers
5679 Strand Court
Naples,FL 34110
Re: Proposal for Environmental Subconsulting Services
Peer RPvipw Lilco Trafford Shore Rrnainn
Dear Brett,
Turrell,Hall&Associates is pleased to provide you with this proposal for environmental services.
Pursuant to our conversations it is my understanding you will require some environmental
review of the shoreline stabilization design and recommendations at Lake Trafford's Anne
Olesky Park.
We estimate there will be 8 hours of time required by Tim Hall,our Senior Ecologist and Principal,
at a rate of$185.00($1,480.00 total).
Please let me know if you have any questions.
Sincerely,
1.
Marielle Kitchener
Operations Manager
SCHEDULE B: RATE SCHEDULE
Standard Hourly
Title Rate
Principal $ 206.00
Senior Project Manager $ 172.00_
Project Manager $ 147.00
Senior Engineer $ 157.00
Engineer $ 123.00
Senior Inspector $ 96.00
Inspector $ 76.00
Senior Planner $ 139.00
Planner $ 110.00
Senior Designer $ 114.00
Designer $ 94.00
Environmental Specialist $ 109.00
Senior Environmental Specialist $ 134.00
Scientist/Geologist $ 93.00
Senior Scientist/Geologist $ 118.00
Marine Biologist/Hydrogeologist _ $ 110.00
Senior Marine Biologist/Hydrogeologist J $ 138.00
Senior GIS Specialist $ 139.00,
GIS Spedalist $ 102.00_
Clerical/Administrative $ 62.00
Senior Technician $ 85.00
Technician $ 72.00
• Surveyor and Mapper $ 120.00
CADD Technician $ 81.00
Survey Crew-2 man $ 130.00
Survey Crew-3 man $ 161.00
Survey Crew-4 man $ 189.00
Senior Architect ~$ 154.00
Architect $ 121.00
This list is not intended to be all inclusive. Hourly rates for other categories of
professional, support and other services shall be mutually negotiated by Collier County
and firm on a project by project basis as needed.
B-1